DILG-CORDILLERA ADMINISTRATIVE REGION


QME-QP-CAR-08
PROCESS QUALITY MONITORING AND Rev. No. Eff. Date Page
02 03.15.19 1 of 1
EVALUATION (QME)
OFFICE
MONITORING AND EVALUATION OF LOCALLY-FUNDED PROJECTS (LFPs) AND PERFORMANCE
PROCEDURE TITLE
CHALLENGE FUND (PCF)
OBJECTIVE
80 % of LFPs and PCF projects are completed through monitoring within prescribed timeline
STATEMENT
CURRENT PERIOD April 2020
INDICATORS Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Total
Objective: 80 % of LFPs and PCF projects are completed through monitoring within prescribed timeline
A Total number of LFPs & PCF projects
0 0 4 0 4
completed within prescribed timeline
B Total number of LFPs & PCF projects 18 18 18 18 18
C Formula: A x 100
Target Result : 22.22
B 0 0 0
80% %
D Gap Analysis: (In case the objective is not
met, put your analysis why it is not met)
Note: For unmet targets, the QMS Secretariat will issue correction and corrective action using the Corrective Action Report
(CAR) duly signed by the QMR.

Prepared By: Noted By:

GYDA H. NAMINGIT REGINA ELIZABETH L. MAMMAG


Deputy Quality Management
Process Owner Representative