Nuclear Power Plant Unit Olkiluoto 3

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 64

Nuclear Power Plant Unit

Olkiluoto 3
Contents

TVO – a pioneer in its own field 3

Olkiluoto 3 4

One unit, many buildings 9

n PRIMARY CIRCUIT 13

Reactor pressure vessel and internal structures 15

Reactor core and fuel 17

Reactor operation and control 23

Primary coolant circuit 25

n SECONDARY CIRCUIT 31

Turbines and generator 33

Condenser 37

n SEA WATER COOLING SYSTEMS 39

n NUCLEAR SAFETY 41

n WATER CHEMISTRY AND VOLUME CONTROL SYSTEMS 47

n INSTRUMENTATION AND CONTROL SYSTEMS 49

n ELECTRICAL POWER SYSTEMS 51

n WASTE PROCESSING SYSTEMS 53

n TRAINING SIMULATOR 57

Technical data 58

The reactor pressure vessel was lifted into the reactor pit in June 2010.

Olkiluoto 3 1
2 Olkiluoto 3
TVO – a pioneer in its own field

Teollisuuden Voima Oyj (TVO) is a non-listed public High in international ranking


company founded in 1969 to produce electricity for its TVO’s nuclear expertise is clearly evident by the high ca-
stakeholders at cost price. TVO is the developer, owner pacity factors of the Olkiluoto plant units. The capacity
and operator of the Olkiluoto nuclear power plant. factors of OL1 and OL2 have varied between 93% and
The production of the nuclear power plant units in 98% since the early 1990s, ranking among the very top by
Olkiluoto (OL1 and OL2) covers about one sixth of the international comparison.
total electricity consumption in Finland. Half of this elec- The high capacity factors indicate reliability of opera-
tricity goes to the industry, the other half is consumed by tion, among other things.
private households, service sector and agriculture. The results achieved are based on meticulous and
Because of the need for increase in both self-sufficien- proactive planning of annual outages and modifications.
cy and additional capacity of electricity production, TVO The radiation exposure doses of the personnel, which
is currently building a third power plant unit, Olkiluoto 3 have been consistently low at the Olkiluoto power
(OL3). With the electrical output of approximately 1,600 plant, have also yielded good results in international
MWe, OL3 will almost double the production capacity of comparison.
the Olkiluoto power plant. In summer 2010 the Finnish
Parliament granted TVO permission to build a fourth TVO’s operating philosophy
unit; Olkiluoto 4 (OL4). As a nuclear power company, TVO is committed to a
high level safety culture, which creates the comprehen-
Solid nuclear expertise sive basis for all activities. According to the principles of
TVO employs a staff of about 800, many of them with the safety culture, issues are prioritised according to their
solid experience in the operation and maintenance of a safety significance and a high degree of operability and
nuclear power plant gained over several decades. This ex- reliability of production are the key objectives of opera-
pertise is also utilised and further developed in the con- tion. Safety and factors affecting safety always take pri-
struction of the OL3 and OL4 units. ority over financial considerations. The future vision of
Throughout its existence, TVO has provided further TVO is to be an acknowledged Finnish nuclear power
training to the employees and improved the competence company and a pioneer in its field. To achieve this goal,
of the staff in nuclear technology. The company’s nuclear TVO acts responsibly, proactively and transparently, fol-
expertise is being sustained by participating in interna- lowing the principles of continuous improvement in close
tional development programmes. Also the upgrading cooperation with various interest groups.
and modernisation projects as well as development and
construction projects carried out at the existing Olkiluoto
units develop the staff ’s expertise. The modernisation
projects implemented over the years have improved the
safety as well as the production capacity and economy of
the Olkiluoto power plant.

Olkiluoto 3 3
Olkiluoto 3

Olkiluoto 3 (OL3) was decided to build for many reasons. components are Civaux 1 and 2 in France, which went
The added capacity brought by OL3 not only meets the on stream in 1997 and 1999, respectively. AREVA NP
increasing demand but also compensates for the decreas- also delivered the principal components to units which
ing output of ageing power plants. Together with the use went on stream in Brazil (Angra 2) and China (Ling Ao 1
of renewable energy, the unit helps Finland to reach its and 2) in 2002.
carbon dioxide emission targets, contributes to the sta- Siemens is one of the leading power plant suppliers in
bility and predictability of electricity prices and reduces the world. The combined output of the power plants de-
Finland’s dependence on imported electricity. livered by Siemens exceeds 600 GWe.
It was on this basis that TVO submitted an applica-
tion to the Government in November 2000 concerning a Technology based on solid practical experience
Decision in Principle for the building of a new nuclear OL3 is an evolutionary unit compared with the current
power plant unit. The Government adopted a Decision power plant units, meaning that its basic design is based
in Principle, and Parliament ratified the Decision in on the proven technology of existing power plants. Its de-
Principle on 24 May 2002. The Decision in Principle velopment was based on plants commissioned in France
states that building the new nuclear power plant unit is in (N4) and Germany (Konvoi).
the interest of society as a whole. Safety features in particular have been developed fur-
After a call for tenders, in December 2003 TVO took ther. The unit was originally designed to allow for the
the decision to invest in the construction of a power plant management of a severe reactor accident (cooling of core
unit with a Pressurized Water Reactor (PWR) with an melt) and a large aircraft crash (double shell of the reac-
output of approximately 1,600 MWe at Olkiluoto. The tor containment building).
type of the unit is known as a European Pressurized
Water Reactor (EPR). The unit is being built on a turn-
key basis by a consortium formed by AREVA NP and
Siemens. AREVA NP is delivering the reactor plant, and Germany (Konvoi)
Siemens is delivering the turbine plant.
Neckarwestheim 2 1,269 MWe 1989
Experienced power plant suppliers Isar 2 1,400 MWe 1988
Emsland 1,290 MWe 1988
Both of the principal suppliers are leaders in their re-
spective fields. AREVA NP has delivered the principal France (N4)
components for a total of 100 light-water reactor units Chooz 1 1,450 MWe 1996
– 94 pressurized water reactors (PWR) and 6 boiling Chooz 2 1,450 MWe 1997
water reactors (BWR). The most recently commissioned Civaux 1 1,450 MWe 1997
PWR units for which AREVA NP supplied the principal Civaux 2 1,450 MWe 1999

4 Olkiluoto 3
Operating principle of a pressurized water reactor (PWR)
A PWR plant has two circuits for heat transfer. Water is kept under high
pressure by the pressurizer (1) and circulated by the reactor coolant
pumps (2) in the primary circuit (3), which transfers the heat from the
reactor (4) to the secondary circuit (5) in the steam generator (7). Reac-
tor power is controlled by control rods (6). The pressure in the secondary
circuit is much lower than in the primary circuit, which makes the water
in the steam generator boil. The steam from the steam generator makes
the turbine (8) rotate. The turbine rotates the coaxially mounted genera-
tor (9), generating electricity for the national grid. The steam from the
turbine is cooled back to water in the condenser (10) with sea water (11).
Condensate water is fed back to the steam generator with feedwater
pumps (12), and the warm sea water is pumped back into the sea.

60 years service life Compared with similar units recently commis-


In addition to safety, the design of OL3 emphasizes econ- sioned in Europe, OL3 will have a reactor output about
omy in particular. The efficiency rate of the new unit, for 1% greater and an electricity output about 10% greater.
instance, is 37% – some four percentage points higher OL3 is being delivered as a turn-key project. TVO has
than the original efficiency of OL1 and OL2. been responsible for site preparation and for the expan-
The design is based on an expected service life of sion of the infrastructure at Olkiluoto. Site preparation
60 years for the largest structures and components and has involved earthmoving, excavation, road building,
30 years for the more easily replaceable structures and electrical power supply for the construction site and the
components. Allowing in advance for such replacements building of the tunnels for the cooling water. The actual
enables the unit to have an economic service life of at construction work that is the responsibility of the AREVA
least 60 years. NP – Siemens consortium began in 2005.

Multi-stage quality control and inspection


are carried out by representatives of TVO, plant
supplier, subcontractors, and authorities.

Olkiluoto 3 5
23 40 13 12 11 41
7 12
11
24 2 15 1325
15 14
24 22 23 7 25
13 13
12 11
13
27 24 23 18 8 25
26 14 11 4
24 13 12 42
41 1 8 13
12
25 3 16 1426
16 15
25 23 24 8 26
14 5 14 12
13 14
28 25 24 19 279 26 15 12
25 14 13 43
1 42 2 9 14
13
26 4 17 1527
17 16
26 24 25 9 27
15 6 15 13
14 15
29 26 25
1 20 2810 27

>>
26 16 13 15 44
1 43 3 10 14
15
2 1 1628
18 17 14
27 10 5 18

>>
27 25 26 26
2 28
16 7 16 14
15 16
30 27 2911 28 17 14
27 1 144 21 16 15
16 45
2 1
3 11 2 4 11
1729 18 15
28 6 19 29 19
1 28 26 27 28 27
3 11 17 1617 1517
3012 29 188 15

