Professional Documents
Culture Documents
AL SAHLA Cargo Manual PDF
AL SAHLA Cargo Manual PDF
AL SAHLA Cargo Manual PDF
CARGO OPERATING MANUAL Section 2: Properties of LNG 3.2.2a DACS Operator Station Panel
3.2.2b Input Panel
LIST OF CONTENTS 3.2.3a DACS Example Screen Display
2.1 Properties of LNG
ISSUE AND UPDATE CONTROL 3.2.3b Valve Symbols
2.1.1 Physical Properties and Composition of LNG 3.2.3a Pump and Motor Symbols
equipment SYMBOLS AND COLOUR SCHEME
Illustrations 3.2 4a Extension Alarm Control Panel System Architecture
ELECTRICAL AND INSTRUMENTATION SYMBOLS 3.2 4b Watch Call Panels
international gas code 2.1.1a Physical Properties of LNG
INTRODUCTION 2.1.1b Composition of Typical LNG
2.1.1c Variation of Boiling Point of Methane with Pressure 3.3 Custody Transfer System (CTS)
2.1.1d Properties of Methane 3.3.1 Radar Primary System (Radar Gauges and Custody
Section 1: Design Concept of the Vessel 2.1.1e Relative Density of Methane and Air Transfer System)
3.3.2 Float Level Gauge
1.1 Principal Particulars 3.3.3 Independent High Level Alarm System
2.2 Characteristics of LNG
1.1.1 Principal Particulars of the Ship 3.3.4 Trim and List Indicator
2.2.1 Flammability of Methane, Oxygen and Nitrogen Mixtures 3.3.5 Loading Computer
1.1.2 Principal Particulars of Cargo Equipment and Machinery
2.2.2 Supplementary Characteristics
1.1.3 General Arrangement Illustrations
1.1.4 Tanks Capacity Plans Illustrations
3.1.1a Radar Gauge System
Illustrations 2.2.1a Flammability of Methane, Oxygen and Nitrogen Mixtures 3.3.1b Cargo Tank Level
2.2.2a Structural Steel Ductile to Brittle Transition Curve 3.3.1c Certificate of Loading
1.1.3a General Arrangement
1.1.3b Accommodation Deck D and Navigation Deck 3.3.1d Example of Custody Transfer Data (Certificate of
Arrangement 2.3 Health Hazards Measurements)
1.1.3c Accommodation Deck C Arrangement 3.3.1e CTS Flow Diagrams
1.1.3d Accommodation Deck B Arrangement Illustrations 3.3.2a Whessoe Gauge System
1.1.3e Accommodation Deck A Arrangement 3.3.2b Whessoe Float Level Gauge
2.3a Methane Safety Card 3.3.3a High Level and Overfill Alarm System
2.3b Nitrogen Safety card 3.3.4a Trim and List Indicator
1.2 Rules and Regulations 3.3.5a Loading Computer Screen Shots
3.3.5b Loading Computer Screen Shots
Illustrations
7.1a Interbarrier Space Purge
Details of each section are given in the first column of the issue and update Illustrations
control table. The table thus forms a matrix into which the dates of issue of the 1.3.1a Cargo Tank Lining Reinforcement March 2009
original document and any subsequent updated sections are located. 1.3.2a Membrane Cargo Containment (GTT Mark III) March 2009
1.3.2b Triplex Membrane March 2009
The information and guidance contained herein is produced for the assistance 1.3.2c
Interbarrier Space (IBS) - Insulation Space (IS)
March 2009
of certificated officers who by virtue of such certification are deemed Flat Panel Junction
competent to operate the vessel to which such information and guidance refers. 1.3.2d Pump Column Base Support March 2009
Any conflict arising between the information and guidance provided herein and 1.3.2e IBS IS Section of Longitudinal Corner March 2009
the professional judgement of such competent officers must be immediately 1.3.2f Hull Steel Grades March 2009
resolved by reference to the Technical Operations Office. Text
Hazardous Areas and Gas Dangerous Zone
1.4 March 2009
Plan
Illustrations
1.4a Gas Hazard Area Plan March 2009
Text
2.1 Properties of LNG March 2009
2.1.1 Physical Properties and Composition of LNG March 2009
Illustrations
2.1.1a Physical Properties of LNG March 2009
2.1.1b Composition of Typical LNG March 2009
Variation of Boiling Point of Methane with
2.1.1c March 2009
Pressure
2.1.1d Properties of Methane March 2009
Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3
2.1.1e Relative Density of Methane and Air March 2009 3.3.3 Independent High Level Alarm System March 2009 4.4 Cargo Compressors March 2009
Text 3.3.4 Trim and List Indicator March 2009 4.4.1 High Duty Compressor March 2009
2.2 Characteristics of LNG March 2009 3.3.5 Loading Computer March 2009 Illustrations
Flammability of Methane, Oxygen and Nitrogen Illustrations 4.4.1a No.1 HD Compressor Screen Shot March 2009
2.2.1 March 2009
Mixtures 3.1.1a Radar Gauge System March 2009 Text
2.2.2 Supplementary Characteristics March 2009 3.3.1b Cargo Tank Level March 2009 4.5 Boil-Off/Warm-Up Heaters March 2009
Illustrations 3.3.1c Certificate of Loading March 2009 4.5.1 High Duty and Boil-Off Gas Heaters March 2009
Flammability of Methane, Oxygen and Nitrogen Example of Custody Transfer Data (Certificate 4.5.2 Vent Gas Heater March 2009
2.2.1a March 2009 3.3.1d March 2009
Mixtures of Measurements) Illustrations
Structural Steel Ductile to Brittle Transition 3.3.1e CTS Flow Diagrams March 2009 4.5.1a No.1 HD Compressor Screen Shot March 2009
2.2.2a March 2009
Curve 3.3.2a Whessoe Gauge System March 2009 4.5.1b Gas Management Screen Shot March 2009
2.3 Health Hazards March 2009 3.3.2b Whessoe Float Level Gauge March 2009 4.5.2a Vent Gas Control Screen Shot March 2009
Illustrations 3.3.3a High Level and Overfill Alarm System March 2009 4.6 LNG Vaporiser March 2009
2.3a Methane Safety Card March 2009 3.3.4a Trim and List Indicator March 2009 Illustrations
2.3b Nitrogen Safety card March 2009 3.3.5a Loading Computer Screen Shots March 2009 4.6a LNG Vaporiser Screen Shot March 2009
3.1 Cargo Control Room Arrangement March 2009 3.3.5b Loading Computer Screen Shots March 2009 4.7 Reliquefaction Plant March 2009
Illustrations Text Illustrations
3.1a Cargo Control Room Arrangement March 2009 4.1 Cargo Manifold March 2009 4.7a Reliquefaction System March 2009
3.1b Cargo Control Console March 2009 4.1.1 Cargo Manifold System March 2009 4.7b Pre-cooler Assembly March 2009
Text 4.1.2 Cargo Strainers March 2009 4.7c Reliquefaction in Free-Flow Mode March 2009
3.2 Main Machinery Control System March 2009 Illustrations 4.7d Cold Box With Separator March 2009
Distributed Alarms and Control System 4.1.1a Cargo Manifold System March 2009 4.7e Reliquefaction in Normal Operating Mode March 2009
3.2.1 March 2009
Overview 4.1.2a Cargo Strainer March 2009 Reliquefaction Plant Fresh Water Cooling
4.7f March 2009
3.2.2 DACS Operator Station March 2009 Text System
3.2.3 Screen Displays March 2009 4.2 Cargo Piping System March 2009 4.7g Reliquefaction Plant (No.1 Compander in use) March 2009
3.2.4 Extension Alarm System March 2009 4.2.1 Cargo Piping March 2009 4.7h Reliquefaction Nitrogen Compander March 2009
Illustrations 4.2.2 Cargo Pipe Insulation March 2009 4.7i Reliquefaction Plant Cold Box and Separator March 2009
Distributed Alarms and Control System Illustrations 4.7j Nitrogen Booster Compressors March 2009
3.2.1a March 2009
Overview Cargo Piping System (With Reliquefaction 4.7k Nitrogen Compander Lubricating Oil System March 2009
4.2.1a March 2009
Distributed Alarms and Control System Plant) 4.7l Cause and Effect Page 1 of 3 March 2009
3.2.1b March 2009
Overview 4.2.1b Cargo Piping System March 2009 4.7m Cause and Effect Page 2 of 3 March 2009
Distributed Alarms and Control System 4.2.1c No.4 Cargo Tank Arrangement March 2009 4.7n Cause and Effect Page 3 of 3 March 2009
3.2.1c March 2009
Overview 4.2.1d Spiral-Wound Jointing March 2009 4.8 Nitrogen Generator March 2009
Distributed Alarms and Control System 4.2.2a Pipe Insulation March 2009 Illustrations
3.2.1d March 2009
Overview Text 4.8a Nitrogen Generator Screen Shot March 2009
3.2.2a DACS Operator Station Panel March 2009 4.3 Cargo Pumps March 2009 4.8b Nitrogen Generator March 2009
3.2.2b Input Panel March 2009 4.3.1 Main Cargo Pumps March 2009 Text
3.2.3a DACS Example Screen Display March 2009 4.3.2 Stripping/Spray Pumps March 2009 4.9 Inert Gas System March 2009
3.2.3b Valve Symbols March 2009 4.3.3 Emergency Cargo Pump March 2009 4.9.1 System Description March 2009
3.2.3a Pump and Motor Symbols March 2009 Illustrations 4.9.2 Operation of the Main System March 2009
Extension Alarm Control Panel System 4.3.1a Main Cargo Pumps March 2009 Illustrations
3.2 4a March 2009
Architecture 4.3.1b Start One Cargo Pump Sequence March 2009 4.9.1a Inert Gas System in the Engine Room March 2009
3.2 4b Watch Call Panels March 2009 4.3.1c Start Two Cargo Pump Sequence March 2009 4.9.1b Inert Gas System on Deck March 2009
Text 4.3.2a Stripping/Spray Pumps March 2009 4.9.1c Oxygen Analyser March 2009
3.3 Custody Transfer System (CTS) March 2009 4.3.2b Spray Pump Start Sequence March 2009 4.9.2a Inert Gas Generator Touch Screen Control Panel March 2009
Radar Primary System (Radar Gauges and 4.3.3a Emergency Cargo Pump March 2009 4.9.2b Inert Gas Generator Sea Water Supply System March 2009
3.3.1 March 2009
Custody Transfer System) Text 4.9.2c Inert Gas Generator Dryer Control Panel March 2009
3.3.2 Float Level Gauge March 2009
Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3
Fixed Gas Sampling and Gas Detection 4.13.2c Cargo Tank Pressure Table March 2009 5.4.5 Fire Detection System March 2009
4.10 March 2009
Systems 4.13.3a Typical Pipeline Relief Valve March 2009 Illustrations
Illustrations Text 5.4.1a Fire Hydrant System in the Engine Room March 2009
4.10a SW2020 Gas Sampling Panels March 2009 Ballast Level and Ship’s Draught Gauging 5.4.1b Deck Fire Main System March 2009
4.14 March 2009
4.10b Gas Detection System March 2009 System 5.4.1c Accommodation Area Fire Main System March 2009
4.10c Deck Area Gas Detection System March 2009 4.14.1 Ballast Piping System March 2009 5.4.1d Emergency Fire Pump Arrangement March 2009
4.10d Cargo Area Gas Detection System March 2009 4.14.2 Remote Level and Draught Indicating System March 2009 5.4.2a Water Spray System March 2009
4.10e CS3000 Gas Detection Panels March 2009 4.14.3 Ballast Exchange System March 2009 5.4.2b Fire Main System in the Engine Room March 2009
4.10f Fire and Gas Detection Screen Shot March 2009 Illustrations 5.4.3a Dry Powder System March 2009
4.10g A Deck Gas Detection Screen Shot March 2009 4.14.1a Ballast System March 2009 Typical FM200 Fire Extinguishing System and
5.4.4a March 2009
Text 4.14.1b Ballast Pumps Screen Shot March 2009 Instruction Plate
4.11 Valve Remote Control System March 2009 4.14.1c Ballast Tank Alarm Levels March 2009 5.4.4b NOVEC 1230 Fire Extinguishing Systems March 2009
Cargo, Ballast, Bunkering and Ship Side Valve 4.14.1d Ballast Operation Screen Shot March 2009 5.4.4c NOVEC 1230 Release Cabinet March 2009
4.11.1 March 2009
Remote Control System 4.14.2a Remote Level and Draught Indicating System March 2009 5.4.5a Fire Detection Panel March 2009
Illustrations 4.14.3a Ballast Exchange Flow Chart March 2009 5.4.5b Engine Room Fire Alarm Repeater Panel March 2009
4.11.1a Cargo Valve Remote Control System March 2009 4.14.3b Ballast Start Permissives Screen Shot March 2009 Reliquefaction Plant Fresh Water Cooling
5.5 March 2009
4.11.1b Flow Chart for Hydraulic Pump Operation March 2009 4.14.3c Ballast Exchange Planning Screen Shot March 2009 System
Ballast, Bilge and Fuel Oil Valve Remote 4.14.3d Ballast Exchange Operation Screen Shot March 2009 Illustrations
4.11.1c March 2009
Control System 5.1 Temperature Monitoring System March 2009 5.5a Cargo Machinery Fresh Water Cooling System March 2009
4.11.1d Hydraulic Power Pack Starter Panels March 2009 Illustrations 5.6 Passageways and Forward Bilge Systems March 2009
Text 5.1a Temperature Sensors in Secondary Barrier March 2009 Illustrations
4.12 Emergency Shutdown Systems March 2009 5.1b Cargo Tank No.1 Temperature Screen Shot March 2009 5.6a Passageways and Forward Bilge System March 2009
Emergency Shutdown and Tank Protection Interbarrier Space and Insulation Space Text
4.12.1 March 2009 5.2 March 2009
Systems Pressure Control 6.1 Insulation Space Pressurising March 2009
4.12.2 Pneumatic Emergency Shutdown System March 2009 Illustrations 6.1.1 Insulation Space Inerting March 2009
Illustrations Cargo Barrier Space Pressure Control Screen 6.1.2 In-Service Test March 2009
5.2a March 2009
4.12.1a Emergency Shutdown Block Diagram March 2009 Shot Illustrations
4.12.1b Emergency Shutdown System Architecture March 2009 Nitrogen Pressurisation and Control System 6.1.1a Nitrogen System March 2009
5.2b March 2009
4.12.1c Emergency Shutdown Control Panels (i) March 2009 (Tank No.5) Cargo Barrier Space Pressure Control Screen
6.1.1b March 2009
4.12.1d Emergency Shutdown Control Panels (ii) March 2009 Text Shot
Emergency Shutdown Panel on Cargo Control 5.3 Cofferdam Heating System March 2009 6.1.1c Insulation Spaces Evacuation March 2009
4.12.1e March 2009
Room Console 5.3.1 Cofferdam Heating and Control March 2009 Nitrogen Pressurisation and Control System
6.1.1d March 2009
4.12.1f Emergency Shutdown Screen Shot March 2009 5.3.2 Hull Ventilation March 2009 (Tank No.5)
4.12.1g Ship-Side Connector Box March 2009 Illustrations 6.1.2a IBS and IS Piping Arrangement on Liquid Dome March 2009
4.12.1h Emergency Shutdown System Telephone March 2009 5.3.1a Glycol Water Heater System March 2009 Text
4.12.2a Emergency Shutdown Pneumatic System March 2009 5.3.1b Cofferdam Heating System March 2009 6.2 Post Dry Dock and Pre-loading Operations March 2009
Control Flow Chart For Pneumatic Ship/Shore 5.3.1c Cofferdam Glycol Heater Screen Shot March 2009 6.2.1 Drying Cargo Tanks March 2009
4.12.2b March 2009
Link 5.3.1d Cofferdam Heating Control Screen Shot March 2009 6.2.2 Inerting Cargo Tanks March 2009
Text 5.3.2a Hull Dry-Air System March 2009 6.2.3 Gassing-Up Cargo Tanks March 2009
4.13 Cargo Relief Valves March 2009 5.3.2b Hull Ventilation March 2009 6.2.4 Cooling Down Cargo Tanks March 2009
4.13.1 Cargo Tank Relief Valves March 2009 Text Illustrations
4.13.2 Insulation Space Relief Valves March 2009 5.4 Fire Fighting Systems March 2009 6.2.1a Drying Cargo Tanks (Summer) March 2009
4.13.3 Pipeline Relief Valves March 2009 5.4.1 Engine Room and Deck Fire Main Systems March 2009 6.2.1b Drying Cargo Tanks (Winter) March 2009
Illustrations 5.4.2 Water Spray System March 2009 6.2.2a Inerting Cargo Tanks Prior to Gas Filling March 2009
4.13.1a Pressure Relief Valve Operation March 2009 5.4.3 Deck Dry Powder System March 2009 6.2.2b Inerting Cargo Tanks with Nitrogen March 2009
4.13.2a Pilot Operated Safety Relief Valve March 2009 FM200 and NOVEC 1230 Fire Extinguishing 6.2.3a Gassing-Up Cargo Tanks - Venting March 2009
5.4.4 March 2009
4.13.2b IBS and IS Pressure Control Table March 2009 Systems 6.2.3b Gassing-Up Cargo Tanks - To Shore March 2009
Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3 Item Issue 1 Issue 2 Issue 3
6.2.3c Gassing-Up Cargo Tanks - To GCU March 2009 6.5.6b Ballasting March 2009 LNG Liquid Leakage into the Interbarrier
7.2 March 2009
6.2.4a Cargo Plant Screen Shot March 2009 Text Spaces (IBS)
6.2.4b Initial Cooldown - Return to Shore March 2009 6.6 Ballast Passage March 2009 Illustrations
6.2.4c Cooldown - GCU March 2009 6.6.1 Ballast Voyage with Reliquefaction March 2009 7.2a LNG Liquid Leakage to IBS March 2009
Text 6.6.2 Cooling Down Cargo Tanks Prior to Arrival March 2009 7.2b Interbarrier Space Stripping March 2009
6.3 Loading and Deballasting March 2009 6.6.3 Sloshing Inside the Cargo Tanks March 2009 7.2c Portable Liquid Level Gauge March 2009
6.3.1 Preparations for Loading March 2009 Illustrations 7.3 Water Leakage to Insulation Space (IS) March 2009
6.3.2 Cargo Lines Cooldown March 2009 6.6.1a Ballast Voyage with Reliquefaction - Start March 2009 Illustrations
Loading Cargo with Vapour Return to Shore via 6.6.1b Ballast Voyage with Reliquefaction March 2009 7.3a Cofferdam/Insulation Space Bilge System March 2009
6.3.3 March 2009
the High Duty Compressor 6.6.1c Spraying During Ballast Voyage March 2009 7.3b Leakage Pipe March 2009
Draining and Inerting Manifold Pipes and 6.6.1d Ballast Voyage with Free-Flow March 2009 7.4 Emergency Cargo Pump Installation March 2009
6.3.4 March 2009
Loading Arms 6.6.2a Cooling Down Cargo Tanks Prior to Arrival March 2009 Illustrations
6.3.5 Deballasting March 2009 Text 7.4a Emergency Cargo Pump Davit Assembly March 2009
Illustrations 6.7 Pre Dry Dock Operations March 2009 7.4b Emergency Cargo Pump Installation Sequence March 2009
6.3.1a Preparations for Loading March 2009 6.7.1 Stripping and Line Draining March 2009 Text
6.3.2a Cargo Lines Cooling Down March 2009 6.7.2 Tank Warm-Up March 2009 7.5 Fire and Emergency Breakaway March 2009
6.3.2b Cooling Down and Loading Flow Chart March 2009 6.7.3 Gas Freeing March 2009 7.6 Ship-to-Ship Transfer March 2009
6.3.3a Loading With Vapour Return to Shore March 2009 6.7.4 Aerating March 2009 7.6.1 General Safety March 2009
6.3.3b Cargo Loading March 2009 Illustrations 7.6.2 Pre-Mooring Preparations March 2009
6.3.4a Manifold - Shore Lines Draining March 2009 6.7.1a Stripping and Line Draining March 2009 7.6.3 Mooring March 2009
6.3.5a Deballasting March 2009 6.7.1b Manifold Draining March 2009 7.6.4 Transfer Operations March 2009
6.3.5b Deballasting - Educting March 2009 6.7.2a Tank Warming-Up March 2009 7.6.5 Unmooring March 2009
Text 6.7.3a Gas Freeing - At Sea or to Shore March 2009 7.7 Cold Spots on Inner Hull March 2009
Loaded Voyage with Boil-off Gas 6.7.3b Gas Freeing - Through the GCU March 2009 7.8 LNG Jettison March 2009
6.4 March 2009
Reliquefaction 6.7.3c Gas Freeing - Spray Line March 2009 Illustrations
Loaded Voyage with Boil-Off Gas 6.7.3d Gas Freeing - Machinery Room 1st Step March 2009 7.8a LNG Jettison March 2009
6.4.1 March 2009
Reliquefaction 6.7.3e Gas Freeing - Machinery Room 2nd Step March 2009 7.9 Vent Mast on Fire March 2009
Illustration 6.7.4a Aerating March 2009
Loaded Voyage with Boil-Off Gas Text
6.4.1a March 2009
Reliquefaction 6.8 One Tank Operations March 2009
Loaded Voyage with Boil-Off Gas 6.8.1 Warm-Up March 2009
6.4.1b March 2009
Reliquefaction - Excess BOG 6.8.2 Gas Freeing March 2009
Text 6.8.3 Aerating March 2009
6.5 Discharging March 2009 6.8.4 One Tank Drying/Inerting March 2009
6.5.1 Preparations for Discharging March 2009 6.8.5 One Tank Gassing-Up and Cooling Down March 2009
6.5.2 Liquid Line Cooldown Before Discharging March 2009 Illustrations
6.5.3 Arm Cooldown Before Discharging March 2009 6.8.1a One Tank Warming-Up - Step 1 March 2009
6.5.4 Discharging With Vapour Return From Shore March 2009 6.8.1b One Tank Warming-Up - Step 2 March 2009
6.5.5 Discharging Without Vapour Return From Shore March 2009 6.8.2a One Tank - Gas Freeing March 2009
6.5.6 Ballasting March 2009 6.8.3a One Tank - Aerating March 2009
Illustrations 6.8.4a One Tank - Drying March 2009
6.5.1a Preparations for Discharging March 2009 6.8.4b One Tank - Inerting March 2009
6.5.2a Liquid Line Cooldown Before Discharge March 2009 6.8.5a One Tank Gassing-Up - Venting/GCU March 2009
6.5.3a Arms Cooling Down Before Discharge March 2009 6.8.5b One Tank - Cooldown March 2009
6.5.4a Discharge With Vapour Return From Shore March 2009 7.1 LNG Vapour Leakage into Barrier Spaces March 2009
6.5.5a Discharge Without Vapour Return From shore March 2009 Illustrations
6.5.6a Ballast System Screen Shot March 2009 7.1a Interbarrier Space Purge March 2009
Nitrogen
Gate Valve Hydraulic Control Sounding Head Air Filter / Regulator Tank Penetration
(Deck Flush Type) Inert Gas
Gas Line
Butterfly Valve Hydraulic Control (Air) HB Fire Hose Box Duplex Strainer Blind (Blank) Flange
BOG
Screw-Down Non-Return Hydraulic Cylinder Rose Box Observation Glass Spool Piece Stripping* and Spray Line
Valve Type Actuator
Needle Valve Surface Valve Steam Trap Sight Glass Gear or Screw Type Pump Hydraulic Oil
Lubricating Oil
Safety / Relief Valve Vapour Control Valve Steam Trap with Strainer Drain Trap A Air Operated Pump
Saturated Steam
Self-Closing Spring Valve Breather Valve Hand Pump Steam Trap Foot Valve Condensate
Pressure Reducing Valve Deck Stand Overboard Discharge Pressure/Vacuum Marine Diesel Oil
Quick-Closing Valve
Relief Valve
Liquid Refrigerant
Three-Way Valve Manual Hydraulic Operated Discharge/Drain A Air Purge Tank Level Gauge Non-Return Ball Valve
Deck Stand
Gas Refrigerant
3-Way Cock Air Vent Pipe Flame Screen Hydrant Pressure Reducer Air Horn Fire/Deck Water
Sludge/Waste Oil
Ball Valve Float Type (Disk) Air Vent Silencer 3-Way Control Valve
Head without Fire Screen
Air
Electrical Signal
A Not Connected
Air Motor Driven Filling Cap Open Scupper
Crossing Pipe
Instrumentation
Rectifier Equipment
Battery Charger (Rectifier)
The safety of the ship depends on the care and attention of all on board. Most All illustrations that are referred to in the text are located either in-text where
General safety precautions are a matter of common sense and good housekeeping sufficiently small, or above the text, so that both the text and illustration are
and are detailed in the various manuals available on board. However, records accessible when the manual is laid open. When text concerning an illustration
Although this ship is supplied with shipbuilder’s plans and manufacturer’s show that even experienced operators sometimes neglect safety precautions covers several pages the illustration is duplicated above each page of text.
instruction books, there is no single document which gives guidance on through over-familiarity and the following basic rules must be remembered at
operating complete systems as installed on board, as distinct from individual all times. Where flows are detailed in an illustration these are shown in colour. A key of all
items of machinery. The purpose of this ‘one-stop’ manual is to assist, inform colours and line styles used in an illustration is provided on the illustration.
and guide competent ship’s staff and trainees in the operation of the systems • Never continue to operate any machine or equipment which
and equipment on board and to provide additional information that may not appears to be potentially unsafe or dangerous and always report
Details of colour coding used in the illustrations are given in the Mechanical
be otherwise available. In some cases, the competent ship’s staff and trainees such a condition immediately.
Symbols and Colour Scheme which is detailed on earlier pages in this Front
may be initially unfamiliar with this vessel and the information in this manual • Make a point of testing all safety equipment and devices Matter section.
is intended to accelerate the familiarisation process. It is intended to be used in regularly. Always test safety trips before starting any equipment.
conjunction with shipyard drawings and manufacturer’s instruction manuals, In particular, overspeed trips on auxiliary turbines must be Symbols given in the manual adhere to international standards and keys to the
bulletins, Fleet Regulations, the ship’s Captain’s and Chief Engineer’s Standing tested before putting the unit to work. symbols used throughout the manual are also given on previous pages in this
Orders, and in no way replaces or supersedes these publications, all of which Front Matter section.
take precedence over this manual. • Never ignore any unusual or suspicious circumstances, no
matter how trivial. Small symptoms often appear before a major
Information relevant to the operation of this vessel has been carefully collated in failure occurs. Notices
relation to the systems of the vessel and is presented in three on board volumes, • Never underestimate the fire hazard of petroleum products,
a CARGO OPERATING MANUAL, a DECK OPERATING MANUAL and a whether fuel oil or cargo vapour. The following notices occur throughout this manual:
MACHINERY OPERATING MANUAL.
• Never start a machine remotely from the cargo and engine
control room without confirming visually that the machine is WARNING
The vessel is constructed to comply with MARPOL 73/78. These regulations can
able to operate satisfactorily. Warnings are given to draw reader’s attention to operations where
be found in the Consolidated Edition, 1991 and in subsequent Amendments.
DANGER TO LIFE OR LIMB MAY OCCUR.
The information, procedures, specifications and illustrations in this manual In the design of equipment, protection devices have been included to ensure
have been compiled by WMT personnel by reference to shipyard drawings and that, as far as possible, in the event of a fault occurring, whether on the part of CAUTION
manufacturer’s publications that were made available to WMT and believed to the equipment or the operator, the equipment concerned will cease to function Cautions are given to draw reader’s attention to operations where
be correct at the time of publication. The systems and procedures have been without danger to personnel or damage to the machine. If any of these safety DAMAGE TO EQUIPMENT MAY OCCUR.
verified as far as is practicable in conjunction with competent ship’s staff under devices are bypassed, overridden or neglected, then the operation of any
operating conditions. machinery in this condition is potentially dangerous.
Note: Notes are given to draw reader’s attention to points of interest or to
supply supplementary information.
It is impossible to anticipate every circumstance that might involve a potential Description
hazard, therefore, warnings and cautions used throughout this manual are
provided to inform of perceived dangers to ship’s staff or equipment. In many The concept of this manual is to provide information to technically competent Safety Notice
cases, the best operating practice can only be learned by experience. ship’s officers, unfamiliar to the vessel, in a form that is readily comprehensible,
thus aiding their understanding and knowledge of the specific vessel. Special It has been recorded by International Accident Investigation Commissions
attention is drawn to emergency procedures and fire fighting systems. that a disproportionate number of deaths and serious injuries occur on ships
If any information in these manuals is believed to be inaccurate or incomplete,
each year during drills involving lifesaving craft. It is therefore essential that
the officer must use his professional judgement and other information available
The manual consists of a number of parts and sections which describe the all officers and crew make themselves fully conversant with the launching,
on board to proceed. Any such errors or omissions or modifications to the
systems and equipment fitted and their method of operation related to a retrieval and the safe operation of the lifeboats, liferafts and rescue boats.
ship’s installations, set points, equipment or approved deviation from published
operating procedures must be reported immediately to the company’s Technical schematic diagram where applicable.
Operations Office, who should inform WMT so that a revised document may be
issued to this ship and in some cases, others of the same class. The valves and fittings identifications and symbols used in this manual are the
same as those used by the shipbuilder.
Main Alternators
Manufacturer: HHI EES
No. of sets: 4
Capacity/rating: 6,600V, 3-phase, 60Hz, 3,800kW, 378A, 4,750kVA
0.8pf, 10-pole, IP44
Speed: 720 rpm
Cooling: Closed air circuit with water-cooled air cooler
Heating: 230V, 1,440W
Reliquefaction Plant
Cryogenic Heat Exchanger LNG Transfer Pumps Vent Gas Heater
Separator
Discharge pressure: 520kPa(g) Glycol Water Heaters
Pump speed: 3,540 rpm Steam Glycol Heaters
Manufacturer; Nordon Cryogenie SAS
Absorbed power: 1.38kW
Material: 5083 aluminium Manufacturer: DongHwa Entec
Installed power: 4.0kW
Volume capacity: 0.89m3 No. of sets: 2
NPSH: 0.2m with supercharger included in scope
Design pressure: 1.0/6.3/4.0MPa Type: Shell and tube
Design temperature: -196°C/+65ºC Capacity: 3.56m3
Pre-Cooler Model: BEU
Manufacturer: Deca
Nitrogen Companders
Heat exchanger medium: LNG/Methane Vapour Glycol Water Circulating Pumps
Manufacturer: Atlas Copco Energas
Heat exchange rate: 147kW
Type: GT032 N3 D0 + ETI 150MS Manufacturer: Shin Shin
Heat exchange surface: 105.37m2
Quantity: 2 No. of sets: 2
Capacity: 3650/41 litres (vapour/liquid)
Mass flow: 118,000kg/h Type: RVP100MH
Design pressure: 0.57MPa(g)
1st Stage compressor: 3.45MPa (design pressure) Capacity: 33m3/h at 410kPa
Design temperature: -196ºC/+80ºC
1st Stage compressor: 150ºC (design temperature) Motor rating: 11kW
1st Stage inter-cooler: 1,942kW (rated duty) Motor speed: 1800 rpm
1st Stage inter-cooler: 3.45MPa (design pressure)
Manufacturer: Sung Mi Co. Ltd, Korea Model: HGD-082-30 (davit), BWE-15-030/030 (winch)
Length: 17.0m Type: Hinged gravity Hydrostatic Units
Safe working load: 7,911kg Manufacturer: Hammar
Lowering speed: 78m/min, maximum (fully loaded) Type: H20
Pilot Access Doors
Hoisting speed: 3m/min (minimum)
Manufacturer: Sung Mi Co. Ltd, Korea Winch motor rating: 5.5kW
Type: Folding Type Pilot Door Breathing Air Compressor
Lowering height: 31m (maximum)
No. of sets: 2 Manufacturer: Bauer
Dimensions: 2.0m x 2.0m (coaming size) No. of sets: 1
Operating unit: Electric Hydraulic Rescue Boat and Davit Model:
Rescue Boat Capacity: 200 litre/minute
Pilot Ladder Reel Manufacturer: Fr. Fassmer GmbH & Co. KG Operating pressure: 300kg/cm2 and 200kg/cm2
Type/model: Rigid rescue boat, RR 4.2
Manufacturer: Sung Mi Co. Ltd, Korea
Length overall: 4.23m Self-Contained Breathing Apparatus
Type: Overhead Stowage Reel
Beam: 1.75m
No. of sets: 2 Manufacturer: Unitor
Height: 0.82m
Length overall: 17.0m Model: UNIPAK
Capacity: 6 persons Number on board: 8
Stepped length: 12.7m
Boat weight: 310kg (with equipment)
Operating unit: Electric hydraulic
Hoisting speed: 10-15m/min approximately
Hoisting load: 200kg Engine
Manufacturer: Tohatsu
Lifeboats Model: M 40 EPL
Type: Petrol outboard
Manufacturer: Hyundai Lifeboats Co., Ltd
Rating: 40hp
No. of sets: 2
Fuel tank capacity: Approximately 24 litres
Model: HDL85CF
Dimensions (LxBxDxH): 8.50m x 3.0m x 1.35m x 2.95m
No. of persons: 50
13 13
13
13 13
30 29 24
25
31 28 22 18 12
15
2
32 5
42 27 21 17 11
50 49 44
45 23 19 9
33 4
43 7
48 46 41 40 26 20
34 16 14 10
6 3 1
39
8
47 38
35
37 36
A.P 10 20 30 40 50 60 70 75 80 85 90 95 100 105 110 115 120 130 140 150 160 F.P
H H H
H H
H
Upper Deck
Up
Up
Dn
Dn Up
Up
Up
Dn
Up
Dn Up Up Up
Dn
Up
Up
H
H H H H H
Midship Section
Key
1. Fore Peak Void 21. No.3 Cargo Tank 41. Heavy Fuel Oil Serving Tank (Port and Starboard)
‘Compass’ Deck 2. Bosun Store 22. No.3 Trunk 42. Heavy Fuel Oil Bunker Tank (Port and Starboard)
‘Nav’ Deck 3. Forward Water Ballast Tank (Central) 23. No.4 Cofferdam 43. Cofferdam (Port and Starboard)
4. Bilge Well 24. Dry Powder Room 44. Low Sulphur Heavy Fuel Oil Bunker Tank
‘D’ Deck
5. Cleaning Locker 25. Cargo Gear Locker 45. Main Marine Diesel Oil Serving Tank (Starboard)
‘C’ Deck 6. Forward Heavy Fuel Oil Tank (Port and Starboard) 26. No.4 Water Ballast Tank (Port and Starboard) 46. Engine Room
‘B’ Deck 7. No.1 Cofferdam 27. No.4 Cargo Tank 47. Central Water Tank
‘A’ Deck
52 8. Forward Heavy Fuel Oil Pump Room 28. No.4 Trunk 48. Aft Peak Tank
and Emergency Fire Pump Room 29. Motor Room 49. Fresh Water Tank (Starboard) Principal Dimensions
‘Upper’ Deck 9. No.1 Cofferdam 30. Cargo Compressor Room 50. Steering Gear Room
10. No.1a Water Ballast Tank (Port and Starboard) 31. No.5 Tank 51. Lifeboat (42 Person) Length O.A 315.16m
11. No.1 Cargo Tank 32. No.5 Cargo Trunk 52. Trunk (Void) Length B.P 303.0m
12. No.1 Trunk 33. Pilot Door (Port and Starboard) 53. Cargo Tank
13. Vent Mast 34. No.5 Water Ballast Tank (Port and Starboard) 54. Water Ballast Tank Breadth Moulded 50.0m
53 14. No.1b Water Ballast Tank (Port and Starboard) 35. Low Sea Chest 55. Pipe Trunk Depth Moulded 27.0m
15. Light Post and Side Lights (Port and Starboard) 36. High Sea Chest 56. Water Ballast Tank Depth (Trunk) Moulded 35.1m
16. No.2 Water Ballast Tank (Port and Starboard) 37. Main Lubricating Oil Sump Tank Draught (Design) Moulded 12.0m
17. No.2 Cargo Tank 38. High Sea Chest Draught (Summer) Moulded 12.3m
18. No.2 Trunk 39. Heavy Fuel Oil Overflow Tank Draught (Scantling) 13.0m
19. No.3 Cofferdam 40. Heavy Fuel Oil Settling Tank (Port and Starboard)
54 55 56 20. No.3 Cargo Tank
Dn
1st Chief
Up Engineer’s Engineer’s
1st Bedroom Bedroom Chief
Engineer’s
Engineer’s
Day Room
Day Room
Engine Room Casing D Deck Lobby
Lobby
Electrical
Dn
and Pipe
Ducts
2nd Gas Engineer’s
Engineer Day Room
Cleaning
Gear
Locker
Gas Battery
Pilot
Night Engineer’s Room
Public
Pantry Bedroom
Toilet Dn Up Navigation Dn
Lobby Locker Wheelhouse
Clean
Linen 1st
2nd Locker Elevator Officer’s
Fan Condenser
Dn Officer Bedroom
Room Unit Room Elevator
Machinery Room
Up Public
Lobby Toilet
Locker
Owner 1st Officer’s
Up Day Room
Dn
Lobby Electrical
and Pipe Ducts
Captain’s
Chief Day
Officer’s Room
Day Room
Lobby Chief Captain’s Lobby
Officer’s Bedroom
Bedroom
Dn
C Deck
Lobby
Dn Up
Lobby
Spare Officers’ Fire Control
Officer (C) TV Room Station
Engine Room Casing C Deck
Electrician
Fan
Room Cargo
(Port) Control
Officers’ Dry
Room
Laundry Room
Dn
3rd Engineer
Cleaning
Locker Electrical
and Pipe Ducts
Gas
Combustion
Unit Training
Room
Dn Up
Telephone
Electrical
Booth
Equipment
Room
Rest
Spare Area
Officer (B)
Elevator
Up
Entertainment
Library
Spare
Officer (A) Conference
Dn
Room
Fan Electrical
Technical
Room and Pipe Ducts
Library
(Starboard)
Chief Public
Steward Toilet
Night
Pantry
Central
3rd Reception Office
Officer Room
Bonded
Store
Dn Up
B Deck
Engine Room Casing B Deck
Lobby
Up Dn
Dn
Dn
Oiler (D) Treatment/ Hospital Cadet (B) Cadet (A)
Dispensary
Oiler (E)
Electrical and
Fan Room (Port) Pipe Ducts
Crew’s Dry
Crew (P) Laundry Room Fitter
Up Dn
Oiler (C)
Locker Public Public
Crew’s Toilet Toilet
TV Room
Oiler (B)
Dn Up
Locker
Gymnasium
Oiler (A)
Elevator
Central
Cooling Fresh Water Electrical and
Expansion Tank Able Pipe Ducts
(Starboard) Messman
Seaman
Up Dn
(A)
Cleaning Gear
Locker
Cook (A)
Dn Up Dn
Lobby
A Deck
Engine Casing Room A Deck
Lobby
Cleaning Gear Locker Up
Dn
Dn Up Up
Locker Safety
Equipment
Gas Combustion Locker
Unit Fan Room Suez Suez Public Crew’s
Worker Worker Toilet Recreation
(4-P) (4-P) Room
Crew’s Distributed
Pantry Dn Up Alarm and
Control System
(DACS)
Cabinets
Galley Elevator
Up
Dn Officers’
Changing
Vent Vent Room
Public
Trunk Trunk
Toilet
Incinerator Waste
Oil Service Tank (Lower) Incinerator
Room Officers’
Officers’ Pantry
Incinerator Waste Mess Room Officers’
Oil Service Tank (Upper) Waste Officers’ Fire Recreation
Management Duty Equip’t Room
Room Mess Room Store
Dn
Up
Lobby Womens’
Changing Room
WATER BALLAST TANKS SG: 1.025 HEAVY FUEL OIL TANKS SG: 0.980
Compartment Location Capacities 100% Full Max. Compartment Location Capacities 95% Full Max.
Free Free
Frame Surface Frame Surface
Moment of Volume Volume Weight LCG VCG Moment
Volume Weight LCG VCG of Inertia
100% 100% from AP From BL Inertia 100% 90% 0.99 from AP From BL
m4 m 3 m3 mt m m m4
m3 mt m m
Forward WB Tank (C) 141 - 153 2571.7 2636.0 133.891 12.894 9816 Forward HFO Tank (P) 121 - 141 3007.4 2706.7 2679.6 121.439 18.032 3102
No.1A WB Tank (P) 116 - 121 2893.5 3006.8 103.425 12.186 3717 Forward HFO Tank (S) 121 - 141 3475.6 3111.8 3080.7 120.751 17.028 3367
No.1A WB Tank (S) 116 - 121 2893.5 3006.8 103.425 12.186 3717 HFO Bunker Tank (P) 55 - 67 608.2 547.4 541.9 -103.285 20.672 125
No.1B WB Tank (P) 111 - 116 4846.3 4967.5 86.625 11.862 9169 HFO Bunker Tank (S) 55 - 67 608.2 547.4 541.9 -103.285 20.672 125
No.1B WB Tank (S) 111 - 116 4846.3 4967.5 86.625 11.862 9169 HFO Settling Tank (P) 63 - 67 111.1 100.0 99.0 -99.500 14.446 42
No.2 WB Tank (P) 100 - 111 6350.1 6508.8 55.56 8.499 36840 HFO Settling Tank (S) 63 - 67 111.1 547.4 541.9 -103.285 20.672 42
No.2 WB Tank (S) 100 - 111 6350.1 6508.8 55.56 8.499 36840 HFO Service Tank (P) 59 - 63 94.8 100.0 99.0 -99.500 14.446 42
No.3 WB Tank (P) 89 - 100 6575.1 6739.5 11.962 8.298 40117 HFO Service Tank (S) 59 - 63 94.8 100.0 99.0 -99.500 14.446 42
No.3 WB Tank (S) 89 - 100 6575.1 6739.5 11.962 8.298 40117 Low Sulphur HFO Bunker 47 - 55 528.1 475.3 470.5 -110.672 19.324 83
No.4 WB Tank (P) 78 - 89 6574.9 6739.3- 32.062 8.299 40115 Tank (S)
No.4 WB Tank (S) 78 - 89 6574.9 6739.3- 32.062 8.299 40115 TOTAL 8621.3 7759.2 7681.6 64.615 17.919 6968
No.5 WB Tank (p) 67 - 78 5761.9 5905.9 -74.808 8.321 32206
No.5 WB Tank (S) 67 - 78 5761.9 5905.9 -74.808 8.321 32206
Aft Peak Tank (C) -6 - 17 3334.0 3417.3 -145.690 14.601 57401
TOTAL 71989.3 73788.9 12.283 9.950 391546
The cargo containment system consists of five double insulated cargo tanks
encased within the inner hull and situated in-line from forward to aft. The Void Area
containment system serves two purposes:
• To contain LNG cargo at cryogenic temperature (-163°C)
• To insulate the cargo from the hull structure
The spaces between the inner hull and outer hull are used for ballast and will Cofferdam
also protect the tanks in the event of an emergency situation, such as collision
or grounding. The ballast spaces around the cargo tanks are divided into two
double bottom wing tanks, port and starboard for each cargo tank. The double
bottom tanks extend to the side of the cargo tanks as far up as the underdeck
pipe passage.
The cargo tanks are separated from other compartments, and from each other,
by six transverse cofferdams which are all dry compartments. The LNG to
be transported is stored in the five cargo tanks numbered 1 to 5, from fore to
aft. All cargo tanks have an octagonal transverse section matching with the
supporting inner hull.
The materials used for the hull structure are designed to withstand varying
degrees of low temperature. At temperatures below their specified limits, these
steels will crystallise and embrittle. The materials used for the containment
system are required to reduce the heat transfer from the hull structure to
minimise the boil-off gas from the cargo, as well as to protect the hull structure
Key
from the effects of cryogenic temperature. The inner hull is lined with the GTT
Mark 3L integrated tank system, consisting of a thin and flexible membrane, Ballast
called the primary barrier, which bears against a supporting insulation structure
embodying a secondary barrier and further secondary insulation bolted Void
and glued to the inner hull. This construction ensures that the entire cargo
Cofferdam
hydrostatic load is transmitted through the membrane and insulation to the Ballast Tank
steel plating of the inner hull structure and thereby to the hull plating of the Pipe Duct
vessel. Pipe Duct
Plywood
PUF Packing
R-PU Foam 100mm
R-PU Foam
Glass Wool 170mm
12.5mm
In addition to failure of the membrane, local cold spots can occur due to failure
of the insulation.
While the inner hull steel quality has been chosen to withstand the minimum
temperature likely to occur in service, prolonged operation at steel temperatures
below 0°C will cause ice build-up on the plating, which in turn will cause a
further lowering of steel temperature due to the insulating effect of the ice. To
avoid this, glycol heating coils are fitted in each cofferdam space, of sufficient
capacity to maintain the inner hull steel temperature at 5°C under the worst
conditions.
Illustration 1.3.2c Interbarrier Space (IBS) - Insulation Space (IS) Flat Panel Junction
Fitting Components
For Flat Panel
Cylindrical Plug
Cylindrical Plug
Nut HM 10
Washer LL 10 Stud
Level Wedge
Anchoring Strip
Inner Hull
Flat Joint
A vapour dome is located near the geometrical centre of each cargo tank
Pump Support Bracket
ceiling. Each vapour dome is provided with:
• A vapour supply/return line to supply vapour to the tank when Main Pump
discharging, vent vapour from the tank whilst loading, and also
vent the boil-off when the tank contains cargo.
• Pick-up for pressure sensors.
In addition, each cargo tank has a liquid dome located near the ship’s centre
line at the aft part of the tank and includes the following:
• Liquid line safety valves exhaust.
• Spray line arrangement for cooldown purposes.
• Two pressure/vacuum relief valves set at 25kPa(g) and -1kPa(g)
vacuum, venting to the nearest vent mast riser.
The liquid dome also supports a tripod mast made of stainless steel (316L),
suspended from the liquid dome and held in position at the bottom of the tank
by a sliding bearing to allow for thermal expansion or contraction depending on
the tank environment. The tripod mast consists of the main discharging pipes
and emergency pump well, in the form of a three-legged trellis structure and
is used to support the tank access ladder and other piping and instrumentation
equipment.
The five cargo tanks are connected with each other by the liquid, vapour and
stripping/spray headers which are located on the trunk deck. The nitrogen
mains supplying the primary and secondary insulation spaces, and other
services directly associated with the cargo system, are also located on the trunk
deck together with the fire main and deck spray main.
Flat Panel
PUF Packing
Mastic
Glass Wool
12.5mm
Sensor
Secondary Barrier
(Triplex, 0.7mm Thick)
Cylindrical Plug
Level Wedge Mastic
Flat Panel
Grade E
Grade A
Grade E(4)
Grade A Ambient conditions for determining material grade of the hull structures are
based on the worldwide service except Alaskan water as follows:
Grade E - Air temperature (at 5 knots) : -18 degrees C
- Sea water temperature : 0 degrees C
Grade E(5)
- LNG supposed on secondary barrier
Grade E(4) The hull structure complies with requirements from Class Society, IGC- code
requirements and USCG regulation for worldwide use except Alaska (46 CFR 154,
Statement of Compliance issued).
Grade E(5)
Key
Grade A (1) Grade A for thickness up to and including 15mm, for higher thickness up to and including 25mm grade B or DH,
for thickness up to 30mm use of grade D.
Grade D(4)
(2) Grade B or AH for thickness up to and including 25mm, for thickness up to 30mm use of grade D necessary.
Grade D(4) (3) Grade B or AH for thickness up to and including 20mm, for higher thickness up to and including 25mm grade D,
for thickness up to 40mm use grade DH.
Grade B(3)
(4) Grade D for thickness up to and including 20mm, for higher thickness up to and including 30mm grade DH,
Grade B(2) for thickness up to 50mm use grade E or EH.
Grade A (5) Possibility to apply grade DH for thickness up to and including 20mm instead of grades E or EH.
Grade B(3)
Grade A(1)
Grade B(2)
Grade D
10m 6m
Profile
25m
H H H
H H
H
Upper Deck
Up
Up
Dn
Dn Up
Up
Up
Dn
Up
Dn Up Up Up
Dn
Up
Up
H
H H H H H
Introduction
Under the IMO code for the Construction and Equipment of Ships Carrying
Gases in Bulk, the following are regarded as hazardous areas.
Gas dangerous spaces or zones, are zones on the open deck within 3.0m of
any cargo tank outlet, gas or vapour outlet, cargo pipe flange, cargo valve and
entrances and ventilation openings to the cargo compressor house.
They also include the open deck over the cargo area and 3m forward and aft of
the cargo area on the open deck up to a height of 2.4m above the weather deck,
and a zone within 2.4m of the outer space of the cargo containment system
where such spaces are exposed to the weather.
The entire cargo piping system and cargo tanks are also considered gas
dangerous.
In addition to the above zones, the code defines other gas dangerous spaces.
Methane CH4 Ethane C2H6 Propane C3H8 Butane C4H10 Pentane C5H12 Nitrogen N2
Boiling Point at 1 bar absolute (ºC) -161 -88.6 -42.1 -0.5 36.1 -195.8
Liquid Density at Boiling Point (kg/m3) 426 544.1 580.7 601.8 610.2 808.6
Vapour SG at 15ºC and 1 bar absolute 0.553 1.04 1.55 2.00 2.49 0.97
Non-
Flammable Limits in Air by Volume (%) 5.3 to 14 3.1 to 12.5 2.1 to 9.5 1.8 to 8.5 3 to 12.4
flammable
Vaporisation Heat at Boiling Point (kJ/kg) 510.4 489.9 426.2 385.2 357.5 199.3
A typical composition of LNG is given in illustration 2.1.1b, and the physical Lumut 89.4 6.3 2.8 1.3 0.05 0.05 463
properties of the major constituent gases are given in illustration 2.1.1a.
Marsa el Braga 70 15 10 3.5 0.6 0.9 531
During a normal sea voyage, heat is transferred to the LNG cargo through
the cargo tank insulation, causing part of the cargo to vaporise, ie, ‘boil-off’. Point Fortin 96.2 3.26 0.42 0.07 0.01 0.008 433
The composition of the LNG is changed by this boil-off because the lighter
components which have lower boiling points at atmospheric pressure, vaporise Ras Lafan 89.5 6.33 2.49 1.26 0.08 0.34 463.7
first. The discharged LNG therefore has a lower percentage content of nitrogen
and methane than the LNG that was loaded, and a slightly higher percentage Withnell 89.02 7.33 2.56 1.03 0 0.06 460
of ethane, propane and butane, due to methane and nitrogen boiling-off in
preference to the heavier gases.
Temperature (OC)
-165 -160 -155 -150 -145 -140 -135 -130 -125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60 -55 -50 -40 -30 -20 -10 0 25 50 75 100
60
50
40
30
20
Propane
2mol % Ethane
10
9
8
7
Methane Ethylene Ethane Propylene Propane bar
6
5
Butadrene
N. Butane
1.3
4
ata
3
1
0.9
0.8
0.7
0.6
-165 -160 -155 -150 -145 -140 -135 -130 -125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60 -55 -50 -40 -30 -20 -10 0 25 50 75 100
Temperature (OC)
Illustration 2.1.1c above shows the vapour pressure diagram of liquid cargoes.
The boiling point of methane increases with pressure and this variation is
shown in the diagram for pure methane over the normal range of pressures on
board the vessel. The presence of the heavier components in LNG increases the
+20
boiling point of the cargo for a given pressure.
0
The relationship between boiling point and pressure of LNG will approximately
follow a line parallel to that shown for 100% methane. Lighter than Air
- 20
- 60
Boiling Point at 100kPa absolute -161°C Methane Vapour
Temperature
- 80
426.0kg/m3 °C
Liquid Density at Boiling Point
-100
Vapour SG at 15°C and 100kPa absolute 0.554
-120
Gas Volume/Liquid Volume Ratio at -161.5°C at 100kPa absolute 619
Heavier than Air
Flammable Limits in Air by Volume 5.3 to 14% -140
17
16 Y
M
15
N
14
G X
13
D
12
11
Oxygen %
10
4
Area HDFCH
Capable of Forming Flammable
3
Mixtures with Air, but Containing too
much Methane to Explode by itself
2
A Z C
10 H 20 30 40 50 60 70 80 90 100
0
Methane %
Area ABEDHA
Not capable of forming
flammable mixture with air
3) Area ABEDHA. Any mixture whose composition is represented a) In practice the tanks and piping containing air are to be inerted
by a point which lies within this area is not capable of forming a with inert gas provided by the inert gas generator, as the nitrogen
flammable mixture when mixed with air. generator capacity is far too small to inert the cargo tanks, before
admitting methane until all sampling points indicate 5% or less
oxygen content.
2) LNG continuously spreads over an indefinitely large area, Nitrogen is used on board for the pressurisation of the cargo tank wedge
Reactivity and insulation spaces, the purging of cargo pipelines and heaters, boiler gas
and it results in a magnification of its rate of evaporation until
vaporisation is complete. lines and Whessoe gauges, and for the sealing of the LNG compressors. It is
Methane is an asphyxiant in high concentrations because it dilutes the amount
produced by the nitrogen generators whose principle is based on hollow fibre
of oxygen in the air below that necessary to support life. Due to its inactivity,
3) No coherent ice layer forms on the water. membranes to separate air into nitrogen and oxygen.
methane is not a significant air pollutant and, due to its insolubility, inactivity,
and volatility, it is not considered to be a water pollutant.
