CONSTRUCTION

OF PATENGA CONTAINER TERMINAL WHARF JETTY


OWNER: 34 ENGINEER CONSTRUCTION BRIGADE
CONSTRACTOR: CRBC‐EEL CONSORTIUM

ID Task Task Name WBS Start Duration Finish % Complete


Mode Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
0 CONSTRUCTION OF PATENGA CONTAINER TERMINAL WHARF/JETTY 16 Dec '18 556 days 23 Jun '20 39%
1 MOBILIZATION PERIOD A 17 Dec '18 90 days 16 Mar '19 100%
2 Rent, site preperation & other work at yard area A.1 17 Dec '18 90 days 16 Mar '19 100% 90 days 100%

3 Mobilization of Equipment A.2 17 Dec '18 90 days 16 Mar '19 100% 90 days 100%

4 TEST PILE WORK & REVIEW DESIGN B 16 Dec '18 161 days 25 May '19 100%


5 Mobilization of Test Pile B.1 16 Dec '18 19 days 03 Jan '19 100% 19 days 100%

6 Bank Area Piile Driving & Load Test B.2 03 Jan '19 105 days 17 Apr '19 100% 105 days 100%

7 F. Area Pile Driving & Load Test B.3 06 Jan '19 120 days 25 May '19 100% 120 days 100%

8 REVIEW DESIGN C 18 Apr '19 56 days 12 Jun '19 100%


9 Review Design of Pile Length for Bay‐B C.1 18 Apr '19 56 days 12 Jun '19 100% 56 days 100%

10 Review Design of Pile Length for Bay‐F C.2 18 Apr '19 56 days 12 Jun '19 100% 56 days 100%

11 RC SHEET PILE D 06 Feb '19 421.3 days 02 Apr '20 71%


12 Casting of RC Precast Sheet Pile D.1 06 Feb '19 212 days 05 Sep '19 100% 212 days 100%

13 Mobilization of Equipment to Jetty Area D.2 10 Feb '19 40 days 21 Mar '19 100% 40 days 100%

14 RC Precast Sheet Pile Driving D.3 31 Mar '19 200 days 16 Oct '19 92% 200 days 92%

15 Construction of Breast Wall & Anchor Wall D.4 15 Apr '19 230 days 02 Apr '20 20% 230 days 20%

16 CASTING OF PRECAST GIRDER & SLAB E 25 Feb '19 250 days 01 Nov '19 91%


17 Casting of Precast Girder E.1 25 Feb '19 250 days 01 Nov '19 87% 250 days 87%

18 Casting of Box Beam E.2 17 Mar '19 200 days 02 Oct '19 99% 200 days 99%

19 Casting of Precast Slab E.3 25 Feb '19 250 days 01 Nov '19 87% 250 days 87%

20 SUPPLY & INSTALLATION OF PHC PILE F 13 Jun '19 54 days 05 Aug '19 100%


21 Pile Fabrication and Manufacture F.1 13 Jun '19 25 days 07 Jul '19 100% 25 days 100%

22 Shipment & Transportation F.2 18 Jul '19 15 days 01 Aug '19 100% 15 days 100%

23 Clearance & Mobilization at Stock Yard F.3 02 Aug '19 4 days 05 Aug '19 100% 4 days 100%

24 PHC PILE DRIVING G 06 Aug '19 200 days 21 Feb '20 28%


25 Bay‐A G.1 08 Aug '19 55 days 01 Oct '19 98% 55 days 98%

26 Bay‐B G.2 06 Aug '19 87 days 31 Oct '19 64% 87 days 64%

27 Bay‐C G.3 20 Sep '19 63 days 21 Nov '19 17% 63 days 17%

28 Bay‐D G.4 24 Oct '19 44 days 06 Dec '19 0% 44 days 0%

29 Bay‐E G.5 10 Nov '19 40 days 19 Dec '19 0% 40 days 0%

30 Bay‐F G.6 01 Dec '19 46 days 15 Jan '20 0% 46 days 0%

31 Bay‐G G.7 20 Dec '19 42 days 30 Jan '20 0% 42 days 0%

32 Bay‐H G.8 05 Jan '20 33 days 06 Feb '20 0% 33 days 0%

33 Load Test of Pile G.9 07 Feb '20 15 days 21 Feb '20 0% 15 days 0%

34 SLOPE PROTECTION WORK H 24 Jul '19 285 days 03 May '20 17%


35 Mobilization of Equipment at Jetty area H.1 24 Jul '19 15 days 07 Aug '19 100% 15 days 100%

36 Compacted Sand Filling H.2 23 Aug '19 250 days 28 Apr '20 16% 250 days 16%

37 Geo Bag & Stone Dumping on River Bed H.3 23 Aug '19 250 days 28 Apr '20 16% 250 days 16%

Task Split Inactive Task Duration-only Finish-only Critical

Project: CONST Flag1 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Date: 22 Jan '2 Flag2 Summary Inactive Summary Manual Summary External Milestone Progress

