Professional Documents
Culture Documents
Safety: Unit Number: Customer: Date: Hour Meter Reading: Country: Location: Engine/Comp Model: Providence: Technician
Safety: Unit Number: Customer: Date: Hour Meter Reading: Country: Location: Engine/Comp Model: Providence: Technician
Safety: Unit Number: Customer: Date: Hour Meter Reading: Country: Location: Engine/Comp Model: Providence: Technician
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
Safety
2 Complete JSA before beginning job. ☐Completed ☐N/A
Safety • Be sure to list all people working on the job.
• Make sure all hazards and special requirements are addressed.
4
Complete Lock Out / Tag Out procedure (LOTO). Indicate number of Number of
Safety
points locked out Lock Outs
• List the number of points a lock was applied. Example; Suction=1,
Discharge=1, Scrubber Drain=1, Fuel Gas=1, Total would be 4.
• Record count of lock points where single or group LOTO applied.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 1 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
Operating Parameters
10 Record unit RPM and Overspeed setting
Running Unit overspeed setting should be set no higher than 5% over the maximum RPM Current Overspeed
of compressor frame or 5% over the maximum RPM of engine, whichever is RPM Setting
lowest.
20 Record Compressor Flow Rate (MMCFD) and Percent Recycle Valve
Running open. Discharge Fuel Gas Recycle
Inlet Meter
If unavailable note N/A Record Meter Meter Open %
In
MMCFD
25 Record process gas system pressures – inlet and discharge of all stages.
Running Record Safety Setting Low (SSL), and Safety Setting High (SSH) for each
process gas panel gauge. Suction Disch. 1 Disch. 2 Disch. 3 Disch. 4 Disch. 5
• Process gas pressure safety settings should be set so that inlet pressure Pressure
cannot approach a vacuum, no system will approach max working
pressure, and that no stage can approach max rod load.
SSL
• Compressor performance programs would be an appropriate source for
determining process pressure safety settings. Special situations would SSH
require management approval.
30 Record process gas temperatures - inlet and discharge of all stages.
Running Record temperature safety settings. Cyl-1 Cyl-2 Cyl-3 Cyl-4 Cyl-5 Cyl-6
• Cylinder discharge temperature SSH's should be set at normal operating Inlet Temp
temperature plus 10%, with 350°F being the maximum allowable setting
unless approved by management. Disch. Temp
• Refer to the compressor performance program for calculated discharge
temperatures. SSH
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 2 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
40 Record all oil pressures and their SSL's. Record all available oil
Running temperatures and their SSH's, Record all filter ΔP's.
• Refer to current OEM publications for minimum and maximum oil PSI
SL Filter ∆ Temp SSH
pressure and temperature settings.
Engine Oil
• Record oil filter differential pressure (DP) if gauges are available, smaller
units are usually not equipped to read oil filter differential. Comp. Oil
• Normal oil filter DP 2-15 PSI, change oil filters if 15 psi differential
pressure.
50 Record all coolant temperatures and their SSH. Record all coolant
Running pressures and their SSL. PSI SSL Temp SSH
Refer to current OEM publications for min. and max. coolant temperatures and
safety settings Engine
Auxiliary
Exhaust Temp Cyl 1 Cyl 2 Cyl 3 Cyl 4 Cyl 5 Cyl 6 Cyl 7 Cyl 8 Cyl SSH Turbo SSH
Left Bank
Right Bank
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 3 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
60 ESM Engine Controller; Verify that each cylinder is firing. Any Issues? ☐ Issues repaired ☐ Issue need to be addressed ☐ All OK
Running Record peak spark/firing number.
Record current ignition timing. Peak Spark/Firing Number Timing BTDC
Record current WKI or Methane number (as applicable) set in controller.
• Confirm cylinders are firing by viewing the ignition control panel diagnostics
screen, and via cylinder exhaust temperature. WKI / Methane Number
• A correct WKI value must be entered into ESM and timing will be managed
through the ESM system. Refer to Waukesha Form 6295, ESM Manual
and/or Waukesha SB 11-2558E, VHP Timing.
