Estimate: Description Qty Rate Amount SL No
Estimate: Description Qty Rate Amount SL No
Sl
Description Qty Rate Amount
No
KSRB 2-2-1 : Earth work excavation for foundation of buildings, water supply, sanitary lines and electrical
conduits either in pits or in trenches 1.5 M and above in width, in Hard Soil not exceeding 1.5 M in depth
1 including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges of
excavation with lead up to 50 M after braking of clods complete as per specifications. (PWDSR 2018-19).
KSRB 5-1-3 : Providing and constructing granite/trap/basalt rubble stone masonry in foundation with cement
5 morter 1:6 (Uncoursed) bond stones at 2 Mtr apart in each course including cost of materials labour curing complete
as per specifications. (P.W.D.S.R. 2018-19 )
L.W. 2 x 12.98 x 0.23 x 1.00 = 5.97 Cum
S.W. 2 x 7.92 x 0.23 x 1.00 = 3.64 Cum
Rate @ 2833.00+3%=2971.99/Cum 9.61 Cum 2340.00 22497.00
KSRB 2.3 : Filling available excavated earth (excluding rock) in sides of foundations upto plinth in layers not
exceeding 20 ems. in depth, compacting each deposited layer by ramming after watering with lead upto 50
m. and lift upto 1.5 m. including cost of all labour complete as per specifications. Specification. No. KBS 2.9
Rate @ 5478.00+3%=5642.34/Cum
KSRB 4.6.7 : Providing and removing centering, shuttering, strutting, propping etc,. and removal of form
work for sides and soffits of beams, beam saunchings, cantilever girders, bressumers and lintels not
7 exceeding 1 M depth including cost of all materials, labour complete as per specifications. (PWDSR 2018-19)
Rate @188.00+3%=193.64/Sqm
KSRB 4.2.1 : Providing and laying in position reinforced cement concrete of design mix M25 with OPC
cement @ 340kgs, with 20mm and down size graded granite metal coarse agreegates @ 0.70cum and fine
agreegates @ 0.47 cum, with super plastisizer @ 3 Ltr confirming to IS9103-1999 reaffirmed 2008, machine
mix, concrete laid in layers not exceeding 15cms thick, vaibrated all works in foundation plainth and ground
floor level for roof slabs, staircase, lintels, retaining walls, return walls, walls, (any Thickness) including
8
attached plasters, colounms, piers, abutments, pillers, posts, struts, buttresses, string, or lessing courses,
parapets, coping, bed blocks, anchor blocks, plain window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per specifications. specification No. KBS 4.1.4.6 (PWDSR
2018-19) For Column.
Super Structure
L.W. 3 X 12.98 X 0.23 X 3.20 28.66 Cum
S.W. 4 X 7.92 X 0.23 X 3.20 23.32 Cum
I.W 1 X 11.98 X 0.23 X 3.20 8.82 Cum (Intermediate wall)
Rate @188.00+3%=193.64/Sqm
KSRB 4.2.1 : Providing and laying in position reinforced cement concrete of design mix M25 with OPC
cement @ 340kgs, with 20mm and down size graded granite metal coarse agreegates @ 0.70cum and fine
agreegates @ 0.47 cum, with super plastisizer @ 3 Ltr confirming to IS9103-1999 reaffirmed 2008, machine
mix, concrete laid in layers not exceeding 15cms thick, vaibrated all works in foundation plainth and ground
16
floor level for roof slabs, staircase, lintels, retaining walls, return walls, walls, (any Thickness) including
attached plasters, colounms, piers, abutments, pillers, posts, struts, buttresses, string, or lessing courses,
parapets, coping, bed blocks, anchor blocks, plain window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per specifications. specification No. KBS 4.1.4.6 (PWDSR
2018-19) For slab.
Rate @ 232.00+3%=238.96/Cum
KSRB 15-3-8 : Providing 18 mm thick cement plaster in single coat with cement mortar 1:4 to brick masonry
18 including rounding of corners wherever required smooth rendering,. Providing and removing scaffolding, including
cost of materials, labour, curing complete as per specifications (P.W.D.S.R. 2018-19)
108.50
108.50 Sqm 3581.00 388524.00
Rate @2014.00+3%=2074.42/Sqm
Providing Skirting to all the rooms with approved quality tiles , including cost of materials, labour,
20
complete as per specifications (P.W.D.S.R. 2018-19) etc.comp
1 X 1 X 87.54 X 0.33 = 28.89 Sqm
28.89 Sqm 975.00 28166.00
KSRB 4.2.9 : Providing and laying in Position reinforced cement concrete of mix 1:2:4 (M20) with 20mm and
down size graded granite metal machine mixed, concrete laid in layers not exceeding 15cm thick, vibrated
21 for RCC Beams, Columns, of all sizes in foundation plinth and superstructure ground floor level for roof slabs, stair
case, lintels, columns, including cost of all materials, labour, HOM of machinery, curing, complete as per
specifications (PWDSR 2018-19) For Stair Case.
Providing and fixing Kitchen Katta as per drawings in Granite including cost of materials, labour, complete
26
as per specifications (P.W.D.S.R. 2018-19) etc.comp
= 2.04 R.m
= 2.04 R.m 3936 8029.44
Providing and Fitting Trolley with panelfor Kitchen Katta as per drawings including cost of materials,
27
labour complete as per specifications (P.W.D.S.R. 2018-19)
= 2.67 Sqm
= 2.67 Sqm 12912 34475.04
Proving all types of P.O.P including cost of materials, labour, complete as per specifications (P.W.D.S.R.
28
2018-19) etc.
= 108.50 Sqm
= 108.50 Sqm 968.4 105067.5264
Providing and Fitting S.S Grill work for staircase ,balcony and verandah including cost of materials, labour,
29
complete as per specifications (P.W.D.S.R. 2018-19) etc.
= 2.4 Sqm
= 2.4 Sqm 3497 8392.8
Providing Bore well for usage of water both drinking and other utilities including drilling,fitting of
30
machineries and labour charges
= 1 L.S 75000
31 Providing wardrobe to Living and dining room as per market value
= 1 L.S 50000
Providing Modern kitchen with all necessary cabad and all glass work as per drawing (as per market value)
32
= 1 L.S 50000
Providing waterproof for slab, including cost of materials, labour, complete as per specifications
33
(P.W.D.S.R. 2018-19) etc.comp(Polymer Based ) 10.20
1 X 1 X 12.98 X 7.92 = 102.80 Sqm
102.80 Sqm 1002 103007.20
Total Rs. 2957453.67
Add Combined Electrical Charges and plumbing charges as 7% 207021.76
Grand Total( Rs) 3164475