4) Under particular circumstances, with a methane concentration
Physical Properties of Nitrogen
below 40%, flameless explosions are possible when the LNG
strikes the water. It results from an interfacial phenomenon in Cryogenic Temperatures Nitrogen is the most common gas in nature since it represents 79% in volume
which LNG becomes locally superheated at a maximum limit of the atmospheric air.
until a rapid boiling occurs. However, commercial LNG is far Contact with LNG or with materials chilled to its temperature of about -160°C
richer in methane than 40% and would require lengthy storage will damage living tissue.
At room temperature, nitrogen is a colourless and odourless gas. Its density is
before ageing to that concentration. near that of air, 1.25kg/m3 under the standard conditions.
Most metals lose their ductility at these temperatures; LNG may cause the
5) The flammable cloud of LNG and air may extend for large brittle fracture of many materials. In the case of LNG spillage onto the ship’s
When liquefied, the temperature is -196°C under atmospheric pressure, density
distances downward (only methane when warmer than -100°C deck, the high thermal stresses generated from the restricted possibilities of
of 810kg/m3 and a vaporisation heat of 199kJ/kg.
is lighter than air) because of the absence of topographic contraction of the plating will result in the fracture of the steel.
features which normally promote turbulent mixing.
Properties of Nitrogen
Behaviour of LNG in the Cargo Tanks
When Agitated By Water Molecular weight: 28.016
When loaded into the cargo tanks, the pressure of the vapour phase is Boiling point at 1 bar absolute: –196°C
6) For example, if a flange drip tray becomes filled with LNG as
maintained substantially constant at slightly above atmospheric pressure.
a result of a leaking flange, under no circumstances should a Liquid SG at boiling point: 0.8086
water jet be directed into the drip tray. Such action will cause
The external heat passing through the tank insulation helps generate convection Vapour SG at 15°C and 1 bar absolute: 0.97
a severe eruption and a rapid expansion/boiling of the LNG
currents within the LNG tank causing warmer LNG to rise to the surface where
within the tray, resulting in LNG and ice particles being blasted Gas volume/liquid volume ratio at –196°C: 649
it then boils-off. The heat necessary for vaporisation comes from the LNG. As
outwards. The LNG should be allowed to boil-off naturally or
long as the vapour is continuously removed by maintaining the pressure as Flammable limits: None
the drip tray warmed with water spray on the sides or base.
substantially constant, the LNG remains at its boiling temperature.
Dew point of 100% pure N2: Below –80°C
Vapour Clouds If the vapour pressure is reduced by removing more vapour than is generated, the
LNG temperature will decrease. In order to make up the equilibrium pressure
1) If there is no immediate ignition of an LNG spill, a vapour cloud
corresponding to its temperature, the vaporisation of LNG is accelerated,
may form. The vapour cloud is long, thin, cigar-shaped and, under
resulting in an increased heat transfer from LNG to vapour.
certain meteorological conditions, may travel a considerable
distance before its concentration falls below the lower flammable
limit. This concentration is important, for the cloud could ignite
and burn, with the flame travelling back towards the originating
Inert gas is used to reduce the oxygen content in the cargo system, tanks, In the event of a spillage or leakage, water spray should be directed at the
piping, void spaces and compressors. This is in order to prevent an air/CH4 spillage to disperse and evaporate the liquid and to protect the steelwork. The
mixture prior to aeration post-warm-up, before refit or repairs and prior to the leak must be stopped, suspending cargo operations if necessary.
T1 T2
gassing-up operation post-refit before cooling down.
In the event of a major leakage or spillage, the cargo operations must be
Inert gas is produced on board using an inert gas generator supplied by Smit stopped immediately, the general alarm sounded and the emergency deck water
Gas System, which produces inert gas at 15,000nm3/h with a -45°C dew point spray system put into operation.
burning low sulphur content gas oil. This plant can also produce dry-air at Structural steels suffer brittle fracture at low temperatures. Such failures can be
15,000nm3/h and -45°C dew point (see Section 4.9 for more details). catastrophic because, in a brittle steel, little energy is required to propagate a
fracture once it has been initiated. Conversely, in a tough material, the energy
The inert gas composition is as follows: necessary to propagate a crack will be insufficient to sustain it when it runs into
Oxygen: < 2.5% in volume sufficiently tough material.
Carbon dioxide: < 15% in volume Plain carbon structural steels have a brittle to ductile behaviour transition
Carbon monoxide: < 65 ppm by volume which occurs generally in the range -50°C to +30°C. This, unfortunately,
precludes their use as LNG materials (carriage temperature -162°C). The effect
Sulphur oxides (SOx): < 1 ppm by volume is usually monitored by measuring the energy absorbed in breaking a notched
Nitrogen oxides (NOx): < 65 ppm by volume bar and a transition curve, as shown in illustration 2.2.2a, is typical for plain
carbon steels.
Nitrogen: Balance
Dew point: < -45°C For this reason, materials which do not show such sharp transition from ductile
to brittle fracture as the temperature is lowered, have found obvious application
Soot: Complete absence
for use in cryogenic situations in general and particularly in liquid methane
carriers, for example, invar (36% nickel-iron alloy), austenitic stainless steel,
The inert gas is slightly denser than air: 1.35kg/m3 abt at 0°C.
9% nickel steel and some aluminium alloys such as 5083 alloy. All of these
materials behave in a ductile manner at -162°C, so that the chance of an
WARNING unstable brittle fracture propagating, even if the materials were overloaded, is
Due to its low oxygen content, inert gas is an asphyxiant. negligible.
EMERGENCY PROCEDURES
STOP GAS SUPPLY. Do not extinguish flame until gas or liquid supply has been shut off, to avoid
Fire possibility of explosive re-ignition. Extinguish with dry powder, halon or carbon dioxide. REACTIVITY DATA
Cool tanks and surrounding areas with water.
Water, Fresh or Salt - No dangerous reaction; Other Liquids or Gases
Liquid DO NOT DELAY. Flood eye gently with clean fresh water. Force eye open if necessary. Do not rub may freeze to form ice or hydrates No dangerous reaction; may freeze to form ice or hydrates
in Eye the affected area. Continue washing for at least 15 minutes. Obtain medical advice as soon as possible.
Air - No reaction
DO NOT DELAY. Remove contaminated clothing. Flood affected area with water. Handle patient gently.
Liquid
Do not rub affected area. Immerse frost-bitten area in warm water until thawed. Obtain medical advice or
on Skin assistance as soon as possible.
REMOVE VICTIM TO FRESH AIR. Remove contaminated clothing. If breathing has stopped or is weak
PHYSICAL DATA
Vapour or irregular, give mouth to mouth/nose resuscitation or oxygen as necessary. Obtain medical advice or
Inhaled assistance as soon as possible
Boiling Point at Coefficient of Cubic Expansion Enthalpy (kJ/kg)
Atmospheric Pressure -161ºC 0.0026 per ºC -165ºC Liquid 29.3 at -165ºC 285.5 at -100ºC
STOP THE FLOW. Avoid contact with liquid or vapour. Extinguish sources of ignition. Flood with large
Vapour 545.1 at -165º 588.3 at -100ºC
Spillage amounts of water to disperse spill, and to prevent brittle fracture. Inform port authorities or coastguard Vapour Pressure Bar (A)
Freezing Point -182ºC
of spill. Relative Vapour Density Latent Heat of Vaporisation
See graph in Figure A1.2
0.55 (kJ/kg)
Specific Gravity See graph in Figure A1.2
Molecular Weight
See graph in Figure A1.2 16.04kg/kmole Electrostatic Generation
EMERGENCY PROCEDURES
Fire NOT FLAMMABLE. Cool nitrogen tanks with water spray in the event of fire near to them.
REACTIVITY DATA
Liquid DO NOT DELAY. Flood eye gently with clean fresh water. Force eye open if necessary. Do not rub
in Eye the affected area. Continue washing for at least 15 minutes. Obtain medical advice as soon as possible. Water, Fresh or Salt - No reaction; Other Liquids or Gases
nitrogen does not dissolve in water No reaction
DO NOT DELAY. Remove contaminated clothing. Flood affected area with water. Handle patient gently. Air - No reaction
Liquid
Do not rub affected area. Immerse frost-bitten area in warm water until thawed. Obtain medical advice or
on Skin assistance as soon as possible.
REMOVE VICTIM TO FRESH AIR. Remove contaminated clothing. If breathing has stopped or is weak
Vapour or irregular, give mouth to mouth/nose resuscitation or oxygen as necessary. Obtain medical advice or PHYSICAL DATA
Inhaled assistance as soon as possible
Boiling Point at Freezing Point -210ºC Enthalpy (kJ/kg)
STOP THE FLOW. Avoid contact with liquid or vapour. Extinguish sources of ignition. Flood with large Atmospheric Pressure -196ºC Liquid 30.7 at -196ºC 145.3 at -150ºC
Spillage amounts of water to disperse spill, and to prevent brittle fracture. Inform port authorities or coastguard Relative Vapour Density Vapour 229.0 at -196º 588.3 at - 150ºC
of spill. Vapour Pressure Bar (A) 0.97
Latent Heat of Vaporisation
1.96 at -190ºC 9.87 at -170º Molecular Weight (kJ/kg)
Specific Gravity 28.01kg/kmole 198.9 at -196ºC 72.4 at -160ºC
0.807 at -196ºC Electrostatic Generation
Coefficient of Cubic Expansion None
TVL Simple Asphyxiant Non Toxic 0.005 per at ºC -198ºC
HEALTH DATA ODOUR THRESHOLD Odourless
ON EYES.Tissue damage due to frost-bite.
Effect of ON SKIN. Tissue damage due to frost-bite.
Liquid BY SKIN ABSORPTION. Nil.
CONDITIONS OF CARRIAGE
BY INGESTION. Not pertinent.
Normal Carriage Condition Control of Vapour within Vapour Detection
Fully refrigerated Cargo Tank None required. Oxygen meter needed
ON EYES. Cold vapour could cause damage. prevent asphyxiation
No
ON SKIN. Cold vapour could cause damage. Ship Type 3G
Gauging Closed or Indirect
WHEN INHALED
Effect of Independent Tank Required No
Acute Effect. Asphyxiation. Headaches, dizziness,unconsciousness or even death could result.
Vapour
Chronic Effect. Nil.
25 15 12
14 11
6
16
Cargo Control Room
22
5
23 24 23 23
13
17
2 10 10
3
1 19
9 4
21
20 8 18
7
Key
1. 5kg CO2 Portable Fire Extinguisher 6. LCD Overhead Screen 11. CCTV Monitors 16. Cargo Control Console 21. Cupboard
2. Hull Stress Monitoring 7. Alarm 12. First Aid 17. Load Computer 22. Table
3. Refrigerator 8. VHF Battery Charging Unit 13. Calendar 18. Whiteboard 23. Smoke Detector
4. Photocopier 9. Dry Powder Remote Control Panel 14. CTS 19. Noticeboard 24. Gas Detector
5. Air Conditioning Unit 10. Ship Network Workstations/Printers 15. Inclinometer 20. Portable Gas Analysers 25. Clock
1 47
Key
1. DACS 23” TFT Monitor
2. DACS Operating Control Panel with Trackball
3. Auto Telephone
4. Telephone Directory
5. 23” TFT Monitor (CCTV)
6. Emergency Stop Pushbutton No.1
Cargo Oil Pumps and Vent Fans
7. Emergency Stop Pushbutton No.2
1 1 1 1 1 Cargo Oil Pumps and Vent Fans
8. Emergency Stop Pushbutton No.3
GCU Fans and Oil Pumps
9. Emergency Stop Pushbutton No.4
GCU Fans and Oil Pumps
10. UHF Main Unit and Microphone
11. VHF Main Unit and Microphone
12. Emergency Stop Pushbutton for the GCU
13. Hotline Telephone
14 14. Common Battery Telephone
3 4 15. Plant Telephone
16. Ship/Shore Link Selector Switch
2 2 2 17. Ship/Shore Link Selector Switch Optical
18. Ship/Shore Link Selector Switch Electric
19. Ship/Shore Link Selector Switch Pneumatic
20. Pneumatic Pressure Setting Switch Normal
21. Pneumatic Pressure Setting Switch Trip
22. Shore Signal Healthy Lamp
23. Ship/Shore Link Switch Inhibit Lamp
24. Ship/Shore Link Switch Wrong Position
25. Pneumatic Link Bypass SW Wrong Position
26. ESDS Manual Switch with Lamp
27. ESDS Reset Switch
5 5 28. ESDS Test Switch
29. ESDS Inhibit Switch
30. CCTV Keyboard
31. Trim / List Indicator
32. Wind Speed / Direction Indicator
33. Receiver for Whessoe Float Level Gauge
33 32 34. Port Draft Indicator
16 17 18 19 20 21 35 0
48 0
43
35. Fwd Draft Indicator
50 50 50 50
36
6 7 12 38 37. Starboard Draft Indicator
22 23 24 25 44 45
1 38 1 38. SP Volume Control Box
31 38 39. VHF Local Handset
26 27 28 29 46 40. Inmarsat-F Remote Telephone
41. Talk-back Remote Controller with Microphone
8 9
42. PA Remote Controller with Microphone
43. Fire Repeater Panel
44. Fire Alarm Pushbutton
45. General Alarm Pushbutton
46. Ceiling Light Switch
13 47. Overhead DACS monitor
15 3 39 4
2 40 48. RPM indicators404040
11 38 30
10 4
Br
-1
idg
To
O eD
S-3 ec
Colour Printer
Laser Printer
2
SV
k
OS C
31
CC
CT C 10 Part of INS Console
SO / C 50” Plasma Screen
S CC
9 CC SVC OS 51 in CCR
Gas Combustion Unit C
OS 8/
(Engine Control Room) 34 CC
C
OS 7/
34 CC CC
Patrol Alarm System Cargo C6 R
2 x Start/Stop Panels C-
PS
2 x Reset Panels CC De
24
0
C5 ck
-R C Side Passageway CC
PS 1 2 x FS (IS) Port C
71 OS 4/
33 CC
C
IS OS 3/
SS 32 CC
Firewall/Router FS C
33 OS 2/
To SMS -x 32 CC
ND C1
To Satellite B1 U
/C
Watch Call
Communications PD 1 4 FS
Panels x 24 Alarm Printer U 00C F
2-2
R - 40 S
Net B FS1 0C F
OS
34 R1 - 40 S
-1
Net C FS 0C F
To
Colour Printer O 33 R1 - 40 S N DAC Input/
S-3 FS 0C D Output Room
5 32 R1 - A U
Laser Printer FS 1
Engine Room 31 PDU
Floor 1 x FS 1-2
UPS 6
FS (IS) IS 0 IS Side Passageway
FS SS
FS 3 x FS (IS) Starboard
Battery 33
-x FS 31 CTS System
CC 60 -x
C9 IS
Patrol Alarm System
EC FS Cargo Motor
x 2 Start/Stop Panels C UPS No.2 Main UPS x 2 33
Re OS 8/ (15kVA) -x Room
-37
Ca lique EC
C
OS 7/
1 x FS 60 Port
rg
o M facti -37
EC EC
oto on P C6
R UPS
r R lan
oo t EC
m C5 Battery
EC Laser Printer
ND C UPS No.1
OS 4/
xx N2 No.2 U -36 E (15kVA)
B2 F CC
PD 4 S OS 3/
U 00C FS -35 EC
2-1 R - 4 C Net A
PS 1
00 OS 2/ GLN100/806
C 35 EC
xx N2 No.1 44 R1 LV C1
FS Po Ro
FS 43 rt om
FS
44
-x FS CC
F/C A-Deck F C
x 1 FS (Port)
FS 40 S CT 10/
44 0C F S
-x FS R - 40 S N
Engine Room FS FS 1 0C D
42 R1 - A U
Ca x 2 FS (Port) 43 FS 2 LV
rgo FS
-x
41 PDU
Ro Com 40 1-1 St Ro
om 0 Engine Room arb om
p -R C oa
Zo ress
x 3 FS (Port) FS
FS 1 rd
ne CTS Console
o 61 FS
1 r 42
-x
Re Engine Room FS
l
Ca ique x 3 FS FS
41
rgo fac (Starboard) -x FS
Mo tion FS
tor Pl FS 41
xx BOG No.2 Ro ant FS Engine Room -x
om -61
x 2 FS
(Starboard)
Engine Room
xx BOG No.1 x 1 FS Key
(Starboard)
Electrical Signal
Monitoring and control is performed by software modules. The basic modules Manual
are:
• Buttons
Auto
• Analogue measurement modules
• Digital measurement modules
Manual Output
• Pulse measurement modules
• Motor/pump control modules
Inhibit On
• Valve control modules
• PID controller modules Inhibit Off
All display views are made up from a set of standard modules. The symbols
on the screen are the symbols associated with these modules, valves, motors, Acknowledge
measurements, etc.
Symbols
The symbols indicate the operational mode and status of the represented
equipment (motor/pump etc) by means of tag mark characters and changes in
colour and appearance.
01/01/08
VIEWS FAULT
POWER FAULT
HOME M/E M/E MACH.
POWER 1 2
PAGE PORT STBD MAIN
COMMAND
GAS ALARMS
CARGO RELIQ. GCU CTS 5 NAV
MANAG.
ALARM
Buttons to Access
Sub-systems Views
01/01/08
INPUT
2 3 PAGE HOME
1
abc def UP
4 5 6 PAGE ESC
ghi jkl mno DOWN
7 8 9
pqrs tuv wxyz
- 0 . abc...
a/A _
]
The silence button (speaker symbol) is used to stop the audible alarm that
INPUT sounds when alarms are raised while the ALARM VIEW button is used to
4 2
display the alarms event window.
2 2
1 2 3 PAGE HOME
UP 3
abc def
Command Group
Key This group contains the TAKE, GIVE and STATUS buttons. The TAKE and
4 5 6 PAGE ESC 1 GIVE buttons allow the operator to transfer command control between the
ghi jkl mno DOWN 1. Roller Ball operator stations. Above each of these buttons there is a green status LED that
2. Mouse Buttons
3 indicates control transfer status. The STATUS button allows the operator to
3 3. Arrow Keys
view the current status of the command control.
4. Alphanumeric Input Keys
7 8 9
pqrs tuv wxyz 5. Toggle Key
6. Light Sensor
- 0 . abc...
3
_
5 1
01/01/08
1 Feb 2008, 21:16:10
House Page
01/01/08
Previous Page
Parent Page
Most Recent Alarm
History Navigator
Navigator
(All System Available)
Report Manager
Message Manager
Event List
Event Pop-Up
System Station
• Reliq. (Reliquefaction Plant) - 14 views Cool Down Sequence Other screens are relevant to the cargo system such as the Ballast, CTS and
Cargo Tank 1 Gas systems.
• GCU (Gas Combustion Unit) - 3 views
• N2 Gen (Nitrogen Generator) - 1 view Cargo Tank and Cofferdam 1 Temperature
• Patrol Man (Watch Panels, Machinery and Cargo) - 1 view Cargo Tank and Cofferdam 3 Temperature
Cargo CT3 Cargo PP Sequence
The system is made up of the following types of views:
Cargo CT3 Spray PP Sequence
• Process: Showing the process equipment under system control
Cargo Tank 4
• Flow: Showing the process equipment under system control
Cargo Tank and Cofferdam 4 Temperature
for software configuration
Cargo CT4 Cargo PP Sequence
• Event: Showing process events and events generated by the
system Cargo CT4 Spray PP Sequence
• Trends: Showing historic trend curves for process variables Cargo Tank 5
• Station Status: Showing the status of the process and operator Cargo Tank and Cofferdam 5 Temperature
control units Cargo Tank 5 Barrier Pressure
Cargo CT5 Cargo PP Sequence
Cargo CT5 Spray PP Sequence
14 ““ Not Mark
The dynamics of a process are shown by changes in the colour of the symbols Windings pump 1 Eng. Speed
S T m L
in a view. For example, the colour of a motor symbol will be grey (background) R
when it is stopped, yellow when it is starting up or shutting down (transient 100 Pump, Manual Mode (Running) Electrical Motor, Manual Mode (Running)
The normal operating procedure for duty/standby pumps is to start the pump • STOP - This stops the motor and is only available in the 2) A motor automatically starting if another in the sequence
intended to be the duty pump and placed in AUTO mode using the pump MANUAL mode. stops due to a failure.
faceplate (see illustration 3.2.3a). The second pump which is intended as • START - This starts the motor and is only available in the 3) A motor automatically starting if, for example, a pressure
the standby pump is now placed in the automatic mode to allow automatic MANUAL mode. switch is used to start an additional LO pump if the LO pressure
switchover should the duty pump fail. is too low in a generator.
• RESET - This command resets the appropriate time-out
counters and can be used to recover from a failed start or stop • BLACKOUT RESTART - This function causes a motor to
If the main pump is put in local or manual mode while running in DUTY/
operation. restart automatically when power is re-established after a
STBY/AUTO function, there will be a duty/standby pair alarm. This is shown
blackout, provided that the motor was running before the
on the alarm page and on the duty/standby dialogue as ‘Error’. The system will • AUTO - This command selects the automatic mode and cancels
blackout occurred. A start delay is provided on each motor to
not start if the standby pump is in local, has an error or is interlocked. the MANUAL mode. When in automatic mode the motor/pump
prevent too many motors starting at the same time.
is controlled by an output signal from another module and not
The standby pump will still start if there is a fault on the duty pump or low via the operation menu. In this case the STOP and START • SHUTDOWN - The control modules have a shutdown function
pressure is detected. The duty pump will then stop when the standby pump run buttons will become blank. that overrides all other control inputs to the module and provides
signal has been confirmed. an emergency stop facility.
• MANUAL - This command cancels the automatic mode and
allows the motor/pump to be controlled via the operation menu. • DUTY/STANDBY - The control modules may be connected in
In the case of a blackout on the 440V switchboards, the pumps will be restarted different duty/standby configurations.
Selection of the manual mode is not possible if the Lock in Auto
when normal power has been recovered. The initial pump situation will
Mode parameter is set to 1 during the system configuration.
normally be restored.
Engine Control Room WATCH BRIDGE UNIT WATCH CABIN UNIT ON DUTY WATCH CABIN UNIT ON DUTY WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT
SVC OS-37
Wheelhouse Extension Extension Alarm Panel 2 Extension Alarm Panel 3 Extension Alarm Panel 4 Extension Alarm Panel 5 Extension Alarm Panel 6 Extension Alarm Panel 7 Extension Alarm Panel 8
Alarm Panel 1 Captain’s Day Room (513) Chief Officer’s Day Room (512) 2nd Officer’s Room (520) 3rd Officer’s Room (521) 3rd Engineer’s Room (523) 2nd Engineer’s Day Chief Engineer’s
Master Machinery and Cargo Room (501) Day Room (506)
Captain’s Bedroom Buzzer Chief Officer’s Buzzer 2nd Engineer’s Buzzer Chief Engineer’s Buzzer
(515) Bedroom (516) Bedroom (502) Bedroom (504)
ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS WATCH CABIN UNIT
CHIEF ESD CHIEF ESD CHIEF CHIEF ESD CHIEF ESD CHIEF ESD
CHIEF ESD
ENG. ENG. ENG. ESD ENG. ENG. ENG. ENG.
2ND MACHINERY 2ND MACHINERY 2ND MACHINERY 2ND MACHINERY 2ND MACHINERY 2ND MACHINERY 2ND MACHINERY
ENG. ENG. ENG. ENG. ENG. ENG. ENG.
3RD CARGO 3RD CARGO 3RD CARGO 3RD CARGO 3RD CARGO 3RD CARGO 3RD CARGO
ENG. SCREEN MENU ENG. SCREEN MENU ENG. SCREEN MENU ENG. SCREEN MENU ENG. SCREEN MENU ENG. SCREEN MENU ENG. SCREEN MENU
4th BRIDGE 4th BRIDGE GAS 4th BRIDGE 4th BRIDGE 4th BRIDGE GAS 4th BRIDGE 4th BRIDGE
SELECT GAS SELECT SELECT GAS SELECT GAS SELECT SELECT GAS SELECT GAS
ENG. WATCH FIRE ENG. WATCH FIRE ENG. WATCH FIRE ENG. WATCH FIRE ENG. WATCH FIRE ENG. WATCH FIRE ENG. WATCH FIRE
CHIEF CCR SYSTEM CHIEF CCR SYSTEM CHIEF SYSTEM CHIEF CCR SYSTEM CHIEF CCR SYSTEM CHIEF CCR SYSTEM CHIEF CCR SYSTEM
TAG TAG CCR TAG TAG TAG TAG TAG
OFF. OFF. WATCH OFF. OFF. OFF. WATCH OFF. OFF.
WATCH DETAILS DETAILS WATCH DETAILS WATCH DETAILS DETAILS WATCH DETAILS WATCH DETAILS
PATROL PATROL PATROL PATROL PATROL PATROL PATROL
CARGO MAN CARGO MAN CARGO MAN CARGO MAN CARGO MAN CARGO MAN CARGO MAN
ENG. ALARM ENG. ALARM ENG. ALARM ENG. ALARM ENG. ALARM ENG. ALARM ENG. ALARM
ECR ECR ECR ECR ECR ECR ECR
WATCH WATCH WATCH WATCH WATCH WATCH WATCH
2ND/3RD 2ND/3RD 2ND/3RD 2ND/3RD 2ND/3RD 2ND/3RD 2ND/3RD
OFF. OFF. OFF. OFF. OFF. OFF. OFF.
4TH/ LAMP SOUND 4TH/ LAMP SOUND 4TH/ LAMP SOUND 4TH/ LAMP SOUND 4TH/ LAMP SOUND 4TH/ LAMP SOUND 4TH/ LAMP SOUND
UNIT UNIT UNIT UNIT UNIT UNIT UNIT
SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL SPARE 1 TEST OFF FAIL
SPARE 2 SPARE 2 SPARE 2 SPARE 2 SPARE 2 SPARE 2 SPARE 2
Extension Alarm Panel 16 Extension Alarm Panel 15 Extension Alarm Panel 14 Extension Alarm Panel 13 Extension Alarm Panel 12 Extension Alarm Panel 11 Extension Alarm Panel 10 Extension Alarm Panel 9
Conference Room (406) Central Office (407) 4th Officer’s Room (414) Spare Officer’s Room (416) Spare Officer’s Room (417) 4th Engineer’s Room (419) Cargo Engineer’s Room (421) Officers’ TV Room (401)
WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT WATCH CABIN UNIT
Extension Alarm Panel 17 Extension Alarm Panel 18 Extension Alarm Panel 19 Extension Alarm Panel 20 Extension Alarm Panel 21 Extension Alarm Panel 22 Extension Alarm Panel 23 Extension Alarm Panel 24
Gymnasium (338) Crew’s TV Room (324) Crew’s Mess Room (225) Crew’s Duty Mess Room (226) Crew’s Reception Room (208) Officers’ Reception Room (212) Officers’ Duty Mess Room (216) Officers’ Mess Room (217)
The alarms will be routed to the engineer on duty as appropriate, for example, When an engine room alarm is activated, it is sounded in the duty engineer’s
cargo alarms will be routed to the cargo engineer when a cargo system alarm cabin, on the bridge and the public rooms. The buzzer can be acknowledged
is activated and machinery alarms will be routed to the engine room duty at any panel.
engineer.
2ND MACHINERY
ENG. DACS Patrol Man Display
2ND MACHINERY
ENG.
3RD CARGO
ENG. SCREEN MENU
4th BRIDGE
SELECT GAS
ENG. WATCH FIRE
Patrol Man is a facility for safe lone man visits to machinery spaces when
responding to watch alarms. Points around the machinery space must
acknowledged within a given time in order to prevent the Patrol Man alarm
being generated.
This facility can be set from the watch panel inside the ECR/CCR or
automatically from the alarm extension system when an alarm is activated.
The reset period is 27 minutes with a pre-warning alarm 3 minutes before the
dead man alarm is set. The status display is shown on the Patrol Man primary
window as shown in illustration 3.2.4b.
3.3.1 Radar Primary System (Radar Gauges and Custody Transfer System)
ALARM ACCEPTED
To ESDS Panel
LOOP FAILURE ACCEPTED
220V AC 99 %
OVERRIDE
CT 1.
99 %
OVERRIDE
CT 2.
99 %
OVERRIDE
CT 3.
99 %
OVERRIDE
CT 4.
OMICRON
TONSBERG - NORWAY
99 %
OVERRIDE
CT 5.
AT
SEA
CTS Monitor
C Trim/List
Duct Keel
220V AC
NL-296 Display
hp
Cargo Control Console
NL-296 Display
Bridge Control Console
Colour Laser Printer
WS Key
220V AC CTS Electrical Signal
Hazardous Area
Cargo Tank No.5 Cargo Tank No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1
Trunk Deck
IS
Pipe Underdeck IBS Pipe Underdeck
Passageway Passageway
Cargo Tank
Pipe Duct
Water Ballast Tank Water Ballast Tank
Temperature and pressure within the tanks for use in the CTS calculations is After loading:
obtained from the temperature and pressure monitoring system as detailed in • Total corrected volume is corrected by the average liquid Failure of the CTS Equipment
Section 5.1 of this manual. temperature
If the CTS equipment should fail in one tank during custody transfer, the levels
The report headings contain the following information: for that tank would have to be measured using the Whessoe float gauge. The
Custody Transfer System volume calculations and corrections then have to be made by hand, using the
• Ship’s name (fixed in the report) hard copy of the tank gauge tables.
The CTS process image can be accessed via the drop-down menu by selecting • Port name (inserted by the operator before the report is started)
WINDOW, then CTS DATA. The display has the following main purposes: The float gauges must be kept blocked at their top stored position when at sea.
• Cargo number (inserted by the operator before the report is In port, during cargo operations, the floats should be manually lowered to the
• To display the measured values relating to the CTS started)
After the cargo operations have been completed, the floats should be returned
to their raised stored position before the vessel leaves the port.
CERTIFICATE OF QUANTITY TRANSFERRED DURING LOADING
In this case a Cargo Record Report Sheet is manually completed using the
SHIP NAME
gauging tables. These contain the correction figures for trim, list, and thermal PORT/BERTH NAME
value (level gauge) of each individual tank in order to give the corrected level VOYAGE/CARGO NO. 02
CHIEF OFFICER
and volume in each cargo tank.
BEFORE LOADING
DATE (DD/MM/YYYY) 03-04-2007
LOCAL TIME (HH:MM) 10:50
TRIM (METRES) 0.94 BY STERN
LIST (DEGREES) 0.65 PORT
AFTER LOADING
DATE (DD/MM/YYYY) 03-04-2007
LOCAL TIME (HH:MM) 11:01
TRIM (METRES) 1.65 BY STERN
LIST (DEGREES) 1.01 STARBOARD
RECEIVER REP
SHIPPER REP
MASTER/CHIEF OFF
SURVEYOR(S)
TANK 1 TANK 2 TANK 3 TANK 4 TANK5 TANK 1 TANK 2 TANK 3 TANK 4 TANK5
LEVEL MEASUREMENT (M) LEVEL MEASUREMENT (M)
NO. 1 2.327 0.207 0.221 0.212 0.212 NO. 1 28753 28.347 28.344 28.350 28.340
NO. 2 2.327 0.204 0.226 0.214 0.214 NO. 2 28753 28.347 28.344 28.350 28.340
NO. 3 2.333 0.208 0.229 0.216 0.216 NO. 3 28753 28.347 28.344 28.350 28.340
NO. 4 2.329 0.214 0.222 0.214 0.214 NO. 4 28753 28.347 28.344 28.350 28.340
NO. 5 2.328 0.212 0.219 0.212 0.212 NO. 5 28753 28.347 28.344 28.350 28.340
AVERAGE LEVEL (M) 2.329 0.209 0.223 0.214 0.214 AVERAGE LEVEL (M) 28753 28.347 28.344 28.350 28.340
TRIM CORRECTION (M) -0.068 -0.089 -0.089 -0.080 -0.080 TRIM CORRECTION (M) 0.000 0.000 0.000 0.000 0.000
LIST CORRECTION (M) -0.003 -0.003 -0.003 -0.003 -0.003 LIST CORRECTION (M) 0.000 0.000 0.000 0.000 0.000
CORRECTED LEVEL (M) 2.258 0.177 0.131 0.131 0.131 CORRECTED LEVEL (M) 28753 28.347 28.344 28.350 28.340
LIQUID VOLUME (CUB. M) 1,629.053 135.469 153.321 136.317 136.317 LIQUID VOLUME (CUB. M) 24493.657 47125.119 47106.036 47100.623 47112.076
TOTAL LIQUID VOLUME (CUB. M) 2,054.160 TOTAL LIQUID VOLUME (CUB. M) 212,937.513
T5 -148.09 V -148.09 V -148.09 V -148.09 V -148.09 V T5 -148.09 V -148.09 V -148.09 V -148.09 V -148.09 V
T4 -152.59 V -152.59 V -152.59 V -152.59 V -152.59 V T4 -162.59 L -162.59 L -162.59 L -162.59 L -162.59 L
T3 -154.36 V -154.36 V -154.36 V -154.36 V -154.36 V T3 -164.36 L -164.36 L -164.36 L -164.36 L -164.36 L
T2 -154.97 V -154.97 V -154.97 V -154.97 V -154.97 V T2 -164.97 L -164.97 L -164.97 L -164.97 L -164.97 L
T1 -158.37 L -158.37 L -158.37 L -158.37 L -158.37 L T1 -165.37 L -165.37 L -165.37 L -165.37 L -165.37 L
-152.50 -150.80 -151.94 -152.09 -152.09 -148.09 -148.09 -148.09 -148.09 -148.09
AVG. VAPOUR TEMP. (DEG. C) AVG. VAPOUR TEMP. (DEG. C)
AVG. VAPOUR TEMP. SHIP (DEG. C) -158.37 -158.40 -158.29 -158.18 -158.18 AVG. VAPOUR TEMP. SHIP (DEG. C) -148.09
AVG. LIQUID TEMP. (DEG. C) -152.50 -150.80 -151.94 -152.09 -152.09 AVG. LIQUID TEMP. (DEG. C) -164.97 -164.97 -164.97 -164.97 -164.97
AVG. LIQUID TEMP.SHIP (DEG. C) -158.18 AVG. LIQUID TEMP.SHIP (DEG. C) -164.97
VAPOUR PRESS. mbar(a)) 1152 1152 1152 1152 1152 VAPOUR PRESS. (mbar(a)) 1152 1152 1152 1152 1152
1152 1152
Average Level
(Based Upon the
Last Five Readings) Average Average Vapour Average Liquid
Level Level Trim List Temperature Temperature
Volume
Temperature Sensor
at -160°C
Corrected Average Level
Average Vapour Temperature
Temperature Sensor
Adding Volume Volume from Other Tanks After Eighty Seconds Quantity of Measurement
from all Tanks The First Page Prints Out Before Loading/Unloading
Snapshot Report
Sorting of Snapshot Report
Stored Data Activated with
Measured Data
Corrected Liquid Volume Defined Printing Intervals
at Observed Average
Temperature
1084 Receiver
Hazardous Area
1084 Receiver
Transmitter Fig. 2047MT Transmitter Fig. 2047MT WHESSOE
(Tank1) (Tank2)
VAREC
IAS
MAINTENANCE
Key
This is the enter or validate key and is used to confirm a selection, command an action or to
validate data.
3304 Gauge 3304 Gauge
Move cursor right key. In user mode this is used to continue to the next screen. In configuration
Transmitter Fig. 2047MT mode it is used to continue to the next tank.
(Tank5)
1761 Move cursor left key. In user mode this is used to return to the previous screen. In configuration
Power Supply mode it is used to return to the previous tank.
Intrisically
Safe
Move cursor down key. This is used to select a line or to scroll through available choices.
In user mode it is used to continue to the next tank.
220V AC 50Hz Move cursor up key. This is used to select a line or to scroll through available choices.
In user mode it is used to return to the previous tank.
3304 Gauge
Exit without validating key. This is used to quit a menu or to return to a higher level.
Loss of Float
In the event of a float becoming detached, Whessoe supply a magnetic retrieval Handle to Raise
device that will attach to the metal plates on the top or bottom of the float so the Float
that it can be recovered without the need for gas freeing.
To retrieve a detached float, first ensure the tape and plunger are stored in the
gauge housing, then fully close the gate valve.
Open the inspection hatch and attach the magnetic retrieval device. Close the
inspection hatch. Cushion Spring
Open the gate valve and lower the retriever to the liquid level to pick up
the float. Raise and store the float, close the gate valve, open the inspection
chamber hatch and remove the float. Disconnect the retrieval device.
If the float has simply become detached and the tape remains in good condition,
simply re-attach the float to the tape and check the store position setting. If the
readings are accurate there will be no need to remove the main gauge cover. Cylindrical Float Inspection Hatch
If the tape has been damaged or cut, it will be necessary to rectify the tape and
hence rectify the gauge readings. In order to rectify the readings it is necessary
to remove the main cover to adjust the gauge read-out and gain access to the
tape.
Removal of the main cover will mean the custody seal will be broken. The
custody seal is there to prevent removal of the main cover and adjustment to
the gauge after accuracy tests have been carried out with the surveyor.
300mm Closure Valve
OMICRON
TONSBERG - NORWAY
99 % 99 % 99 % 99 % 99 %
OVERRIDE OVERRIDE OVERRIDE OVERRIDE OVERRIDE
CT 1. CT 2. CT 3. CT 4. CT 5.
Float Guide
Sensor Switch
Safe Area
Hazardous Area
High (96%)
Level Sensor Level Sensor Level Sensor Level Sensor Level Sensor
Tank No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1
Pressing the BUZZER SILENCE pushbutton silences the audible alarm and
when the ACCEPT/RESET button is pressed, the respective alarm LED on Alarm Hold Facility
the panel and on the OAU-01A/Ex unit inside the panel will flash in slow In addition to the normal alarm functions detailed above, there is also an
motion. ALARM HOLD button fitted. This function handles all of the tanks separately
and independently and is selected by pressing the ALARM HOLD button on
The alarm LED will continue to flash in slow motion until the loop failure has the alarm panel. The function remains in operation as long as the button is
been repaired. activated. The alarm hold function operates as follows:
Manufacturer: Kongsberg
Model: Display BEKA BA688C (NL296)
Sensor: Sensorex GL2263
Number: 1
A two axis Sensorex inclinometer is used to input the trim and list of the vessel.
This is located in the pipe duct space and as near to the ship’s centre line as
possible. The list is displayed as 1/10º, while the trim is displayed as ‘metres’
measured to two decimal points. The manual input of trim and list is also
possible using the ship’s draught information if necessary.
Trim/list displays are mounted on the cargo control console and on the bridge
console, in addition the trim and list is displayed on numerous screens both on
the bridge and in the CCR.
The data is displayed on the BEKA BA688C unit (NL296) graphic display
unit.
• Automatic calculation • Open Plan - Read a loading plan currently saved as a *LDP file
in the LOADPLAN directory Utility Menu
• Displacement and dead weight calculation
• Recent Loading Plan - Read a recent loading plan • Calculator - Leads the operator to the MS windows calculator
• Trim and draught (fore, aft and mean) calculation
• Save Plan - Save the current loading condition to the LOADPLAN • Control Panel - Leads the operator to the control panel where it
• Draught (fore, aft and mean) correction due to the difference in directory
the sea water density is possible to change colours, printer attributes etc
• Save as - Save the current loading condition to the LOADPLAN • Shifting - Shift a load from one compartment to another
• Heeling angle calculation directory as a different file name
• Trim and heeling adjustment by using two pair of forward and • Trimming - Carry out adjustment trim by adding cargo/ballast to
• Delete Plan - Delete the current loading plan two designated compartments:
aft tanks
• File Explorer - File explorer can be used to format discs, make • Trim with Cargo add - Control trim by adding weight
• Propeller immersion calculation back-ups and get an overall view of the file system
• Shear force and bending moments at the prescribed frame points • Trim with Cargo shift - Control trim by moving a weight
• Print - Print out the selected item
with visual • Rolling Period - Show and calculate the rolling period
• Print setup - Print set-up
• Maximum values of bending moments and shear forces with • Propeller Immersion - Shows information of propeller
their actual position • Exit - Exit the Ship Manager 88 session immersion
• Displacement and deadweight calculation based on actual • Hydrostatics - Shows following information:
draughts physically measured on the draught marks Result Menu
• Displacement, draught equivalent, LCG, LCB, MTC, LCF
• Static stability (KTM, KG, GGo, GoM) calculation • Intact Stability Results - Data and graph calculated by IMO TKM, KG etc.
• Intact stability calculation including GoM according to IMO A.749(18) criteria
A.749(18) • SF/BM Result - Table of actual shear force and bending Option Menu
• Free surface moment (Maximum /Actual) moments on each bulkhead:
• Constants - Inquiry or change deadweight constants
• SWBM and SF in the hold flooded condition cargo hold acc.to • Graph of actual value on each bulkhead
• Sea Water Density - Inquiry or change sea water density
IACS UR S17 • The ratio of shear force and bending moments ( allowable
shear force and bending moments on each bulkhead at sea • Load Limitation - Inquiry or change limitation of cargo tanks
• Damage stability according to Marpol 73/78
or in port) • Cargo Grade - Enter the name and API, density or SG of the
• Trend curve
• Maximum shear force and bending moment and their cargo (Speed button)
position • FS Moment - Inquiry or change maximum or actual inertia
• Damage Stability - Data calculated by MARPOL 73/78 criteria moment
Menu System
• Loading Status - The operator can see an image outline of the • Unit Selection - Select units for cargo calculation and others
The loading condition files are managed by use of the file menu. This menu loading status of the vessel which consists of profile, tank top • Calculation Mode - Select volume calculation before or after
contains several sub-menus and each menu function is as follows. plan and midship section loading
• Configuration - Ship Manager 88 allows the user to configure
screen set-up to individual choice
a) From the file pull-down menu the operator selects Voyage Full details of the operation and use of the Ship Manager 88 are contained in
PULL DOWN MENU the user’s manual and should be studied before using the equipment.
Description and enters the relevant details.
This controls the loading program, all main menus can be accessed by the pull-
down method. b) From either the pull-down menu or a speed button open a new
loading condition or one from the stored examples.
SPEED BUTTON MENU
c) Using the function key F2 or the pull-down menu, save the file
On the toolbar there are a series of speed buttons that have the same function giving it a name. Where the plan is an old example the Save As
as the pull-down menus, by clicking on the appropriate button the respective
menu would be used with a new name.
menu is displayed.
d) From the speed button toolbar select ‘Grade’. Enter the grade
and either the API, density or specific gravity into the relevant
column. The table automatically updates the other two columns
and selects the correct PM table.
Ship Side
Key
LNG Liquid*
Gas Line*
Spray Line
3,360mm or 3010 from 16” flange
Heavy Fuel Oil
Diesel Oil 3400mm
25mm
125mm
The cargo manifold system is situated in the area between No.3 liquid dome
The principal particulars are as follows:
and No.3 vapour dome, and comprises two 700mm branch liquid headers
extending out to the port and starboard from the main fore and aft liquid header
Manifolds towards the ship’s sides. Each liquid branch header reduces down and splits
to provide two 500mm liquid connections, two forward and two aft of the
Manifold height above waterline at design draught 20.951m
vapour manifold to which the portable reducer/spool connection piece, with the
12.0m
strainers in position, are connected and ultimately the cargo arms.
Spacing between liquid line and vapour line 3.50m
Distance between ship manifold QCDC spool piece and 3.01m The 650mm vapour branch header extends from the 700mm fore and aft
ship side main vapour header towards each ship side, it also reduces to provide a single
Distance between centre of manifold flange and working 1.6m 500mm connection with a portable reducer/spool connection piece, port and
platform starboard.
Distance between working platform and upper deck 4.351m
Each liquid manifold has a manual shut-off and an automatic valve, whereas
Distance between centre of manifold flange and upper 5.951m
the vapour manifold has an automatic valve only, the manual shut-off valve is
deck
located on the inboard side of the automatic valve. The automatic valve (ESD
Rail height 1.14m valve) is connected to the ESD system on board, and in the event of an ESD
situation occurring can be closed either from the ship or shore.
Reducers/Spool Piece
Cargo Manifold and Spray Header Connection
QCDC connection piece Liquid 4 pieces 20"/20"
length 350mm 8 pieces 20"/16" On each liquid manifold are connections into the spray header, located between
Vapour 1 piece 20"/20" the ESD valve and the manual shut-off valve. These connections, together with
2 piece 20"/16" the respective cooldown valves, can be used by the operator to cool down or
Reducer for STS Liquid/Vapour 4 pieces 16"/8" drain the main liquid header and shore arms.
Bunkering connections JPI 150PSI 2 pieces 12"/10"
Each liquid manifold is provided with two pressure relief valves, located
2 pieces 12"/8" inboard and outboard of the ESD valve, which in the event of a pressure build-
2 piece 12" x 6" up between the manual shut-off valve and the ESD valve or the ESD valve and
2 piece 6" x 4" the blank flange, would drain back to No.4 or No.5 cargo tank liquid dome.
2 piece 4" x 3" At the top of each liquid manifold is a pressure gauge connection and sample
Nozzle for cargo jettison 16" flange reducing to 8" outlet, to extend not vent with a quick connection for a nitrogen purge, there is also a drain cock on
approx 6.5 metre length less than 3 metres outboard of ship’s side. the bottom of the line outboard of the ESD valve.
On the vapour manifold there is no manual shut-off valve, only the automatic
Bi-Directional Conical Strainers
ESD valve with a small 25mm bypass line and valve for purging purposes.
Stowed in box on manifold deck for each ship’s side 8 sets x 60 mesh
There is also a pressure gauge connection, drain cock and sample vent with a
quick connection.
Each manifold is also provided with a small davit for use during the connection
or disconnection of the spools and reducers and for inspection of the
strainers.
Before arriving at the LNG terminal, ensure that the 60 mesh strainers in the
liquid manifolds are clean and securely bolted in place by the QCDC spool
pieces, to ensure that no debris can enter the cargo tanks or be discharged to
the receiving terminal during the cargo loading or discharge.
1020mm 584mm 495mm 483mm 393mm 470mm
The strainer is constructed and designed for bi-directional flow so that it can be
left in place after inspection without having to be turned round 180 degrees.
After the flow rates have stabilised, the deck watch should periodically notify
the CCR of the pressure on each of the four liquid manifold gauges and the
pressure on the liquid crossover gauges.
A 42mm
60mm
Section A-A
Outer Strainer
Support
Inner Strainer
Support
RN832
CR
CG811 CN951 RR822
002
CR863 RN841
LNG Vaporiser RN867
RL820
RN836
RN834
CR862 No.1 H/D Demister RN837
CS051
CS804 Pre-Cooler CG816 CG802 CG804 RN871 CR008 005
Compressor Vessel CR
CS803 CR007 006
RN802
CG818 CG819
RN835
RR823 RN870
RG816 RG810 RN801
RR813
RN831
RR820 CL022 CL024 CL023 CL021
RR821
RN865
RL816 Heater CG826
CG841
CS052
RG822 1 st
2 nd RG802 RG804
CG832 RN838 CS064 CS063
RL819 RL818 RL817
RN842
RN879 RN829 RN868 RN827 RN825 RN823 RN821
No.2 BOG Compressor No.1
CS801 CG833 BOG Heater
RN840 Oil Separator Dryer Separator
RR809
RL827 CG825 CG072 CG071
RG815 RG809 RN833 RN866
CG839 CG831
RL829
CG078 CG077
RL805 RL832
RL806 RL831
CG820
RN809 RN810
RN806
RR811
RL823 RL824
Vent RG843
RN804
Pumps RG827
Gas CR011 CR010
Heater RN820 RN819 RN816
RG846
RG845 RG826 RG844
RL810 RL848 RG849 RG825 CG CR012 CR009
RL808
RR810
RC804
RG850
RG847
No.2 Separator Expander Module
RG851
RN807 RN808
RN805
RL849
RL815
RL807
RG842
RN803
To Gas
Combustion CG900 RN864 RN818 RN817 RN815
Unit
CG901 RC810 RC809
EXP 3rd 2nd 1st
No.1 Nitrogen Key
RC803 Compressor /
Expander Module LNG Liquid*
CG604
RC806 RC805
650 Vapour Return to Shore LNG Vapour*
650 Cargo Vapour
From Inert Gas Dryer Cargo Liquid
Nitrogen*
CG001 700
and Plant CG 700 Cargo Liquid
CG702
CG608 CG607 079 125 Spray Main
CG606
CG605
CG610
CL601
CR602
CR706
CG611
CG609
CL701
CG703
CG701
CR701
CL757 CS756 CS752 CS751
GCU N2
Vent Line CG171
CR702
CR CR
CL310
CL110
CL510
SAS551
707
SAS151
SAS451
CL210
413
SAS351
SAS251
CL410
CS155
CS255
CS555
CS355
CS455
CR CR CR CR CR
511 411 311 211 111
CG571
CG471
CG271
CG171
CG371
CR CR CR CR CR
512 412 312 212 112
CS560
CS456
CS460
CS156
CS356
CS556
CS254
CS154
CGR CGR CGR CGR CGR
CR513
CR414
CS557
CS457
CS554
CS454
CL508
CL308
CL501
CL107
CL401
CL301
CL208
CL201
CL101
CS150 CS157
CS350 CS356
CL408
CS250 CS257
501 401 301 201 101
CG570
CG470
CG370
CG270
CG170
CR561
CR461
CR309
CR209
CR109
CS552
CS552
CS551
CS450
CS401
CS402
CS352
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
CL207
CL202
CL200
CL106
CL102
CL100
Port Port Port Port Port
CL504
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
Starboard Starboard Starboard Starboard Starboard
No.2(P) No.1(S) No.5 Tank No.2(P) No.1(S) No.4 Tank No.2(P) No.1(S) No.3 Tank No.2(P) No.1(S) No.2 Tank No.2(P) No.1(S) No.1 Tank
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 2nd 1st RG821
Cold Box
CS052
No.1 BOG Compressor
No.1 No.2
LNG Transfer CS064 CS063
CG880
Gas Pumps
RL830
CG852 CG854 RG847
Combustion RG810 RG816 To Separator
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 RG822
2 nd
1 st
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Nitrogen*
Vapour Return Line
Inert Gas*
CG807 CG808 Gas Line*
CG809 Spray Line
Dry-Air Supply
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
During single tank operations it is possible to connect the gas main to the inert The cargo compressor room lines and the vapour return line can also be purged
gas generator by means of a removable bend. with inert gas or air by means of a spool piece and isolation valve on the line
leading to this space. There is also a means to inert the compressor room via
At certain points along the gas main, blank flanges and sample points are fitted its own IG supply line with an isolation valve and spool piece.
to facilitate the taking of readings during pre and post-refits.
The ballast spaces can be also be connected to the IG system through an
isolation valve and spool piece to the ballast main.
CL CRR CS CG
410 413 455 471
CSR Key
412
LNG Liquid
SAG474 SAG471
CS456 LNG Vapour
No.4
Vent Mast
CL408 CS450 CS457 SAG473 Gas Line
CL CL CL CL CS CR
CSR Spray Line
401 402 400 407 454 460 SAS451 SAG470
411 CGR402
CS
SAL403 413
SAL432
Port
Float Radar
Type Level Beam Type
Starboard
Gauge Level Gauge
Sprayers
Emergency
CL CL Pump Column
403 404
Illustration 4.2.1d Spiral-Wound Jointing Minimum Tightening Torque as Recommended by the Gasket
Manufacturer
20
25mm 4 x 15.9 30.9
R3
2 -150
3STA
163
50mm 4 x 19.0 90.5
65mm 4 x 19.0 108.9
80mm 4 x 19.0 133.3
100mm 8 x 19.0 99.1
125mm 8 x 22.2 151.4
150mm 8 x 22.2 179.8
200mm 8 x 22.2 229.3
250mm 12 x 25.4 258.6
Hoop (Metal Winding) Filler 300mm 12 x 25.4 307.2
350mm 12 x 28.6 413.4
400mm 16 x 28.6 486.3
Graseal Inner Outer
Ring Ring 450mm 16 x 31.7 625.3
Expanded Graphite Filler Vortex Gaskets 500mm 20 x 31.7 609.7
550mm 20 x 35.1 698.2
TOMBO No. - 1839R 600mm 20 x 34.9 809.4
Size - Class 150 2" 650mm 36 x 22.2 186.8
Metal Winding - Stainless Steel 316
700mm 40 x 22.2 203.4
750mm 44 x 22.2 187.9
Filler - Flexible Graphite
800mm 48 x 22.2 172.8
Inner Ring - Stainless Steel 316
Fibreglass Reinforced
Plastic Protective Layer
PUF
PUF
Pipe 15-700mm
32-100mm
Outer Layer for all Size Pipes 2mm Fibreglass Reinforced Plastic (FRP)
Fibreglass Reinforced
Plastic Protective Layer
Type 2
PUF
Outer Layer for all Size Pipes 2mm Fibreglass Reinforced Plastic (FRP)
Cargo liquid and vapour pipes are insulated and pipes can be easily identified.
