Professional Documents
Culture Documents
Transformer Technology State-Of-The Art and Trends of Future Development
Transformer Technology State-Of-The Art and Trends of Future Development
Transformer Technology State-Of-The Art and Trends of Future Development
TRANSFORMER TECHNOLOGY
STATE-OF-THE ART AND TRENDS
OF FUTURE DEVELOPMENT
R. Baehr, former Chairman of Study Committee 12 (Transformers)
2. STRATEGIC DIRECTIONS
OF DEVELOPMENT
During the last century which might be called
“the century of the engineers” the pride of
engineers was to strive for the best technical
solution. Now times have changed and engineers
must deal with economics if they want to act
successfully in the world wide market.
Deregulation and privatisation of the electrical
energy supply industry influenced the direction of
development considerably.
Concerning the transformer for a long time
economical considerations were limited to
FIGURE 2 : Change of characteristics with time.
purchase price and loss evaluation with
Example : 200 MVA/220 kV Transformer.
depreciation figures based on rather long pay-back
period, say 20 years or more. Since low loss by
physical law requires more material high loss
evaluation figures can compensate for higher first
cost in the total cost evaluation when purchasing a
new transformer. Evaluation figures vary in a wide
range reflecting the local conditions regarding
availability of capital, interest rate, depreciation
time, source and cost of primary energy, loading
characteristic etc. Table 1 presents a comparison of
loss evaluation figures of several countries with quite
different economic conditions and not all of them
look very reasonable, but they are of eminent
influence on the design and cost of the product. To
give an example : if availability of capital is the
paramount parameter it is not reasonable, but
misleading for the designer to specify high loss
evaluation figures. On the other hand : if the
purchaser’s decision is based on life cycle cost low
losses may offer the best result.
In the past most of the parameters were
regarded as fix during the lifetime of the
transformer, but to day quick and unexpected
changes of market conditions must be taken into
consideration which makes the evaluation more
complicated.
The rapid decrease of pay-back time as a
consequence of shorter estimated service time in
some parts of the world seems to be a most
important change. By this change significant
technical decisions are influenced, beginning with
the design, the choice of material and ending up
with changed maintenance strategies. Furthermore
designing for shorter lifetime and less maintenance
may require more and better monitoring and
diagnostic tools. To run no increased unknown risks
improved methods to estimate condition and life
expectancy of the individual transformer have to
TABLE 1 : Loss evaluation figures of transmission transformers be developed. An indispensable precondition for
USD/kW. reliable lifetime estimation is the availability and
3. DEVELOPMENT OF
THE TECHNOLOGY
The impressive progress of transformer
technology in recent decades is based on two
factors : improved characteristics of material,
especially core material, and development of
advanced design tools.
develop material with higher Si content upto 6.5 % length of several hundred meters – a precondition
where magnetostriction disappears. When for the use in transformers. Ductile Bi-based
produced in a conventional manner by rolling Fe- superconductors which offer better workability and
material with more than 4 % Si is extremely brittle. Only which do not need be embedded are in the scope
a rapid quenching process can produce ductile of new development programs.
material which can easily be handled by the trans- However the commercial application of
former manufacturer. However high temperature superconductors in transformers will depend of
annealing is required to generate a texture which further steps towards lower conductor price.
guarantees magnetic properties comparable to
those of normal grain oriented sheets of best quality.
Recent information say that optimum power loss is
3.3 Insulation Material
achieved at a thickness of about 0.1 mm. The
saturation polarisation is said to be 1.8 Tesla. It is highly remarkable that new insulation systems
Latest development work is concentrating on based on plastics and synthetic fluids were not able
3 % Si material with low magnetostriction, but to substitute cellulosic material, i.e. paper,
without sacrificing the favourable loss properties of transformer board, (laminated) wood and mineral
most advanced Fe-Si material. oil as the predominating insulation system for the
majority of power transformers. This is due to the
high reliability, long lifetime and of course the
3.2 Conductor Material comparatively low price of the oil-cellulose system.
Only under stronger environmental conditions
Compared to the evolution of core material the (fire hazard, contamination of the ground water
progress in the area of conductor material was only
supply in residential and high populated areas) the
marginal as far as conventional conductors are
combination of polymere films and SF 6 gas was
concerned. Nevertheless the introduction of
introduced as an alternative.
