CostEstn PDF
Determining
Manufacturing Costs
John Anderson
Dow Chemical
Making early estimates of a product’s
cost components enables developers to
manage resources wisely and
evaluate the product’s economic viability.
E
stimating manufacturing costs of a new product or pro- product’s success than the items on the cost side.
cess soon after research and development (R&D) has A great deal of information has been published on methods of
commenced can provide a good indication of the projec- estimating manufacturing costs. However, much of this work
t’s economic viability. “Early” estimates can be used to direct has addressed the costs of a specific product or process or has
research efforts to promising opportunities for cost reduction, concentrated on capital equipment and its depreciation, which is
and allow businesses to better assign resources to new products. only one component of total product cost.
Although potentially compromised because some informa- Cost components. Product manufacturing costs can be cate-
tion may be missing, early estimates are often sufficiently accu- gorized as fixed or variable (Table 1). Those that are insensitive
rate to shed light on a product’s long-term viability. to the volume of product made are considered to be fixed. Labor,
Quick determination of the relative contribution of variable although not completely fixed, is somewhat independent of
costs, fixed operating costs, and capital depreciation to the total product volume, since the number of people operating a plant
product costs allows cost-reduction efforts to be focused on and their salaries are not easily adjusted as demand fluctuates.
those cost components that are likely to be most significant. Raw material costs are variable — if more product is to be made,
Because the tasks required to develop cost estimates are virtually more raw material is required.
the same for all products, time invested in developing a general- No cost is completely fixed or completely variable. Although
ized and consistent methodology for making cost assessments labor is considered to be a fixed cost, personnel supply can be
and comparisons can pay large dividends. adjusted in response to anticipated seasonal product demand.
In this article, the term “economics” is not used because cost Prices for raw materials fluctuate slightly with changes in
assessments, which play a significant role in project economics, demand. However, for estimates made in the early stages of a
must be combined with information about the revenue the prod- product’s development or for the purpose of high-level decision-
uct is expected to generate. For example, the value of a new making, determining which costs are largely fixed and which are
toothpaste formulation must be determined by those with knowl- largely variable, and then assigning them complete dependence
edge of its market. Many technical personnel do not have the or independence from production volume, will facilitate the
expertise required to address all relevant economics questions. development and use of a cost-estimating method.
The income side of the ledger can have a greater impact on a
Estimating variable costs
Table 1. Example of variable and fixed production costs. Raw material usage. A simple material balance and flow-
Variable Costs Fixed Costs sheet must be developed in order to estimate the variable costs of
raw materials. Spreadsheets are useful tools for this purpose,
Raw Materials Capital Supplies (office,
Depreciation janitorial, etc.) and, once created, can be appended to cost worksheets for easy
Waste Labor (both Plant Support (e.g.,
retrieval. The importance of effective documentation cannot be
Treatment operations and R&D personnel overstated. Cost estimation typically results in unpopular deci-
supervisory) dedicated to plant sions that are frequently challenged. Confidence about exactly
troubleshooting)
what was estimated is invaluable during such discussions.
Utilities (for Utilities (for small- Site Services (e.g., The material balance may be subject to uncertainties, such as
large-volume volume processes) plant security,
processes) support of plant reaction yields or catalyst usage. Treating these quantities as
infrastructure) variables and locating them in a convenient place in a spread-
Plant Maintenance sheet is helpful. Use a single worksheet that can be populated
Example 1. Medium-to large-volume product small because their impact on total cost is also small.
Assume: Raw material prices. Once the material balance is
Production Volume = 5 million lb/yr established, raw material prices must be identified.
Required Capital Investment (correlation) = $50 million For those materials that are produced internally or
Total Significant Operating Sections =3 are already purchased, pricing data can be obtained
Waste Generation = 3 lb aqueous waste/lb product
from purchasing or commercial departments. Some
+ 0.5 lb organic waste/lb product
a. Raw Material Cost
pricing information is available free or by subscrip-
Usage Rate Price Cost Contribution tion from sources such as ICIS Chemical Business
Raw Material (lb/lb of product) ($/lb raw material) ($/lb product) (formerly Chemical Market Reporter), SRI
A 1.2 $1.50 $1.80 Consulting (www.sriconsulting.com), Chemical
B 2.0 $2.50 $5.00 Market Associates, Inc. (www.cmaiglobal.com),
C (catalyst) 0.001 $200.00 $0.20 Chemical Week (www.chemweek.com), The Plastics
Total Raw Material Cost = $7.00 Web (www.ides.com) and reference texts such as the
b. Waste Treatment Cost
“Kirk-Othmer Encyclopedia of Chemical
Total Waste Treatment Cost = (3.0 × $ 0.01/lb) + (0.5 × $ 0.20/lb)
= $0.11/lb product
Technology” and “Ullman's Encyclopedia of
c. Capital Depreciation Industrial Chemistry.” Many prices fluctuate widely,
(from Eq. 2) Depreciation = $50,000,000 / [(10 yr × 5,000,000 lb/yr)] = $1.0/lb so using time-weighted averages is recommended.
d. Other Fixed Costs Specialty products (e.g., fine chemicals, pharma-
Using data from Table 2: ceutical raw materials, etc.) often require raw materi-
Operating Labor Cost = 3 operating personnel/shift × 4 shifts × $75,000/yr als that are not widely available in the marketplace.