65 Record AFR controller data (If equipped). Record target value and sensor Stepper
Running value. Record stepper position(s). Record controller gain setting. Note if Target Actual Position Gain Tracking?
controller is “Tracking” or out of range. Review, analyze and correct any
faults. Right Bank
Become familiar with current local emissions regulations. Follow compliance
Left Bank
regulations when operating and maintaining emission control systems.
• Verify temperatures and trends are within limits and SSH are correctly
Engine Bearing
set. Comp. Bearing
• Maximum Main Bearing Temperature 250°F.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 4 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
80 Record engine control screen shots. (ESM) Attach Screen Shots ☐Completed ☐N/A
Running
85 Review and analyze all safety settings for adequate equipment ☐Completed ☐N/A
Running protection limits.
Compare found settings to where they SHOULD be set at. Research current OEM
publications and the compressor performance program for correct settings.
90 Review and analyze alarm codes and fault history. Record any issues ☐Completed ☐N/A
Running that will need to be addressed.
100 Document all comments and issues found regarding parameters. Type comments or
issues found:
Running
199 Document all issues discovered during walk around inspection. Type comments or issues found:
Running
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 6 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
299 Document all issues discovered during temperature gun checks. Type comments or issues found:
Running
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 7 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
340 Any internal leakage at compressor recycle valve, dump valves, relief ☐Yes ☐No
Running valves?
Check the temperature difference between downstream vs upstream of a
particular valve to determine if leakage is occurring. Downstream side will be
cooler then upstream side.
350 Inspect scrubber dump valve controllers. Are scrubber level controllers ☐Yes ☐No
Running maintaining the appropriate level?
360 Are there any apparent worn or otherwise malfunctioning parts with ☐Yes ☐No
Running scrubber level controllers, dump valves, or site glasses?
370 Are all scrubber site glasses clean and valves are functioning? ☐Yes ☐No
Running
380 Verify correct instrument supply pressure and record reading.
Running Pressure
399 Document all discovered Cylinder lubrication and scrubber dump issues. Type comments or issues found:
Running
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 8 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
425 Adjust crankcase pressure to 0” to -2” H₂O (if adjustable). ☐Completed ☐N/A
Running
430 Record estimated hours on engine and/or compressor oil (if NOT
Running changing this service). Engine Oil Hours Comp Oil Hours
435 Indicate oil samples were collected? ☐Engine Oil Sample collected ☐Compressor oil Sample Collected
Running Did the previous oil analysis flag any issues? ☐Yes, Issues flagged ☐No issues flagged ☐Unknown
Sample at operating temperature, using a clean sample port located upstream of, ☐Not sampled
or prior to, filtering.
440 Collect coolant sample. ☐Sample collected ☐Not Sampled
Running Sample using a clean sample port (collected every 6 months).
445 Did the previous coolant analysis flag any issues? ☐Already addressed ☐Addressing this service
Running ☐Not sampled ☐No Issues ☐Unknown
450 Inspect coolant condition and color. Mark all that apply.
Running Perform freeze point test on coolant to verify sufficient protection. ☐Good Color ☐Clean ☐Not Freeze
☐ Weak Color ☐Dirty Checked Point
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 9 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
470 Drain fluid from fuel filter, fuel header, and supply gas regulators. ☐Filters Drained ☐N/A
Running Verify regulators are functioning properly. Pressure Setting
Verify start gas, fuel gas, and instrument supply pressures are set at Start Supply Left “A” Regulator
correct pressure. Record pressures
Item Recommended Maximum Fuel Supply Right “A” Regulator
IR Vane Starter 150 psi 150 psi Instrument Left Power Screw
TDI Turbine Starter 40 - 150 psi 150 psi
Fuel (2nd Cut)- L5794GSI; L7044GSI 24 – 50 psi 75 psi Pre Chamber Right Power Screw
Fuel (2nd Cut) - L5794LT; L5774LT 43 – 60 psi 75 psi
Fuel “A” Reg.- GSI 4” – 5” H2O 7” H2O
Fuel “A” Reg.- LT 5.5” – 6.5” H2O 7” H2O
Instrument Gas System dependent 30-45 psi
499 Document all discovered issues with the coolant, cooling system, Type comments or issues found:
Running governor and misc. items.