Liquid:
• 32 - 100mm diameter pipes: 25 + 25mm thick - two layers
• Above 125mm diameter pipes: 40 + 40mm thick - two layers
• 25mm diameter and under: 30mm thick - single layer
Vapour:
• 32 - 100mm diameter pipes: 20 + 20mm thick - two layers
• Above 125mm diameter pipes: 30 + 30mm thick - two layers
• 25mm diameter and under: 30mm thick - single layer
Type 1
Insulation of type 1 is for large diameter pipes and consists of two layers of
PUF (polyurethane foam) of density 40kg/cm3 on pipes and 300kg/cm3 at
supports. The outer layer is covered by 2mm thick fibreglass reinforced plastic
(FRP). The FRP cover is used to prevent water/vapour from leaking into the
insulation and also protects it from mechanical damage.
Type 2
Insulation of type 2 for pipes of 25mm and below has one layer of PUF and is
covered by a 2mm layer of FRP.
200 500
Head
End Bell Assembly 180 450
H
160 400
P
Shaft Power at 0.50 SG
100 250
Housing Assembly
80 Efficiency 200
E
40 100
NPSHR
20 50
0 0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800
Bearing Assembly
Flow (m³/h)
Impeller Assembly
Inducer
Reference Ebara International Drawing: PPC-408001 Rev. B - Calculated Pump Performance Curves
Relay: 24.2 amps • If the pump has been stopped by a low current signal, this is an No.2 cargo switchboard: Main cargo pump 2 in tank No.1
Delay (start-up): 10 secs automatic feature fitted inside the pump’s starter panel. Main cargo pump 2 in tank No.2
Delay (normal): 10 secs • A gas dome low low pressure alarm exists in the pump’s Main cargo pump 2 in tank No.3
associated cargo tank. Main cargo pump 2 in tank No.4
• A gas dome high high pressure alarm exists in the pump’s Main cargo pump 2 in tank No.5
Overcurrent
associated cargo tank.
Relay: 52.3 amps The motors are controlled using soft starters via circuit-breakers. After starting,
Delay (start-up): 5 secs When starting a pump, the discharge valve will have to be opened to between the current should go to the starting value and then decrease to the normal
Delay (normal): 0 secs 15% and 25% (normally 20% from experience), before initiating the start operating current within a period of approximately 3 seconds. If the starting
sequence, with the valve then being controlled through the DACS. The valves current has not decreased to the normal operating value after 10 seconds, the
Low discharge pressure:
are operated in automatic mode where the set point of the valve can be adjusted pump must be stopped and the cause of the high starting current investigated.
Relay setting: 200kPa(g) through the DACS keyboard to a value of between 0% and 100%.
Delay setting: 10 secs Note: The minimum liquid level in a cargo tank to allow the main cargo
pumps to start during bulk cargo operations is 1,000mm, but this figure can
be reduced to 580mm for pump restarts during stripping operations.
Controller No No
Auto First Pump
in Tank?
Yes
No
Feedback Start Pump
Pump Running No.1
Yes Stop
Sequence
Release
Controller
for Discharge
Valve
b) Check the level of the liquid in the tank. The tank liquid level Pump Restarts (Normal)
Overload Starting
must indicate that the pump housing is completely submerged, The restart of any pump during normal operations is restricted, depending on
for an initial start the DACS permissive start level is 1200mm, the liquid level above the submerged electric motor and is normally 1200mm, If the starting current increases to its maximum value but then falls to an
the pump manufacturer’s minimum tank level for a pump start but no pump can be restarted with the tank level below the minimum liquid intermediate level between the starting value and the normal full load current
is 1,000mm. The temperature indicator in the tank must also be level of 580mm. and the pump is known to be turning, check the starting voltage. If the voltage
stable at the specification temperature of the liquid. falls below 10% of the normal value, the problem may be with the power
During a normal restart sequence the following times apply: supply.
c) Before starting the pump, from the DACS graphic display open • 1st restart: minimum 5 minutes after shutdown
the pump discharge valve to between 15% and 25%. If the pump Single-Phase Fault
discharge valve is open less than 20%, the start-up sequence will • 2nd restart: 15 minutes after 1st restart
If the starting current increases to its maximum value and remains high, a
not operate. Conversely, starting the pump with the valve fully • 3rd restart: 15 minutes after 2nd restart single-phase fault in the power supply may exist. Checking the voltages and
open when pumping liquid which has a high specific gravity, current in each phase will determine if this is the case.
will overload the motor. • No more than 4 restarts within one hour (DACS will not permit
more)
d) Start the cargo pump using the DACS by clicking on the PUMP Reversed Rotation
icon in the screen display to bring up the faceplate and clicking The cargo pumps may be restarted consecutively a maximum of 3 times. After
the third time a 30 minute waiting period must be applied and then another 3 If during the start-up procedures, the current falls to around the no-load current
on the RUN soft key. The operator should keep a close watch on value and the discharge pressure is 75% or less than normal, the pump may be
starts can be made. This procedure must be adhered to as heat build-up from
the discharge pressure and the motor current. operating in the wrong direction. To correct this, disconnect the power supply
the high starting current may not be carried away during stripping operations,
which may be due to the lack of liquid flow when (and if) the pump does not at the main isolator and change over two of the phases to the pump. The pump
e) During the starting procedure and while the discharge pipe is can then be restarted and checked for correct operation.
prime, due to the extremely low level of LNG during stripping operations.
being filled, the current may be above the ammeter red line.
After starting, the current should go to the starting value and
The pumps are started and stopped from the CCR via the IAS system, but in an Low Liquid Level
then decrease to the normal operating current within a period
emergency all of the pumps can be stopped by the activation of the emergency
of approximately 3 seconds. If the starting current has not If during the start-up procedures the current falls close to the no-load value and
shutdown system (ESDS).
decreased to the normal operating value after 10 seconds, the the discharge pressure is near to zero, a low suction level may be the cause.
pump must be stopped and the cause of the high starting current As detailed previously, the minimum tank level for a pump start should not be
investigated. Pump Restarts (Emergency) less than 580mm.
If attempting an emergency restart of a cargo pump it is still necessary to
f) When the pump discharge pipe is filled to the discharge check that the minimum level inside the tank is above the 1,000mm level (see Note: The minimum liquid level in a cargo tank to allow the main cargo
valve, a substantial increase in the discharge pressure and a note). The pump can then be started, but a period of a least 30 minutes must pumps to start during (bulk) cargo operations is 1,000mm, but this figure can
corresponding decrease in current should be observed. be allowed to pass before attempting a restart, and then there must be no more be reduced to 580mm for pump restarts during stripping operations (Ebara
than two restarts in an hour. cargo pump manufacturers). On the DACS there is a starting interlock at
g) Once the pump is operating normally, adjust the discharge valve 1200mm.
to obtain the required flow or pressure. The operator should
monitor the pump motor running current, taking care not to Abnormal Starts
exceed the maximum current level. Discharge of Cargo
Locked Rotor
If the starting current increases to its maximum and remains while there is no Operating a pump at, or close to, its design flow capacity of 1,400m3/h is in
CAUTION
evidence that the pump is rotating, it may be because the pump has seized. If the best interests of the pump lifespan and operating performance. However,
The pumps should only ever be operated between their minimum and after investigations it is considered to be a mechanical problem, then the pump operating the pump at flow rates which are less than this cannot be avoided, this
maximum continuous discharge capacities of 511m3/h and 1,400m3/h will have to be removed from the tank for repairs. In the case of a sustained is especially the case when the shore receiving facility cannot accept the rated
respectively. Operating them outside of this range will result in damage locked rotor start, an attempt to restart the pump must only be made after a flow. However, it should be remembered that it is better to operate one pump
to the pump and decreased performance. period of at least 30 minutes has elapsed, and then with no more that two restart at the design flow rather than two pumps running at 50% flow. The pump’s
attempts in total. rated flow should only ever be exceeded during the starting period while the
discharge valve is adjusted.
Yes
Available Soft Soft Starter
Open Tank No Starter for Available
Valve Position Pump 2 for Pump 2
Filling Valve=100%
95%
CLn00
Yes
Feedback Pump No
Liquid Common Start Pump 2
Valve Position No Running
5% Valve
CLn10
Yes
Open Discharge
Valve Position
Open Discharge Release Controller Valve = 20%
Valve Position No 15%
Valve = 20% CLn02
17%
CLn01
Yes
HOLD
Release Yes
Controller
HOLD
When the liquid level reaches less than 1m above the pump inlet, avoid Overcurrent:
stopping the pump if at all possible until the cargo has been fully discharged.
• Relay: 52.3 amps
If the shore facility is unable to accept the liquid for intermittent periods, it is
preferable to keep the pump going and recirculate the liquid back into the tanks • Delay (start-up): 5 seconds
until the cargo discharge can be resumed and completed. • Delay (normal): 0 seconds
• Always try to run the cargo pumps at the design flow rate • Relay setting: 0.37m
whenever possible.
160 24
P
100 15
Housing for
Motor 80 12
60 Efficiency 9
E
40 6
20 3
NPSHR
Bearing Assembly
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Flow (m³/h)
Impeller Assembly
Inducer
Reference Ebara International Drawing: PPC-408002 Rev C - Calculated Pump Performance Curves
Controllers
in Auto
Open Spray
Error
Valve Position Return Valve=
>95% 100%
CSn64
Yes
Open Spray
Valve Position Return Valve Error
>17% 20%
CSn60
Yes
Error
Pump Running Start Pump
Release Spray
Pump Current
Controller
Release Spray
Line Pressure
Controller
End
Stop Sequence
240 192.0
Top Bearing
220 176.0
HEAD
P
200 160.0
120 96.0
Rotor
100 80.0
Stator
80 Efficieny 64.0
E
60 48.0
40 32.0
20 NPSHR 16.0
0 0.0
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
Lower Bearing
Flow (m³/h)
Automatic Thrust
Balancing Device
Impeller
Pump Inlet
Reference Ebara International Drawing: PPC-408003 Rev C - Calculated Pump Performance Curves
The emergency pump will be stopped automatically should any of the following
Abnormal Starts occur:
Locked Rotor • Activation of the ship or shore emergency shutdown (ESD)
system
If the starting current increases to its maximum and remains while there is no
evidence that the pump is rotating, it may be because the pump has seized. If • Motor single-phasing
after investigations it is considered to be a mechanical problem then the pump • Low electric motor current (undercurrent) - 76A for 10 seconds
will have to be removed from the tank for repairs. In the case of a sustained during start-up and 10 seconds during normal running
locked rotor start, an attempt to restart the pump must only be made after a
Operating Procedures n) Start the compressor. The shaft vibration monitoring system is
Capacity Control released after approximately 14 seconds. Check that no alarm or
The compressor controller detects the pressure in the vapour main pipeline To prepare the HD compressors for operation, proceed as follows: trip lamps are on.
and alters the guide vane position to meet the pressure required. It is possible
to change the guide vane control to LOCAL mode if required, but a bumpless a) Check the oil level in the compressor sump tank. o) Check the bearing temperatures and the vibration levels.
transfer is required when returning back to REMOTE operation.
b) Start the LO heater between 1 and 6 hours prior to the expected p) The auxiliary (standby) LO pump should stop after the
compressor start-up, depending on the ambient temperature. compressor-driven pump has run up to speed and is delivering
Compressor Trips
full system pressure.
The following conditions trip the HD compressors: c) Ensure that the nitrogen seal gas supply manual valve is open.
Observe the following parameters:
• The emergency shutdown system (ESD)
d) Open the compressor suction and discharge valves.
• Tank high high level alarm 99% q) The seal gas differential pressure should read 20kPa to 25kPa.
• High high gas discharge temperature e) Run the auxiliary LO pump to warm-up the gearbox and Adjust the supply reducer if required.
bearings. Check the LO system for leaks.
• High high bearing temperature r) The LO supply pressure should read between 150kPa and
• Excessive rotor vibration f) Open the cooling water inlet and outlet valves for the LO cooler 160kPa. Adjust the supply regulator if required.
and ensure cooling water is available.
• Low low pressure - bulkhead
s) The LO supply temperature to the gearbox should be above
• Low low system LO pressure - gearbox g) Ensure that the instrument air supply to the control panel is 30°C.
• High high LO temperature - bulkhead operational.
t) Check the local control panel for alarms.
• Low low gas seal pressure h) Switch on the power to the control cabinet and reset any
• Electrical power failure alarms. u) Check the complete operating system for oil, seal gas, air, water
and product leakage.
Non-trip alarms are indicated on the DACS and are listed as follows: i) Check with the ECR that there is sufficient power available at
the cargo switchboards. To avoid the build-up of pressure inside the compressor, the suction and
• Compressor discharge gas temperature - high
discharge valves should remain open when the machine has been stopped.
• Compressor LO filter differential pressure - high In the cargo control room:
• Compressor gearbox LO pressure low
j) Select the HD compressor DACS screen mimic for the appropriate
• Oil tank level low operation.
• Oil tank temperature high
k) Press the compressor’s RESET button and check if all of the
• Oil tank temperature low alarms and trip lamps are off and if the READY TO START
• Temperature of oil system high lamp is on.
• Temperature of oil bulkhead
Note: Ensure that the anti-surge valve, inlet guide vanes, electric motor-
• LO bulkhead pressure low driven and auxiliary LO pumps are all set to the AUTO mode.
• Oil tank temperature low
l) The inlet guide valve should to be set at 73°, which equates to
• Seal gas pressure low
the minimum open position (0%). The anti-surge controller is
• Motor aft bearing temperature set at minimum, ie, the bypass valve is fully open.
• Motor forward bearing temperature
Position Description Valve Procedure for Shutting Down the High Duty Heater
Open High duty heater condensate drain trap outlet CS35
valve a) Close the LNG inlet valve CG861 to the heater.
Closed High duty heater condensate drain trap CS34 b) Allow the inlet and outlet temperatures to equalise.
bypass valve
c) Close the steam supply valve CS28 to the heater.
c) Open the heater shell side vent valve to the save-all.
d) Crack open the shell side vent valve and slowly reduce the
Note: The high duty heater does not have a steam inlet bypass, so warming pressure in the heater.
through is carried out using the main steam inlet supply valve.
e) Once the shell pressure is at atmospheric pressure, fully open
d) Crack open the heating line steam inlet valve CS28 and the shell vent valve.
commence warming-through the heater.
f) Close the condensate inlet and outlet valves CS33 and CS35 to
e) When the heater shell side vent valve starts to exhaust steam, the steam trap and open the bypass valve CS34.
close in the valve to the save-all until it is just cracked open.
Allow the heater to slowly warm-through and close the valve g) Close the LNG outlet valve CG862 from the heater.
when the condensate outlet temperature is approximately
164°C.
The procedure for setting up the Low Duty heater into operation is the same as
that detailed above except for the valve numbering.
Note: The cargo machinery room exhaust fans and the gas sampling system
must be in operation prior to and during any cargo operations which involve
LNG entering the cargo machinery room pipework system.
CAUTION
Thorough checks around the heater and the associated flange connections
must be conducted during operation.
The vent gas is heated to ambient temperature in a vent gas heater upstream of Note: The vent gas heater does not have a steam inlet bypass, so warming
the GCU, and the outlet temperature is controlled to ensure that the temperature through is carried out using the main steam inlet supply valve.
stays within the GCU operating limitations.
d) Crack open the heating line steam inlet valve CS62 and
commence warming-through the vent gas heater.
Introduction
e) When the vent gas heater shell side vent valve starts to exhaust
There is one steam heated vent gas heater provided in the cargo machinery steam, close-in the valve to the save-all until it is just cracked
room to warm-up any of the gaseous natural gas (GNG) produced from the open. Allow the vent gas heater to slowly warm-through and
cold box separator during the cooling sequence of the reliquefaction process close the valve when the condensate outlet temperature is
prior to it being burned in the gas combustion unit. approximately 164°C.
Procedure for Preparing the Vent Gas Heater for Use f) Once the steam pressure has risen to the operating pressure,
slowly fully open the main steam inlet valve CS62. The vent gas
a) Ensure that the engine room control air supply valve to the cargo heater is now ready for use.
control room is open. (Normally never closed.)
g) Open the vent gas heater gas outlet valve RG842.
b) Set up the valves as in the following table:
h) Open the vent gas heater gas inlet valve RG843.
Position Description Valve i) Open the vent gas heater control isolation valves RG848 and
Open Engine room main steam isolating valve to T101 RG849.
the deck
Open Condensate return valve to the dump T62V j) Confirm that control valve bypass RG847 is closed.
condenser/drain cooler
Closed Bypass valve on the dump condenser/drain T61V k) Operate the three-way valve RG827 to direct GNG to the
cooler heater.
Open Drain cooler for cargo heater inlet valve CS56
l) Operate the control valve RG827 to supply GNG to the heater.
Open Drain cooler for cargo heater outlet valve CS57
Closed Drain cooler for cargo heater bypass valve CS55 m) Monitor all of the pressures and temperatures until the vent gas
Open Drain cooler for cargo heater FW cooling FC31 heater has stabilised.
inlet valve
Open Drain cooler for cargo heater FW cooling FC32 CAUTION
outlet valve
Thorough checks around the heater and the associated flange connections
Closed Drain outlet valve on the gas vent drain tank CS58 must be conducted during operation.
CAUTION
Thorough checks around the LNG vaporiser and the associated flange
connections must be conducted during operation.
d) Crack open the shell side vent valve and slowly reduce the
pressure in the vaporiser.
f) Close the condensate inlet and outlet valves CS30 and CS32 to
the steam trap and open the bypass valve CS31.
Note: The cargo machinery room exhaust fans and the gas sampling system
must be in operation prior to and during any cargo operations which involve
LNG entering the cargo machinery room pipework system.
RN832
Tanks CG801 CN951 RR822
CG844
RL820
CG821 CG834
RN836
RN834
Cargo De-Mister
CR863 Pre-Cooler CG831 No.1 H/D CG833 CG832 RN837
Tanks CG871
Vessel
Compressor
CS873
RN802
CG883 CG882
RN835
44 RR823 RN870
RG816 RG810
RN831
High Duty Bar RN801
CG861 RR820
RR821
RN865
RL816 Heater
RR813
CG862
CG881
RG822 1st 2nd RG802 RG804
RL819 RL818 RL817 RN838 Oil
RN842
RN879 RN829 RN868 RN827 RN825 RN823 RN821
No.2 BOG Compressor Separator No.1
CS861 BOG Heater
RN840 Dryer Separator
RR809
RL827 CG852
RG815 RG809 No.1 Nitrogen Booster Compressor RN833 RN866
CG851
RI829
RL805 RL832
RL806 RL831
CG880
RN809 RN810
RG821 RG801 RG803 RN806
RL821
RL823 RL824
RG846
RG845 RG826 RG844
RL848 RG849 RG825 CG
RL810 RL808
No.1 Cold Box 900 RC812 RC811 No.2 Nitrogen
RR810 EXP 3rd 2nd 1st
Compressor /
RL811
RL822
RC804
RG850
RG847
No.2 Separator Expander Module
RG851
RR808 RC808 RC807
RL815
RL809
RN807 RN808
RL807 RL849
RN805
RL842
To Separator RG848 RN813
RL813
Cryogenic Heat RR803 RR801
RL830
RN863 RN851 RN850 Exchanger
To Gas RN803
Combustion CG900 RN864 RN818 RN817 RN815
Unit CG901 No.1 Nitrogen
RC810 RC809
EXP 3rd 2nd 1st Compressor /
RC803 Expander Module
RC806 RC805
Reliquefaction System
Vent
BOG +100
Compressor 0 +100
+100
-100 Cold 0
Boil-Off 0
-200 Box -100
+100
Gas -100
-200
0
Pre-Cooler -200 -100
-200
+100
0
Nitrogen
-100
Reservoir
-200
To / From Separator
Cooling Water
System
+100
LNG Transfer Key
0
-100
Pump +100
LNG Liquid*
Compressor / Expander 0
-200 +100
-100 LNG Vapour*
0
-100
-200 Nitrogen
-200 To Tanks
RN832
CR
CG811 CN951 RR822
002
CR863 RN841
LNG Vaporiser RN867
RL820
RN836
RN834
CR862 No.1 H/D Demister RN837
CS051
CS804 Pre-Cooler CG816 CG802 CG804 RN871 CR008 005
Compressor Vessel CR
CS803 CR007 006
RN802
CG818 CG819
RN835
RR823 RN870
RG816 RG810 RN801
RR813
RN831
RR820 CL022 CL024 CL023 CL021
RR821
RN865
RL816 Heater CG826
CG841
CS052
RG822 1 st
2 nd RG802 RG804
CG832 RN838 CS064 CS063
RL819 RL818 RL817
RN842
RN879 RN829 RN868 RN827 RN825 RN823 RN821
No.2 BOG Compressor No.1
CS801 CG833 BOG Heater
RN840 Oil Separator Dryer Separator
RR809
RL827 CG825 CG072 CG071
RG815 RG809 RN833 RN866
CG839 CG831
RL829
CG078 CG077
RL805 RL832
RL806 RL831
CG820
RN809 RN810
RN806
RR811
RL823 RL824
Vent RG843
RN804
Pumps RG827
Gas CR011 CR010
Heater RN820 RN819 RN816
RG846
RG845 RG826 RG844
RL810 RL848 RG849 RG825 CG CR012 CR009
RL808
RR810
RC804
RG850
RG847
No.2 Separator Expander Module
RG851
RN807 RN808
RN805
RL849
RL815
RL807
RG842
RN803
To Gas
Combustion CG900 RN864 RN818 RN817 RN815
Unit
CG901 RC810 RC809
EXP 3rd 2nd 1st
No.1 Nitrogen Key
RC803 Compressor /
Expander Module LNG Liquid*
CG604
RC806 RC805
650 Vapour Return to Shore LNG Vapour*
650 Cargo Vapour
From Inert Gas Dryer Cargo Liquid
Nitrogen*
CG001 700
and Plant CG 700 Cargo Liquid
CG702
CG608 CG607 079 125 Spray Main
CG606
CG605
CG610
CL601
CR602
CR706
CG611
CG609
CL701
CG703
CG701
CR701
CL757 CS756 CS752 CS751
GCU N2
Vent Line CG171
CR702
CR CR
CL310
CL110
CL510
SAS551
707
SAS151
SAS451
CL210
413
SAS351
SAS251
CL410
CS155
CS255
CS555
CS355
CS455
CR CR CR CR CR
511 411 311 211 111
CG471
CG571
CG271
CG371
CR CR CR CR CR
512 412 312 212 112
CS560
CS456
CS460
CS156
CS356
CS556
CS254
CS154
CGR CGR CGR CGR CGR
CR513
CR414
CS557
CS457
CS554
CS454
CL508
CL308
CL501
CL401
CL301
CL208
CL107
CL201
CL101
CS150 CS157
CS350 CS356
CL408
CS250 CS257
501 401 301 201 101
CG570
CG470
CG370
CG270
CG170
CR561
CR461
CR309
CR209
CR109
CS552
CS552
CS551
CS450
CS401
CS402
CS352
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
CL207
CL202
CL200
CL106
CL102
CL100
Port Port Port Port Port
CL504
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
Starboard Starboard Starboard Starboard Starboard
No.2(P) No.1(S) No.5 Tank No.2(P) No.1(S) No.4 Tank No.2(P) No.1(S) No.3 Tank No.2(P) No.1(S) No.2 Tank No.2(P) No.1(S) No.1 Tank
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
The compressed boil-off gas transferred from the BOG compressor is cooled Manufacturer: Nordon Cryogenie SAS The LNG pump skid unit consists of the following main equipment:
and condensed in a large multi-pass heat exchanger called a cold box. The Material: 3003 aluminium • Pump
temperature in the heat exchanger is lowest at the bottom (-164°C) and
Duty N2 Pass 1: 7,633kW
highest at the top where it is slightly above the cooling water temperature. The • Pump bearing heater
low pressure nitrogen flows through from the bottom of the cryogenic heat Duty N2 Pass 2: 6,330kW
• Vent gas heater
exchanger to the top before it is returned to the suction side of the first stage Duty LNG Pass 3: 1,303kW
compressor on the nitrogen compander. Design pressure: 1.0/6.3/4.0MPa • Control panel
Design temperature: -196°C/+65ºC • Flow element with transmitter
The heat exchanger temperature is allowed to change at a maximum rate of 1°C
per minute, and the expander bypass valve protects the cold box temperature
from changing quicker than this. Separator LNG Transfer Pumps
CR001
From Nitrogen Purging/ RN601
RR824 CR004
Sealing Line
CR002
RN602
RN832
CN951 RR822 CR003
CG811
CR703
RN846 RN847 RN848 RN849
CR863
CR005
LNG Vaporiser RN841 RN867 CS062 CS061
RL820
CG821 CG810
CS051
CR008
RN836
RN834
CR006
CR862 Pre-Cooler CG816 No.1 H/D CG802 CG804 Demister RN837
CS804 RN871
Compressor Vessel CR007
CS803
RN802
CG818 CG819
RN835
RR823 RN870 CL022 CL024 CL023 CL021
RG816 RG810 RN801
RR813
RN831
RR820
CS052
RR821
RN865
RL816 Heater CG826 CS064 CS063
CG841
RG822 1st 2nd RG802 RG804
CG832 RN838
RL819 RL818 RL817
RN842
RN879 RN829 RN868 RN827 RN825 RN823 RN821
No.2 BOG Compressor No.1
CS801 CG833 BOG Heater CG072 CG071
RN840 Oil Separator Dryer Separator
RR809
RL827 CG825
RG815 RG809 RN833 RN866
CG839 CG831 CG078 CG077
RL829
CS066 CS065
RL805 RL832
RL806 RL831
CG820
RN809 RN810
RN806
RR811
RL823 RL824
RN804
Pumps RG827
Gas
RN820 RN819 RN816 CR012 CR009
Heater
CG801
RG846
RG845 RG826 RG844
RL810 RL808 RL848 RG849 RG825
RR810
RC804
RG850
RG847
No.2 Separator CL042 CL044 CL043 CL041
Expander Module
RG851
RN807 RN808
RN805
RL849
RL815
RL807
RG842
RG848 RN813
To Separator CR016 CR013
Cryogenic Heat RR803 RR801
RL830 RL813 RN863 RN851 RN850 Exchanger
RN803
To Gas Key
Combustion CG900 RN864 RN818 RN817 RN815
Unit LNG Liquid*
CG901 RC810 RC809 No.1 Nitrogen
EXP 3rd 2nd 1st LNG Vapour*
RC803 Compressor /
Expander Module
RC806 RC805 Nitrogen*
CG802
650 Vapour Return to Shore
650 Cargo Vapour
From Inert Gas Dryer CG001 700 Cargo Liquid
CG079
and Plant 700 Cargo Liquid
CG702
CG608 CG607 125 Spray Main
CG606
CG605
CR704
CG610
CL601
CR602
CR706
CG611
CG609
CR601
CR705
CL700
CG703
CG701
CR701
CL757 CS756 CS752 CS751
GCU N2
Vent Line CG171
CR702
CR707
CR413
SAS551
SAS451
SAS251
SAS351
SAS151
CS555
CS355
CS255
CS155
CR511
CR411
CR311
CR211
CR111
CS455
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CR512
CR412
CR312
CR212
CR112
CS560
CS460
CS456
CS356
CS256
CS156
CS556
CS254
CS154
CGR CGR CGR
CS554
CGR
CL408
CGR
CR513
CR414
CS557
CS454
CS457
CL508
CL501
CL308
CL208
CL107
CL401
CL301
CL201
CL101
CS150 CS157
CS350 CS356
CS250 CS257
501 401 301 201 101
CG570
CG470
CG370
CG270
CG170
CR561
CR461
CR309
CR209
CR109
CS552
CS552
CS551
CS450
CS401
CS402
CS352
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
CL207
CL202
CL200
CL106
CL102
CL100
Port Port Port Port Port
CL504
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
Starboard Starboard Starboard Starboard Starboard
No.2(P) No.1(S) No.5 Tank No.2(P) No.1(S) No.4 Tank No.2(P) No.1(S) No.3 Tank No.2(P) No.1(S) No.2 Tank No.2(P) No.1(S) No.1 Tank
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Position Description Valve g) When all the machinery systems are operating, check that • Oil temperature in the oil tank to be >20°C (minimum)
the correct temperatures and pressures are being maintained • Oil temperature at the gearbox inlet when in operation:
Open No.1 HD compressor LO cooler inlet valve FC21
throughout the systems. Check also for system leaks when at the Approximately 48°C
Open No.1 HD compressor LO cooler outlet valve FC22 correct operating temperature.
Open No.2 HD compressor LO cooler inlet valve FC25 • Oil pressure when the compressor is in operation to be nominally
Open No.2 HD compressor LO cooler outlet valve FC26 Additional information: 2.5 bar(g), although this can vary between 2.5 and 3.0 bar(g)
Open No.1 HD compressor motor inlet valve FC19 • Water inlet temperature: Approximately 38°C • Differential pressure across the filters in operation should be
Open No.1 HD compressor motor outlet valve FC20 approximately 0.2 to 0.5 bar
• Water outlet temperature: Approximately 46°C when operating
Open No.2 HD compressor motor inlet valve FC23
• Cooling water operating pressure: >1.5 bar(g) BOG Compressor Cooling Water
Open No.2 HD compressor motor outlet valve FC24
Open Nitrogen compressor (skid No.1) inlet valve FC03 • Main electric motor cooling water flow rate: 60m3/h This system should be lined-up in accordance with the procedure already
Open Nitrogen compressor (skid No.1) outlet valve FC01 • Oil cooler cooling water flow rate: 29m3/h detailed for the nitrogen compander.
Open Nitrogen compressor (skid No.2) inlet valve FC04 • Gas cooler cooling water flow rate: 512m3/h Additional information:
Open Nitrogen compressor (skid No.2) outlet valve FC02
• Water inlet temperature: Approximately 36°C
Open No.1 nitrogen booster compressor inter-cooler Seal Gas System
inlet valve • Outlet temperature: Approximately 46°C when in operation
Confirm that the supply gas quality is within specification and that the system
Open No.1 nitrogen booster compressor inter-cooler • Cooling water operating pressure: >1.5 bar(g)
is in operation before the auxiliary oil pump is started.
outlet valves (2)
• Main electric motor cooling water flow rate: 7.3m3/h
Open No.2 nitrogen booster compressor inter-cooler Additional information:
inlet valve • Oil cooler cooling water flow rate: 8.2m3/h
• Seal gas system pressure: 0.2 bar
Open No.2 nitrogen booster compressor inter-cooler
outlet valves (2) • Seal gas expander to atmosphere: 0.1 to 0.3 bar Bulkhead Seal Gas System
Open No.1 nitrogen booster compressor after-cooler • Seal gas pressure to atmosphere: 0.1 to 0.3 bar Confirm that the seal air quality is within specification and that the system is
inlet valve in operation.
• Air supply antifreeze protection expander: 0.2 bar
Open No.1 nitrogen booster compressor after-cooler
outlet valves (2) • Differential pressure seal gas to gap pressure stages 1, 2 and 3: Additional information:
Open No.2 nitrogen booster compressor after-cooler 0.2 bar • Instrument air supply pressure: Between 1.5 and 10.0 bar (dew
inlet valve • Differential pressure seal gas to gap pressure expander: 0.2 bar point – 40°C)
Open No.2 nitrogen booster compressor after-cooler • Differential pressure seal gas filter: 0.05 to 0.2 bar • Nitrogen supply pressure: Between 1.0 and 10 bar. (Nitrogen
outlet valves (2) system is in case of air system failure.)
Open Cargo heater drains cooler inlet valve FC31
• Operating temperature: Approximately 40°C
Open Cargo heater drains cooler outlet valve FC32 BOG Compressor Oil System
d) At the local control panel, start one of the fresh water cooling a) Check that the oil level in the BOG compressor reservoir is
Compressor Seal Gas System
pumps and set the other to automatic standby. Check that the between the maximum and minimum levels. Replenish with the
correct grade of oil as necessary. It should be noted that the level Confirm that the supply gas quality is within specification and that the system
fresh water cooler 3-way temperature control valve is set at
will fall when the system starts. is in operation.
38°C and that the valve is operating correctly.
b) Warm-through the oil reservoir heater and allow the oil to heat Additional information:
e) Check that sea water cooling is being supplied to the fresh
water coolers in accordance with Section 2.4.1 of the Machinery up to above 20°C. The BOG compressor is equipped with a • Nitrogen supply pressure: Between 3.5 and 10 bar
Operating Manual. steam operated LO heater with the steam flow being controlled
by a thermostat located inside the reservoir.
f) Circulate the reliquefaction plant and cargo machinery cooling
water system and check all users are being supplied with cooling
water at the required temperature and pressure. Additional information:
• Reservoir oil content to be between 575 litres and 700 litres
Nitrogen
To No.5 N2 Vent Mast
Reservoir
RR601 CN705
RN832
Tanks
CG801 CN951 RR822
CG811 RN822
To
Cargo CG821
RN836
RN834
CR863 Pre-Cooler CG831 No.1 H/D CG802 CG804 Demister RN837
Tanks CS871
Compressor Vessel
CS873
RN802
CG882
RN835
RR823 RN870
RG816 RG810
RN831
High Duty RN801
CG861 RR820
RR821
RN865
RL816 Heater
RR813
CG862 RN821
CG881
RG822 1st 2nd RG802 RG804
CG883
RL819 RL818 RL817 RN838 Oil
RN842
RN879 RN829 RN868 RN827 RN825 RN823
No.2 BOG Compressor Separator No.1
CS861 BOG Heater
RN840 Dryer Separator
RR809
RL827 CG852
RG815 RG809 No.1 Nitrogen Booster Compressor RN833 RN866
CG851
RI829
RL805 RL832
RL806 RL831
CG880
RN809 RN810
RG821 RG801 RG803 RN806
RL821
RL823 RL824
RG846
RG845 RG826 RG844
RG849 RG825 CG
RL810 RL808 RL848
No.1 Cold Box 900 RC812 RC811 No.2 Nitrogen
RR810 EXP 3rd 2nd 1st
Compressor /
RL811
RL822
RC804
RG850
RG847
No.2 Separator Expander Module
RG851
RN807 RN808
RL849
RL815
RL807
RN805
RL842
• Cooling water flow: Sufficient to give 10°C to 12°C rise across Pre-Cooler Cold Box and Separator
the machine. Verify that the pre-commissioning activities have been completed and that the
Position Description Valve
cooler has been purged with nitrogen before initial start-up.
Open Cold box regulator isolating valve RN850
Nitrogen Dryers
Open Cold box regulator isolating valve RN863
a) Nitrogen gas is to be made available from ship system. The Nitrogen Reservoir
permissible residual oil content in the compressed nitrogen Verify that the pre-commissioning activities have been completed. The reservoir
before entering the dryer must not exceed 3mg/m3. An additional Nitrogen Compander (No.1 in use)
has to be purged and then filled with nitrogen from the nitrogen booster system
pre-filter will need to be installed if higher residual oil contents with a dew point of –80°C. Position Description Valve
are encountered.
Open No.1 compander nitrogen supply inlet valve RN803
Piping Open No.1 compander nitrogen supply inlet valve RN805
b) Nitrogen to be flushed through the drier until the dew point is
acceptable (-80°C). All of the system piping has to be purged with dry nitrogen before gassing-up Open No.1 compander inlet valve RN807
and start-up. The purge gas must have a nitrogen content of at least 97%, be Open No.1 compander inlet valve RN808
When starting the process flow, particular attention must be paid to the clean and have a dew point of -80°C. Closed No.2 compander nitrogen supply inlet valve RN804
operating pressure so that it does not fall below the specified minimum Closed No.2 compander nitrogen supply inlet valve RN806
operating pressure of 5 bar(g). If necessary, the filling of the downstream lines
has to be carried out via a throttling device. The specified values for minimum Closed No.2 compander inlet valve RN809
operating pressure and maximum flow rate have to be kept to prevent an undue Closed No.2 compander inlet valve RN810
loading of the dryer and the desiccant. Open No.1 compander compressor outlet valve RC817
Open No.1 compander compressor outlet valve RC818
Absorption dryers need a certain time when initially started up for stabilising Open No.1 compander expander inlet valve RC809
the process. During this time the dew point may be higher than specified.
Open No.1 compander expander inlet valve RC810
Open No.1 compander expander outlet valve RC805
Nitrogen
To No.5 N2 Vent Mast
Reservoir
RR601 CN705
RN832
Tanks
CG801 CN951 RR822
CG811 RN822
To
Cargo CG821
RN836
RN834
CR863 Pre-Cooler CG831 No.1 H/D CG802 CG804 Demister RN837
Tanks CS871
Compressor Vessel
CS873
RN802
CG882
RN835
RR823 RN870
RG816 RG810
RN831
High Duty RN801
CG861 RR820
RR821
RN865
RL816 Heater
RR813
CG862 RN821
CG881
RG822 1st 2nd RG802 RG804
CG883
RL819 RL818 RL817 RN838 Oil
RN842
RN879 RN829 RN868 RN827 RN825 RN823
No.2 BOG Compressor Separator No.1
CS861 BOG Heater
RN840 Dryer Separator
RR809
RL827 CG852
RG815 RG809 No.1 Nitrogen Booster Compressor RN833 RN866
CG851
RI829
RL805 RL832
RL806 RL831
CG880
RN809 RN810
RG821 RG801 RG803 RN806
RL821
RL823 RL824
RG846
RG845 RG826 RG844
RG849 RG825 CG
RL810 RL808 RL848
No.1 Cold Box 900 RC812 RC811 No.2 Nitrogen
RR810 EXP 3rd 2nd 1st
Compressor /
RL811
RL822
RC804
RG850
RG847
No.2 Separator Expander Module
RG851
RN807 RN808
RL849
RL815
RL807
RN805
RL842
BOG GCU Reliq Modes and compander valves have been correctly lined-up. Also check RL803 0 °C 25VA101
Separator
Sequence status:
Active status:
NOT ACTIVE
Heater
0%
BOG Burn
WG Oil Burn
Reliq Start that all of the nitrogen reservoir valves have been correctly set. 0%
Reliq STBY
38 % WG BOG Burn
Reliq Stop M 25DCE201
Seq
13 °C
-145°C
Start Stop 0% Ballast gauge b) Check and confirm that all of the BOG compressor valves have
-150°C Laden gauge
-160°C Vent Gas RG847 Laden absolute been correctly lined-up. The following items will be checked and run under this sequence to bring the
-164°C Heater Heater
25HH-100
Cold Box 0%
GCU mode
Reliq Mode
plant to Reliq Start mode:
c) Check and confirm that all of the pre-cooler and LNG pump
-113 °C RG827 Auto Man
valves have been correctly lined-up. • Nitrogen booster compressor in AUTO mode
To Cargo Tank Booster1 Lead
0%
Booster2 Lead
• LNG transfer pump in AUTO mode
RG826
RN843
0% Auto Man d) Check and confirm that all of the cold box and separator valves
N2 CMP No.1 Lead • BOG compressor in AUTO mode
N2 CMP No.2 Lead have been correctly lined-up.
RL804
-161 °C 2.87 bar Auto Man
• Nitrogen compander in AUTO mode
0%
1096 mm 1 Bog No.1 Lead
Bog No.2 Lead
e) Check and confirm that the isolation valve between the vapour • Duty compander running
Auto Man
header and the pre-cooler (CG610) is open.
-161 °C
LNG Pump No.1 Lead
• Nitrogen pressure satisfactory
LNG Pump No.1 Lead
70 % Full Reliq
f) Check that the nitrogen reservoir pressure is 40 bar • BOG system stopped
-160 °C
RL803 0 °C 25VA101
Separator
Sequence status: NOT ACTIVE
• Expander temperature satisfactory
0%
Active status:
g) Set up and start one spray pump recycling on a cargo tank ready
Seq for cooling the pre-cooler. • Cold box inlet valve RG825 open
13 °C M 25DCE201
Note: Pressing the RELIQ START button will set the system to operate in Reliquefaction Stop b) When the active alarms have been cleared, try to restart the
either free-flow, full reliquefaction mode, vent gas mode or excessive BOG compander. If a restart is not possible, wait until the suction
a) To stop the reliquefaction process, ideally move first to the
mode depending on which tank pressure control settings have been chosen pressure has reached 6.5 bar(g) and try again. If the compander
Standby mode which will allow the BOG compressor to slow
and the actual tank pressure. Sequences will follow in a controlled manner still fails to start, select the second compander as the lead
down and finally stop, then press the RELIQ STOP button (2)
as the computer follows the planned logic system to bring the plant into compander and go through the starting sequence already
on the screen mimic shown. This will stop the process and set
reliquefaction mode. described.
the system to a non-operating condition, ready for the items of
equipment to be shut down and the associated manual valves
It is first necessary for the R-Loop to start up, the compander being adjusted closed. Note: Parallel operation of the two machines is not possible and the two
to allow the circulated nitrogen to cool down the cold box at a rate of companders are isolated from each other via double isolation valves. All of
approximately 1°C per minute. the isolation valves have an interlock system fitted that utilise limit switches
BOG
and the lead compander cannot be started before all of the double shutdown
GCU Reliq Modes
The pre-cooler and lines to the BOG compressor are cooled down using a spray Heater
0%
BOG Burn 4 Reliq Start isolating valves are open. Similarly, all of the shutdown valves that are used
WG Oil Burn
pump to supply liquid to the pre-cooler at 3.5 bar and cycling the vapour outlet 38 % WG BOG Burn
1 Reliq STBY
2 Reliq Stop
to isolate the standby compander must be closed. When starting the standby
back to the vapour header via CG610, unless free-flow is the preferred mode. -145°C
Start Stop 0% Ballast gauge compander, the situation is correspondingly opposite.
-150°C Laden gauge
-160°C Vent Gas RG847 Laden absolute
-164°C Heater Heater
Note: Where the tank pressure/boil-off is not sufficient to support a 25HH-100
Cold Box 0%
3 GCU mode
Reliq Mode Shutdown from Operation with One BOG Compressor Running
compressor, free-flow the BOG via the compressor surge bypass lines to the -113 °C RG827 Auto Man
cold box once the cold box has reached temperature. Otherwise wait until the To Cargo Tank Booster1 Lead
Booster2 Lead Note: When operating with one BOG compressor, should this trip, it will
temperature at the outlet of the expander is approximately -140°C and the RN843
0%
RG826 automatically initiate the shutdown of the nitrogen compander.
0% Auto Man
BOG compressor will start automatically as part of the sequence. N2 CMP No.1 Lead
N2 CMP No.2 Lead
-161 °C
RL804 2.87 bar Auto Man
If the operating BOG compressor trips, restart the plant in ‘GCU AUTO mode’
Reliquefaction Standby Mode 0%
1096 mm Bog No.1 Lead
Bog No.2 Lead after selecting the lag BOG compressor for use. When the plant is restarted in
a) Pressing the RELIQ STANDBY button (1) on the screen mimic -161 °C
Auto Man this mode, the reliquefaction plant will be given priority over the GCU. The
LNG Pump No.1 Lead
shown below will take the system to Standby mode. LNG Pump No.1 Lead cargo tank pressure then has to be controlled by a combination of flow to the
70 %
-160 °C
Full Reliq
GCU and R-loop. If the R-loop is out of operation and the boil-off rate exceeds
RL803 0 °C
The following items will be checked and run under this sequence to bring the
25VA101
Separator
Sequence status:
Active status:
NOT ACTIVE
that which can be handled by the GCU, controlled venting must take place in
plant to Standby mode:
0%
parallel with the GCU operation.
M 25DCE201
Seq
13 °C
• Nitrogen booster compressor in AUTO mode a) Check the alarm list and acknowledge the alarms that are present.
• LNG transfer pump in AUTO mode GCU Mode Start Check out the nature of the alarms and correct as necessary via
reference to the manufacturer’s instruction manual.
• BOG compressor in AUTO mode
a) Start the tank pressure control process in GCU mode by pressing
• Nitrogen compander in AUTO mode the GCU MODE button (3) on the screen mimic shown. b) Restart the ‘lead’ nitrogen compander.
• Duty compander running
c) Select the standby (lag) BOG compressor as the lead machine
• Liquid level in separator satisfactory GCU Mode Stop
via the screen mimics as previously described, and when the
• Cold box temperature below 150°C a) To stop the gas burning process, press the RELIQ START valves have been lined-up correctly, start the compressor.
button (4) on the screen mimic. This will stop the process in a
• Ramp down BOG flow to <1,000kg/h
controlled manner by restarting the reliquefaction process and Shutdown from Operation with Two BOG Compressors Running
• Stop the BOG compressors set the GCU system to a preparatory condition.
• Close the cold box inlet valve RG825 Note: The shutdown of one BOG compressor when two are running will not
initiate a shutdown of the nitrogen compander.
Process Shutdown
The standby mode is of most use in conserving power by keeping the plant in
immediate readiness to respond to rising tank pressures. Where tank pressures Nitrogen Compander Process Shutdown a) Check the alarm list and acknowledge the alarms that are present.
are rising very slowly, such as on a ballast passage, it may be necessary to If the duty nitrogen compander trips during operation, proceed as follows: Check out the nature of the alarms and correct as necessary via
revert to the standby mode, as the power consumption is about 25% of the reference to the manufacturer’s instruction manual.
design power consumption. a) Check the alarm list and acknowledge the alarms that are present.
Check out the nature of the alarms and correct as necessary.
Note: Any manual operation of the reliquefaction system components can b) Ensure that RN803 or RN804 are open. b) Select and start a BOG compressor to supply boil-off gas to
cause a system shutdown if not operated correctly.
the GCU via the BOG heater and stop the free-flow via the HD
c) Set RN801 or RN802 to manual compressors.
Pre-cooler Liquid Supply Control Valve RL818
d) Increase the running loop inventory by manipulating RN801 or c) Prior to starting the reliquefaction plant, start a compander
If the valve fails, the BOG compressors inlet temperature can be controlled as RN802. cooling down the R-loop until the cold box reaches -150°C by
follows:
pressing the START button on Reliquefaction Compander Main
R-Loop Unloading Control Valve RN843 screen to perform a sequence start.
a) Close valve RL817 manually.
If the valve fails, decrease of inventory capacity can be controlled as follows:
d) STOP the BOG compressor and free-flow to the GCU across
b) Manually adjust the bypass valve RL816 to maintain the
a) Close valve RN842 manually. the HD compressors while setting up to start the reliquefaction
temperature between -120°C and -125°C.
plant.
-113 °C
d) Start the nitrogen compander as described previously.
Close No.1 compander inlet valve RN807 RG827
To Cargo Tank
Auto
Booster1 Lead
Man
Close No.1 compander compressor outlet valve RN818 N2 CMP No.2 Lead When in Normal Reliquefaction mode:
-161 °C 2.87 bar
RL804 Auto Man
Close No.1 compander expander inlet valve RC809 1096 mm Bog No.1 Lead • Press the GCU START button (1) to quickly handle a
Close No.1 compander expander inlet valve RC810
0% Bog No.2 Lead
rapidly increasing tank pressure and free-flow across the HD
-161 °C
Auto Man
compressors.
Close No.1 compander expander outlet valve RC805 LNG Pump No.1 Lead
LNG Pump No.1 Lead
Close No.1 compander expander outlet valve RC806 70 % Full Reliq • Observe the BOG control valve (3), and when the valve closes,
-160 °C
RL803 0 °C 25VA101 Sequence status: NOT ACTIVE press the CGU STOP button (2).
