Annex 1 - Quality Plan FMR PDF
Annex 1 - Quality Plan FMR PDF
PLGU LOGO
QUALITY PLAN (OUTLINE) FOR ROAD SUBPROJECT (Please specify sub-project title)
Form No. ___________ Date : ________________________________
1. Project Organization
1.1 Organizational Structure - Staff Qualifications Standards - LGU-EO for Creation and Designation of PPMIU members- upon approval of change of - PPMIU/RPCO/PSO - IMA/MOA
personnel NPCO (1)
1.2 Activity Schedule - Program of Work - S-Curve/PERT-CPM - to be revised in accordance - PPMIU/RPCO/PSO - IMA/MOA
- per time Requirement of PRDP Operations Manual w/ Operations Manual NPCO (1)
1.3 Human & Material Resources - Manning Schedules - start of project - PPMIU/RPCO/PSO - construction contract
- Budget Schedule - re-alignment NPCO
(1)
- re-budgeting
3. Design Review
- IBUILD Manual / a. Design Cosiderations - upon project presentation - PPMIU/RPCO/PSO - Compliance (1) Design Review may include:
Operations Manual - evaluation of existing transport infrastructure - after RPAB's conditional NPCO - Non-Compliance Report (NCR) (2)&(3)
- DPWH Guidelines - traffic data approval - Corrective Action Report POW - Preconstruction Survey
- AASHTO/ACI - pre-construction activities - NCR Close-out Safety Manual - Allocation for soil investigation
b. Engineering Design
- Field Survey Information
- Drainage Data
- Soil and geological conditions
- Natural and Man-made features affected by the
general alignment and to be considered in the
project design
- Soil subsurface information
e. Design concept
f. Design criteria
g. Implementation Schedule
h. Cost Estimate/Price Analysis
i. Contract Documents
j. Safety
Roads 1 of 2
PLGU LOGO
QUALITY PLAN (OUTLINE) FOR ROAD SUBPROJECT (Please specify sub-project title)
Form No. ___________ Date : ________________________________
4. Inspection/Testing
- DPWH Standard Specifications Vol. 2 a. Pre-construction Joint Survey - as required by specs - PPMIU/RPCO/PSO - survey report ITP & MMTR
- IBUILD Manual / b. Alignment (H + V) / ROW Establishment - as required by specs NPCO - survey report
Operations Manual c. Removal of Existing Structures and Obstruction - as required by specs - survey report (4)
- DPWH/ASSHTO/ASTM Standards d. Materials Testing - as required by specs - test reports (4)
- Inspection and Test Plan (ITP) d.1 Receiving Inspection and Testing (Delivered
- Min. Materials and Testing Requirements Samples Materials, Grading, CBR) For all inspection & test results.
(MMTR) d.2 In-process Inspection and Testing (FDT, Slump - Compliance
Test, Concrete Breaking, RSB Test) - Non-Compliance Report (NCR)
d.3 Final Inspection and Testing (Core Sampling, - Corrective Action Report
NDT, Drilling, etc.) - NCR Close-out
5. Document Control
Project Documentation Procedures a. Contractor Supplied Documents - as required by construction - Contractor - Traceability If by contract
contract - PPMIU/RPCO/PSO
NPCO
( 1 ) IBUILD Operations Manual ( 3 ) DPWH Design Guidelines Criteria and Standards (Volume II)
( 2 ) DPWH Design Guidelines Criteria and Standards (Volume I) ( 4 ) DPWH Standard Specifications Vol 2 (Bridge; Highway and Airports) 1988
CC: RPCO/PSO/NPCO
Note: This Quality Plan applies to all infrastructure projects under the PRDP, however, the LGU may revised or formulate their own Quality Plan as they consider necessary and applicable
Roads 2 of 2