Professional Documents
Culture Documents
FEEDER ROADS Maintenance Manual - Ghana
FEEDER ROADS Maintenance Manual - Ghana
FOR THE
OF THE
MINISTRY OF TRANSPORTATION
ii
Definitions and Acronyms
DEFINITIONS
1. Work Order Number (refer form M1): A serial number assigned to the work orders issued to
contractor from time to time. Numbers shall be two (2) digits starting from 01 and continuing
in increments of one (1).
2. Work Measurement Number (refer form M2): A serial number assigned to the works measured
from time to time. Numbers shall be two (2) digits starting from 01 and continuing in
increments of one (1).
ACRONYMS
1.0 INTRODUCTION
1.1 Background
An emerging challenge for DFR is to ensure the provision of safe all weather accessible feeder roads
at optimum cost for the effective planning, development, rehabilitation and maintenance. Key issues
that have been confronting DFR over the years include decreasing road budgets, inconsistency and
unreliable data from inventories for planning, budgeting and monitoring.
In addressing the key issues and also in preserving investments made on improved roads and bridges
and to minimise the deteriorating feeder roads network, an effective maintenance management system
was required. In 1992, the GOG with assistance from the World Bank and in association with other
Development partners put in place the National Feeder Roads Rehabilitation and Maintenance Project
(NFRRMP). Subsequently in 1994, the Danish International Development Agency (DANIDA)
supported DFR to put in place the Maintenance Performance Budgeting System (MPBS).
The MPBS provided operational criteria for the expedient choice of maintenance options in particular
pertaining to routine and recurrent maintenance. Although the MPBS has been in operation since
1994, it has operated alongside other routine and recurrent maintenance systems. After a decade of
practicing MPBS, there was the need to review it owing to the following reasons:
DFR in collaboration with Management Support Team (MST) of Department for International
Development (DFID) had a series of meetings in four Regions to have a critical look at the various
routine maintenance systems. THE consensus from these meeting was that there was the need to
review the MPBS.
Consequently, a working group of five DFR personnel were formed and tasked to come out with a
routine maintenance management system and a manual to unify the MPBS, other routine maintenance
systems and the Geographical Information System (GIS) being developed by DFR with assistance
from DFID.
This manual shall form the basis of developing course material for training programmes for DFR staff
and other implementers of feeder roads routine and recurrent maintenance programmes.
In support of the Government of Ghana‟s Highway Sector Investment Programme, the Government of
the United Kingdom, through DFID provided a grant for a Rural Feeder Roads Programme that will be
executed by the DFR. Part of the proceeds of that grant was applied to procure consultancy services
for undertaking an inventory of all engineered and unengineered roads comprising the district road
networks in each of the regions in Ghana.
The inventory was used to build the feeder road network definition database of Ghana. In defining the
total feeder road network in the regions an inventory and condition survey of each road on the regional
feeder road network and records of Geographical Position System (GPS) co-ordinates along the road
alignment were collected. The GPS co-ordinate inventory data was presented in ArcView Shape Files.
With this system in place, it has made available for the use by DFR the following:
Revised digital maps of each district road network and regional road network showing the location
of intersections, culverts and bridges and social amenities (schools, health facilities, markets, etc.)
on the road alignment.
Electronic versions of the GPS co-ordinate data software for use by DFR‟s GIS Unit in updating
the existing digital district road maps in Ghana.
Hard copies of drawings containing all relevant GPS co-ordinate inventory data.
Unique identification number for each road section
The details of the DFR GIS and Road Data Base user guide are published in separate document as
Road Data Base user manual.
Recurrent Maintenance. Maintenance required at intervals during the year with a frequency that
depends on the volume of traffic using the road.
In order to facilitate the planning of works, routine and recurrent maintenance operations have been
grouped into three levels. These are minimum, basic and standard levels of maintenance as shown in
Table 3.1.
This level is to provide vegetation control and drainage maintenance. The activities involved are Grass
cutting or Bush clearing, Ditch cleaning, Re-excavate ditches and Cleaning culverts, inlet and outlet
channels.
This level is to provide some surface maintenance in addition to the minimum level of maintenance.
The additional activities included are Blading and Reshaping of road surface.
This level is to provide full maintenance of the road. It includes all of the activities of the basic level
and essential minor works like; minor culvert repairs, sectional regravelling, construction of new
culverts and sectional raising.
Generally, each activity is identified by a two digit number. The first digit represents the general
purpose of the activity by sub-group, for example, drainage maintenance. The second digit represents
the individual activity within the sub-group. A third digit is used to differentiate two or more similar
activities of different nature. Each activity number is followed by the letter „F‟ to denote that the
activity applies to feeder road maintenance.
Each activity is identified by a distinct name for easy and clear reference.
The description and purpose is to standardize the terms used to ensure clear and concise
communication and to remove any ambiguities in the scope of work to be carried out.
The technical specifications give information on the quality of construction, workmanship and
materials required.
This gives guidelines on work methods to be adopted to reduce accidents and hazards on site.
This gives guidelines on work methods to be adopted to reduce negative environmental impacts on the
communities along the road corridor.
The method of measurement is to make it clear as to how work carried out shall be measured for the
purpose of payment.
This indicates the dimensions that shall be used to measure the work.
