You got 58 of 72 possible points.


Your score was: 81 %

Question Results

Question: Score 1 of 1

On which organizational level do you maintain profit center accounting in SAP


S/4HANA?

Response:

Financial statement version

Controlling area

Operating concern

Company code

Question: Score 0 of 1

Which of the following objects can be selected in templates for activity-based


costing?
There are 2 correct answers to this question.

Response:

WBS element

Cost center/activity type

Internal order

Business process

https://www.erpprep.com/node/16254/myresults/1515616 1/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 0 of 1

For which revenue-carrying cost objects does the system perform results
analysis?
There are 3 correct answers to this question.

Response:

Internal order

Business processes

Work breakdown structure

Cost center

Customer service orders

Question: Score 1 of 1

Which customizing activity do you perform in overhead cost controlling?

Response:

Create value fields

Define company centers categories

Maintain costing variant parameters

Define cost center categories

Question: Score 0 of 1

In your company, you tend to go through many reorganizations leading to extra


master data maintenance work. Which grouping functionality can save you time
maintaining profit center groups?

Response:

Creating multi-dimension sets

Defining flexible hierarchies

https://www.erpprep.com/node/16254/myresults/1515616 2/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Copying groups with suffix

Configuring derivation rules

Question: Score 1 of 1

When you create a profit center, what company code(s) is it assigned to by


default?
Please choose the correct answer.

Response:

All company codes within the operating concern

All company codes within the controlling area

All company codes, irrespective of controlling area

All company codes where profit center is activated

Question: Score 1 of 1

In which module do you process profit center allocations in SAP S/4HANA?


Please choose the correct answer.

Response:

Profit Center Accounting

General Ledger Accounting

Cost Center Accounting

Product Cost Accounting

Question: Score 1 of 1

Which statement best describes a cost center standard hierarchy?


Please choose the correct answer.

Response:

https://www.erpprep.com/node/16254/myresults/1515616 3/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

It represents an organizational unit in SAP S/4HANA where the costs and revenues
are incurred and reported.

It is a structure to which all the cost centers within a controlling area are assigned.

It is grouped together with alternative hierarchies to represent decision control and


responsibility units.

It enables you to assign the same attributes to similar cost centers within a
controlling area.

Question: Score 1 of 1

You want to set up integrated planning for your internal orders. What do you
need to do?
There are 2 correct answers to this question.

Response:

Set the relevant indicator in the controlling area.

Set the relevant indicators in the CO version.

Set the relevant indicator in the planning profile of the order type.

Set the relevant indicator in the internal order master record.

Question: Score 1 of 1

You want to create cost centers for your company. What is the prerequisite to
building an organizational structure for overhead cost controlling?
Please choose the correct answer.

Response:

Functional area

Cost center categories

Cost center types

Standard hierarchy top node

https://www.erpprep.com/node/16254/myresults/1515616 4/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 1 of 1

You want to use a template to consider overhead during product costing. How do
you assign the template to your material?
Please choose the correct answer.

Response:

Using a special procurement type and an overhead group

Using an overhead group and an overhead key

Using an origin group and an overhead group

Using a profit center and an overhead key

Question: Score 1 of 1

Why would you use manual cost allocation in Controlling?


There are 2 correct answers to this question.

Response:

To correct secondary postings

To allocate costs using an allocation cycle

To run simple allocations of plan data

To run simple allocations of actual data

Question: Score 1 of 1

Which characteristic controls the eligible cost element categories for G/L
accounts in SAP S/4HANA?

Response:

Field status group

Account type

Account currency

https://www.erpprep.com/node/16254/myresults/1515616 5/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Account group

Question: Score 1 of 1

You are implementing SAP S/4HANA and you want to run analytical reports off a
single data model. Which statement best describes reporting in SAP S/4HANA?
Please choose the correct answer.

Response:

Reporting on data is available in real-time at every level of detail.

Reporting analytical data is always done in a business warehouse system.

Reporting can be either broad and deep for analysis, or speedy and simple, but not
both.

Reporting on data in real time is difficult, and complex to design.

Question: Score 1 of 1

What values flow from Sales and Distribution billing to costing-based


Profitability Analysis?
There are 2 correct answers to this question.

