Professional Documents
Culture Documents
To Rica
To Rica
I. MOBILIZATION
Site Clearing/Temfacil/Fencing 1 lot 60,000.00 60,000.00
Total 60,000.00
II. EARTHWORKS
A. Excavation
Column Footings 24 cu.m 300.00 7,200.00
Wall Footings 6 cu.m 300.00 1,800.00
Sceptic Tank 7 cu.m 300.00 2,100.00
Catch Basin 1 cu.m 200.00 200.00
B. Backfilling
Column Footings 24 cu.m 200.00 4,800.00
Wall Footings 6 cu.m 200.00 1,200.00
Grading & Compaction 59 sq.m 200.00 11,800.00
C. 4" Gravel Bedding
Footings 3 cu.m 550.00 1,650.00
Wall Footings 4 cu.m 550.00 2,200.00
Sceptic Tank 1 cu.m 550.00 550.00
Floor 5 cu.m 550.00 2,750.00
D. Soil Poisoning 20 cans 1,100.00 22,000.00
Material Cost 58,250.00
Labor Cost 26,212.50
Total 84,462.50
V. REINFORCING BARS
A. Footings
16mm dia. Rebars 20 pcs. 350.00 7,000.00
#16 Tie Wire 3 kg. 100.00 300.00
B. Wall Footing
12mm dia. Rebars 8 pcs. 200.00 1,600.00
10mm dia. Rebars 10 pcs. 175.00 1,750.00
#16 Tie Wire 1 k.g 100.00 100.00
C. Columns
20mm dia. Rebars 48 pcs. 600.00 28,800.00
10mm dia. Rebars 42 pcs. 175.00 7,350.00
#16 Tie Wire 5 kg. 100.00 500.00
D. Tie Beam
16mm dia. Rebars 55 pcs. 385.00 21,175.00
10mm dia. Rebars 86 pcs. 175.00 15,050.00
#16 Tie Wire 12 kg. 100.00 1,200.00
E. Floor Beam
12mm dia. Rebars 55 pcs. 200.00 11,000.00
16mm dia. Rebars 86 pcs. 385.00 33,110.00
#16 Tie Wire 9 kg. 100.00 900.00
F. Roof Beam
12mm dia. Rebars 55 pcs. 200.00 11,000.00
16mm dia. Rebars 86 pcs. 385.00 33,110.00
#16 Tie Wire 9 kg. 100.00 900.00
F. Stairs
12mm dia. Rebars 17 pcs. 200.00 3,400.00
16mm dia. Rebars 5 pcs. 385.00 1,925.00
#16 Tie Wire 2 kg. 100.00 200.00
G. Slab ( Ground Floor )
12mm dia. Rebars
10mm dia. Rebars 34 pcs. 175.00 5,950.00
#16 Tie Wire 2 kg. 100.00 200.00
H. Slab ( 2nd Floor )
10mm dia. Rebars 120 pcs. 175.00 21,000.00
#16 Tie Wire 10 .kg 100.00 1,000.00
I. Cath Basin
10mm dia. Rebars 4 pcs. 175.00 700.00
#16 Tie Wire 1 .kg 100.00 100.00
J. Kitchen Counter
10mm dia. Rebars 7 pcs. 175.00 1,225.00
#16 Tie Wire 1 kg. 100.00 100.00
K. Septic Tank
12mm dia. Rebars 33 pcs. 200.00 6,600.00
10mm dia. Rebars 9 pcs. 175.00 1,575.00
#16 Tie Wire 4 kg. 100.00 400.00
Material Cost 219,220.00
Labor Cost 98,649.00
Total 317,869.00
VII. FINISHING
B. Ground Floor , 2nd Floor, Toilet and Bathroom
.60m x .60m Tiles 270 pcs 250.00 67,500.00
Tile Grout 16 packs 100.00 1,600.00
Tile Adhesive 14 bags 300.00 4,200.00
Total
SAY