Vegetation control
Drainage maintenance
Structural maintenance
Surface maintenance
General items
The product of the above items gives the cost of a particular activity. The sum of the cost of the
relevant activities gives the average cost per kilometre of the level of maintenance under
consideration. Sample calculations of the cost per kilometre for the various levels of maintenance are
shown in Appendix 3.
Poor Poor
Basic Good
Fair
ROAD
Fair
Minimum Good
Good
The District or Area Engineer shall assess the routine and recurrent maintenance needs of individual
roads and generate a draft budget targeted at achieving a reasonable level of maintenance. Using the
average cost per kilometre for each level of maintenance estimated by the Region, the total budget
requirement for the Network can then be determined as shown in Figure 5.1
District C
District B
District A
Section Length for level of maintenance
Road from to Standard Basic Minimum
Name (km) (km) (km) (km) (km)
The region shall collate the draft budgets from all its districts to prepare a draft regional budget. This
shall be forwarded to Head Office.
Head Office shall collate the draft budgets from all the Regions to prepare the DFR national routine
and recurrent maintenance budget and submit to the Ministry of Road Transport (MRT).
Based on the Regional budget allocations, the regions shall review their budgets to suit the allocated
funds and shall review the Districts or Area draft budgets accordingly. Figure 5.2 shows the flow chart
of the budget reviewing process.
Finalise budget
7.0 PROCUREMENT
The procurement of the works shall be in conformity with the procurement law of the Republic
of Ghana, Act 663 (2003) and procedures for procurement as directed by DFR Head Office.
Contract documents shall be prepared using the DFR standard contract document for routine
and recurrent maintenance works. The contract document shall include the various road
reference numbers and a sketch or a map showing the locations of all the roads for the project.
The DFR standard forms for supervision of works shall be used appropriately. These forms are
designated as S- and M- forms. The full set of these forms are shown in Appendices 5 and 6
respectively.
Works shall be scheduled to cover a period of three (3) months. However, in exceptional cases, works
shall be scheduled for periods shorter than three (3) months.
The spread and quantum of works per work order shall ensure that the contractor‟s resources are
efficiently utilized.
The contractor shall be required to submit a work programme based on the work order received. The
work order shall be approved or reviewed by the Maintenance Engineer before the execution of the
works.
The activities shall be scheduled with due consideration to climatic conditions. It should be noted that
some activities are preferably performed before or after rainy seasons.
The technical specifications of the activity specification where appropriate, specify the activities that
shall precede any particular activity. In the execution of works, the sequencing of activities shall be
adhered to.
For activities requiring more than one (1) frequency, the scheduling shall be done taking into
consideration the duration of the contract and the timing of activities.
9.2 Reporting
Monitoring and control shall depend on information and data generated from reports. The following
reports shall be prepared and submitted as stated.
The site supervisor (foreman or work superintendent) shall keep daily records of all site activities
using DFR supervisors‟ site visit report (Form S3) and site visit check sheet (Form S4).
The site supervisor (foreman or work superintendent) shall in addition to forms S3 and S4 complete
the DFR Supervisor‟s Diary (Form S2) and submit to the Area or District Engineer on weekly basis.
The Area or District Engineer shall collate the reports from the site supervisors (foremen or work
superintendents) in addition to his own operations into a monthly report. This report shall be submitted
to the Regional office by the last working day of the month.
The Regional Engineer shall collate the monthly reports from the Areas or Districts into a Regional
Monthly report and submit to the Head Office by the tenth (10th) day of the ensuing month.
The Regional Engineer shall in addition to the monthly reports, prepare and submit quarterly, mid-year
and annual reports to the Head Office
Where applicable, the materials division shall carry out appropriate quality control tests and submit
reports to the Regional Engineer.
The Area or District Engineer shall satisfy himself that the works have been executed to the Technical
Specifications and shall measure the completed works as per the method of measurement in the
activity specification. The work measurement form (Form M2) shall be used for this purpose.
The Area or District Engineer shall submit the work measurement form to the Maintenance Engineer.
The Maintenance Engineer shall satisfy himself that the works have been executed to the Technical
Specifications and have been accurately measured before giving approval and recommending to the
Regional Engineer for certification.
The Regional Engineer shall accept or amend the measured work and request for certification.
The Maintenance Engineer and Area or District Engineer shall liaise with the Quantity Surveyor to
prepare the payment certificate comprising;
Certificate form
Progress report form (M7)
Work order form (M1)
Work measurement form (M2)
Work payment form (M3)
Price adjustment form (M4) where applicable
Contract payment summary form (M5)
Contract monitoring form (M6)
The Area or District Engineer shall sign the payment certificate and submit to the District or
Municipal or Metropolitan Assembly for the necessary endorsement.
The Area or District Engineer shall submit the endorsed payment certificates to the Regional Engineer.
The Regional Engineer shall endorse the payment certificates and forward same to Head Office with a
request for payment.
10.0 MONITORING
The monitoring of the condition of the network, monitoring and control of operations and systems
procedures shall be an essential element of the management of the routine and recurrent maintenance
projects. Without adequate monitoring and control, the ability to fulfill work programmes, achieve
specified work quality, operate within budget and produce reliable data for planning will be affected.
10.1 Pre-contract
The Regional Office shall ensure that before commencing the budgeting process for the ensuing year,
road inventory data for each road shall be updated. Also they the region shall carry out road condition
survey on the entire network using the criteria shown annex A
10.1.2 Budgeting
The Regional Office shall ensure that the total cost of planned works does not exceed the approved
routine and recurrent maintenance budget for the year.
