Professional Documents
Culture Documents
THE Liquefaction Plant: Fig. 5-1. Natural Gas Liquefaction Ow Diagram (Source: Poten & Partners)
THE Liquefaction Plant: Fig. 5-1. Natural Gas Liquefaction Ow Diagram (Source: Poten & Partners)
LIQUEFACTION
PLANT 5
INTRODUCTION
The liquefaction process transforms natural gas into
LNG by cooling it to –163ºC, after which it is stored until it
can be shipped on board LNG tankers (fig. 5–1). There are
variations in liquefaction plant designs, but fundamentally
the liquefaction processes are very similar and, setting aside
the scale, quite straightforward. Liquefaction is nothing more
than a giant refrigeration process, involving no application of
chemical processes to the natural gas other than pretreatment
for impurities.
Feedgas Acid Gas Dehydration Mercury Gas NGL Liquefaction Nitrogen LNG
Receiving Removal Removal Precooling Separation Removal Storage
Fractionation
SITING CONSIDERATIONS
The LNG plant is a large and complex industrial undertaking. It typically
includes gas processing and purification, liquefaction, product storage and
marine loading systems, utilities, control rooms, material and equipment
warehousing, maintenance shops, and infrastructure facilities, often
including housing for the operating staff.
Because the feedgas pipeline to the plant can be costly, sponsors
generally seek to minimize the distance between the gas fields and the
liquefaction plant. For example, a two-train 6.6 MMt/y (9.2 Bcm/y) LNG
project requires more than 1 Bcf/d (10.3 Bcm/y) of feedgas. A 40-inch pipeline
to transport this quantity of gas daily could cost around $2–$5 million per
mile, depending on a variety of factors including whether the gas fields are
onshore or offshore, the topography and complexity of the terrain (tropical
jungle being more challenging than desert) between the fields and the
plant, environmental considerations, the remoteness of the facilities, and
the availability of pipe-laying equipment.1 By contrast, the cost to construct
liquid-loading lines and harbor infrastructure is so high that there are clear
advantages to locating close to deepwater. These are examples of the trade-
offs that play a major role in site selection.
Other issues relate to the environmental and physical aspects of the
site. Factors such as water depths, tides, currents, and wave activity have
a direct impact on the marine facilities. For plants located in the Northern
Hemisphere, the potential for ice buildup in the harbor is a factor to be
considered. Onshore soil and seismic conditions also influence the design
of storage and other structures.
The need to build roads, airstrips, construction docks for material and
equipment delivery, utilities, and housing for employees can raise the overall
cost of liquefaction projects substantially. In remote or challenging areas,
the cost of labor also increases as employees receive higher compensation
for tougher work conditions; the costs associated with transportation and
employee care are also much higher. In this respect, the various Qatar
LNG projects now hold an advantage, since they are ideally located close
to the gas field and have access to infrastructure developed for earlier
projects. Indonesian projects at Arun and Tangguh, by contrast, are far more
remote and consequently incur much higher costs. Australia’s NWS project
encountered high costs as a result of its remote location, extreme heat, and
the cost of dealing with Australian labor unions. Russia’s Sakhalin Island,
with its below-freezing temperatures, tundralike conditions, and ice-prone
waters, represents the most remote and tough project environment to date,
as well as one of the costliest. The two-train Sakhalin II LNG facility in the
The Liquefaction Plant 111
Russian Far East entails the construction of offshore oil and gas production
facilities, costs associated with construction in extreme cold weather, a
pair of 500-mile oil and gas pipelines to bring the production to a nearly
ice-free port, and substantial support infrastructure. Theoretically, these
disadvantages are balanced by Sakhalin’s proximity to its target markets of
Japan, Korea, and Mexico.
Political risk considerations also have to be factored in before choosing
a potential location. Some locations are more vulnerable to disruptions,
including sabotage, kidnappings, and threats of terrorism.
