Professional Documents
Culture Documents
Piul Mom - 04 11 2020
Piul Mom - 04 11 2020
PARTICIPANTS:
PIUL
Gireesh Hegde
Vijaykumar Patel
Ajay Kurup
SARPI
HAMMITOUCHE – Available, Zoubir Kalkil (SQM)– Not available,
SADEK BRAHMI – Available, Mohamed Bourabia – Not available, Sami – from Site –
Available, Hamid – from Site – Not available, Zaidi Djahid (SQM) - Available
Attachments: NIL
Page 1 of 9
PIUL-MOM
MINUTES
25/10/2020
Plan for welders’ qualification to start construction welding SARPI 02/11/2020
1.4 activity after PQR qualification, SARPI to provide tentative
06/11/2020
plan with date and total number of welders to be qualified.
Page 2 of 9
PIUL-MOM
PIUL has reviewed the ITP for Welding and NDT in Code-
2. SARPI to add requirements as commented by PIUL TBA
including testing as per basis of design document. SARPI 15/11/2020
1.9
PIUL has reviewed and sent ITP on 27/10/2020. SARPI to
incorporate comments and revise the document.
Page 3 of 9
PIUL-MOM
Page 4 of 9
PIUL-MOM
Page 5 of 9
PIUL-MOM
Laboratory testing
4.0 INFO --
CRTI Algiers
Page 6 of 9
PIUL-MOM
7.0 SARPI to check and confirm when PQT will start after 18/10/2020
receiving HSS materials at Site
Page 7 of 9
PIUL-MOM
PIUL sent email for PQT requirement for HSS/coating For all
repair procedure on 03rd October 2020. So far, SARPI has activities
only submitted procedure and not yet taken actions on all
above points.
Accepted on behalf of
PIUL
(Signed)
Accepted on behalf of
SARPI
(Signed)
Page 8 of 9
PIUL-MOM
Common
Resources –
NDT Welding
Planned Engineer / any R& R and
crew overlap
Pipeline Start other
KP No of (Exclud
Diameter Date Civil Welding discipline between
to Welding ing
and Inspectors Inspectors two
KP Crews NDT
thickness (Level-4 (Please address responsible
supervi
Schedule) in the Org. Chart personnel
sor)
also, this
position is not
shown)
Spread-1
Spread-2
Spread-3
Spread-X nos.
Page 9 of 9