Separator Active status:
M 25DCE201
Seq
13 °C
FIC
123 ZALL ZAHH ZALL ZAHH
P P
P 180 181 182 183
P P
HH
XX H Purge / Vacuum ZSLL ZSHH ZSLL ZSHH
107 RN811 180 181 182 183
I FK ZT
Instrument Air P 123 123
Key
Nitrogen RN813
RN807 RN808
Fresh Water Cooling P Cooling Cooling
Water Water Water RN803 RN805
Air PDI
HH
H
P 107
Electical Signal Nitrogen
HH
TE TI H Supply
111 111 PDT
107
P
P P P PT
RN815 P TI
HH
H 101
HH
I HH
After-Cooler HH HH
Inter-Cooler TI Inter-Cooler 103 P
TK ZT TIC H PI H TI H
H
P 104
120 120 120 110 106 2nd Stage 1st Stage HH
TE PT PI H
L
TE 103 102 102
PI PT TE LL
041
P
TI Key
020
TE TI Nitrogen
025 025
LNG Gas
PT
002 LNG Liquid
Hydraulic Oil
FI PI
015 010 Electrical Signal
Nitrogen
Supply From TI
Ship’s System RN850 RN851 RN863 095
To LNG
Transfer Pumps
RN864
From Nitrogen
Expander
To Nitrogen
Expander
PK
055
To 1st Stage
of Nitrogen Booster
RN849 RN848 RN846 Vent Vent Compressors
Instrument RN847
I
Vent
Air P
RN
601
To 1st Stage
Inlet of Nitrogen
Nitrogen
Companders
Reservoir
RN
602
ZSL P
HY HK P
157 P
ZSL 255 255 PAHH PALL
HK RN 260 Cooling TI TAHH 232 230 HK MT MIC
ZSL PAHH 234 234
157 837 Water 235
P 250 274 274
HY
HK 255 HY
260 RN836 TSHH PI PI PSHH PI PSLL 250 PDI
Control HY 260 PSHH 234 233 238 232 231 230 ZSL 273
157 235 250
Signal To
Oil
Atmosphere
Separator PALL PSLL RN RN RN
RN839 RN880 RN832
RN830 236 236 859 828 826 RN824
Control HY HY
Cooler
ZSL PI PI
Signal 241 240 HY P
M
261 237
No.2 Nitrogen Booster 270 271
ZSL
Compressor RN857
256 HK HY No.2
261 261 Cooling
Dryer
Control ZSL ZSL HY
HK Water
PIC
158 258 H 256 256 Separator
Signal 055 PIC
045
HK HK RN834 HY HY
158 RN 258 RN 276 277
Interlock
TAHH TSHH Compander
1094 1094
Gearbox
TAH TSH TE
1094 1094 510
TI T TE
1094 1094 510
TAL TSL
1094 1094
Oil Pump
Start
Permission
Vent into Motor Room
TCLL Interlock
Winterstation On
1094 PALL PSLL
1094 1094
Auxiliary Oil TCLH 69RK- 69RK- 69RK- 69RK-
Pump Off 1094 PI P PT 822/828 821/827 820/826 819/825 Oil Demister
(During 1094 1094 511 On / Off
Compressor PAL
M
PSL On Off
Standby) 1094 1094 HS HS
Auxiliary Oil Start - -
Pump On Permission
MCC
Motor I
Oil ON - OFF -
Demister
Running
69RX- PI
E EL
521
Set at 250kPa(g) PCV 818/824 - -
512
Fault
EA EAL
PI - -
520
Set at 600kPa(g)
PCV7901 LI
500
Oil Pump
Lubricating Oil Heaters
Filters Cooler Oil Heater
Reservoir TCLH TSH TH Off TAH
Off
HS 69RX-817/823 (2,000 Litres) 503 503 - -
-
Oil Heater
Off Off
HS MCC TCLH TSH TH TAH
- Motor M 504 504 - -
ON - OFF
To From HS
Cooling Water -
Auxiliary Oil
PDG Off
508
System HS I Pump On
- -
Running Key
EL E
- -
Lubricating Oil
Start Oil Demister Fresh Water
Permission On / Off
Fault Electrical Signal
EAL EA
- -
DESCRIPTION
N2 COMPANDER #2 ANTISURGE
N2 BOOSTER COMPRESSOR #1
N2 BOOSTER COMPRESSOR #2
PSD TRIP LNG PUMP #1
PSD TRIP LNG PUMP #2
RG-827 (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
(DE-ENERGIZE)
(DE-ENERGIZE)
EFFECT ACTION
87 DE 104 DE-ENERGISE
87 DE 124 DE-ENERGISE
87 DE 224 DE-ENERGISE
87 DE 304 DE-ENERGISE
25 HY 113 DE-ENERGISE
25 HY 213 DE-ENERGISE
87 DE 504 DE-ENERGISE
40 HY 123 DE-ENERGISE
87 DE 604 DE-ENERGISE
40 HY 223 DE-ENERGISE
40 HY 162 DE-ENERGISE
25 HY 080 DE-ENERGISE
40 HY 150 DE-ENERGISE
40 HY 158 DE-ENERGISE
40 HY 160 DE-ENERGISE
40 HY 161 DE-ENERGISE
40 HY 250 DE-ENERGISE
40 HY 258 DE-ENERGISE
40 HY 260 DE-ENERGISE
40 HY 261 DE-ENERGISE
25 HY 031 DE-ENERGISE
87 DE 110 ENERGISE
87 DE 154 ENERGISE
87 DE 254 ENERGISE
87 DE 354 ENERGISE
87 DE 404 ENERGISE
87 DE 454 ENERGISE
87 DE 554 ENERGISE
87 DE 654 ENERGISE
87 DE 320 START
87 DE 420 START
87 DE 520 START
87 DE 620 START
40 PV 060 OPEN
TAG
CAUSE
A B C D E F G H I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Comments
PSD TRIP BOG COMPRESSOR #1 A X X X X X
PSDTRIP BOG COMPRESSOR #2 B X X X X X X
PSD TRIP N2 COMPANDER #1 C X X X X X X X X X
PSD TRIP N2 COMPANDER #2 D X X X X X X X X X
PSD TRIP LNG PUMP #1 E X X X
PSD TRIP LNG PUMP #2 F X X X
PSD SEAL OF COLD BOX INLET G X X X
PSD TRIP BOOSTER COMPRESSOR #1 H X X X X X X X X
PSD TRIP BOOSTER COMPRESSOR #2 I X X X X X X X X
TRIP LIMIT
TAG DESCRIPTION SIGNAL LIMI UNIT
rev 04 1
rev 04 2
25 LT 041 SEPARATOR LEVEL LOW 25 LALL 041 500 .mm 3 X X
25 LT 041 SEPARATOR LEVEL HIGH 25 LAHH 041 400 .mm 4 X
rev 04 5 TD = 30 sec signal error
rev 04 25 ZSH 081 COLD BOX VALVE RG-825 (NOT CONFIRMED OPEN) 25 ZAHH 081 X DI 6 X X X
25 PT 102 BOG COMPRESSOR #1 - SUCTION PRESSURE - STAGE 1 25 PALL 102 0.7 kPa g 7 X LL setpoint -38.3 for IBS drainage
25 PT 102 BOG COMPRESSOR #1 - SUCTION PRESSURE - STAGE 1 25 PAHH 102 TBI kPa g 8 X
25 TE 106 BOG COMPRESSOR #1 - SUCTION TEMPERATURE - STAGE 1 25 TAHH 106 60 ºC 9 X
rev 04 10
25 TE 109 BOG COMPRESSOR #1 - DISCHARGE TEMPERATURE 25 TAHH 109 180 ºC 11 X
25 PT 111 BOG COMPRESSOR #1 - DISCHARGE PRESSURE 25 PAHH 111 000 kPa g 12 X
25 PDT 116 BOG COMPRESSOR #1 - SURGE PROTECTION 1ST STAGE 25 PDAHH 116 X Logic 13 X see surge prot. Logic
25 PDT 117 BOG COMPRESSOR #1 - SURGE PROTECTION 2ND STAGE 25 PDAHH 117 X Logic 14 X see surge prot. Logic
25 PDT 118 BOG COMPRESSOR #1 - SURGE PROTECTION 3RD STAGE 25 PDAHH 118 X Logic 15 X see surge prot. Logic
25 TE 118 BOG COMPRESSOR #1 - SUCTION TEMPERATURE - STAGE 2 25 TAHH 118 65 ºC 16 X
25 TE 119 BOG COMPRESSOR #1 - SUCTION TEMPERATURE - STAGE 3 25 TAHH 119 65 ºC 17 X
25 TE 150 LNG PUMP #1 - MOTOR TEMPERATURE HIGH 25 TAHH 150 150 ºC 18 X
25 TE 152 LNG PUMP #1 - TEMPERATURE LOW 25 TALL 152 -35 ºC 19 X
25 TE 152 LNG PUMP #1 - TEMPERATURE HIGH 25 TAHH 152 110 ºC 20 X
rev 04 21
25 PT 202 BOG COMPRESSOR #2 - SUCTION PRESSURE - STAGE 1 25 PALL 202 0.7 kPa g 22 X LL setpoint different for IBS drainage
25 PT 202 BOG COMPRESSOR #2 - SUCTION PRESSURE - STAGE 1 25 PAHH 202 TBI kPa g 23 X
25 TE 206 BOG COMPRESSOR #2 - SUCTION TEMPERATURE - STAGE 1 25 TAHH 206 60 ºC 24 X
rev 04 25
25 TE 209 BOG COMPRESSOR #2 - DISCHARGE TEMPERATURE 25 TAHH 209 180 ºC 26 X
25 PT 211 BOG COMPRESSOR #2 - DISCHARGE PRESSURE 25 PAHH 211 000 kPa g 27 X
25 PDT 216 BOG COMPRESSOR #2 - SURGE PROTECTION 1ST STAGE 25 PDAHH 216 X Logic 28 X Surge trip after 3 surges
25 PDT 217 BOG COMPRESSOR #2 - SURGE PROTECTION 2ND STAGE 25 PDIHH 217 X Logic 29 X Surge trip after 3 surges
25 PDT 218 BOG COMPRESSOR #2 - SURGE PROTECTION 3RD STAGE 25 PDIHH 218 X Logic 30 X Surge trip after 3 surges
25 TE 218 BOG COMPRESSOR #2 - SUCTION TEMPERATURE - STAGE 2 25 TAHH 218 65 ºC 31 X
25 TE 219 BOG COMPRESSOR #2 - SUCTION TEMPERATURE - STAGE 3 25 TAHH 219 65 ºC 32 X
25 TE 250 LNG PUMP #2 - MOTOR TEMPERATURE 25 TAHH 250 150 ºC 33 X
25 TE 252 LNG PUMP #2 - TEMPERATURE 25 TALL 252 -35 ºC 34 X
25 TE 252 LNG PUMP #2 - TEMPERATURE 25 TAHH 252 110 ºC 35 X
rev 04 36
25 PDT 304 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 304 2 kPa 37 X
25 PDT 314 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 314 2 kPa 38 X
25 PDT 324 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 324 2 kPa 39 X
80 TE 321 BOG COMPRESSOR #1 - DE MOTOR BEARING TEMP. 25 TAHH 321 95 ºC 40 X
80 TE 322 BOG COMPRESSOR #1 - NDE MOTOR BEARING TEMP. 25 TAHH 322 95 ºC 41 X
80 TE 331 BOG COMPRESSOR #1 - MOTOR U WINDING TEMP. 25 TAHH 331 145 ºC 42 X
80 TE 332 BOG COMPRESSOR #1 - MOTOR V WINDING TEMP. 25 TAHH 332 145 ºC 43 X
80 TE 333 BOG COMPRESSOR #1 - MOTOR W WINDING TEMP. 25 TAHH 333 145 ºC 44 X
25 TE 380 BOG COMPRESSOR #1 - BEARING TEMP. - STAGE 1 25 TAHH 380 125 ºC 45 X
25 VT 381 BOG COMPRESSOR #1 - SHAFT VIBRATION - STAGE 1 25 VAHH 381 39 µm 46 X
25 TE 382 BOG COMPRESSOR #1 - BEARING TEMP. OPPOSITE STAGE 1 25 TAHH 382 125 ºC 47 X
25 VT 383 BOG COMPRESSOR #1 - SHAFT VIBRATION OPPOSITE STAGE 1 25 VAHH 383 39 µm 48 X
25 TE 384 BOG COMPRESSOR #1 - BEARING TEMP. - STAGE 2 25 TAHH 384 125 ºC 49 X
25 VT 385 BOG COMPRESSOR #1 - SHAFT VIBRATION - STAGE 2 25 VAHH 385 37 µm 50 X
25 ZT 386 BOG COMPRESSOR #1 - AXIAL DISPLACEMENT BULL 'GEAR 25 ZAHH 386 0.3 .mm 51 X
26 ZT 386 BOG COMPRESSOR #1 - AXIAL DISPLACEMENT BULL 'GEAR 26 ZALL 386 -0,3 .mm 52 X
25 TE 386 BOG COMPRESSOR #1 - SHAFT VIBRATION - STAGE 3 25 TAHH 386 125 ºC 53 X
25 VT 387 BOG COMPRESSOR #1 - SHAFT VIBRATION - STAGE 3 25 VAHH 387 37 µm 54 X
25 PDT 404 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 404 2 kPa 55 X
25 PDT 414 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 414 2 kPa 56 X
25 PDT 424 BOG COMPRESSOR #1 - DIFF. PRES. BUFFER GAS AGAINST SUCTION LIN 25 PDALL 424 2 kPa 57 X
80 TE 421 BOG COMPRESSOR #2 - DE MOTOR BEARING TEMP. 25 TAHH 421 95 ºC 58 X
80 TE 422 BOG COMPRESSOR #2 - NDE MOTOR BEARING TEMP. 25 TAHH 422 95 ºC 59 X
80 TE 431 BOG COMPRESSOR #2 - MOTOR U WINDING TEMP. 25 TAHH 431 145 ºC 60 X
80 TE 432 BOG COMPRESSOR #2 - MOTOR V WINDING TEMP. 25 TAHH 432 145 ºC 61 X
80 TE 433 BOG COMPRESSOR #2 - MOTOR W WINDING TEMP. 25 TAHH 433 145 ºC 62 X
25 TE 480 BOG COMPRESSOR #2 - BEARING TEMP. - STAGE 1 25 TAHH 480 125 ºC 63 X
25 VT 481 BOG COMPRESSOR #2 - SHAFT VIBRATION - STAGE 1 25 VAHH 481 41 µm 64 X
25 TE 482 BOG COMPRESSOR #2 - BEARING TEMP. OPPOSITE STAGE 1 25 TAHH 482 125 ºC 65 X
25 VT 483 BOG COMPRESSOR #2 - SHAFT VIBRATION OPPOSITE STAGE 1 25 VAHH 483 41 µm 66 X
25 TE 484 BOG COMPRESSOR #2 - BEARING TEMP. - STAGE 2 25 TAHH 484 125 ºC 67 X
25 VT 485 BOG COMPRESSOR #2 - SHAFT VIBRATION - STAGE 2 25 VAHH 485 37 µm 68 X
25 ZT 486 BOG COMPRESSOR #2 - AXIAL DISPLACEMENT BULL 'GEAR 25 ZAHH 486 0.3 .mm 69 X
25 ZT 486 BOG COMPRESSOR #2 - AXIAL DISPLACEMENT BULL 'GEAR 25 ZALL 486 -0,3 .mm 70 X
25 TE 486 BOG COMPRESSOR #2 - BEARING TEMP. - STAGE 3 25 TAHH 486 125 ºC 71 X
25 VT 487 BOG COMPRESSOR #2 - SHAFT VIBRATION - STAGE 3 25 VAHH 487 37 µm 72 X
DESCRIPTION
N2 COMPANDER #2 ANTISURGE
N2 BOOSTER COMPRESSOR #1
N2 BOOSTER COMPRESSOR #2
PSD TRIP LNG PUMP #1
PSD TRIP LNG PUMP #2
RG-827 (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
(DE-ENERGIZE)
(DE-ENERGIZE)
EFFECT ACTION
87 DE 104 DE-ENERGISE
87 DE 124 DE-ENERGISE
87 DE 224 DE-ENERGISE
87 DE 304 DE-ENERGISE
25 HY 113 DE-ENERGISE
25 HY 213 DE-ENERGISE
87 DE 504 DE-ENERGISE
40 HY 123 DE-ENERGISE
87 DE 604 DE-ENERGISE
40 HY 223 DE-ENERGISE
40 HY 162 DE-ENERGISE
25 HY 080 DE-ENERGISE
40 HY 150 DE-ENERGISE
40 HY 158 DE-ENERGISE
40 HY 160 DE-ENERGISE
40 HY 161 DE-ENERGISE
40 HY 250 DE-ENERGISE
40 HY 258 DE-ENERGISE
40 HY 260 DE-ENERGISE
40 HY 261 DE-ENERGISE
25 HY 031 DE-ENERGISE
87 DE 110 ENERGISE
87 DE 154 ENERGISE
87 DE 254 ENERGISE
87 DE 354 ENERGISE
87 DE 404 ENERGISE
87 DE 454 ENERGISE
87 DE 554 ENERGISE
87 DE 654 ENERGISE
87 DE 320 START
87 DE 420 START
87 DE 520 START
87 DE 620 START
40 PV 060 OPEN
TAG
CAUSE
A B C D E F G H I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Comments
PSD TRIP BOG COMPRESSOR #1 A X X X X X
PSDTRIP BOG COMPRESSOR #2 B X X X X X X
PSD TRIP N2 COMPANDER #1 C X X X X X X X X X
PSD TRIP N2 COMPANDER #2 D X X X X X X X X X
PSD TRIP LNG PUMP #1 E X X X
PSD TRIP LNG PUMP #2 F X X X
PSD SEAL OF COLD BOX INLET G X X X
PSD TRIP BOOSTER COMPRESSOR #1 H X X X X X X X X
PSD TRIP BOOSTER COMPRESSOR #2 I X X X X X X X X
TRIP LIMIT
TAG DESCRIPTION SIGNAL LIMI UNIT
BOG COMPRESSOR #1 - PDT MEASUREMENT FAILURE - 2 OUT OF 3 -
NA NA NA 25PDT116, 25PDT117, 25PDT118 NA NA NA X Logic 73 X TD = 30 sec
BOG COMPRESSOR #2 - PDT MEASUREMENT FAILURE - 2 OUT OF 3 -
NA NA NA 25PDT216, 25PDT217, 25PDT218 NA NA NA X Logic 74 X TD = 30 sec
25 LSHH 101 BOG COMPRESSOR #1 - LEAKAGE DETECTION INTERCOOLER #1 25 LAHH 101 X DI 75 X
25 LSHH 102 BOG COMPRESSOR #1 - LEAKAGE DETECTION INTERCOOLER #2 25 LAHH 102 X DI 76 X
25 LSHH 103 BOG COMPRESSOR #1 - LEAKAGE DETECTION INTERCOOLER #3 25 LAHH 103 X DI 77 X
25 LSHH 201 BOG COMPRESSOR #2 - LEAKAGE DETECTION INTERCOOLER #1 25 LAHH 201 X DI 78 X
25 LSHH 202 BOG COMPRESSOR #2 - LEAKAGE DETECTION INTERCOOLER #2 25 LAHH 202 X DI 79 X
25 LSHH 203 BOG COMPRESSOR #2 - LEAKAGE DETECTION INTERCOOLER #3 25 LAHH 203 X DI 80 X
NA NA NA GCU TRIP - RELIQUEFACTION PLANT RUNNING IN GCU MODE NA NA NA X Logic 81 X X
rev 04 NA NA NA GCU TRIP - VENT GAS MODE NA NA NA X Logic
rev 04 NA NA NA GCU TRIP - EXCESSIVE BOG MODE NA NA NA X Logic X X Trip lag BOG compressor
NA NA NA BOG COMPRESSOR #1 - STONEWALL DETECTED NA NA NA X Logic 82 X
NA NA NA BOG COMPRESSOR #2 - STONEWALL DETECTED NA NA NA X Logic 83 X
COLD BOX INLET VALVE (RG-825) CLOSED WHEN RUNNING IN
NA NA NA EXCESSIVE BOG MODE NA NA NA X Logic 84 X X
rev 04 40 PT 046 N2 RESERVOIR PRESSURE 40 PAHH 046 4100 kPa g 85 X X
40 PT 102 N2 COMPANDER #1 - SUCTION PRESSURE - STAGE 1 40 PALL 102 20 kPa g 86 X Trip only active at 100% speed
40 PT 102 N2 COMPANDER #1 - SUCTION PRESSURE - STAGE 1 40 PAHH 102 1200 kPa g 87 X Trip only active at 100% speed
40 TE 103 N2 COMPANDER #1 - INLET TEMPERATURE - STAGE 1 40 TAHH 103 53 ºC 88 X Trip 3 min delay after start
40 TE 104 N2 COMPANDER #1 - INLET TEMPERATURE - STAGE 2 40 TAHH 104 53 ºC 89 X Trip 3 min delay after start
40 TE 106 N2 COMPANDER #1 - INLET TEMPERATURE - STAGE 3 40 TAHH 106 53 ºC 90 X Trip 3 min delay after start
rev 04 91 Surge trip
40 PT 110 N2 COMPANDER #1 - DISCHARGE PRESSURE - STAGE 3 40 PAHH 110 5000 kPa g 92 X Also trip if 40PT110 & 40PDT107 meas. failure
40 XX 110 N2 COMPANDER #1 - SURGE PROTECTION 40 XAHH 110 X Logic 93 X Surge trip
rev 04 40 TE 111 N2 COMPANDER #1 - 3RD STAGE COOLER OUTLET TEMP. 40 TAHH 111 53 ºC 94 X
40 TE 114 N2 COMPANDER#1 - EXPANDER OUTLET TEMP. 40 TAHH 114 80 ºC 95 X
40 TE 114 N2 COMPANDER #1 - EXPANDER OUTLET TEMP. 40 TALL 114 A) ºC 96 X A) Acc. Dewpoint temp. + safety margin
40 TE 113 N2 COMPANDER #1 - EXPANDER OUTLET 40 TXALL 113 80 ºC 97 X Trip level = (Dewpoint temp.+ margin)
rev 04 40 TE 021 N2 COMPANDER #1 - TEMP. TO BOTTOM OF COLDBOX 40 TAHH 021 TBI ºC 98 X
rev 04 40 TE 021 N2 COMPANDER #1 - TEMP. TO BOTTOM OF COLDBOX 40 TALL 021 TBI ºC 99 X
40 PSLL 130 N2 BOOSTER COMP. #1 - SUCTION PRESSURE 40 PALL 130 400 kPa g 100 X
40 PSHH 132 N2 BOOSTER COMP. #1 - SUCTION PRESSURE 40 PAHH 132 525 kPa g 101 X
40 TSHH 134 N2 BOOSTER COMP. #1 - DISCHARGE TEMPERATURE 40 TAHH 134 155 ºC 102 X
40 PSHH 135 N2 BOOSTER COMP. #1 - DISCHARGE PRESSURE 40 PAHH 135 4000 kPa g 103 X
40 PSLL 136 N2 BOOSTER COMP. #1 - OIL PRESSURE 40 PALL 136 100 kPa g 104 X
40 ZSL 180 N2 COMP. #1 - SUCTION ISOLATION VLAVE RN-807 & RN-808 (NOT 40 ZALL 180 X DI 105
X N2 Compander #2 running
rev 04 40 ZSL 182 CONFIRMED CLOSED) 40 ZALL 182 X DI 106
Trip lead BOG compressor, delay 2 sec (LAG BOG, if
rev 04 NA NA NA N2 COMPANDER #1 TRIP AND VALVE RG-825 OPEN NA NA NA X Logic 107 X running, may continue to run towards GCU, LAG will
automatically become LEAD BOG)
Trip lead BOG compressor, delay 2 sec (LAG BOG, if
rev 04 NA NA NA N2 COMPANDER #2 TRIP AND VALVE RG-825 OPEN NA NA NA X Logic 108 X running, may continue to run towards GCU, LAG will
automatically become LEAD BOG)
40 ZSL 184 N2 COMP. #1 - VALVES TO COLDBOX TOP RN-818 & RN-817 (NOT 40 ZALL 184 X DI 109
X N2 Compander #2 running
rev 04 40 ZSL 186 CONFIRMED CLOSED) 40 ZALL 186 X DI 110
rev 04 111-112
40 ZSL 188 N2 COMP. #1 - VALVES FROM COLDBOX MIDDLE RC-810 & RC-809 (NOT 40 ZALL 188 X DI 113
X N2 Compander #2 running
rev 04 40 ZSL 190 CONFIRMED CLOSED) 40 ZALL 190 X DI 114
rev 04 115-116
40 ZSL 192 N2 COMP. #1 - VALVES TO COLDBOX BOTTOM RC-806 & RC-805 (NOT 40 ZALL 192 X DI 117
X N2 Compander #2 running
rev 04 40 ZSL 194 CONFIRMED CLOSED) 40 ZALL 194 X DI 118
rev 04 119-120
40 PT 202 N2 COMPANDER #2 - SUCTION PRESSURE - STAGE 1 40 PALL 202 20 kPa g 121 X Trip only active at 100% speed
40 PT 202 N2 COMPANDER #2 - SUCTION PRESSURE - STAGE 1 40 PAHH 202 1200 kPa g 122 X Trip only active at 100% speed
40 TE 203 N2 COMPANDER #2 - INLET TEMPERATURE - STAGE 1 40 TAHH 203 53 ºC 123 X Trip 3 min delay after start
40 TE 204 N2 COMPANDER #2 - INLET TEMPERATURE - STAGE 2 40 TAHH 204 53 ºC 124 X Trip 3 min delay after start
40 TE 206 N2 COMPANDER #2 - INLET TEMPERATURE - STAGE 3 40 TAHH 206 53 ºC 125 X Trip 3 min delay after start
rev 04 126 Surge trip
40 PT 210 N2 COMPANDER #2 - 3RD STAGE OUTLET PRESSURE 40 PAHH 210 5000 kPa g 127 X Also trip if 40PT110 & 40PDT107 meas. failure
40 XX 210 N2 COMPANDER #2 - SURGE PROTECTION 40 XAHH 210 X Logic 128 X Surge trip
rev 04 40 TE 211 N2 COMPANDER #2 - 3RD STAGE COOLER OUTLET TEMP. 40 TAHH 211 53 ºC 129 X
40 TE 214 N2 COMPANDER#2 - EXPANDER OUTLET TEMP. 40 TAHH 214 80 ºC 130 X
40 TE 214 N2 COMPANDER #2 - EXPANDER OUTLET TEMP. 40 TALL 214 A) ºC 131 X A) Acc. Dewpoint temp. + safety margin
40 TE 213 N2 COMPANDER #2 - EXPANDER OUTLET 40 TXALL 213 80 ºC 132 X Trip level = (Dewpoint temp.+ margin)
40 PSLL 230 N2 BOOSTER COMP. #2 - SUCTION PRESSURE 40 PALL 230 400 kPa g 133 X
40 PSHH 232 N2 BOOSTER COMP. #2 - SUCTION PRESSURE 40 PAHH 232 525 kPa g 134 X
40 TSHH 234 N2 BOOSTER COMP. #2 - DISCHARGE TEMPERATURE 40 TAHH 234 155 ºC 135 X
40 PSHH 235 N2 BOOSTER COMP. #2 - DISCHARGE PRESSURE 40 PAHH 235 4000 kPa g 136 X
40 PSLL 236 N2 BOOSTER COMP. #2 - OIL PRESSURE 40 PALL 236 100 kPa g 137 X
40 ZSL 280 N2 COMP. #2 - SUCTION ISOLATION VLAVE RN-809 & RN-810 (NOT 40 ZALL 280 X DI 138
X N2 Compander #1 running
rev 04 40 ZSL 282 CONFIRMED CLOSED) 40 ZALL 282 X DI 139
rev 04 140-141
DESCRIPTION
N2 COMPANDER #2 ANTISURGE
N2 BOOSTER COMPRESSOR #1
N2 BOOSTER COMPRESSOR #2
PSD TRIP LNG PUMP #1
PSD TRIP LNG PUMP #2
RG-827 (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
VALVE (DE-ENERGIZE)
(DE-ENERGIZE)
(DE-ENERGIZE)
EFFECT ACTION
87 DE 104 DE-ENERGISE
87 DE 124 DE-ENERGISE
87 DE 224 DE-ENERGISE
87 DE 304 DE-ENERGISE
25 HY 113 DE-ENERGISE
25 HY 213 DE-ENERGISE
87 DE 504 DE-ENERGISE
40 HY 123 DE-ENERGISE
87 DE 604 DE-ENERGISE
40 HY 223 DE-ENERGISE
40 HY 162 DE-ENERGISE
25 HY 080 DE-ENERGISE
40 HY 150 DE-ENERGISE
40 HY 158 DE-ENERGISE
40 HY 160 DE-ENERGISE
40 HY 161 DE-ENERGISE
40 HY 250 DE-ENERGISE
40 HY 258 DE-ENERGISE
40 HY 260 DE-ENERGISE
40 HY 261 DE-ENERGISE
25 HY 031 DE-ENERGISE
87 DE 110 ENERGISE
87 DE 154 ENERGISE
87 DE 254 ENERGISE
87 DE 354 ENERGISE
87 DE 404 ENERGISE
87 DE 454 ENERGISE
87 DE 554 ENERGISE
87 DE 654 ENERGISE
87 DE 320 START
87 DE 420 START
87 DE 520 START
87 DE 620 START
40 PV 060 OPEN
TAG
CAUSE
A B C D E F G H I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Comments
PSD TRIP BOG COMPRESSOR #1 A X X X X X
PSDTRIP BOG COMPRESSOR #2 B X X X X X X
PSD TRIP N2 COMPANDER #1 C X X X X X X X X X
PSD TRIP N2 COMPANDER #2 D X X X X X X X X X
PSD TRIP LNG PUMP #1 E X X X
PSD TRIP LNG PUMP #2 F X X X
PSD SEAL OF COLD BOX INLET G X X X
PSD TRIP BOOSTER COMPRESSOR #1 H X X X X X X X X
PSD TRIP BOOSTER COMPRESSOR #2 I X X X X X X X X
TRIP LIMIT
TAG DESCRIPTION SIGNAL LIMI UNIT
40 ZSL 284 N2 COMP. #2 - VALVES TO COLDBOX TOP RN-820 & RN-819 (NOT 40 ZALL 284 X DI 142
X N2 Compander #1 running
rev 04 40 ZSL 286 CONFIRMED CLOSED) 40 ZALL 286 X DI 143
rev 04 144
rev 04 145
40 ZSL 288 N2 COMP. #2 - VALVES FROM COLDBOX MIDDLE RC-812 & RC-811 (NOT 40 ZALL 288 X DI 146
X N2 Compander #1 running
rev 04 40 ZSL 290 CONFIRMED CLOSED) 40 ZALL 290 X DI 147
rev 04 148-149
rev 04 40 ZSL 292 N2 COMP. #1 - VALVES TO COLDBOX BOTTOM RC-808 & RC-807 (NOT 40 ZALL 292 X DI 150
X N2 Compander #1 running
rev 04 40 ZSL 294 CONFIRMED CLOSED) 40 ZALL 294 X DI 151
rev 04 152-153
40 PT 510 N2 COMPANDER #1 - SEAL AIR PRESSURE 40 PALL 510 10 kPa g 154 X
80 TE 521 N2 COMPANDER #1 - MOTOR BEARING DE TEMP. 40 TAHH 521 95 ºC 155 X
80 TE 522 N2 COMPANDER #1 - MOTOR BEARING NDE TEMP. 40 TAHH 522 95 ºC 156 X
80 TE 531 N2 COMPANDER #1 - MOTOR WINDING U TEMP. 40 TAHH 531 145 ºC 157 X
80 TE 532 N2 COMPANDER #1 - MOTOR WINDING V TEMP. 40 TAHH 532 145 ºC 158 X
80 TE 533 N2 COMPANDER #1 - MOTOR WINDING W TEMP. 40 TAHH 533 145 ºC 159 X
40 PT 540 N2 COMPANDER #1 - SEAL GAS PRESSURE TO ATMOSPHERE 40 PAHH 540 90 kPa g 160 X
40 PT 560 N2 COMPANDER #1 - SEAL GAS PRESS. EXPANDER TO ATMOSPHERE 40 PAHH 560 90 kPa g 161 X
40 TE 580 N2 COMPANDER #1 - BEARING TEMP. - STAGE 1 40 TAHH 580 125 ºC 162 X
40 VT 581 N2 COMPANDER #1 - SHAFT VIBRATION - STAGE 1 40 VAHH 581 56 µm 163 X
40 TE 582 N2 COMPANDER #1 - BEARING TEMP. - STAGE 2 40 TAHH 582 125 ºC 164 X
40 VT 583 N2 COMPANDER #1 - SHAFT VIBRATION - STAGE 2 40 VAHH 583 56 µm 165 X
40 TE 584 N2 COMPANDER #1 - BEARING TEMP. - STAGE 3 40 TAHH 584 125 ºC 166 X
40 VT 585 N2 COMPANDER #1 - SHAFT VIBRATION - STAGE 3 40 VAHH 585 50 µm 167 X
40 TE 586 N2 COMPANDER #1 - EXPANDER BEARING TEMP. 40 TAHH 586 125 ºC 168 X
40 VT 587 N2 COMPANDER #1 - EXPANDER SHAFT VIBRATION 40 VAHH 587 50 µm 169 X
40 ZT 590 N2 COMPANDER #1 - AXIAL DISPLACEMENT BULLGEAR 40 ZAHH 590 +0.313 .mm 170 X
rev 04 40 ZT 590 N2 COMPANDER #1 - AXIAL DISPLACEMENT BULLGEAR 40 ZALL 590 -0.313 .mm 171 X
40 PT 610 N2 COMPANDER #2 - SEAL AIR PRESSURE 40 PALL 610 10 kPa g 172 X
80 TE 621 N2 COMPANDER #2 - MOTOR BEARING DE TEMP. 40 TAHH 621 95 ºC 173 X
80 TE 622 N2 COMPANDER #2 - MOTOR BEARING NDE TEMP. 40 TAHH 622 95 ºC 174 X
80 TE 631 N2 COMPANDER #2 - MOTOR WINDING U TEMP. 40 TAHH 631 145 ºC 175 X
80 TE 632 N2 COMPANDER #2 - MOTOR WINDING V TEMP. 40 TAHH 632 145 ºC 176 X
80 TE 633 N2 COMPANDER #2 - MOTOR WINDING W TEMP. 40 TAHH 633 145 ºC 177 X
40 PT 640 N2 COMPANDER #2 - SEAL GAS PRESSURE TO ATMOSPHERE 40 PAHH 640 90 kPa g 178 X
40 PT 660 N2 COMPANDER #2 - SEAL GAS PRESS. EXPANDER TO ATMOSPHERE 40 PAHH 660 90 kPa g 179 X
40 TE 680 N2 COMPANDER #2 - BEARING TEMP. - STAGE 1 40 TAHH 680 125 ºC 180 X
40 VT 681 N2 COMPANDER #2 - SHAFT VIBRATION - STAGE 1 40 VAHH 681 56 µm 181 X
40 TE 682 N2 COMPANDER #2 - BEARING TEMP. - STAGE 2 40 TAHH 682 125 ºC 182 X
rev 04 40 VT 683 N2 COMPANDER #2 - SHAFT VIBRATION - STAGE 2 40 VAHH 683 56 µm 183 X
40 TE 684 N2 COMPANDER #2 - BEARING TEMP. - STAGE 3 40 TAHH 684 125 ºC 184 X
40 VT 685 N2 COMPANDER #2 - SHAFT VIBRATION - STAGE 3 40 VAHH 685 50 µm 185 X
40 TE 686 N2 COMPANDER #2 - EXPANDER BEARING TEMP. 40 TAHH 686 125 ºC 186 X
40 VT 687 N2 COMPANDER #2 - EXPANDER SHAFT VIBRATION 40 VAHH 687 50 µm 187 X
40 ZT 690 N2 COMPANDER #2 - AXIAL DISPLACEMENT BULLGEAR 40 ZAHH 690 +0.313 .mm 188 X
40 ZT 690 N2 COMPANDER #2 - AXIAL DISPLACEMENT BULLGEAR 40 ZALL 690 -0.313 .mm 189
69 PSLL 354 BOG COMPRESSOR #1 - OIL PRESSURE UPSTREAM 'GEAR BOX 69 PALL 354 190 kPa g 190 X
69 TSHH 356 BOG COMPRESSOR #1 - OIL TEMPERATURE BEHIND OIL COOLER 69 TAHH 356 65 ºC 191 X
69 PSLL 454 BOG COMPRESSOR #2 - OIL PRESSURE UPSTREAM 'GEAR BOX 69 PALL 454 190 kPa g 192 X
69 TSHH 456 BOG COMPRESSOR #2- OIL TEMPERATURE BEHIND OIL COOLER 69 TAHH 456 65 ºC 193 X
69 TE 510 N2 COMPANDER #1 - OIL TEMPERATURE BEFORE 'GEAR BOX 69 TAHH 510 60 ºC 194 X
69 PT 511 N2 COMPANDER #1 - OIL PRESSUER UPSTREAM 'GEAR BOX 69 PALL 511 190 kPa g 195 X
69 TE 610 N2 COMPANDER #2 - OIL TEMPERATURE BEFORE 'GEAR BOX 69 TAHH 610 60 ºC 196 X
69 PT 611 N2 COMPANDER #2 - OIL PRESSUER UPSTREAM 'GEAR BOX 69 PALL 611 190 kPa g 197 X
87 DE 357 BOG COMPRESSOR #1 E. STOP 87 DAHH 357 X DI 198 X
87 DE 457 BOG COMPRESSOR #2 E. STOP 87 DAHH 457 X DI 199 X
87 DE 557 N2 COMPANDER #1 E. STOP 87 DAHH 557 X DI 200 X
87 DE 657 N2 COMPANDER #2 E. STOP 87 DAHH 657 X DI 201 X
87 DE 157 N2 BOOSTER COMPRESSORS #1 & #2 E. STOP 87 DAHH 157 X DI 202 X X
87 DE 104 LNG PUMP #1 & #2 E. STOP 87 DAHH 104 X DI 203 X X
NA NA NA BOG COMPRESSOR #1 E.STOP FROM DACS MIMIC NA NA NA X DI 204 X
NA NA NA BOG COMPRESSOR #2 E.STOP FROM DACS MIMIC NA NA NA X DI 205 X
NA NA NA N2 COMPANDER #1 E.STOP FROM DACS MIMIC NA NA NA X DI 206 X
NA NA NA N2 COMPANDER #2 E.STOP FROM DACS MIMIC NA NA NA X DI 207 X
NA NA NA N2 BOOSTER COMP. #1 & #2 E. STOP FROM DACS MIMIC NA NA NA X DI 208 X X
NA NA NA LNG PUMP #1 & #2 E. STOP FROM OPERATOR STATION MIMIC NA NA NA X DI 209 X X
80 DE 338 BOG COMP. #1 MOTOR PURGE AIR LOW PRESS. TRIP 80 DALL 338 X DI 210 X To be confirmed by the Yard
80 DE 438 BOG COMP. #2 MOTOR PURGE AIR LOW PRESS. TRIP 80 DALL 438 X DI 211 X To be confirmed by the Yard
80 DE 519 COMPANDER MOTOR #1 PURGE AIR LOW PRESS. TRIP 80 DALL 519 X DI 212 X To be confirmed by the Yard
80 DE 619 COMPANDER MOTOR #2 PURGE AIR LOW PRESS. TRIP 80 DALL 619 X DI 213 X To be confirmed by the Yard
87 DE 302 BOG COMP. #1 LOSS OF RUNNING SIGNAL 87 DALL 302 X DI 214 X
87 DE 402 BOG COMP. #2 LOSS OF RUNNING SIGNAL 87 DALL 402 X DI 215 X
87 DE 502 N2 COMPANDER #1 LOSS OF RUNNING SIGNAL 87 DALL 502 X DI 216 X
87 DE 602 N2 COMPANDER #2 LOSS OF RUNNING SIGNAL 87 DALL 602 X DI 217 X
rev 04 Send Start Command To N2 Compander & BOG
? ? ? Loss Of Main Switch Board Electrical Power - (Black Out Condition N/A N/A N/A X DI 218 X X X X X X X X
Compressor Auxiliary Oil Pumps
TIAH
To Bilge
Well
CAUTION
Running Temperature: The running temperature must be adjusted so
that the difference between the the running temperature and the inlet air
temperature is between 50-60°C, eg, if the air inlet temperature is 35°C,
the minimum running temperature is 85°C ( 35 + 50) and the maximum
temperature 95°C (35 + 60).
Maintenance
Note: Oil carry-over can destroy the membranes, therefore the filter elements
should be changed as required. See previous notes in relation to changing the
membranes.
PI PY
7-1 12-1 10 S
From/To 12-3
PI
S Ballast TI
35 62 476 TS TT TI 1
Cooling 12-2 498 498 478
LS LsAl LsAl Water
7-1 191 191 191 TI System TsAh PI
PI 179 425 498 464
Air Blower Fans with Motors 161
(See Illustration 430
TAh
N2 4.9.2b) 498 Inert
TS 421
IsAl 4 HIC HIC I13V PI 192
Gas To
7-2 7-2
180-2 159 FS FsAl TT Inert Gas Cooler TI Deck
PIC PI TsAh 499-1 499-1 494-1 TT 479
IS
7-2 162 192 494-2
424 426
180-2
II IsAl IS II Inert Gas PI
PI
180-2 181-2 181-2 181-2
50 Generator 214 Condenser
PT
M M 214 446-1
109-2 110-2 46 427 428
PI
PI PY
PIC
434-7
7-2
212
S S TI SG
PI 175 114 434-2
TT Oil Separator 429-1 429-2
150 TT LS 491-2
178 193 PT PI
7-2 Test Test 481-1
Air Blower Fans with Motors LsAh
Fresh 193 2
PI TS TI PI
Key Water 178 178 70 49 442-3 434-1
164 LsAh 465
Inlet PsAl PS 178 434-8 PI
Inert Gas TsAh TI 44 48 AAI
184 184 462
Brine
178 178
29 204
446-2 M 422
PsAl AAh 414
Marine Gas Oil 184 FI 204
Sea Water 201 FI PT PI 442-1 TT TT 1V
S AAhh PI TI
5 PT 468 434-6 481-4 495 496
Refrigerant 212 AT 204
204 S PI
Air PY AAI M PT TT FS FsAl
14 204 412 481-3 491-1 499-2 499-2
Fresh Water 434-5 435-2 442-2 PT
S PI
O2 AI AE AS AAh 434-3 434-4
Saturated Steam Screw Compressor 481-2
11V
10V VP
Analyser
204 204 204 204
Condensate 15 AAhh
VP Evaporator
S 434-10
Nitrogen To Oily LS 204
All Valves Prefixed with the Bilge AI AI 1 434-9 435-1 441
Letter ‘I’ Unless Otherwise Stated Tank 14 9V 204 204
Inert Gas Composition After this process the inert gas is dehumidified further by cooling it down in
Fuel Oil Pump Unit an inert gas cooling plant where chilled brine, cooled by R404a refrigerant, is
Oxygen: 0.5~2% by volume circulated and used as the cooling medium. The condensate is drained away
Manufacturer: Allweiler
Carbon dioxide: 15% by volume via a water seal. The gas is then further dried by passing it through one of two
No. of sets: 1 large desiccant dryers, after which the now scrubbed and dry gas then flows to
Carbon monoxide: 100 ppm maximum
Type: Positive displacement, screw deck via the delivery valve.
Sulphur oxides: 1 ppm maximum
Capacity: 1,9000kg/h at 25 bar
Nitrogen oxides: 100 ppm maximum The system is operated from the main control panel using a touch screen,
Motor rating: 4.6kW, 440V, 60Hz, 3,450 rpm
Nitrogen: Remainder mounted in the panel door, from which the system is started and stopped. The
Diesel oil consumption: 1,830kg/h
Steam consumption: 640kg/h to the dryer heater panel includes alarm monitoring of the system during operation. When in use
the operation of the IGG plant is monitored via the DACS.
Refrigeration/Cooling Plant Inert Gas Generator Sea Water Cooling Pump (Ballast Pump) In addition to the main panel are local panels for the following:
Manufacturer: Hamworthy Moss AS Manufacturer: Shin Shin Machinery Co., Ltd. • Starter panel for the fuel oil pump
No. of sets: 1 Model: CAD450-12V48
• Starter panel for the blower
Compressor type: HSO 2024, screw-type Type: Vertical centrifugal, motor-driven
Cooler type: Shell and tube • Starter panel for the refrigerant plant
No. of sets: 3
Cooling medium: Brine (20% ethylene glycol/water) Capacity: 3,200m3/h at 30mth • Main control panel for the dryer system
Gas inlet condition: 37°C at 100% relative humidity (maximum) Motor rating: 120kW at 1,200 rpm
The IGG also utilises an oxygen analyser for the indication of the oxygen
Gas outlet condition: 5°C at 100% relative humidity (maximum)
content in the inert gas that is being discharged from the plant. The analyser
Refrigerant: R404a takes samples of the IG after it has been through the demister, and is fitted
with maximum and minimum setting alarms. The gas is led to the deck main
depending on the gas analysis. The delivery is normally controlled by the
oxygen and dew point analysers, and the gas is allowed to pass to the deck line
only when the gas analysis meets with the set requirements.
PI PY
7-1 12-1 10 S
From/To 12-3
PI
S Ballast TI
35 62 476 TS TT TI 1
Cooling 12-2 498 498 478
LS LsAl LsAl Water
7-1 191 191 191 TI System TsAh PI
PI 179 425 498 464
Air Blower Fans with Motors 161
(See Illustration 430
TAh
N2 4.9.2b) 498 Inert
TS 421
IsAl 4 HIC HIC I13V PI 192
Gas To
7-2 7-2
180-2 159 FS FsAl TT Inert Gas Cooler TI Deck
PIC PI TsAh 499-1 499-1 494-1 TT 479
IS
7-2 162 192 494-2
424 426
180-2
II IsAl IS II Inert Gas PI
PI
180-2 181-2 181-2 181-2
50 Generator 214 Condenser
PT
M M 214 446-1
109-2 110-2 46 427 428
PI
PI PY
PIC
434-7
7-2
212
S S TI SG
PI 175 114 434-2
TT Oil Separator 429-1 429-2
150 TT LS 491-2
178 193 PT PI
7-2 Test Test 481-1
Air Blower Fans with Motors LsAh
Fresh 193 2
PI TS TI PI
Key Water 178 178 70 49 442-3 434-1
164 LsAh 465
Inlet PsAl PS 178 434-8 PI
Inert Gas TsAh TI 44 48 AAI
184 184 462
Brine
178 178
29 204
446-2 M 422
PsAl AAh 414
Marine Gas Oil 184 FI 204
Sea Water 201 FI PT PI 442-1 TT TT 1V
S AAhh PI TI
5 PT 468 434-6 481-4 495 496
Refrigerant 212 AT 204
204 S PI
Air PY AAI M PT TT FS FsAl
14 204 412 481-3 491-1 499-2 499-2
Fresh Water 434-5 435-2 442-2 PT
S PI
O2 AI AE AS AAh 434-3 434-4
Saturated Steam Screw Compressor 481-2
11V
10V VP
Analyser
204 204 204 204
Condensate 15 AAhh
VP Evaporator
S 434-10
Nitrogen To Oily LS 204
All Valves Prefixed with the Bilge AI AI 1 434-9 435-1 441
Letter ‘I’ Unless Otherwise Stated Tank 14 9V 204 204
IG02
Vapour Main
Liquid Main
Key
IG07
To Vapour Return Inert Gas
Compressor
Room
No.5 No.4 No.3 No.2 No.1 Hull
IG05 Duct
Trunk Trunk Trunk Trunk Trunk IG05
To Ballast Tank
Ventilation
No.5 Water Ballast No.4 Water Ballast No.3 Water Ballast No.2 Water Ballast No.1 Water Ballast
Tank (P & S) Tank (P & S) Tank (P & S) Tank (P & S) Tank (P & S)
IG04 IG03
IG05
IG07
Exhaust Vent Fan No.5 No.4 No.3 No.2 No.1
For Pipe Duct Liquid Liquid Liquid Liquid Liquid IG05
Dome Dome Dome Dome Dome
No.4 Gas No.3 Gas No.2 Gas No.1 Gas
IG01 Dome Dome Dome Dome Natural Vent
For Pipe Duct
No.5 Liquid Vapour No.4 Trunk No.3 Trunk No.2 Trunk No.1 Trunk
Trunk Main Main
Vapour
Return
SAMPLE
GAS 2
SAMPLE
GAS 1
Selecector Valve Sample/Test Gases
!
HOT
15
10 20
150
50
0
0
cl
30
kPa
200
Flow Control Valve
1 MENU STRUCTURE
SBS1500OXYGEN
2. Use ( / ) to select menu level.
3. Press ‘E’ to select submenu.
ANALYZER
GAS 4. Use ( / ) to select/change settings.
5. Press ‘E’ to save changes.
M E
6. Press ‘M’ to return.
7. “Decision to bbe made-Save/Abort”.
Oxygen Analyser
8. Press ‘E’ to SAVE.
9. Press ‘M’ to Abort.
Hamworthy Moss AS
15
10 20
150
50
0 30
200
0 cl
kPa
Power Supply
Bubble Glass
Output Signal
E 910 E 910
OXYGEN OXYGEN GAS GAS DELIVERY DEW DELIVERY D E L I V E RY OXYGEN GAS DEW D E LIVERY DELIVERY
SET POINT CONTENT PRESSURE PRESSURE POINT TEMPERATURE PRESSURE CONTENT PRESSURE POINT T E M PERATURE PRESSURE
HIC %02 AI %02 PI bar PI bar MI C TI C PI mmWG AI %02 PI bar MI C TI C PI mmWG
204 1.5 204 31.0 214 -0.0 213 -0.0 503 3 o
219 18 o
18 2 -2 204 -0.0 214 0.00 503 --0 o
219 --0 o
182 ---0
h83 h83
TO TO
h158 ATMOSPHERE AT MOSPHERE
HIC HIC
7-1 25 7-1 25
h/o113 h/o114 h / o 11 3 h / o 11 4
h152
AUTO AUTO A U TO A U TO
START START HIC S TA R T S TA R T HIC
7-2 25 7-2 25
h209 h156 h209 h152 h156
TI TI
498 h2 498 h2
COOLING DRYER COOLING D RY E R
-20 A PLANT 18 °C PLANT PLANT 18 °C PLANT
-20 A
h102-1 h400-1 500-1 h/o107-1 h102-1 h400-1 500-1
h101-1 12-2 12-3 h10 h1 SELECT h101-1 12-2 12-3 h10 h1
PID BLOWER
h7-1 101-1 h7-1
h200 I N E RT G A S 102-1 h200 INERT GAS
PUSH TO SELECT PUSH TO SELECT S U P P LY M A I N P U S H TO S E L E C T P U S H TO S E L E C T SUPPLY MAIN
h/101 h/o107-2
h102-2 12-1 h17 h102-2 12-1 h17
h101-2 h/0308 SELECT h101-2 h/0308
CLASS FLAME BLOWER FLAME
ALARM ON FI280 SELECT ON FI280 SELECT
TEST h7-2 CONSUM. 101-2 h7-2 CONSUM.
-158 m 3 /h 102-2 -158 m 3 /h
-20 A TI-178 TI-178
-20 A
18 °C --0 °C
MAIN h129 h129
h5 h5
MANUAL MODE NOT RUNNING
MANUAL SELECT
S TA R T / REMOTE
S TO P : 07-10-20 9 : 0 3 : 2 4 h 5 0 0 - C O M M U N I C AT I O N F A I L U R E W I T H D R Y E R C T CONTROL 07-10-21 1 0 : 2 3 : 3 6 h 5 0 0 - C O M M U N I C AT I O N F A I L U R E W I T H D R Y E R C T
h/0121 h/0121 h/082 h/0209 h/0152 h/0156 0307 0309 h / o 3 11 h/o310 h/0312 0307 0309
BLOWER 101-1 READY
BLOWER 102-1 READY
ALARM ALARM ALARM S TO P S TA R T S TA R T S TA R T BLOWER 101-2 READY ALARM ALARM ALARM STOP
ACCEPT RESET LIST MAIN IGG AIR IGG BLOWER 102-2 READY ACCEPT RESET LIST
S . W. F.O. IGNIT- MAIN A U TO PURGE MANUAL
PUMP B LOWER PUMP GLOW ION BURNER
BA070F
WS102F WS101F
PI
Inert Gas Generator
TI Dryer Cooler TI
422V To MGPS
PCL For Auto
HV020 Stop
Control Panel
BA014F
420V BA423F PI
PX PS PX
PI
424V BA606 No.3 BA603 S-131V
CI
Ballast Pump CI
PI
Inert Gas Generator 3,200m3 x 3.0kg/cm2
PI
TI
Refrigeration TI 404V412V BA611
415V Condenser 419V BA010F 403V BA005F
PX
LCAL
413V 416V 417V C8008
414V BA018F
LS
406V
BA009F PCL For Auto To/From Sea
418V HV008 Stop
Water Ballast
PI PI PI Tank (Port)
PX PS PX
BA012F
BA605 No.2 BA602 BA610
Ballast Pump BA-25
CI CI BA002F
3,200m3 x 3.0kg/cm2 To Pipe Duct
PX Bilge Overboard
411V Key
407V
LMS LMS
Sea Water
BA150F No.1 WS002F WS001F Electrical Signal
408V
TEMPERATURE TEMPERATURE
IN ADS 1 IN ADS 2
100 100
50 50
A 0 0
150
100
50 0 0 0 1 4 5 h
HIGH HEATING ELEMENT EMERGENCY STOP CONTROL POWER REGENERATION TIME REGENERATION FAN
TEMPERATURE ALARM ALARM FAILURE TOO LONG ALARM RUNNING FAILURE
REGENERATION REGENERATION
STARTER TEST
FAN HEATING FAN HEATING
OFF ON SELECT STEAM SELECT ELECTRIC MANUAL LAMP
LOCAL OFF REMOTE OFF ON ALARM RESET
HEATER TOPPING UP REGENERATION ON TEST
EMERGENCY STOP
c) Press touch key 311 START IGG AUTO. The start sequence If the IGG is to be used for the production of dry-air the system is started in Air • The dryer plant will stop.
will then commence as follows: Purge Mode. The system is started in the same way and will deliver dry-air to • The refrigeration plant will stop.
the tanks as no combustion or inert gas is involved.
• Sea water inlet valve I5 will open to supply water to the
cooling tower.
a) Press key 111 AUTO START to allow automatic start of the
• The IGG sea water overboard valve I14 will open. Manual Mode
cooling plant and remotely start the sea water system.
• The selected air blowers will start after a preset delay (17 When running in manual mode the fuel oil pump and air blower are stopped by
seconds) and will purge the combustion chamber for a b) Press key 114 AUTO START to allow automatic start of the separate touch keys or by pressing key 304 STOP.
preset time of 3.5 minutes. dryer system. The dryer bypass valve 17 will close when the
cooling plant outlet temperature and gas oxygen content are If the plant is to be shut down for an extended period of time, the combustion
• Upon completion of the purge, the fuel oil supply pump will within preset limits. chamber jacket will need to be flushed with fresh water for approximately 2
start. hours after the burner has been stopped for approximately 2 hours.
• The ignition burner glow plug will be activated for a preset c) Press key 311 START AIR PURGE. The start sequence will
time (30 seconds), after which fuel and combustion air will commence as follows: The scrubber tower will then need to be flushed for approximately 2 hours.
be supplied to the ignition burner. When all of these operations have been completed, all of the water remaining
• Sea water inlet valve 5 will open to supply water to the inside the units must be completely drained out.
• Fuel oil is supplied to the main after a further timed delay of cooling tower.
5 seconds. • Sea water overboard valve 14 will open. Procedure for Regeneration
• After 10 seconds the fuel and air to the ignition burner will • The selected air blowers will start after a preset delay (17
be switched off and the glow plug de-energised. The dryer vessels need to be changed over every 6 hours to dry out (regenerate)
seconds). the desiccant in the recently used vessel. The hot air +150°C from the steam
• The burner flame is monitored by the detector and if stable • If the cooling plant outlet temperature is within limits the heater flows in the opposite direction to the gas flow in order to evaporate the
after a timed delay of 17 seconds, the main burner fuel and dryer plant will start after a timed delay of 3.5 minutes. water which is then carried off in the flushing stream.
air supply will be switched to normal capacity.
• The dew point is monitored for a timed delay of 3.5
• If the cooling plant outlet temperature and gas oxygen minutes.
content are within limits, the dryer plant will start after a
timed delay of 60 seconds. • Press touch key SELECT CONSUMER, and if the dew
point is within preset limits, the vent valve to atmosphere 2
• The gas oxygen content and dew point are monitored for a will close and the delivery valve to deck 1 will open.
timed delay of 3.5 minutes.
• Press touch key SELECT CONSUMER, and if the oxygen
content and dew point are within preset limits, the vent valve
to atmosphere 2 will close and the delivery valve to deck 1
will open.
SW2020
POWER ON..............
GAS
DISCONNECTION....
001 ZZ005 HI ALARM LEVEL.....
EXTERNAL ALARM...
SAMPLING ALARM STATUS 1................
POINT LEVEL STATUS 2................
SYSTEM FAULT.........
DETECTOR
F1 F2 F3 F4 ABNORMAL COND....
