The Contractor shall construct the Project Facilities in accordance with the
provisions of this Agreement. Such Project Facilities shall include:
(d) Landscaping
(o) others
Traffic signs and pavement markings shall include road side signs, overhead
signs, curve mounted signs and road marking along the project highway. The
locations for these provisions shall be finalised in consultation with
Authority’s Engineer and as per latest IRC Standard.
(ii) Concrete Cats eye, Crash Barrier, Metal beam crash barrier,
Separators (MS railings)
Cats eye shall be provided thorough length of the project as per the spacings
mentioned in IRC.
The minimum length of 6.20 km (including LHS & RHS) Km Metal beam
crash barrier and separator (M.S. railings) shall be provided as per Schedule
D and for safety of traffic & users. . The locations shall be finalised in
consultation with Authority Engineer. Increase in length shall not be
considered under change of scope.
(iii) Traffic Safety Devices in consultation with Authority’s Engineer &
Latest IRC standards
(iv) Boundary Stones shall be placed throughout the project road as per
schedule ‘D’
(v) Hectometer / Kilometer Stones as per schedule ‘D’
(vi) Solar Traffic blinker signal (L.E.D) shall be provided at intersections.
(vii) Gantry structure shall be provided at the Start and end point of the road and
at the stretches where four lanning/ urban stretches begins
c) Pedestrian Facilities
The additional pedestrians’ facilities in the form of guard rails, footpath, lighting etc.
shall be provided in built-up area and high embankment of structures.
For proper approaches to adjoining agricultural fields along excavated drains,
900mm dia. NP2 pipes for about minimum 7.5m length or length as per width of
Rehabilitation and Up-gradation of Chikhali-Bhokardan-Sillod-Jalna National Highway Packagen: 2 from Design km
28+000 (Dhad) to km 67+600(Bhokardan) & Bhokardan (13+450) to Sillod (0+000) to Two lane with paved shoulders/Four
lane Configurations in the state of Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract.
Page | C-2
MoRT&H, NH Division, (PWD), Maharashtra Schedules to Concession Agreement
road with adequate cushion over pipe at an interval of 500 m on both sides &
wherever required as per site requirements in consultation with Authority Engineer
shall be provided.
d) Landscaping and Tree Plantation
Landscaping of the highway shall be done as per IRC: SP-21-2009 on, but not limited
to, the following:
• Median
• Grade Separated intersections
• Entry and Exit ramp
• At grade islands of intersection locations
• Landscaping and road side plantation shall be provided in accordance with
the Manual of Specifications and Standards as referred in Schedule B and D.
Contractor Shall be responsible for implementation of Environment
Management Plan (EMP) on the project. The cost of EMP shall be Bourne by
Contractor.
• In case of availability of space between proposed ROW and side drain, tree
plantation shall be done as per IRC: SP-21-2009.
2 47+100 Jamb
3 55+950 Aasai
4 65+400 Viregaon
Sillod to Bhokardan
Bus Bays & bus shelter shall be provided at locations given below. The Bays and
shelter shall be designed based on IRC-SP-73 – 2015, Clause 12.6 and Figure 12.3.
• Bus shelters:
2 37+750 Dhad
3 50+450 Mahora
4 58+950
Sillod to Bhokardan
i. Street/Highway Lighting
Street Light: Street lighting on decorative lamp post with LED /energy efficient
lighting system of standard make with minimum 40 Lux capacity shall be provided @
30m interval for entire project highway. Street lights shall be provided with dual
lights on single pole and single lights on single pole. The height of street light pole
shall be about 9m above FRL and that of high mast shall be 25m. The street light
arrangement is given in following table:
Chainage No of No of
Height
Sr. Length Spacing One way Two way
of Pole
No From To (km) (m) Light Light
(m)
A
Poles Poles
1 32+400 35+000 2.600 30 9 87
b
2
o 50+000 51+500 1.500 30 9 50
3 v 66+100 67+600 1.500 30 9 50
e Sillod to Bhokardan
4
n 0+000 0+500 0.500 30 9 17
u Total Length of Stretch: Total
m
6.10Km 204--
Nos.-
numbers of street lights are indicative and minimum specified. The actual
numbers of street lights shall be determined by the Contractor in accordance
with the Manual requirements with approval from the Authority's Engineer.
Any increase in the numbers specified in this Clause of Schedule C shall not
constitute a Change of Scope.
ii. High Mast Lighting
High mast lighting shall be provided at Major junctions, Flyovers toll plaza
and Bus Bay /Truck Lay byes using LED / energy efficient lighting system.
The high mast shall be provided at required locations:
Note: The above specified locations are minimum specified. If required the contractor
shall provide High Mast lightning wherever necessary in consultation with the
Authority Engineer. However, this shall not be treated as change of scope.
iii. Solar lights blinkers shall be provided at major & minor junctions etc.
iv. The lighting work shall be got done from the qualified specialised agency.
v. The scope include providing entire lighting systems, trenching, underground /
building in cabling, transformers etc and obtaining electric supply /
approval from concern Govt. department such as MSECDL, MSEB etc.
i) Emergency Medical Services/Medical Aid Post: NIL
o) Others:
1. Slope protection
The slope protection by lawn or any other method using green technology
will be provided at locations, where embankment height is more than 1.00
m and in approaches of Viaducts/Flyover/bridges as per Manual and as
directed by Authority.
2. Utility pipe ducts/Passges
The ducts shall be laid as per IRC-SP-73-2015, Clause 2.15 & as per IRC-SP-
84-2014, Clause 2.16 (with chamber size 900mm by 900 mm) at a suitable
depth as approved by Authority Engineer.
Utility Passages are provided with paver blocks at 200m c/c with DLC
below it. In urban areas.
3. Utilities
Utilities to be identified at site and certified by the Authority Engineer then
shifting may be taken by contractor.
Note: In case of any discrepancy in numbers or locations of any of the project
facilities mentioned in this Schedule C, shall be constructed and
provided in consultation with the Authority Engineer as per site/design