Electrical Systems
500 Record alternator AMP output (if equipped).
Running Record total battery voltage (if equipped). Amps Volts ☐N/A
599 Document all discovered issues with the electrical and charging system. Type comments or issues
found:
Running
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 10 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
630 Test all ESD switches and actuators prior to start-up. ☐ Completed ☐N/A
Running Note number of devices checked. No. Devices checked
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 11 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 12 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
Base 2L 2R
Current 2L 2R
Recession 2L 2R
Base 3L 3R
Current 3L 3R
Recession 3L 3R
Base 4L 4R
Current 4L 4R
Recession 4L 4R
Base 5L 5R
Current 5L 5R
Recession 5L 5R
Base 6L 6R
Current 6L 6R
Recession 6L 6R
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 13 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
1050 Set engine cylinder head valves (Per Cylinder Method – hydraulic lifters) ☐Completed ☐N/A
Shutdown
Clearances, Torques and Firing order
Valve Valve Setting Bridge Setting Firing Order
Intake 6 Cylinder 12
Cylinder 16 Cylinder(*)
0.000” + ½ turn CW 0.000” - Flat
Exhaust 1-5-2-4-3-6 1R 6L 5R 2L 3R 4L 6R 1L 2R 5L 4R 3L R1 L1 R3 L3 R7 L7 R5 L5 R8 L8 R6 L6 R2 L2 R4 L4
Mating Cylinder 6-2-5-3-4-1 6R 1L 2R 5L 4R 3L 1R 6L 5R 2L 3R 4L R8 L8 R6 L6 R2 L2 R4 L4 R1 L1 R3 L3 R7 L7 R5 L5
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 14 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
1070 Inspect valve cover gaskets, replace if needed (always replace on Top ☐OK- Reused ☐Replaced ☐N/A
Shutdown Ends and Overhauls when gaskets are provided in Head set).
1090 Inspect main and auxiliary water pumps (Rebuild or exchange if worn). ☐Rebuilt ☐Exchanged ☐OK – Reused ☐N/A
Shutdown
1099 Document comments and all issues found regarding Top End Task. Type comments or issues found:
Shutdown
Frame Overhaul
1510 Inspect crosshead, guide, wrist pin, Throw # 1 2 3 4 5 6
Shutdown and connecting rod areas.
Crosshead Condition G = Good / R = Replaced
Remove compressor distance piece side
Crosshead Guide Condition G = Good / R = Replaced
doors for inspections.
Crosshead Clearance Thousands of Inches (.010)
• Use a micrometer to measure.
• Document wear/condition. Crosshead Clearance within
Y = Yes / N = No
Mfg. Specifications?
• Verify weights are tight (if
applicable). Wrist Pin Condition G = Good / R = Replaced
• Replace only excessively worn Wrist Pin dimensions within
parts. Y = Yes / N = No
Mfg. Specifications?
Connecting Rod Small End
G = Good / R = Replaced
Bearing Condition
Connecting Rod large End
G = Good / R = Replaced
Bearing Condition
1530 Inspect frame running gear. ☐Completed ☐N/A
Shutdown Remove compressor top cover and visually inspect for wear metals and other issues.
• Check and adjust drive chain if required, if equipped.
• Bump and/or spot check rod bearings.
1550 Inspect all shaft seals. Replace as needed. ☐Completed ☐N/A
Shutdown Note findings and/or repairs made.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 15 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
1599 Document comments and all issues found concerning frame area. Type comments o
issues found:
Shutdown
Compressor Cylinders
1600 Inspect/clean all installed gas cone screens/strainers (as equipped) and Cleaned or None or
Component N/A
Shutdown inspect placement of restriction orifices. Confirmed Removed
• Inlet gas cone screen/strainer shall be remove inspect, clean and reinstall Inlet Cone Screen/Strainer ☐ ☐ ☐
• All other cone screens/strainers shall be removed at first service interval. Other Cone Screens/Strainers ☐ ☐ ☐
• If other than inlet cone strainers are installed, note location, condition, Orifices confirmed to P&ID ☐ ☐ ☐
and reasoning in comment.