ALARM MUTE
CH4 %LEL
ALARMS IN QUEUE 7 8 9 LIST
LIST
SAMPLING
LIST ALARMS
FAULT
STU VWX YZ* POINTS
CH4 VOL%
4
JKL
5
MNU
6
PUR
LIST DISCONNECTIONS LIST FAULTS M MUTE
CH4 VOL%
0 .,-
ENTER ESC HOME Pg Pg
Repeater Panel
Salwico MN400
GAS ALARM REPEATER UNIT
List
List
On
Alarms
Local mute
Faults
Lamp test
Illustration 4.10b Gas Detection System Combined Sensor Module Communication and Communication and Sensor Safe Hazardous
IR Gas Detector EEx iad Hazardous Safe and IS Barrier Box Power Loop Power Loop Module Area Area CC Type Gas Detector EEx d ST600EX
Intrinsically Safe Area Area Signal Cable 4-20mA Loop 11 Out Loop 15 Out
GCU Hood Room ISOL SM-13/11 SM-13/11 Accom. Upper Deck Entrance Lobby (104)
GCU Hood Room Upper Deck Air Handling Unit Room (121)
Gas Duct (No.1) C Deck Fwd Entrance Lobby (P) (403)
Gas Duct (No.2) ISOL SM-13/11 Accom. B Deck Gym Exhaust Fan Inlet (338)
IR Type Gas Detector EEx d ST600EX-IR C Deck Fwd Entrance Lobby (S) (409)
LAST ALARM GAS(1) SEC 1 H2S2 15.0 PP
GAS 006 002 MOONPOLE GAS(1) ZONE 1 CxHy 2, 2%LEL
(NOT MUT PUMP ROOM
7 8 9 FAULT
1 2 3
Accom. Upper Deck Entrance Lobby (S) (111) in EX-d type Max 10 Shielded Cable In Box
Accom. A Deck Entrance lobby (S) (215) Detectors per Loop Rectifier and Twisted Pairs
Accom. A Deck Officer Rec. Room (212) SM-13/11 Loop 14 In Battery 14,4Ah
Note A - The Required Cable Area Depends on the Cable System Loop
System Loop Communication Cable 220V AC Input from UPS Distboard
No.1 Tank IBS for Gas Dome Length, Resistance and the Connected Units Power Consumption Relay Outputs and 24V DC Outputs Fire Control Comm. Cable
Twisted Pair 3x2 min 0, 75mm²
No.2 Tank IBS for Gas Dome 1 Station Twisted Pair
2
No.3 Tank IBS for Gas Dome 3 MN3400 Wheelhouse
4 3x Relay Outputs
No.4 Tank IBS for Gas Dome 5 Repeater
6 Common Fault Gas Alarm FDS Event
No.5 Tank IBS for Gas Dome 7
8 and Power Fault Printer
No.1 Tank IS for Gas Dome 9
10 Reset by Mute
No.2 Tank IS for Gas Dome 11 GAS 001 ZZ005
MN400
12
No.3 Tank IS for Gas Dome
F1 F2 F3 F4
13
FAULT
Repeater
7 8 9
4 5 6
14 COMM. and
1 2 3
LAST ALARM GAS(1) SEC 1 H2S2 15.0 PP
15
PUMP ROOM
F1 F2 F3 F4
24V DC POWER
7 8 9 FAULT
16
No.5 Tank IS for Gas Dome
4 5 6
1 2 3
17 0
18
No.1 Vent Mast 19 Shielded Cable
No.2 Vent Mast 20
21 Twisted Pairs
No.3 Vent Mast 22
23 SW2020 GS3000
No.4 Vent Mast 24
25 Gas Sampling Fire Detection
No.5 Vent Mast 26
27 System Central ECC No.1 CCC No.1 System Central
Side Passageway Starboard Fwd 28
29
Side Passageway Starboard Mid MN3000 MN3000 MN3000
Pipe Duct Fwd 30
Side Passageway Starboard Aft 31
Repeater Repeater Repeater
Pipe Duct Aft 32
COMM. and
Side Passageway Port Fwd 33
Accommodation
CN CN CN CN
655F 637F 620F 603F
No.5 No.5
No.5
Gas Vent
Liquid CN CN CN CN
Dome Mast
Dome 412F 312F 212F 112F
CN CN No.4 No.3 No.2 No.1
507F 682F CN Gas CN Gas CN Gas CN Gas
407F Dome 307F Dome 207F Dome 107F Dome
CN No.4 No.4
No.3 No.3 No.2 No.2 No.1 No.1
512F Liquid Vent
Analysing Unit Liquid Vent Liquid Vent Liquid Vent
Dome Mast
(DACS I/O Dome Mast Dome Mast Dome Mast
Room)
CN Air
682F Lock
Cold
Gas Vent
Box
Drain Tank Cargo Electrical
Machinery Motor
Room Room
No.6 Cofferdam No.5 Cofferdam No.4 Cofferdam No.3 Cofferdam No.2 Cofferdam No.1 Cofferdam
Key
No.5 No.4 No.3 No.1
Vent Vent Vent Vent Infrared Detection Line
Mast Mast Mast Mast
DACS I/O
Room
Analysing
Unit
Bosun
Store
No.1b No.1a
No.5 No.4 No.3 No.2 Water Ballast Water Ballast
Water Ballast Tank Water Ballast Tank Water Ballast Tank Water Ballast Tank Tank Tank Fwd
Engine Room (Port and Starboard) (Port and Starboard) (Port and Starboard) (Port and Starboard) (Port and (Port and Heavy
Starboard) Starboard) Fuel Fwd
Oil Water
Tank Ballast F.P
Void
Tank
No.6 Cofferdam No.5 Cofferdam No.4 Cofferdam No.3 Cofferdam No.2 Cofferdam No.1 Cofferdam
Wheelhouse
Repeater
Unit
Safe Dangerous
Area Area
Cargo Tank
Port Starboard
Vent Mast
Liquid/Gas Dome
Gas Vent
Filter Drain Tank Cargo Machinery
Room Filter
Trunk
Gas Detection
Lines
Key
Infrared Detection Line
Other fault alarms monitor the internal condition of the gas sampling system.
Fault Alarm
1) An analysing pump fault is caused by a pressure switch and stops
the pump and scanning sequence if the system does not have the
Repeater Unit - Located in the Fire Control Station
pump redundancy option. The pressure switch is detecting that
the pump pressure is too low, the cause is probably a membrane The Man Machine Interface
leakage of the pump or a fault of the pressure switch itself.
Service is needed if the fault cannot be reset. • Gas alarms are shown on the Mini Repeater.
- The previous and next alarms (if any) can be listed with the
2) A bypass pump fault is caused by a pressure switch. The Arrow Keys.
scanning cycle continues. The bypass pump stops. The cause for
this fault is the same as described for the analysing pump. • Unmuted faults are shown if there are no unmuted gas alarms in
the system.
3) Internal leakage in the analysing unit is indicated when the - The previous and next faults (if any) can be listed with the
automatic leakage control fails. This control is automatically Arrow Keys.
initiated every 24 hours by closing all the sampling valves, • The clock is shown when there are no alarms or faults in the
running the analysing pump and checking that the vacuum system.
switch is activated. If the vacuum switch is not activated the
cause is a leakage at the vacuum side of the pump from pipes, • The Local mute button has dual functions.
solenoid valves, a pipe coupling or the vacuum switch itself. – It mutes the local buzzer if there are any entries in the fault
or alarm lists.
Salwico GS3000
POWER ON
GAS
DISCONNECTION
006 002 TEST......
ALARM TRANSFER
SECTION DETECTOR EXTERNAL ALARM
DELAY OFF.....
SYSTEM FAULT..
F1 F2 F3 F4 ABNORMAL COND.
ALARM LEVEL 1
ALARM MUTE
ALARM LEVEL 2 ALARMS IN QUEUE 7 8 9 Z ZONE EA
EXTERNAL FAULT
ALARM
4 5 6 D DETECTOR EC EXTERNAL
CONTROL
M MUTE
ALARM LEVEL 2
IN QUEUE 0 ON OFF TIMER LIST
Repeater Panel
Salwico MN3400
List
On line FIRE ALARM
List
More alarms
Local mute
Lamp test
GS3000 The GS3000 fixed gas detection system consists of 25 fixed gas detectors Engine Room Area
GAS ZONE 2 DETECTOR 5 of the infrared type at various locations in the GCU area, engine room,
accommodation, emergency generator room, cargo motor room, bosun’s store Loop Location Warning Alarm Remark
ALARM 2 OF 4 (NOT RESETTABLE)
and deck passageways. The detectors will activate a gas alarm if the LEL 12.1 No.1 E/R supply fan (S) 30% LEL 60% LEL Duct-mounted
reading reads 30% or above. A high-high alarm will be activated if the reading 12.2 No.3 E/R supply fan (S) 30% LEL 60% LEL Duct-mounted
Reset Gas Alarm: increases to 60% LEL. 12.3 No.4 E/R supply fan (P) 30% LEL 60% LEL Duct-mounted
• Select the appropriate gas alarm 12.4 No.2 E/R supply fan (P) 30% LEL 60% LEL Duct-mounted
The types of detector heads in use:
• Press ALARM RESET to reset the gas alarm. 12.5 E/R 2nd deck (S) 30% LEL 60% LEL
1. Infrared FGD-3, EEx iad llC T4; used to detect flammable gas 12.6 E/R 2nd deck (P) 30% LEL 60% LEL
The system is trying to reset the gas alarm. (methane) in air with an operating detection range of 0 to 100%
LEL.
The Gas Alarm is Reset: Accommodation Area
• The gas alarm is reset and it disappears from the alphanumerical Cargo Machinery Trip System Loop Location Warning Alarm Remark
display. The gas alarm is moved from the Not Resettable list to 13.1 Wheelhouse (601) 30% LEL 60% LEL
the Gas History list. The text LIST EMPTY is displayed when Loop Location Warning Alarm Remark 13.2 D deck entrance lobby 30% LEL 60% LEL
the gas alarm list is empty. The system returns to the normal 11.1 GCU hood room 30% LEL 60% LEL Duct-mounted (P) (524)
menu after a few seconds and the text GS3000 CONTROL 11.2 GCU hood room 30% LEL 60% LEL Duct-mounted 13.3 C deck aft entrance lobby 30% LEL 60% LEL
UNIT is displayed.
11.3 Gas duct (No.1) 30% LEL 60% LEL Duct-mounted (P) (422)
The Gas Alarm is Not Reset: 11.4 Gas duct (No.1) 30% LEL 60% LEL Duct-mounted 13.4 C deck officers’ TV room 30% LEL 60% LEL
(401)
• The reason why the gas alarm is not reset is displayed on line
2. Infrared Bucom ST600EX-IR EEx d llC T6; used to detect 13.5 C deck CCR (404) 30% LEL 60% LEL
three. This text disappears after a few seconds, but the gas alarm
remains displayed on line one and two. Check the problem and flammable gas (methane) in air with an operating detection 13.6 B deck entrance lobby 30% LEL 60% LEL
deal with it, then try to reset the gas alarm again. range of 0 to 100% LEL. (P) (326)
13.7 B deck crew’s TV room 30% LEL 60% LEL
Cargo Machinery Trip System (322)
Fault Indication 13.8 A deck crew’s mess room 30% LEL 60% LEL
Loop Location Warning Alarm Remark (225)
FAULT is Flashing:
11.5 Inert gas line 30% LEL 60% LEL Special duct 13.9 A deck entrance lobby 30% LEL 60% LEL
• The FAULT indicator is flashing and the internal buzzer is mounting (P) (205)
sounding. One or more faults are detected in the system. The kit 13.10 A deck crew’s recreation 30% LEL 60% LEL
fault is not displayed if there is a gas alarm in the system. It room (205)
is instead put in the Fault list. Otherwise the first line displays
3. Catalytic Combustible Bucom ST600EX EEx d llC T6; used 14.1 D deck entrance lobby 30% LEL 60% LEL
the word FAULT, a fault code, a zone number, a detector type,
to detect flammable gas (methane) in air with an operating (S) (519)
and a fault message. Additional text is displayed on line two, if
detection range of 0 to 100% LEL. 14.2 C deck central office 30% LEL 60% LEL
provided. The total number of faults is displayed on line 3. The
faults can, one at a time, be acknowledged/muted and reset by (407)
using the MUTE and RESET keys situated in the Fault fields. 14.3 C deck aft entrance lobby 30% LEL 60% LEL
If there is a gas alarm in the system use the LIST key to display (S) (413)
the fault in the display. The fault codes are listed in Appendix A: 14.4 B deck entrance lobby (S) 30% LEL 60% LEL
Fault Codes in the User’s Guide. (316)
14.5 B deck gym supply fan 30% LEL 60% LEL Duct-mounted
Acknowledgement of faults, fault finding, disconnection and changes to the inlet (336)
set-up are covered in detail in the User’s Guide.
14.6 A deck galley (223) 30% LEL 60% LEL
14.7 A deck officers’ mess 30% LEL 60% LEL
room (217)
14.8 Upper deck entrance 30% LEL 60% LEL
lobby (S) (111)
Loop Location Warning Alarm Remark Type of detector: Catalytic Combustible Bucom ST600EX EEx d llC T6; used Portable Gas Analysers and Detectors
to detect flammable gas (methane) in air with an operating detection range of
14.9 A deck entrance lobby 30% LEL 60% LEL
0 to 100% LEL. The portable gas detection equipment on board is both comprehensive and
(S) (215)
well proven. Each instrument is certificated and comes with manufacturer’s
14.10 A deck officers’ 30% LEL 60% LEL operating instructions and recommended spares and test kits. The certificates
Loop Location Warning Alarm Remark
recreation room (212) are to be suitably filed and the monthly tests recorded.
16.5 Bosun store 30% LEL 60% LEL
15.1 Upper deck entrance 30% LEL 60% LEL
lobby (P) (104) WARNING
Type of detector: Electro-chemical ST400EX, EEx ia llC T6; used to measure
15.2 Upper deck air handling 30% LEL 60% LEL Duct mounted oxygen levels with an operating detection range of 0 to 25% vol. The batteries in these instruments must never be replaced in a hazardous
unit room (121) area due to the potential for an electrical discharge.
15.3 C deck forward entrance 30% LEL 60% LEL Loop Location Warning Alarm Remark
lobby (P) (403) These instruments measure the level and volume of O2, CO2, CO and CH4
16.3 Electric motor room 1 19% VOL 17% VOL
15.4 B deck gym exhaust fan 30% LEL 60% LEL Duct mounted (methane) present in a tank when the tank is being inerted or gassed-up.
16.4 Electric motor room 2 19% VOL 17% VOL
outlet (336)
16.6 Cargo compressor room 1 19% VOL 17% VOL Manufacturer: Crowcon
15.5 C deck forward entrance 30% LEL 60% LEL
lobby (S) (409) 16.7 Cargo compressor room 1 19% VOL 17% VOL Gases detected: O2, CH4, CO, H2S
15.6 D deck air intake galley 30% LEL 60% LEL Model: Tetra 3
(223) If the detectors inside the cargo motor room are set off, the motor room supply No. of sets: 6
fan will be tripped causing all non-intrinsically safe power supplies to the
15.7 F/Casing upper deck 30% LEL 60% LEL motor room to be tripped. This will result in stopping the HD compressor
em’cy gen room (701) motors and the auxiliary LO pumps, glycol heating circulating pump, air lock
supply fan.
Other Spaces
Note: When testing the motor room trip system, shut-off the steam supply to
Type of detector: Infrared FGD-3, EEx iad llC T4; used to detect flammable
the glycol heater.
gas (methane) in air with an operating detection range of 0 to 100% LEL.
Manufacturer: Draeger
Manufacturer: Reiken
No. of sets: 12 2
No. of sets: 1
Type: Pac 3000 Pac 7000
Type: GX-2003 F
Gases detected: 02 CO2
This instrument measures the dew point during the drying process of a tank or Gases detected: O2, CH4
hold.
The ship carries two dew point meters to measure the moisture in air or gas
samples with positive pressure. The battery powered hygrometer indicates both
dew point temperatures and water vapour to less than one part per million, on
the large meter dial. As the reading is specific to water vapour, calibration is
accurate for different gases. Dew point meters should be sent ashore every
twelve months for reconditioning and recalibration.
4.11.1 Cargo, Ballast, Bunkering and Ship Side Valve Remote Control System
Al Sahla Cargo Operating Manual
No.5 Cargo Tank No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
CS550 CL500 CS450 CL400 CS350 CL300 CG072 CL012 CS250 CL200 CS150 CL100
CS551 CL501 CS451 CL401 CS351 CL301 CL022 CS251 CL201 CS151 CL101
CS552 CL502 CS452 CL402 CS352 CL302 CL032 CS252 CL202 CS152 CL102
CS554 CL507 CS454 CL407 CS354 CL307 CL042 CS254 CL207 CS154 CL107
CS555 CL510 CS455 CL410 CS355 CL310 CS255 CL210 CS155 CL110
Engine Accommodation
Casing
No.7 No.3
CS870 Solenoid Solenoid
Valves Valves
(P) (T)
CG800 CG841 RG821 CG071 CL011
CG801 CG851 RG822 CG079 CL021
No.10 CG803 CG861 RG825 CL031
I9V Solenoid CG806 CG900 CL041
Valves CG831 CG901
(P) (T)
50 Litres
50 Litres
0.2MPa
50 Litres
50 Litres
0.5MPa 0.5MPa 0.5MPa Temperature
Switch:
AF 50 Litres
NE 70°C 50 Litres
M M M
Drain
Reference Shipyard Drawing: SS-VH61-H191A
Issue: Ship Visit July 2008 IMO No: 9360855 Section 4.11 - Page 2 of 9
Produced by: WMT Limited, UK
Email: manuals@wmtmarine.com
Al Sahla Cargo Operating Manual
Pressure Build-Up
12MPa
If High
Pressure <13MPa> If Motor If High Pressure
Overload 13MPa
Alarm
If Pressure ≥ 10.5MPa Alarm Alarm
If Pressure ≥ 10MPa If
Low Level
Alarm Alarm
If Low
Time Delay Level
15 Seconds Standby Pump Start
(Main Pump Stop)
Alarm
If Pressure ≥ 14.3MPa
If Motor Alarm
Overload
Alarm
If Pressure ≤ 14.3MPa
If Pressure ≥ 10.0MPa
Alarm
If Pressure ≥ 9MPa If
Low Low
If Low
Level
Alarm Level
Alarm
If Pressure ≤ 9MPa Alarm
Alarm
EDDS Signal Relief Valve ESD Activation Pump Stop Relief Valve Operates
Activate Pump Stop Works
Illustration 4.11.1c Ballast, Bilge and Fuel Oil Valve Remote Control System
Hydraulic Power
Pack Room
VR002
To/From Power
Pack For Cargo Valves FO01
VR003 No.4 Water Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1b Water No.1a Water FO02
(Port and Starboard) (Port and Starboard) (Port and Starboard) Ballast Tank Ballast Tank FO04 Forward
(Port and (Port and FO07 Heavy
Starboard) Starboard) FO03 Fuel Oil
Engine No.5 Water Ballast Tank Pump
FO09
Room (Port and Starboard) Room
FO28 FO39
FO29 FO40 9.0MPa 10.0MPa 10.5MPa 13.0MPa 4~20mA RI RI
FO30 FO42 DO11 PI I
FO35 FO43 DO12 P Overflow
FO36 FO44 DO13 Line
FO37 FO45 DO14
FO38 FO46 DO15
0.2MPa
Temperature
Switch: AF
NE 70°C
M M M
Valve No. Type Size Description Ballast, Bilge, Fuel Oil And Ship Side Valves System One is located on the engine room second deck aft and supplies the ship side
valves, while the other is located at the engine room floor level and supplies
CG900 Butterfly - Open/ 200A BOG to gas combustion unit
the ballast and HFO system valves.
Shut Ballast Hydraulic Power Pack
CG901 Ball - Open/Shut 80A Vent gas heater to gas Manufacturer: AMRI-SEIL All of the valves are normally operated via the DACS screen mimic in the
combustion unit ECR/CCR, but they can also be operated from their solenoid cabinets as
Model: SS-HP-1890
CG800 Butterfly - Throttle 650A HD compressors discharge to previously described. In addition, each ship side valve, listed in solenoid box
Pump capacity: 2 Main hydraulic pumps: 78 litres/minute at 12MPa
vapour return line No.10, is fitted with a stationary handpump for operating the valve in the event
and 1,750 rpm (each).
CG831 Butterfly - Open/ 600A No.1 HD compressor suction of hydraulic power failure.
Topping-up hydraulic pump: 18 litres/minute at
Shut valve
1,750 rpm
CG841 Butterfly - Open/ 600A No.2 HD compressor suction No.10 Solenoid Cabinet (Engine Room 2nd Deck)
Motors: 2 Main motors: 25kW, 440V, 60Hz, 3-phase,
Shut valve
1,750 rpm, IP55, insulation class: F Valve No. Type Size Description
CG851 Butterfly - Open/ 200A BOG heater inlet valve
Topping-up motor: 4.8kW, 440V, 60Hz, 3-phase, WBV377 Butterfly - Open/ 16K Eductor overboard discharge
Shut
1,750 rpm, IP55, insulation class: F Shut 300A
CG861 Butterfly - Open/ 550A HD heater inlet valve
Shut Oil tank capacity: 2,000 litres WBV378 Butterfly - Open/ 10K Ballast main overboard
CS870 Ball - Open/Shut 50A Inlet valve to vaporiser 1,280 litres normal operating level Shut 750A discharge
RG821 Butterfly - Open/ 300A No.1 BOG compressor inlet Operating pressure: 12MPa WBV372 Butterfly - Open/ 10K Main sea water crossover low
Shut valve Maximum pressure: 14.3MPa Shut 1000A sea chest (starboard)
RG822 Butterfly - Open/ 300A No.2 BOG compressor inlet Accumulators: WBV371 Butterfly - Open/ 10K Main sea water crossover high
Shut valve Capacity: 50 litres by 3 sets = 150 litre plus Shut 1000A sea chest (starboard)
RG825 Butterfly - Open/ 200A Cold box inlet isolating valve WBV375 Butterfly - Open/ 10K Main sea water crossover low
1 by 45 litre nitrogen cylinder at 8.2MPa
Shut Shut 1000A sea chest (port)
WBV374 Butterfly - Open/ 10K Main sea water crossover high
Ballast, Bunkering and Ship Side Valves Hydraulic Power Pack Shut 1000A sea chest (port)
No.8 Solenoid Cabinet (Port Aft Underdeck Passageway)
Description Set Point S64V Butterfly - Open/ 10K Central cooling SW system
Valve No. Type Size Description Shut 350A overboard (starboard sea chest)
Relief valve 14.3MPa
CS551 Ball - Open/Shut 40A No.5 cargo tank starboard spray S134V Butterfly - Open/ 10K Central cooling SW system
High pressure alarm 13.0MPa
rail supply valve Shut 350A overboard (port sea chest)
Standby pump starting pressure 10.5MPa S63V Butterfly - Open/ 10K Central cooling SW system
CS552 Ball - Open/Shut 40A No.5 cargo tank port spray rail
supply valve Low pressure alarm 10.0MPa Shut 350A overboard (starboard sea chest)
CL500 Butterfly - Throttle 400A No.5 cargo tank filling valve Motor defect 740 litre I9V Butterfly - Open/ 10K Inert gas overboard drain
CL510 Butterfly - Throttle 400A No.5 cargo tank liquid branch Tank low level switch alarm 520 litre Shut 350A
master valve Tank low low level alarm -
Oil high temperature alarm 70°C If there is a failure in the control system, a valve can also be operated by
CS555 Globe - Throttle 65A No.5 cargo tank spray master
manually pressing the button on the end of the solenoid valve in the required
valve Filter clogging 0.2MPa
direction. In the event that there has been a hydraulic power pack failure, all
CS550 Globe - Throttle 65A No.5 cargo tanks spray pump of the valves in the system can be operated by utilising an auxiliary handpump
discharge valve The hydraulic power unit used on the ballast, bunkering and ship side valves is or using a handwheel or spanner accordingly. A description on how to use the
CS554 Globe - Throttle 50A No.5 cargo tanks spray return the same as that used for the cargo valves and is located in the hydraulic power handpump has been given later in this manual.
valve pack room on the starboard side of the 2nd deck. The operation of this power
pack is the same as that already described, with there being two main pumps The ship side valves can also be operated from an emergency switch box in the
CL507 Globe - Throttle 200A No.5 cargo tank emergency
and one topping-up pump. fire control station.
pump discharge valve
CL501 Globe - Throttle 300A No.5 cargo tank starboard pump
discharge valve Hydraulic Valve Cabinets
CL502 Globe - Throttle 300A No.5 cargo tank port pump The ballast, bunkering and ship side valves, are supplied from two solenoid
discharge valve valve cabinets, numbered No.9 and No.10 as shown in illustration 4.11.1b.
No.1 Motor Starter (for Ballast & E/R VRC) No.1 Motor Starter (for Cargo VRC)
1 2 3 4 5 6 7 8 9 10 11 1 2 3 4 5 6 7 8 9 10 11
12 13 12 13
100
200 300
60
0
90
14 100
200 300
60
0
90
14
0 0 0 0
0 A 0 A
0 0 0 0 1 H 0 0 0 0 1 H
15 16 17 18 19 15 16 17 18 19
Key
No.2 Motor Starter (for Ballast & E/R VRC) No.2 Motor Starter (for Cargo VRC) 1. No.1 Motor Failure Alarm
11 11
2. No.2 Motor Failure Alarm
3. Topping-Up Pump Motor Failure Alarm
12 13 12 13
14 14
4. Low Level Alarm
200 300 200 300
100 60
0 100 60
0
90 90
0 0 0 0
0 A 0 A
0 0 0 0 H 0 0 0 0 H
5. Low Low Level Alarm
1 1
0 A 0 A
0 0 0 0 1 H 0 0 0 0 1 H
HPP Alarm and Control (for Ballast & E/R VRC) HPP Alarm and Control (for Cargo VRC)
20 20
Interlock Operation
ESDS Test Test Switch (CCR)
Electric Power Fail (Blackout) No.1 HV CSBD And HV CSBD Nos.1 and 2 IGG Blower ESD
No.2 HV CSBD Qty - 2
Hydraulic Oil Pressure Low (Hydraulic Power Pack
For Control Valve) S/S Pneumatic Link Box Air Release Solenoid Valve Box ESD
Qty - 1
Gas High High (Motor Room,
Or
Cold Box)
IS Barrier
GCU Trip
Motor Room Difference
Pressure Low
Motor Room Supply Fan Fail
Motor Room Vent System
Not Run
S/S Link Cabinet
ESD Alarm Blocking
Maintenance On
Elec. Connector Optical Pneumatic
Tank Protection System 1 Interface Interface Interface
Cargo Tank Pressure Low
Electrical Signal Optical Signal Air Signal
ESD ESD ESD
Tank Protection System 2
Cargo Tank Level HH At Port (CTS Cabinet) ESDS From/to Shore ESDS From/to Shore ESD To Shore
Cargo Tank Level VH At Sea
DACS Cabinet Room Cargo Control Room Ship Side On Deck (Port)
Fax
Ship-Shore Link Enclosure (SSL) RJ11
Socket
Public PABX
Telephone Telephone
Hot Line
Telephone
Serial
C/O
Junction Switch
PSU Box
FIBRE OPTIC
TFL I/F MODULE
MODULE
Fibre-Optic/Electric
LAMP TEST FIBRE OPTIC SYSTEM SYSTEM SELECTOR ELECTRIC SYSTEM
SHIP ESD ESD STATUS ESD STATUS ELECTRIC SHORE ESD
STATUS TRIP INPUTS
FIBRE-OPTIC ELECTRIC
ESD
Selector Module
SELECTED SELECTED
SHORE RECEIVING TANK
HIGH LEVEL
AC 220V
INHIBIT INHIBIT LOADING ARM TRIP 1
POWER
LOADING ARM TRIP 2
Fibre-Optic Port
RESET RESET
FIBRE OPTIC /ELECTRIC
SYSTEM SELECTOR MODULE
Selector Module
FIBRE OPTIC PORT STARBOARD SELECTOR MODULE
220V
FIBRE OPTIC FIBRE OPTIC
FIBRE OPTIC
MODULE SYSTEM TELEPHONE SYSTEM
ESD SYSTEM
LAMP TEST FAULT NORMAL
SHIP SHORE
NORMAL
Emergency
ABNORMAL
ROR
POWER SHORE SHIP
AUDIO ALARM
CIRCUIT
FIBRE OPTIC CONTROL & ALARM MODULE TEST
ON
PRIMARY
I/P POWER
SECONDARY
I/P POWER
+24V
OUTPUT
Module
OFF
ESD SYSTEM SELECT TEL CH1 TEL CH2 TEL CH3 TEL CH4
Configuration
C MIYAKI C C C C
B D B D B D B D B D
A E PYLE ITT A E A E A E A E
CANNON
MODULE
LAMP TEST FIBRE OPTIC SYSTEM SYSTEM SELECTOR ELECTRIC SYSTEM
PRESS SHIP ESD ESD STATUS ESD STATUS ELECTRIC SHORE ESD
TO STATUS TRIP INPUTS
TEST FIBRE-OPTIC ELECTRIC
ESD
SELECTED SELECTED
SHORE RECEIVING TANK
HIGH LEVEL
POWER
LOADING ARM TRIP 2
RESET RESET
FIBRE OPTIC /ELECTRIC
SYSTEM SELECTOR MODULE
PORT STBD
CIRCUIT
FIBRE OPTIC CONTROL & ALARM MODULE TEST
OFF
ESD SYSTEM SELECT TEL CH1 TEL CH2 TEL CH3 TEL CH4
C MIYAKI C C C C
B D B D B D B D B D
A E PYLE ITT A E A E A E A E
CANNON
3 0 0 0 0 0
The selection position will again be dependent on which LNG terminal is being a) Ensure that the SSL is powered down. Ship-Side Connection Boxes
visited.
b) Pull the SCM out from the SSL far enough to allow the lid to be Stainless steel ship-side boxes and connectors are provided port and starboard
removed to gain access to the PCB. midships. These carry:
Switch No.5 - Public Telephone Channel No.3
Switch position: c) Use the information obtained from Seatechnik to make the 1) A 37-way Pyle-National connector is fitted for signal transmission
necessary ‘patching’. to shore, and 4-way earthing connectors are installed with local
A) Pins 1 and 2 are connected.
earthing to enable shore-ship bonding by local rules in French
B) Pins 3 and 4 are connected. terminals. The connectors are spring-loaded and the plugs
d) Return the SCM into the SSL.
C) Pins 5 and 6 are connected. disconnect while the barrel is still connected to the receptacle.
D) Pins 7 and 8 are connected. Cargo Control Room ESD Panel Illustration 4.12.1g Ship-Side Connector Box
E) Pins 9 and 10 are connected.
Located in the centre section of the cargo control console is the ESD panel
The selection position will again be dependent on which LNG terminal is being which contains the following:
visited.
STRAINSTALL CONNECTOR
The selection position will again be dependent on which LNG terminal is being • Ship/Shore link switch wrong position indicator lamp
visited.
• Pneumatic link bypass switch wrong position indicator lamp
ON - HOTPHONE IN USE
OFF - P/L PHONE
CALL SIGNAL
To Make Call: Lift handset - Press ‘CALL’ Lift handset - Hear ring
& hold while tone and
speaking speak when
or - Press ‘SIGNAL’ phone is
& hold to alert
called phone
answered
www.seatechnick.com
To Answer Call: Lift handset and speak Lift handset and speak
To End Call: Replace handset Replace handset
No.1 Pressure
Terminal Box Transmitter
for Air
Control Board
To Shore
Pressure
Switch
Suppy Air
Pressure
Air Control Board
Test Test
Normal Normal
Close
Open Signal Converter
PI
(Isolation) To DACS
Air Supply Needle PT PT
Mist (Pressure Monitor)
Air In Solenoid Valve Air Out In Out
Separator Valve 0 - 1MPa
with Filter Air Supply
4 - 20mA
Solenoid
Valve 24V
PI Pressure
Transmitter Box
(Intrinsically Safe Type)
In Out
In Out
Control Air In Out
Supply
In Out
Exhaust
Solenoid Valve Box
(Flame-proof Type)
Introduction 1) The pneumatic dump valve will route the air from the ESD line
S/S Pneumatic Link Selected
(CCR)
between the ship and the shore to atmosphere.
In the event of either the optical or the electrical link being unavailable, a
pneumatic link can be used. 2) The ship’s air supply will be disconnected from the ESD line
between the ship and the shore.
The ESD will be activated if the pneumatic link is disconnected or broken Set the ‘Normal Press’ Set the ‘Trip Press’
and the air pressure falls below the preset trip setting which is adjustable in (CCR) (CCR)
3) The operatives on the ship and shore must now remove any
the cargo control room. The DACS mimic screens will indicate the reason inhibits on the DACS. The system is now in a healthy state.
for the ESD situation by a change of colour, from green to red, of the item
causing the ESD. The cargo pump and spray pump symbols will change colour,
indicating that there is a block on their operation and further operations are No Press ‘RESET PB’ Ship-to-Shore ESD Pneumatic Trip
within 5 seconds
not permissible. Once the cause of the ESD has been cleared, the ESD system Generating a ship-to-shore ESD trip is achieved by opening the ship-side
can be enabled by activating the RESET button on the cargo control console. contacts. When this is done the soft dump valve will de-energise, causing the
Yes
Symbols will change from red to green, indicating that further operations are S/S Pneumatic Link ‘Not Used.
(CCR)
air in the system to vent to atmosphere. Both the ship and shore-side systems
permissible. Valve Control will detect this change in pressure. The shore-side circuit will then open,
1. Air Supply Valve Close indicating an ESD unhealthy condition.
The pneumatic link consists of an air hose connected to the terminal and 2. Quick Charging Valve Close
3. Air Releasing Valve Open
pressurised to a setting which is agreed between the ship and the terminal. The 4. EP Regulator Power ‘Off’
pressure is set in the cargo control room. Shore-to-Ship ESD Pneumatic Trip
Valve Control If the shore terminal exhausts the system air at the shore facility, this will
Both the ship and the terminal have pressure switches which will activate an 1. Air Supply Valve Close
2. Quick Charging Valve Close
generate a shore-to-ship ESD. The ship’s pressure transducer will then sense
ESD trip in the event of a loss of air pressure. Unlike the electrical and optical Start the Electro Pneumatic
Pressure Control to ‘NORMAL PRESS’ 3. Air Releasing Valve Open the drop in pressure and on dropping below the SET value, the latching relay
links, there is no communication link, so communication can only be achieved 4. EP Regulator Power ‘Off’ will drop out.
by radio.
Closed
Dome
The valve is kept closed by the pressure in the sensing chamber, boost chamber
Introduction and dome chamber being equal to the tank pressure and less than the force
exerted by the spring-load.
Each cargo tank is fitted with two pressure/vacuum relief valves as required
by the IMO code. The primary insulation and secondary insulation spaces are When the tank pressure reaches the set pressure it overcomes the spring-load,
each protected by two pressure relief valves per cargo tank. The valves are allowing the disc of the pilot valve to open slightly, causing a small flow of gas
manufactured by Fukui Seisakusho and are designed specifically to work on through the pilot line to be discharged via the pilot valve outlet.
marine-based LNG systems.
This discharge causes a pressure drop in the sensing chamber, which in turn
4.13.1 cargo tank relief valves destroys the pressure balance condition between the sensing chamber and
boost chamber, causing the pilot valve to open fully.
Manufacturer: Fukui Seisakusho
Type: PORV 10 *12 When the pilot valve opens, it in turn causes a drop in pressure within the main
Model: PSL-MD13-131-NS1(B) valve dome chamber and the main diaphragm is pushed upwards, raising the
sealing disc and opening the main valve, venting the tank to the respective vent
Tag No: CGR101//501,102//502 mast riser.
No. of units: 10
No. per tank: 2 When the tank pressure drops to a predetermined level, the spring-load begins
Set pressure: 25kPa(g) to overcome the system pressure again, causing the pilot valve to go down and
re-seat. The tank pressure acts on the main diaphragm, causing the main valve
Closing pressure: 22kPa(g)
to close and the pressure in all the chambers is again equalised.
Blowdown pressure: 3kPa
Blowdown %: 12%
Flow rate per valve: 23,840Nm3/h
Vacuum setting: -1kPa(g) ±25%
The cargo tank relief valves are fitted at the top of each tank liquid dome
and vent to their associated vent mast riser. The relief valves are of the pilot
operated relief valve type (PORV). A cargo tank pressure sensing line relays
the pressure directly to the pilot operating valve, therefore, accurate operation
at low pressures prevailing inside the tank is assured.
The cargo relief valves are set up initially by the manufacturer for the
requirements on the ship. If overhaul of the valves by ship’s staff is carried
out, the valves must be checked and reset to the original settings. (See the
manufacturer’s instructions for details.)
Diaphragm
Set Plates
Boost
Disc Diaphragm
Spring
Guide Cover Boost Cap
Lock Nut
Disc Diaphragm
Seat Cover Centre Cover
Spindle
Sleeve Body
Nozzle
Seat Diaphragm
Upper Spring
Washer
Sense
Sense Pipe Diaphragm
Valve Body
Upper Case
Diaphragm
Retainer
Model: PSL-MD13-131-S1(B)
A gas detection line is led out from below each of the valves to the gas
Tag No: NC102//502,103//503 monitoring system to give a constant indication of the atmosphere inside the 3.5 Pressure Relief Valve Open
Number of units: 10 interbarrier and insulation spaces.
Number per tank: 2
Set pressure: 3.0kPa(g) The IBS space relief valve outlet is led to a separate vent line, which runs up 3.0 Pressure Relief Valve Open
alongside the associated vent mast. This is in order to prevent any counter-
Closing pressure: 1.8kPa(g)
pressure or back-flow from the main vent mast should the cargo tank relief
Blowdown pressure: 1.2kPa valves lift, or from the nitrogen snuffing system. 2.5 High Pressure Alarm
Blowdown %: 40%
Flow rate per valve: 398Nm3/h It is extremely important the vent line is checked on a regular basis and drained N2 Exhaust
(0.7kPa) Valve Open
Vacuum block: -80kPa(g) (no leakage for 1 minute) of any accumulation of water. The purpose of this is to ensure that the relief 2.15
valves operate at their correct settings, which would otherwise be altered if any
N2 Exhaust
water were to accumulate in the vent mast and flow onto the valve assembly. 2.0 (0.5kPa) Valve Close
Insulation Spaces (IS)
The IS insulation space relief valves vent directly out to the deck, via a N2 Supply
Manufacturer: Fukui Seisakusho downward-facing tail pipe. It is not necessary for these to be led to a mast (0.4kPa) Valve Close
Type: PORV 2*3 riser, as the likelihood of there being LNG vapour in this insulation space is N2 Supply
Model: PSL-MD13-131-S1(B) very remote. Valve Open
1.5 (0.2kPa)
Tag No: NC101//501,104//504 High Pressure Alarm
The IBS and IS insulation space relief valves are set up initially by the Low Pressure
Number of units: 10 1.0 N2 Exhaust Valve Open Alarm
manufacturer for the requirements on the ship. If overhaul of the valves by
Number per tank: 2 ship’s staff is carried out, the valves must be checked and reset to the original 0.8 N2 Exhaust Valve Close
(0.0kPa)
Set pressure: 3.5kPa(g) settings. (See the manufacturer’s instructions for details.)
0.7 N2 Supply Valve Close
Closing pressure: 2.1kPa(g)
IBS Pressure
Blowdown pressure: 1.4kPa The above values in ( ) are the
Blowdown %: 40% 0.5 N2 Supply Valve Open Differential Pressures between the
IBS and IS.
Flow rate per valve: 481Nm3/h 0.4 .
Low Pressure Alarm
Vacuum block: -80kPa(g) (no leakage for 1 minute)
404V
412V WBV LX
600
376
400 400 400 400 400 400 400 400 400 400 400 400
WBV091 1000
PI CP WBV WBV WBV WBV WBV WBV LCAL
251 241 231 221 213 211
LIAHL
400 600 WBV
WBV WB WBV331 WBV WBV WBV WBV WBV LIAHL
BA32 212
WBV 334 333 No.3 Water 252 242 232 222 214
LS
366 Ballast Pump WBV BA31
LX WBV332 052
600 600 600 400
LX
WBV WBV335
PI CP WBV LCAL WBV WBV011
364 LS
362 012
400
Aft WBV324 WB323 WBV321 LCAL Fore
WBV LS Pipe Duct
Peak WBV No.2 Water WBV Peak
361
Tank 363 Ballast Pump 022 Forward Tank
WBV322 Void Water
WBV WBV050 (Central) Ballast
WBV315 200 200
051 Tank
PI CP
WBV
600 600 600 400
351
WBV314 WBV021
WBV WBV313 WBV311 WBV
365 No.1 Water 341 BA33
Ballast Pump WBV WBV WBV WBV WBV WBV LS
152 142 132 122 114 112
WBV312 200 BA34
WBV WBV WBV WBV WBV WBV
WBV354 WBV352 WBV WBV345 LCAL
No.2 151 141 131 121 113 111
250 373
WBV353 200 400 400 400 400 400 400 400 400 400 400 400 400
WBV344
No.1 200 WBV342 1000
Key
Sea Water
Hydraulic Oil
Electrical Signal
Instrumentation
The on-screen ballast menu also shows when the pumps are switched to remote
or manual operation, pump’s amps, pump’s suction and discharge pressure, the
position of the valves and the contents of the tanks, which can be displayed as
a combination of the following choices:
• Level in metres
• Ullage in metres
• Volume in m3
• Volume as a percentage
• Weight in metric tonnes
• Density in tonnes/m3
4 x Digital Indicators
For Draught
M M M M
24V DC
Power Supply
DACS IS Barrier Box
Air
From 7 bar
Pressure
Air Supply
Controller
The ballast and draught transmitter signals are linked into the Distributed
The following methods can be used to measure hydrostatic pressure.
Alarm and Control System (DACS) and to the draught digital display units
located in the CCR.
1) Sounding Pipe Method
The measuring line from all the electric-pneumatic type transmitters are led Applicable to tanks where the bubbling air can be fed to the tanks, such as
back to the DACS in the CCR and passed to their respective displays. ballast tanks, diesel and fuel oil tanks etc, and is also suitable for draught
measurement.
Note: The draughts displayed on the cargo console digital display are
the actual draughts at the transmitter positions. These are automatically
2) Pressure Converter Method
corrected at the transmitter box to give the true draught at the fore, aft and
beam perpendiculars. The corrected draughts are then displayed on the Applicable where the feed air to the tank is prohibited, such as drinking water
various monitors. tanks.
Due to the introduction of alien marine species from foreign ballast water being 1. Automatic Ballast Exchange (ABE) Ballast Exchange Start-Up
discharged into their port areas and upsetting the local ecological balance, Ballast/Deballast Sequence Description
several countries now require that vessels arrive with ballast loaded in deep On the Ballast Exchange Planning mimic the target levels are set up by
In the sequential method of ballast exchange the ballast tanks are discharged pressing the CHANGE button, followed by the APPLY button when complete.
sea open conditions.
and filled in a thirteen step sequence with due regard to the stability, trim and This must be done before starting ABE.
heel of the vessel. Protection is given to the tanks with interlocks for both high
During the ballast voyage the vessel will have to discharge the ballast tanks
level and low level in the ballast tanks. On the ballast valve mimic, enter maximum open and throttle limits for
and re-ballast with clean deep sea water. This has to be carried out taking into
consideration the effects on the stress and stability of the vessel during any automatic operation.
ballast change. Note: Where the tanks have been part discharged or filled, this is to allow
for the correcting of any heel or to maintain trim and stress within suitable On the Ballast Exchange Operation mimic, place the pump and tank systems
Ballast changes are carried out in deep sea areas over a period of time, usually limits. in AUTO, then press the ABE LINE UP button to set the pumps in sea-to-sea
discharging one or two sets of tanks at a time, subject to the stresses and mode.
stability calculations, then refilling with deep sea clean water. This sequence The whole exchange process is executed in two parallel sequences, one for
of changes is continued until all ballast water from the discharge port has been port and one for starboard. At the end of each empty or fill step a cross-check Activation of the ABE is done via the start permissive mimic by pressing
discharged and replaced. is performed to ensure that the parallel sequences remain in phase. In the the ACTIVATE button. If ABE is terminated or finished the system will be
transition stage between empty and fill operations and vice versa the system deactivated, buttons for terminating should only be used for safety reasons.
All changes and ballast operations are to be entered in the Ballast Record will circulate water from the selected sea chest to overboard to avoid frequent
Book, giving the position when the operation commenced, when completed pump start/stop operations. Monitoring and control of the operation is carried out from the Ballast
and quantities involved. Similar entries are made in the Deck Log Book. When Exchange Operation mimic.
the vessel arrives at the loading port the port authorities may inspect these The ballast/deballast sequence controls and/or monitors the following:
documents to confirm that the entries agree. Some countries also require a • Ballast valves Flow-Through Method
chemist to take samples of ballast water and carry out tests before allowing any
discharge of ballast within territorial waters. • Ballast tank level
The flow-through method, whereby tanks are overfilled by pumping in
• Ballast pumps additional water, has the advantage it can be used in weather conditions which
Note: Failure to comply with the above requirements and provide an accurate • Trim and list limits if exceeded pumps will change sea-to-sea would be marginal for use of the sequential method, since there is little change
record can result in severe penalties for both the vessel and the shipping in the condition of the ship.
company. • Loading stability computer
There are safety considerations to be taken into account, and these are outlined
During ballast exchange while at sea the following draughts should be The ballast operator cannot start a ABE unless the following are satisfied: in the Ballast Water Management Procedures.
complied with. • Ballast pump and tank system in automatic mode
It is necessary to pump in three times the volume of the tank to achieve a 95%
The minimum forward draught is to avoid slamming of the bow, ballast • Ballast pumps are in sea-to-sea mode (ABE line-up button) change of water. Pumping in once the volume produces a 63% exchange, twice
exchange where the forward draught will be less than stated is only to be • Ballast Exchange Planning is confirmed ‘READY’ produces 86% exchange, while four times produces 98% water exchange.
carried out in suitable weather.
• The interface to the load and stability computer is OK and there
are no Critical Force alarms.
The minimum aft draught is to ensure adequate propeller immersion.
• Lines are fully flooded
Minimum forward draught: 8.80m
• No pumps are selected for IGG
Minimum aft draught: 8.80m
• Hydraulic pressure is above the alarm limit
• No tanks are active that is an ongoing ballast operation
TIAL
CTn01
Fwd
(Hull)
TIAL Side Wall IAL
T
9A
CTn09 Side Wall TE
CTn15
16A
4A
9B TIAL TE
CTn03 16B
TIAL 4B
10A CTn18
10B
1B
1A Fwd
TIAL
Chamfer
8A
CTn06
Lower
TIAL 3A 8B
TIAL
CTn17
CTn04
3B
Port
2A 2B
TIAL
CTn05
Starboard
General Description
Monitoring equipment is provided in the cargo control room for the insulation
barrier and inner hull temperatures to give warning in case of a failure of the
insulation or a leakage into the interbarrier spaces and/or insulation spaces.
Each sensor is of the resistance type PT-100 (RTD). The sensors are installed in
the insulation barriers and alongside the inner hull associated with each cargo
tank. The temperature range of each sensor is: -200°C to +100°C.
The interbarrier space (IBS) RTDs (sensors), are installed in three locations
as indicated on the illustration 5.1a, all of them in pairs. The insulation barrier
(IS) RTDs are installed at seven points around the space as shown, all of them
in pairs. During normal conditions, one RTD is in service whilst the other is
on standby.
For the inner hull temperature measurement there are five sensors in each
tank, three are located along the bottom of the tank in the duct keel, while two
sensors are located in the trunk deck.
In the cofferdam spaces there are three temperature sensors on each of the
forward and aft bulkheads, except the forward bulkhead of No.1 cofferdam
which has five sensors, and the aft bulkhead of No.5 cofferdam which also has
five sensors as indicated in illustration 5.1b.
The RTDs for the IS barrier sensors alarm point is set at -140°C and for the IBS
barrier sensors (bottom) -150°C. The RTDs for the inner hull sensors alarm
point is set at 0°C.
Nitrogen Generating Plant IS supply valve open setting = IBS + 0.2kPa (opens when the IS is less than
0.2kPa above the IBS). Nitrogen Header Alarms
The nitrogen generators are operated locally from a dedicated control panel
with alarms and system conditions being monitored by the DACS. There is one Tag No. Description Low High
IBS exhaust valve open setting = 1kPa (opens when the IBS pressure increases
control cabinet that contains mimic panels and oxygen analyser read-outs for Header pressure 2kPa 6kPa
above 1kPa).
the two generators. The DACS monitors the generating plant and indicates any Nitrogen bleed line pressure 0.2kPa
alarms or shutdowns that have been activated. The local control panel permits IS exhaust valve open setting = IBS + 0.4kPa (opens when the IS is more than
fully automated unmanned operation of the units and contains the following: 0.4kPa above IBS).
Procedure for Setting Nitrogen System
• Monitoring process and status indications
• Monitoring alarms and changing alarm settings IBS and IS Alarms The nitrogen generator is operated through an E600 controller mounted in the
compressor cabinet door. The details and procedure for operating this and the
• Stop/Start of the nitrogen system • IBS low pressure: 0.2kPa nitrogen generating plant have been given in Section 4.8 of this manual.
• Changing controller set points and parameters • IBS high pressure: 1.5kPa
• Continuous oxygen content reading With the nitrogen generator in automatic mode and the buffer tank pressurised,
proceed as follows:
• Dew point analyser output • IS low pressure: 0.4kPa
• Electrical heater temperature control • IS high pressure: 2.5kPa a) The manual valves each side of the supply and exhaust control
valves, together with the valves to the liquid and gas dome
• Emergency stop pushbutton gauge boards, should be fully open.
• IBS/IS differential pressure: 0.2kPa (low)
• Mains isolating switch
• IBS/IS differential pressure: 0.5kPa (high) b) The IBS nitrogen supply control valves NC109, NC209, NC309,
NC409 and NC509 are normally set to 0.5kPa at the DACS, and
the IS supply control valves, NG14, NG31, NG50, NG68 and
NG90, set for IBS plus 0.2kPa(g), eg, 0.7kPa.
NG98 CR501
PS PIAL No.5 Liquid Dome
DACS
Gauge Board NG76
PI To Aft IS Bilge Well PI
NG91
IBS
Dome
IS
Liquid Key
IBS
IS
40V Set at 32V
0.55MPa Dome To No.5 Gas Nitrogen
Set at NC506 Dome Gauge Board
0.55MPa Electrical Signal
37V 38V CR503 NC505
34V No.5 Liquid Dome To Fixed Gas
36V NC501
Gauge Board Detection System
NC507
NG
Set PX
Set
PCV-8.70 PCV-8.68 NC502 NC504 114
0.5MPa 0.5MPa NC513
PI NC514 NC503 NG77
33V 35V NC517 NC515
NC518
From
Set at
Engine Room
1.3MPa
V-8.64 NC516
To Spray Line
CR502
Valve SAS551
NC512 NG108
Nitrogen Buffer Tank PI NC510 NC509 NC508 To Fixed Gas
(65m3) Detection System Motor Room
Compressor Room
NC511
NG75
NC519
NG74
From Nitrogen No.2 HD Compressor Shaft Seal
Generator NG72
Plug No.1 HD Compressor Shaft Seal
To Nitrogen To Nitrogen
Generator Membrane No.2 BOG Compressor Shaft Seal
Booster
For Purging No.2 BOG Compressor BHD Seal Cold Box
Compressor
Insulation
No.1 BOG Compressor Shaft Seal Skid
No.1 BOG Compressor BHD Seal
NG73 NG113
Note: Ensure that the manual bypass/isolating valves situated on both the
supply and exhaust lines on each tank are closed, eg, NC108 and NC110 for
No.1 tank IBS supply and NC101 and NC103 for the IBS exhaust.
In the event of cargo gas leakage into an insulation space, each space can be
swept with a continuous feed of nitrogen by opening the exhaust bypass valve
from the space and allowing a controlled purge. Close monitoring of the gas
analyser on this space will be necessary during purging.
CAUTION
The insulation spaces must at all times be protected against over-
pressure which might otherwise result in membrane failure.
The system will automatically adjust the pressures in the IBS and IS spaces,
exhausting if the pressure exceeds the exhaust valve set point and making up if
it falls below the supply valve set point.
Key
Glycol
Glycol Storage
CH115 Fresh Water
Tank
(6.0m3)
Air
CH114 Steam
Condensate
Drains
Electrical Signal
Expansion
LAH
From Deck Tank TAHH
Compressed (1.0m3)
CH113 Air System TX
Steam
TIAL TS TIAH TIC
CH111
TX PI PI TI TI PI TX TX
From CA50
Glycol No.2 Glycol
Fresh Water FW10 (See Illustration 5.3.1b) D B (See Illustration 5.3.1b)
Transfer Pump Water Heater
System (2m3/h x 100kPa) CH107 CH103 CH99 CH97 GH693 CH91 CH88
(2.14.1a No.2 Glycol Water
Machinery) CH112 CH109 Circulating Pump CH95 TI
Condensate
CH105
PIAL
Water / Glycol PX
CH89
Mixing Tank
(0.2m3) PIAL
PX
TAHH
CH117
CH104
CH110 Steam TIAH TIC
TIAL CH94 TS
TX TX
TX PI PI TI TI PI
No.1 Glycol
(See Illustration 5.3.1b) C A (See Illustration 5.3.1b)
Water Heater
CH106 CH102 CH98 CH96 GH692 CH90 CH87
No.1 Glycol Water
CH108 Circulating Pump TI
(33m3/h x 410kPa) CH161
Condensate
CH118
Motor Room
(See Illustration 5.3.1a) Key
A B C D Glycol (Main Line)
Glycol (Standby Line)
ZI ZI
Electrical Signal
CH CH CH CH
TIC 18 17 16 15
CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH
86 85 78 77 74 73 66 65 60 59 52 51 46 45 38 37 32 31 24 23 14 13 06 05
CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH CH
120 119 76 75 64 63 62 61 50 49 48 47 36 35 34 33 22 21 20 19 04 03 02 01
CH CH CH CH CH CH CH CH CH CH CH CH
82 81 70 69 56 55 42 41 28 27 10 09
The glycol/water mixture is circulated through the system of heaters by means c) Assuming that the No.1 steam heater and the main (primary)
heating coils are to be used, prepare the heater valves in Position Description Valve
of a circulating pump, one in use, with the other on standby.
accordance with the following table: Open Primary supply line air eliminator valve CH18
The cofferdam spaces each have two sets of heating coils. The flow of glycol/ Open Primary return line air eliminator valve CH15
water mixture to each set of coils is through a three-way valve and a throttling Position Description Valve Open Secondary supply line air eliminator valve CH17
valve. The second standby set can be put into service immediately as a totally Auto No.1 steam heater temperature control valve GH92 Open Secondary return line air eliminator valve CH16
separate system in the event of failure in the primary system.