>>
28 231 2 1 22 17 46
3 1 45 2 16
17
2
4 2 3 5 13012 1830
20 19 16
2 29 27 29
28 29 28
4 1 12 7 20 18
30 19 9 1718 1618
29 332 346 2 1 23 3113 16 18 47
4 2 3 18
17
3
5 3 4 6 2 13 19 20 17
3 30 28 30
29 30 29
51 2 13 8 21 19
31 21 31
2010 1819 1719
30 433 447 3 2 24 3214 31 17 19 118
19 48
5 3 4
4
6 1 4 5 7 3 14 20 21 18
4 31 29 30 31 30
62 3 14 9 22 2022 32
32 20 18
19 20
534 31 548 4 3 25 15 21
33 32 11 18 220 1 49
6 31 4 20 19
5 6 8
5
5
7
1 2 5 10 4 15
21
23 22
33
19
19
32 30 32 73 4 15 33
23
21 20
213 21
31 31 22
7 32
635 32
5 649 5 4 26 3416 3312 19 21 20
21 2 50
6
8 6 6 7 9 5 16 20
6 2 3 2234
24 23 20
33 33 84 5 16 11 34
24
22 224 22
31 32 32 23 21
8 33
736 33
6 750 6 5 27 3517 3413 20 22 22 3 51
7
9 77 8 10 6 17 21
7 3 4 23
25 24
35 21
34 32 34 95 6 17 12 25 35
23 24 23521
22 23
9 33
837 34 33 8 7 6 28 3618 3514 21 4 52
34 7 51 23 23
8
10 8 8 9 11
7 18 22
8 4 5 2436 25 22
35 33 35
938 35
34 10
6
34
7 18 13 26 36
24 2526 24622
23 24 5
10 35 8 9 8 7 29 371983615 22 24 24 53
9 52 9 9 10 12 19 23
9 51
11 6 25 26
37 23
36 34 10
35
36 7
35
11
8 19 14 27 37
25 2627 25723
24 25 6
11 36
39 36 9 10 9 8 30 382093716 23 25
25 54
10 53 1010 20 24
10 62
12 7 119 13 15 26 27 24
37 35 36
37 8 20 38
28
26 2728 38 26824
25 26 7
11
40 37 36
12 10 9 3921 38 17 124 26 55
12 37 10 1154 31 10 26 25
11 11
73
13 811 11 12 14 21
2739 28 25
38 36 38 9 10 16 29 39
27 2829 27925
26 27 8
37 38
12 37
13 10 21 39 18225 27
13 38 41 11 32 4022 56
114 1255 91212 11 1 27 26
12 12
8
14 13 15 17 2922
2840
30 29 26
39 37 13
39 10 11 22 40
30
28 281026
27 28 9
14 38 39 38
14 23 40 19 3 28 57
39 42 12 11 33 41 12 2 26
125 135610 13 13 14 16
28 27
27
13 13
9
15 3023
29 30
40 38 14 40
39 40 39
15
11 12 23 18 31 2920
41 31 41
427 291127
28 29
29 10
15 40 43 13 12 34 24 41 3 58
136 1457 1414 42 13 29 28
14 14
10
16 11 15 17 19 24
30 31 28
39 15
40 41 13 24 30
42
32 3132 42 301228
29 30
30 11
41 16 40
16
12 5
41
44 41 147 1558 1515 13
14 35 4325
1442 4 21 28 30 29
59
15 15
17 12 16 18 25 29
42 40 16 42 11
17
13 14 25 20 33 43
3143
3233 32 30 1329 12
17 41
45 42 41 16
59 15 14 36 4426
15
31
43 5 22629 31 31 31 60
42 158 16 19 31 30
16
17 43
16
18
12 13 16 17 26
3244
3334 33
30
1430
43 18 41 18
14 15 26 21 34 44
32 7 32 32
31 32 13
42
46 43 42 17 16 15 37 4527
1644 6 23 30 61
17 43 169 60 17 32 31
17
19
13 14 17 18 20 3427
33 34 1531
44 19 42
18 44
19
15 16 27 22 35 45
337
35 845 33
32 31
33
33
14
43
47 44 43 17 4628
174524 31
18 44 1710 1861 1818 16 38
33 32
62
18
20
14 15 19 21 3528 1632
19 45 17 28 23 36 34
36 94635 15
45 20 43 44 20
16
44 19 46
348 34
33 32
34
34
48 45 18 17 39 4729
1846 25 32 63
19 45 1811 62 1919 20 34 33
20 19
15
21 16 22 3629 1733
46 18 29 24 37 35
37104736 16
46 21 44 45 17
45
21 47
359
194726 35
34 35
33
35
20 46
49 46 1912 2063 2020 18
19 40 4830 33 35
64
20
16
22 17 21 23 3730
3648 37 1834
34 17
47 22
21 47 18 19 30 25 38 48
10 3811 36
34
45 46
50 47 46
22 20 19 20 36
4827 34 36
35 36
47 2013 2164 41 4931 65
36
21
21
17
23 182121 22 24 3831
3749 38 1935
35 18
22 48 20 26 39 49 3912 37
35
48 23 46 47 19
47
23 31 37
11
49 37
36 37
48 51 48 21 20 42 50 21
32 28 35 66
22 2114 226519 2222 23 25 39 37 2036
36 19
23 49 22
18
24 27 40 32
38
40 39
50 38
49 24 47 20 21 32 50
38
1229 13 38 36
37 38
4852 49 48
24 2250 67
22 21 43 5133 36
23 49 2215 236620 2323 26 40 38 37
A Reactor building 50 13
25 Primary 48
24
circuit volume control
50
23
C Safeguard building 24
19
25 division 2 28 5134
33
39
4114 40
51
Containment 39 system20
2137
heat removal
37
49 49
25
21 22 33 23 39
13
41 39
38 39
1 Inner and outer containment system heat exchangers
50 53 50 22
16 Main control23
room
22 44 5234 51 30 37
heat exchanger 68
24 23 2467 39 38
24 24 24 27 41
F 34 2238
building 14 Core melt spreading area
26
25
51
20
23 Computer
26 21room 25 29 52 Fuel
40
15 52building
41 40 21
51 49 cooling water
15 Emergency 50 24 Emergency feedwater23
50
26 tank34 244235 42
40
14 40 38
39 40
2 Reactor building main crane
25 54storage
51 2217 2568 24 23 45
Fuel building crane
5335 5231 38 69
51refueling water 40
(polar crane) (In-containment
26 24
D Safeguard25
25
27
building division 3
25 26 28
22 feedwater
3642 Refuelling machine
3516 53 2339
39 22
3 Containment heat removal52 system: 27 storage 50
tank, IRWST) 52 21
25 Emergency 24pump 30 53 15 41
37 43 Fuel42
pools 41
39
51 27
23
51 35 2543
41
53 40
41
sprinklers 26 16 Intake screens52 55 52
for the cooling 18
26 Medium
26 69 head25safety
24 46
injection 5436 38 32
pump 39transfer tube 41
Fuel 70
27 25
26 2626 27 294 4336 2440
41 system 40
4 Equipment hatch (large
53
28 system for reactor emergency
53
28
E Safeguard
22 23building division
25 31 26
39
16
54
17
Fuel
42
44 54pool cooling
43 42 heat 23
40
components) cooling and51 containment 52 heat
56 53 28
24
52
27
19 Switchgear room 36 44 exchanger
42
54 42
41 42
27 53 2770 26 25 47 5537 33 40
5 Refuelling machine removal system 28 26
28 Instrumentation
2727 & control room
30 G44 Reactor plant42auxiliary
2541building 24
29 Hydraulic accumulator of the54 27
29
23 24 28 3718 55 41
43
6 Steam generator 54 17 52 29 Battery rooms 26 37 32 2745 17
55 43
40 45 44 supply and storage system
Coolant
7 Main steam lines 28 reactor emergency
5357 54 29
25
5320 27 26 tank 48 43
5638 5541 34
43 41
42 43
54 cooling system 30 Emergency
27 28 feedwater
45 Coolant
41 supply and storage system
43 2642
29 28
30 28 28 29 3819 25
8 Main feedwater lines 30 Primary circuit pressurizer 55
18 31 Component
25 cooling system 31heat 42 44Offgas delayer
55 53 valves 54
24
30
26
54 27 38 33 2846 18
56 46 56 45 44
42
42
9 Reactor control rod drives
29 19 Main steam 58 55 exchanger
21 29 28 27 49 5739 44
5643 Ventilation
35 42 stack44
43 44
10 Reactor pressure vessel
55
20 Feedwater valves 30 28
32 Low head29safety injection pump H46 39Radioactive44 waste27
processing
43 26
31 Main steam system safety valve
56
29
25
31 26 29 30 32
29 19
57 47
20
4557 46 45
43
11 Primary circuit reactor coolant
56 21 54 55 33
27
55 Containment heat 28 39 34 47
removal system building
4536 43
pump
30 and relief valve
59 56
56exhaust silencer 31
22 heat
29 30exchanger29 28
(sea water50circuit)5840 574447 Liquid
45 45
44
43 waste45collecting
2844tank
31 1 30 3030 40 46 27
12 Primary circuit main coolant lines B32
Safeguard building division 57 26
32 27 31 33 30 45
20
58 21 58
Monitoring
46 47
48
tanks 44
57 55 56 28
56 29 40 35 48
46
58 46 44
31 60 57 3223 30 29 5941 4837 44 45 46
57 51
32 30 31 46 2945 47 28
33 58 31
27
33 283131 32 34 2141 2259
47 48 45
58 56 57 58 29
57 30 36 3159
49 49 45
3324 41 60 59 47 47 47
46
32 58 61
32 31 30 52 42 4938 45 47 3046 29
33 31 32 23 48
34 59 32
28
34 29 32 33 35 2242 60
48 49 46
6 Olkiluoto 3 33
59 57
59
58 59
62
30
58
3425 31 42 61 5039
53 43
60
37 325048
60
50
48
47 48 46
34 33 32 31 46 48 3147 30
35 32 303333 34 36 24 49
47
60 60 33
29
35 38 33 23 43
4961
51 50
34 58 59 60 5926 32 43 61
51
4940 49 47
48 49
63 35
31 61
47 49 57
43 45 10 3 50 54 67
40 44 53 61
31 51 48
48 15 50 49 49 5050 58
1 58
44 46 11 4 51 55 62 68

>>
32 45 49 54
1641 51 52
50 50 59
49 5151 59
45 2 12 5 52 56 69
47 55 63
33 46 50
1742 52 53
51 51 60
50 3 5252 60
46 48 13 6 53 57 64 70
34 47 51 56
1843 53 54
52 52
51 4 5353 61 61
47 49 14 7 54 58
48 57 65
35 1944 54 55 53 52
52 53 5454 62
5 15 8 62
48 50 55 59 66
36 2045 49 53 58
55 56 54
53 6 54 5555 63
49 16 9 60 63
51 56 59 67
37 50 54
2146 56 57 55
55
54 7 17 10 5656 64 64
50 52 57 61 68
38 51 55 60
2247 57 58 56
56
55 1 8 18 5757 65 65
51 53 11 58 62
52 69
39 2348 58 59 57 56 61
56 2 9 1957 12 5858 66 66
52 54 59 63 70
40 2449 53 59 60 58 57 62
57 3 10 2058 13 5959 67 67
53 55 60 64
2550 54 58 63
41
58
60
4 11 59 59
61
6060 68
54 21 14 68
1 56 61 65
2651 55 59 64
42
59 615 12 60 60
62
69
22 15 6161 69
2 55 57 62 66
43 2752 56 60 65
62 63 61
60 6 13 2361 16 6262 70 70
3 56 58 63 67
2853 57 66
44 63 64 62 61
61 7 14 2462 17 6363
4 57 59 64 68
2954 58 67
45 65 62
62
648 15 2563 63
18 6464
5 58 60 65 69
30 59 68
46 55 66 63
63
659 16 2664 64
19 6565
6 59 66 70
3156 60 61 69
47 64
64
66
10 17 2767
65 65
20 6666
7 60
3257 62 67 70
48 61 65
6711 18 2868
66 66
21 6767
8 65
61 3358 63 68
49 62 66
12 19
68 2969
67 67
22
9 66 6868
62 34 64 69
50 59 63 67
13 20
69 3070
68 68
23 6969
10 67
63 35 65 70
51 60 64 68
68
70
14 21 3169 69
24 7070
11 64 36 66
52 61 65 69 1
15 22 3270 70
1
25 1

12 69 2 1
65 37 67
2
2

53 62 66 16 23 70 3 2
33 26 3
3
13 70 4 3
66 38 68
4
4

54 63 67 17 24
5 4
34 27 5
5
14 6 1 5
67 39 69
6
Olkiluoto 3 building complexes
6

55 64 68 18 25 35 28 1
7 2
7
6
7
1
15 AREVA NP 8(nuclear
3 island)
7
68 40 70
2 8
1 2 8

56 65 69 19 26 36 29 Siemens
3
9
PG (turbine
9
4 8
island) 9
2 3
16 10 5 9
69 41 4
TVO (the office
10
3
building)
4 10

57 70
6646 Concentrate 20 27
tanks 37 30
58 Turbine building main crane 5 11
1 11 4
6 10
5 11
17 47 Drum storage area 59 Low-pressure feedwater preheater 1
12
7
11
70 42 6 2 12 5 6 12
60 Feedwater pumps
67I Emergency power generating
21 28
8
58 38 31 1
7
2
13
3 13 6
12
7
18 building 61 Low-pressure feedwater preheater 3
9
13
13
18 14
43 48 Emergency diesel generators M Switchgear building 21 4 14 7 8 14
22 29
10
59 68J Access building 39 32
62 Transformer boxes 32
1
1 29 4
15
5 15 8
14
9
19 2
1 15

44 K Office building N Circulating water pump building 43


3
12 10
1
5
16
6
11
16 9
15
10
2 16
60 69L Turbine building23 30 40 O Essential service water pump
33 54
3 4
23 11
2
6
17
7
12
17 10
16
20 49 Moisture separator/reheater building 4
3
3
7 13
11 17

45 50 High-pressure feedwater P Anti-icing pumps 65 1 5


34 12
18
8
4
18
11
17
12 18
65
70 preheaters 24 31
5 14
61 41 34
Q Auxiliary boiler building 76
5 6
42 13
4
8
19
9
5
19
18
13 19
21 6
12
15
46 51 High-pressure turbine 63 Demineralized water storage tanks 87
6 7
53 14
5
9
20
10
6
20
19
14 20
13 66
25 32
52 Low-pressure turbine 42 64 Auxiliary stand-by transformer
35 7
7 8 6
10 16 20
62 98 64 15 21
11 21 14
22 65 Unit transformers
7 15
47 53 Condensers
21
8 7 17 64
9 8 9
75 11
22 21
10 16
54 Cross over lines 33 66 Auxiliary normal transformers 12
8 22 15 16 22
26 43 36 9
9 10 8 18

2363
10 86 12
23 22
55 Generator 67 Switchyard 11
17 13
9 23 16 17 23
48 56 Exciter 68 High-voltage lines 11
10
10
97 11
18
9
13
24
14
19
24 17
23
12 10 18
57 Feedwater tank27 34
24
44 37
Computer graphics: Images & Process 11 10 20

2464
8 12
10
11 14
25 24
12 19 15 25 18
13 11 19 25
49 13
12
9 13
12
11 20
11
15
26 21 25
16 26 19
28 35 45 38
14
13
12
22
20 26

2565
1014
13 12
16
27 26
14
15 12 21 17 27 20
13 27
50 14 13
17
28 23
21
27
15 1115
14
13 28
29 36 46 39
16
15
22 18
14 21
24
22 28

2666 1516 14
18
29 28

7
16
17 12
14 23 19 29
51 16
15
15
19
30
22
25
23
29
29
Olkiluoto 3
17 1617
13
30 37 47 40 18
17
15 24 20
16
30
23
26
24 30

2767 1718 16
20 30
18 14
16 25 31
19 21 31 24
52 18
17
17 27
25 31
The reactor building is surrounded Safeguard
by the fuel building and four inde- building
pendent safeguard building divisions.
division 1

Safeguard
building
Fuel building division 2

Safeguard
building
Reaktorirakennus
division 3
Polttoaine-
rakennus

Safeguard
building
division 4

Reaktorilaitoksen poikkileikkaus

CONTAINMENT BUILDING
(REACTOR BUILDING)

