PERT CPM QUIZ 2

Activity A B C D E F G
Immediate Predecessors - - A A,B D C,E E
Expected Time (weeks) 7 9 12 8 9 6 5

A ES EF
t LS LF

Slack = 2 Slack = 7 Slack = 0


A 0 7 C 7 19 F 26 32
7 2 9 12 14 26 6 26 32

Start
Finish

Slack = 0 Slack = 0 Slack = 0 G Slack


26 =31
1
B 0 9 D 9 17 E 17 26
9 0 9 8 9 17 9 17 26 5 27 32
Critical Path: B-D-E-F