Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Name of Work; Septic Tank Construction

Bill of Quantity

No Particular Quantity unit Rate Per Amount Total


Material
1 Hardcore 112.44 cuft 450 cuft 50,599.97
2 Cement 21.79 Bags 10,000 Bags 217,854.25
3 Sand 201.31 cuft 1,600 cuft 322,103.70
4 Chipping 175.69 cuft 1,200 cuft 210,824.79
5 Brick 5891.77 Nos 120 Nos 707,012.55
6 Broken Brick 110.45 cuft 500 cuft 55,223.44
7 10mm dia. M.S Rod 144.29 kg 360 lbs 51,945.75
9 Binding Wire 4.93 lbs 200 lbs 986.62 1,616,551.07
Labour
1 Mason 20.08 Nos 16,000 Nos 321,250.13
2 Fixer 2.47 Nos 16,000 Nos 39,464.96
3 Worker 181.52 Nos 8,000 Nos 1,452,166.76 1,812,881.86
Total 3,429,432.93

You might also like