• If orifices are installed, confirm size and position.
1610 Inspect corrosion coupons (if equipped). Coupon
☐N/A
Shutdown > Document observation, trend wear Measurements
1620 Remove and inspect all compressor valves. ☐Completed ☐N/A
Shutdown > Torque all valve caps. DO NOT use impacts. (Refer to Annex - Compressor Valve
Removal & Installation)
> Seek advice to tailor valves to site-specific application, when having premature
and/or reoccurring failures.
1640 If process gas is dirty, remove and inspect piston, rings, cylinder, and ☐Completed ☐N/A
Shutdown piston rod.
1. Use a micrometer to measure.
2. Document wear/condition.
3. Replace components that are worn beyond wear limits.
List worst case (Reuse all components if with-in wear limits)
1699 Document comments and all issues found with compressor cylinders and Type comments or issues found:
Shutdown components.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 16 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 17 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
1900 Check turbochargers for buildup, for signs of oil leakage, signs of cold ☐Completed ☐N/A
Shutdown housing contact and for excessive play in shaft.
If in doubt, measure play with indicator, compare to specification.
1920 Visually inspect turbo oil supply line clamps ☐Completed ☐N/A
Shutdown Supply lines will crack without clamps in place.
1930 Visually Inspect for signs of leakage at air inlet hoses, O-rings and gaskets, ☐Completed ☐N/A
Shutdown exhaust manifolds, expansion joints, exhaust collar rings, after/inner
coolers, turbo(s) and waste gates (as applicable).
Repair as needed
1999 Document comments and all issues found with turbo (and/or air intake) Type comments or issues found:
Shutdown systems.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 18 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
2020 Inspect and clean engine oil system (as applicable) Mark all that apply
Shutdown • Inspect and clean the magnetic plugs in the cylinder head lube headers, (Mark just the “All Completed” if ALL applicable completed)
front and rears, and in turbo oil supply lines as equipped.
• Clean oil strainers (as equipped). All Magnets Checked & Cleaned ☐No ☐Yes
• Clean oil sump and clean pick-up screen (as equipped and accessible). Oil Strainers Checked & Cleaned ☐No ☐Yes
• Drain oil shell & tube cooler (oil tube side) or section in gas cooler. Oil Sump Checked and Cleaned ☐No ☐Yes
• Visually inspect lubrication hoses on engine. ☐All
Oil Pick-up Checked & Cleaned ☐No ☐Yes
• Inspect and clean Engine Oil Level Controller. Completed
Oil Cooler Drained ☐No ☐Yes
• Repair/Replace as needed
Lubrication hoses visually inspected ☐No ☐Yes
Le
vel Controller Checked & Cleaned ☐No ☐Yes
2050 Compressor oil and filter(s). Oil Filters ☐Changed ☐Not Changed ☐N/A
• Compressor oil shall be changed when engine oil is changed Lube Oil ☐Changed ☐Not Changed ☐N/A
• If directed by management or otherwise NOT changed, indicated
hours on compressor oil at this service. Enter hours on oil
if NOT changed
2099 Document comments and all issues found regarding engine and Type comments or issues found:
Shutdown compressor oil.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 19 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 20 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 21 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
Coupling
• If soft foot in question on engine, check crankshaft
deflection Bolt Torque ft.lbs. BASE DEFLECTION
1L 2L 3L 4L 5L 6L 7L 8L
flywheel.
• Total of 0.001", positive to negative, all other throw.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 22 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
Coupling
• If soft foot in question on engine, check crankshaft
Bolt Torque ft.lbs. BASE DEFLECTION (Mark as applicable)
deflection
1L 2L 3L 4L 5L 6L 7L 8L
Engine Thrust
Compressor Thrust
2580 Check crosshead, frame, and engine mounting bolts for tightness. Inspect ☐Completed ☐N/A
Shutdown bottle supports for correct setting. Torque distance piece support bolts.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 23 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
2599 Document comments and all issues found regarding cooling systems. Type comments or i
sues found:
Shutdown
2699 Document comments and all issues found with PSV’s and scrubber Type comments o
r issues found:
Shutdown dumps.