Response:

Sales deductions

Revenue

Maintenance overhead costs

Accrued production overhead

Question: Score 1 of 1

You want to run an assessment cycle in Profitability Analysis to allocate cost


center costs during period-end closing for your organization.

Which of the following objects is part of the assessment cycle?


Please choose the correct answer

Response:
https://www.erpprep.com/node/16254/myresults/1515616 6/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Template

PA transfer structure

Tracing factor

Cycle iteration

Question: Score 1 of 1

Which default values can you configure for the product cost collector?
There are 2 correct answers to this question.

Response:

Results Analysis (RA) key

Costing variant for preliminary costing

Results Analysis (RA) version

Variance variant

Question: Score 1 of 1

In the Product Cost by Order component, what does the system calculate
depending on the order status?
Please choose the correct answer.

Response:

WIP at actual costs or variances

WIP at planned costs or variances

Both WIP and variances or only variances

WIP at target costs or variances

Question: Score 1 of 1

https://www.erpprep.com/node/16254/myresults/1515616 7/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

What must the referenced cost estimate and the receiving cost estimate have in
common?
Please choose the correct answer.

Response:

The quantity structure

The company codes

The plant

The cost component structure

Question: Score 1 of 1

Which activities can you perform while you create cost center hierarchies?
There are 2 correct answers to this question.

Response:

Create a cost center without specifying a standard hierarchy.

Assign a standard hierarchy to several controlling areas.

Append nodes and cost centers to a node of the standard hierarchy.

Reassign a cost center to another node of the standard hierarchy.

Question: Score 1 of 1

You need to assign a company code to a controlling area. Which settings must be
identical for both organizational objects?
There are 2 correct answers to this question.

Response:

Operational Posting period

Fiscal year variant

Currency

Operational Chart of accounts

https://www.erpprep.com/node/16254/myresults/1515616 8/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 0 of 1

Which objects do you use when you assign costs and revenue to the value fields
in costing-based CO-PA?

Response:

Transfer structure

Overhead group

Allocation structure

Allocation template

Question: Score 1 of 1

Which functionalities can create primary cost component splits?


There are 2 correct answers to this question.

Response:

Cost center/activity type price calculation

Execution of the assessment cycles

Settlement of internal orders

Business processes price calculation

Question: Score 1 of 1

A profit center standard hierarchy contains all profit centers that are assigned to
which organizational unit?
Please choose the correct answer.

Response:

Plant

Operating concern

https://www.erpprep.com/node/16254/myresults/1515616 9/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Client

Controlling area

Question: Score 1 of 1

How does the system derive the requirement type from the material master
data?
There are 2 correct answers to this question.

Response:

MRP group -> strategy group -> planning strategy -> requirements type

Strategy group -> planning strategy -> requirements class -> requirements type

MRP group requirements class -> planning strategy -> requirements type

Strategy group -> planning strategy -> requirements type

Question: Score 0 of 1

Which process determines the target costs of the cost object in a product cost by
order scenario?

Response:

Work in progress (WIP) calculation

Variance calculation

Accrual calculation

Actual costs calculation

Question: Score 0 of 1

You want to set up budget availability control for your projects and internal
orders. What can you check using budget availability control?
There are 2 correct answers to this question

Response:

https://www.erpprep.com/node/16254/myresults/1515616 10/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

The availability of funds according to tolerance limits

The availability of funds in object currency

The availability of funds on period level

The availability of funds using overall plan value

Question: Score 1 of 1

Which receiver must be allowed in the settlement profile of a product cost


collector?
Please choose the correct answer.

Response:

Material

Business process

Cost center

Order

Question: Score 0 of 1

How can you configure cycles for period-end allocation?


There are TWO correct answers for this question

Response:

Define allocation for the same cost center in multiple segments

Create cycles that iterate with each other

Assign several segments to a cycle

Use different allocation rules within one segment

Question: Score 0 of 1

https://www.erpprep.com/node/16254/myresults/1515616 11/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

You have implemented Product Cost by Sales Order in conjunction with revenue-
based results analysis in your organization. For a particular sales order item, you
have the following:

- Plan revenue = 3000


- Plan costs = 2000
- Actual revenue = 1200
- Actual costs = 1000

What data does the system calculate during results analysis?