Open No.1 steam heater inlet valve CH96
Open No.1 steam heater outlet valves CH90, CH87 i) Start circulating pump No.1 either locally or on the DACS
The automatic flow control to each cofferdam and liquid dome is achieved display screen.
by means of a three-way valve on each header and the operating signals for Closed Crossover valve to secondary coils CH89
regulation are via the DACS mimic. Throttling valves on each header return j) Bleed the system and remove any air from the heating coils.
line are set after conducting trials and should not be adjusted unless in a d) Ensure the valves from the expansion tank are open:
problematic situation. k) Monitor the cofferdam temperatures and adjust as necessary.
Position Description Valve
Operating Procedure for Heating Coils Open Expansion tank drop valve CH111 The standby heating coils can be prepared for operation in the same way so that
they are ready for immediate use should the need arise.
In normal operation conditions, No.1 glycol circulating pump will operate e) Open the normal glycol water supply and return valves to each
on heating the main coil, while the No.2 circulating pump will be switched set of cofferdam heating coils. The No.1 cofferdam is listed
to standby operating on the secondary coil. The standby pump will then start below as a typical example:
automatically if the duty pump has a low discharge pressure, if there is a pump
failure or there is a loss of running signal. No.1 Cofferdam (Typical Example)
a) Prepare the valves on both circulating pumps in accordance with Position Description Valve
the following table: Open Cofferdam inlet valve to main coil CH14
Automatic Cofferdam control valve to main coil GH12
Position Description Valve Open Cofferdam outlet valves from main coil CH01, CH03
Open No.1 circulating pump isolation valve CH106 CH05
Open No.1 circulating pump suction valve CH102 Open Cofferdam main coil bypass valve CH07
Closed No.2 circulating pump isolation valve CH107 Open Cofferdam inlet valve to secondary coil CH13
Open No.2 circulating pump suction valve CH103 Automatic Cofferdam control valve to secondary coil GH11
Open No.1 circulating pump expansion valve CH104 Open Cofferdam outlet valves from secondary coil CH02,CH04
Open No.2 circulating pump expansion valve CH105 CH06
Closed Expansion line drain valve CH110 Open Cofferdam secondary coil bypass valve CH08
b) Warm-through the heater prior to use. Set the other cofferdam heating coil valves in the same manner as listed above,
then in the cargo control room, proceed as follows:
IG02
Vapour Main Key
Compressor
Room
No.5 No.4 No.3 No.2 No.1 Hull
IG05 Duct
Trunk Trunk Trunk Trunk Trunk
IG04 IG03
From Inert Gas
Dry-Air Plant
IG06 No.5 Cargo No.4 Cargo No.3 Cargo No.2 Cargo No.1 Cargo
Tank Tank Tank Tank Tank
To Ballast Tank
Ventilation
No.4 Water Ballast Tank No.4 Water Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1 Water Ballast Tank
(Port & Starboard) (Port & Starboard) (Port & Starboard) (Port & Starboard) (Port & Starboard)
IG04 IG03
Vapour
Return
M/H M/H
Manhole Cover M/H M/H
for Cofferdam No.2 CD No.1 Trunk
No.4 CD No.3 Trunk No.3 CD No.2 TR
M/H M/H to be opened Entrance Entrance Hatch Hatch Entrance
when Gas Freeing Entrance Hatch Hatch Entrance Hatch Hatch Entrance M/H
Passageway
Mechanical Passageway
Passageway
Exhaust Vent Nat. Supply Vent
Nat. Supply Vent
Injured Person Injured Person Injured Person Injured Person Injured Person Injured Person
Hatch Hatch Hatch Hatch Hatch Hatch
No.5 Cargo Tank No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
WARNING
If it has been found that nitrogen consumption has increased beyond
normal acceptable levels, then added precautions should be observed
before entering the cofferdam spaces.
Dry-air is sent from the IG plant, through valves GI601 and GI602, into the
ballast main and then to the required ballast tank via its suction valve.
The ballast tank lid is opened to allow the air to be exhausted to atmosphere.
Illustration 5.4.1a Fire Hydrant System in the Engine Room Upper Deck (See Illustration 5.4.1b)
To Water Spray
Main
BF110
Compressed Air 3rd Deck (Starboard Stores) 3rd Deck (Port Aft)
BF128 BF129
Bilges
3rd Deck (Starboard Middle) 3rd Deck (Port Middle)
Electrical Signal BF86 BF87
4th Deck (Starboard Diesel Generator Room) 4th Deck (Port Diesel Generator Room)
BF126 BF127
4th Deck (Starboard Middle) 4th Deck (Port Middle)
BF84 BF85
Floor (Starboard Aft) Floor (Port Aft)
BF124 BF125
Floor (Starboard Forward) Floor (Port Forward) From Starboard Stern
From BF82 BF83 Tube Cooling Water Tank
Port Stern Tube (2.4.2a Machinery Operating Manual)
To Exhaust Gas
Cooling Water Tank From Port Aft Bilge System Economiser Washing
PIAHL From
(2.4.2a Machinery Operating Manual) (2.9.1a Machinery Operating Manual) PX
Drain Tank Discharge
MM029 Starboard Aft
14V
Eductor Bilge System
PI
To Overboard (2.9.1a Machinery Operating Manual)
Sea Chest (Port) Bilge Main
110V
LMS 111V
129V
P36V To Ballast
109V 107V
To 15V Stripping
LMS
Sewage Self-Priming Type 13V WBV Eductors
Collecting 14V From 347
PI Self-Priming PI No.2 Bilge, Fire
Tank Type
Inter-
and General Starboard
Lock
Cleaning Fire Pump Service Pump Fresh Water Tank PI
P9V PI 18V Water Spray
(150m3/h x (225/150m3/h x No.1 Bilge, Fire and (2.14.1a Machinery
CI CI Pump (900m3/h x
1.1MPa) 305kPa/1.1MPa) General Service Pump Operating Manual) 900kPa)
(225/150m3/h x CI
305kPa/1.1MPa) CI
128V
141V 139V
Air Air
LMS
Inter-Lock WBV 12V
104V LMS
18V 11V 348 High Sea
High Sea 105V
Chest (Port) Chest
WBV WBV Fire Bilge Pump Air S106V WBV WBV (Starboard)
Start/Start Fire Line
374 376 Forward Pressurising Pump 373 373
Low Sea LMS To Bilge LCHL
LS 120V 126V LMS Low Sea
Chest PP138 Bilge Well 16V (2.0m3/h x 500kPa) Chest
Well To Bilge Separator
(Port) LAH (Port) LMS
(Starboard)
WBV BG105
LS
Air Forward
PI CI Service and Bilge Pump WBV
LS LAH 372
375 From Cofferdam Bilge Well LS
BG104
132V Around Pipe Duct LCHL (Starboard) 125V
PP137
The fire main and deck wash system supplies the hydrants located in the engine Pump Control
Bilge, Fire and General Service Pumps
room, around the accommodation block and out on deck. If a hydrant valve
Manufacturer: Shinko Industries Ltd. is opened beyond the capacity which can be accommodated by the fire line The fire line pressurising pump runs continually, discharging overboard via
No. of sets: 2 pressurising pump, the pressure in the fire main will fall, and because the fire an orifice, and maintains the fire main at a constant pressure of 300kPa. In
line pressurising pump has insufficient capacity to maintain the pressure due to normal operation the bilge, fire and GS pumps will have their valves lined-up
Type: Vertical centrifugal motor-driven to operate on the fire main and the pump control set to DACS. The bilge, fire
the volume of flow through the hydrant, it will be necessary to manually start
Model: RVP200-2MS the fire pump or the duty bilge, fire and GS pump to meet the demand. Neither and GS pumps, fire pump and emergency fire pump are started in remote mode
Capacity: 255/150m³/h at 305/1.1MPa the fire pump, the emergency fire pump or the bilge, fire and GS pumps have from the DACS workstations, or they can be started at the emergency panels or
Motor rating: 440V, 110kW at 1,800 rpm an automatic start function. locally at the pump(s) local starter panel(s).
For routine wash deck requirements the fire pump will be started manually Deck Fire Main
Fire Pump with the fire main then being bled through one or more of the hydrants. When
any of the pumps which can be used to supply the fire main and deck wash The deck ring main has a number of isolating valves which allows a section
Manufacturer: Shinko Industries Ltd. of the ring main to be isolated if it is damaged, while maintaining the integrity
system are running, at least one of the hydrants must remain open at all times
No. of sets: 2 and sea water supply on either side of the isolated section.
to ensure there is always a flow of water through the pump’s casing which will
Type: Vertical centrifugal motor-driven prevent overheating.
Model: RVP160-2MS The deck fire main and deck wash water is supplied from the engine room via
The two bilge, fire and GS pumps located in the engine room can also be a single isolating valve BF109, which is located forward of the engine room
Capacity: 150m³/h at 1.1MPa
lined-up to take suction from the sea water crossover main and discharge to casing on the main deck level. The emergency fire pump supplies the deck fire
Motor rating: 440V, 90kW at 1,800 rpm main and deck wash water (and back-feeds if necessary into the engine room)
the fire main and deck wash system. If they are to be used in this way, their
suction valves on to the bilge main MUST be closed in order to ensure that from the forward section of the deck ring main. The deck fire main runs inside
the supply of bilge water to the fire main, which could result in traces of oil the port and starboard side passageways, with the individual section isolating
Fire Line Pressurising Pump valves operated by extended spindles from the open deck. The supply from
contained in any bilge water being directed to a burning fire, is not allowed, or
Manufacturer: Shinko Industries Ltd. the additional possibility of the bilge, fire and GS pumps losing suction due to the fire main deck wash water system to the forward bilge eductors and the
No. of sets: 1 an empty bilge well. In order to ensure that the bilge suction isolation valves on hawse pipe wash water can be isolated via valve BF13. The supply to the port
the pump(s) cannot be opened when the pump(s) discharge to the fire main is and starboard sides of the accommodation can be isolated on the upper deck
Type: Horizontal centrifugal motor-driven
open, a signal control line has been fitted on the solenoid control valve which via BF92 and BF123. The supply to the after deck including the steering gear
Model: SVS400MS compartment and emergency generator room is isolated via BF114.
operates the pneumatically operated bilge suction valves. When the discharge
Capacity: 2.0m³/h at 500kPa valve from the pump(s) to the fire main is opened an interlock signal is directed
Motor rating: 440V, 3.7kW at 3,600 rpm to the solenoid valve which will block the opening of the bilge isolating valve. The fire main and wash deck system can supply sea water to the following:
Additionally, the two bilge, fire and GS pumps can also be arranged to have • Hawse Pipes - The water can be used at the two anchor chain
their suction lined up to the port and starboard aft peak tanks. hawse pipes for cleaning the chain as the anchors are being
Emergency Fire Pump retrieved. Each hawse pipe has its own isolating valve fitted to
Manufacturer: Shinko Industries Ltd. The sea water crossover main can be isolated into port and starboard systems allow them to be operated individually from the main deck level.
Model: RVP160-2MS if necessary via isolating valve S106V. The fire pump and No.1 bilge, fire and The valves are BF02 and BF01 for the port and starboard hawse
GS pump are situated on the port side of S106V, while No.2 bilge, fire and pipes respectively.
Type: Motor-driven, vertical centrifugal
GS pump is situated on the starboard side of S106V. The fire line pressurising
Sets: 1 • Cargo Manifold Water Curtain - Each water curtain spray rail
pump is located on the port side of S106V.
has holes drilled into it and has deflector plates fitted to ensure
Capacity: 72m³/h x 1.1MPa
that all of the spray water is directed down the side shell of the
The bilge, fire and GS pumps and the fire pump can be cross-connected to
ship.
supply the water spray main on deck if necessary.
Emergency Generator BF81 BF77 BF71 BF64 BF63 BF59 BF47 BF43 BF41 BF37 BF33 BF29 BF27 BF21 BF17 BF03
Room To BF02
Engine Casing Accommodation
To Foam No.5 Trunk No.4 Trunk No.3 Trunk No.2 Trunk No.1 Trunk
BF122 A
System
BF123 BF06
BF13
BF90 BF72 BF56 BF38 BF24
BF69 BF60 BF44 Side Passageway BF30 BF22 BF14
BF116 BF134
BF93 BF78 BF74 BF65 BF34 BF18
BF50 BF49
BF48
To Bilge Eductor Driving Line
in Side Line Boarding Spaces Cargo Manifold
Side Elevation
BF51 Water Curtain
Eductor Driving Line
To Deck for Bosun’s Store
BF02
Fire Main BF07
BF03
System
A Detail B Detail BF13
Bosun’s Store
PI Eductor Driving Line
Emergency Fire Pump BF06
BF05 for Chain Locker
BF110 BF109 (72m3/h x 1.1Mpa)
Procedure for Pressurising the Fire Main Using the Fire Line BF112 BF133
Pressurising Pump Bilge, Fire and General Service Pumps For Emergency Upper Deck
Generator Room BF92
Position Description Valve
a) Ensure that the sea water suction main is flooded with either the
high or low sea suction valve open, in normal operations the sea Locked No.1 bilge, fire and GS pump sea suction valve B12V BF94
BF117
water crossover isolation valve S106V is open. open
Interlocked No.1 bilge, fire and GS pump bilge suction valve B11V BF91
BF114
b) Open the fire line pressurising pump suction valve B125V from closed
the sea water main, the pump discharge valve B126V to the fire Closed No.1 bilge, fire and GS pump water spray rinsing B15V Emergency Generator BF81
main and the overboard discharge valves B120V, B110V and line discharge valve Room
Engine Casing
B130V. Closed No.1 bilge, fire and GS pump discharge valve to B13V
overboard/port and starboard sea water service BF122 To Foam BF109
System BF110
c) Start the fire line pressurising pump at the local starter panel. line
Interlocked No.1 bilge, fire and GS pump fire main discharge B14V BF121
From Engine Room
The fire line pressurising pump will now maintain the fire main pressure at a open valve Steering Gear BF115 (See Illustration 5.4.1a
BF
constant pressure of 500kPa. As the fire pump is normally left with its suction and 113
Machinery Operating Manual)
Locked No.2 bilge, fire and GS pump sea suction valve B104V Rope Store
and discharge valves locked open, the pressure in the fire main developed by
open BF111
the fire line pressurising pump will be retained because the fire pump has been
fitted with a non-return valve on its discharge side. Interlocked No.2 bilge, fire and GS pump bilge suction valve B105V
BF112 BF80
closed
Note: Valves which are normally open or closed on any pump must be Closed No.2 bilge, fire and GS pump ballast eductor/water B107V BF123
maintained in a good working condition. These valves must be lubricated spray rinsing line discharge valve
and should be tested at weekly intervals to ensure that they operate correctly. Interlocked No.2 bilge, fire and GS pump fire main discharge B109V BF116 BF90
After testing, the valve must be returned to its normal open or closed position open valve BF93
and a check made to ensure that the valve is correctly set. Locked Crossover line valve onto the water spray system B111V
closed
Emergency Generator BF81 BF77 BF71 BF64 BF63 BF59 BF47 BF43 BF41 BF37 BF33 BF29 BF27 BF21 BF17 BF03
Room To BF02
Engine Casing Accommodation
To Foam No.5 Trunk No.4 Trunk No.3 Trunk No.2 Trunk No.1 Trunk
BF122 A
System
BF123 BF06
BF13
BF90 BF72 BF56 BF38 BF24
BF69 BF60 BF44 Side Passageway BF30 BF22 BF14
BF116 BF134
BF93 BF78 BF74 BF65 BF34 BF18
BF50 BF49
BF48
To Bilge Eductor Driving Line
in Side Line Boarding Spaces Cargo Manifold
Side Elevation
BF51 Water Curtain
Eductor Driving Line
To Deck for Bosun’s Store
BF02
Fire Main BF07
BF03
System
A Detail B Detail BF13
Bosun’s Store
PI Eductor Driving Line
Emergency Fire Pump BF06
BF05 for Chain Locker
BF110 BF109 (72m3/h x 1.1Mpa)
Position Description Valve Valve Situation Illustration 5.4.1d Emergency Fire Pump Arrangement
Locked Line drain valve B133V BF115 Casing upper deck port side
closed BF132 ‘B’ deck casing level port side
Closed Sewage collecting tank cleaning valves P36V
P9V A drain valve, B133V, has been fitted to the lowest point along the fire main
in the engine room to allow the water to be drained and the pipework left dry B Detail
Closed Soot collecting tank eductor sea water drive supply M20V Bosun’s Store
valve in cold weather to prevent any possible damage by the water freezing in the
lines. Emergency Fire Pump
(72m3/h x 1.1Mpa)
Note: To avoid overheating of the fire pump and the bilge, fire and GS
pump’s impeller and casing, at least one outlet valve on the fire main should Note: After use, the hose and nozzle unit at each fire hydrant must be BF118
correctly stowed in the hose box ready for future use. Any defects found in BF119
be open when a pump is in operation.
the hose, nozzle, valve or system must be reported immediately and rectified BF120
The fire pump and the two bilge, fire and general service pumps have their as soon as possible. Hose boxes must never be left with components which BF10
electrical supply from the main switchboard and can be started from the are defective. BF11
BF12 High Expansion
following positions: Foam Sea Water Pump
(650m3/h x 1.5MPa)
• Locally Emergency Fire Pump Sea
Chest
Sea
Chest
• Fire control station/foam room
The emergency fire pump is located in the forward HFO transfer pump room
• Main switchboard group starter panels and has a dedicated sea suction chest. The emergency fire pump electrical
• Wheelhouse supply is from the emergency switchboard and can be started from the
following positions:
• ECR and CCR via the DACS workstations Side Elevation
• Locally
Eductor Driving Line
Although the pumps can be started locally, it is normal practice to select • Fire control station for Bosun’s Store
To Deck BF02
REMOTE on the respective starter box and the electric motor heater in the ON Fire Main BF07
BF03
• Emergency switchboard group starter panel in the DACS I/O
position, so that the desired pump is readily available for starting remotely. System
cabinet room on A deck BF13
• Wheelhouse
Engine Room Fire Hydrant Locations Eductor Driving Line
BF06
• ECR and CCR via the DACS workstations BF05 for Chain Locker
Valve Situation
Bosun’s Store
BF83 Floor port side (forward) Forward BF04
To operate the pump, proceed as follows: Heavy Fuel Bilge
BF124 Floor port side (aft ) Oil Tank Well Fore Peak
BF82 Floor starboard side (forward) (Port and Tank
a) Check that the emergency fire pump suction strainer is clear Starboard)
BF125 Floor starboard side (aft) and confirm that the pump’s suction valve BF118 and discharge
Forward Water
BF85 4th deck port side (middle) valve BF119 are open. Ballast Tank
B
BF127 4th deck port side (diesel generator room) (Port and
b) Close the emergency fire pump drain valve BF120 and line Starboard)
BF84 4th deck starboard side (middle) BF08
drain valve BF12.
BF126 4th deck starboard side (diesel generator room) BF09
WS-30
WS-17
Accommodation
Area
Lifeboat
No.5 Cargo Tank No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
Satcom
Dome
Engine
Room WBV346
Nav Deck
To Ballast D Deck
Eductors
C Deck
111V (See Illustration
133V 6.3.5a) B Deck
PI Upper Deck
Water Spray
Pump
(900m3/h x
CI
900kPa)
From Water
From Bilge, Fire Spray Pump
and General WBV348 in Engine Room
Service Pumps
(See Illustration Key
5.4.1a) Fire Water
Gas
Sea Water
Crossover Main Sea Water
Illustration 5.4.2b Fire Main System in the Engine Room Upper Deck (See Illustration 5.4.1b)
To Water Spray
Main
BF110
Bilges 4th Deck (Starboard Diesel Generator Room) 4th Deck (Port Diesel Generator Room)
BF126 BF127
Electrical Signal
4th Deck (Starboard Middle) 4th Deck (Port Middle)
BF84 BF85
Floor (Starboard Aft) Floor (Port Aft)
BF124 BF125
Floor (Starboard Forward) Floor (Port Forward) From Starboard Stern
From BF82 BF83 Tube Cooling Water Tank
Port Stern Tube From Port Aft (2.4.2a Machinery Operating Manual)
To Exhaust Gas
Cooling Water Bilge System Economiser Washing
PIAHL From
Tank (2.4.2a Machinery Operating Manual) (2.9.1a Machinery Operating Manual) PX
Drain Tank Discharge
MM029 Starboard Aft
14V
Eductor Bilge System
PI
To Overboard (2.9.1a Machinery Operating Manual)
Sea Chest (Port) Bilge Main
110V
LMS 111V
129V
P36V To Ballast
109V 107V
To 15V Stripping
LMS
Sewage Self-Priming Type 13V WBV Eductors
Collecting 14V 347
PI Self-Priming PI No.2 Bilge, Fire
Tank Type
Inter-
and General
Lock From Starboard
Cleaning Fire Pump Service Pump
PI
P9V PI 18V Fresh Water Tank Water Spray
(150m3/h x (225/150m3/h x No.1 Bilge, Fire and
CI CI (2.14.1a Machinery Pump (900m3/h x
1.1MPa) 305kPa/1.1MPa) General Service Pump
Operating Manual) 900kPa)
(225/150m3/h x CI
305kPa/1.1MPa) CI
128V
141V 139V
Air Air
LMS
Inter-Lock WBV 12V
104V LMS
18V 11V 348 High Sea
High Sea 105V
Chest (Port) Chest
WBV WBV Fire Bilge Pump Air S106V WBV WBV (Starboard)
Start/Start Fire Line
374 376 Forward Pressurising Pump 373 373
Low Sea LMS To Bilge LCHL
LS 120V 126V LMS Low Sea
Chest PP138 Bilge Well 16V (2.0m3/h x 500kPa) Chest
Well To Bilge Separator
(Port) LAH (Port) LMS
(Starboard)
WBV BG105
LS
Air Forward
PI CI Service and Bilge Pump WBV
LS LAH 372
375 From Cofferdam Bilge Well LS
BG104
132V Around Pipe Duct LCHL (Starboard) 125V
PP137
a) Start the No.1 bilge, fire and GS pump and when it is operational
and has stabilised, start the No.2 bilge, fire and GS pump.
WARNING
Care must be taken when using the bilge, fire and GS pumps to ensure
that the suction valves to the bilge main and forward bilge wells are
closed, as the supply of oily bilge water to the water spray system could
result in oil being added to a burning fire.
After use, flush through the system with fresh water taken from the starboard
fresh water tank via the connection to No.1 bilge, fire and GS pump. To do this,
turn the spectacle flange in the line between the starboard fresh water tank and
the pump and open one of the bilge, fire and GS pump suction and discharge
valves. With the pump’s other valves confirmed closed, the starboard fresh
water tank suction valves, 46V and 16V, should be opened. The pump can then
be started and the system flushed through, one section at a time.
SUS316 R R R R R R R
PI PI
R
Key
Main Regulator
Nitrogen
CO2
SUS316 R R R R R R R R
No.2 No.1
Connection Connection
PI PI PI
Valve Valve
PI PI
R
Main Regulator
When the main nitrogen cylinders have been opened by any of the pilot bottles,
the gas from the 68 litre cylinders is injected into the lower part of the tank to
fluidise the powder and to pressurise the whole of the tank.
SUS316 R R R R R R R
PI PI
R
Key
Main Regulator
Nitrogen
CO2
SUS316 R R R R R R R R
No.2 No.1
Connection Connection
PI PI PI
Valve Valve
PI PI
R
Main Regulator
If the remote pilot cylinders have failed to activate the nitrogen bottles in g) Recharge/replace the pilot operating cylinder(s) that were used
the storage compartments, they can all be opened manually. To achieve this, in the discharge.
proceed as follows:
b) The pressure in the tank will build up and open the main valve.
The dry powder discharge then begins.
After any operation of the dry powder system it is essential the system is
cleaned at once with N2. This is to prevent any residue powder remaining in the
lines thereby causing a blockage to subsequent usage. There is usually enough
N2 remaining in the bottle bank to do this.
a) Set the No.3 control valve to the CLOSE position. This will
close the main dry powder discharge valve.
b) Set the No.1 control valve to the N2 STOP position. This will
stop the nitrogen cylinders pressurising the dry powder tank.
e) When the operation has been completed and the nitrogen bottles
exhausted, return all of the valves to their normal operating
positions.
Illustration 5.4.4a Typical FM200 Fire Extinguishing System and Instruction Plate
PS
FM200
CONTROL
PANEL
L
E
F
350LB X 1 BTL
THE SYSTEM MAY BE OPERATED BY REMOTE, LOCAL MANUAL AND EMERGENCY. B. EMERGENCY OPERATION
FOR REMOTE MANUAL OPERATION, DISCHARGE BUTTONS ARE LOCATED IN THE FIRE CONTROL
STATION AND NEAR THE ENTRANCE DOORS TO THE SPACE. 1) ENSURE NO PERSONNEL IN THE SPACE AND CLOSE THE DOOR, OPENINGS AND STOP
THE VENT FANS.
FOLLOW THE INSTRUCTION WHEN THE FIRE IS NOTED IN THE SPACE
2) GO TO THE MASTER CYLINDER WITH LEVER OPERATED CONTROL HEAD IN FM200
A. REMOTE AND LOCAL MANUAL OPERATION CYLINDER PACKAGE UNIT.
1) GO TO THE DISCHARGE PUSHBUTTON LOCATED NEAR TO THE OUTSIDE OF ENTRANCE 3) TAKE OUT THE SAFTY PIN ON LEVER OPERATED CONTROL HEAD AND HOOK UP
DOOR OR CONTROL PANEL OF FIRE CONTROL STATION THE LEVER.
2) ENSURE NO PERSONNEL IN THE SPACE TO BE FLOODED AND CLOSE THE DOOR, 4) THE FM200 DISCHARGE SIGNAL IS TRANSMITTED FROM THE PRESSURE SWITCH TO
OPENINGS AND STOP THE VENT FANS. F&G AND THE OPERATION IS COMPLETED.
5) THE FM200 DISCHARGE SIGNAL IS TRANSMITTED FROM PRESSURE SWITCH TO FIRE & GAS 2) BEFORE PERMITTING ANYONE TO ENTER THE SPACE, VENTILATE THOROUGHLY, OR
SYSTEM AND THE OPERATION IS COMPLETED. USE SELF-CONTAINED BREATHING APPRATUS.
IF NOT OPERATED WITHIN A MINUTE, FOLLOW THE EMERGENCY OPERATION. 3) RESET THE SYSTEM TO RESERVE UNIT FOR SERVICE.
FM200 Control Panel (Fire Control Station) 4) RE-FILL FM200 GAS FOR USED CYLINDER AND RESET THE SYSTEM TO MAIN UNIT.
H H Starboard Loop
DS1
Electric Horn
PS PS
Flashing Light
NOVEC F
1230
Relay
Box Vent Stop
24V DC 220V AC
Maintained (Main)
Supply Local Release Cabinet PS
220V AC
(Emergency)
PI PS PS PI PS PI PS
PI PI
H H
DS1
No.1 No.2 No.8 No.9
PS PS
Electric Cylinder
Motor JB JB JB JB
Room Monitoring (N.C)
Fault 9 Cylinders
Entrance
Monitoring
Facility NOVEC Released (N.C)
24V DC
Maintained Fire Cargo Compressor Room
Remote Release Cabinet
Supply Control
Station Port Loop
PI
H H Starboard Loop
DS1
Electric Horn
PS PS
Flashing Light
NOVEC F
1230
JB
Relay
Box Vent Stop
220V AC
(Main)
Local Release Cabinet PS
220V AC
(Emergency)
PI PS PS PS PI PS PI
PI PI
H H
DS1
No.1 No.10 No.11
PS PS
No.2 Key
NOVEC 1230
Compressor Cylinder
JB Room JB JB JB JB Pilot Line
Entrance Monitoring (N.C)
Fault 11 Cylinders Electrical Signal
Monitoring
NOVEC Released (N.C)
Facility DS Door Switch
JB Junction Box
d) Pull down on the lever to release the FM200 gas. a) Ensure that all personnel have evacuated the space and that all
doors are closed, ventilation fans are stopped and their dampers
e) The gas will be discharged and the discharge pressure activates closed, and any other means of feeding the fire with fuel or air
the pressure switch to the audible alarm system. are stopped.
a) Ensure that the fire is completely extinguished before ventilating c) Obtain the release control cabinet key from its storage location
the space. in a breakable glass container next to the cabinets.
b) Before permitting anyone to enter the space, ventilate thoroughly d) Open the release cabinet door. This will set off an audible alarm
or use self-contained breathing apparatus. and stop the ventilation fans if they have not been previously
shut down.
c) Reset the system to reserve the unit for service.
e) Open the cylinder outlet valve on one of the two pilot cylinders.
d) Replace the used cylinders and reset the system. Ensure a pressure is indicated on the pressure gauge. If no
pressure is indicated, open the other cylinder.
f) Open one pilot line valve within the cabinet to activate the
NOVEC 1230 cylinder release mechanisms. If the cylinders fail
to operate, open the second line valve.
CS3000
POWER ON
FIRE SEC 2 DET 13
FIRE
DISCONNECTION
1 (1)
ECR TEST......
ALARM TRANSFER
ZONE DETECTOR EXTERNAL ALARM
MENU DELAY OFF.....
SYSTEM FAULT..
F1 F2 F3 F4 ABNORMAL COND.
ALARM MUTE
ALARMS IN QUEUE 7 8 9 S SECTION EA
EXTERNAL FAULT
ALARM
4 5 6 D DETECTOR EC EXTERNAL
CONTROL
M MUTE
SECTION / DETECTOR
NOT RESET 0 ON OFF TIMER LIST
Auto Release
1 2
FIRE DOORS
Consilium Consilium Consilium Consilium Consilium Consilium Consilium Consilium Consilium Consilium
1 1 2 1 2 1 2 1 2 1 2 1 2 1 2
2 3 4 3 4 3 4 3 4 3 4 3 4
3 5 6 5 6 5 6 5 6 5 6 5 6
4 7 8 7 8 7 8 7 8 7 8 7 8
5 9 10
6
Salwico LPK-1 Salwico LPK-2 Salwico KPK-2 Salwico UTK-2 Salwico SPK-2 Salwico SPK-2 Salwico SPK-2 Salwico SPK-2 Salwico SPK-2 Salwico SPK-2
Main Power
Emergency Power
Battery Charge
Fault
Battery Fault
Power Fault
Earth Fault
Output2 Battery Power
4A 4A 20A 20A 2 x 4A
F1 F2 F3 F4 F5 F6
SW1
Fire Alarm Panel Mute: This is a fault handling key used to acknowledge
Introduction faults and to mute the buzzers.
When a fire alarm is detected on the system the FIRE indicator on this panel
The CS3000 fire alarm and detection system is a computerised fully addressable flashes and the zone number and the detector in alarm are displayed on the Reset: Fault handling key used to reset the faults.
fire alarm system with analogue detectors. The operating panel, control unit numeric display. The keys and the operation of them are as follows:
and power supply are contained in a central cabinet located in the wheelhouse.
On, Off, Timer: These are operation keys used to choose the operation
Three repeater panels have been fitted and these are located in the fire control
Alarm Mute: This key is used to acknowledge the fire alarm to perform.
station, ECR and on the cargo control room console. The repeater panels allow
the ship’s staff to monitor alarms and scroll through the alarms in the queue and to mute the buzzer.
list, but not to perform any disconnections or reconnections. List: This is used to open the list function and the up and
Alarm Reset: This key is used to reset the fire alarm. down arrow keys are used to scroll through them.
There are nine loops connected in the system with a battery back-up provided
in the event of a power failure. The fire detection system has a direct input into Alarms in Queue: The LEDs indicate the existence of multiple Power On: This is illuminated when the power source is on.
the DACS for recording any alarms, faults and disconnections, and the outputs alarms which can be scrolled through using this
of the system are used to stop ventilation fans and close fire doors in the event key. Each alarm is listed in the alphanumeric Disconnection: General disconnection of detectors indicator.
of a fire. display.
Test: This is illuminated when the central unit is in test
The nine detection loops in the system are as follows: External Control Activated: This LED indicates that an external control mode.
1. Wheelhouse, accommodation - D deck and C deck levels output is active.
2. Accommodation - B deck and A deck levels Alarm Transfer: This is illuminated when the dedicated fire output is
Section/Detector Not Reset: This LED indicates that an alarm reset has activated (steady light) and is flashing when the door
3. Accommodation - upper deck, been attempted but failed and the detector is is open, the fire output is deactivated.
4. Engine room casing - upper deck, A deck, B deck and C deck still in alarm.
(starboard) levels External Alarm: This is illuminated when an external alarm output has
been disconnected or is faulty.
5. Engine room - steering gear room on 3rd deck level Operating Panel
6. Engine room - 2nd deck level, 3rd deck level (mid and
The operating panel is used for controlling the system and to display extra Delay Off: This is illuminated when the time delay is
starboard)
information in the case of a fire alarm. The alphanumeric display is used as a deactivated.
7. Engine room - 4th deck level and floor level complement to the numeric display on the fire alarm panel, as a communication
8. Cargo motor room, cargo machinery room, forward pump room, medium when operating the system, and to display guiding texts for the System Fault: This is illuminated when a fault has occurred in the
bosuns’ store function keys. Under normal conditions, when the central unit is in normal system.
status, the text ‘CS3000’ is displayed together with the date and time. The keys
9. Emergency generator room and the operation of them on this panel are as follows:
Abnormal Condition: This is illuminated when an abnormal condition has
The detection system consists of a wide range of detectors and sensors to suit occurred on the system.
different needs and conditions, as listed above.
CS3000
POWER ON
FIRE ZONE 2 DET 13
FIRE
DISCONNECTION
1 (1)
TEST......
ALARM TRANSFER
ZONE DETECTOR EXTERNAL ALARM
MENU DELAY OFF.....
SYSTEM FAULT..
F1 F2 F3 F4 ABNORMAL COND.
ALARM MUTE
ALARMS IN QUEUE 7 8 9 Z ZONE EA
EXTERNAL FAULT
ALARM
4 5 6 D DETECTOR EC EXTERNAL
CONTROL
M MUTE
SECTION / DETECTOR
NOT RESET 0 ON OFF TIMER LIST
Disconnections
Different parts of the fire alarm system such as detectors, manual call points,
section units, alarm devices, external control devices and loops can be
disconnected from the system if required. This can be useful when there are
activities such as welding in a particular section or the removal of detectors
is required for maintenance work, etc. A whole section can be disconnected
permanently or for a defined time interval using the timer function. If this
is undertaken, the disconnected section can only be reconnected from the
‘Disconnections’ list.
When operating the system, a mistake can be corrected using the BACK key to
erase one step at a time backwards. To interrupt the disconnection function and
return to the normal status, press the RETURN key. The system will then return
to its normal status and the words CS3000 indicated on the screen.
Disconnection Process
d) When the section has been disconnected the text on line three
will be changed to ORDER DONE.
Further in-depth operations of the fire detector panel are available from the
manufacturer’s manual.
Position Description Valve The auxiliary cooling water system booster pumps are normally selected
as a duty/standby pair, one pump normally being able to meet all cooling
Open No.2 nitrogen booster compressor jacket cooler RX806
requirements in this system. The individual pumps are selected from the DACS
outlet valve
in the same manner as for reliquefaction cooling water pumps. From the DACS
Open No.1 nitrogen booster compressor after-cooler RX831 select one pump, then START and place the pump in AUTO, now go to the
inlet valve second pump and place in AUTO. The Duty and Standby pumps have now
Open No.1 nitrogen booster compressor after-cooler RX802 been selected.
outlet valve
Open No.2 nitrogen booster compressor after-cooler RX810 The system is set up using the following valves:
inlet valve
Open No.2 nitrogen booster compressor after-cooler RX812 Position Description Valve
outlet valve Open No.1 auxiliary central cooling FW booster pump W251V
inlet valve
d) Set the reliquefaction cooling water pumps to duty/standby. Open No.1 auxiliary central cooling FW booster pump W252V
From the DACS select one pump, then START and place in outlet valve
AUTO, now go to the second pump and place in AUTO. The
Open No.2 auxiliary central cooling FW booster pump W253V
Duty and Standby pumps have now been selected.
inlet valve
e) Check that the fresh water cooler three-way temperature control Open No.2 auxiliary central cooling FW booster pump W254V
valve is set at 36°C and that the valve is operating correctly. outlet valve
Open No.1 HD compressor motor inlet valve FC19
f) Check that sea water cooling is being supplied to the fresh Open No.1 HD compressor motor outlet valve FC20
water coolers in accordance with Section 2.4.1 of the Machinery Open No.2 HD compressor motor inlet valve FC23
Operating Manual. Open No.2 HD compressor motor outlet valve FC24
Open No.1 HD compressor LO cooler inlet valve FC21
g) Check the water level in the expansion tank and replenish if
required. Vent individual coolers as necessary. Open No.1 HD compressor LO cooler outlet valve FC22
Open No.2 HD compressor LO cooler inlet valve FC25
h) Check the level of chemical treatment and dose as required. Open No.2 HD compressor LO cooler outlet valve FC26
Open Cargo heater drain cooler inlet valve FC31
i) Circulate the reliquefaction plant and cargo machinery cooling Open Cargo heater drain cooler outlet valve FC32
water system and check all users are being supplied with cooling
water at the required temperature and pressure.
Two high duty (HD) compressors are installed in the cargo machinery room
and are used for compressing the LNG vapour for return to the shore terminal
during cargo loading, tank purging and tank warming-up. The two auxiliary
central cooling fresh water booster pumps draw their supply from the starboard
LT cooling water system and supply the cooling water for the compressors and
the cargo heater drain cooler.
No.5 Cofferdam
No.1 Cofferdam
BG02
From
Forward
Fire Main
No.5 Trunk No.1 Trunk Water Ballast Fore Peak Tank 50
Tank
50
65 50
BG01
LAH LAH No.3 BG09
LAH
BG26
LAH
50
40 No.2
LS LS From Fire Main
LS
LS BG05
Bilge
Shore BG20 50 40 BG08 BF06
50 BG04
Connection BF78
Chain
50 No.6 50 65 40 Locker
Fresh 50 65
Water Tank BG06
From 65
LS (Starboard) LAH LAH
65 Fire Main
BG24 BG22
Bosun’s BG07 From
Sewage
Store Fire Main
LAH Shore From No.4 LS LS
Connection Fire Main BF74
BG18
50
LS
Pilot Boarding Space
From Fire Main Fire Main From Fire Main
Compressed LAH
Air System From
Detail of Cargo Machinery Room BF75 BF74 Chain 40 BF05 Fire Main
50 BF06 Locker No.1
Compressor Room Motor Room BG10 65 BG03
No.2
50
25 50 BG27
CA88 BG08 Bosun’s
BG01
Bilge BG09 Store
65 BG02
Tank
A No.5 No.4 BG06 BG07
65
25
BG19 BG18 Forward
Heavy Fuel
25 BG17 25 25 BG28 No.3
50 50 Oil Tank
(Port and
BG16 BG27
BG14 BG13 BG12 Starboard)
From
Fire Main
BF08 BG29 Forward Water
Typical Section Ballast Tank
LAH (Centre)
40 40 Fire Main Fire Main BG05 50
Forward
Fore Peak Tank
Heavy Fuel Oil
50
40 BG15 40 BG11 LS Pump Room
25
No.7 No.6
65 65
BG04 50 50 BG26
LS LS
To Engine Upper Deck Upper Deck
Room Bilge
Void
Primary Tank Side Passageway LAH LAH
The forward bilge systems operate to pump bilge water out of the spaces which a) Set the designated bilge, fire and GS pump to supply sea water Position Description Valve
are external to the engine room. These spaces include: to the fire and wash deck line, from which the required eductor Open No.3 eductor driving water inlet valve BF-08
• The chain lockers is supplied. One pump is normally left set-up for this purpose.
Open No.3 eductor discharge valve BG-06
• The focsle store areas b) When an adequate vacuum has been established the relevant Open Overboard discharge valve BG-07
• The forward HFO pump room bilge suction valve can be opened. Open Void space forward bilge suction valve BG-26
Open Void space aft bilge suction valve BG-04
• The forward void space c) When the selected bilge is empty, close the suction valve, stop Open Forward HFO pump room bilge well suction BG-05
• The pilot boarding spaces the bilge, fire and GS pump and close the eductor valves. valve
• The aft passageways Closed No.2 eductor discharge valve BG-08
d) If any flanges have had their blank flanges removed then these
• The cargo machinery spaces are to be refitted.
Note: When discharging bilge water from the forward HFO pump room great
Any water leakage into the various spaces, except the cargo machinery spaces, care must be taken to ensure that no oil is present in the water.
Chain Locker Bilge Wells Using No.1 Eductor
is removed using bilge eductors. The eductors have their driving water supplied
from the fire and wash deck main as shown in illustration 5.6a. Unlike the The chain locker bilges are discharged overboard using the eductor and the Starboard Pilot Boarding Space Bilge Using No.4 Eductor
engine room bilge system, there is no oil content monitor fitted to the overboard valves in the table below:
discharges of these systems, so care must be taken when emptying any of the The starboard pilot boarding space bilge well is discharged using the eductor
bilge wells that no oil contamination exists. The monitoring of the bilge wells and valve in the table below. The driving water is supplied via a flexible pipe
Position Description Valve
is achieved by the use of float switches linked to the DACS. and the discharge line is normally fitted with a blank flange which will require
Open No.1 eductor driving water inlet valve BF-05 removal before any bilge water is discharged.
There are seven 5m³/h bilge eductors covering the forward bilge sections. The Open No.1 eductor discharge valve BG-03
list below shows the various eductor locations and from where they derive their Open Port chain locker bilge well suction valve BG-02 Position Description Valve
bilge suction. Open Starboard chain locker bilge well suction BG-01 Open No.4 eductor driving water inlet valve BF-74
valve Operational Starboard pilot boarding space bilge suction BG-18
• No.1 eductor located in the bosun’s store - chain lockers.
non-return valve
• No.2 eductor located in the bosun’s store - bosun’s store bilge
Bosun’s Store Bilge Wells Using No.2 Eductor
wells.
The bosun’s store bilges are discharged overboard using the eductor and valves Port Pilot Boarding Space Bilge Using No.5 Eductor
• No.3 eductor located in the forward HFO pump room - void
in the table below. Valve BG-06 on the discharge line from the forward HFO The port pilot boarding space bilge well is discharged using the eductor and
space and forward HFO pump room.
pump room should be kept closed. valve in the table below. The driving water is supplied via a flexible pipe and
• No.4 eductor located in the starboard pilot boarding space
the discharge line is normally fitted with a blank flange which will require
bilge. Position Description Valve removal before any bilge water is discharged.
• No.5 eductor located in the port pilot boarding space bilge. Open No.2 eductor driving water inlet valve BF-06
Open No.2 eductor discharge valve BG-08
No.5 Cofferdam
No.1 Cofferdam
BG02
From
Forward
Fire Main
No.5 Trunk No.1 Trunk Water Ballast Fore Peak Tank 50
Tank
50
65 50
BG01
LAH LAH No.3 BG09
LAH
BG26
LAH
50
40 No.2
LS LS From Fire Main
LS
LS BG05
Bilge
Shore BG20 50 40 BG08 BF06
50 BG04
Connection BF78
Chain
50 No.6 50 65 40 Locker
Fresh 50 65
Water Tank BG06
From 65
LS (Starboard) LAH LAH
65 Fire Main
BG24 BG22
Bosun’s BG07 From
Sewage
Store Fire Main
LAH Shore From No.4 LS LS
Connection Fire Main BF74
BG18
50
LS
Pilot Boarding Space
From Fire Main Fire Main From Fire Main
Compressed LAH
Air System From
Detail of Cargo Machinery Room BF75 BF74 Chain 40 BF05 Fire Main
50 BF06 Locker No.1
Compressor Room Motor Room BG10 65 BG03
No.2
50
25 50 BG27
CA88 BG08 Bosun’s
BG01
Bilge BG09 Store
65 BG02
Tank
A No.5 No.4 BG06 BG07
65
25
BG19 BG18 Forward
Heavy Fuel
25 BG17 25 25 BG28 No.3
50 50 Oil Tank
(Port and
BG16 BG27
BG14 BG13 BG12 Starboard)
From
Fire Main
BF08 BG29 Forward Water
Typical Section Ballast Tank
LAH (Centre)
40 40 Fire Main Fire Main BG05 50
Forward
Fore Peak Tank
Heavy Fuel Oil
50
40 BG15 40 BG11 LS Pump Room
25
No.7 No.6
65 65
BG04 50 50 BG26
LS LS
To Engine Upper Deck Upper Deck
Room Bilge
Void
Primary Tank Side Passageway LAH LAH
Position Description Valve Cargo Machinery Room Bilges Position Description Valve
Open No.4 eductor driving water inlet valve BF-75 Normally No.1 bilge primary tank inlet valve in engine B235V
The cargo machinery room has two separate bilge systems, the motor room
Operational Port pilot boarding space bilge suction non- BG-19 open room
bilge system and the compressor room bilge system. Each room has a port and
return valve starboard bilge well and these are equipped with high level float switches which Open Compressor room port bilge well suction BG-17
are linked to the DACS. The bilge wells in both rooms are pumped out using a valve
dedicated air operated pump. The pump discharges to a small bilge tank in the Open Motor room port bilge well suction valve BG-28
Starboard Aft Passageway Bilges Using No.6 Eductor
CMR. The small bilge tank is also drained to the engine room bilge primary Set Valve to drain to BG-12 BG-13
The starboard aft passageway bilge well is discharged using the eductor and tank, or to the upper deck, depending on the condition of the bilge water. Open CMR Bilge tank outlet valves to No.1 tank BG-12, BG
valve in the table below. The discharge line is normally fitted with a blank
Closed Bilge tank outlet valves BG-14
flange which will require removal before any bilge water is discharged. The bilge wells can also be drained directly to the upper deck by opening
valves BG-11 and BG-15 for the motor and compressor rooms respectively, Open Air operated pump compressed air supply CA88
depending on the condition of the bilge water. valve
Position Description Valve
Open No.6 eductor driving water inlet valve BF-78 c) When the selected bilge is empty, stop the air operated pump
Operational Starboard aft passageway bilge suction non- BG-20 Compressor Room Bilge System by closing valve CA88. Close the bilge suction valves and the
return valve pump discharge valve BG29.
Description Valve
Starboard bilge well suction valve BG-16
Port Aft Passageway Bilges Using No.7 Eductor Note: The bilge wells are pumped to the bilge tank in the cargo machinery
Port bilge well suction valve BG-17
room and then drained by gravity from the bilge tank to the engine room
The port aft passageway bilge well is discharged using the eductor and valve in Bilge tank drain valve BG-12 drain tank.
the table below. The discharge line is normally fitted with a blank flange which
Starboard and port bilge well drain valve BG-15
will require removal before any bilge water is discharged.
To empty the bilge wells to the engine room No.1 bilge primary tank, proceed
as follows:
From Nitrogen
PX PI NG FX
Buffer Tank in FX PX PI PI PX PX
Engine Room NG99 109
NG
NG58 43
NG64
NG98 NG34 NG27 NG17 NG10
NG NG71
CR 76 CR To Aft CR CR CR
NG To Aft IS 501 NG 401 NG IS Bilge 301 NG To Aft IS 201 NG To Aft IS 101
Bilge Well To Aft IS
91 69 51 Well 32 Bilge Well 15 Bilge Well
NG83 To Fixed Bilge Well NG57 To Fixed NG38 To Fixed NG21 To Fixed NG04 To Fixed
NG Gas NG Gas NG Gas NG Gas NG Gas
NG NG NG NG
90 Detection 68 Detection 50 Detection 31 Detection 14 Detection
88 NG NG NG 48 NG 29 NG 12 NG
NG NG System NG NG System NG NG System NG NG System NG NG System
86 66 60 41 24 07
92 89 NG 70 67 52 49 33 30 16 13
PI PI PI PI
NG NG 79 PI
NG NG NG NG NG NG NG NG
85 82 59 56 40 37 23 20 06 03
CR CR CR CR NG CR
NG NG NG46 NG NG NG NG
504 404 NG 304 204 26 104
84 NG 58 NG 39 22 09 05
63
NG81 78 NG55 45 NG36 NG19 NG02
NG NG
NG
NG80 NG54 NG NG35 25 NG18 08 NG01
62
No.5 To No.5 No.4 To No.4 Gas No.3 44 To No.3 Gas No.2 To No.2 Gas No.1 To No.1 Gas
Gas Gas Gas Gas Gas
Liquid Gas Dome Liquid Dome Gauge Liquid Dome Gauge Liquid Dome Gauge Liquid Dome Gauge
IBS
IBS
IBS
IBS
IBS
IBS
IBS
IBS
IBS
IBS
IS
IS
IS
IS
IS
IS
IS
IS
IS
IS
Dome Dome Dome Dome Dome
Dome Gauge Board Dome Board Dome Board Dome Board Dome Board
PI PX PI PI
PX PI FX PX PI NG
NG99 109
To Gas
Combustion NG98 NG97 NG96
Unit NG100
NG103 NG102
PAL DPIC
PS
MMO79 NG76
PI
NG98 Gas
No.5 VP NG78
IBS
Dome
IS
Liquid
IBS
IS
40V Pressure Gauge and Twin
NG89 NG90 NG91 Dome
Chambers Water Guard System Detail
Set at
PI
0.55MPa
37V 38V NG92
A
34V 36V Valve Closed
During IBS
Set Set PI and IS
0.5MPa PCV-8-70 0.5MPa PCV-8-68 Vacuum
NC505
Process
NC514 NG77 Water
33V 35V NC515 NC512 To Fixed Gas
NC517
Detection System
NC518 NC507
NC501 From
Set at To Fixed Gas Engine Room
1.3MPa Detection
V-8-64 System NC504 NC502 Twin Chambers Water Guard System is Used
PSV-8-61 NC516
to Protect Insulated Spaces During Filling
To Spray Line With Nitrogen Operation
NC503
6.1 Insulation space pressurising The nitrogen production plant is maintained in an automatic mode, but during Position Description Valve
normal operations, one generator (capacity 145m3/h) is able to maintain
Closed IS exhaust sample/purge valve NG81
6.1.1 Insulation Space Inerting the pressure in the buffer tank owing to the small demands placed upon the
system. When a high nitrogen demand is detected, the second generator will Closed IBS exhaust control valve NC502
On completion of a dry dock period the insulation and interbarrier spaces may start automatically. (See Section 4.8 of this manual for details of the nitrogen Closed IBS exhaust control isolation valves NC501, NC503
require inerting and this can be carried out either by using the on board nitrogen production plant.) Closed IBS exhaust control bypass valve NC504
generator or having the nitrogen vapour supplied from ashore. Normally the Closed IBS fixed gas detection take-off valve NC507
ship’s nitrogen generators are sufficient for providing the nitrogen.
Operating Procedure for Vacuum Process Closed IBS exhaust sample/purge valve NC505
Prior to any inerting of these spaces, either with the nitrogen being supplied (See illustration 6.1.1c)
c) Remove the safety relief valves CR503 and CR504 on No.5
from ashore or on board, great care has to be taken to ensure that all sampling
and control systems are fully operational and personnel are fully conversant Because the insulated spaces must be at the same pressure during evacuation, a liquid dome and replace with the twin water guard system
with the operation. temporary bypass is installed between the IBS and IS exhaust lines at the relief units.
valve flanges on the gas dome, the relief valve having been removed. Similarly,
If possible, the cargo tanks should be maintained at a pressure of at least 3kPa a pressure gauge and twin water guard system is installed at the relief valve d) Remove the safety relief valves CR501 and CR502 on No.5
above atmospheric during the inerting and drying of the insulation spaces to flanges on the liquid dome. During the vacuum process the inlet valve to this vapour dome and connect to the vacuum pump.
reduce the risk of over-pressurising the spaces. unit must be closed.
e) Close the inlet valve on each of the twin water guard units.
In the extreme case where the oxygen content in the insulation spaces was Assuming the No.5 cargo tank insulation space is to be evacuated and refilled,
above 10%, then the vacuum pumps would be required to pull a vacuum of proceed as follows: f) Start the vacuum pump and carefully bring the insulation spaces
20kPa absolute in both the IBS and IS spaces simultaneously and back-fill
down to a 20kPa absolute vacuum, monitoring the progress
with nitrogen. a) Set the nitrogen supply valves to the interbarrier and insulation locally on the twin water guard system pressure gauges and the
spaces as follows: local pressure gauge board.
The vacuum pump is supplied from shore as the vessel does not normally carry
these.