Flag3 Project Summary Manual Task Start-only Deadline Manual Progress

Page 1
CONSTRUCTION OF PATENGA CONTAINER TERMINAL WHARF JETTY
OWNER: 34 ENGINEER CONSTRUCTION BRIGADE
CONSTRACTOR: CRBC‐EEL CONSORTIUM

ID Task Task Name WBS Start Duration Finish % Complete


Mode Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
38 Riprap Work at Jetty Area H.4 28 Aug '19 250 days 03 May '20 14% 250 days 14%

39 PILE CAP CASTING (INCLUDED EMBEDDED PART) I 21 Aug '19 287 days 02 Jun '20 7%


40 Bay‐A I.1 28 Aug '19 69 days 04 Nov '19 49% 69 days 49%

41 Bay‐B I.2 21 Aug '19 59 days 18 Oct '19 69% 59 days 69%

42 Bay‐C I.3 05 Oct '19 55 days 28 Nov '19 0% 55 days 0%

43 Bay‐D I.4 08 Nov '19 55 days 01 Jan '20 0% 55 days 0%

44 Bay‐E I.5 25 Nov '19 55 days 18 Jan '20 0% 55 days 0%

45 Bay‐F I.6 16 Dec '19 55 days 08 Feb '20 0% 55 days 0%

46 Bay‐G I.7 04 Jan '20 55 days 27 Feb '20 0% 55 days 0%

47 Bay‐H I.8 20 Jan '20 55 days 14 Mar '20 0% 55 days 0%

48 OTHER STRUCTURAL WORK (PC GIRDER, CIS BEAM, BB etc.) I.9 28 Aug '19 280 days 02 Jun '20 5%


49 Installation of Precast Girder I.9.1 12 Sep '19 230 days 28 Apr '20 8% 230 days 8%

50 CIS Beam (without Embedded Part) I.9.2 27 Sep '19 250 days 02 Jun '20 2% 250 days 2%

51 Installation of Berthing Block I.9.3 27 Sep '19 250 days 02 Jun '20 2% 250 days 2%

52 CIS High Mast Foundation (i/c Embedded Part) I.9.4 28 Aug '19 235 days 18 Apr '20 14% 235 days 14%

53 CIS Slab I.9.5 27 Sep '19 250 days 02 Jun '20 2% 250 days 2%

54 Installation of Precast Slab I.9.6 06 Nov '19 210 days 02 Jun '20 0% 210 days 0%

55 CONSTRUCTION OF CIS SURFACE SLAB (I/C EMBEDDED PART) &  J 13 Jun '19 372 days 18 Jun '20 7%


CURB
56 Bay‐A J.1 13 Jun '19 25 days 07 Jul '19 100% 25 days 100%

57 Bay‐B J.2 17 Dec '19 25 days 10 Jan '20 0% 25 days 0%

58 Bay‐C J.3 11 Jan '20 25 days 04 Feb '20 0% 25 days 0%

59 Bay‐D J.4 05 Feb '20 25 days 29 Feb '20 0% 25 days 0%

60 Bay‐E J.5 01 Mar '20 25 days 25 Mar '20 0% 25 days 0%

61 Bay‐F J.6 26 Mar '20 25 days 19 Apr '20 0% 25 days 0%

62 Bay‐G J.7 20 Apr '20 25 days 14 May '20 0% 25 days 0%

63 Bay‐H J.8 15 May '20 25 days 08 Jun '20 0% 25 days 0%

64 Construciton of CIS Curb J.9 22 Dec '19 180 days 18 Jun '20 0% 180 days 0%

65 MISCELLANEOUS WORK K 20 Apr '20 65 days 23 Jun '20 0%


66 Installation of Fender K.1 30 Apr '20 45 days 13 Jun '20 0% 45 days 0%

67 Installation of Bollard K.2 20 May '20 25 days 13 Jun '20 0% 25 days 0%

68 Installation of QU Rail K.3 05 May '20 45 days 18 Jun '20 0% 45 days 0%

69 Installation of Ladder K.4 30 May '20 25 days 23 Jun '20 0% 25 days 0%

70 Installation of Railing K.5 25 May '20 25 days 18 Jun '20 0% 25 days 0%

71 Construction of Anchor Pit Cover K.6 20 Apr '20 60 days 18 Jun '20 0% 60 days 0%

72 Expansion Joint Work K.7 04 Jun '20 15 days 18 Jun '20 0% 15 days 0%

73 Colour Marking at Jetty Area K.8 17 Jun '20 7 days 23 Jun '20 0% 7 days 0%

74 Demobilization & Handover K.9 25 May '20 30 days 23 Jun '20 0% 30 days 0%

Task Split Inactive Task Duration-only Finish-only Critical

Project: CONST Flag1 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Date: 22 Jan '2 Flag2 Summary Inactive Summary Manual Summary External Milestone Progress

Flag3 Project Summary Manual Task Start-only Deadline Manual Progress