GANPATI CONSTRUCTION COMPANY

DAILY PROGRESS REPORT


Site :- IIT Guwahati Number of staff :- 15 Date:- 01-11-20

CONTRACTOR REPORT
MAN POWER
SL.NO CONTRACTOR NAME working Remark / Work Report
TOTAL WORKING OVER TIME
location

i kasim L-2 17 16 13 10:00 PM 3rd FL slab beam binding

ii bador L-1 32 3 0 3rd FL slab panding,

Hafijul L-3 23 23 13 10:00 PM 3rd to 4th FL column binding,Lift shuttering,.

R-1 16 3rd fl slab beam binding,

iii R-2 0 No work.


azijur 32
R-4 4 0 3rd fl covering, clining,

R-3 12 3rd FL Beam bottam shuttering

AAC
iv Abdul ali 15 15 ---- ---- ground FL parking, AC outdoor, casting
Block
v Supply (Dulal) ---- ---- 0 mixtur operatar
vi supervisor ---- 2 2
1 Dulal Ali Total = 121 91 30 REST
2 Feroj khan 5 5 electrical work
3 Saugar 2 2 Plumber work
Hatim Tai 16 16 Drin wall shuttering,
4
Supply (Hatim)
5 Mouni Daka
WORK DONE REPORT
7th RA Bill In complete
SL.NO ITEMS QTY Before qty CUM QTY UNIT Upcoming RA Bill QTY
work QTY

1 All RCC-M30 Work 8.31 9538.55 9546.86 cum 56.44 240.44

2 All Shuttering Work 24 20032.1 20056.1 sqm 602.11 1663.36

3 Brick work 0
94.09 94.09 cum 0.00 0.00

4 Steel 0 1460.27 1460.27 MT 29.48 25.35


5 AAC (600×200×200) 0 42.576 42.576 cum 0.00 0.00
6 AAC (600×200×150) 0 15.1 15.1 cum 0.00 0.00
RCC- M25
7 0 20.158 20.158 cum 0.00 0.00
(for- AAC Block)
8 PCC 1:3:6 (Drain) 0 10.8 10.8 cum
9 Shuttering (Drain) 0 622.56 622.56 cum
10 Steel (Drain) 0 0 MT
11 RCC M-25 (Drain) 0 66.336 66.336 cum

MATERIAL RECEIVED REPORT


Total
Received QTY (per B/F Cum.
SL.NO MATERIAL DETAILS Cumulative UNIT Remark
Day) Rec
QTY
1 CEMENT 0 63085 63085 Bags

2 TMT 8MM 0 154.876 154.876 MT

3 TMT 10MM 0 220.4 220.4 MT

4 TMT 12MM 0 31.03 31.03 MT


Total Steel Received Qty(mt)=
5 TMT 16MM 0 437.501 437.501 MT
1655.126
6 TMT 20MM 0 207.259 207.259 MT

7 TMT 25MM 0 417.21 417.21 MT

8 TMT 32MM 0 186.85 186.85 MT


9 20MM STONE 48.66 7972.35 8021.01 CUM

10 SAND 46.87 5809.87 5856.74 CUM

11 DIESEL 400 20302 20702 LTR

12 Brick 0 45000 45000 Nos


13 AAC (600×200×200) 0 5404 5404 Nos
14 AAC (600×250×200) 0 1718 1718 Nos
15 AAC (600×200×150) 0 6817 6817 Nos
16 AAC (600×250×150) 0 250 250 Nos
17 10 mm Stone 0 17.74 17.74 CUM

MATERIAL CONSUMPTION REPORT


Total
Consumation QTY B/F Cumu. Balance qty Remark
SL.NO MATERIAL Cumulative UNIT
(per day) Cons.
QTY
1 TMT 8MM 0
131.154 131.154 MT 23.72

2 TMT 10MM 0
176.203 176.203 MT 44.20

3 TMT 12MM 0
19.779 19.779 MT 11.25
Total Balance Steel
4 TMT 16MM 0
422.780 422.78 MT 14.72 Qty(mt)=
5 TMT 20MM 202.191 202.191 MT 5.07 194.85
0
6 TMT 25MM 0 379.443 379.443 MT 37.77

7 TMT 32MM 0
128.724 128.724 MT 58.13
cover-3, casting-64
8 CEMENT 77 61623 61700 Bag 1385 ,drain-10
Apx 200 cum sand
9 SAND 4.41
5225.54 5229.95 Cum 626.79
shortage as per site

10 20mm STONE 6.4


7597.03 7603.43 Cum 417.6

11 DIESEL 230
20255 20485 LTR 217

12 Brick 0
32931.5 32931.5 nos 12068.5
13 AAC (600×200×200) 0 1788 1788 nos 3616
14 AAC (600×200×150) 0 846 846 nos 5971
15 10 mm Stone 0 12.58 12.58 Cum 5.16

COMPANY MACHINERY REPORT


CLOSING
METER/ Total Diesel
MACHINE OPENING METER/ CLOSING Remark
(Hrs) (Ltr)
SL.NO STARTING TIME TIME

1 JCB 1588.70 1596.30 7.60 60.00 soil cutting for drain

2 Concrete pump 895.16 898.05 2.89 90.00


0:00
3 Mixture Machine - 01
10:30
0:00
4 Mixture Machine - 02 0:00
0:00
12:00 PM 3:00 PM 3:00
5 Mixture Machine - 03 0:00 10.00
0:00

HIRE MACHINERY REPORT


CLOSING
METER/ Total Diesel
MACHINE OPENING METER/ CLOSING Remark
(KM) (Ltr)
SL.NO STARTING TIME TIME
9:30 AM 1:30 PM 4:00
1 pocklen 2:30 PM 5:00 PM 2:30 70.00
5:30 PM 7:00 PM 1:30