= $900,000/yr For these, a supplier inquiry is necessary. This task
Non-Operating Labor Cost = 0.6 × $900,000/yr = $540,000/yr
can be cumbersome, as many suppliers are reluctant
Supplies = 0.3 × $900,000/yr = $300,000/yr
Administration/Overhead = 0.9 × $900,000/yr = $810,000/yr
to quote prices for projects that they consider specu-
Maintenance = 0.02 × $50,000,000 = $1,000,000/yr lative. The price of such raw materials will always
Utilities = 0.01 × $50,000,000 = $500,000/yr depend on the volume and quality required, as well
Miscellaneous = 0.01 × $50,000,000 = $500,000/yr as on the project’s timeframe. Some speculation is
Total Annual Fixed Costs = $4,550,000/yr necessary. Suppliers appreciate honesty when they
Total Fixed Costs = ($4,550,000/yr) / (5,000,000 lb/yr) = $0.91/lb are asked to spend time developing pricing for prod-
e. Total Manufacturing Cost ucts that are not off-the-shelf items.
Total Manufacturing = $7.00/lb + $0.11/lb + $1.00/lb + $0.91/lb = $9/lb
To find the appropriate supplier, use catalogs to
obtain a Chemical Abstracts Registry Number (CAS
$10 Fixed Costs No.), which can be input as a search term on such websites as
Capital Depreciation ChemNet (www.chemnet.com), Chemcompass
$8 Waste Treatment (www.chemcompass.com), and the subscription-only Directory
Raw Material C of World Chemical Producers. This will yield a list of companies
Raw Material B
$6 claiming to produce each compound. Cursory knowledge of
Raw Material A
how to make a given compound can be helpful for identifying
$4 legitimate suppliers. Research can usually reveal which compa-
nies have the required know-how and can offer dependable price
$2
estimates. Be wary of suppliers claiming to have the ability to
make everything. To eliminate the need to make repeated
$–
Volume = Volume = inquiries and reduce estimating time, maintain a database of
5,000,000 lb/yr 25,000,000 lb/yr pricing information collected from suppliers.
Cost of Manufacturing, $/lb If a raw material price seems impossible to find, it may make
sense to estimate as if it were to be made internally. The risk of
■ Figure 1. Early-phase estimates for Example 1 use a limited error with this approach can be reduced if a knowledgeable col-
number of significant digits to underscore uncertainty. Since Raw league can suggest an efficient production method. Estimating
Material B contributes more than 50% of total product cost, efforts
should focus on reducing its usage by yield improvement, etc.
techniques used for evaluating the final product can be applied to
a raw material for which pricing information is unavailable.
with inputs for variables whose values are expected to change. It is often unwise to consult laboratory supplier catalogs for
Key outputs can be placed on the same sheet to simplify the commercial pricing information. These suppliers invest heavily
study of changes. in inventories and packaging that suits the needs of lab-scale
Areas of uncertainty can easily be explored through “what-if” customers. These listed costs do not scale well.
questions. A project team often includes an expert whose guess- Example 1 in the box at the left shows that increasing volume
work can approximate the value of variables sufficiently for the results in dramatic reduction of capital and fixed costs on a per-lb
estimator to proceed. Completion of a cost estimate using educat- basis because these costs are not strong functions of volume in
ed guesses often reveals that the importance of some variables is most chemical processes.
the largest share of the plant’s utility cost. In these cases, it is rea- ■ Figure 2. The cost distribution for Example 2 shows a dramatic
sonable to estimate the total utility cost as a function of the reduction in capital and fixed costs on a “per lb” basis. A valid
plant’s capital. A value of 2% of the plant’s capital for an overall volume forecast is always important, but is most important for
utility cost is reasonable for such processes (e.g., the annual cases where volume begins to approach zero.
utility costs for a plant that cost $50 million to construct would
be approximately $1 million per year). This utility estimate is the process must be available along with at least some funda-
very rough and should be reserved for cases where utility costs mental information (e.g., size, capacity) about each.
are known to be small, but it is often adequate for cost estimates For early-stage estimates, this information is difficult to
for very specialized products. obtain or develop. A much more significant problem is that
equipment-based estimates depend on the completeness of the
Estimating fixed capital costs equipment list. In early stages of a product’s development, the
Capital estimation is treated in a number of textbooks and equipment list is always incomplete. For example, an equipment
articles (2–7). Many techniques are available for developing list for such a product is unlikely to include a filter that removes
capital cost estimates, including a variety of commercially avail- black specks if the black specks in question have not yet been
able software packages. Unfortunately, many of these methods observed in laboratory work. Likewise, the need for a column
are equipment-based, so a list of the specific items required by would not be considered in an equipment list made before an
Table 2. Relative complexity of common unit operations. (www.netl.doe.gov). These can be used for rough com-
parisons when the process is similar to one for which
Relative Relative
Operation Complexity Operation Complexity data are published.