continuously transposed conductors (CTC)
influenced the winding design essentially and
reduced the additional losses caused by eddy and
circulating currents. In the past the broader 3.4 Advanced Design Tools
application of CTCs was limited by the mechanical and Manufacturing Processes
weakness of the bunch of single strands, but the
problem was solved by the introduction of epoxy The development of powerful computers and
coating of the strands and curing of the bundle mathematical methods and models allowed more
during the drying process of the winding. Further precise prediction of electrical and mechanical
improvement of the mechanical strength was stresses including heat transfer and vibrations.
achieved by additional hardening procedures Advanced calculation methods (Finite
during the manufacturing process of the strands Elements) are used to create 2 – or 3 – dimensional
which result in a controlled increase of the yield field plots and to optimise the design of insulation
point of the copper conductor. structures and to check losses and vibrations in
For the application in LV-windings CTCs without structural parts of complicated geometry (Fig. 4) as
additional insulation of the bunch are in use which well as short circuit capability and thermal
offer excellent cooling properties without performance.
jeopardising the insulation safety. The voltage distribution under transient
Of future interest is the development of conditions can be determined by calculation in the
superconducting material. While the first steps time and frequency domain for different wave
towards superconducting transformers using low shapes and complex winding arrangements.
temperature superconductors (LTSC) were not very As a consequence dimensions and tolerances
promising due to the high demand of cooling could be reduced substantially. At the same time
power, the discovery of high temperature reliability was improved and test and service failure
superconductors (HSTC) reanimated activities in this rate considerably reduced.
field. The critical temperature of these materials is
above 80 K. Therefore liquid nitrogen (77 K) can be Manufacturing of power transformers is still
used as coolant which reduces the expenditure for mainly hand work done by skilled workers. Attempts
the cooling plant by one order of magnitude. At to introduce automatic core stacking and winding
present conductors based on ceramic material processes were not successful due to the high
embedded in silver can be manufactured at a variety of parameters and the low repetition rate of
The discovery of high temperature supercon- the refrigerator capacity permit optimum design
ductivity (HTSC) of some ceramic alloys and the and utilisation of the transmission system as a whole.
development of suitable multi filament wires of Environmental compatibility and nonflammability
adequate length revived research work and stud- are additional arguments to continue
ies of large power transformers using superconduc- development. Nevertheless there are increasing
tive windings at a service temperature of 77 K, the restraints in view of short term economical
temperature of liquid N2. At this temperature level considerations.
the expense for cooling decreases by one oder of
magnitude.
Two lines of development are pursued. A more
4.3 Other Non-conventional
futuristic approach presents the design of a ring-
shaped coreless transformer. With the more Designs
conventional approach only the windings are
The application of cable technologies opens
made from superconductive material and housed
new possibilities to increase the functionality of
in a separate cryostat at the relevant low
transformers. The use of conventional PE cable as
temperature necessary to maintain the supercon-
stator winding allows to combine power generation
ductivity of the windings. The core is built and
and first step of transformation in one unit instead of
cooled in a conventional manner. Prototypes up to
using a conventional generator connected to a
10 MVA were designed, smaller units were
manufactured and tested in the laboratory and in separate GSU-transformer. A voltage level of 220 kV
service. Special attention is payed to traction and more is said to be practicable. As a second
transformers because of light weight and low losses, option the cable technology is used for dry-type
both beneficial for high speed trains. power transformers where oil-free, non-flammable,
Recent studies concerning the total cost of large non-explosive transformers are required.
