Sanjen Jalavidhyut Company Limited (SJCL) : Sanjen (Upper) 14.8 MW and Sanjen (42.50MW) Hydroelectric Projects
Sanjen Jalavidhyut Company Limited (SJCL) : Sanjen (Upper) 14.8 MW and Sanjen (42.50MW) Hydroelectric Projects
Civil Works (Lot 2), is approx. 93% % completed. Penstock installation is almost completed and
Hydro-mechanical Works has been completed approx. 89%. Electromechanical Works
particularly EM installation works is yet to be started and this works has been severely impacted
due to COVID 19 as the delivery of equipment and deployment of manpower from China is
halted due to lockdown and border sealed in both side. The civil works in powerhouse is almost
completed and waiting for EM installation works. The project is targeted to completed and
commissioned within this fiscal year.
This project is cascade project of SUHEP and has gross head 442 m. Additional 0.5 m3/s
discharge from Chhupchung Khola is to total design discharge 11.57 m3/s. This project will
produce total 251.94 GWh with total annual salable energy is 241.86 GWh. The overall progress
of the project is approx. 78%.
Page 1 of 2
In Civil Works, headrace tunnel excavation is
completed, Chhupchung headworks, balancing
pond, syphon pipes, inlet slopes is almost
completed. Most critical part of this works of
Penstock shaft excavation accomplished and
penstock installation and backfilling is about to
start. Superstructure concreting of powerhouse
is almost finished and waiting for EM
installation however EM Works (Lot-3) is
severely impacted by COVID 19 for delivery of
some of the equipment and deployment of
Figure: SHEP Headworks& Powerhouse
technical manpower for installation from
contractor home country China.