The Regional Office shall ensure that the actual field data based on the road inventory and condition
survey shall be used in the project preparation.
The Regional Office shall ensure that all the relevant information is captured in the tender document.
Attention shall be given to the following data:
Correct Tender Number
Invitation to Tender
Instructions to Tender
Form of Tender
Tender Data
Contract Data
Appropriate Conditions of Contract
Line Diagrams
Bills of Quantities
Technical Specification
Drawings
The Head Office and Regional office shall ensure that the provisions of the Procurement Act 663
(2003) or any other applicable procurement guideline are adhered to.
Prior to signing the contract agreement, the Regional Engineer shall ensure that the contract document
contains all the relevant sections of the tender document dully filled where necessary and any other
data prescribed by the Procurement Act 663 (2003).
10.2 Post-contract
The contractor‟s programme of works shall form the basis for monitoring the progress of works. The
following forms shall be used:
Supervisor‟s diary (Form S-2)
Site visit report (Form S-3)
Site visit check sheet (Form S-4)
Progress report (Form M-7)
The Regional Engineer shall ensure that the quality and standard of works shall conform to the activity
specifications.
The Regional Engineer shall monitor and control the contract to ensure that the cost of the project is
within budget. The following forms shall be used to monitor and control the cost of the project:
Contract monitoring (Form M-6)
Progress report (Form M-7)
Additional works shall only be allowed in exceptional cases e.g. emergency situations
The Regional Engineer shall monitor the actual performance of the contractor against the contractors‟
approved programme of works to ensure that works are completed within schedule. The contract
duration should not be more than one (1) year.
Management systems that overload senior management with excess detail and minor operational
decision making are inefficient. Management systems that allow, or depend on, senior management
reaching down and dictating, or unduly influencing, operational programmes are usually unsustainable
and ineffective.
In order that management tasks are fulfilled, it is necessary to clearly define the roles of the various
management levels, and the authority and responsibilities of those levels.
To enable management carry out their duties, especially to maintain control, ensure effective use of
funds and monitor performance, there has to be a flow of information up and down the management
chain.
Development strategies to meet Ministry and Government policies and objectives (such as: to
provide adequate maintenance to the rehabilitated feeder road network).
Preparation of long-term (5-year) plans to identify:
the extent of the engineered network, every year
work programmes and funds required to maintain the network, every year
resources needed to execute those work Programme every year
staffing levels and training requirements to administer and supervise those work programmes,
every year.
Allocation of funds and the authorization of expenditure to a defined network of roads to meet
DFR objectives within budgetary limitations
Administration of an emergency fund taken from the total national budget and allocated as
needed to those regions suffering extraordinary storm damage beyond the scope of the normal
maintenance work programme
Monitoring of maintenance contracts awarded by regions to ensure conformity with work
quantity objectives and budget limits, and application to the defined engineered network only
Monitoring performance by regions, by report analysis and field visits, in terms of:
correct expenditure of funds as authorised
progress towards planned work quantity objectives and activity emphasis
execution of work according to established activity standards
accuracy of performance summary reports and contract payment certificates
preparation of monthly national performance summary reports collated from the regional
reports
identification of significant deviations from policy, planned work quantities and authorised
expenditure at regional levels
preparation of accurate summary performance reports and the prompt submission of these
reports to DFR Head Office
ACTIVITY SPECIFICATION
PREAMBLE
GENERAL
The Bill of Quantities shall be read in conjunction with the Instructions to Bidders.
The short descriptions given for the items of the Bills of Quantities are intended to provide essential
information and identify the work included in the item. The full scope of the Contractor‟s tasks and
obligations involved in the execution of the work under the item is to be ascertained from the
Drawings, Activity Specifications and other relevant Contract Documents. Any omission from or
inclusion or reference in the item description in no way absolves the Contractor of his obligations
under all sections of the Contract Documents.
The Quantities in the Bill of Quantities are approximate only and in no case shall such quantities be
considered to limit or extend the amount of work to be done and material to be supplied by the
Contractor.
The measurement of all completed work shall be as detailed in the Activity Specification and
elsewhere in the Contract Documents. The quantity of work satisfactorily completed under the various
items in the Bill of Quantities shall be agreed between the Contractor and the Engineer. Failing such
agreement, the quantities, as determined by the Engineer shall be final and binding on the Contractor
and payment shall be made accordingly.
Activities carried out shall be adequately covered by photographs. The Engineer may also request for
photographs of critical stages of activities.
As much as possible suitable materials shall be located within 5km. Activity 5.4F shall be applicable
only when directed to be carried out by the Engineer in writing and where such items as
aforementioned go beyond 5km.
In carrying out any activity, the appropriate protective clothing shall be worn by all workers on site.
The appropriate road signs shall be put in place where work is being carried out in such manner not to
endanger road users.
First Aid box with adequate basic items for first aid care shall be kept on site at all times.
Any waste material generated from any activity shall be properly disposed off site as may be directed
by the Engineer.
All items of work indicated in the Bill of Quantities shall be valued by measuring net in the units
stated in the Bill of Quantities, such actual quantities of the Permanent Works as have been executed
strictly in accordance with the Contract Documents or further instructions issued in writing by the
Engineer. Works shall not be valued where they have been executed in excess of the dimensions
shown on the Drawings or where the engineer has not instructed them. In particular, no allowances
shall be made by the Engineer for working space (including exposed concrete faces requiring tanking),
temporary works, or the operation of constructional equipment.
