CE40-2 / E01

CONSUEGRA, Eliza Gail Roque October 16, 2020


2018102337 CE-2

M2-CLASS PRODUCED REVIEWER

Calculating the Present Values (PV) of all projects:

PROJECT A:
PW = -150 , 000 + ( 28 , 000 - 1 , 000 )( P / A,12%,10 ) + 20 ,000 ( P / F,12%,10 )
= -150 , 000 + 152 ,556.02 + 6 , 439.46 = 8 , 995.48

PROJECT B:
PW = - 85 , 000 + ( 16 , 000 - 550 ) ( P / A,12%,10 ) + 10, 000 ( P / F,12%,10 ) = - 85 , 000 + 87 , 295.95 + 3 ,219.73
= 5,515.68

PROJECT C:
PW = - 75,000 + ( 15, 000 - 500 )( P / A,12%,10 ) + 6, 000 ( P / F,12%,10 ) = - 7 5 , 000 + 81,928.23 + 1,931.84
= 8 ,860.07

PROJECT D:
PW = - 120,000 + ( 2 2,000 - 7 00 )( P / A,12%,10 ) + 11,000 ( P / F,12%,10 ) = -1 20, 000 + 120,349.26 + 3,541.71
= 3,890.97

The project having the highest Present Worth (PW) will be having the highest Equivalent Worth (EW).
Therefore, project A will have the highest EW with a PW of $8,995.48.
PW A 8995.48
EW A = = = 1,592.06
( P / A,r,n ) ( P / A,12%,10 )