Position Description Valve g) When the insulation spaces reaches a 20kPa absolute vacuum,
Before cooling down the cargo tanks, the nitrogen in the insulation spaces Closed IS supply sample/purge valve NG98 stop the vacuum pump and slowly open the nitrogen supply to
should contain less than 3% oxygen and be dryer than -20°C dew point. The Closed IS supply bypass valve NG92 the spaces via the bypass valves NC519 and NG92 and fill to a
nitrogen provides a dry and inert medium for the following purposes: Closed IS supply control valve NG90 pressure of 95kPa absolute, open the inlet valve to the twin water
guard system to prevent over-pressurisation of the spaces.
• To prevent the formation of a flammable mixture in the event of Closed IS supply control isolating valves NG89, NG91
an LNG leak Closed IS portable gas sampling high point valve NG88 h) Repeat the above process three times or until the nitrogen in the
• To permit easy detection of a leak through a barrier Closed IBS supply bypass valve NC511 insulation spaces contains less than 3% oxygen and be dryer
Closed IBS supply bypass valve NC519 than -20°C dew point.
• To prevent corrosion
Closed IBS supply control valve NC509
i) When the nitrogen content in the insulation space is within
The nitrogen is produced by two nitrogen generators located in the engine Closed IBS supply control isolating valves NC508, NC510
the required limits the system can be set up ready for normal
room and is stored in a pressurised 65m3 buffer tank at 0.9MPa, ready to be Closed IBS portable gas sampling low point valves NC515, NC514
supplied to the pressurisation headers through make-up regulating valves. operations.
NC516
Closed IBS portable gas sampling high point valves NC517, NC518
From the headers, branches are led to the interbarrier and insulation spaces of CAUTION
each tank. Any excess nitrogen is vented through regulating exhaust valves to Closed Fixed gas detection take-off valve NC512 The pressure within the insulation spaces should be kept at atmospheric
the nitrogen vent mast on each tank from the IBS and to deck from the IS. until the tank pressure increases sufficiently for it to be constantly
b) Set up the nitrogen exhaust valves to the interbarrier and maintained at least 30kPa above the insulation spaces pressure during
The system is automatically maintained by alternate exhaust and make-up insulation spaces as follows: normal operations. This is because the insulation spaces MUST be
as the atmospheric pressure and the temperature rises and falls, between a protected at all times against over-pressurisation which could result in
pressure of 0.5kPa and 1.0kPa above atmospheric. Position Description Valve membrane failure.
Closed IS exhaust control valve NG85
Both the IBS and IS spaces on each tank are provided with pressure relief
Closed IS exhaust control isolating valves NG84, NG86
valves which open at a pressure, sensed in each space, of 3kPa for the IBS and
3.5kPa for the IS above atmospheric. A manual bypass with a globe valve is Closed IS exhaust control bypass valve NG83
provided for local venting and sweeping of a space if required. Closed IS fixed gas detection take-off valve NG82
To Gas
PX PI
Combustion FX PX PI PI PX PI
NG FX
Unit NG99 109 Interbarrier and Insulation
Spaces Pressurisation Header
NG98 NG97 NG96
Purging and Sealing Header
NG103 NG102 NG100
CR501
NG98
PIAL
PS
DACS No.5 Liquid Dome NG76
To Aft IS Gauge Board
PI NG91 Bilge Well
PI
NG90 NG86
NG88 NG87
45V NG92 NG89 NG85 NG83 NG79
To Fixed Gas
CR NG84
46V NG82 Detection System
To Safety 504
Chamber
44V NG81
To No.5 Gas
Set at NG80 Dome Gauge Board
0.55MPa Gas NG78
No.5
IBS
Dome
IS
Liquid Key
IBS
IS
40V 32V
Dome To No.5 Gas Nitrogen
Set at
NC506 Dome Gauge Board
0.55MPa Electrical Signal
37V 38V CR503 NC505
No.5 Liquid Dome To Fixed Gas
CN008 36V NC501
Gauge Board Detection System
NC507
NG
Set
Set PCV-8.70 PCV-8.68 PX NC502 NC504 114
0.5MPa 0.5MPa NC513
PI NC514 NC503 NG77
33V 35V NC515
NC517
NC518
From
Set at
Engine Room
1.3MPa
V-8.64 NC516
CR502
To Spray Line
NG108
NC512
Nitrogen Buffer Tank PI NC510 CN509 NC508 To Fixed Gas
(65m3) Detection System Compressor Room Motor Room
NC511
NG75
NC519
NG73
From Nitrogen No.2 HD Compressor Shaft Seal
Generator NG72
Plug No.1 HD Compressor Shaft Seal
To Nitrogen To Nitrogen
Generator Membrane No.2 BOG Compressor Shaft Seal
Booster
For Purging No.2 BOG Compressor BHD Seal Cold Box
Compressor
Insulation
No.1 BOG Compressor Shaft Seal Skid
No.1 BOG Compressor BHD Seal NG74
NG113
Operating Procedure for Normal Inerting d) The IBS exhaust valves, NC102, NC202, NC302, NC402 and
(See illustration 6.1.1d) NC502, are set for 1.0kPa via the space split range controller,
and the IS exhaust valves, NG06, NG23, NG40, NG59 and
a) The manual valves on each side of the supply and exhaust NG85, are set for IBS plus 0.4kPa gauge, ie, 1.4kPa via the
control valves, together with the valves to the liquid and gas space split range controller.
dome gauge boards, should be fully open. For clarity the No. 5
tank has been used as an example, all other tanks should be set e) The pressure control valve from the nitrogen buffer tank reduces
up as below: the pressure from 0.9MPa to 0.5MPa to supply the IBS/IS
pressurisation header.
Position Description Valve
f) Open the manual isolating valves NG100 (to purging and
Closed IS supply sample/purge valve NG98 sealing header), NG96 and NG98 on the insulation space
Closed IS supply bypass valve NG92 pressurisation header and set the control valve NG97 to 30kPa
Automatic IS supply control valve NG90 at the DACS, bypass valve NG99 is to be closed to allow the
Open IS supply control isolating valves NG89, NG91 supply of nitrogen to the headers from the nitrogen buffer tank
Closed IS portable gas sampling high point valve NG88 in the engine room.
Closed IBS supply bypass valve NC511
In the event of cargo gas leakage into an interbarrier space, each space can be
Closed IBS supply bypass valve NC519 swept with a continuous feed of nitrogen by opening the exhaust bypass valve,
Automatic IBS supply control valve NC509 eg, NC504 for No.5 tank, from the space and allowing a controlled purge
Open IBS supply control isolating valves NC508, NC510 through the IBS supply valve NC511. Close monitoring of the gas analyser on
Closed IBS portable gas sampling low point valves NC515, NC514 this space will be necessary during purging.
NC516
Closed IBS portable gas sampling high point valves NC517, NC518 CAUTION
Open Fixed gas detection take-off valve NC512 The insulation spaces must be protected at all times against over-
pressurisation which could result in membrane failure.
b) Set up the nitrogen exhaust valves to the interbarrier and
insulation spaces as follows: A portable elbow bend can be connected to the IBS supply header for
connection to the spray line for IBS stripping if required, see Section 7.2 of
this manual for details.
Position Description Valve
Automatic IS exhaust control valve NG85
Set Points
Open IS exhaust control isolating valves NG84, NG86
Closed IS exhaust control bypass valve NG83 Space Set Point Action
Open IS fixed gas detection take-off valve NG82 IBS 0.2kPa Low pressure alarm
Closed IS exhaust sample/purge valve NG81 IBS 0.5kPa Nitrogen supply valve control
Automatic IBS exhaust control valve NC502 IBS 1.0kPa Nitrogen exhaust valve control
Open IBS exhaust control isolation valves NC501, NC503 IBS 1.5kPa High pressure alarm
Closed IBS exhaust control bypass valve NC504 IBS 3.0kPa Pressure relief valve opens
Open IBS fixed gas detection take-off valve NC507 IS 0.0kPa Low differential pressure alarm
Closed IBS exhaust sample/purge valve NC505 IS 0.4kPa Low pressure alarm
IS IBS +0.2kPa (0.7kPa) Nitrogen supply valve control
c) The IBS nitrogen supply control valves, NC109, NC209, IS 1.0kPa High differential pressure alarm
NC309, NC409 and NC509, are normally set to open at 0.5kPa
IS IBS + 0.5kPa (1.5kPa) Nitrogen exhaust valve control
and close at 1.0kPa by the split range controller via the DACS,
and the IS supply control valves, NG14, NG31, NG50, NG68 IS 2.5kPa High pressure alarm
and NG90, are set for IBS plus 0.2kPa, ie, 0.7kPa, via the split IS 3.5kPa Pressure relief valve opens
range controller for the space.
6.1.2 In-Service Test Illustration 6.1.2a IBS and IS Piping Arrangement on Liquid Dome
Depending on the degree of leakage the gas concentration can be controlled by Safety Valve
purging with nitrogen or alternatively it may be necessary to take the vessel out Connection
of service to effect repairs. for IBS
IS
am
ff erd
Co
N2 Distribution of Nitrogen at IBS Bottom and
Stripping of the Leaked Cargo in IBS (Bottom
AFT Part)
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st
2 nd
RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG078 CG077
CG855 CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
CG079
CS750
No.1 HD Compressor Pre-Cooler
RL816
RL821
CG821 CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 Nitrogen
Vapour Return Line Atmospheric Air
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CG801
CS756
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.2 Post Dry dock and Pre-loading b) Install the spool piece to connect the discharge line from the j) Monitor the dew point at the gas dome through the sample
Operations dry-air/inert gas plant with the liquid header. valves on the vapour header located between the two manual
vapour valves, these valves are listed as SAG170 and SAG170
c) Confirm the spectacle flanges on the vapour dome are in the at the No.1 tank, and are also fitted on tanks Nos.2, 3, 4 and 5
6.2.1 drying cargo tanks
open position. respectively.
Introduction d) Open valve CL702 to supply dry-air to the liquid header. k) When the dew point has reached -20°C or less, close the filling
and the vapour valves of the tank.
During a dry docking or tank inspection, the cargo tanks which have been e) Using the DACS, open the individual tank filling and branch
opened up and contain wet-air must be dried out before cargo can be carried valves in accordance with the following table: Note: The No.1 tank should be the final tank processed to ensure that the
again. The drying process is necessary to avoid the formation of ice when the system is always full of dry-air.
tanks are cooled down and to prevent the formation of corrosive agents if the Position Description Valve
humidity combines with excess sulphur and nitrogen oxides present in the inert Open No.1 tank filling and branch valves CL100, CL110 l) Wet-air which may be contained in the discharge lines from the
gas. cargo pumps, float level piping and any associated pipework in
Open No.2 tank filling and branch valves CL200, CL210
the cargo compressor room must also be purged with dry-air;
Before gassing-up, the tanks are filled with inert gas to prevent the possibility Open No.3 tank filling and branch valves CL300, CL310
this is normally carried out in conjunction with the drying of
of any flammable air/LNG mixtures forming. Normal humid air is initially Open No.4 tank filling and branch valves CL400, CL410 the cargo tanks. Section 6.7.3 of this manual provides a detailed
displaced by dry-air and then the dry-air is displaced by inert gas produced Open No.5 tank filling and branch valves CL500, CL510 procedure on this, simply substitute dry-air for inert gas.
from the dry-air/inert gas plant. (Refer to Section 4.9, Inert Gas System).
f) Open the manual header valves to the vapour domes in m) When all of the tanks have been dried, stop the inert gas plant
Note: The inert gas is primarily nitrogen and carbon dioxide containing less accordance with the following table: and close the supply valve CL702 to the liquid header. Valve
than 1% oxygen and with a dew point of -45°C or below. CG721 is to be left open at all times, except for isolation or
Position Description Valve maintenance.
In the summer the dry-air is heavier than the ambient air, therefore the dry-air Open No.1 tank vapour valves CG170, CG171
from the dry-air/inert gas plant is introduced to the bottom of the cargo tanks Note: It is necessary to lower the tank’s dew point by the use of dry-air to
Open No.2 tank vapour valves CG270, CG271
through the filling pipes. The ambient air is displaced from the top of each tank at least -20°C before feeding the tanks with inert gas. This is to avoid the
through the vapour header, and is discharged from the vent mast at No.1 tank. Open No.3 tank vapour valves CG370, CG371
formation of any corrosive agents.
This is followed by introducing inert gas using the same piping route and the Open No.4 tank vapour valves CG470, CG471
displacement method. The nitrogen system should be ready to be brought into Open No.5 tank vapour valves CG570, CG571 The parameters for operation are as follows:
use. Open Vapour header valve to No.1 vent mast riser CG721
Tanks 100% capacities of each tank, excluding domes are:
In winter the dry-air can be lighter than the ambient air and in this case the g) Raise the set point of the regulating valve CG720 to 100mbar
dry-air is introduced into the top of the tank through the gas dome and vapour and maintain the cargo tank pressure at least 20mbar higher than
header. The ambient air is displaced up the filling line into the liquid header No.1 24,871.71m³
the insulation spaces, venting through the No.1 mast riser as No.2 47,852.48m³
and then vented to atmosphere through the forward vent mast at No.1 tank. necessary.
No.3 47,833.10m³
The dry-air operation can be carried out in port or at sea, taking approximately No.4 47,827.60m³
h) From the inert gas control panel, start the inert gas generator to
20 hours to reduce the dew point to < -20°C, at which time the plant operation No.5 47,839.24m³
produce dry-air. This will automatically discharge to the funnel
is changed over to produce inert gas.
until the correct dew point is obtained. When the dew point is Total tank volume 216,224.13m³
at -45°C, the valve to deck will open and the discharge valve to Volume of dry-air produced per hour 21,000m³/h
Operating Procedure for Drying Tanks (Summer) the funnel close.
Time taken for drying operation 20 hours (2 volume changes)
(See illustration 6.2.1a above)
i) Monitor the dew point of each tank by taking a reading with
All of the valves are assumed closed prior to operations. a portable meter at the three liquid dome sample lines. These
sample lines measure at stepped levels from the top to the
Dry-air, with a dew point of -45°C is produced by the dry-air/inert gas plant at bottom of the tank and the valves are in pairs, listed as SA101/
a flow rate of 21,000Nm³/h. SA102, SA103/SA104 and SA105/SA106 on No.1 tank, and are
also fitted on tanks Nos.2, 3, 4 and 5 respectively.
a) Prepare the dry-air/inert gas plant for use in the dry-air mode.
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900 CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st
2 nd
RG822
CG078 CG077
CG855 CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
CG079
CS750
No.1 HD Compressor Pre-Cooler
RL816
RL821
CG821 CS068 CS067
RL817
RL824 RL823
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 Nitrogen
Vapour Return Line
Atmospheric Air
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Operating Procedure for Drying Tanks (Winter) i) Raise the set point of regulating valve CG720 to 100mbar and The parameters for operation are as follows:
(See illustration 6.2.1b above). maintain the cargo tank pressure at least 20mbar higher than
the insulation spaces, venting through the No.1 mast riser as Tanks 100% capacities of each tank, excluding domes are:
All of the valves are assumed closed prior to operations. necessary.
No.1 24,871.71m³
Dry-air, with a dew point of -45°C is produced by the dry-air/inert gas plant at j) From the inert gas control panel, start the inert gas generator to No.2 47,852.48m³
a flow rate of 21,000Nm³/h. produce dry-air. This will automatically discharge to the funnel
No.3 47,833.10m³
until the correct dew point is obtained. When the dew point is
at -45°C, the valve to deck will open and the discharge valve to No.4 47,827.60m³
a) Prepare the dry-air/inert gas plant for use in the dry-air mode.
the funnel close. No.5 47,839.24m³
b) Install the spool piece to connect the discharge line from the Total tank volume 216,224.13m³
dry-air/inert gas plant with the vapour header via the compressor k) Monitor the dew point of each tank by taking a reading with Volume of dry-air produced per hour 21,000m³/h
suction line. a portable meter at the three liquid dome sample lines. These Time taken for drying operation 20 hours (2 volume changes)
sample lines measure at stepped levels from the top to the
c) Install the spool piece to connect the liquid header with No.1 bottom of the tank and the valves are in pairs, listed as SA101/
vent mast riser at valve CL700. SA102, SA103/SA104 and SA105/SA106 on No.1 tank, and are
also fitted on tanks Nos.2, 3, 4 and 5 respectively.
d) Confirm the spectacle flanges on the vapour dome are in the
OPEN position. l) When the dew point has reached -20°C or less, close the filling
and the vapour valves of the tank.
e) Open valves SAG843 and CG843 to supply dry-air to the vapour
header. Note: No.1 tank should be the final tank processed to ensure that the system
is always full of dry-air.
f) Using the DACS, open the individual tank filling and branch
valves in accordance with the following table:. m) Wet-air which may be contained in the discharge lines from the
cargo pumps, float level piping and any associated pipework in
Position Description Valve the cargo compressor room must also be purged with dry-air;
Open No.1 tank filling and branch valves CL100, CL110 this is normally carried out in conjunction with the drying of
the cargo tanks. Section 6.7.3 of this manual provides a detailed
Open No.2 tank filling and branch valves CL200, CL210
procedure on this, simply substitute dry-air for inert gas.
Open No.3 tank filling and branch valves CL300, CL310
Open No.4 tank filling and branch valves CL400, CL410 n) When all of the tanks have been dried, stop the inert gas plant.
Open No.5 tank filling and branch valves CL500, CL510 Close the supply valve CL609 to the vapour header. Valve
CG721 is to be left open at all times, except for isolation or
g) Open the manual header valves to the vapour domes in maintenance.
accordance with the following table:
Note: It is necessary to lower the tank’s dew point by the use of dry-air to at
Position Description Valve least -20°C, before feeding the tanks with inert gas to avoid the formation of
Open No.1 tank vapour valves CG170, CG171 corrosive agents.
Open No.2 tank vapour valves CG270, CG271
Open No.3 tank vapour valves CG370, CG371
Open No.4 tank vapour valves CG470, CG471
Open No.5 tank vapour valves CG570, CG571
Open Liquid header valve to No.1 vent mast riser CL700
h) Open the manual liquid header valve to No.1 vent mast riser.
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box
CS052
No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG078 CG077
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800
Dry-Air
Vapour Return Line Nitrogen
Inert Gas
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.2.2 Inerting Cargo Tanks Position Description Valve k) When all of the tanks are inerted to less than 2% oxygen and
dried to -40°C dew point:
Open No.1 tank filling and branch valves CL100, CL110
Introduction Open No.2 tank filling and branch valves CL200, CL210 • Stop the supply of inert gas
Open No.3 tank filling and branch valves CL300, CL310 • Close the supply valve CL702 to the liquid header
Inert gas, with an oxygen content of less than 1% and a dew point of -45C, is
Open No.4 tank filling and branch valves CL400, CL410 • Close the tank filling valves CL100~CL500
produced by the dry-air/inert gas plant with a flow rate of 21,000Nm³/h. For
a more detailed description on the operation of the inert gas generating plant, Open No.5 tank filling and branch valves CL500, CL510
• Ensure vapour header vent valve, CG720, is set in auto to
refer to Section 4.9 of this manual. 230mbar
f) Open the manual header valves to the vapour domes in
• Remove the spool piece that connects the inert gas header to
The emergency pump column has to be inerted with nitrogen before inerting accordance with the following table:
the liquid header
the cargo tanks.
Position Description Valve • Valve CG721 is to be left open at all times, except for
WARNING isolation or maintenance
Open No.1 tank vapour valves CG170, CG171
Inert gas from this generator and pure nitrogen will not sustain life. Open No.2 tank vapour valves CG270, CG271
Great care must be exercised to ensure the safety of all personnel Note: Until the ship is ready to load LNG, the tanks can be maintained
Open No.3 tank vapour valves CG370, CG371 under inert gas pressure for as long as necessary. While the cargo tanks are at
involved with any operation using inert gas of any description to avoid
Open No.4 tank vapour valves CG470, CG471 atmospheric pressure the insulation spaces must remain under a vacuum. The
asphyxiation due to oxygen depletion.
Open No.5 tank vapour valves CG570, CG571 cargo tank pressure must be maintained at least 20mbar above the insulation
The time taken to reduce the oxygen content to less than 2% by volume and Open Liquid header valve to No.1 vent mast riser CL700 spaces pressure and to reduce leakage once the tanks are pressurised, isolate
the final dew point to -40°C is a further 20 hours. Inert gas can be introduced all of the valves at the forward venting system.
without first using dry-air where the tanks have been maintained during refit g) Raise the set point of regulating valve CG720 to 100mbar and
with a flow of dry-air. This reduces the combined operation time by 20 hours. maintain the cargo tank pressure at least 20mbar higher than
the insulation spaces, venting through the No.1 mast riser as
During the time that the inert gas plant is in operation for drying and inerting necessary.
the tanks, the inert gas is also used to dry and to inert all of the other LNG and
vapour pipework. Before introduction of LNG liquid or vapour, the pipework h) From the inert gas control panel, start the inert gas generator
not purged with inert gas must be purged with nitrogen. to produce inert gas. This will automatically discharge to
the funnel until the correct dew point and oxygen content is
obtained. When inert gas with an oxygen content of less than
Procedure for Inerting the Cargo Tanks 1% in volume and a dew point of -45C is produced, the valve to
(See illustration 6.2.2a). deck will open and the discharge valve to the funnel close.
a) Prepare the dry-air/inert gas plant for use in the inert gas i) Monitor the dew point at the gas dome through the sample
mode. valves on the vapour header located between the two manual
vapour valves, these valves are listed as SAG170 and SAG170
b) Install the spool piece to connect the discharge line from the at the No.1 tank, and are also fitted on tanks Nos.2, 3, 4 and 5
dry-air/inert gas generator with the liquid header. respectively. Oxygen (O2) content is to be less than 2% and the
dew point less than -40°C. Progress of the inerting can also be
c) Confirm the spectacle flanges on the vapour dome are in the monitored using the liquid dome sampling points, these sample
OPEN position. lines measure at stepped levels from the top to the bottom of the
tank.
d) Open valve CL702 to supply dry-air to the liquid header.
j) During tank inerting, purge the air contained in the lines and
e) Using the DACS, open the individual tank filling and branch equipment for approximately 5 minutes by using the sample
valves in accordance with the following table: point valves. (See Section 6.7.3, Gas Freeing, for a detailed
procedure.)
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st
2 nd
RG822
CG078 CG077
CG855 CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
CG079
CS750
No.1 HD Compressor Pre-Cooler
RL816
RL821
CG821 CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed Key
CG800
Nitrogen
Vapour Return Line
Nitrogen Vapour
CG807 CG808 Dry-Air
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Drying and Inerting the Cargo Tanks Using Liquid Nitrogen Position Description Valve Note: No.1 tank should be the final tank to be inerted to ensure that the
Open Vaporiser inlet valve CS870 system is always full of nitrogen.
There are occasions where it is not possible to use the on board inert gas plant
to dry and inert the tanks, and the alternative method is to use liquid nitrogen Open Vaporiser manual discharge valve CG821
k) When all the tanks have been dried, stop the supply of liquid
from ashore. Open Vaporiser outlet valve to liquid header CL807
nitrogen and close the manifold supply valve to the spray header
Open No.1 tank filling valves CL100, CL110 and the regulating valve at No.1 vent mast riser. Raise the set
Liquid nitrogen is loaded from ashore and sent to the vaporiser via the spray Open No.2 tank filling valves CL200, CL210 point of CG720 to 230mbar.
header. The liquid nitrogen is vaporised and the gaseous nitrogen distributed to Open No.3 tank filling valves CL300, CL310
the liquid header and then to each of the tanks through the liquid filling line.
Open No.4 tank filling valves CL400, CL410 Position Description Valve
The warm gaseous nitrogen vapour displaces the atmospheric air through the Open No.5 tank filling valves CL500, CL510 Close No.1 liquid manifold ESDS (S) valve CL011
vapour main and to atmosphere at No.1 mast riser. Close No.1 manifold double-shut bypass valve CS061
f) Open the valves to discharge the air in the tanks to atmosphere Reset Vapour header pressure control valve CG720
The cargo tanks, associated pipework and machinery are considered to be dried via the No.1 vent mast riser.
and inerted when the readings from the portable oxygen and dew point meters l) Allow the vaporiser and cargo lines to warm-up to ambient
give the tank contents as being less than 2% O2 and a dew point of -40°C or Position Description Valve temperature before shutting off the steam supply to the vaporiser
less. This will normally take approximately 20 hours. and closing the system down. This is to avoid over-pressurisation
Open No.1 tank vapour valves CG170, CG171
within the pipelines due to the cold nitrogen vapour expanding
Open No.2 tank vapour valves CG270, CG271
Procedure for Drying and Inerting the Cargo Tanks Using as it warms-up. Monitor the pressure in the vaporiser and if
Open No.3 tank vapour valves CG370, CG371 necessary vent to one of the cargo tanks.
Liquid Nitrogen Open No.4 tank vapour valves CG470, CG471
(See illustration 6.2.2b). Open No.5 tank vapour valves CG570, CG571 m) Atmospheric air which may be contained in the discharge lines
Open Vapour header valve to No.1 vent mast riser CG721 from the cargo pumps, float level piping and any associated
a) Warm-through the main vaporiser as described in Section 4.6. pipework in the cargo compressor room, must be purged with
g) Check that the water curtain is in operation, then open the nitrogen. This is normally carried out in conjunction with the
b) Connect the spool piece between the vaporiser discharge line nitrogen supply valve to the spray header. drying of the cargo tanks by venting through the respective
and the liquid header in way of valve CL702. sample points, located on the pipework, until an acceptable
reading is obtained on the portable dew point and oxygen
Position Description Valve
c) Open the spray header to the main vaporiser. meters.
Open No.1 liquid manifold ESD(S) valve CL011
Position Description Valve The procedure for drying and inerting the associated pipework and machinery
h) Request the shore to supply the liquid nitrogen at slow speed space with nitrogen is identical to that used during the drying and inerting of
Open No.1 liquid manifold cooldown valve CS061 to cool down the spray header, vaporiser and liquid line. As the the tanks, using the on board inert gas/dry-air plant.
Open Spray header block valves CS750, CS752 system cools down, the automatic inlet and temperature valves
Open Spray header to vaporiser inlet valve CS756 will control the amount of flow and temperature in the vaporiser.
The outlet temperature should be +20°C, supply inlet pressure
d) Set the main vaporiser control valves. 2.5 bar, inlet flow 28m³/h and outlet flow 16,457m³/h.
Position Description Valve i) The tank pressure is controlled via the vapour header pressure
Set Vaporiser automatic inlet control valve CS871 control valve CG720 set in the automatic mode. Raise the set
point of this to 70mbar and maintain the cargo tank pressure at
Set Vaporiser automatic temperature control CS872
least 20mbar higher than the insulation space pressure.
valve
j) Monitor the dew point and oxygen content of each tank by
e) Open the valves to supply nitrogen gas to the liquid header and
taking a reading with the portable dew point and oxygen meters
open the tank isolating and filling valves.
at the sample points. When the dew point is -40°C or less and
the O2 content less than 2%, close in the filling and vapour
valves of the tank.
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG078 CG077
CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
Pre-Cooler
CG079
CS750
No.1 HD Compressor
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 Nitrogen
Vapour Return Line Inert Gas
LNG Vapour Warm
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.2.3 Gassing-Up Cargo Tanks The first stage of the operation while venting to atmosphere will take Position Description Valve
approximately 10 hours, the second stage can be in two forms, with either
Auto LNG vaporiser control valve CS871
vapour returned to shore for 10 hours, or the use of the gas combustion
Introduction unit which will take approximately 20 hours based on the GCU capacity of Open LNG vaporiser outlet valve CG821
1,800m³/h. Open Supply to the vapour header CG805
After lay-up or dry dock, the cargo tanks are filled with inert gas or nitrogen.
If the purging has been carried out with inert gas, the cargo tanks have to On completion of warm LNG vapour purging, the cargo tanks will normally g) Open the header valves to the vapour domes in accordance with
be purged with LNG vapour and cooled down when the vessel arrives at the be cooled down. the following table:
loading terminal. This is because, unlike nitrogen, inert gas contains 15%
carbon dioxide (CO2) which will freeze at around -60°C and produces a white
powder or foam which can block valves, filters and nozzles. To avoid any Procedure for Gassing-Up the Cargo Tanks - Venting Position Description Valve
problems with blocked filters, etc, the manifolds, spray header and vaporisers Open No.1 tank vapour valves CG170, CG171
(See Illustration 6.2.3a).
are purged with nitrogen prior to the purging of the cargo tanks with inert Open No.2 tank vapour valves CG270, CG271
gas. It has been assumed, though unlikely, that all of the valves are closed prior to Open No.3 tank vapour valves CG370, CG371
use.
Open No.4 tank vapour valves CG470, CG471
The inert gas in the cargo tanks is then replaced with warm LNG vapour to
remove any freezable gases such as CO2 and to complete the drying of the a) Install the following removable bends/spool pieces: Open No.5 tank vapour valve CG570, CG571
tanks. Close Vapour header valve to No.1 vent mast riser CG721
• Liquid header to No.1 mast riser
• Liquid header to HD compressor supply Note: For safety reasons, ensure that the hull water curtain on the connected
Operation side is in operation and that all purge/sampling valves are closed.
b) Prepare the LNG vaporiser for use.
LNG is supplied from the terminal to the liquid manifold where it passes to the
h) Using the DACS, open the individual tank loading valves in
stripping/spray header via the appropriate ESDS liquid valve. c) Adjust the set point of the temperature control valve to +20°C accordance with the following table:
for the vaporiser.
It is then fed to the vaporiser and the LNG vapour produced is passed at +20°C
to the vapour header and then into each tank via the vapour domes. Position Description Valve
d) Using the DACS, adjust the set point of the flow control valve
for the vaporiser to provide a flow of 34m³/h, which will give an Open No.1 tank filling and branch valves CL100, CL110
The LNG vapour is lighter than the inert gas, which allows the inert gases in inlet pressure of 6 bar and an outlet flow of 18,841m³/h. Open No.2 tank filling and branch valves CL200, CL210
the cargo tanks to be exhausted up the tank loading column to the liquid header. Open No.3 tank filling and branch valves CL300, CL310
The inert gas then free-flows to shore through the HD compressors and vapour e) Adjust the set point of the regulating valve at the No.1 mast riser Open No.4 tank filling and branch valves CL400, CL410
manifold. so that at all times the cargo tank pressure is at least 20mbar
Open No.5 tank filling and branch valves CL500, CL510
higher than the insulation spaces.
Note: It may be possible at some terminals to discharge the inert gas to
i) Using the DACS, open valve CL011, the No.1 ESD manifold
atmosphere until the 5% hydrocarbon (% figure will be specified by the Position Description Valve valve on the starboard side, and request the terminal to
particular port authority) is detected at No.1 mast riser. The exhaust gas is
Set No.1 mast riser control valve CG720 commence the supply of LNG liquid to the ship at a slow rate.
then directed ashore via the HD compressors or to the GCU.
Open Liquid header to No.1 vent mast crossover CL700 Slowly increase the rate of delivery until the required rate to
The operation is considered complete when the hydrocarbon content (HC), as valve the vaporiser is attained. Whether rate or pressure is used will
measured at the top of the cargo filling pipe exceeds 95% by volume, 99% at depend on the terminal, either start at 1 bar and slowly build up
the tank bottom, and the CO2 less than 0.5% by volume. This normally entails f) Set up the spray header to supply LNG to the vaporiser in to 6 bar or start at 2m³/h and build up to 34m³/h.
approximately 1.5 changes of the volume of the atmosphere in the cargo tank. accordance with the following table:
j) Adjust the No.1 mast riser pressure with CG720 to 100mbar,
On completion of the warm LNG vapour purging, the cargo tanks will normally Position Description Valve as a minimum the cargo tank pressure must be at least 20mbar
be cooled down. higher than the insulation spaces.
Open No.1 starboard manifold double shut-off CS061
bypass valve to spray main
It may be necessary to undertake the purging of one or more tanks at sea using k) Monitor the inert gas exhausting at each liquid dome using the
Open Spray header block valves CS750, CS752 mid cargo tank sample cock initially, followed by the sample
LNG liquid already on board. In this case the liquid will be supplied to the
Open Spray header to vaporiser inlet CS756 cock at the vapour dome. Also monitor the inert gas exhausted
vaporiser via the stripping/spray header using the stripping/spray pump of a
cargo tank containing LNG liquid. Open LNG vaporiser inlet block valve CS870 at No.1 mast riser, using the sample cock.
Auto LNG vaporiser temperature control valve CS872
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800
Key
Vapour Return Line LNG Liquid
Nitrogen
CG807 CG808
Inert Gas
LNG Vapour Warm
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL401
CL301
CL208
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
l) When 5% hydrocarbon, (or the quantity the port authority will Procedure to Purge the Cargo Tanks - Vapour to Shore If the cargo tank pressure increases, request the terminal to reduce the supply
allow) is detected at the No.1 mast riser and each vapour dome, of LNG.
Stage Two
request permission from the terminal personnel to direct exhaust
gas to the terminal facilities. (See illustration 6.2.3b). If the cargo tank pressure decreases, either shut down one of the compressors
as necessary, or request the terminal to increase the LNG liquid supply to the
The second stage of the procedure is to bring the hydrocarbon content inside vaporiser.
Procedure to Purge the Lines and Equipment with LNG the cargo tanks up to 99% by volume at the tank bottom, utilising the HD
Vapour compressors returning vapour to shore. When the cargo tank hydrocarbon content reaches 99% by volume at the tank
bottom, throttle-in the individual tank loading valve until it is only just cracked
Where it has not been possible to purge the spray header and cargo machinery a) Prepare both HD compressors for use. open.
space equipment with nitrogen prior to the gassing-up of the tanks, then these
areas will have to be purged with LNG to ensure all traces of the inert gas are b) Install the spool piece connecting the liquid line to the suction i) Request the terminal to stop the supply of LNG liquid.
removed. This would normally be carried out during the gassing-up of the for the HD compressors if not already installed.
cargo tanks. j) Stop both HD compressors.
c) Adjust the set point of both HD compressors’ pressure control
During the change of atmosphere, purge the following sections for about five valve to 60mbar(g), or the required value. k) Close valve CS756, the spray header to vaporiser inlet valve.
minutes each:
d) On the HD compressors, open the following valves: l) Do not shut down the vaporiser until it has been warmed-
a) All sections of the stripping/spray header and tank connections, through to the ambient temperature.
via the valves at each liquid dome. Position Description Valve
• No.1 tank CS156, CS151, CS152, SAS151 Open Liquid header to IG crossover line CL702 m) Remove and blank the removable bends after purging them with
nitrogen and testing the gas content.
• No.2 tank CS256, CS251, CS252, SAS251 Open Crossover line to HD compressor supply CG808
• No.3 tank CS356, CS351, CS352, SAS351 Open No.1 HD compressor inlet valve CG831 n) Prepare the cargo system for cooldown.
Open No.2 HD compressor inlet valve CG841
• No.4 tank CS456, CS451, CS452, SAS451
Open No.1 HD compressor outlet valve CG832
• No.5 tank CS556, CS551, CS552, SAS551 Open No.2 HD compressor outlet valve CG842
Auto HD compressor discharge line to vapour CG800
b) At the manifolds, purge the manual, ESD and manifold return to shore line valve
bypass valves which are not in use, using the sample and drain
connections. Note: Ensure that valve CG079 vapour main to vapour manifold is closed,
otherwise the vapour will recirculate around the system.
c) Purge the following lines and equipment for five minutes each:
• Both heaters, BOG compressors and emergency vent line e) Open the vapour manifold ESDS valve CG071 (starboard side).
This will enable a free-flow of gas to the terminal and is a check
• Extremities of vapour header via sample points
that the pipeline layout on board has been lined-up correctly.
d) Continue with gassing-up of the cargo tanks while carrying out
the above. f) Using the DACS, adjust the set point of the No.1 mast riser
control valve CG720 to the required value, for example,
200mbar(g), so that this valve will remain closed during normal
running of the compressors, but would act in a safety capacity if
necessary.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed LNG Liquid
CG800
Nitrogen
Vapour Return Line
Inert Gas
LNG Vapour Warm
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Procedure to Purge the Cargo Tanks - Vapour to GCU f) Using the DACS, adjust the set point of No.1 mast riser control
valve CG720 to the required value, for example, 200mbar(g), so
Stage Two
that this valve will remain closed during normal running of the
(See illustration 6.2.3c). compressors, but would act in a safety capacity if necessary.
The following procedure would be used where the vapour to shore was not g) As the tank pressure increases, use the DACS system to start one
available. or both of the compressors as necessary, returning vapour to the
GCU.
The procedure is to bring the hydrocarbon content inside the cargo tanks up
to 99% by volume at the tank bottom, utilising the HD compressors returning h) Using the DACS, monitor the pressure inside the tanks.
vapour to the GCU.
If the cargo tank pressure increases, request the terminal to reduce the supply
The following procedure is limited by the capacity of the GCU: of LNG.
a) Prepare both HD compressors for use. If the cargo tank pressure decreases, either shut down one of the compressors
as necessary, or request the terminal to increase the LNG liquid supply to the
b) Install the spool piece connecting the liquid line to the suction vaporiser.
for the HD compressors if not already installed.
When the cargo tank hydrocarbon content reaches 99% by volume at the tank
c) Adjust the set point of both HD compressors’ pressure control bottom, throttle-in the individual tank loading valve until it is only just cracked
valve to 60mbar(g), or the required value. open.
d) On the HD compressors, open the following valves: i) Request the terminal to stop the supply of LNG liquid.
e) Set up the high duty heater to supply to the GCU at 25°C. n) Remove and blank the removable spool pieces after purging
them with nitrogen and testing the gas content.
Position Description Valve
o) Prepare the cargo system for cooldown.
Open High duty heater inlet valve CG861
Auto High duty heater supply control valve CG864
Auto High duty heater temperature control valve CG865
Open High duty heater outlet valve CG862
Open High duty heater crossover valve to GCU CG883
Open Supply to GCU CG900
6.2.4 Cooling Down Cargo Tanks Cooling down cargo tanks from +30 to -130°C so they can be loaded requires Initial Avg Tank Temp Time to Cool to Avg Temp -130°C Quantity
LNG to be sprayed into the tanks for about 10 hours at a rate of 126m³/h, or
°C Hours m3
about 1,260m³ total. That quantity is sufficient to cool the tank vapour and
Introduction primary membrane to the desired -130°C temperature to permit the tanks to be -118 2 250
loaded within 12.5 hours. -125 1 125
Arriving at the terminal to load the first cargo after refit or repairs where the -130 0 0
vessel was required to be gas free, the cargo tanks will be inert and at ambient
temperature. After the cargo system has been purge-dried and gassed-up, the LNG Quantity Used for Cooldown in 10 Hours
LNG is supplied from the terminal to the cooldown manifold and from there
headers and tanks must be cooled down before loading can commence. The
directly to the spray header which is open to the cargo tanks. Once the cargo
cooldown operation follows immediately after the completion of gassing-up, If all five cargo tanks are cooled simultaneously through the spray nozzles in
tank cooldown is nearing completion, the liquid manifold crossovers, liquid
using LNG supplied from the terminal. one cooldown header for 10 hours continuously at an average spray header
header and loading lines are cooled down.
pressure of 3 bar, then the LNG quantity used for cooldown will be about
Unlike rigid cargo tank designs, vertical thermal gradients in the tank walls are 1,260m³ and the average temperature in each tank will be -130°C or colder.
Cooldown of the cargo tanks is considered complete when the temperature
not a significant limitation on the rate of cooldown. The rate of cooldown is
sensors in each tank indicate an average temperature of -130°C or lower over
limited for the following reasons: The following table from Gaz Transport & Technigas is based on the average
the whole tank. This applies only for the first cooldown after the tank has
cooldown data from other Mark 111 type membrane vessels, with 3 bar pressure
• To avoid excessive pump tower stress. been warmed-up, subsequent cooldowns only require the bottom temperature
to the spray rail. This is only a guide and individual vessels may differ.
• Vapour generation must remain within the capabilities of the sensors to be -130°C or lower. When this temperature has been reached, and
HD compressors to maintain the cargo tanks at a pressure of the Custody Transfer System (CTS) registers the presence of liquid, bulk
Cooling Down Time Primary Barrier loading can begin.
between 5 and 7kPa(g). Mean Temperature
• To remain within the capacity of the nitrogen system to maintain 0 hour 30°C Vapour generated during the cooldown of the tanks is returned to the terminal
the interbarrier and insulation spaces at the required pressures. 1 hour 12°C via the HD compressors and the vapour manifold as in the normal manner for
2 hours -20°C loading.
If the terminal can handle the vapours, all five cargo tanks can be simultaneously
cooled down to an average temperature in each of -130°C in 10 hours and use 3 hours -47°C
During cooldown, nitrogen flow to the IBS and IS spaces will significantly
about 1,260m³ of LNG. 4 hours -67°C increase. It is essential that the rate of cooldown is controlled, so that it
5 hours -85°C remains within the limits of the nitrogen system to maintain the interbarrier
LNG is supplied from the terminal to one of the four liquid manifolds and 6 hours -100°C space pressures at 0.2~0.7kPa gauge, and the insulation space pressure at
from there directly to the spray header which is open to one of the two spray IBS+0.2kPa gauge.
7 hours -113°C
headers in each tank, the other header is a 100% back-up. Once the cargo tank
cooldown is nearing completion, the liquid manifold crossovers, liquid header 8 hours -118°C
Once the cooldown is complete and the build-up to bulk loading has commenced,
and loading lines are cooled down. 9 hours -125°C the tank membrane will be at or near to the liquid cargo temperature, but it will
10 hours -130°C take some hours to establish fully cooled down temperature gradients through
Cooldown of the cargo tanks is considered complete when the temperature the insulation. Consequently, boil-off from the cargo will be higher than
sensors in each tank indicate an average temperature over the whole tank of The following table can be used as a guide to calculate the quantity of LNG normal during the first 3-4 days after loading to fully cool all of the cargo tank
-130°C or colder at most terminals. Arzew requires a bottom temperature of and the time required to complete cooldown of all five tanks that are not fully insulation to the loaded voyage operating temperature.
-145°C before start of loading. When these temperatures have been reached, cooled down to -130°C before loading can be started.
and the Custody Transfer System (CTS) registers the presence of liquid, bulk Procedure to Prepare for Tank Cooldown
loading can begin. Initial Avg Tank Temp Time to Cool to Avg Temp -130°C Quantity
°C Hours m3 Place in service the heating system for the cofferdams.
Vapour generated during the cooldown of the tanks is returned to the terminal
via either the terminal’s vapour return compressors (Arzew), or one of the 30 10 1,260
a) Prepare the records for the tank, secondary barrier and hull
ship’s HD compressors and the vapour manifold as in the normal manner for 12 9 1,125 temperatures.
loading. -20 8 1,000
-47 7 875 b) Check that the nitrogen pressurisation system for the insulation
During cooldown, nitrogen flow to the IBS and IS spaces will significantly spaces is in automatic operation and lined-up to supply the
-67 6 750
increase as those spaces cool down. It is essential that the rate of cooldown in additional nitrogen necessary to compensate for the contraction
the cargo tanks is controlled, so that it remains within the limits of the nitrogen -85 5 625
from cooling of the tanks. Prior to the cooling down, the nitrogen
system to maintain the interbarrier and insulation space at a minimum pressure -100 4 500 pressure inside the IBS will be raised to 0.7kPa(g) and the IS
of at least 0.3kPa above atmospheric pressure. -113 3 375
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG078 CG077
CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
Pre-Cooler
CG079
CS750
No.1 HD Compressor
RL816
RL821
CG821 CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 LNG Vapour
Vapour Return Line Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
will be maintained at IBS +0.2kPa(g). Pressurise the buffer tank c) Prepare both HD compressors for use. k) Cooldown of the cargo tanks is considered complete when
to the maximum pressure. the top (99%) and bottom (end) temperature sensors in each
d) Adjust the set point of both HD compressors’ pressure control tank indicate temperatures of -130°C or lower. When these
c) Check that the gas detection system is in normal operation. valve to 5kPa, or the required value. temperatures have been reached, and the Custody Transfer
System (CTS) registers the presence of liquid, bulk loading can
d) Prepare the nitrogen generators for use. e) On the HD compressors, open the valves in accordance with the begin.
following:
e) Prepare both HD compressors for use. This procedure will normally take approximately 10 hours.
Position Description Valve
Procedure for Cooldown with Gas Return Through the Vapour Open Vapour header valve to compressor supply CG803
line
Header
(See illustration 6.2.4b). Open No.1 HD compressor inlet valve CG831
Open No.2 HD compressor inlet valve CG841
Assuming the ship is ready to prepare for cooldown after the completion of Open No.1 HD compressor outlet valve CG832
gassing-up. Open No.2 HD compressor outlet valve CG842
AUTO Compressor discharge valve to vapour return CG800
Note: When cooling down, one spray rail should be sufficient for this to shore line
operation, experience will dictate whether the second rail needs to be used.
f) Open the vapour manifold ESD valve CG071 (starboard side).
a) Open the spray header valves to each tank and the spray rails. This will enable a free-flow of gas to the terminal and is a check
that the pipeline layout on board has been lined-up correctly.
Position Description Valve
Open Spray crossover valve to spray main CS750 g) Confirm open valves CL011 and CS061, the ESD valve and
Open Spray line block valves CS751, CS752 cooldown valve to the stripping/spray line, if using the No.1
liquid manifold on the starboard side.
Open No.1 tank spray master valve CS155
Open No.1 tank spray rail inlet valves CS151, CS152 h) Request the terminal to supply LNG liquid for the cooling down
Open No.2 tank spray master valve CS255 operation at minimum flow.
Open No.2 tank spray rail inlet valves CS251, CS252
Open No.3 tank spray master valve CS355 i) When the vapour pressure inside the tanks rises to approximately
5kPa, start one or both of the compressors as necessary using
Open No.3 tank spray rail inlet valves CS351, CS352
the DACS. Increase the spray nozzle pressure.
Open No.4 tank spray master valve CS455
Open No.4 tank spray rail inlet valves CS451, CS452 Note: Ensure that valve CG079, vapour main to vapour manifold, is closed,
Open No.5 tank spray master valve CS555 otherwise the vapour will recirculate around the system.
Open No.5 tank spray rail inlet valves CS551, CS552
j) Using the DACS, monitor the pressure inside the tanks and
b) Confirm the vapour valves on each tank, as all the tanks are kept temperature cooldown rate. Adjust the in-use spray rail inlet
connected to the vapour header. valves CS151/2, CS251/2, CS351/2, CS451/2 and CS551/2 to
obtain an average temperature fall of 20/25°C per hour during
Position Description Valve the first 5 hours, thereafter 10/12°C per hour.
Open No.1 tank vapour valves CG170, CG171
If the tank pressure continues to increase, request the terminal to reduce the
Open No.2 tank vapour valves CG270, CG271
supply of LNG.
Open No.3 tank vapour valves CG370, CG371
Open No.4 tank vapour valves CG470, CG471 If the tank pressure decreases, either shut down one of the compressors or
Open No.5 tank vapour valves CG570, CG571 request the terminal to increase the supply of LNG.
Close Vapour header valve to No.1 vent mast riser CG721
RL848
RL849
RL813
CS062 CS061
CS051
RG846
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
CS052
Cold Box No.1 BOG Compressor
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG072 CG071
CG883
RL810
RL809
BOG Heater RG804 RG802 1st
2 nd
RG822
CG855 CG078 CG077
CG851 No.2 BOG Compressor CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
Pre-Cooler
CG079
CS750
No.1 HD Compressor
RL816
RL821
CG821 CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
LNG Liquid
CG822
Locked
Closed
CG800
LNG Vapour
Vapour Return Line Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Procedure for Cooldown with GCU and Using the Ship’s c) Set up to supply excess vapour to the GCU via the high duty
Stripping Pump heater and one HD compressor.
(See illustration 6.2.4c).
Position Description Valve
In this example it has been assumed that the gassing-up has been completed Open Vapour header valve to compressor supply CG804
alongside, as well as the cooling down of No.5 cargo tank and loading of line
LNG to that tank with at least sufficient LNG to cool down the remaining four Open No.1 HD compressor inlet valve CG831
tanks. Open No.1 HD compressor outlet valve CG832
Open HD compressor discharge to HD heater CG861
Note: It is assumed that due to the large quantity of vapour that will be
produced, the high duty compressor and heater would be required to control Automatic HD heater temperature control valve CG865
the pressure within the tanks. The pipeline configuration allows for the HD Automatic HD heater flow control valve CG864
compressor to supply the BOG heater, also the BOG compressor to supply Open HD heater outlet valve CG862
the HD heater. Open HD heater crossover valve to GCU CG883
Open Supply to GCU unit master valve CG900
a) Open the spray header valves to each tank and the spray inlet
valves. Start No.5 cargo tank stripping pump and open the pump d) Using the DACS, monitor the pressure inside the tanks and
discharge valve CS550. Set in automatic mode valve CS554 temperature cooldown rate. Adjust the in-use spray rail inlet
stripping pump return line to tank. valves CS151/2, CS251/2, CS351/2, CS451/2 and CS551/2 to
obtain an average temperature fall of 20/25°C per hour during
Position Description Valve the first 5 hours, thereafter 10/12°C per hour.
Open Spray line block valves CS751, CS752
Open No.1 tank spray master valve CS155 Note: The rate of cooldown will be controlled by the ability of the GCU
Open No.1 tank spray inlet valves CS151, CS152 to control the vapour generated, therefore it will be necessary to increase
Open No.2 tank spray master valve CS255 or reduce the pressure generated by the spray pump to maintain the tank
pressures within reasonable limits.
Open No.2 tank spray inlet valves CS251, CS252
Open No.3 tank spray master valve CS355 e) Cooldown of the cargo tanks is considered complete when
Open No.3 tank spray inlet valves CS351, CS352 the top (99%) and bottom (end) temperature sensors in each
Open No.4 tank spray master valve CS455 tank indicate temperatures of -130°C or lower. When these
Open No.4 tank spray inlet valves CS451, CS452 temperatures have been reached, and the Custody Transfer
Open No.5 tank spray master valve CS555 System (CTS) registers the presence of liquid, bulk loading can
begin.
Note: When cooling down, one spray rail should be sufficient for this
operation, experience will dictate whether the second rail needs to be used.
b) Confirm the vapour valves on each tank, as all the tanks are kept
connected to the vapour header.
6.3.3 Loading Cargo with Vapour Return to Shore via the High Duty Compressor
6.3.5 Deballasting
Al Sahla Cargo Operating Manual
Loading is complete when all of the tanks are 98.0% full by volume. • A pre-loading meeting is to be held together with the terminal
representatives. The ship/shore safety list is to be filled in.
During loading the boil-off and displaced gas is returned to the shore facilities. • The Custody Transfer Measurement (CTM) is to be carried
It will normally be necessary to use at least one HD compressor whilst loading out together with the terminal representatives, surveyors and
to reduce and maintain the cargo tank pressure to the required pressure of authorities (customs).
between 5kPa and 10kPa gauge. Both compressors can be used in parallel if
• All connections (bonding wire, telephones, loading and
required.
bunkering arms) at the manifold are to be carried out according
to the terminal’s cargo handling manual.
Operation • The HD compressors are to be made ready for use in sending
vapour to the shore.
LNG is loaded via the loading manifolds to the liquid header and then to each
tank filling valve. • The chief officer is to supervise all loading operations on
board.
The boil-off and displaced vapour leaves each tank via the gas domes to the • The sounding, temperature and pressure on all cargo tanks is to
vapour header. The vapour is initially free-flowed to shore via the vapour be checked and noted according to the schedule for the loading.
crossover manifold. As the tank pressure rises, one HD compressor is brought The Cargo Monitoring Record is to be filled in.
into operation to increase the gas flow to shore and limit the vapour main and
hence cargo tank pressure. • Vessel is ready to cool down the loading arms.
(See illustration 6.3.1a, Preparations for Loading).
Deballasting is undertaken at the same time as cargo loading and the
deballasting sequence is arranged to keep the vessel within the required limits
of draught, trim, stress and stability.
The flow of nitrogen to the interbarrier space (IBS) and the insulation space (IS)
is increased to maintain a positive pressure in these spaces during completion
of cooldown and the start of loading. The automatic nitrogen control system
will maintain the pressure in the insulation spaces, however, raise the set point
of the IBS from +0.2kPag to +0.7kPag prior to cooldown, (with experience it
may be found unnecessary to do this).