LIQUEFACTION PROCESS:
TECHNOLOGY OVERVIEW
Feedgas purification and pretreatment
The natural gas entering a liquefaction facility will often contain
several contaminants that must first be reduced to acceptable levels to
ensure satisfactory liquefaction plant performance or to meet LNG sales
specifications or both. The level of each contaminant depends largely on
the characteristics of the production field and the extent of upstream gas
treatment. A description of the various pretreatment processes follows.
First, any hydrocarbon condensates still present in the incoming natural
gas stream are separated, used as plant fuel, or resold. Acid gas removal
comes next, reducing carbon dioxide levels to around 50 parts per million
(ppm), to prevent freezing in the main cryogenic exchanger. Hydrogen sulfide
levels are similarly reduced, to below 3 ppm, to meet normal sales gas
specifications.2 LNG facilities typically use either any of the many available
amine-type systems or Sulfinol to meet these specifications. If the feedgas
contains significant hydrogen sulfide, it may also be necessary to convert
this compound to sulfur by running the separated acid gas effluent stream
through a sulfur recovery unit.
Feedgas leaving the acid gas removal system is saturated with water
vapor that must be removed to prevent freezing in the main liquefaction
exchanger. This dehydration is achieved in two steps. First, the gas is cooled
using air or water and a precooling refrigerant to condense much of the water
out of the gas stream. Second, the gas is passed through a molecular sieve
to reduce residual water vapor to very low levels (below 0.1 ppm).
The feedgas may also contain mercury. This contaminant must be
removed down to the smallest detectable amount, about 0.1 microgram
112
per normal cubic meter (Nm3), because even trace quantities of mercury
can cause corrosion of aluminum heat exchanger equipment.3 Mercury
removal is typically achieved by passing the feedgas through a sulfur-
impregnated carbon bed, where the mercury reacts with the sulfur to form
mercuric sulfide.
Finally, any remaining heavier-hydrocarbon components, such as
pentanes, hexanes, and aromatics (e.g., benzene), must be separated to
prevent freezing in the main cryogenic exchanger. These heavy hydrocarbons
are removed by condensing the liquids using a precooling refrigeration
process ahead of the main liquefaction process. The separated liquids are
typically fed into a fractionation system involving a succession of distillation
columns, typically a de-ethanizer, de-propanizer, and de-butanizer in
sequence, with each column stripping out one component from the liquid
mix. Any recovered lighter hydrocarbons from this fractionation process,
such as ethane, propane, or butane, are either used as refrigerant makeup,
reinjected into the liquefaction feedgas (up to the gas specification limits),
used for plant fuel, or sold as separate NGL products.
Liquefaction processes
Several proprietary processes are marketed today for large-scale
baseload natural gas liquefaction plants. These processes fall into the
following broad categories:
• Pure-refrigerant cascade process
• Propane-precooled mixed-refrigerant processes
• Propane-precooled mixed-refrigerant, with back-end nitrogen
expander cycle
• Other mixed-refrigerant processes
• Nitrogen expander-based processes
Table 5–1 shows the processes used in liquefaction facilities. All these
liquefaction process designs are proprietary. The choice of an initial design is
critical since all future trains will certainly utilize the same design. Expansion
licenses are generally negotiated at the front end of each EPC contract for
development of a new plant.
The Liquefaction Plant 113
Malaysia, MLNG Satu and Dua 1983 and 1994 APCI MCR
Inlet scrubber
Amine
treater
Dry gas filter
Scrubber
Propane
surge
LNG
Heat exchangers Heat exchangers Heat exchangers
Ethylene surge
NGL/(C2+)
Ship vapor blower
To ship loading
facilities
Transfer pump
Source: ConocoPhillips
The main advantages of the C3-MR process are its proven technology and
high efficiency. C3-MR liquefaction systems have been widely used for nearly
30 years in a wide variety of process and environmental settings. Start-up and
operation of these facilities have generally been free of major problems, and
plants have generally exceeded design throughputs on a continuous basis.4
The C3-MR process also achieves high efficiencies by adding the propane
precooling stage for both feedgas and the mixed-refrigerant loop, allowing
the MCR vaporization temperature curve to closely match the natural gas
liquefaction curve. This, of course, comes at an extra equipment cost, but the
operational gains have proven this additional investment to be justified.