Information collected by the company from past
Reaction/Workup
projects should be retained. These data from existing
Gas stripping (sparge from 0.60 Crystalllizer 1.00 plants can be used to develop crude, but useful, correla-
separate vessel) (separate vessel)
tions of capital costs as a function of various factors,
Secondary reaction 0.80 Decantation 0.90 including: number of unit operations, volume, location,
(neutralization, post cooking) (seprate vessel)
materials of construction, and operating conditions.
Reaction 1.00
The Viola method captures the effects of these
Separation variables and has proven useful (6). In general, the
Atmospheric distillation 1.20 Leaf or plate-and-frame 0.30 variable that most often differentiates one process
(no tower) type filtration (no solids from another is process complexity. Means for quantify-
packing; no slurry tank)
ing this, by estimating the number of unit operations or
Atmospheric distillation 1.40 Centrifugation (no solids 1.50 reaction steps, are imperative. Table 2 can serve as a
(with tower) packing; no reslurry tank)
rough guideline for the relative capital investment
Vacuum distillation (no tower) 1.40 Dryer 1.30
required for some of the operations encountered in
Candle filtration (no solids 0.60 Vacuum distillation 1.60 chemical processing plants, including small auxiliary
packing; no reslurry tank) (with tower)
items required for operation, e.g., the numbers for
Solids Handling distillation systems reflect the need for a reboiler,
Size enlargement 1.30 Centrifugation (isolate 1.60 condenser, etc.
solids in packs) The effect of volume on capital is known to be non-
Drum, pack or bag handling 0.20 Mills, crushers, grinders 0.50 linear. The predictions presented in (Ref. 6) underscore
Filtration (isolate solids in 0.60 Centrifuge (biochemical 2.00 this point. A common guideline for extrapolation of a
packs) stack disk, decanter) capital estimate to a different volume is the six-tenths
Storage and Transfer rule:
Conveyors 0.10 Intermediate processing 0.50
⎛ Vy ⎞ 0.6
tank (reslurry tank, etc.)
CVy = CVx ⎜ ⎟ (1)
Raw materials storage, 0.50 Intermediate storage 0.40 ⎝ Vx ⎠
unloading, handling, transfer (solvents for recycling,
surge tanks, etc.)
where Cvy is capital at volume y, Cvx is capital at volume
Utility x, Vy is volume y, and Vx is volume x. Many references
Unloading station 0.30 Hot oil system 0.50 include tables that suggest refinements of this rule
Demineralized water 0.30 Cooling tower 0.30 (2–4, 8–10).
generation system The effect of location is not considered in Viola’s
Refrigeration unit 1.30 Thermal treatment unit, 2.50 method, nor is it within the scope of this article. It is
including fume scrubber frequently a strong function of local labor rates and, in
Waste Handling some cases, import taxes, which vary widely with
Carbon adsorption (gases; 0.10 Process fume scrubbing 0.60 respect to both time and region.
cannisters) Materials of construction costs are increasing rapid-
Carbon adsorption (liquid) 0.80 ly, owing, in part, to the large amount of construction
occurring in China and India, which has resulted in
R&D team realizes that a separation is necessary. materials shortages. Thus, it is necessary to update this informa-
This problem can be reduced by using higher-level tech- tion frequently. Equipment suppliers can often provide guidance
niques based on existing operational plants and processes. Since on this. The net effect of increasing material costs is lessened
such uncertainties have presumably been eliminated in plants somewhat when calculations reflect the installed cost of a fully
that are already running, estimates that extrapolate from them fabricated piece of equipment, and not simply the cost of the
include the cost of all items implicitly (even those for which the material in its raw form (e.g., sheet metal).
need is not initially obvious). Corrections for extreme operating conditions (i.e., tempera-
Methods for capital-cost estimation that require less informa- tures greater than 200ºC or less than –10ºC, pressures greater
tion are indispensable for early stages of process/prod-uct devel- than 200 psia or less than atmospheric) typically add 10–20% to
opment. Data on the capital invested in a large number of exist- the total capital cost computed by this method. This relatively
ing plants and processes are available in reports available by minor impact results from the fact that much of the cost of any
subscription from SRI Consulting, Chem Systems equipment item is independent of the amount of material used to
(www.chemsystems.com), and government laboratories, such as build it (e.g., installation and instrumentation costs are somewhat
the National Renewable Energy Laboratory (NREL; insensitive to operating conditions).
www.nrel.gov) and the National Energy Technology Laboratory Capital depreciation. Depreciation calculations assign some