FUEL BUILDING SAFEGUARD BUILDING


DIVISIONS 2 AND 3

STORAGE AREA
FOR RPV –
CLOSURE H.
SPENT FUEL
MAST BRIDGE

INCORE
INSTRUMENT

STORAGE
POOL
SPRAY
FUELSTORAGE POOL

TRANSFERTATIONS

VALVES

SPRAY
LINES

SG –BLOW DOWN
SYSTEM
PIPE CVCS
DU CT

CVCS
PIPE
VALVE VALVE DU CT
EBS–TANK ROOM ROOM

PIPE IRWST
SPREADING AREA
CVCS PUMP DU CT

EBS PUMP
SUMP

8 Olkiluoto 3
One unit, many buildings

The new OL3 power plant unit is being built to the west of temperature and pressure loads that may be caused by
the existing ones. The buildings in the new complex can pipe breaks. The massive outer containment is a cylinder
be roughly divided into three parts: the nuclear island, in reinforced concrete that shares the same base slab as
the turbine island, and auxiliary and support buildings. the inner containment and protects it against external
hazards. This massive double-shell structure is a new
Nuclear island safety feature which the earlier power plants do not have.
The principal components of the nuclear island are the Preventing release of radioactive material in case of an
reactor containment, the fuel building and safeguard accident sets extreme requirements on the leak-tightness
building divisions surrounding it. The reactor primary of the containment building, which has an inner liner
circuit is housed in a gas-tight and pressure-resistant of steel for this reason. The tightness of the building is
double-shelled containment building, also known as the closely monitored. Any leaks which occur are arrested
reactor building. between the inner and outer shells of the containment
The fuel building, which houses pools for fresh and building, then filtered and delayed in the annulus ven-
spent fuel, is on the south side of the reactor building and tilation system before being conveyed to the ventilation
is about 50 m long, about 20 m wide and more than 40 m stack.
high. In addition to fuel storage, it is connected to work- Personnel access to the containment building is man-
shop areas. Flanking the fuel building are the reactor aged through a special airlock during normal operation.
plant auxiliary building and waste management building; The airlock has double-sealed doors at both ends; it is
the latter is used for handling plant waste. impossible to open both ends of the airlock at the same
The reactor building, fuel building and safeguard time. Personnel access is at ground level. There is also
building divisions are designed to be able to withstand an emergency airlock on the service floor at about 19 m
various types of external hazards such as earthquakes and level through which personnel access to and from the
pressure waves caused by explosions. All these buildings containment building can be managed.
are built on the same base slab. The big equipment hatch on the maintenance plat-
The reactor building, the fuel building and two of the form is used during construction and annual outages for
safeguard building divisions are designed to withstand a bringing large components and devices into the contain-
crash by a large aircraft. ment building. The main crane of the reactor building,
located above the containment building service floor has
Reactor containment building a lifting capacity of 320 tonnes.
The OL3 reactor unit has a double-shelled containment The reactor building has an external diameter of about
building in reinforced concrete. 57 m, a volume of about 80,000 m3 and a total height in-
The shape of the building was chosen for strength cluding underground levels of about 70 m. The ventila-
and on the basis of construction technology. The inner tion stack is about 100 m high.
containment is a prestressed cylinder in reinforced con-
crete with an elliptical cover. It is designed to withstand

Olkiluoto 3 9
The inner containment building is clad with steel
to ensure the gas-tightness of the building.
The containment’s design pressure is 5.3 bar.

Lifting of the steel liner dome part in November 2009.

10 Olkiluoto 3
Safeguard buildings above four. The emergency and station blackout diesel
The OL3 plant unit has parallel redundant safety systems generators ensure that the safety systems have power sup-
which are physically separated from each other to ensure ply even under abnormal circumstances.
safe operation under all circumstances. The safety sys-
tems are divided into four independent subsystems, each Turbine island
of which is housed in a separate safeguard building di- The turbine building is almost 100 m long, 60 m wide
vision. All four buildings have their own low head and and 60 m high, including underground levels. Its volume
medium head safety injection systems, a residual heat re- is about 250,000 m3. Adjacent to it are the circulating
moval system, an intermediate cooling system, a sea wa- water pump building and switchgear building. The main
ter cooling system, and an emergency feedwater system. transformers and plant transformers are located to the
The electrical and instrumentation and control systems north of the turbine building.
are located on the upper levels of the safeguard building
divisions. The control room is located in one of the safe- Auxiliary and support buildings
guard building divisions. Beside safeguard building divisions 2 and 3, there is an
Buildings 2 and 3 are between the reactor building and access building, which contains locker rooms and wash-
the turbine island, and buildings 1 and 4 are on opposite rooms, and a monitored accessway to the radiation-con-
flanks of the reactor building. Each of the buildings is trolled area. There is a bridge from the access building
about 30 m long, 20 m wide and 30 m high. to the office building, where radiation-controlled office
The power plant unit has four emergency diesel gen- space is available during annual outages. The power plant
erators suppling power to the safety systems in case of area also contains separate buildings for housing diesel
loss of offsite power. There are also two additional diesel generators, the sea water system buildings (mainly un-
generators, station blackout diesels, independent of the derground), and a number of minor support buildings.

September 2010

Olkiluoto 3 11
Primary circuit main components

1 Reactor pressure vessel


2 Main coolant line, hot leg
3 Steam generator
4 Main coolant line, cross-over leg
5 Reactor coolant pump 3
6 Main coolant line, cold leg
7 Pressurizer
8 Pressurizer surgeline

8
4 5
2

12 Olkiluoto 3
PRIMARY CIRCUIT

Primary circuit
The OL3 primary circuit system consists of four individual loops. It is
designed for a service life of 60 years and constructed to withstand the
loads caused by every conceivable situation of operation or accident.

Primary circuit main functions The safety systems are designed so that in abnormal
In each of the four loops comprising the primary circuit, events they are able to perform a rapid shut-down of
the coolant leaving the reactor pressure vessel at a tem- the reactor, known as a reactor scram. This ensures that
perature of 328°C goes through the main coolant line hot the reactor releases as little energy as possible while also
legs to the steam generators, where heat is transferred to helping reduce pressure with maximum efficiency and
the secondary circuit. The coolant, its temperature now keeping the actuation of the safety valves to a minimum.
approximately 296°C, is returned by the reactor coolant
pump to the reactor through the inlet nozzles. Inside the
reactor pressure vessel, the coolant first flows down out-
side the reactor core. From the bottom of the pressure
vessel, the flow is reversed up through the core, where
the coolant temperature increases as it passes through the
fuel rods and the assemblies formed by them.
The pressurizer connected to the primary circuit keeps
the pressure in the reactor high enough to prevent the
coolant from boiling. Under normal conditions, the cir-
cuit is full of water which effectively transfer heat from
the reactor core. Connected to one of the four individual Aligning of a cross-over leg.
loops, the pressurizer is larger in volume compared with
the existing power plants so that it can better respond
to any pressure transients during operation. This helps
smooth pressure spikes and extends the useful life of the
main components of the primary circuit.

Reactor cooling system properties

Reactor thermal power 4,300 MWth


Primary circuit flow 23,135 kg/s
Primary coolant flow per loop 28,330 m3/h
Coolant temperature in the cold leg 296°C
Coolant temperature in the hot leg 328°C
Primary circuit design pressure 176 bar
Primary circuit operating pressure 155 bar
Secondary circuit design pressure 100 bar
Main steam pressure under normal conditions 78 bar
Main steam pressure during hot shut-down 90 bar

Olkiluoto 3 13
Properties of the reactor pressure vessel and itsPWR
inner structures Cross-section of reactor
pressure vessel and internal structures
Control Rod Drive
Reactor pressure vessel Mechanis
Design pressure 176 barm
(CRDM)
Design temperature 351°C
Control rod drive mechanism Reactor level measurement probe
Life time (capacity factor 90%) 60 years
Inside diameter (under cladding) 4,885 mm
Wall thickness (under cladding) 250 mm
Bottom wall thickness 145 mm
Height with closure head 12,708 mm Reactor pressure
vessel head
Base material 16 MND 5
Cladding material stainless steel
(less than 0.06% cobalt)
Mass with closure head 526 t Control
End of life fluence level (E > 1 MeV) rod guide
assembly
- design value 2.65 x 1019 n/cm2
- expected value ca. 1 x 1019 n/cm2
Core
Base material final RTNDT barrel
(final ductile-brittle transition temperature) ca. 30°C Coolant Coolant
Closure head inlet outlet
nozzle nozzle
Wall thickness 230 mm
Number of penetrations:
- control rod mechanisms 89 pcs
- dome temperature measurement 1 pcs Pressure
- instrumentation 16 pcs vessel
shell
- coolant level measurement 4 pcs
Base material 16 MND 5*
Cladding material stainless steel
(less than 0.06% cobalt)
Control
Upper inner structures assembly
Upper support plate thickness 350 mm
Upper core plate thickness 60 mm
Main material Z3 CN 18-10 / Z2 CN 19-10**
Lower inner structures
Lower support plate thickness 415 mm
Core support grid Fuel assembly
Lower inner structure material Z3 CN 18-10 / Z2 CN 19-10**
Neutron reflector
Material Z2 CN 19-10**
Weight 90 t
* low-alloy ferrite steel Flow distribution plate
** austenitic stainless steel

14 Olkiluoto 3
Reactor pressure vessel and
internal structures

Primary circuit
Pressure vessel structures include the control rod guide
The reactor pressure vessel contains the thimbles, whose fastenings and beams are
reactor core. Both the pressure vessel and fixed to the control rod support plate and
the vessel head are made of forged ferrite the upper core support plate.
steel. They are also clad with stainless steel
on the inside to prevent corrosion. Core barrel
The pressure vessel is supported by The flange of the core barrel rests on the
beams which rest on the support ring in machined flange of the pressure vessel,
the top part of the reactor cavity, under and is kept in place by a large spring. The
the eight primary circuit pipes. The vessel fuel assemblies rest on a perforated core
head is fastened with bolts and a sealing Source: AREVA support plate, made of forged stainless
gasket. Reactor pressure vessel upper inner steel and welded to the core barrel. Each
To manufacture the reactor with as few structures (Chooz 1, France). fuel assembly is positioned by two pins
welding seams as possible, the flange and 180° apart.
nozzle area of the pressure vessel is forged
from a single piece of metal. There are no welding seams Neutron reflector (heavy reflector)
between the flange and the nozzles. Combined with the There is a steel neutron reflector, heavy reflector, around
structure of the nozzles, this ensures that there is a con- the polygonal core, between the core and the cylindrical
siderable distance and a large volume of water between core barrel. The reflector reduces the number of neutrons
the nozzles and the top of the core. This minimizes the escaping from the core and flattens the power distribu-
exposure of the structures to neutron radiation. tion. It also reduces the exposure of the pressure vessel to
the neutron radiation that reduces ductility in its mate-
Internal structures rial, and also dampens any pressure spikes which the in-
The internal structures of the reactor pressure vessel sup- ternal structures and fuel in the reactor might be exposed
port the fuel assemblies in the core, enabling the reactiv- to in case of pipe break.
ity of the core to be controlled by the control rods and The heavy reflector consists of pieces of stainless steel
the fuel to be cooled with water under all circumstances. piled up and linked together. The tie rods bolted to the
The inner structures are partly removed during refuelling core support plate keep the pieces in place axially. The
and can be completely removed for an inspection of the heat generated in the steel by gamma radiation is ab-
inner wall of the pressure vessel. sorbed by the primary coolant flowing through cooling
The pressure vessel also contains upper internal struc- ducts in the reflector.
tures, whose function is to support the top of the fuel as-
semblies and to keep them correctly aligned axially. These

Olkiluoto 3 15
Initial core loading In-core instrumentation

TC

Low enriched assembly without gadolinium


(neutron flux measurement

Medium enriched assembly with gadolinium


Core instrumentation
calibration system)
Aeroball system

High enriched assembly with gadolinium

Reactor core properties

Reactor thermal power 4,300 MWth


Operating pressure 155 bar 12 lance yokes, each comprising:
Primary coolant temperature in the inlet 296°C 3 core outlet temperature sensors
6 in-core neutron flux detectors
Primary coolant temperature in the outlet 329°C 3-4 aeroball probes
Equivalent diameter 3,767 mm 89 control assemblies
Active core height 4,200 mm 4 water level probes
Number of fuel assemblies 241 pcs core external neutron flux measurements
TC temperature measurement
Number of fuel rods 63,865 pcs
Average linear heat rate 156.1 W/cm