The rates and prices in the priced Bills shall, except in so far as it is otherwise provided under the
Contract, include all constructional Equipment, labour, supervision, materials, erection, maintenance,
insurance, profit taxes and duties together with all general risks, liabilities and obligations set out or
implied in the Contract.
A rate or sum must be entered against each item in the Bill of Quantities as required in the
corresponding column. Where no rate or sum is inserted by the Bidder against any item, it cost will be
deemed to be included in other Bill items. It is the Bidder‟s responsibility to ensure that his prices
included for adequate equipment to complete the works.
The whole cost of complying with provisions of the Contract shall be included in the items provided in
the Bills of Quantities and where no items are provided, the cost shall be distributed among the rates
and prices entered for the related items of works.
Entries within the “Unit Rate” and “Amount” columns appearing in the Bill of Quantities and
Schedules of Day Work Rates shall only be in Ghanaian Cedis in Accordance with the instructions to
Bidders. Should there be any discrepancy in extension, the unit rates will be taken as the correct
entries, and the amounts and summaries will be amended in accordance with the Instructions to
Bidders.
Provisional sums included and so designated in the Bill of quantities shall be expended in whole or in
part at the direction and discretion of the Engineer. Price Adjustment Provisions shall not apply to
Provisional sum Items and any other items where payments are made on a “cost plus” basis. Such
items shall be deemed not to attract any price escalation.
UNITS OF MEASUREMENT
UNIT ABBREVIATION
Millimetre mm
Metre m
Square Millimetre mm2
Square Metre m2
Hectare Ha
Cubic Metre m3
Kilogram Kg
Metric ton (1,000kgf) T
Lump sum Sum
Provisional sum p.sum
Number nr
Hour hr
Week wk
Month mth
Kilometre-Cubic Metre Km-m3
WORK ITEMS
A list of approximate quantities of the principal components of the works can be found in the
Invitation to Bid.
The list is given for the sole purpose of assisting bidders in making a rapid assessment of the general
scale and character of the proposed works prior to an examination of the reminder of the Bills of
Quantities and other contractual documents on which the Bid will be based.
ADJUSTMENT ALLOWANCE
Item for “Adjustment allowance” in the Grand summary has been inserted for the convenience of
Bidders in making last minute adjustments to their Bid Price without the necessity of altering the unit
rates and prices within the actual Bills themselves. Where any such Allowance is entered, it shall be
assessed by the Engineer as a percentage of subtotal in the Grand Summary, and shall be deemed to
apply uniformly to all unit rates and prices in the Bill of Quantities for the purposes of the Contract
and therefore limit of amount stated shall not apply Discount for alternative solutions may also be
entered under this item.
DAYWORK SCHEDULE
Reference should be made to Activity 5.7F of the Bill of Quantities. Work shall not be executed on a
daywork basis except by written order of the Project Manager. Bidders shall enter basic rates for
daywork items in the schedules, which rates shall apply to any quantity of daywork executed.
Payments for daywork shall not be subject to price adjustment unless otherwise stated in accordance
with the provisions in the Conditions of Contract.
DAYWORK LABOUR
In calculating payments due to the Contractor for the execution of dayworks, the hours for labour will
be reckoned from time of arrival of the labourer to the job site to execute the particular item of day
work to the time of return to the original place of departure, but excluding meal breaks and rest
periods. Only the time of classes of labour directly doing work ordered by the Project Manager and
for which they are competent to perform will be measured. The time of gangers (charge hands)
actually doing work with gangs will also be measured but not the time of foremen or other supervisory
personnel. The Contractor shall be entitled to payment in respect of the total time that labour is
employed on daywork rates:
1. “Labour”, together with an additional percentage payment on basic rates representing the
Contractor‟s profit, overheads, etc. as described below:
a. the basic rates for labour shall cover all direct costs to the Contractor, including (but not
limited to) the amount of wages paid to such labour, transportation time, overtime, subsistence
allowance, and any sum paid to or on behalf of such labour for social benefits in accordance
with Ghanaian law. The basic rates will be stated in local currency, as applicable; and
b. An additional percentage payment to be quoted by the bidder and applied to the local currency
payments made under (a) above shall be deemed to cover the Contractor‟s profit, overhead,
superintendence, liabilities and insurance and charges incidental to the foregoing.
DFR Routine Maintenance Management Manual 24
Appendix 1: Activity specifications
c. The cost of hauling materials for use on work ordered to be carried out, as daywork from the
store or stockpile on the Site to the place where it is to be used
will be paid in accordance with the terms for Labour and Constructional Equipment in this
Schedule.
The Contractor shall be entitled to payment in respect of materials used for daywork (except for
materials for which the cost is included in the percentage addition to labour costs as detailed hereto
fore), at the basic rates entered by him in the “Schedule of Daywork Rates (as shown in Table A1).
2. Material” together with an additional percentage payment on the basic rate to cover overhead
charges and profit, as follows:
a. The basic rates for materials shall be calculated on the basis of the invoiced price, freight,
insurance, handling expenses, damage, losses, etc., and shall provide for delivery to store or
stockpiling at the site. The basic rates shall be stated in local currency as applicable, and
b. An additional percentage payment to be quoted by the bidder and applied to the local currency
payments made under (a) above shall be deemed to cover the local currency payments made
under (a) above shall be deemed to cover the Contract‟s profit, overhead, superintendence,
liabilities and insurance and charges incidental to the foregoing.
