ALTERNATIVE METHOD FOR SPEEDY CULVERT CONSTRUCTION

CASE STUDY IN KEGALLE DISTRICT

BY
PRASANNA KANGARA
[RESIDENT ENGINEER - KEGALLE)
INTEGRATED ROAD INVESTMENT PROGRAM
Need for Speedy Method
 Stage construction is limited due to restricted ROW
 Difficult to construct By-Pass roads due to restricted ROW and
Terrain/Geometry in Kegalle Area

 Impossible to close roads for longer durations

Solution – PRE CAST CULVERTS


> PRE CAST CULVERTS
Two types…..
* PRE CAST BOX CULVERTS
* PRE CAST HUME PIPE CULVERTS
PRE CAST BOX CULVERTS
 Pre Cast Box Culvert is formed by pouring Grade 25/20 concrete in to the
reinforced box panel which consist of 950mm Wide, 175mm Thick (Base &
Deck) and 600mm High & 175mm Wide Double Walls,1 m long at Pre Cast
yard.

00 00
10 10 17
5

175
60
0
95 95
0 0 17
5

600
Y10 @ 150
Y10 @ 150 Y10 @ 150
90
Y10 @ 150

175
40
Y10 @ 150 Y10 @ 150
85

950
950

90 40
Y10 @ 150
PRE CAST BOX CULVERTS…Contd…
 The inward & outward sockets can be introduced in pre
cast box panels which is used to control lateral, upward &
downward movements of pre cast boxes.
PRE CAST BOX CULVERTS…Contd…
 After the curing, pre cast boxes shall be transported to construction sites by a
boom truck.
 Head Walls up to culvert Base Level shall be constructed before placing of pre cast
boxes.
 The Placing bed for Pre Cast Boxes shall be prepared with ABC (150mm Thick) plus
15mm Thick quarry dust layer.
 Pre Cast Boxes shall be placed across the road by a Boom Truck

 Placing of a pre cast box using a Boom Truck


PRE CAST BOX CULVERTS…Contd…
 300mm wide Geo-textile Layers shall be wrapped at joints of pre cast boxes
to avoid infiltration of backfill material around the pre cast boxes in to the
culvert through the joints.
PRE CAST BOX CULVERTS…Contd…
 The excavated area should be back filled using suitable material [Ex.
Sand, Quarry Dust, ABC or Soil] and ABC overlay will be done to allow
for traffic.

 The possible time frame for this method of a pre cast box culvert
completion is about 08 Hours, and can be opened for traffic.
(Except Balance Part of the Head Walls etc..)

 Labour Requirement
- Two Skilled Workmen
- Two Un-skilled Workmen
- Boom Truck Operator
PRE CAST BOX CULVERTS…Contd…

 Head walls along the road shall be constructed up to road


finish levels and then catch pit for up stream side will be
launched to divert up stream flow.

 Down stream side leader way should be cleared for free


flow across the culvert to the end of leader way path.
PRE CAST BOX CULVERTS…Contd…
 After Completion…
PRE CAST PIPE CULVERTS…Contd…

Pre Cast Hume Pipe Culverts also can be


constructed with same procedure as
described below.
PRE CAST PIPE CULVERTS…Contd…
 3D Drawing – With Encasement

00
12

10
00

150
15
0
1000

75
0 15
60 0

150
75
PRE CAST PIPE CULVERTS…Contd…
 3D Drawing – Without Encasement

75mm Collar Ring

Pre Casted Pipe Joint For


Fill Height Over 600mm

200
12

150
00

0
30
COST COMPARISION OF CULVERT
Mn/per m
CONSTRUCTION TYPES
0.08

0.07

0.06

0.05

0.04

0.03

0.02

0.01

0.00
Time
TIME COMPARISION FOR ROAD CLOSURE
Consumed FOR CULVERT CONSTRUCTION TYPES
Days

30

25 Days

25
25 Days

20
17 Days

15

10

5 5 Days
1 Days
1 Days
1 Days
0
INNOVATION LEADS CONVENIENCE