Professional Documents
Culture Documents
Method Statement of STP Tank Inside & Outer Side Wall Water Proofing
Method Statement of STP Tank Inside & Outer Side Wall Water Proofing
Method Statement of STP Tank Inside & Outer Side Wall Water Proofing
METHOD STATEMENT
Corporate Office:
PSP House,
Opp. Celesta Courtyard,
Opp. Lane of Vikramnagar Colony,
ISCON-Ambli Road,
Ahmedabad – 380058.
Tel Nos.: +91 -079 – 2693 6200, 2693 6300, 2693 6400
Fax Nos.: +91–079 – 2693 6500
E Mail: coordination@pspprojects.com
Web: www.pspprojects.com
1|Page
Project: Hospital Project at Sitapur
CONTENTS
1 Introduction
2 Scope of Work
3 References
4 Work Programme
5 Material
6 Temporary Services
7 Methodology
8 Health and Safety
Sign
Name
Date
1. Introduction:
This method statement describing the outline procedure to be followed for STP water
proofing in (Outer side wall) to be executed at Hospital Project at Sitapur.
2|Page
Project: Hospital Project at Sitapur
2. Scope of Work:
Water proofing on STP Outer side wall
2. :
7. Methodology
7.1 Surface Preparation: -
Careful surface preparation is essential for optimum finish and durability. The surface
needs to be clean, dry and sound, free of any contamination, which may harmfully affect
the adhesion of the membrane. Maximum moisture content should not exceed 5%.
Substrate compressive strength should be at least 25MPa, cohesive bond strength at least
1.5MPa. New concrete structures need to dry for at least 28 days. Old, loose coatings,
dirt, fats, oils, organic substances and dust need to be removed by a grinding machine.
Possible surface irregularities need to be smoothened. Any loose surface pieces and
grinding dust need to be thoroughly removed.
3|Page
Project: Hospital Project at Sitapur
depth of 10-15 mm. The width:depth ratio of the movement joint should be at a rate of
approx. 2:1. Apply some MARIFLEX® PU 30 Joint-Sealant on the bottom of the joint only.
Then with a brush, apply a stripe layer of MARISEAL® 270, 200mm wide centered over and
inside the joint. Place the MARISEAL® FABRIC over the wet coating and with a suitable
tool, press it deep inside the joint, until it is soaked and the joint is fully covered from the
inside. Then fully saturate the FABRIC with enough MARISEAL® 270. Then place a
polyethylene cord of the correct dimensions inside the joint and press it deep inside onto the
saturated FABRIC. Fill the remaining free space of the joint with MARIFLEX® PU 30
sealant. Do not cover. Allow 12-18 hours to cure.
4|Page
Project: Hospital Project at Sitapur
5|Page