The table below is shown, the question describes to create two budgets one for

early-start schedule and one for late-start schedule and give an explanation of why
the two budgets are different.

Activity Duration (days) Immediate predecessors Cost

A 3 – $3,000

B 4 –  2,000

C 3 –  6,000

D 2 C  2,000

E 1 B  1,000

F 5 A 10,000

G 2 B  4,000

H 3 B  9,000

I 11 C 11,000

J 3 D, E  3,000

K 1 F, G  1,000

L 4 K  2,000

M 4 J, H  8,000
There are already answers to this question provided in this website, I do not
consider that answer to be right, please do not copy the same answer but rather
provide me cash-flow of the early start schedule and the cash flow of the late
schedule.
Also, you don't need to show how to create the network diagram and calculating
the critical path but rather show how to calculate the cash flow.