Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

1 2 3 4 5 6

A A

B
ST159KWH-50HV Product Drawing B

No. Drawing Name


1 Drawing Cover
C C
2 Dimensions and Internal Layout
3 Foundation Design Reference Diagram
4 Cable Entry Layout

D D

1. The drawing may be not the final version and it is used for reference only.
For the final drawing, refer to the documentation in the scope of delivery. E
E
2. Foundations Note : Not for construction. The foundation should be
constructed according to onsite conditions as well as local design
specifications.The drawings are for information purpose, showing the
factors to be considered when designing the foundations the final
engineering drawings must be prepared by professional personal .
F
F

Drawn by Date 2019-12-28 Drawing Name Drawing Scale 1:1


Product Model
Checked by Date 2019-12-28
Drawing No.

Approved by Date 2019-12-28


Drawing Cover ST159KWH-50HV DW_20191228_ST159KWH-50HV_Drawings_4-1 Page 1 of 4
1 2 3 4 5 6
1 2 3 4 5 6

A A

1800 1000

2400
B B

M10 Bolt

2-20*50

C 216S2P 100Ah Lithium-ion Batteries 159KWH


C
SC50HV

2-20*50

5:1 magnification
Local Controller

D D
HVAC
(Hiding under the top cover )

Battery Unit

50KVA Transformer

E E
Here is the HVAC air inlet, at least 200mm behind
Here is the SC50HV install location, at least 600mm
the obstruction
right the obstruction

600 [1'-11.62"]
[0'-7.87"]
200
Depth area requirements
1934 [6'-4.12"]

50KVA Transformer
[2'-4.88"]

6 1
734

5 Local controller 1
F
2400 [7'-10.49"]
Width area requirements

F Note:
4 HVAC 1

3 Battery Unit 216S 100AH 2


1) The layout drawing is for reference. There may be partial adjustments in the detailed design.
2) This design is limited for 0.33C charge and discharge ratio(The ambient 2 Inverter SC50HV 1
temperature is designed from a minimum of -30 degrees Celsius to a maximum of 50 degrees 1 Unit 1
Non - standard
Celsius), other application scenarios need to be designed separately.
3) weight 3.4tons(2.4tons without battery); Serial number Name Model Quantity Note

Drawn by Date 2019-12-28 Drawing Name Drawing Scale 1:1


Product Model
Checked by Date 2019-12-28
Drawing No.
Dimensions and Internal Layout ST159KWH-50HV DW_20191228_ST159KWH-50HV_Drawings_4-2 Page 2 of 4
Approved by Date 2019-12-28
1 2 3 4 5 6
1 2 3 4 5 6

A A

B B

2400
[7'-10.50"]

C C

[0'-3.94"]
[0'-3.94"]

100
100

D 1197 2400 1197 2400 D


[3'-11.12"] [7'-10.50"] [3'-11.12"] [7'-10.50"]

E E
Notes:
1) The total weight of the turnkey station is about 3.4 tons.The turnkey station is installed on the foundations, the foundation size must meet the
requirements of the bearing capacity of the bearing stratum.the ground surface must be solid and flat, with no risk of collapse or sliding.
2) The turnkey station is recommended to be placed 100mm above the ground level. the final height above the ground level should be designed
according to the actual situation . The platform is not in the scope of delivery.You can Increase the platform at the openings outside door according
to the actual situation .
3) The upper surfaces of the foundations should be at the same level (unevenness shall be less then 5mm)
4) After the Unit enclosure stacked on the bottom of the pier, adjust the position of the Unit base, fix the Unit base with screws and L angle;The
final fixed mode must be prepared by professional personal.
5) Reserved for inlet and outlet pipe threading, size and number of outlet conduit should be selected according to the cable type and number of the
line is determined.
6) Ground points should be reserved for foundation, and the contact points of energy storage containers should be firmly and reliably connected. F
7) All of the buried pipe at both ends of the temporary plug, so as not to enter the debris, to facilitate the construction of the cables.
8) Not for construction. These drawings are for information purpose, showing the factors to be considered when designing the foundations; the
F final engineering drawings must be prepared by professional personal.

Drawn by Date 2019-12-28 Drawing Name Drawing Scale 1:1


Product Model
Checked by Date 2019-12-28
Drawing No.

Approved by Date 2019-12-28


Foundation Design Reference Diagram ST159KWH-50HV DW_20191228_ST159KWH-50HV_Drawings_4-3 Page 3 of 4
1 2 3 4 5 6
1 2 3 4 5 6

A A
1800 [5'-10.87"]

B B

2400
[7'-10.50"]

1000
[3'-3.37"]

C C

[7'-10.48"]
2400

[0'-3.94"]
[0'-3.94"]

600 [1'-11.64"]
L1/L2/L3

100
100

D D
1197 2400 1197 2400
[3'-11.12"] [7'-10.50"] [3'-11.12"] [7'-10.50"]

Notes:
E 1) The total weight of the turnkey station is about 3.4 tons.The turnkey station is installed on the foundations, the foundation size must meet the E
requirements of the bearing capacity of the bearing stratum.the ground surface must be solid and flat, with no risk of collapse or sliding.
2) The turnkey station is recommended to be placed 100mm above the ground level. the final height above the ground level should be designed
according to the actual situation . The platform is not in the scope of delivery.You can Increase the platform at the openings outside door according
to the actual situation .
3) The upper surfaces of the foundations should be at the same level (unevenness shall be less then 5mm)
4) After the Unit enclosure stacked on the bottom of the pier, adjust the position of the Unit base, fix the Unit base with screws and L angle;The
final fixed mode must be prepared by professional personal.
5) Reserved for inlet and outlet pipe threading, size and number of outlet conduit should be selected according to the cable type and number of the
line is determined.
6) Ground points should be reserved for foundation, and the contact points of energy storage containers should be firmly and reliably connected.
7) All of the buried pipe at both ends of the temporary plug, so as not to enter the debris, to facilitate the construction of the cables.
8) Not for construction. These drawings are for information purpose, showing the factors to be considered when designing the foundations; the
final engineering drawings must be prepared by professional personal.
F
F

Drawn by Date 2019-12-28 Drawing Name Drawing Scale 1:1


Product Model
Checked by Date 2019-12-28
Drawing No.

Approved by Date 2019-12-28


Cable Entry Layout ST159KWH-50HV DW_20191228_ST159KWH-50HV_Drawings_4-4 Page 4 of 4
1 2 3 4 5 6

You might also like