The cost of hauling materials for use on work ordered to be carried out, as daywork from the store
or stockpile on the site to the place where it is to be used will be paid in accordance with the terms
for Labour and Constructional Equipment in the “Schedule of Daywork Rates (as shown in Table
A1) .
The Contractor shall be entitled to payments in respect of constructional Equipment already on site
and employed on day work at the rental rates entered by him in the “Schedule of Daywork rates (as
shown in Table A1).
a) The basic rates shall be deemed to include due and complete allowance for
depreciation, interest, indemnity and insurance, repairs, maintenance, supplies, fuel,
lubricants and other consumable. The cost of drivers, operators and assistants will
be paid for separately as described under the section on Daywork Labour. In
calculating the payment due to the contractor for Constructional Equipment
employed on daywork, only the actual number of working hours will be eligible for
payment, except that where applicable and agreed with Project Manager, the
travelling time from the part of the site where the Constructional Equipment was
located when ordered by Project Manager to be employed on daywork and the time
for return journey thereto shall be included for payment, and
b) An additional percentage to be quoted by the bidder and applied to the local
currency payments made under (a) shall be deemed to cove the Contract‟s profit
overhead and administrative costs related to the use of such equipment.
In inviting tenderers, the approximate quantities of the principal components of the Works
shall be added in a tabular form as shown below
DFR Routine Maintenance Management Manual 25
Appendix 1: Activity specifications
Lot Region/ Road Name Road Bid Principal Quantities of work items
No. District Length Security
(¢x106)
Clearing Filling Blading/ Sub- Haulage of
(Ha) (cu.m) Scarifica base sub-base
tion (cu.m) material
(cu.m-km)
Labour
Foreman hr
Labourer hr
Carpenter hr
Mason hr
Steel bender hr
Operator (Equipment) hr
Sub-Total
Materials
Cement to BS 12 50 kg -bag
Coarse aggregate m3
Fine aggregate m3
Gravel m3
Formwork m2
Sub-Total
TO COLLECTION ¢
Equipment
Dozer hr
Wheeled loader hr
Grader hr
3
Tipper truck- 5m hr
3
Concrete mixer (10/7), 0.65m hr
Pedestrian roller hr
Bitumen Distributor hr
Sub-Total
TO COLLECTION ¢
COLLECTION
Labour
Materials
Equipment
Technical Specification:
1. Grass cutting shall only be carried out by hand. No attempt shall be made to carry out
this activity using a grader or other heavy equipment.
2. Grass shall be cut to a height of not more than 10cm.
3. The width to be cut on straight roads and outside curves shall be one (1) metre beyond
the back slope.
4. The width to be cut on inside curves shall be sufficient to ensure good visibility as
directed by the Engineer.
5. When this activity is completed work shall be inspected and measured prior to the
commencement of any carriageway or ditch maintenance activities on the same section
of the road.
6. All vegetative matter, roots and topsoil shall be removed to a distance of at least
three (3) metres from the edge of the road carriageway and well clear of any drainage
channels.
Environmental Issues:
1. Grass shall not be removed by burning or the use of chemicals
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Technical Specification:
1. On engineered roads, this activity shall only be carried out by manual labour using
chainsaws, cutlasses and other hand tools to clear secondary growth.
2. On unengineered roads, bush shall be cleared completely including removal of roots
and topsoil, using either manual labour or equipment.
3. The width to be cleared on straight roads and outside curves, shall be one (1) metre
beyond the back slope, or as directed by the Engineer.
4. The width to be cut on inside curves shall be sufficient to ensure good visibility as
directed by the Engineer.
5. When this activity is completed work shall be inspected and measured prior to the
commencement of any carriageway or ditch maintenance activities on the same section
of the road.
6. All vegetative matter, roots and topsoil shall be removed to a distance of at least
three (3) metres from the edge of the road carriageway and well clear of any drainage
channels.
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Technical Specification:
1. On engineered roads, this activity shall only be carried out by manual labour using
chainsaws, cutlasses and other hand tools to clear secondary growth.
2. On unengineered roads, bush shall be cleared completely including removal of roots
and topsoil, using either manual labour or equipment.
3. The width to be cleared on straight roads and outside curves, shall be one (1) metre
beyond the back slope, or as directed by the Engineer.
4. The width to be cut on inside curves shall be sufficient to ensure good visibility as
directed by the Engineer.
5. When this activity is completed work shall be inspected and measured prior to the
commencement of any carriageway or ditch maintenance activities on the same section
of the road.
6. All vegetative matter, roots and topsoil shall be removed to a distance of at least
three (3) metres from the edge of the road carriageway and well clear of any drainage
channels.
Environmental Issues:
1. Bush shall not be removed by burning or the use of chemicals
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Technical Specification:
1. On engineered roads, this activity shall only be carried out by manual labour using
chainsaws, cutlasses and other hand tools to clear secondary growth.
2. On unengineered roads, bush shall be cleared completely including removal of roots
and topsoil, using either manual labour or equipment.
3. The width to be cleared on straight roads and outside curves, shall be one (1) metre
beyond the back slope, or as directed by the Engineer.
4. The width to be cut on inside curves shall be sufficient to ensure good visibility as
directed by the Engineer.
5. When this activity is completed work shall be inspected and measured prior to the
commencement of any carriageway or ditch maintenance activities on the same section
of the road.