16 Olkiluoto 3
Reactor core and fuel

Primary circuit
The OL3 reactor core consists of 241 fuel Carrier gas
output are controlled using the control
assemblies identical in structure. For the assemblies.
initial core loading, the assemblies are di- Ball guide The main core properties and opera-
vided into three groups according to their tube tional conditions have been selected to
enrichment level. The two groups with the Shroud achieve a high thermal power and low
highest levels of 235U also contain gadolin- Steel balls
fuel costs. The OL3 reactor core is also
ium, which acts as a neutron absorber and designed to be adaptable to various refuel-
Active core height

thus reduces the reactivity of the initial ling intervals and operating situations.
phase of the reactor’s operation and flat-
tens the power distribution. Core instrumentation
The number and properties of the fuel The core power is measured with both in-
assemblies replaced annually depend on ternal and external instrumentation. The
the fuel management plan chosen, par- fixed in-core instrumentation comprises
ticularly the load pattern and the length of neutron flux and temperature measure-
Ball stop
the refuelling interval. ments monitoring the distribution of the
The refuelling interval of the reactor neutron flux in the core and the tempera-
Aeroball system
core can be 12 to 24 months. ture distribution in the upper part of the
Balls made of a vanadium alloy
The primary coolant, due to its com- core. Ex-core instrumentation is used for
are fed into 40 narrow tubes from
position, is a significant neutron mod- above the reactor and pneumatically
power measurement and also for monitor-
erator and reflector. The coolant conveys propelled to the reactor core through
ing core sub-criticality during outages. All
heat from the core at a pressure of ap- guide tubes in the fuel assemblies. the penetrations required for core instru-
proximately 155 bar and a temperature The activation of the balls in one mentation are in the pressure vessel head.
of 312°C on average. The primary coolant tube is measured at 36 points. The The core power distribution is also
contains boron, which absorbs some of the results are used to calibrate the measured at regular intervals using the
neutrons. Adjusting the boron level helps devices used to measure the neutron aeroball system. The results thus achieved
control changes in reactivity that are fairly flux in the reactor core. are used for calibrating fixed in-core neu-
slow, such as the impact of fuel burn-up. tron flux measurement devices.
Rapid changes in reactivity and in power

Olkiluoto 3 17
17 x 17 fuel assembly

Top nozzle

Spacer grid

Fuel rod

Fuel properties

Fuel uranium dioxide UO2


Fuel assembly type 17 x 17 HTP
Number of fuel rods per assembly 265 pcs
Number of guide thimbles per assembly 24 pcs Bottom nozzle
Number of spacer grids per assembly 10 pcs
Length of fuel assembly 4.8 m
Weight of fuel assembly 735 kg
Width of fuel assembly 213.5 mm
Cladding material M5TM
UO2 pellet density 10.45 g/cm3
Fuel discharge burnup 45 MWd/kgU

18 Olkiluoto 3
Primary circuit
Fuel assembly Fuel rods
A fuel assembly consists of fuel rods, spac- A fuel rod is a tube containing compressed
er grids and top and bottom nozzles. The ceramic pellets of uranium dioxide (UO2).
guide thimbles, spacer grids and the end The rods are welded hermetically leak-
pieces form the supporting structure of tight and pressurized using helium. The
the assembly. power of the reactor comes from the fis-
The fuel rods form a 17 x 17 matrix. sion of the uranium in the pellets, mainly
Each fuel assembly contains 265 fuel rods, the isotope 235U. The enrichment level of
24 guide thimbles and 10 spacer grids, the pellets varies, being just under 5% at
tied together by end pieces at either end. its highest. In some of the fuel rods, the
The bottom nozzle is shaped to dis- Source: AREVA fuel pellets are made of an alloy of UO2
tribute coolant flow evently. There is also The fuel supplier for the and Gd2O3, the latter helping to reduce re-
a debris filter at the lower end to prevent OL3 reactor is AREVA NP. activity and to flatten the power distribu-
any foreign objects that may end up in the tion in fresh fuel rods.
primary circuit from entering the fuel assembly; such ob- The cladding tubes of the fuel rods are made of a zir-
jects could mechanically damage it. The top nozzle has conium alloy. The cladding is the first barrier to the re-
a leaf spring set on each side to achieve the force with lease of radioactive emissions as it separates the fuel and
which the fuel assemblies are kept stationary against the their fissile products from the primary coolant. There is
primary coolant flow. space for fission gases within the fuel rod, which reduces
The eight middle spacer grids in the fuel assembly are the pressure increase caused by gases released from the
made of zirconium alloy. They have flow guides to en- uranium pellets in the nuclear reaction. The pellets are
hance heat transfer from the fuel rods. The uppermost held in place by a spring inside the top of the fuel rod.
and lowermost spacer grids are made of nickel-based al-
loy because of their higher strength requirements.

Olkiluoto 3 19
Primary circuit

Fuel handling Spent fuel assembly handling


Fresh fuel assemblies are stored either in the fresh fuel After being removed from the reactor, spent fuel assem-
dry storage or in storage racks in the fuel pools where blies are kept in the spent fuel pools in the fuel building
spent assemblies are also stored. During a refuelling out- for a few years to cool them off. At the same time, the
age, some of the spent fuel assemblies in the reactor are radioactivity of the spent fuel decreases substantially.
replaced with fresh ones. For example, if the reactor is After sufficient cooling, the spent fuel is transported to
being operated at 12-month cycles, one quarter of fuel is an interim storage facility at the power plant site using a
replaced annually. Different kinds of fuel assemblies are spent fuel cask which is docked below the spent fuel pool
placed in the reactor in compliance with the restrictions using a transfer facility.
on the reactor core and fuel use. Before placement in the final repository, the spent fuel
Fuel assemblies are moved between the reactor and is kept in interim storage for several decades. During this
the fuel building through the fuel transfer tube. There is a time, the radioactivity and heat output of the fuel de-
fuel handling machine in the reactor building and in the crease to less than 1/1000 of their original values, making
fuel building. the further handling of the fuel much simpler.
Core unloading takes about 40 hours in all, and core The final repository for spent fuel is being built at
reloading plus a final core inspection using the camera Olkiluoto by Posiva Oy, a company which is jointly
in the refuelling machine takes about 45 hours. The final owned by TVO and Fortum Power and Heat Oy, who will
inspection is intended to ensure the correct placement of also be responsible for its operation. The spent fuel from
fuel assemblies in the core, following the refuelling plan. the nuclear power plant units in Loviisa will also be de-
The Finnish Radiation and Nuclear Safety Authority posited at Olkiluoto. Final placement will begin in 2020.
(STUK), Euratom and the IAEA all participate in each
final inspection to ensure the appropriate handling and
safeguard measures of reactor fuel.
Spent fuel assemblies that have been in the reactor are
kept under water at all times for cooling and radiation
protection. Although 1 m of water would be sufficient
radiation protection, at Olkiluoto the fuel assemblies are
always kept under at least 3 m of water.

20 Olkiluoto 3
Primary circuit
Transferring fuel out of and into the core fuel building. The container is again turned to a vertical position, and the
The refuelling machine lifts a fuel assembly out of the reactor core and spent fuel mast bridge lifts the fuel assembly out and transfers it to the
transfers it to the transfer container, which is in a vertical position. The spent fuel storage rack in the spent fuel pool.
transfer mechanism turns the transfer container to a horizontal position Installing new fuel assemblies in the core is performed using the same
and moves it from the reactor building through the transfer tube to the process in reverse.

Fuel transfer systems in the reactor building and fuel building

Spent fuel mast bridge


in the fuel building
Refuelling machine
in the reactor building

Fuel transfer tube

Fuel assembly
transfer mechanism

Olkiluoto 3 21
Cross-section of control rod drive mechanism

Plug connector

Upper limit position


indicator coil Drive
Control rod system properties rod
upper
final
Rod cluster control assemblies position
Number 89 pcs
Weight 61.7 kg
Control rods per assembly 24 Position indicator coil Sheet steel
Absorber casing
B4C part (upper part)
Lower limit position
- natural boron 19.9% 10B atoms indicator coil
Drive rod lower
- specific weight 1.79 g/cm3 final position
- external diameter 8.47 mm
- length 1,340 mm Lifting pole
AIC part (lower part) Lifting coil
- weight composition:
silver, indium, cadmium (%) 80,15, 5 Lift armature
- specific weight 10.17 g/cm3
- external diameter 8.65 mm Gripping
coil
- length 2,900 mm Gripping armature
Cladding Gripping latch
Material stainless steel
Gripping latch carrier
Surface treatment (external surface) ion nitrification
External diameter 9.68 mm Holding pole Holding
coil
Internal diameter 8.74 mm Holding latch carrier
Filling gas helium Holding armature
Control rod drive mechanisms Holding latch
Number of drive mechanisms 89 pcs Flange connection
Weight 403 kg
Sealing area
Lifting power >3,000 N
Travel range 4,100 mm
Stepping speed 375 mm/min or Control rod drive
750 mm/min mechanism nozzle
Maximum scram time allowed 3.5 sec
Materials austenitic and martensitic stainless steel

22 Olkiluoto 3
Reactor operation and control

Primary circuit
The control assemblies are one system to 36 elements control the temperature of the
control the reactor power. In addition to primary circuit and flatten vertical power
short-term power control, they also flatten distribution in the reactor core.
vertical power distribution in the reactor The control assemblies in the control
core. In the long term, decreasing the bo- bank are further divided into quadruplets,
ron content helps compensate for the loss which are used in various drive sequences
of reactivity due to fuel burnup. and insertion sequences depending on the
refuelling interval in progress. The current
Control rod system insertion sequence and control assembly
The control rod system is a part of the re- banks can be changed at any time regard-
actor power control system. It consists of less of the current reactor power.
Source: AREVA

the control assemblies formed with con- The individual control rods of the The control bank in operation is regu-
trol rods, the control rod drive mecha- reactor control assemblies move in larly changed at intervals of about 30 days
nisms and the control rod drive mecha- the guide thimbles in the fuel assem- of power operation. This avoids fuel dis-
nism operating system. The system is used blies. These guide thimbles are also charge burnup from affecting the effec-
for controlling the reactor power and for a used for placing instrumentation and tiveness of the control and equalizes the
reactor scram. The control rods enter the neutron sources. burnup.
core through guide thimbles in the fuel
assemblies. Control rod drive mechanisms
The control rod system is governed by the reactor A control rod drive mechanism consists of the pressure
control, surveillance and limitation system and manually housing with flange connection, the latch unit, the drive
by the control room operators. The reactor scram is trig- rod, the coils and their housings. The role of the control
gered automatically by the protection system or its back- rod drive mechanisms in controlling the reactor is to
up system, a hardwired back-up system. An operator may move the 89 control assemblies throughout the length of
also trigger the reactor scram manually. the core and to keep them at any location required. Their
secondary role is to drop the control assemblies into the
Control assemblies reactor, thus stopping the chain reaction and shutting
There are 89 identical control assemblies. Each consists the reactor down in a number of seconds, particularly in
of 24 identical absorber rods attached to a single mount. a scram situation. When the reactor scram signal is acti-
The rods contain materials that absorb neutrons (silver, vated, all operating coils are de-energized, the latches are
indium, cadmium and boron carbide). When the rods retracted from the rod grooves, and the control assem-
are completely inserted into the core, they almost totally blies drop into the core by force of gravity.
cover the active length of the fuel assemblies. The control rod drive mechanisms are installed into
The control assemblies are divided into separate con- adapters welded to the reactor pressure vessel head. Each
trol groups. The majority of them, 53 elements, are in the drive mechanism is a separate entity that can be installed
shut-down bank, which executes a rapid shut-down of and removed independently of the others.
the reactor, or reactor scram, if necessary. The remaining

Olkiluoto 3 23
Cross-section of steam generator

Steam outlet nozzle

Steam dryer
Secondary
manway

Steam separator
Steam generator properties

Number of steam generators 4 pcs Emergency


Emergency feedwater ring
Heat transfer surface per
feedwater nozzle
steam generator 7,960 m2
Feedwater ring
Primary circuit design pressure 176 bar
Primary circuit design temperature 351°C Feedwater nozzle
Secondary circuit design pressure 100 bar
Secondary circuit design temperature 311°C
Upper lateral Bundle double wrapper
Heat transfer tube external diameter / support brackets
wall thickness 19.05 mm / 1.09 mm
Number of tubes 5,980 pcs
Triangular pitch 27.43 mm
Total height 23 m
Materials
Bundle wrapper Tube support plates
Tubes Inconel 690 alloy,
heat treated
Shell 18 MND 5*
Cladding tube sheet Ni-Cr-Fe alloy
Tube support plates 13% Cr-treated Tube sheet Partition plate
stainless steel
Tube bundle
Other
Total weight 520 t
Feedwater temperature 230°C
Main steam moisture content 0.25%
Main steam flow 2,443 kg/s
Partition plate
Main steam temperature 293°C (primary circuit)
Main steam saturated pressure 78 bar
Pressure during hot shut-down 90 bar Coolant inlet nozzle Coolant outlet nozzle
*low-alloy ferrite steel

24 Olkiluoto 3
Primary coolant circuit

Primary circuit
Steam generators Inconel 690, which has a cobalt content of less than 0.015%.
A steam generator is a heat exchanger which transfers heat The shell of the steam generator is made of 18 MND 5 steel.
from the primary coolant circuit to the water in the second- The design concept, with the cold feedwater being mixed
ary circuit. As in a typical heat exchanger, the contents of with only 10% of the warmer recirculated water, ensures a
the primary and secondary circuits never come into direct larger temperature differential and hence a more efficient
contact with one another. The steam generator in an EPR heat transfer. As a result, the main steam pressure of the OL3
power plant unit is of the vertical type. steam generator is 3 bar higher per unit of heat exchange ar-
The primary coolant passes through U-shaped tubes in ea than that of power plant units which the design is based
the steam generator. The feedwater of the secondary circuit, on. The efficiency of the steam generator is achieved through
which is to be turned into steam, circulates inside the shell the asymmetrical conveying of feedwater into a discrete
of the steam generator. The steam separators and steam dry- channel separated from the walls of the steam generator.
er at the top of the secondary circuit portion separate the In the design of the OL3 steam generators, particular at-
steam from the water. The separated water returns down tention was paid to the prevention of cross-flows in the sec-
along the outer shell of the steam generator. The feedwater ondary circuit and of the adverse effects caused by thermal
pipes continously refill the secondary side of the steam gen- layering due to the efficient heat exchange. The steam space
erator with water equivalent to the mass of steam fed into has been enlarged, increasing the steam volume.
the turbine. On the other hand, the steam generator also has a higher
The axial feedwater preheater enables not only a larger water volume than in the power plant units upon which the
heat exchange area but also a saturation pressure of 78 bar, design is based. This improves the safety margin and in-
which is a significant factor in the high efficiency (37%) of creases the grace period in a situation where all feedwater
the power plant unit. The tubes in the steam generator are systems malfunction and no cooling water is available for
made of wear-resistant and corrosion-resistant alloy called feeding into the steam generator.