Please choose the correct answer.

Response:

Revenue = 1200; Cost of sales = 800; Reserve = 200

Revenue = 1200; Cost of sales = 1000; WIP = 200

Revenue = 1200; Cost of sales = 1000; Reserve = 200

Revenue = 1200; Cost of sales = 800; WIP = 200

Question: Score 1 of 1

Which costs exist in SAP S/4HANA?


There are TWO correct answers for this question

Response:

Primary costs with G/L account

Secondary costs without G/L account

Primary costs without G/L account

Secondary costs with G/L account

Question: Score 1 of 1

What are some of the characteristics of SAP Core Data Services (CDS) views?
There are 3 correct answers to this question.

Response:

CDS views have no latency.

https://www.erpprep.com/node/16254/myresults/1515616 12/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

CDS views are considered system modifications.

CDS views support authorizations.

CDS views duplicate data for reporting efficiencies.

CDS views have ready-to-use content.

Question: Score 1 of 1

Which parameters are controlled by the costing type in a costing variant?


There are 2 correct answers to this question.

Response:

Save with date key

Costing sheet

Price for materials

Price updates

Question: Score 1 of 1

How can you populate local variables in Profitability Analysis reports?


Please choose the correct answer.

Response:

By Business Add-In

By user exit

By populating from user parameters

By user entry during report execution

Question: Score 1 of 1

What are some of the characteristics of Profit Center Accounting in SAP


S/4HANA?
https://www.erpprep.com/node/16254/myresults/1515616 13/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

There are 2 correct answers to this question.

Response:

It is possible to derive the profit center from the segment in configuration.

It can be used with period and/or cost of sales accounting.

It can be used in the settlement rule for internal orders.

It is integrated in the universal journal.

Question: Score 1 of 1

To which objects do you settle values of the results analysis?


There are TWO correct answers for this question

Response:

Cost center

Profit center

Profitability segment

Segment

Question: Score 1 of 1

In which SAP S/4HANA components can you report the results of the results
analysis?
There are 3 correct answers to this question.

Response:

Financial accounting

Profitability analysis

Profit center accounting

Sales and distribution

Inventory management
https://www.erpprep.com/node/16254/myresults/1515616 14/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 1 of 1

You define rules in a status profile and assign the profile to your internal order
type. What do you use the status profile for?
There are 3 correct answers to this question.

Response:

To permit or forbid specific transactions

To set the initial status as Created or Released

To activate the CO partner update

To define the user status

To define users for the order

Question: Score 1 of 1

You want to maintain a cost component structure. What can you determine for
each cost component?
There are 3 correct answers to this question

Response:

Relevance of cost component to results analysis

Assignment of cost component to calculation base for overheads in costing sheet

Relevance of cost component to inventory valuation

Assignment of cost component to cost component group

Relevance of cost component to goods manufactured

Question: Score 1 of 1

What are some of the objectives of Profitability Analysis?


There are 2 correct answers to this question.

Response:
https://www.erpprep.com/node/16254/myresults/1515616 15/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Provide the company with a detailed view of its financial statements by


responsibility units.

Allow the company to determine if the sales force achieved their contribution
margin goals.

Allow the company to determine standard costs and revenues according to the
period accounting method.

Provide the company with information on the performance of its market segments.

Question: Score 0 of 1

You want to understand why costs are collected on sales order item level. What
do you need to check in the configuration?
There are 3 correct answers to this question.

Response:

Requirement type

Requirements class

Valuation variant

Costing type

Account assignment category

Question: Score 1 of 1

What does the internal order settlement profile define?


There are THREE correct answers for this question

Response:

The valid receivers

The template allocation

The accounting document type

Whether commitment management is necessary

https://www.erpprep.com/node/16254/myresults/1515616 16/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Whether settlement is necessary

Question: Score 1 of 1

Which statement best describes the Query Browser for reporting?


Please choose the correct answer.

Response:

It is a strategic analytical tool in SAP S/4HANA.