On completion of loading, the liquid header and other liquid lines are drained
to the No 5 cargo tank. The liquid remaining in the inclined part of the liquid
manifolds is pushed inboard using nitrogen pressure from ashore and the
loading arms are then purged and disconnected. If the vessel is not sailing
immediately, the reliquefaction plant can be used to control the tank pressures
or the GCU can burn any excess boil-off gas to control the tank pressure.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 Key
Vapour Return Line LNG Liquid
LNG Vapour
CG807 CG808
Nitrogen
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.3.2 cargo lines cooldown Position Description Valve Position Description Valve
Open No.1 tank vapour valves CG170, CG171 Open Starboard liquid manifold ESD valves CL011, CL021,
Pre-cooling of Liquid Pipes Before Loading Open No.2 tank vapour valves CG270, CG271 CL031, CL041
Open No.3 tank vapour valves CG370, CG371 Open No.1 manifold cooldown valve CS061
The cargo tanks will normally be maintained at -130ºC or colder during a ballast Open No.2 manifold cooldown valve CS063
Open No.4 tank vapour valves CG470, CG471
voyage by drawing off the LNG vapour and returning the cold condensate back
Open No.5 tank vapour valves CG570, CG571 Open No.3 manifold cooldown valve CS065
to the cargo tanks via the spray main and spray nozzles after being liquefied
via the reliquefaction plant. Open Vapour main block valve to No.1 mast riser CG721 Open No.4 manifold cooldown valve CS067
Open No.1 tank liquid branch valve CL110 Open Manifold spray/liquid line cooldown valves CS051, CS052
As long as the tanks are at this temperature, the cooling down of the cargo Open No.2 tank liquid branch valve CL210
liquid lines can begin. This operation must be started in sufficient time before l) Request shore to supply LNG at a slow rate through all four
Open No.3 tank liquid branch valve CL310
loading commences with approximately 90 minutes being required, this will loading arms.
vary with terminals. Open No.4 tank liquid branch valve CL410
Open No.5 tank liquid branch valve CL510 m) The pre-cooling must be thoroughly monitored by observation
LNG is introduced into the liquid crossover and liquid header at a limited flow Open 10% No.1 tank filling valve CL100 of the temperatures and pressures. Temperature monitoring at
rate. The liquid flashes-off immediately due to the high temperature within Open 10% No.2 tank filling valve CL200 the liquid header crossover connection and at each cargo tank is
the pipes and the vapour that is generated is introduced to all of the tanks via Open 10% No.3 tank filling valve CL300 available at the DACS. As the filling valves are already open, the
the filling valves which are 10% open. The pre-cooling is then carried out as pressure in the tanks will start to rise, bringing the tank pressures
Open 10% No.4 tank filling valve CL400
follows: up together. As the pressure rises the HD compressor(s) should
Open 10% No.5 tank filling valve CL500 be started and controlled from the DACS.
Procedure for Cooling Liquid Lines g) Prepare both HD compressors for use. Adjust the set point of
Note: Ensure valve CG079 is closed once the HD compressor is started,
both HD compressors’ pressure control valve to 5kPa, or the otherwise vapour will circulate around the system.
In this case it has been assumed that the vessel is berthed starboard side required value.
alongside.
n) When the temperature at the liquid header for the tanks has
h) On the HD compressors, open the following valves:
a) Check the connection of the liquid and vapour arms, fallen to approximately -100°C, the liquid manifold double-shut
communications with shore, ship/shore electrical and pneumatic valves can be opened and the bypass valves closed.
Position Description Valve
connection and ESDS safety devices. Carry out safety tours.
Open Compressor supply from vapour header valve CG803 Position Description Valve
b) Complete the relevant ship/shore safety checklist. Open Vapour free-flow valve to vapour manifold CG079 Open No.1 starboard liquid double-shut valve CL013
Open No.1 HD compressor inlet valve CG831 Open No.2 starboard liquid double-shut valve CL023
When the shore terminal is ready to purge the manifold connections with Open No.2 HD compressor inlet valve CG841 Open No.3 starboard liquid double-shut valve CL033
nitrogen: Open No.1 HD compressor outlet valve CG832 Open No.4 starboard liquid double-shut valve CL043
Open No.2 HD compressor outlet valve CG842 Close No.1 manifold double-shut bypass valve CS061
c) Open liquid manifold ESDS valves CL011, CL021 CL031 and
CL041. Open Vapour return valve to vapour manifold CG800 Close No.2 manifold double-shut bypass valve CS063
Close No.3 manifold double-shut bypass valve CS065
d) Pressurise the loading arms and manifold, then leak test. Purge i) Open the vapour manifold ESD valve CG071 (starboard side).
This will enable a free-flow of gas to the terminal and is a check Close No.4 manifold double-shut bypass valve CS067
to atmosphere via the manifold drain valves until a reading of
that the pipeline layout on board has been arranged correctly. Close Manifold spray/liquid line cooldown valves CS051, CS052
1% oxygen is obtained, then close the ESD valves.
j) Using the DACS, adjust the set point of No.1 mast riser control Once the ship and shore pipelines have cooled down (about 90 minutes, but
e) Pressurise the vapour arm/manifold with nitrogen and leak test.
valve CG720 to the required value, for example, 23kPa, so will vary with terminals), open all of the tank filling valves fully and commence
This is carried out with the vapour manifold closed. Purge the
that this valve will remain closed during normal running of the loading at the agreed rate. As the loading rate increases the HD compressors
vapour arm to atmosphere via the manifold vent valve.
compressors, but would act in a safety capacity if necessary. should be able to limit the tank pressure to 5~10kPa gauge. Experience of the
equipment will determine if the operation of the compressors is carried out in
When it is agreed between the ship and the shore that the vessel is ready to
k) Set up the starboard manifold, numbered from forward to aft as the automatic or manual mode, low flow rates are sometimes better controlled
cool down:
follows. Most terminals only provide three chicksans, for sake in manual mode. If the compressors are unable to cope with the volume of boil-
of clarity all manifolds are used. off and displaced gas, it will be necessary to reduce the loading rate.
f) Open the tank valves in accordance with the following table:
Tank No.3
97.5% Stop Pump No.6
97.7% Stop Pump No.7
CS751 CS752 CS753 Spray After 8 to 10 Hours Start HD Compressors 1 & 2 During First 45 Minutes 98.0% Finish Cargo Tank No.3
Open 100% CS155 CS255 CS355 Isolating Cargo Tank Average Temperature -130ºC Until Terminal has all Loading Pumps Running Close CL302
CS455 CS555 Valves Stop One HD Compressor when Tank Pressure
Starts to Fall
Tank No.5
One Hour Before Finish of Cooldown 98.0%
Start Cooling Down Ship’s Liquid Line Stop Pump No.8
CS152 CS252 CS352 Less
Port Spray Drainings Finish Cargo Tank No.3
Open With all Loading Pumps Running
Valves
CS452 CS552 and at Full Loading Rate Leave Open Filling Valve CL500
Adjust Valves Position %
CL011 CL021 CL031 ESD CL102 55%
Open CL202 90%
CS063 CS065 CS067 CS751 CS752 Spray C/O CL302 80%
When Commencing Cooldown CL402 100% Loading Completed
Note: It is important to patrol the deck area to monitor for cargo leaks. All
leaks, no matter how small, must be corrected immediately, even if this
requires slowing down or stopping the loading.
The following procedures are carried out when the vessel arrives with the
tanks cool and ready for loading. There are occasions where the vessel will
arrive with the tanks gassed-up but warm, eg, where it has heeled-out due to
charterer’s requirements, and the flow chart 6.3.2b is an example for cooling
down and loading. Each vessel may produce their own sequence based on the
vessel’s experience.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Key
Closed
CG800
LNG Liquid
Vapour Return Line
LNG Vapour
Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.3.3 LoadING Cargo with Vapour Return to Shore d) On the HD compressors, open the following valves: j) Monitor the tank pressures in order to achieve a pressure of
via the High duty compressor about 5-10kPa.
Position Description Valve
It has been assumed for clarity of the following description that all of the valves Open Compressor supply from vapour header valve CG803 k) Start one of the HD compressors as necessary.
are CLOSED prior to use and that the ship is starboard side alongside.
Open Vapour free-flow valve to vapour manifold CG079
Note: Ensure valve CG079 is closed once the HD compressor is started,
Open No.1 HD compressor inlet valve CG831
otherwise vapour will circulate around the system.
Preparations Before Loading a Cargo Open No.2 HD compressor inlet valve CG841
Open No.1 HD compressor outlet valve CG832 l) Adjust the opening of the tank filling valves to maintain an even
To prepare for cargo loading operations proceed as follows:
Open No.2 HD compressor outlet valve CG842 distribution.
• Switch on the unblocking level alarms in the custody transfer Open Vapour return valve to vapour manifold CG800
system and run a custody transfer print-out for official tank m) Ease in the filling valve of each tank as the tank approaches full
gauging capacity. Arrange to terminate the tanks at 15 minute intervals.
e) Open the vapour manifold ESD valve CG071 (starboard side).
• Confirm that the cargo system has been cooled down as detailed This will enable a free-flow of gas to the terminal and is a check
in Section 6.3.2 that the pipeline layout on board has been arranged correctly. n) The level alarms will sound when the tanks are at the following
levels:
Procedure for Loading Cargo with Vapour Return • High level alarm sounds at 95%, No.1 tank 27.704m, No.2
Note: The HD compressor capacity during loading is based on an average
(See illustration 6.3.3a). tank 27.131m, No.3 tank 27.13m, No.4 tank 27.134m and
tank temperature of -130°C, initially it may be necessary to use two HD
No.5 tank 27.125m.
compressors, but by midway through the loading, normally only one HD
a) Open the tank valves in accordance with the following table.
would be used with the load steadily decreasing, the second compressor • High High level alarm sounds at 98.2%, TANK FILLING
The tank vapour valves normally remain open, but have been
remains on standby. VALVES CLOSE. No.1 tank 28.665m, No.2 tank 28.432m,
included in the table for completeness.
No.3 tank 28.429m, No.4 tank 28.434m and No.5 tank
f) Set up the starboard manifold, numbered from forward to aft as 28.428m.
b) Open the tank valves in accordance with the following table:
follows:
Position Description Valve The tanks are topped-off at 98% capacity in Nos.1, 2, 3, 4 and 5 tanks. The
Position Description Valve filling valve will be manually closed from the DACS. No.1 tank 28.603m, No2
Open No.1 tank vapour valves CG170, CG171
Open Starboard liquid manifold ESD valves CL011, CL021 tank 28.347m, No.3 tank 28.344m, No.4 tank 28.35m and No.5 tank 28.34m.
Open No.2 tank vapour valves CG270, CG271 CL031, CL041
Open No.3 tank vapour valves CG370, CG371 Open No.1 manifold double-shut valve CL013 Note: The independent extremely high level alarm will operate at 99.0%
Open No.4 tank vapour valves CG470, CG471 Open No.2 manifold double-shut valve CL023 capacity and initiate an emergency shutdown. There is a preparatory alarm at
Open No.5 tank vapour valves CG570, CG571 95% which closes the individual tank loading valve if it is still open.
Open No.3 manifold double-shut valve CL033
Open Vapour main block valve to No.1 mast riser CG721 Open No.4 manifold double-shut valve CL043
Open No.1 tank liquid branch valve CL110 CAUTION
Open No.2 tank liquid branch valve CL210 g) Request shore to supply LNG at a slow rate through all four The very high level alarms and shutdowns are emergency devices only
Open No.3 tank liquid branch valve CL310 loading arms. During the time of slow loading it is important and should on no account be used as part of the normal topping-off
to patrol the whole deck area to monitor for all potential cargo operation.
Open No.4 tank liquid branch valve CL410
leaks. All leaks, even the smallest one, must be corrected
Open No.5 tank liquid branch valve CL510 o) Before topping-off the first tank, request the shore to reduce
immediately, even if this requires slowing down or even
Open 15% No.1 tank filling valve CL100 stopping the loading. the loading rate and continue reducing when topping-off each
Open 15% No.2 tank filling valve CL200 following tank. When a tank is at its required level, close the
Open 15% No.3 tank filling valve CL300 h) Increase the loading rate in stages as agreed with the terminal at corresponding loading valve, ie:
Open 15% No.4 tank filling valve CL400 the pre-loading meeting. • Tank No.1 - CL100
Open 15% No.5 tank filling valve CL500 • Tank No.2 - CL200
i) Start the deballasting programme. Keep the draught, trim
c) Prepare both HD compressors for use. Adjust the set point of and hull stresses within permissible limits by controlling the • Tank No.3 - CL300
both HD compressors’ pressure control valve to 5kPa, or the deballasting.
• Tank No.4 - CL400
required value.
• Tank No.5 - CL500
Close Cargo FIlling Close Cargo FIlling Close Cargo FIlling Close Cargo FIlling Close Cargo FIlling
Valves Valves Valves Valves Valves
CL100 CL200 CL300 CL400 CL500
End
It is convenient to finish loading into tank No.5 for ease of line draining. Completion of Loading c) When ready to start the reliquefaction plant, SEQUENCE start
a compander to cool down the R loop until the cold box reaches
p) Slow down and stop the HD compressors as falling tank When the vapour manifold is closed for purging and disconnection the tank -150°C, this could take several hours.
pressures require. When the compressors are stopped, leave all pressure will start to rise quickly. In this situation carry out the following:
compressor valves open to free-flow vapour to shore via vapour
crossover valve CG079. a) Press the START button to start the GCU and initially free-flow
across the HD compressors and through the HD heater.
q) Stop loading when the final tank reaches 98.0% capacity minus
an allowance for line draining, and leave the tank loading valve
CL500 open. The final tank loading valve is put into MANUAL
operation to prevent inadvertent automatic closing at the 98.2%
alarm and to allow draining of the lines.
WARNING
Per the IGC Code, no cargo tank can be loaded to more than the
maximum fill limit of 98.9% capacity. If a tank is accidentally loaded
to more than 98.9% capacity, then a pump in that tank shall be used to
pump the excess LNG to another tank or back to the loading terminal
before the final CTS measurement is taken by the gauging surveyor.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 Key
Vapour Return Line LNG Liquid
LNG Vapour
CG807 CG808 Nitrogen
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.3.4 Draining and Inerting manifold pipes and b) Operate the following manually operated valves locally: j) Disconnect the vapour arm.
loading arms
Position Description Valve Note: The above are a guide, individual terminals may require a different
Open Spray header block valves CS750, CS752 disconnection sequence and procedure.
Introduction
Closed No.2 starboard manifold manual double shut- CL023
When the loading and discharge operations are completed, draining and off valve Liquid Lock Avoidance on Completion of LNG Operation
purging operations are carried out to remove all trapped liquid and vapour in Open No.2 starboard manifold cooldown valve CS063
the manifold liquid pipes and loading arms in order that the loading arms can No LNG liquid can remain enclosed in a pipe section between two valves.
be safely disconnected. The system is provided with two-valve protection to c) Request the shore terminal to start the nitrogen gas supply and There are safety relief valves fitted on the pipelines that should open and
prevent an accidental release of LNG. to raise the pressure in the liquid arm to 3 bar. That pressure is release any pressure build-up in these pipe sections to the nearest gas dome.
sufficient to force the liquid trapped in the large cargo manifold
To further prevent against accidental spillage, only one loading arm is to be piping to enter the 80mm diameter cooldown pipe, and be In order to avoid any pressure build-up and prevent the activation of the safety
disconnected at a time. The ship manifold is fitted with hinged manifold blanks, forced by the nitrogen vapour to rise up the 5 metre high vertical valve, both the liquid and spray header valves are left open to the cargo tanks
which allow the blank flange to easily and quickly be swung into position after cooldown pipe into the spray main and flow into cargo tank to allow any trapped liquid to flash-off as the lines warm-up. Once the operator
the loading arm is disconnected. The gasket must be installed and at least four No.5. is happy that there is no liquid remaining, the valves can be closed.
bolts inserted and tightened in the blank flange before the next loading arm can
be disconnected. The ship’s staff are to complete the bolting of the blank flange It should take about 5 minutes to blow the liquid up the cooldown pipe. When Position Description Valve
at the same time the next loading arm is being disconnected. the pressure in the liquid arms suddenly decreases to about 40kPa (0.04MPa), Open No.1 tank filling valve CL100
it indicates the liquid has been forced up and out of the large manifold pipes.
Open No.2 tank filling valve CL200
The cargo manifold is located about 5 metres below the crossover piping on Continue the nitrogen purge for one minute, then close manual manifold
this ship so the trapped LNG cannot drain by gravity to the cargo tanks. double-shut bypass valve CS063. Open No.3 tank filling valve CL300
Open No.4 tank filling valve CL400
Nitrogen vapour from the shore terminal is used to blow the LNG liquid Check for remaining LNG liquid by opening the liquid manifold manual drain Open No.5 tank filling valve CL500
and vapour in the liquid arms and ship manifold piping to the ship’s cargo valves. Open No.5 tank branch valve CL510
tanks through the 80mm diameter spray piping system connecting the cargo
Open Stripping main block valves CS750 CS751,
manifolds to the cargo tanks. If LNG liquid is still in the pipe, repeat the above operations. CS752,CS501
CS502
Vapour in the vapour manifold is blown to the cargo tanks through the vapour d) When hydrocarbon readings obtained from a portable meter
header by nitrogen gas supplied from the shore terminal. Open Stripping header spray master valves CS155, CS255
are less than 1.0% HC by volume at the vent cocks, close the
CS355, CS455
liquid manifold ESD valve CL013 and the manifold double-shut
CS555
bypass valve CS063.
Operation Procedure Open No.5 tank stripping return valve CS554
e) Request the shore terminal to stop the nitrogen supply. Open Manifold cooldown valves (starboard) CS061, CS063
The procedure described below is based on draining and inerting the starboard
CS065, CS067
side No.2 cargo manifold to cargo tank No.5.
f) Slowly open the liquid manifold manual drain valves to ensure Open Manifold double-shut valves (starboard) CL013, CL023
a) Operate the following valves from the DACS: the pressure in the arm is at atmospheric, then close the valves CL033, CL043
and advise the shore terminal it is safe to disconnect the loading
arm.
Position Description Valve
Open No.5 tank filling valve CL500 g) Repeat the above operation for each loading arm and manifold.
Open No.5 tank spray master valve CS555
Open No.5 tank spray return valve CS554 h) When all the liquid lines have been purged and disconnected,
Open No.5 tank spray/liquid line valve CS556 shut the ESD valve CG071 on the vapour manifold and open the
vapour bypass valve CG077.
Open No.2 starboard manifold ESD valve CL021
i) Request shore to purge with nitrogen until the portable meters
read less than 1% HC by volume, close the vapour bypass valve
CG077.
WBV091 PI CP
WBV331 WBV WBV WBV WBV WBV WBV LCAL
373
WBV343
WBV
Water Spray Pump WBV WBV LIAHL LIAHL LIAHL LIAHL LIAHL LIAHL
377
WBV 371 372
378 Sea Sea
WBV348 WBV347 WBV346 LX LX LX LX LX LX
Chest Chest
High Low No.5 Water Ballast Tank No.4 Water Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1b Water No.1a Water
(Starboard) (Starboard) (Starboard) (Starboard) Ballast Tank Ballast Tank
(Starboard) (Starboard)
Key
Sea Water
Hydraulic Oil
Electrical Signal
Instrumentation
b) Open the valves on the tank(s) to be emptied as per the Note: The pipeline configuration allows for a combination of 1, 2 or 3 ballast c) Open the discharge valve on the pumps in use in accordance
deballasting plan, ensuring that the vessel remains upright and pumps to be used for discharging ballast via one or both overboard discharge with the following:
stability is within the acceptable limits at all times. valves. Normally a maximum of two pumps would be used, No.1 and No.3
for the following example. Position Description Valve
Description Valve Open No.1 ballast pump discharge valve WBV314
Position Description Valve
Forward water ballast tank (C) valves WBV022 Open No.3 ballast pump discharge valve WBV334
Open No.1 ballast pump suction valve WBV311
WBV050
Open No.3 ballast pump suction valve WBV331 Ensure that ballast lines are not put under vacuum when changing from one set
No.1A ballast tank (port) valves WBV211
WBV212 Closed Ballast pump discharge to ballast main valves WBV335 of tanks to another by opening the next set of tanks before those currently in
WBV315 use reach the final level.
No.1A ballast tank (starboard) valves WBV111
WBV112
b) Confirm that the required ballast tank valves are open in Note: The ballast main pressures are monitored via the DACS and pressure
No.1B ballast tank (port) valves WBV213
accordance with the ballast plan, then from the DACS start the and vacuum alarms are also provided in the DACS. Tank valves are
WBV214
ballast pump(s). interlocked with the four level switches in the ballast ring main.
No.1B ballast tank (starboard) valves WBV113
WBV114 d) When the suction has been lost on all tanks, stop the pumps and
close the main ballast system down.
WBV091 PI CP
WBV331 WBV WBV WBV WBV WBV WBV LCAL
373
WBV343
WBV
Water Spray Pump WBV WBV LIAHL LIAHL LIAHL LIAHL LIAHL LIAHL
377
WBV 371 372
378 Sea Sea
WBV348 WBV347 WBV346 LX LX LX LX LX LX
Chest Chest
High Low No.5 Water Ballast Tank No.4 Water Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1b Water No.1a Water
(Starboard) (Starboard) (Starboard) (Starboard) Ballast Tank Ballast Tank
(Starboard) (Starboard)
Key
Sea Water
Hydraulic Oil
Electrical Signal
Instrumentation
Position Description Valve c) Open the suction valve on first tank to be stripped. (Water
ballast tanks 1 to 5 have two suctions, the after most suction
Closed No.1 ballast pump discharge valve WBV314
would normally be used for draining, the forward water ballast
Closed No.3 ballast pump discharge valve WBV334 tank has a suction direct from the starboard main and also one
Closed No.1 ballast pump suction valve WBV311 from the port main, the fore and aft peak tanks have a single
Closed No.3 ballast pump suction valve WBV331 suction.)
Closed Ballast main crossover valves WBV361
WBV362 Description Valve
Closed Ballast discharge valves to high overboard WBV365 Forward water ballast tank (C) suction valves WBV022
WBV366 WBV050
Closed Ballast high overboard discharge valve WBV378 No.1A ballast tank (port) aft suction valve WBV212
No.1A ballast tank (starboard) aft suction valve WBV112
e) Strip the ballast tanks as required, it may be necessary to do this
No.1B ballast tank (port) aft suction valve WBV214
after sailing (see below).
No.1B ballast tank (starboard) aft suction valve WBV114
Note: The pipeline configuration allows for a combination of 1, 2 or 3 ballast No.2 ballast tank (port) aft suction valve WBV222
pumps to be used during bulk discharge. No.2 ballast tank (starboard) aft suction valve WBV122
No.3 ballast tank (port) aft suction valve WBV232
No.3 ballast tank (starboard) aft suction valve WBV132
Operating Procedure to Strip the Ballast Tanks Using a Ballast
No.4 ballast tank (port) aft suction valve WBV242
Eductor
No.4 ballast tank (starboard) aft suction valve WBV142
The ballast eductor drive water is supplied from the 900m³/h water spray No.5 ballast tank (port) aft suction valve WBV252
pump. No.5 ballast tank (starboard) valve WBV152
Aft peak suction valve WBV091
a) From the DACS, set up ballast eductor using the water spray
pump to supply the drive water.
d) Start the water spray pump to supply the eductors.
Position Description Valve
e) When all of the tanks have been stripped, stop the water spray
Open Water spray suction valve (normally open) WBV348
pump and close the eductor system down.
Open Water spray discharge valve WBV347
Open No.1 eductor drive inlet valve WBV343 Position Description Valve
Open No.2 eductor drive inlet valve WBV353 Close No.1 eductor drive inlet valve WBV343
Open No.1 eductor drive outlet valve WBV344 Close No.2 eductor drive inlet valve WBV353
Open No.2 eductor drive outlet valve WBV354 Close No.1 eductor drive outlet valve WBV344
Open Eductor overboard discharge valve WBV377 Close No.2 eductor drive outlet valve WBV354
Close Eductor overboard discharge valve WBV377
b) From the DACS, set up the ballast main for educting.
Close No.1 ballast eductor suction valve WBV341
Position Description Valve Close No.2 ballast eductor suction valve WBV351
Open No.1 ballast eductor suction valve WBV341
Open No.1 ballast eductor suction valve WBV351
Note: One eductor can be used on both the port and starboard ballast mains
by opening the eductor suction crossover valve WBV345.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 LNG Liquid
Vapour Return Line LNG Vapour
Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.4 loaded voyage with Boil-off Gas the same capacity and load-share. The transition between single control and Position Description Valve
reliquefaction master control with two compressors running is done by a time-based ramp.
Open No.1 tank vapour valves CG170, CG171
Where the BOG compressors are unable to contain the tank pressure with Open No.2 tank vapour valves CG270, CG271
6.4.1 loaded voyage with Boil-Off Gas reliquefaction alone, the excess BOG is passed through the BOG heater prior Open No.3 tank vapour valves CG370, CG371
reliquefaction to being burnt in the GCU. Open No.4 tank vapour valves CG470, CG471
Open No.5 tank vapour valves CG570, CG571
Introduction Gas Combustion Unit Open Vapour header valve to No.1 vent mast riser CG721
Manufacturer: Hamworthy Combustion Engineering Ltd. Automatic No.1 vent mast riser control valve set to CG720
The gas control system automatically controls the pressure within the cargo
Model: AMOxsafe 23kPa
tanks using one or both of the boil-off gas (BOG) compressors. Depending
on the amount of BOG generated it may be necessary to use both BOG Quantity: 1
b) Set up to supply vapour to the BOG compressors.
compressors and the gas combustion unit (GCU) to control the pressure in the BOG firing rate: 0~3,111kg/h (one fan running- GCU load 0-55%)
tanks between 5kPag and 19kPag. 0~5,657kg/h (two fans running- GCU load 0-100%) There is a starting interlock on all of the compressors which prevents them
0~850kg/h (free-flow mode) from going on standby if the diffuser guide vanes (DGV) are not in the fully
BOG Compressors BOG supply pressure: 3.3 bar closed position (to prevent an overcurrent trip). Start the compressor with the
DGV closed and interlock for the anti-surge valve which must be open, then
Furnace temperature: 450°C
Manufacturer: Atlas Copco Energas GmbH adjust the set point to 60%.
Exhaust gas temperature: 535°C (maximum)
Type: GT 026 T2 K2
Quantity: 2 Position Description Valve
During the voyage, the liquid cargo will start to boil-off into vapour. This
Mass flow: 6793kg/h Open Crossover from vapour header to BOG CG801
vapour is drawn off from the cargo tanks by the BOG cargo compressors.
compressors
Design pressure: 1MPa From the BOG compressor, the LNG vapour, at high temperature and pressure,
passes to the cryogenic heat exchanger in the cold box where it is turned into Open No.1 BOG compressor inlet valve RG821
Design temperature: -170/+100ºC
liquid by the colder nitrogen passing through the cryogenic heat exchanger Open No.2 BOG compressor inlet valve RG822
Motor: 460kW (rated duty), constant speed
tubes. This cold liquid leaves the cold box via a separator to the LNG transfer Open No.1 BOG compressor bypass valve RG815
pumps where it is returned to the cargo tanks via the return condensate line to
No.4 and No.5 cargo tank bottoms, and/or to the spray main to be returned to Open No.2 BOG compressor bypass valve RG816
One Running Compressor (0% -100% Boil-off Rate)
the tanks via the spray return line. Automatic No.1 BOG compressor bypass control valve RG809
Each BOG compressor is a two-stage centrifugal compressor with diffuser
guide vanes (DGV) on each stage for controlling the compressor capacity. Automatic No.1 BOG compressor bypass control valve RG810
Once the vessel departs the loading port the reliquefaction plant will be
When one compressor is running, the suction pressure controller will modulate Open No.1 BOG compressor outlet valve RG803
required to maintain the cargo as close to its loading temperature and pressure
the recycle valve and the DGVs to control the pressure in the cargo tanks. If
as possible for the duration of the laden passage. These compressors will have Open No.2 BOG compressor outlet valve RG804
the cargo tank pressure increases above the set point, the recycle valve closes
been started at the load port by the reliquefaction plant control system, the Open Inlet valve to cryogenic heat exchanger RG825
and the DGVs will open in a split range arrangement. The DGVs will not start
valves required for this operation are listed below.
to open until the recycle valve is fully closed. The BOG compressor is running
at 100% capacity when the DGVs are fully open. c) Set up to supply condensate to the cargo tanks via the LNG
The reliquefaction plant and its operations have been described in greater detail
transfer pumps.
in Section 4.7 of this manual.
When the suction pressure drops below the set point the DGVs will close and
then the recycle valve will open in a split range arrangement. The recycle valve Position Description Valve
will not start to open until the DGVs are fully closed unless overridden by the Operating Procedures with Natural Boil-Off Gas Open No.1 LNG transfer pump inlet valve RL848
anti-surge control function.
During local operation, all alarms and trips are available and can be monitored Open No.2 LNG transfer pump inlet valve RL849
Two Running Compressors (100 – 150% Boil-off Rate) through the DACS. Open No.1 LNG transfer pump outlet valve RL810
Open No.2 LNG transfer pump outlet valve RL809
When two BOG compressors are running at the same time, one master a) Confirm the vapour dome outlet valves to the vapour header are
controller will be controlling the pressure in the cargo tanks. The ‘lead’ Open Condensate return control isolation valves RL822, RL824
open; these valves are normally always open.
compressor controller will then take the function as the master controller and Automatic Condensate return control valve RL823
the ‘lag’ compressor’s controller will be disabled. The output signal of the
Open Pre-cooler control isolation valves RL819, RL817
master controller will be sent to both compressors which will then operate at
Illustration 6.4.1b Loaded Voyage with Boil-Off Gas Reliquefaction - Excess BOG
Gas
Manifold
Combustion
Unit CG901 RG842 RG843 RG827 CL012 CL014 CL013 CL011
Vent Gas Heater
Safety Valve RR808
Header RG844 RG826 RG845 Port Forward Starboard
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed LNG Liquid
CG800
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
Position Description Valve b) Ensure that the gas outlet temperature of the heater is set to Position Description Valve
approximately 25°C.
Automatic Pre-cooler control valve RL818 Automatic Cold box separator waste gas control valve RG826
Open Pre-cooler supply valve RL815 The cargo reliquefaction and gas burning piping system is arranged so that Open Vent gas heater inlet valve RG843
Open Condensate return to spray main CR863 excess boil-off gas can be vented should there be any inadvertent stopping of Open Vent gas heater temperature controller RG848, RG849
the pressure control systems. The automatic control valve CG720 at the No.1 isolation valves
Open Condensate return to No.4 and No.5 cargo CR862
vent mast is set to operate at 23kPa and vents any excess gas to atmosphere. Automatic Vent gas heater temperature control valve RG847
tanks
Open No.4 cargo tank condensate return valve CR460 Open Vent gas heater outlet valve RL842
Note: It is possible for the operator to alter the setting of the forward vent Automatic GCU inlet valve CG901
Open No.5 cargo tank condensate return valve CR560 mast control valve from the DACS.
Open No.3 spray master and spray return valves CS355, CS354 b) Set up to supply waste gas to the cargo tanks via the liquid
Open No.2 spray master and spray return valves CS255, CS254 In the event of an automatic or manual shutdown of the pressure control system, header.
or if the tank pressure falls to 2kPa above the insulation spaces pressure, the
Open No.1 spray master and spray return valves CS155, CS254 following safety procedures are activated:
Open Spray main block valve CS752 Position Description Valve
• GCU master valves CG900 and CG901 will close and the gas Open Cold box separator waste gas outlet to liquid RG827
supply line to the GCU will be purged with nitrogen, exhausting header valve
Note: The LNG condensate can be returned to the bottom of the No.4 and to No.5 vent mast via the GCU nitrogen scavenging line and a
No.5 cargo tanks and/or to the spray main where it can be distributed back to non-return valve at the vent mast. Open Waste gas to liquid header valve CG802
any one of the five tanks via the spray return. Open No.5 cargo tank spray master valve CL555
• Reliquefaction plant goes to standby mode.
Open 10% No.5 cargo tank filling valve CL500
Note: If the volume of the boil-off gas exceeds the capacity of the • BOG compressors stop.
reliquefaction plant, the GCU has to be put into operation. • Waste gas valve switches to tanks.
Personnel should always be present when the heater is put into operation, to Position Description Valve
locally monitor the temperature in the steam exhaust line and the vapour outlet. Open Cold box separator waste gas outlet RG844, RG845
During local operation all monitoring facilities are available via the DACS isolation valves
display screens.
6.5.6 Ballasting
Al Sahla Cargo Operating Manual
Arrival
Secure ship at jetty Main propulsion on standby
Hand over crew list Ship advises terminal of readiness
Pilot/loading master advises
Display appropriate signage Cool Down to start cool down of loading arms
terminal on completion
Cool down unloading arms
Use of main communication CCR advises terminal and sends
Equipment and radars prohibited Terminal advises ship when ready low flow of cargo via cargo pump
Hot work prohibited
Observe port regulations Cool all arms simultaneously
until frosted over entire length
Continuously check mooring tension Operation controlled by loading
master (approx. 45/90 minutes)
Rig
Witness and check rigging of ESD Test
Gangway Terminal staff gangway (Cold) Terminal advises ship when ready Initiate ESD1 signal from ship/shore
Witness and log ESD1 operation Witness and log ESD1 operation
of all shore valves of all ship's valves
Safety
Carry out safety inspection Carry out safety inspection
Inspection
Complete and sign safety checklist Complete and sign safety checklist
Check O2 levels at sampling points Safety Carry out safety checks jointly Check through terminal safety
Checks with ship checks jointly with terminal staff
Pre-discharge
Terminal staff Relevant ship's personnel
Meeting
Review discharge schedule Review discharge schedule
Confirm safety checks Confirm safety checks
Ready For Discharging
Connect
Arms Vapour return arm connected first Start manifold water curtain
followed by the loading arms Discharge strainers in place
Position safety locks Manifold blanks removed
Pressure test with N2
Inert to <1% O2
Connect ESD/Communications link
6.5 discharging The cargo pumps can discharge each tank to a level of approximately 0.3m b) Select and start a BOG compressor to supply boil-off gas to
where the discharge is based on using only the cargo pumps. One of the two the GCU via the BOG heater, stop the free-flow via the HD
pumps in each tank is stopped at a level of approximately 1.0 to 0.6m to avoid compressors.
Introduction excessive turbulence at the tank bottom which can create a disturbance at the
suction of both pumps. Discharge is continued with one pump, throttling-in c) When ready to start the reliquefaction plant, SEQUENCE start
In co-ordinating LNG operations, the ship must be compatible with the shore on the discharge valve to maintain the current until the pump stops on low a compander to cool down the R loop until the cold box reaches
side terminals. The ship and shore-based personnel must also be familiar with discharge pressure cut-out or low current. -150°C, this could take several hours.
each other’s equipment and the division of all of the responsibilities.
Where the requirements are for the vessel to heel out, the stripping pump is run d) STOP the BOG compressor and free-flow to the GCU across
Each terminal has its own procedures which have to be strictly followed together with the remaining main pump from the 1 metre level until the main the HD compressors while setting up to start the reliquefaction
regarding the following operations: pump stops on low discharge pressure cut-out or low current. The vessel can plant.
• Approaching the terminal continue the discharge to a level of approximately 0.08m in each tank with a
3.0m trim using the stripping/spray pumps. e) Start the reliquefaction plant as per the section under REMOTE
• Mooring
OPERATION OF RELIQUEFACTION PLANT, Section 4.7,
• Connecting On completion of the discharge, the loading arms and pipelines are purged page 14.
and drained to the No.5 cargo tank and the arms are then gas freed and
• Loading disconnected.
6.5.1 PreparationS for discharging
• Disconnecting
Due to the manifold configuration it is necessary to purge the cargo lines using Preliminary Preparation:
• Departure
nitrogen at a pressure of at least 3 bar. This is done several times to ensure
successful draining at the manifold connections. • The chief officer is to prepare a detailed discharge and ballasting
During a normal discharge, only the main cargo pumps will be used and a plan which includes the trim and stability conditions during
quantity of cargo will be retained on board for maintaining the tanks in a discharge.
The vapour arm is normally disconnected and the resumption of reliquefaction
cold condition. The quantity being retained in the tanks varies according to
will cope with any vapour evolution. • The pre-arrival checklists are to be completed.
the charterer’s requirements and will be influenced by the operations of the
reliquefaction plant. • A pre-discharge meeting is to be held together with the terminal
When the vapour manifold is disconnected the tank pressure will start to rise
quickly. In this situation carry out the following: representatives. The ship/shore safety list is to be filled in.
If the ship has to warm-up tanks for technical reasons, the stripping/spray
• The custody transfer measurement (CTM) is to be carried out
pumps will be used to discharge the remaining cargo on completion of the bulk
a) Press the START button to start the GCU and initially free-flow with the terminal representatives, surveyors and authorities.
discharge with the main cargo pumps.
across the HD compressors and through the HD heater.
• All connections (bonding wire, telephones, loading and
During the cargo discharge, LNG vapour will be returned from the shore bunkering arms) at the manifold are to be carried out according
terminal to maintain the correct pressure in the cargo tanks. to the terminal’s cargo handling manual.
• The chief officer is to supervise all of the discharge operations
Operation on board.
• The sounding, temperature and pressure on all cargo tanks is
The main cargo pumps discharge LNG to the main liquid header and then to to be checked and noted according to the schedule during the
shore via the amidships liquid crossover manifold connections. Should the unloading. The Cargo Monitoring Record is to be filled in.
vapour return from the shore be insufficient to maintain the tank pressures,
other means of supplying vapour to the tanks either by using the tank sprays or • The vessel’s lines are to be made ready to allow cooldown of the
the main vaporiser have to be used. discharging arms.
During the discharge period, the ship is kept on an even keel. If it is necessary
to empty a cargo tank, the ship needs to be trimmed according to the terminal’s
maximum draught by the stern to assist in the stripping of the tank.
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked Key
Closed
CG800
LNG Liquid
LNG Vapour
Vapour Return Line Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.5.2 Liquid Line Cool down Before discharging c) Prepare the manifold for cooling down. f) Using the No.3 tank spray pump, LNG is passed via the spray
header to the manifold and then through the spray line to the
Position Description Valve liquid header crossover valves into the liquid header, returning
Introduction to No.3 cargo tank via the loading line.
Open Manifold spray to liquid header valves CS051, CS052
The cargo lines are cooled down and the cargo plant is prepared to the highest g) From the DACS, start No.3 spray pump to allow cooldown to
possible level before arrival at the loading or discharging port. This is to allow d) Confirm that the vapour header valves are open.
commence.
the discharging to commence as soon as the vessel is moored and all procedures
have been completed. The spool pieces and reducers with their required filters Position Description Valve h) As cooldown of the header progresses, open and close each
are to be mounted. Open No.1 tank vapour valves CG170, CG171 of the tank loading valves in turn to permit cooldown of the
Open No.2 tank vapour valves CG270, CG271 complete liquid header.
The liquid line cooldown is carried out using the spray pump in No.3 tank
to pump LNG from No.3 cargo tank through the spray header to the liquid Open No.3 tank vapour valves CG370, CG371
Open No.4 tank vapour valves CG470, CG471 i) During line cooldown, monitor the following:
manifold pipework.
Open No.5 tank vapour valves CG570, CG571 • Cargo tank levels
Vapour displaced from the crossover pipework passes through the liquid header Open Vapour header valve to No.1 vent mast riser CG721 • Liquid crossover pressure
and then back to No.3 cargo tank via the filling line.
Automatic No.1 vent mast riser control valve set to CG720 • Liquid crossover temperature
23kPa
Vapour from the tanks will be supplied to the BOG compressors for • Liquid header temperature
reliquefaction and returned to the No.4 or No.5 cargo tanks as condensate.
e) Set up to supply vapour to the BOG compressors and LNG • Vapour header pressure
Although the text and illustration above indicates No.3 spray pump being used transfer pumps.
for cooldown, any of the spray pumps could be used if required. j) The line cooldown will be complete when the liquid header
Position Description Valve temperature falls below -100°C and frosting occurs at the
Open Crossover valve from vapour header to BOG CG801 loading valves.
Operating Procedure to Cool Down the Liquid Lines compressors
k) When the cooldown is completed, stop the No.3 spray pump
Open No.1 BOG compressor inlet valve RG821
a) Prepare the spray header system for cooling down. from the DACS.
(See illustration 6.5.2a). Open No.2 BOG compressor inlet valve RG822
Open No.1 BOG compressor bypass valve RG815 Position Description Valve
Position Description Valve Open No.2 BOG compressor bypass valve RG816 Closed No.3 spray pump discharge CS350
Open No.3 spray pump discharge valve CS350 Automatic No.1 BOG compressor bypass control valve RG809
approximately 15% l) If the time between cooldown completion and berthing is
Automatic No.1 BOG compressor bypass control valve RG810
Open No.3 tank spray master to spray main CS355 lengthy, the spray pump may be restarted.
Open Spray header block valves CS751, CS750 Open No.1 BOG compressor outlet valve RG803
Open Spray pump return valve to No.3 tank CS354 Open No.2 BOG compressor outlet valve RG804 Note: Return of cooldown liquid to the bottom of the tank via the loading line
Open Inlet valve to cryogenic heat exchanger RG825 can give rise to a localised temperature increase at the tank bottom sensor.
Sufficient time should be allowed for this to stabilise prior to gauging.
b) Prepare the liquid header system for cooling down. Open No.1 LNG transfer pump inlet valve RL848
Open No.2 LNG transfer pump inlet valve RL849
Position Description Valve Open No.1 LNG transfer pump outlet valve RL810
Open No.1 tank liquid branch valve CL110 Open No.2 LNG transfer pump outlet valve RL809
Open No.2 tank liquid branch valve CL210
Open Condensate return control isolation valves RL822, RL824
Open No.3 tank liquid branch valve CL310
Automatic Condensate return control valve RL823
Open No.4 tank liquid branch valve CL410
Open No.5 tank liquid branch valve CL510 Open Condensate return to No.4 and No.5 cargo CR862
tanks
Open 10% No.3 tank filling valve CL300
Open No.4 cargo tank condensate return valve CR460
Open No.5 cargo tank condensate return valve CR560
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked Key
Closed
CG800
LNG Liquid
Vapour Return Line
LNG Vapour
Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.5.3 Arm Cool down before Discharging Position Description Valve Operating Procedure for Cooling Down the Shore Liquid Arms
Open No.4 manifold cooldown valve CS067 Using a Cargo Pump
Introduction Open No.1 ESD liquid manifold valve CL011
On completion of testing the discharge arm connections, the vessel uses one
Open No.2 ESD liquid manifold valve CL021 main cargo pump circulating on its own tank to cool down the shore arms.
After the discharging arms are connected to the ship’s manifold, they are Open No.3 ESD liquid manifold valve CL031
pressurised with nitrogen and purged to atmosphere until the oxygen content is Where pre-cooling of the ship’s liquid line has not been carried out this can be
below 1%. The nitrogen is delivered from the shore at a pressure of up to 3 bar. Open No.4 ESD liquid manifold valve CL041 done at the same time as the shore arms.
The connections are then tested for leaks using soapy water.
c) From the DACS, start No.3 spray pump circulating on No.3 a) Set up the starboard main cargo pump in No.2 tank ready to cool
The cooldown procedure of the discharging arms follows the terminal’s cargo tank. down the shore arms and manifolds via the double-shut bypass
procedure and is carried out using the ship’s spray pump or a cargo pump, valves. The starboard side is to be used.
in co-operation with the shore terminal. Reference should be made to the d) Adjust No.3 spray pump return valve to pressurise the spray line
terminal’s cargo operation manual. and starboard manifold. Position Description Valve
Open No.2 starboard cargo pump discharge valve CL201
The ship/shore safety checks must have been completed, custody transfer e) Once the shore arms start to show frosting, crack open the 20%
completed and the ship/shore vapour line opened. double-shut valves to remove any vapour lock.
Open No.2 cargo tank filling valve 20% CL200
Open No.2 tank liquid branch valve CL210
Position Description Valve
Operating Procedure for Cooling Down the Shore Liquid Arms Open 5% No.1 starboard manifold double-shut valve CL013
Using a Spray Pump Open 5% No.2 starboard manifold double-shut valve CL023 b) Open the starboard manifold ESD and double-shut valves ready
to cool down the shore arms.
Open 5% No.3 starboard manifold double-shut valve CL033
On completion of testing the discharge arm connections, the vessel uses one Open 5% No.4 starboard manifold double-shut valve CL043
spray pump circulating on its own tank to cool down the shore arms. Where Position Description Valve
pre-cooling of the ship’s liquid line has not been carried out this can be done Open No.1 starboard manifold double-shut valve CL013
f) The cooling down is complete when the manifold, ship’s liquid
at the same time as the shore arms. Open No.2 starboard manifold double-shut valve CL023
line and shore arms are approximately -130°C. This will take
approximately 80 minutes but will vary with terminals. Once the Open No.3 starboard manifold double-shut valve CL033
For the purposes of clarity all four manifolds are shown in use. The manifolds
shore arms have been cooled down fully, open the double-shut Open No.4 starboard manifold double-shut valve CL043
used will depend on the requirements of the terminal being discharged at.
valves and close the manifold double-shut bypass valves.
Open No.1 ESD liquid manifold valve CL011
a) Set up No.3 spray pump ready to cool down the shore arms and Open No.2 ESD liquid manifold valve CL021
manifolds via the double-shut bypass valves. The starboard side Position Description Valve
Open No.3 ESD liquid manifold valve CL031
is to be used. Closed No.1 manifold cooldown valve CS061
Open No.4 ESD liquid manifold valve CL041
Closed No.2 manifold cooldown valve CS063
Position Description Valve Closed No.3 manifold cooldown valve CS065 c) From the DACS, start No.2 starboard cargo pump circulating
Open No.3 spray pump discharge valve CS350 Closed No.4 manifold cooldown valve CS067 on No.2 cargo tank. Adjust No.2 loading valve to pressurise
approximately 15% Open No.1 starboard manifold double-shut valve CL013 the liquid line and starboard manifold. Monitor the progress of
Open No.3 tank spray master to spray main CS355 Open No.2 starboard manifold double-shut valve CL023 frosting on the shore arms.
Open Spray header block valve CS751 Open No.3 starboard manifold double-shut valve CL033
d) The cooling down is complete when the manifold, ship’s liquid
Open Spray pump return valve to No.3 tank CS354 Open No.4 starboard manifold double-shut valve CL043 line and shore arms are approximately -130°C. This will take
approximately 80 minutes but will vary between terminals.
b) Prepare the starboard manifold ready to cool down the shore g) Stop No.3 spray pump and open the pump return valve to drain
arms. spray header back to tank. e) Stop No.2 cargo pump ready for an ESD test.
Position Description Valve Position Description Valve On completion of the cooldown and when the shore facility is ready for
Open No.1 manifold cooldown valve CS061 Open Spray pump return valve to No.3 tank CS354 discharge, proceed as outlined in Section 6.5.4 of this manual for discharging.
The terminal will require the vessel to carry out a cold ESD test on completion
Open No.2 manifold cooldown valve CS063
of the arm cooldown.
Open No.3 manifold cooldown valve CS065
RL848
RL849
RL813
RG846 CS062 CS061
CS051
To and From RG809 RG815
Reliquefaction LNG Separator
Plant
RG850 CL022 CL024 CL023 CL021
RG848
RG849
RG825 RG803 RG801 1st 2nd RG821
Cold Box No.1 BOG Compressor
CS052
No.1 No.2
CS064 CS063
CG880
Gas
RL808
RL807
RL830
CG852 CG854 RG847 LNG Transfer
Combustion RG810 RG816 Pumps
Unit CG900
CG883
CG072 CG071
RL810
RL809
BOG Heater RG804 RG802 1st 2nd RG822
CG855 CG851 No.2 BOG Compressor CG077
CG078
CS066 CS065
CG881
CG862 CG864
CG834 RL820 RL815
CG882
RL818 RL819
RL822
CG865 CG861 CG832 CG833 CG831
No.1 HD Compressor Pre-Cooler
CG079
CS750
RL816
RL821
CG821
CS068 CS067
CG844
RL817
RL824 RL823
CL042 CL044 CL043 CL041
LNG Vaporiser
CS871
CS872
Locked
Closed
CG800 LNG Liquid
Vapour Return Line LNG Vapour
Nitrogen
CG807 CG808
CG809
Dry-Air Supply
CG802
CG804
CS757
CG803
CS756
CG801
CG806
CG805
CL702
CG721
CG722
Liquid Main
CS752 CS751
CR862
SAS551
SAS451
SAS351
SAS251
SAS151
CG720
CS555
CS455
CS355
CS255
CS155
CL510
CL410
CL310
CL210
CL110
CG571
CG471
CG371
CG271
CG171
CS556
CS456
CS356
CS256
CS156
CR560
CR460
CS554
CS454
CS354
CS254
CS154
CGR502 CGR402 CGR302 CGR202 CGR102
CS550 CS557
CS450 CS457
CS350 CS357
CS250 CS257
CS150 CS157
CL508
CL501
CL408
CL308
CL208
CL401
CL301
CL201
CL108
CL101
CGR501 CGR401 CGR301 CGR201 CGR101
CG570
CG470
CG370
CG270
CG170
CS551
CS552
CS451
CS452
CS351
CS252
CS251
CS152
CS151
CL507
CL502
CL500
CL407
CL402
CL400
CL307
CL302
CL300
C3352
CL207
CL202
CL200
CL107
CL102
CL100
Port Port Port Port Port
CL503
CL404
CL403
CL304
CL303
CL204
CL203
CL104
CL103
No.5 Tank No.4 Tank No.3 Tank No.2 Tank No.1 Tank
No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S) No.2(P) No.1(S)
Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump Cargo Pumps Spray Pump
6.5.4 Discharging with Vapour Return From Shore f) Start the remainder of the cargo pumps according to shore Liquid Lock Avoidance on Completion of LNG Operation
terminal instructions.
No LNG liquid can remain enclosed in a pipe section between two valves.
Introduction g) Once all the pumps are in operation adjust the discharge valves There are safety relief valves fitted on the pipelines that should open and
to obtain the required full rate. This is normally 80% load with release any pressure build-up in these pipe sections to the nearest gas dome.
This section follows on from the completion of loading arm cooldown and an ammeter reading of 42- 44 amps.
either starts with a cold ESD test or starting of the cargo pumps. In order to avoid any pressure build-up and prevent the activation of the safety
h) Request the shore terminal to supply return gas to the ship to valve, both the liquid and spray header valves are left open to the cargo tanks.
a) On completion of a cold ESD test, operate the following maintain a tank pressure of between 7 and 9kPa.
valves:
Position Description Valve
Completion of Discharge Open No.1 tank filling valve CL100
Position Description Valve
Open No.2 tank filling valve CL200
Open Manifold liquid ESD valves CL011, CL021
CL031, CL041 Towards the end of the discharge, the flow of the pumps will diminish. In Open No.3 tank filling valve CL300
order to maintain the pressure differential over the pump, the discharge valve Open No.4 tank filling valve CL400
Open Double-shut valves CL013, CL023
will have to be throttled-in to maintain about 35 amps. When the level in the
CL033, CL043 Open No.5 tank filling valve CL500
tank approaches 1 metre, stop one pump and continue to discharge with the
Open Manifold vapour ESD valve CG071 remaining pump. Open No.5 tank branch valve CL510
Open Vapour manifold block valve CG079 Open Liquid spray block valves CS751, CS750
Open Cargo tank liquid branch valves CL110, CL210 If any fluctuations are observed on the motor ammeter or the pump discharge CS703, CS051
CL310, CL410 pressure gauge during final pumping, the discharge flow rate should be further Open Liquid spray cooldown valve CS052
CL510 reduced until the readings stabilise. When the flow is throttled-down to the Open Spray master valves CS155, CS255
minimum continuous flow of 511m³/h, the required non-pumpable suction CS355, CS455
Discharge will commence from No.5 tank, then No.4 tank, followed by No.3 height (NPSH) will be about 50cms. This level represents the minimum level CS555
tank, No.2 tank and No.1 tank. attained by pumping. Artificially increasing the tank pressure can help to
Open No.5 tank spray return valve CS554
reduce the NPSH (see SIGGTO Liquified Gas Handling Principles).
Open Manifold cooldown valves (starboard) CS061, CS063
b) Open the discharge valve for No.5 starboard cargo pump,
Subject to trading patterns and charterer’s requirements a heel may be required CS065, CS067
CL501, 20% and start the cargo pump.
for maintaining the tank temperatures during the ballast voyage. The actual Open Manifold double-shut valves (starboard) CL013, CL023
quantity is allowed for in the discharge plan and the pumps are to be stopped CL033, CL043
Note: Check the pump motor ammeter carefully, the current should be steady
after the motor has been running for 3 seconds. During starting, while the at the required ullages.
discharge line is being filled, the current reading may be above normal.
Note: When the liquid level reaches 2 metres or less, avoid stopping the
c) Open the discharge valve CL501 for No.5 starboard cargo pump pump if at all possible until the cargo has been fully discharged. If the shore
to 20% and allow the pressure to stabilise. facility is unable to accept the liquid for intermittent periods, it is better to
keep the pump running and recirculate it back into the tanks until discharge
d) Adjust the discharge valve CL501 to obtain 66% load, 35 can be resumed and completed.
amps.
All LNG remaining in the downward leg of the loading arms and manifold
e) Carry out the procedures in b), c) and d) for the port cargo connection is to be drained to the tanks through the liquid line assisted by
pump. nitrogen pressure from ashore as per Section 6.3.4. The LNG and vapour
manifolds are then purged with nitrogen until an acceptable hydrocarbon
CAUTION content is reached.
Do not exceed the maximum rated current by 50% for more than 2 or
3 seconds when the tank is full. If the running current after this time is Note: Check the pump motor ammeter carefully, the current should be steady
more than 150% of the maximum rated current, the overcurrent trip after the motor has been running for 3 seconds. During starting, while the
will be activated and the pump stopped. Determine the cause of high discharge line is being filled, the current reading may be above normal.
current (possible blockage) before attempting to restart.