Olkiluoto 3 25
Cross-section of reactor coolant pump
1. Flywheel
2. Radial bearings
3. Thrust bearing
4. Air cooler
5. Oil cooler
6. Motor (stator)
7. Motor (rotor)
8. Motor shaft
9. Spool piece
10. Pump shaft
11. Shaft seal housings
Pump casing
12. Main flange
13. Seal water injection
14. Thermal barrier
Reactor coolant pump and pipe properties 15. Diffuser
16. Impeller
Pump 17. Pump casing
Number of pumps 4 pcs 18. Outlet nozzle
Design pressure 176 bar 19. Inlet nozzle
Design temperature 351°C
Primary coolant flow 28,330 m3/h
Design head 100.2 m ± 5%
Seal water injection 1.8 m3/h
Seal water return 0.680 m3/h
Speed 1,465 rpm
Total height 9.3 m
Total weight without water and oil 112 t
Motor
Rated power 9,000 kW
Frequency 50 Hz
Main circulation pipes
Internal diameter 780 mm
Wall thickness 76 mm
Material Z2 CN 19-10*
Pressurizer connection pipe
Internal diameter 325.5 mm
Thickness 40.5 mm
Material Z2 CN 19-10*
*low carbon stainless austenitic steel

26 Olkiluoto 3
Primary circuit
Reactor coolant pump The shaft seal system consists of three
The reactor coolant pumps provide forced dynamic seals assembled into a cartridge
circulation of water through the reactor and a standstill seal. The first seal is a
coolant system. This circulation removes hydrostatically controlled leakage seal,
heat from the reactor core to the steam which takes the full primary pressure. The
generators, where it is transferred to the second seal is a hydrodynamic seal which
secondary circuit. In each of the four loops receives the remaining pressure but can
of the primary circuit, the reactor coolant also withstand the entire primary pres-
pump is located between the steam gen- sure if necessary. The third seal is also
erator outlet and the reactor inlet. hydrodynamic and is a backup leak seal.
The reactor coolant pumps have hydro- Source: AREVA The standstill seal ensures that no prima-
static bearings, which ensure a low vibra- Reactor coolant pump ry coolant is lost in the event of a loss of
tion level. The OL3 reactor coolant pumps at the Jeumont plant in France power or the simultaneous malfunction of
have three separate shaft seals and an ad- (N4, 1,500 MWe). all shaft seals when the pump is stopped.
ditional standstill seal which is operated When the pump is in operation, the
by gas pressure. shaft seals are cooled and lubricated with
A reactor coolant pump consists of three main parts: seal injection water which is injected below the seals at a
the pump itself, the shaft seals and the motor. pressure slightly higher than that of the primary coolant.
The pump hydraulic cell consists of the impeller, the The third shaft seal, which is a backup to the first two,
diffuser and the suction adapter. The pump shaft is in two receives its cooling water from the demineralized water
parts connected by a spool piece which can be removed distribution system.
for seal maintenance. The shaft is supported on three The motor is a drip-proof squirrel-cage asyncronous
bearings: two oil-lubricated bearings in the motor and motor. A spool piece placed between the pump and the
one hydrostatic bearing at the impeller. There is a double- motor shafts and the shaft seal housing structure enable
action thrust bearing at the top of the motor shaft, under maintenance to be carried out on the seal pack without
the flywheel, to compensate axial forces. removing the motor.

Olkiluoto 3 27
Cross-section of pressurizer

Access hatch
Venting nozzle Safety valve nozzle

Level and
temperature Convex end
measurement
nozzle

Spray inlet
Source: AREVA

Spray nozzle

Cylinder
shells

Pressurizer properties

Design pressure 176 bar Support plate


Design temperature 362°C Support
Total volume 75 m3
Total length 14.4 m
Base material 18 MND 5*
Cylindrical shell thickness 140 mm
Number of heaters 108 Convex end
Total weight, empty 150 t Level and
Total weight, filled with water 225 t temperature
measurement
Number of safety valves and capacity nozzle Flow distributor
under design pressure 3 x 300 t/h
Relief valve capacity under design
pressure (doubled for valves) 1 x 900 t/h Heaters Surge line
* low-alloy ferrite steel

28 Olkiluoto 3
Primary circuit
Pressurizer All components of the pressurizer shell, except for the
The pressurizer contains primary coolant in its lower part heater penetrations, are made of forged ferrite steel with two
and steam in its upper part. The pressurizer is part of the layers of cladding. The material is the same as in the reactor
primary circuit and is connected through a surge line to the pressure vessel. The heater penetrations are made of stain-
hot leg of one primary loop. The purpose of the pressurizer less steel and are welded using a corrosion-resistant alloy.
is to keep the pressure in the primary circuit within speci- The pressurizer supports are welded to its frame.
fied limits. Compared with plants which the design of OL3 is based
The pressure in the primary circuit is controlled by regu- on, the volume of the pressurizer has been increased in or-
lating the steam pressure. For this purpose, the pressurizer der to smooth the response to operational transients.
has heaters in its lower part to produce steam and a spray
system in its upper part to condense steam into water. Main coolant lines
The pressure-relief and safety valves at the top of the The main coolant lines of the four loops that form the pri-
pressurizer protect the primary circuit against excessive mary circuit and the pressurizer surge line are part of the
pressure. There are two parallel pressure-relief lines with reactor coolant system in the reactor building. The main
valves which the operators can use, in the case of a severe coolant lines convey the primary coolant from the reactor
accident, to relieve pressure quickly in the primary circuit: pressure vessel to the steam generators and onward to the
the primary coolant released from the primary circuit is dis- reactor coolant pumps, which return the coolant to the
charged to the pressurizer relief tank, where a rupture disk pressure vessel. One of the four loops is connected to the
breaks and releases the coolant into the containment build- pressurizer.
ing. There the steam condenses into water, which is collect- Each of the four loops has three parts: the hot leg from
ed in the emergency cooling water storage tank at the reactor pressure vessel to the steam generator, the
the bottom of the containment building and cross-over leg from the steam generator to the re-
pumped back into the reactor. actor coolant pump, and the cold leg from the
The maintenance platform running reactor coolant pump to the reactor pressure
around the pressurizer facilitates heater vessel.
replacement and reduces radiation dos- The main circulation pipes are made of
es during valve maintenance. forged austenitic stainless steel, which is re-
sistant to thermal fatigue and can be inspect-
ed using ultrasound.

The pressurizer was installed in


November 2010.

Olkiluoto 3 29
1 Moisture separator reheater (MSR)
2 High-pressure turbine
3 Low-pressure turbine
4 Condenser
5 Generator

30 Olkiluoto 3
SECONDARY CIRCUIT

Secondary circuit
The purpose of the steam-water secondary circuit in the turbine plant is
to convert the thermal energy of the main steam entering from the nuclear
island into electrical energy through the turbine and generator as efficiently
as possible and to return the secondary-circuit feedwater to the steam
generators in the reactor plant. There is no radioactivity in the secondary
circuit because the water of the primary and secondary circuits are
separated from each other.

Main steam system Main condenser and condensate system


The main steam generated in the steam generators be- There are three condensate extraction pumps (CEP), two
longing to the primary circuit is fed to the turbine plant pumping the main condensate from the condenser con-
through the four main steam lines. The main steam is fed densate chambers (hot wells) to the feedwater storage tank
to the high-pressure (HP) turbine through the high pres- through the low-pressure feedwater preheating system.
sure turbine stop and control valves located in each main The third pump acts as a stand-by pump.
steam line. Every main steam line has a relief train, safety The main condensate is preheated in four low-pressure
valves and an isolation valve in the event of abnormal op- feedwater heating stages to improve the efficiency of the
eration. The steam is conveyed through the relief system steam-water process. The main condensate system also
and the safety valves straight into the atmosphere. contains a mechanical condensate purification system for
The exhaust steam from the HP turbine is dried and re- removing impurities.
heated in the moisture separator reheaters (MSR). The re-
heating is performed in two stages, using extracted steam Feedwater system
from the HP turbine extraction A7 and from the main steam There are four feedwater pumps, three pumping feedwater
extracted between the HP turbine stop and control valves. from the feedwater storage tank through the high pressure
From the MSRs, the reheater steam goes through the LP feedwater preheating system to the steam generators. The
turbine stop and control valves to the three LP turbines. fourth pump acts as a stand-by pump.
The exhaust steam from the LP turbines is condensed The feedwater is preheated in three feedwater heating
in three separate sea water condenser units. In addition to stages in two trains, each train consisting of two high-pres-
condensing the steam from the LP turbines, the turbine sure feedwater preheaters and the reheating stage 2 con-
bypass steam is also condensed in these condenser units. densate coolers. The steam is extracted into the high-pres-
The purpose of the turbine bypass steam system is to sure feedwater preheaters from the HP turbine extractions
control the main steam pressure depending on the power A7 and A6. From the preheating system, the feedwater is
plant operation mode. conveyed through the feedwater valves in the safeguard
building divisions into the steam generators.

Olkiluoto 3 31
The HP turbine is a double-
flow turbine consisting
of inner and outer casing
structures split horizontally.

Turbine plant main figures Lifting of the HP turbine rotor


in September 2008.
General
Gross electrical output 1,720 MWe
Net electrical output 1,600 MWe
Main steam pressure (HP turbine) 75.5 bar
Main steam temperature 290°C
Steam flow 2,443 kg/s
Rated speed 1,500 r.p.m.
HP turbine 1
LP turbine 3
Last expansion stage
- exhaust area 30 m2
- last stage blade (LSB) airfoil length 1,830 mm
- overall diameter 6,720 mm
Length of turbine-generator rotor train 68 m
Condenser
Cooling surface 110,000 m2
Cooling medium sea water
Cooling water flow 53 m3/s
Vacuum at full load 24.7 mbar abs.
Sea water temperature rise 12°C
Feedwater
Preheating stages 7
Final feedwater temperature 230°C Inner casing of the HP turbine.