6. All vegetative matter, roots and topsoil shall be removed to a distance of at least
three (3) metres from the edge of the road carriageway and well clear of any drainage
channels.
Environmental Issues:
1. Bush shall not be removed by burning or the use of chemicals
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Unit of Measurement:
The unit of measurement shall be in metres (m).
Environmental Issues:
1. Waste material shall be disposed of in a manner that minimises environmental impact.
2. If drains are not cleared properly, they can overtop and discharge onto farmland or
cause erosion elsewhere.
Method of Measurement of Work:
Work shall be measured on the basis of linear metres of ditch cleaned and reshaped.
Unit of Measurement:
The unit of measurement shall be in metres (m).
Technical Specification:
1. This activity shall only proceed after grass cutting/bush clearing on the same section of
road have been completed, inspected and approved.
2. Work shall be carried out at the location and to the specification as directed by the
Engineer.
3. Work shall be executed to the dimensions as specified in the contract drawings.
4. Side ditches shall be excavated to a minimum depth of 40 cm below edge of roadway
and with side slopes of 1: 1 for back slope and 1: 2 inner slopes for machine ditching
or 1:2.5 inner slopes for hand ditching. A drain template should be used to check the
cross section of the drain.
5. Turnouts shall have side slopes of 1:1.
6. All waste material shall be removed to a safe location on completion of the work and
the site left in a clean and tidy condition.
7. The ditch levels shall be set out to ensure a ditch gradient of not less than 1% to the
ditch outlet.
8. Excavated material shall where directed be used to build turn out block-offs.
9. Waste material from ditch excavation shall be removed to a distance of at least
three (3) metres from the edge of the road carriageway and well clear of any drainage
channels.
Environmental Issues:
1. Waste material shall be disposed of in a manner that minimises environmental impact.
2. Discharge points shall be selected to ensure they do not cause any environmental
problems, such as siltation of waterways, or direct discharge onto farmlands.
Unit of Measurement:
The unit of measurement shall be in metres (m).
Environmental Issues:
1. Waste material shall be disposed of in a manner that minimises environmental impact.
2. If a blocked culvert overtops, the water can cause erosion across the road, damage the
culvert and flood farmland and adjacent dwellings.
3. Where communities have deliberately blocked a culvert in order to provide a washing
area, this shall be reported to the Engineer.
Unit of Measurement:
The unit of measurement shall be in metres (m).
Technical Specification:
1. Areas for this activity shall be prepared to a firm base by placing gravel compacted in
150mm layers, inspected and approved before rip rap is placed.
2. Boulders of sizes between 150mm to 300mm shall be placed as directed.
3. The quality of boulder shall be erosion resistant.
4. The rip rap shall be hand packed and tightly wedged to form an even surface.
5. This activity shall include haulage of boulders of up to 5km.
Environmental Issues:
Unit of Measurement:
The unit of measurement shall be in square metres (m2).
Environmental Issues:
Unit of Measurement:
The unit of measurement shall be in square metres (m2).
Technical Specification:
1. Areas for this activity shall be prepared to a firm base by placing gravel compacted in
150mm layers, inspected and approved before boulders is placed.
2. Boulders of sizes between 250mm to 400mm shall be placed as directed.
3. The quality of boulder shall be erosion resistant.
4. This activity shall include haulage of boulders up to 5km.
Environmental Issues:
Unit of Measurement:
The unit of measurement shall be in cubic metres (m3).
Technical Specification:
1. The Engineer will indicate the location and extent of the work.
2. Concrete grade shall be C20/20.
3. The defective part of the culvert shall be broken to sound concrete.
4. Formwork shall be used where necessary.
5. Concrete is to be mixed on site. If mixed by hand, mixing shall continue for not less
than 5 minutes by turning over the cement and dry aggregates for a minimum of 3 times
and further 3 times after adding water or until a thorough mix is achieved.
6. Batching boxes and graduated water containers shall be used to correctly batch the
concrete and a slump cone shall be used to fine tune the water content to produce a
workable concrete slump of 75mm.
7. Concrete shall be placed in the shortest possible time after mixing
(max. 30 minutes), and shall be thoroughly compacted in 10 cm layers.
8. Concrete shall be cured for at least 7 days.
9. This activity shall include haulage of materials.
Health and Safety:
1. Use signs to warn road users that work is in progress.
2. Clean up the site after repairs.
3. Appropriate protective clothing shall be worn during breaking of concrete.
Environmental Issues:
1. Ensure that waste materials are properly disposed of to prevent pollution of nearby
streams.
Unit of Measurement:
The unit of measurement shall be cubic metres (m3)
Technical Specification:
1. As specified in Part 2 of the Special Specifications to MRT Technical Specifications for
Roads and Bridges. (1991 Edition), which is available for reference at the Engineer‟s
office.
2. Refer to design drawings in the tender documents.
3. This activity shall include haulage of all materials.
4. This activity includes the construction of headwalls, wingwalls and aprons.
Environmental Issues:
1. Failure to provide a new culvert can create ponding of water, thereby, resulting in
breeding of mosquitoes.
2. Lack of critical culverts can also lead to access loss to road users.
3. Ensure that waste materials are properly disposed off to prevent pollution of nearby
streams.
Method of Measurement:
Work shall be measured on the basis of length of the culvert between the outside faces of the
headwalls.