A disadvantage of the MCR process is limited flexibility to shift
refrigeration load between the propane and mixed-refrigerant cooling
circuits, but to some degree, this problem has been alleviated by more-
recent designs having both propane and MCR compression stages on a
single turbine driver, to better balance the available turbine power.
The Liquefaction Plant 117
NGL
to tank
HP MP
propane propane
chiller chiller
Natural
gas feed
LP
propane
NGL to fractionation chiller
Mixed
refrigerant
HP MP LP loop
propane propane propane
chiller chiller chiller
LNG
LNG SubCooler
Compander
Feed C3
pre-cooling N 2 economizer
range for the more robust centrifugal compressor designs and reducing
spares costs. No baseload Liquefin facilities have been built to date, although
front-end engineering designs (FEEDs) incorporating this process have been
drafted for several potential projects.
Fig. 5–5. Axens Liquefin dual mixed-refrigerant (DMR) process (Source: Axens, BP)
NG
Pre-cooling
section
E1A
E1B CW1
C1
Liquefaction
section
CW
E2 2A/B
C2
Sub-cooling
section
E3 CW
3A/B
G
X1 C3
LNG
Driver technology
The choice of drivers for the refrigeration compressors has for several
years been a source of ongoing debate, which seems likely to continue. The
very earliest plants used steam turbines to drive the compressors, with
the notable exception of the Kenai project, which used gas turbines (more
efficient at Alaska’s colder ambient temperatures). Steam turbines offered the
advantage of reliability, although the need for vast amounts of treated cooling
water was a major drawback. By the late 1980s, as industrial gas turbines
became more broadly accepted in a variety of applications, especially in
power generation, these became the drivers of choice. However, there are
several differing approaches: ALNG uses multiple, smaller gas turbines in a
very flexible arrangement, while the Nigerian and Qatari projects use much
larger turbines coupled to multiple compressors. A further variation is the
use of electric drive compressors with the electric power provided from gas
turbines operating as power generators. Air cooling has generally replaced
water cooling. While air cooling has a much larger footprint, the technology
appears more reliable and avoids the need for complex, maintenance-
intensive water-cooling systems.
Utilities
As liquefaction plants are often located in remote regions, the provision
of utilities may be a critical feature of the plant design. The plants usually
have their own power generation facilities, with 100% redundancy to minimize
operational interruptions. Water supply may also be a factor, especially if
water-cooled equipment is being used in the process.
Single-containment tanks
Single containment refers to a freestanding, open-top inner tank made of
9% nickel steel, with a carbon steel outer tank. A layer of several feet of perlite
insulation is sandwiched between the two tanks. The base of the inner tank
rests on rigid foam blocks for insulation, then on the foundation. The choice
of foundation is dictated by site soil conditions and can have a ringwall, pile,
or stone column design. The tank base usually includes a heater system to
maintain the ground at a constant temperature and prevent tank disturbance
due to frost heaves. The tank has a steel roof designed to contain gas vapor
and support a suspended ceiling that insulates the top surface of the inner
tank. The outer steel tank wall will not contain any LNG in the event of a
breach in the inner tank, so this type of tank must have external secondary
containment, usually a bermed area with sufficient capacity to contain the
entire contents of the tank plus a margin of safety. This tank design is the
The Liquefaction Plant 123
Double-containment tanks
Double-containment tanks are similar to single-containment systems,
except that the outer tank is capable of containing liquid spills in the event
of a breach in the inner tank wall. This tank design has a freestanding 9%
nickel inner tank and an outer tank made of either prestressed reinforced
concrete or poured-in-place reinforced concrete strengthened by an earthen
or rock embankment. Double-containment tanks require less plot area than
single-containment designs because of their concrete outer wall. However,
the roof is still constructed of steel and will not contain vapor produced
by failure of an inner tank. The approximate cost for a double-containment
tank is 40% higher than for a single-containment design. Recent steel cost
increases have raised prices for this tank design nearer to the cost of the
all-concrete full-containment design. This is a subject of discussion in the
next section.