32 Olkiluoto 3
Turbines and generator

Secondary circuit
The thermal energy generated in the re- LP turbines
actor is converted to mechanical energy The three OL3 LP turbines produce ap-
by the turbines and then to electricity by proximately 60% of the gross power out-
the generator. The high 1,600 MWe power put of the power plant unit (approximately
output of OL3 is partly due to the high ef- 320 MWe each). LP turbines are double-
ficiency of the turbine-generator set. flow reaction turbines consisting of fol-
The single-shaft turbine-generator set lowing main components:
consists of one HP turbine and three LP • inner casings
turbines, a generator and an exciter. Each • outer casings
turbine rotor is mounted on two bearings, • 9 expansion stages, stationary blade
i.e. there are double bearings between and running blade stages (6 stages
each turbine module. The OL3 LP turbines are double- with shrouded blades and 3 stages as
The rated speed of the turbine-generator flow turbines with running blades free-standing blades)
is 1,500 r.p.m., and its shaft length is 68 m. attached to blade wheel discs • rotor (forged and machined spindle
The planned service life of the replace- shrunk on to the turbine shaft. shaft where shrunk-on fitted forged
able components of the turbine is 30 years, and machined blade wheel discs)
and the planned service life of the turbine
plant as a whole is 60 years. The inner and outer casings of the LP turbines consist of
inner and outer casing constructions split horizontally.
HP turbine The inner casing of an LP turbine is attached to the tur-
The OL3 HP turbine produces about 40% of the gross bine foundation structure, and the outer casing is welded
power output of the power plant unit (650 MWe). It is a permanently to the condenser construction, which is
admission double-flow reaction turbine consisting of fol- supported by the base foundation structures. The station-
lowing main components: ary blades and running blade seal strips are attached to
• inner casing (cast, machined) the inner casing structures. The thermal expansion of the
• outer casing (cast, machined) outer casing structures is separated from the inner casing
• rotor (6.26 m and 100 t, forged and machined) and rotor construction of the LP turbines.
• 12 expansion stages, stationary blade and running The LP turbine rotor consists of a through-bored spin-
blade stages dle shaft with eight blade wheel discs (four for each flow)
shrunk-on fitted. The coupling flanges of the LP turbine
The inner and outer casings of the HP turbine are formed rotors are also partly secured to the rotor shaft with a
with horizontally split inner and outer casing construc- shrink-on fit.
tions. The inner casing is attached to the outer casing The running blades and stationary blade seal strips of
construction. The stationary blades of the HP turbine the LP turbine are attached to grooves machined in the
and the running blade seal strips are attached to the HP blade wheel discs. The first six running blade stages are so
turbine inner casing. The shaft seal constructions are at- called drum stages and have blade bands, and the last three
tached to the HP turbine outer casing. blade stages are so called free-standing blades. The exhaust
The HP turbine rotor is machined from the forging. area of the last running blade stage is 30 m2, produced by
The running blades of the rotor and the stationary blade the 1,830 mm profile length of the last running stage blades
seal strips are attached to the rotor machined blade and (LSB). The stationary blades in the last stage are hollow
seal strip grooves. vane type, and part of moisture of the expanding steam is
separated via cuts on the hollow vane before the LSB stage.

Olkiluoto 3 33
1. Water tank
2. Four hydrogen / water heat exchangers
3. Fan
4. Shaft seals

Generator properties

Rated speed 1,500 r.p.m.


Frequency 50 Hz
Effective power 1,793 MWel
Nominal rating 1,992 MVA
Power factor 0.9
Voltage 27 kV ± 5%
Efficiency ca. 99%
Magnetization current 9,471 A
Cooling water temperature 45°C
Hydrogen cooling medium temperature 40°C

34 Olkiluoto 3
Secondary circuit
Generator The rotor windings are cooled using hy-
The OL3 generator is a four-pole, hydro- drogen, which is conveyed axially through
gen-cooled generator with a brushless ex- the windings at a pressure of 5 bar. The
citation system. The stator winding and hydrogen is cooled in the hydrogen/water
the winding terminals are water-cooled. heat exchangers. The hydrogen circuit in-
side the generator is powered by a multi-
stage fan mounted on the rotor.

The generator output terminals


transfer the electricity generated
through the bus duct to the main
transformer and onward to the
national grid.

The hydrogen-cooled generator rotor


rotates at 1,500 r.p.m., weighs 250 t
and is almost 17 m long.

Olkiluoto 3 35
Secondary circuit

Construction of cooling water tubes for condenser unit. Condenser unit from the inside.

Two of the three turbine island condensor


pumps are in use, one is a standby pump.

36 Olkiluoto 3
Condenser

Secondary circuit
The exhaust steam from the LP turbines is condensed used as coolant is fed into the tubes through the water
into water in the condenser. There is a condenser unit chambers. The temperature rise of the cooling water in
under each LP turbine, divided into two separate sea wa- the condenser is about 12°C.
ter chambers. The structural design allows one sea water The condenser tubes are cleaned by feeding soft clean-
chamber to be removed and inspected without turbine ing balls (Taprogge) into the cooling water flow and col-
shut-down. lecting them once they have passed through the condens-
In addition to condensing the exhaust steam from the er tubes.
LP turbines, the condenser receives condensate and gas The condenser must have a sufficient low vacuum in
flows extracted from various process systems. order to increase the power plant effeciency. The vacuum
The condenser has a total cooling surface of about pump system maintains a sufficient vacuum in the con-
110,000 m2. The tube material used is titanium, which denser by extracting air and uncondensed gases.
is highly resistant to sea water corrosion. The sea water

One sea water chamber for a condenser


section weighs about 250 t. There are
six of them in total, two for each LP turbine.

Olkiluoto 3 37
A = Cooling water systems
B = Service water system
C = Anti-icing system
D = Essential service water piping system
E = Essential service water system pumping station
F = Anti-icing pumps
G = Circulating water

38 Olkiluoto 3
SEA WATER COOLING SYSTEMS

Sea water cooling systems


Sea water is conveyed along its own un- The pumping station contains four
derground cooling water tunnel at a rate sea water pumps, which are vertically
of 57 m3/s into the OL3 pump station. mounted in a concrete casing. Each pump
Before entering the tunnel, major impuri- conveys about 13 m3/s of sea water to the
ties are filtered out of the sea water with condensers. To cool the power plant sys-
coarse screens. In the pumping station, tems, 4 m3/s of the total sea water flow is
the water is conveyed through four fil- used. From the condenser, the water goes
tering lines to the sea water pumps. The to a seal pit and then through the outfall
filtering lines contain a fine screen and a tunnel to the sea. The outfall channel is
chain basket filter to remove minor impu- shared with OL1 and OL2.
rities from the sea water.
The cooling water intake tunnel has
a cross-section of about 60 m2.

The cooling water pumped by the


sea water pumps is conveyed into
a sea water condenser through the
manifold shown below.

Olkiluoto 3 39
The safety system consists of four parallel
trains, each capable of performing the
required safeguard function on its own.
The four parallel trains are located in
separate buildings on different sides of the
reactor building to eliminate the possibility
of simultaneous failure.

40 Olkiluoto 3
NUCLEAR SAFETY

Nuclear safety
The general objective is to ensure the safety of the nuclear power plant
so that its use causes no radiation risks to the health of employees or
of people living in the vicinity, nor any other damage to the environment
or property. The general principle is that no radioactive substances must
ever be released into the environment.

In case of abnormal operation, OL3 has safety systems Third barrier


consisting of four redundant subsystems, each capable of The primary circuit is completely enclosed by the leak-
performing the required safety function on its own. tight containment with massive concrete walls. The dou-
Three functions are a prerequisite to ensure reactor ble concrete walls of the OL3 containment are built on
safety under all circumstances: a thick base slab, and the inner containment is covered
1. Control of the chain reaction and of the power with a leak-tight metal liner.
generated by it. Any one of these barriers is tight enough to ensure
2. Cooling of the fuel also after the chain reaction has that no radioactive materials can be released into the
stopped, i.e. removal of residual heat. environment.
3. Isolation of radioactive products from the environment.
Safety features of OL3
Reactor safety is based on three protective barriers to OL3 represents evolutionary technology developed on
prevent radioactive releases and on the defence-in-depth the basis of the most recent German Konvoi plants and
principle. French N4 plants. The operating experience from these
plants has been carefully studied and considered for the
Three protective barriers design of OL3. In the development process, the main fo-
The concept of three protective barriers refers to a series cus has been on safety systems and the prevention of se-
of strong and leak-tight physical barriers between radio- vere reactor accidents, as well as minimizing the damage
active products and the environment. The barriers pre- caused by an accident.
vent releases of radioactive products in all circumstances. The design of the safety systems is based on quadruple
redundancy of systems. It means that the systems consist
First barrier of four parallel trains, each capable of performing the re-
The uranium fuel in which radioactive products are quired safety task on its own. The four trains are physi-
formed is enclosed in a metal fuel rod cladding. cally separated and located in different parts of the reac-
tor building in independent divisions.
Second barrier Each of the four safeguard building divisions contains
The primary circuit is a closed circuit made of thick steel. a low and medium-pressure emergency cooling system
The reactor pressure vessel forms part of this circuit. The with the closed cooling and essential service water circuits
uranium fuel encased in metal fuel rods is within this cooling them, the steam generator emergency feedwater
vessel in the reactor core. system, and the electrical equipment and instrumenta-
tion and control systems required for these systems.

Ceramic uranium fuel enclosed Reactor pressure vessel and Double concrete walls
in a metal fuel rod cladding primary circuit of the gas-tight containment

Olkiluoto 3 41
Nuclear safety

Examples of principal safety features of Olkiluoto 3

Double containment Core melt spreading area


(ventilation, filtering)

Containment heat
removal system

Emergency cooling water


storage tank (in-containment
refuelling water storage tank)
Safety systems: four-fold redundancy

42 Olkiluoto 3
Nuclear safety
The emergency cooling systems take their water from steam generators are minimized by lowering pressure
the in-containment emergency cooling water storage through the turbine bypass relief valves and automatic
tank. isolation of the damaged steam generator. The activation
The probability of a serious reactor accident has been pressure levels of the OL3 emergency cooling systems are
further reduced compared with earlier power plants by lower than the pressure levels that open the steam gener-
enhancing preventive systems. The OL3 systems have ator safety valves so that in case of a leak between the pri-
also been further developed to drastically limit the conse- mary and secondary circuits, the steam generator safety
quences of a severe accident. valves will not be actuated.

Safety design Emergency core cooling and residual


All the reactor protection and safety functions required heat removal system
to be instantly activated in an abnormal operating situa- The emergency core cooling system consists of low and
tion or accident are based on automatic systems. This al- medium-pressure injection pumps, nitrogen-pressurized
lows for a planning period of 30 minutes for corrective pressure accumulators and the in-containment refuelling
actions by the plant control room. water storage tank. Under normal use, the system func-
The OL3 safety design is based on the concept that in tions as a residual heat removal system when the plant
the event of abnormal operation, the plant will automati- unit is being powered down to a cold shut-down. The
cally be transferred to a controlled state known as a hot system consists of four separate divisions, each of which
shut-down and further, by manual control, to a stable can independently pump water into the primary circuit
cold shut-down. The controlled state is achieved by using using the low and medium-pressure injection pumps.
the emergency feedwater system, the main steam relief Each subsystem is housed in its own safeguard building
train and the primary circuit emergency boron injection division and feeds into a different one of the four loops of
system. The level at which the residual heat removal sys- the primary circuit. This arrangement ensures sufficient
tem can operate (30 bar and 180°C) is attained by cooling cooling capacity in case of loss of coolant.
through the secondary circuit and by lowering the pres-
sure in the primary circuit. The emergency cooling or re- Emergency boron injection
sidual heat removal systems are then used to attain cold This design concept counteracts the rare event of a failed
shut-down. reactor scram. If the control assemblies fail to drop when
The volumes of the largest reactor components, i.e. the automatic scram conditions are actuated, the reactor
the pressure vessel, the steam generators and the pressu- coolant pumps stop and the emergency boron injection
rizer, have been increased over previous plant designs to system, which has two lines and three pumps, starts up.
slow down the time progression of the reactor transients The piston pumps used for emergency boron injection
and to give the operators more time to initiate corrective can pump boron-containing water at pressures up to 260
actions. bar.
The large steam volume of the steam generator means
that it takes a long time to fill with water from the pri- Residual heat removal
mary circuit in case of a ruptured heat transfer tube. The During normal use or in case of an accident, the excess
steam is conveyed from the damaged steam generator energy and residual heat produced by the fuel can be
primarily to the condenser through the turbine bypass transferred through the steam generators to the second-
valves and not straight into atmosphere. When the con- ary circuit. The steam generators are provided with water
denser is not available, environmental releases from any through the feedwater system during normal use and the
leak between the primary and secondary circuits in the emergency feedwater system in case of an accident.