Unit of Measurement:
The unit of measurement shall be in metres (m)
Unit of Measurement:
The unit of measurement shall be in cubic metres (m3)
Environmental Issues:
1. Potholes on road surface are dangerous to traffic.
2. Waste materials shall be properly disposed off.
3. Borrow pits can be unsightly and shall be carefully reinstated after use so as not to pond
water.
Method of Measurement:
Work shall be measured on the basis of the volume of material placed
Unit of Measurement:
The unit of measurement shall be in Cubic metres (m3)
Technical Specification:
1. Grass cutting or bush clearing and patching of the road surface shall be completed,
inspected and approved before carrying out this activity.
2. Blading shall be carried out over the full width of the road carriageway.
3. When blading, material shall be moved from both edges of road towards the centre of
road, and the windrow material shall then be spread across the road depositing all the
material to give the correct camber.
4. This activity shall include the removal of all oversize stones and foreign material.
5. No material shall be imported as part of this activity
6. This activity shall be carried out in a manner not to lose surface material.
7. This activity shall not include compaction of the road surface.
Environmental Issues:
1. The activity can generate dust if the road surface is dry.
Method of Measurement:
Work shall be measured on the basis of area of road bladed.
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Environmental Issues:
1. The activity can generate dust if the road surface is dry.
Method of Measurement:
Work shall be measured on the basis of area of road reshaped.
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Technical Specification:
1. Material used to raise the road shall be from an approved source.
2. Gravel material shall be used if it is available within 5km.
3. The finished surface of the road shall be shaped to 6% - 8% (compacted) camber.
4. Compaction shall be in layers of 150mm.
5. This activity shall include the haulage of material up to 5 km.
Environmental Issues:
1. Borrow pits can be unsightly and shall be carefully reinstated after use so as not to pond
water.
2. The activity can generate dust if the road surface is dry.
Method of Measurement:
Work shall be measured on the basis of the volume of material placed
Unit of Measurement:
The unit of measurement shall be in Cubic metres (m3)
Technical Specification:
1. If required, reshaping and compaction of the same section shall be completed, inspected
and approved before this activity commences. This activity only includes the provision
of gravel and the spreading, shaping and compaction of the placed gravel.
2. Regravelling shall be carried out over the full width of the road carriageway.
3. Gravel material from an approved source shall be used.
4. Gravel shall be spread and compacted to specified thickness.
5. The camber of the finished surface shall be 6-8 %. Camber board shall be used.
6. This activity shall include the haulage of gravel up to 5 km.
Environmental Issues:
1. Borrow pits can be unsightly and should be carefully reinstated after use so as not to
pond water.
2. The activity can generate dust if the road surface is dry.
Method of Measurement:
Work shall be measured on the basis of the volume of material placed
Unit of Measurement:
The unit of measurement shall be in Cubic metres (m3)
Technical Specification:
1. Compaction shall start at the edge of the road and work towards the centre, until full
compaction has been achieved.
2. If watering is needed the water bowser shall spray the road before rolling starts and
further water shall be added during rolling to obtain the optimum moisture content for
compaction.
Environmental Issues:
1. Excessive noise and vibration shall be avoided.
Method of Measurement:
Work shall be measured on the basis of the area of road surface compacted.
Unit of Measurement:
The unit of measurement shall be in square metres (m2)
Technical Specification
1. Photographs shall be taken before, during critical stages, and on completion of each
activity.
2. Photographs may also be taken as directed by the Engineer.
3. The date that a photograph is taken should appear on the photograph itself.
4. Photographs shall be printed in sets of two (2) copies in colour and to a size of
5 inches X 7 inches, and indicating the following
Contract name
Name of contractor
Activity name
Activity location
5. Digital pictures are preferred, and when compressed .jpg files of a quality at least
equivalent to the printed photos (normally 2 megapixel or better) are provided to match
the printed photos additional payment will be made according to fixed guidelines.
Environmental Issues
Photographs shall be taken in such a way that they do not injure the sensibilities of the
communities
Method of Measurement
Photographs shall be measured on the basis of approved sets of two photos provided. If the
photos are taken with a digital camera and acceptable quality digital file copies of the same
photos are provided in addition to the hard copies an additional 20% payment will be made.
Unit of Measurement
The unit of measurement shall be in sets of photographs (SET)
Technical Specification:
1. Signs shall be provided as specified in the contract or as directed by the Engineer.
2. The sign and post shall be done as specified in the contract drawings.
3. The letters shall be written in reflective paint.
Environmental Issues:
1. Material for the construction of sign posts shall be environmentally friendly.
Method of Measurement:
Road signs shall be measured on the basis of the approved number provided.
Unit of Measurement:
The unit of measurement shall be in number (nr)
Technical Specification:
Assistance to Supervisor (5.3.1F)
1. The following equipment shall always be available on site as appropriate to the work in
progress, for the use of the Supervisor when inspecting work:
(i) Camber board, Ditch templates, Slump Cone.
(ii) Spirit level, measuring tape, boning rods, twine, pegs, paint, hammer.
2. Assistance to the Supervisor in making measurements to update the road inventory on
sections of road where work has been carried out.
3. Assistance to the Supervisor in recording the condition rating of culverts and bridges on
sections of road where work has been carried out.
Supervisors vehicle (5.3.2F)
4. Fuel for the Supervisor‟s vehicle for use while inspecting the site, in accordance with
current DFR guidelines. The quantity of fuel shall be 10 gallons of diesel and 4 gallons
petrol per week.