It is available as an additional license product in SAP S/4HANA.

It is a design studio app that comes as standard SAP Fiori content.

It is a desktop browser that integrates with SAP S/4HANA.

Question: Score 0 of 1

Which of the following are typical activities of the sales planning phase in SAP
S/4HANA?
There are TWO correct answers for this question

Response:

Manual entry of data

Bottom-up distribution

Transfer of GL account data

Top-down distribution

Question: Score 1 of 1

Which of the following statements best describe Product Cost by Order?


There are 2 correct answers to this question.

Response:

It is used when controlling by individual production lots or discrete quantities is


needed.

https://www.erpprep.com/node/16254/myresults/1515616 17/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

It is recommended for products with a long production time.

It is used when you perform repetitive manufacturing.

It is used when full cost traceability is needed.

Question: Score 1 of 1

Which of the following controls can you set when you determine a characteristic
derivation?
There are 3 correct answers to this question.

Response:

Conditions for execution

System response when unsuccessful

Display authority

Valuation calculation

Overwriting authority

Question: Score 1 of 1

Which controls can you set when you determine a characteristic derivation?
There are 3 correct answers to this question.

Response:

Display authority

Conditions for execution

Valuation calculation

System response when unsuccessful

Overwriting authority

https://www.erpprep.com/node/16254/myresults/1515616 18/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 0 of 1

What do you use to map the primary cost component split to the production cost
component structure?

Response:

Transfer structure

Assignment scheme

Cost Component groups

Allocation structure

Question: Score 1 of 1

Which object can you select for reporting in costing-based Profitability Analysis,
and NOT in account-based Profitability Analysis?
Please choose the correct answer.

Response:

Cost element

Company code

Period/year

Record type

Question: Score 0 of 1

Which parameters can you enter when you create a costing run?
There are THREE correct answers for this question

Response:

Transfer control

Costing version

Costing variant

https://www.erpprep.com/node/16254/myresults/1515616 19/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Valuation variant

Production version

Question: Score 1 of 1

During posting, from which object does the system first derive the profit center
if the profit center is NOT directly assigned to a network activity?

Response:

Dummy profit center

WBS element

Network header

Project definition

Question: Score 0 of 1

You want to enable WIP calculation in Product Cost by Period. What do you need
to configure?
Please choose the correct answer.

Response:

Valuation variant

Variance variant

Settlement profile

Profitability Analysis (PA) transfer structure

Question: Score 0 of 1

Which currency types can you use for costing-based CO-PA?


There are TWO correct answers for this question

Response:

https://www.erpprep.com/node/16254/myresults/1515616 20/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Operating concern currency

Controlling area currency

Group currency

Company code currency

Question: Score 1 of 1

At what level do you create the structure of the operating concern?


Please choose the correct answer.

Response:

Controlling area level

Company code level

Client level

Sales organization level

Question: Score 1 of 1

You want to determine which operations of the routing should be considered in a


product cost calculation. How do you do this?
There are 2 correct answers to this question.

Response:

By marking the cost indicator in the control key assigned to the operation

By assigning a cost center to the work center in the operation

By marking the Relevance to Costing indicator in the operation

By defining a usage key in the header of the routing

Question: Score 1 of 1

https://www.erpprep.com/node/16254/myresults/1515616 21/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Where can you find actual transaction data of account-based CO-PA in SAP
S/4HANA?

Response:

BSEG

CE1XXXX

COEJ

ACDOCA

Question: Score 1 of 1

Where can you adjust the automatic account assignment?


There are TWO correct answers for this question

Response:

Substitution (TA: GGB1)

Cost center (TA: KS01)

Default account assignment (TA: OKB9)

G/L account (TA: FS00)

Question: Score 1 of 1

Which are levels of internal order planning?