HSTC transformers in comparison with conventional
units are promising provided the progress to A special technology for on-site assembly of
develop conductors of lower AC losses and lower large power transformers was developed for
cost continues and loss evaluation figures remain at applications where close restrictions in transport
the current level. The inherent fault limiting feature weight and dimensions do not allow conventional
combined with reduced transformer reactance transportation to site. This technology includes
and the overload capability which is limited only by specific processing of the prefabricated windings,
core stacking, assembly, drying and final testing
on site.
While the development towards higher ratings
and higher voltage stagnated during the last two
decades Tokyo Electric Power Company (TEPCO) is
planning to begin commercial operation of
Japan’s first 1 000 kV transmission sytems in the
beginning of the 21st century. Prototype
transformers of 3 000 MVA / 1 000 kV were already
designed, produced, delivered and tested under
service conditions in a field test station (Fig.5).
● the impact of decentralised power genera- maintenance to safeguard the same level of
tion on transformers reliability. Modern monitoring and communication
tools and the development of high sophisticated
● reliability and maintenance for more eco-
evaluation methods – e.g. learning systems, fuzzy
nomic usage of assets
logic – offer the opportunity for more reliable
● lack of qualified engineering staff. statistical and individual forecasting of the
remaining life of transformers in various scenarios
The effect of decentralisation will presumably and for supporting decisions on service alternatives
strengthen the tendency towards smaller rated and optimised maintenance strategies. The
transformers and probably decrease the number of development of such tools requires close
transformation steps in the grid. Where improved cooperation between manufacturers and
power quality and fast reaction to disturbances in customers and the success will mostly depend on
the network are required electronic devices may the availability and quality of data ; hence an open-
replace the classic transformer, e.g. FACTS, book-policy of both parties will be indispensable.
electronic voltage regulators, variable shunt
reactors, electronic tap changers etc. By this the Learning expert systems will support the efforts
total number of transformers could be reduced in for reliability and safe supply, but it is questionable if
the future. such systems can totally replace the experience of
In the past many countries applied the n + 1 qualified engineers. Therefore the management
philosophy to ensure safe energy supply. In view of must take care of adequate well educated and
the stronger competition of privatised suppliers and experienced engineering capacity. As a
due to the open, deregulated market the safety contribution to the education of engineers Study
philosophy is reconsidered. The aim is to replace Committee 12 is going to offer tutorials on specific
spare capacity by preventive condition based topics of transformer technology and operations. ■
REFERENCES
n CIGRE WG 12.20 “Economics of transformer management”, MoM Budapest meeting, June 13, 1999 ; internal paper.
n D. Bonmann, “Superconducting transformers - benefits of upgrading and future electrical networks”, Key note
CIGRE SC12 Power Transformer Colloquium, Budapest 14-16 June, 1999.
n N.L.Fantana, L. Pettersson, “Transformer life assessment and condition monitoring – tools and cases”, Proceedings
of Intern. Conf. on Power Transformers, New Delhi, 6-7 April, 2000.
n A. Jaksts et al., “A major breakthrough in transformer technology”, CIGRE Paper 12-101, Paris 2000
n P. Boss et al., “Economical aspects and practical experience of power transformer on-line monitoring”, CIGRE
Paper 12-202, Paris 2000.
n C. Beduz et. al., “The design, construction and operation of high temperature superconducting transformers – prac-
tical considerations”, CIGRE Paper 12-203, Paris 2000.
n S. Tenbohlen et al., “Enhanced diagnosis of power transformers using on-and off-line methods : results, examples
and future trends”, CIGRE Paper 12-204, Paris 2000.
n E. Serres et. al., “Current limitation in high temperature superconducting Transformers and impact on the grid”,
CIGRE Paper 12-205, Paris 2000.
n Y. Yamagata et. al., “Development and field test of 1000 kV / 3000 MVA transformer”, CIGRE Paper 12-303, Paris 1998.
n R. Baehr, “How to obtain high performing power transformers in service”, Key note CBIP Int. Conf. April 6/7, 2000 in
New Delhi.
n R. Baehr, “Recent and future development of power transformers”, Key note, Meeting of the Australian CIGRE NC,
Melbourne 1997.