5. Motorbike repairs (to be specified)
Environmental Issues:
Method of Measurement:
Assistance to Supervisor: Measured on the basis of percentage of work completed.
Supervisor‟s vehicle: Reimbursable from provisional sum with mark-up of 15% of the
reimbursable cost
Unit of Measurement:
Assistance to Supervisor: The unit of measurement shall be in sum (Sum)
Supervisor‟s vehicle: Provisional sum (P.sum)
Technical Specification:
Haulage shall be in excess of 5km
Environmental Issues:
1. The material shall be well covered to avoid dust nuisance.
Method of Measurement:
Work shall be measured on the basis of cubic metres kilometres, where the km are measured
after the first 5 km from the gravel/boulders source.
Unit of Measurement:
The unit of measurement shall be in cubic metre kilometres (m3- km)
Technical Specification:
Heavy equipment shall be moved along major roads using a low-loader
Environmental Issues:
1. Movement and disposal of material shall be done properly to minimise environmental
impacts.
Method of Measurement:
Movement of resources within the package shall be measured on the basis of percentage of
work completed.
Unit of Measurement:
The unit of measurement shall be in sum (Sum)
Technical Specification:
1. The Engineer will mark in chalk the road code, the chainage, the direction for the arrow,
the drainage structure ID and the position where these shall be painted in chalk on each
culvert (or other location).
2. Letters shall be written in letters 75mm high in red paint on a white background using
weatherproof paint, as per drawings.
3. The road code, the chainage and the drainage structure ID shall be clearly written on
both headwalls of each culvert so that they can be seen from the road, or as otherwise
directed by the Engineer, with an arrow indicating the direction of increasing chainage.
4. Locations other than culverts may be marked as directed by the Engineer.
Examples of markings:
BA-ASN-A-027 BA-ASN-A-027
km 5.567 km 5.567
ASN_00123 ASN_00123
Environmental Issues:
1. Disposal of material shall be done properly to minimise environmental impacts.
Method of Measurement:
This work shall be measured by the number of locations marked.
Unit of Measurement:
The unit of measurement shall by number (nr).
Technical Specification:
1. Only as instructed by the Engineer in writing.
Environmental Issues:
1. As applicable to instruction given.
Method of Measurement:
As per schedule of rates.
Unit of Measurement:
As per schedule of rates.
List of activities
ACT. NO. DESCRIPTION UNIT
VEGETATION CONTROL
1.1F GRASS CUTTING m2
1.2F CLEAR SAVANNAH BUSH m2
1.3F CLEAR LIGHT BUSH m2
1.4F CLEAR THICK BUSH m2
DRAINAGE MAINTENANCE
2.1.1F DITCH CLEANING - UNLINED m
2.1.2F DITCH CLEANING - LINED m
2.2F RE-EXCAVATE DITCHES m
2.3F EXCAVATE NEW DITCHES m
2.4F REPAIR/REPLACE SCOUR CHECKS nr
2.5F CLEANING CULV& INLET/OUTLET DITCHES m
2.6F PROVISION/REPAIR OF RIPRAP m2
2.7F PROVISION/REPAIR OF STONE PITCHING m2
2.8F FILLING WITH BOULDERS m3
STRUCTURE MAINTENANCE
3.1F MASS CONCRETE CULVERT REPAIRS m3
3.2F REINFORCED CONCRETE CULV REPAIRS m3
3.3.1F CONSTRUCTION OF NEW CULVERTS 900mm U m
3.3.2F CONSTRUCTION OF NEW CULVERTS 1200mm U m
3.3.3F CONSTRUCTION OF NEW CULVERTS 1800mm U m
SURFACE MAINTENANCE
4.1F PATCHING OF BITUMEN SURFACE m3
4.2F PATCHING OF GRAVEL/EARTH SURFACE m3
4.3F BLADING ROAD SURFACE m2
4.4F RESHAPING ROAD SURFACE m2
4.5F SECTIONAL RAISING OF ROAD m3
4.6F SECTIONAL REGRAVELLING m3
4.7F COMPACT ROAD SURFACE m2
GENERAL ITEMS
5.1F PROVISION OF PROGRESS PHOTOGRAPHS nr
5.2F PROVISION OF ROAD SIGNS nr
5.3.1F ATTENDANCE ON SUPERVISOR - ASSISTANCE sum
5.3.2F ATTENDANCE ON SUPERVISOR - VEHICLE p.sum
5.4F HAULAGE OF MATERIALS m3-km
5.5F MOVEMENT OF RESOURCES WITHIN PACKAGE sum
5.6F MARKING CHAINAGES ON CULVERTS nr
5.7F DAYWORKS p.sum
Annex A
ROAD CONDITION SURVEY AND TRAFFIC COUNT
The table below shall be used to determine the condition of the road and its appurtenances
Traffic Count
Undertake a 2 day, 12-hour, traffic tally count on the market day and a non market day using the methodology
in the handbook to estimate the Average Daily Traffic Summary (p.5 of handbook).
Roughness
Roughness is the irregularity of the road surface. This is sometimes identified as “riding comfort” and is a
measure of the longitudinal evenness of the road. Roughness is normally measured in units on the international
roughness index (IRI)
Definitions of three roughness levels are suggested, and it is possible to correlate each level to an IRI value, or
the comfortable travel speed of a vehicle, although the latter requires careful calibration. Below is the
relationship between IRI and speed.