Full-containment tanks
Full-containment tank designs add a concrete roof to the double-
containment tank’s concrete outer walls (fig. 5–7). This roof can withstand
higher pressures and lower temperatures than the steel tank design,
providing containment for any vapor produced by a breach in the inner tank.
Full-containment tanks provide the greatest design integrity and allow the
closest spacing between tanks and process equipment when land area is
constrained. However, this is the most expensive aboveground tank design,
with a cost about 50% higher than for a single-containment design.
124
Membrane tank
Membrane tanks are similar to the designs found in membrane
containment LNG tankers. Primary LNG containment is provided by a flexible
stainless steel membrane, supported by a layer of insulation mounted on
an outer prestressed concrete wall. This outer concrete wall and roof can
contain both the liquid and vapor from a leak in the primary membrane.
Membrane tanks have similar or slightly higher costs than freestanding full-
containment designs. Very few membrane tanks are in service, as they are
perceived to be less durable than other tank designs.
Two-Train LNG Project Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Conceptual Idea
Feasibility Study
Basis of Design (BOD)
Front-End Engineering and Design (FEED) Bid
FEED
EPC Bid
EPC Contract
Ready for Start of Train 1
Ready for Start of Train 2
Fig. 5–8. LNG export facility development phases (Source: Poten & Partners)
RECENT TRENDS
Larger trains
Economies of scale as a result of bigger individual trains and larger
venture production capacity have enhanced the competitiveness of LNG
in international energy markets. A decade ago, the largest LNG production
The Liquefaction Plant 129
train was about 2.5 MMt/y (3.5 Bcm/y). By the mid-to-late 1990s, 3 MMt/y
(4.2 Bcm/y) became the benchmark, rising to 4–5 MMt/y (5.6–7 Bcm/y) by
the turn of the century. The latest LNG mega-trains in Qatar have nameplate
capacities of 7.8 MMt/y (10.9 Bcm/y). This progression in liquefaction train
size is illustrated in figure 5–9.
APCI
7
Phillips
APCI or Phillips
6
Shell
Linde
Train Size (MMt/y)
5
Technip
4 Pritchard
Technip/ Pritchard
3
0
1960 1970 1980 1990 2000 2010
Start-up Year
Fig. 5–9. LNG train size growth (Source: Poten & Partners)
shaft gas turbines as compressor drivers. LNG train capacities were then
increased to 3.3 MMt/y (4.6 Bcm/y) or more for the C3-MR liquefaction
process by stepping up to GE Frame 6 gas turbine drivers for the propane-
precooling refrigeration cycle compressor and GE Frame 7 gas turbine
drivers for the mixed-refrigerant compressor. This was followed by the use of
GE Frame 7 gas turbine drivers for both the propane and mixed-refrigerant
cycles, taking individual train capacity up to 4–5 MMt/y (5.6–7 Bcm/y). The
upcoming Qatari mega-trains have taken this trend further, using GE Frame
9 gas turbine drivers for the propane, MCR, and nitrogen cycles. Large
electric motors are being used as compression drivers on Norway’s Snøhvit
project, but their widespread use will require designers to overcome start-
up, operating flexibility, and cost issues associated with these motors.
While mega-trains are demonstrably technically feasible, establishing
their commercial viability is a far more complex issue. Although mega-train
projects do provide economies of scale, they require a larger reserve base
than typical projects and place more capital at risk. Finding sales outlets
for mega-trains also constitutes a greater challenge than for traditional
projects, as volumes are substantially greater. Only a few buyers may be
willing to make large purchase commitments from single trains, as LNG
buyers typically seek multiple smaller LNG contracts to diversify their supply
sources and match the requirements of newly liberalizing and competitive
LNG markets. Thus, the trend with the Qatari mega-trains has been to
have the sponsors emerge as the buyers for the entire train production and
assume the risk of placing the LNG in the market.