Olkiluoto 3 43
Nuclear safety

The emergency feedwater system consists of four sepa- Preparedness for severe reactor accidents
rate parallel subsystems that are independent of each In the design of OL3, a severe reactor accident is ad-
other, each of which feeds water into one of the steam dressed: even if the multiple redundant and independ-
generators. Each injection pump has its own emergency ent safety systems were all to fail, the impact of the event
feedwater tank. The tanks and systems are housed in sep- beyond the power plant site would be minor in terms of
arate compartments in the safeguard building divisions. both time and range.
Residual heat can be removed either through the steam Situations that would result in a release of any signifi-
generators to the secondary circuit and then through the cant amounts of radioactive products into the environ-
condensers to the sea or by release of steam into the out- ment have been virtually eliminated.
side air through the main steam relief trains. In case of a The integrity of the reactor containment building in
complete coolant loss in the secondary circuit, pressure in case of a core meltdown is ensured with structures that
the primary circuit can be lowered by steam discharge in- retard the progression of core melt and a passive core
to the containment through the pressurizer relief lines or melt cooling system. At the bottom of the containment,
safety valves. In such cases, make-up water is injected into there is a core melt spreading area consisting of a metal
the primary circuit using the low and medium-pressure structure (core catcher) covered with a 10 cm layer of
injection pumps, and the 2,000-tonne in-containment sacrificial concrete. The purpose of the catcher is to cool
refuelling water storage tank is cooled using an inter- the core melt and to protect the base slab of the reactor
mediate cooling circuit powered by an emergency diesel building against damage that might lead to leaks. Water
generator, or using the independent containment heat circulates in cooling channels under the core melt spread-
removal system. Heat is transferred through the cooling ing area, and water will also rise above the core melt. The
chain formed by the reactor cooling system, the closed large area of the core catcher (170 m2) ensures cooling of
cooling water system and essential service water system the core melt.
to the ultimate heat sink. The suction pipes of the safety If the reactor pressure vessel fails, the core melt is col-
systems have a guard pipe up to the first isolation valve to lected at the bottom of the reactor pit. The transfer of
prevent water loss in case of a suction pipe break. core melt from the reactor pit into the spreading area is
initiated as a passive event, with the hot core melt forcing
Essential service water system its way through the aluminium plug into the core catcher.
The essential service water system is a safety system The 50 cm layer of sacrificial concrete over the alumini-
consisting of four physically separated pumping chains um plug melts into the core melt, delaying the failure of
housed in the four safeguard building divisions. The sys- the plug until all the core melt has accumulated in the re-
tem transfers heat from the heat exchangers of the closed actor pit under the pressure vessel.
cooling water system, which cools the safety systems, to As the core melt enters the spreading area, the cooling
the sea. system is passively activated. The sacrificial concrete over
In addition to the four main chains, the essential the core catcher melts into the core melt. Cooling contin-
service water system has two dedicated pumping chains ues as a passive process with water from a tank inside the
which form part of the independent heat transfer chain reactor containment, flowing down by gravity into the
that is used in case of a severe accident. channels under the core catcher and onto the core melt.
The efficiency of the cooling system is sufficient to
solidify the core melt within a few days, after which the
post-accident long-term management can begin.

44 Olkiluoto 3
Nuclear safety
Emergency cooling water
storage tank Core melt spreading area

Source: AREVA

Core melt cooling system

In the highly unlikely event of a core meltdown at OL3, the core melt is transferred
to the core melt spreading area, where it is cooled and solidified.

Spray nozzles

Passive
flooding
device

Containment emergency
heat removal system Core melt spreading area
Emergency cooling
(2 x 100%) water storage tank

Melt flooding Water level in case of water injection


via cooling device into spreading area
Flow limiter

Olkiluoto 3 45
Coolant handling system

Heat exchanger
Letdown
Auxiliary spray
heat exchanger

Component cooling
High-pressure

Low pressure reducing station


water system
CCWS

Pressurizer
PRT Sampling
Loop 2 system
M

M
Charging line

Reactor
Loop 1 pressure
vessel
Coolant
purification

Loop 4 Loop 3
Coolant
degassing
Reactor coolant
pump seal
injection and
leak-off system
Coolant storage

Boron-containing
make-up water

Make-up water

Gaseous waste
processing system

Volume
control tank
Emergency Emergency
cooling water cooling water
storage tank storage tank
(IRWST) (IRWST)

Gas
treatment

N2 H2

46 Olkiluoto 3
WATER CHEMISTRY AND
VOLUME CONTROL SYSTEMS

Water chemistry and volume control systems


OL3 has a total of about 120 process systems for handling liquid, steam
and gas flows. The chemical and volume control system of the reactor
plant is an essential one, acting as an interface between the high-pressure
primary circuit and the low-pressure systems.

The coolant treatment systems manage Boron and make-up water system
the boron content in the primary circuit The boron in the coolant is enriched with
coolant, water chemistry, purification of regard to one of its two natural isotopes
the circulating coolant, injection and con- (10B, ca. 30–32% by weight). Its purpose
trol of chemicals, dissolved gases in the is to compensate for residual reactivity in
coolant; and the degassing, handling and the reactor core. The boric acid solution
storage of extracted coolant in various is stored at a concentration of 4%, which
situations. The systems are also used for corresponds to about 7,000 ppm of boron.
preparing, storing and injecting the boron All the solutions required for the plant
solution needed for various systems in the systems are made from this storage solu-
plant. During outages, the systems ensure tion, using pure ion-exchanged water for
The boron content of the make-up
the availability of make-up water needed diluting.
water added to the primary circuit is
in the draining and refilling of the prima-
monitored with double continuous- Controlling core reactivity
ry circuit.
action measurement devices
The most important of the coolant Core reactivity is at its highest at the be-
that control the automatic
treatment systems is the chemical and ginning of the refuelling interval because
safety function.
volume control system, which is directly of the fresh fuel. When fresh fuel is loaded
connected to the regulation of the chemi- into the core, all control rod assemblies
cal and physical properties of the coolant in the primary are inserted, and the primary circuit, the reactor pool and
circuit, e.g. its boron content and volume. the transfer pool are filled with a boron solution whose
The chemical and volume control system also man- concentration is about 1,550 ppm. The boron injection
ages the reactor coolant pump seal injection and leak-off. system is always used when the reactor is powered down
The volume control system inlet line is also the source of to a cold shut-down, so as to ensure the sub-critical state
coolant for the pressurizer auxiliary spray system, which of the reactor regardless of its temperature. When the re-
helps lower pressure in the pressurizer. actor is powered up, the control rod assemblies are first
Boron is used in OL3 in the form of boric acid dis- retracted, after which the boron level rod in the primary
solved in water. The boron content of the primary circuit circuit is decreased by diluting until the critical level is
coolant is regulated by adding either pure water or bo- reached. The boron level maintained during use is always
ric acid solution to the coolant fed into the circuit, as re- less than 1,200 ppm.
quired. The volume of the coolant added to and extracted Slow changes in power output over the long term
from the primary circuit must be consistent with the run- and the decline in the neutron flux due to fuel discharge
ning situation. burnup are compensated for by lowering the boron level
gradually until it reaches a level of about 5 ppm just be-
fore refuelling.

Olkiluoto 3 47
Instrumentation & control systems architecture

I&C service Technical Control room


centre support centre

Terminal bus

Plant bus

SA I&C

Field instrumentation Switchgear Control Release Field instrumentation Switchgear Field instrumentation Switchgear

Functional I & C Control rods Safety instrumentation Severe accident management

SICS Safety information and control system PS Protection system TGI Turbine-generator instrumentation SA I&C Severe accident management system
PICS Process information and control system SAS Safety automation system TXS TeleprmXS protection automation system
RCSL Reactor control, surveillance and PAS Process automation system TXP TeleprmXP automation system
limitation system PAC Priority and actuator control
HBS Hardwired backup systems

48 Olkiluoto 3
INSTRUMENTATION AND
CONTROL SYSTEMS

Instrumentation and control systems


Instrumentation and control (I&C) systems consist of field instrumentation,
control systems as well as I&C user interfaces used for the monitoring and
control of the plant.

Safety and availability have been emphasised in the Architecture


design of I&C systems for OL3. The I&C systems of The I&C architecture is designed to follow the defence-
the plant unit are fully automated using proven digital in-depth principle. The following functional levels have
technology, backed up by conventional hardwired been defined to ensure safety:
technology. 1. The process I&C systems, which maintain the
state of the plant unit within normal operating
Design bases parameters.
The functions and equipment of the I&C systems, just 2. Limitation systems, which take corrective action
like all other systems, are classified according to their to restore normal operation if normal operating
nuclear safety significance. The equipment used to im- parameters are exceeded.
plement the I&C systems fulfil the quality requirements 3. The reactor protection system, which automati-
based on the respective safety classification. The OL3 cally initiates the required safety functions (reactor
I&C systems and the associated functions and equipment scram and any situation-specific action required), if
are designed to comply with the general principles of nu- the plant or process parameters exceed any of the
clear safety, including physical and functional separation, protection system limit values.
diversity and redundancy. For example, the emergency 4. The hardwired safety automation system, which is
cooling system and the emergency feedwater system, independent of the other I&C systems and can be
each consisting of four redundant and independent sub- used if the digital I&C systems are lost.
systems, also have four redundant and independent con- 5. The severe accident management system, which is
trol system subsystems. independent of the other I&C systems and used for
According to the design basis of the plant, the protec- the severe accident management.
tion I&C shall be capable of responding to transients and
accidents for the first thirty minutes without operator I&C system functions
intervention. This gives the operators time to establish All the subsystems of the I&C system (measurements,
the cause of the transient and to investigate the required controls, instrumentation, user interface) are divided into
transient and emergency procedures. The monitoring different levels by functions:
and control of the plant is implemented using the work- • Level 0 (process instrumentation or process inter-
station-based user interface in the main control room. face) consists of e.g. sensors and switches.
Each operator has a specific work area in the main con- • Level 1 (I&C system level) consists of control loops
trol room, with several display screens, which present the involved in reactor protection, reactor control, sur-
information on the basis of which the operators carry veillance and limitation functions, safety and process
out the actions required for the control and monitoring automation.
of the plant. A conventional hardwired panel is provided • Level 2 (process monitoring and control) consists of
for use as backup in case of the workstation-based user the user interfaces, i.e. the workstations, the control
interface is not available. The unit can be brought to a panels in the main control room, the remote shut-
safe shutdown state in a controlled manner also from a down station and the technical support centre. Level
remote shutdown station, if necessary. 2 also comprises the I&C systems, which link user
interfaces to system-level I&C.

Olkiluoto 3 49
Simplified schematic of the Olkiluoto 3 power plant unit

400 kV 110 kV

Unit transformer Auxiliary normal Auxiliary normal Auxiliary stand-by


transformer transformer transformer

G
10kV 10kV 10kV 10kV
Generator
M M M M
Turbine island

690V 690V 690V 690V


400V 400V 400V 400V

EDG EDG EDG EDG


Nuclear island

RCP RCP RCP RCP


G M G M G M G M
10kV 10kV 10kV 10kV

M M M M

690V 690V 690V 690V


400V 400V 400V 400V

50 Olkiluoto 3
ELECTRICAL POWER SYSTEMS

Electrical power systems


The electrical power systems have two purposes: to transfer the
electricity generated into the external grid and to supply and distribute
the electricity needed by the power plant itself. The former function
involves the generator busbar, the main transformer and the 400 kV
switchyard and power line. The latter function involves the auxiliary
unit transformers, medium-voltage switchgear, diesel generators and
low-voltage distribution network.

The generator busbars between the gen- supplied by the Olkiluoto gas turbine
erator and the main transformer are in- plant.
dependent, single-phase busbars with The systems are designed to ensure suf-
earthed metal cladding. The main trans- ficient capacity for maintaining nuclear
former consists of three single-phase units. safety even if one division fails and anoth-
The transformer is cooled with oil run- er is simultaneously out of operation due
ning through the coils, which is cooled by to maintenance.
a separate, external water-cooling circuit. Safety-critical systems are connected to
The electricity needed by the power backed-up electrical power systems. These
plant itself is taken from the 400 kV grid are systems that ensure safe reactor shut-
through two auxiliary unit transform- down and residual heat removal and pre-
ers, which are backed up by an auxiliary 400 kV power line isolator chain. vent the spreading of radioactivity.
stand-by transformer connected to the In case of the loss of all exter-
110 kV grid. These two power supplies are nal power supplies, the malfunc-
independent of one another. tion of all four diesel generators at once, i.e. the
The reactor plant electrical power system is divided complete loss of all AC power, the plant unit has
into four parallel and physically separated sub-divisions. two smaller diesel generators with an output of
The power supply to equipment critical for the safety of approximately 3 MVA each. These ensure power supply to
each division is backed up with a 7.8 MVA diesel gen- safety-critical systems even in such a highly exceptional
erator. The busbars of the diesel generators can also be situation.

Olkiluoto 3 51
Discharge of clean water

Radioactive waste water collection and storage


3. Evaporation Return
plant

2.
Monitoring tank
Centrifuge
plant
1. Controlled
water
Ion-exchange outlet
Solid waste* resin dosing tank
Ion-exchange resins from the
Tank sludge feedwater purification system

Concentrate tank
Buffer tank Mixing circuit

Condensate

Concentrate and resin drying


in drums by vacuum heating
(drying station)
1. Radioactive water from primary circuit and
fuel pools, and decontamination water
2. Low-level radioactive water, e.g. from laundry * Waste separated in centrifugal apparatus is
and washrooms also dried by vacuum heating (drying station)
3. Possibly radioactive water from the steam and the waste drying drum is then filled with
generator dump valves concentrated waste to be further solidified

Gaseous waste handling schematic


Degasification system and vent stack
Pressure relief station
Decay filters

Compressor Pressure
relief station

Gas Recombiner Cooler Pre-dryer Gas filter


dryer
Coolant
degassing
system

Gel dryer
Flushing
the tanks in
the reactor
building Reduction stations

Flushing the tanks in the auxiliary


building and fuel building

52 Olkiluoto 3
WASTE PROCESSING SYSTEMS

Waste processing systems


Radioactive waste is classified on the basis of its radioactivity and physical
and chemical properties. Each type of waste is processed appropriately.
High-level radioactive waste is kept separate from low-level radioactive
waste at all times, and there are separate processing lines for different
types of solid, liquid and gaseous waste.

