Consultant: Client: Contractor:

SITE INSPECTION REPORT

To : Engr. Mawea Designation : Safety In-Charge


Company : SUBCON/WELTECH Inspection Date : 04-Nov-2019
From : HSE Department Close out Date : ASAP
Inspector Name : Bernard D. Frane Ref. No. :

Loss Potential High Medium Low


Action Level Immediate 2 days 5 days 14 days Others:(Specify)

Inspector Observation
1. During my site surveillance I found out that most of WELTECH personnel still not wearing
PPE’s. including some Foreman.
Potential Hazard:
1. Personnel injury fatality and property damage.
2. RFI cancellation if found by Consultant, which will lead to operation interruption,progress
delay and loss of production
Recommendation:
1. Assess your personnel and submit the required number of PPE to be withdrawn from RTCC
store which will subject for your billing deduction.( See attached photos)
SAFETY

NOT WEARING HELMET AND VISIBILITY VEST.

Close-out Inspection of above Abnormalities


SAFETY

Closed Out: Yes No

(RTCC-HS-FM-017 / Rev00) Page 1 of 2


5.06.8.1 SITE INSPECTION REPORT

NOT WEARING VISIBILITY VEST AND HELMET

. NOT WEARING VISIBILITY VEST AND HELMET

Page 2 of 2 Date: 04/11/2019