Greenfield projects
$300
Expansion projects
$/MMtpa
$200
$100
$0
1998 2000 2002 2004 2006 2008
Start-up Year
Fig. 5–10. LNG plant unit costs (Source: Poten & Partners)
The cost reductions observed until 2003 were due to many factors. An
early move away from steam turbines (used in Algeria, Indonesia, and Brunei)
toward gas turbines (as in Australia’s NWS and Malaysia’s LNG Dua and all
subsequent projects) increased train capacities and brought costs down,
as gas turbines are generally cheaper than steam turbines, which typically
require boilers, boiler feed water makeup facilities, and steam condensers.
The transition from water cooling (Brunei) to air cooling (at NWS) also
allowed further cost reductions. In LNG storage, the use of larger-sized
storage tanks helped bring down costs. Early tank designs were typically
smaller than 40,000 cubic meters. In the 1990s, tank volume rose to 150,000
cubic meters, and today, tanks with capacities of 188,000 cubic meters
have been built. Finally, increased engineering experience, tighter design
margins, a competitive FEED and EPC bidding environment, and increased
application of larger turbine drivers to reap economies of scale allowed less
conservative designs to emerge and costs to fall further.
However, recent cost increases across several key raw materials—
such as carbon and stainless steel, nickel, and concrete—combined with
strong demand for qualified engineering contractors, project personnel,
and skilled labor have combined to reverse this cost trend. EPC costs for
132
projects committed during 2005 rose to between $250 and $350 tpa and cost
escalation did not slow during 2006. Project management has been strained,
with several projects experiencing serious cost overruns and delays in their
projected start- up dates.
The effect that rising costs will have on LNG project feasibility remains
to be seen. While LNG facility costs have risen sharply, the accompanying
increase in oil prices and a seller’s market for LNG make it more likely
that constrained personnel, equipment and construction resources, rather
than pure cost concerns, may dictate any potential slowdown in the rate
of LNG growth.
many of the process units on barges and towing the completed units to
the site. However, much of the motivation in this last case was to minimize
the effect of Arctic conditions on the construction schedule, rather than to
provide a broadly applicable construction approach. Ironically, part of the
delay in the Snøhvit project came as a result of delays in shipyard fabrication
of the liquefaction modules, illustrating the risks associated with innovative
engineering and construction techniques.
One drawback to extensive off-site modularization is that most LNG-
exporting countries do not have the strong manufacturing and fabricating
industry that is needed. On the contrary, these countries would rather see
old-fashioned in-place construction techniques, which tend to generate
more construction jobs.
LNG FPSO
Liquefaction
GBS
Regasification
NOTES
1
Poten & Partners and Merlin Associates. 2004. LNG Cost & Competition. New York:
Poten & Partners and Merlin Associates, pp. 172–74.
2
Peebles, Malcolm W. H. 1992. Natural Gas Fundamentals. London: Shell International
Gas Limited.
3
Poten & Partners and Merlin Associates, LNG Cost & Competition.
4
Ibid.
5
Ibid.
6
Ruster, Jeff. 1996. Mitigating commercial risks in project finance. Public Policy for the
Private Sector. February. Note 69.
7
Poten & Partners and Merlin Associates, LNG Cost & Competition.
8
Cornot-Gandolphe, Sylvie, and Ralf Dickel. 2002. Flexibility in Natural Gas Supply and
Demand: Supply and Demand. OECD.
9
Groothuis, Cas, Dave Fletcher, and Rob Klein Nagelvoort. 2001. Changing the LNG
Game. Paper presented at the 13th International Conference & Exhibition on
Liquefied Natural Gas. Seoul, May 14–17.