Solid operating waste Waste of this type is first stored in tanks


Solid operating waste is divided into low- and then mixed in a drying process.
level waste and intermediate-level waste. The ion exchange resins, evaporator
No solid waste classified as intermediate- concentrates and other sludges are after
level waste requiring final disposal is pro- tank storage dried in the barrel drying
duced, in substance, at the OL3 unit. facility provided in the waste process-
Low-level waste comprises materials ing building of OL3. A filter element can
and substances contaminated with radio- be placed in the barrel before the drying
activity. Such material includes fire-resist- is started. The filter element will then be-
ant fabrics, plastic covers, protective cloth- come enclosed in the drying material. The
ing, and low-active components, such as waste to be dried is placed in a 200-litre
Impurities in the coolant are bound
seals, removed from the systems. Low- barrel and dried through heating in a
into the ion-exchange resins by a
active waste is divided into the following vacuum, until 90% of the waste is dry.
chemical reaction and thus removed
groups; mixed maintenance waste, scrap Heating is continued at a temperature of
from the circuit.
metal, waste dried in a barrel, filter ele- ca. 130°C until all water has evaporated.
ments, filter inserts and solidified mixed The condensed water is returned to the
liquids. liquid waste processing system.
The initial activity level of the waste and filter ele-
Processing of mixed maintenance waste and scrap ments dried in barrels can be equal to intermediate-level
metal waste. These waste groups are first stored inside the OL3
So-called small items representing low-level waste are unit, before they are transferred to TVO’s interim storage
collected at the point where they are produced either in- for intermediate-level waste, where the waste is kept until
to plastic bags or directly into 200-litre steel barrels and Co-60, which is the primary (>90%) nuclide making the
transported to the sorting facility for sorting according to waste radioactive, has undergone 5–10 half-lives. After
their activity content and type. Waste collected into bags that the waste can be emplaced for final disposal in the
is later packed in barrels. The compactable waste packed operating waste repository like other low-level waste.
in barrels is compacted to a smaller volume in the bar-
rels and some of the barrels are also compressed to half Processing of solidified mixed waste
of the original size in vertical direction. Large items are Solidified mixed waste includes e.g. different waste oils
packed either in steel boxes or directly in concrete boxes, contaminated with activity. The activity of the waste oil
and the barrels are also placed in concrete boxes before is measured and the oil is placed in 200-litre barrels for
they are emplaced in the operating waste repository for solidification in the system already used for waste gener-
final disposal. Mixed maintenance waste is very low-level ated at OL1 and OL2.
waste as a rule.
Final disposal
Processing of filter elements and waste dried in The solid operating waste produced at OL3 is placed in
barrels concrete boxes and transferred for final disposal to the
Waste dried in barrels primarily consists of evaporator operating waste repository located in Olkiluoto. The
concentrates, tank bottom sludge, ion exchange resin and repository is also used for final disposal of operating
filter elements used in the purification of process water. waste generated at OL1 and OL2. Accurate records are

Olkiluoto 3 53
Waste processing systems

maintained of all solid waste emplaced in tanks, to reduce the hydrogen concentra-
the repository (activity data and location tion of these gases catalytically by convert-
in the repository). ing hydrogen gas into water, and to flush
with inert nitrogen gas various storage
Liquid waste tanks where waste gases may accumulate.
All water removed from the unit is col- The pressurised active carbon filters of the
lected from the liquid waste collection and delay unit are designed to retain radioac-
processing systems into inspection tanks tive noble gases (Xenon, Krypton) so as to
where samples are taken for activity meas- reduce their radioactivity to an acceptable
urements and chemical analyses. When an level before the gases are released. From
acceptable inspection result is obtained, the delay unit the gases are released for
Offgases are delayed, filtered and
separate permission is issued to discharge further processing into a ventilation sys-
conveyed from the plant into the
the water from the unit. tem equipped with separate filters. Plant
atmosphere through a 100-metre-
start-up and shut-down, process actions
Gaseous waste high ventilation stack.
and events such as nitrogen flushing of
Gaseous radioactive waste mostly consists the reactor pressure vessel head can cause
of fission gases released from the nuclear fuel and dis- a substantial gas flow to the gaseous waste processing
solved in the primary coolant and in the airspace of the system.
tanks of the associated auxiliary systems. These fission The overflow is in this case conveyed through the ac-
gases include e.g. noble gases Krypton and Xenon. The tive carbon filter units of the delay unit in the pressurised
concentrations of the fission gases, the hydrogen added part of the system and further through the mechanical
to create the chemical conditions required by the reactor coarse and micro filters to the vent stack. The activity
coolant, and other dissolved gases are controlled in the level of the gas flow is analysed in the ventilation system
degasifier, which is included in the chemical and volume and if an excessive activity level is detected, the gas flow
control system of the primary circuit. If necessary, the is diverted after the mechanical filters further to an io-
gases dissolved in the coolant can be removed complete- dine-treated active carbon filter system. The mechanical
ly. The amount of fission gases in the coolant is propor- filters of the ventilation system retain any active aerosols
tional to the integrity of the fuel. Light water reactors also and other small particles possibly contained in the waste
produce gaseous waste, when neutron radiation activates air. The iodine-treated active carbon filters of the same
the natural Argon contained in air and present in the air- system bind any radioactive iodine possibly introduced
space that surrounds the structures of the reactor pres- into the waste gas as a result of e.g. severe fuel damage.
sure vessel. A residual concentration of Argon can also The systems involved in the processing of waste gases
be dissolved in the primary coolant. Argon-41 is a short- are designed to either completely retain or delay the ra-
lived isotope with a half-life of less than two hours. dioactive materials contained in the gas flow until their
In order to minimize gas emissions, a gaseous waste activity has been reduced to an acceptable level. The ac-
processing system based on a semi-enclosed circuit has tivity of all gases released from the plant is finally moni-
been selected. It consists of two parts: the flushing unit tored with continuously operating activity measurements
and the delay unit. The flushing unit is designed to re- in the vent stack.
ceive gas from the degasifier and the coolant storage

54 Olkiluoto 3
Waste processing systems
Some of the solid plant waste is packed into 200-litre drums. A special vehicle takes the waste packages
to the Olkiluoto disposal repository.

Olkiluoto 3 55
56 Olkiluoto 3
TRAINING SIMULATOR

Training simulator
Part of the OL3 power plant supply to The purpose of the training simula-
TVO will include a full-scope training tor is for personnel to practise all pos-
simulator, which will be completed and sible events that may occur at the power
ready for use one year before the first fuel plant unit, including transients and ac-
loading of the power plant unit. The simu- cidents, and to validate operation, abnor-
lator can replicate exactly the functions of mal operation and emergency operation
the new unit, and the simulator control procedures.
room is a full-scale replica of the real one. The plant supplier is responsible for
The simulator will mainly be used for op- designing and building the simulator to-
erator training before the power plant unit gether with several well-known suppliers
is started up, and subsequently for annual in the field. The simulator and its auxiliary
Simulator control room being tested
supplementary training. facilities will be housed in a new annexe
in the manufacturer’s facilities.
to be built at the existing TVO training
centre.

3D process models are utilized in


training the nuclear power plant
operators.

Olkiluoto 3 57
Technical data

General Fuel
Reactor thermal power 4,300 MWth Fuel uranium dioxide UO2
Electrical power, gross 1,720 MWe Assembly type 17x17 HTP
Electrical power, net 1,600 MWe Fuel rods per assembly 265
Efficiency ca. 37% Guide thimbles per assembly 24
Primary coolant flow 23,135 kg/s Spacer grids per assembly 10
Reactor operating pressure 155 barabs Length of fuel assembly 4.8 m
Coolant temperature in the reactor Weight of fuel assembly 735 kg
pressure vessel, average 312°C Width of fuel assembly 213.5 mm
Coolant temperature in the hot leg 328°C Cladding material M5TM
Coolant temperature in the cold leg 296°C UO2 pellet density 10.45 g/cm3
Electricity output per year ca. 13 TWh Fuel discharge burnup 45 MWd/kgU
Sea water flow 57 m3/s
Service life ca. 60 years Control assemblies
Building volume 1,000,000 m3 Number of control assemblies 89
Containment volume 80,000 m3 Absorber length:
Containment design pressure 5.3 bar lower part 2,900 mm
upper part 1,340 mm
Reactor core total length 4,717.5 mm
Number of fuel assemblies 241 Absorber material
Active core height 4.2 m lower part silver, indium,
Core diameter 3.77 m cadmium
Total fuel weight ca. 128 tU upper part boron carbide
Fuel enrichment level, initial core loading 1.9%—3.3% 235U
Fuel enrichment level, reloading 1.9%—4.9% 235U Pressure vessel
Fuel consumption per year ca. 32 tU Inner diameter 4.9 m
Fuel consumption per year ca. 60 assemblies Inner height 12.3 m
Wall thickness 250 mm
Bottom thickness 145 mm
Thickness of stainless steel cladding 7.5 mm
Design pressure 176 bar
Design temperature 351°C
Weight with cover 526 t

58 Olkiluoto 3
Turbine plant Generator
Turbine generator unit 1 Nominal rating 1,992 MVA
Gross electrical output ca. 1,720 MW Power factor, nominal 0.9
Main steam pressure 75.5 bar Rated voltage 27 kV ± 5%
Steam temperature 290°C Frequency 50 Hz
Steam flow 2,443 kg/s Rated speed 1,500 r.p.m.
Rated speed 1,500 r.p.m. Cooling, stator coils water
HP turbine 1 Cooling, rotor hydrogen
LP turbine 3 Magnetization current 9,471 A
HP turbine stop and control valves 4/4 Cooling water temperature 45°C
LP turbine stop and control valves 6/6 Hydrogen cooling medium temperature 40°C
Last stage
– exit annulus area 30 m2 Power supply
– blade length 1,830 mm Main transformer 3 x 1-phase
– overall diameter 6,720 mm Nominal rating 3 x 701 MVA
Turbine-generator shaft length 68 m Rated voltage 410/27 kV
Auxiliary unit transformers 2
Condenser Nominal rating 90/45/45 MVA
Cooling surface 110,000 m2 Rated voltage 400/10.5 kV
Cooling medium sea water Auxiliary standby transformer 1
Sea water flow 53 m3/s Nominal rating 100/50/50 MVA
Vacuum at full load 24.7 mbar Rated voltage 110/10.5 kV
Temperature rise 12°C Emergency power supply 4 x EDG and 2 x SBO
Nominal ratings 4 x 7.8 MVA and
Feedwater 2 x 3.0 MVA
Preheating stages 7 Turbine plant diesel engine 1
Final feedwater temperature 230°C Nominal rating 1.6 MVA

Olkiluoto 3 59
1

10 9/2010

1
11
2
12
3
13
4
14
5
15
6
16
7
17
8
18
9
19
10
20
1
11
21 Source: AREVA

2
12
22
3
13
23
4
14
24
5
15
25
6
16
26
7
17
27
8
18
28
9
19
29
10
20
30
11
21
31 11/2009
12
22
32
13
23
33
14
60 O24
lkiluoto 3
34
15
25
1
1. Installation of steel structures on top of the inner containment dome 4. Acidifying of a battery at the turbine island.
preceded the construction of the outer dome. 5. Lifting
2 of the reactor pressure vessel.
2. Installation of the steam generator tubes. 6. Closure head of the reactor pressure vessel inside the reactor
1
3. Delivering the steam generators to the site. 3
building.

2 7. The low-pressure turbine rotors.


4

3 5

4 6

5 7

6 8

7 9

8 10

1
9 11
2
10 12
3 5/2010
11 13
4
12 14
5
13 15
6
14 16
7
15 17
1
8
16 18
2
9
17 19
3
10
18 20
4
11
19 21
5 6/2010 9/2010
12
20 22
6
13
21 23
7
14
22 24
8
15
23 25
9
16
24 26
10
17
25 27
11
18
26 28
12
19
27 29
13
20
28 30
14
21
29 31
15
22 10/2008
30 32
16
23
31 33
17
24
32 34
18
25 Olkiluoto 3 61
33 35
19
26
Teollisuuden Voima Oyj
Olkiluoto
FI-27160 EURAJOKI, FINLAND
Tel. +358 2 83 811
Fax +358 2 8381 2109
www.tvo.fi

Teollisuuden Voima Oyj


Töölönkatu 4
FI-00100 HELSINKI, FINLAND
Tel. +358 9 61 801
Eura Print Oy 12/2010 2,000 pcs

Fax +358 9 6180 2570

Teollisuuden Voima Oyj


4 rue de la Presse
BE-1000 BRUSSELS, BELGIUM
Tel. +32 2 227 1122
Fax +32 2 218 3141

You might also like