There are TWO correct answers for this question

Response:

Integrated planning

Primary and secondary cost and revenue planning

Group costing

Overall planning

https://www.erpprep.com/node/16254/myresults/1515616 22/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 1 of 1

You want to define requirement levels for users for the authorization check in
Profitability Analysis reporting. Which requirement level would you set to enable
user access to all the interactive drilldown functions?
Please choose the correct answer

Response:

1 - Level 1

3 - ALL

2 - Level 2

0 - ALL

Question: Score 1 of 1

For which objects can you revaluate activities and business processes at actual
prices?
There are THREE correct answers for this question

Response:

Profitability segments

Profit centers

Work centers

Cost centers

Work breakdown structure elements

Question: Score 1 of 1

Which object controls the tiles a business user can assign to their SAP Fiori
launchpad?
Please choose the correct answer.

Response:

App library

https://www.erpprep.com/node/16254/myresults/1515616 23/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Tile catalog

Tile group

App finder

Question: Score 1 of 1

You have activated budget availability control for an internal order and entered
an overall budget of 10000. Actuals of 10000 were posted for this internal order
in the current year.

How is that possible?


There are 2 correct answers to this question.

Response:

The purchase order was entered in a different year than the budget.

The purchase order has NOT generated a budget document yet.

The cost element is exempted from budget availability control

The difference of 1000 is within the tolerance limits defined in the configuration.

Question: Score 1 of 1

Which customizing do you use for calculating work in progress (WIP)?


There are THREE correct answers for this question

Response:

Settlement profile table

Assignment table

Allocation structure table

Posting rule table

Update table

https://www.erpprep.com/node/16254/myresults/1515616 24/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Question: Score 1 of 1

Which object can you configure t offset overhead surcharges for a cost object?
There are THREE correct answers for this question

Response:

Cost center

Profit center

Internal order

Business process

Profitability segment

Question: Score 1 of 1

Which of the following values can be calculated using results analysis?


There are 3 correct answers to this question.

Response:

Cost of sales

Gross margin

Cost of goods manufactured

Work in progress

Reserves for unrealized costs

Question: Score 1 of 1

Which are mandatory attributes, when you create an operating concern with
costing-based and account-based CO-PA?
There are TWO correct answers for this question

Response:

Fiscal year variant

Company code currency in costing-based CO-PA


https://www.erpprep.com/node/16254/myresults/1515616 25/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Second period type

Operating Concern Currency

Question: Score 1 of 1

Which of the following statements are applicable to automatic account


assignment in SAP S/4HANA?
There are 2 correct answers to this question.

Response:

It can be overwritten in the application.

It can be defined for postings on general ledger accounts of secondary costs type.

It can be defined for postings on general ledger accounts of primary costs type.

It takes precedence over validation and substitution.

Question: Score 1 of 1

You want to create alternative plan versions for your controlling area, in
addition to version 000. What would you use additional CO versions for?
There are 2 correct answers to this question.

Response:

To store different plan data

To store different budget data

To store parallel valuation

To store actual-plan variance

Question: Score 1 of 1

You use a production order with Product Cost by Period and you entered a
results analysis key and variance key. How does the system calculate variances

https://www.erpprep.com/node/16254/myresults/1515616 26/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

in Product Cost by Period?


Please choose the correct answer.

Response:

Variances = Actual costs - Delivery value - WIP

Variances = Target costs - Delivery value

Variances = Actual costs - Delivery value

Variances = Target costs - Delivery value - WIP

Question: Score 1 of 1

What can you use to difference two or more cost estimates for the same
material?
There are TWO correct answers for this question

Response:

Valuation variant

Transfer control

Costing version

Costing variant

Question: Score 1 of 1

You post an expense line in an accounting document and enter an internal order
and a cost center as the account assignments. After posting, the system allows
you to settle the posted values from the internal order.

Which settings do the cost center and internal order have?


Please choose the correct answer.

Response:

Statistical internal order


Real cost center

Real internal order


Statistical cost center

https://www.erpprep.com/node/16254/myresults/1515616 27/28
4/15/2020 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates - Full | ERPPrep

Real internal order


Real cost center

Statistical internal order


Statistical cost center

Question: Score 1 of 1

Which object do you configure to reuse material cost estimate for the costing
process?

Response:

Quantity structure control

Valuation variant

Group costing

Transfer control

Money Back Guarantee Testimonial FAQs Privacy Policy Terms and Conditions About Us Join Us
Contact Us

https://www.erpprep.com/node/16254/myresults/1515616 28/28

You might also like