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 24 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
2799 Document comments and all issues found with PSV’s and scrubber Type comments o
r issues found:
Shutdown dumps.
All Applicable - OK
Cooler Drive ☐ ☐ ☐ ☐ ☐
• Properly tensioned belts will feel alive springy. Belts too tight will not Fan/Radiator ☐ ☐ ☐ ☐ ☐
deflect, loose belts feel non-reactive.
Governor ☐ ☐ ☐ ☐ ☐
• Refer to Annex “Belt Tensions or service manual for tension information
PTO Drive ☐ ☐ ☐ ☐ ☐
• Mark what belt issues were addressed and how
WP – Aux. ☐ ☐ ☐ ☐ ☐
• A single X in the “All applicable – OK” column represents all applicable
check and all OK
WP - Main ☐ ☐ ☐ ☐ ☐
Sheaves ☐ ☐ ☐ ☐ ☐
2810 Grease all applicable points as defined below. Indicate number of points Item Amount No. Points
Shutdown greased.
• Use a Lithium based grease such as Hydrotex Parasyn 70, Lithoplex® Actuator Linkage ½ -1 Pump each joint
Grease No 2, or equivalent. Alternator Idler 1- 2 Pumps
• Use High Temperature Grease on Spill Port Valves and on Linage near Aux. Water Pump 1 Pump
waste gates. Cooler Bearings 3 – 5 Pumps
• Repair any broken grease lines. Control Linkage ½ -1 Pump each joint
• Replace any non-working grease fittings. Fan Bearing (Radiator) 1- 2 Pumps
• All points grease each down service except VVCP’s Fan Idler (Radiator) 1- 2 Pumps
• VVCP need only to greased annually VVCP’s 1 Pump annually
2899 Document all discovered issues with belts, sheaves, and grease points. Type comments or issues found:
Shutdown
Startup
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 25 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
3010 Prepare unit for restart. (Note multiple steps!) ☐Completed ☐N/A
Starting 1. Inspect all work, remove LOTO, check for leaks, purge, pressure test system,
and close out all safety permits. Safety Note: Never address any leak under pressure! Always blow
2. Reset regulators, carburetors, steppers that were replaced or repaired to down and initiate LOTO.
previously recorded setting.
3. Check fluid levels, drain valves, make up tank valves, and process valve
positions.
4. Test engine pre-lube function. Refill lubricator
5. Test compressor pre-lube function. Refill lubricator
6. Ensure all personnel are clear.
7. Restart, check oil pressures and conduct walk around before and after
loading.
3030 Verify fuel settings RIGHT BANK (And Single Carbureted Engines)
Running RICH BURN (No AFR Controller)
Manifold Pressure
1. Verify Engine is loaded, running at a steady RPM, and fuel is at a steady state
2. Verify fuel pressure regulator settings are correct. “A” Regulator Setting
3. Verify ignition system is functioning properly - no miss-fires; engine timing Power Screw Position or Inches OUT
correct. Load Screw
MID
4. Additionally (R) | | | | | | (L) Inches
a. On dual carbureted Vee-Engines, verify banks are balanced OUT
mechanically. ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
5. On turbocharged engines, verify that wastegate’s establish sufficient boost
(but not excessive boost) over manifold differential pressure.
6. Tune power screws (and sequentially A Regulator(s)) if needed to obtain LEFT BANK
lowest manifold pressure (Boost Method), then lean out ½” Hg per bank – Manifold Pressure
Stoichiometric setting “A” Regulator Setting
7. Record final Settings (as applicable)
RPM Power Screw Position or Inches OUT
Load Screw
Load (HP %)
MID
(R) | | | | | | (L) Inches
Bank Balance OUT
Fuel Supply PSI ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 26 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
3035 Verify fuel settings RIGHT BANK (Or Single Carbureted Engines)
Running RICH BURN WITH AFR CONTROLLER
Manifold Pressure
1. Verify Engine is loaded, running at a steady RPM, and fuel is at a steady state
2. Verify fuel pressure regulator settings are correct. “A” Regulator Setting
3. Verify ignition system is functioning properly - no miss-fires; engine timing Power Screw Position or Inches OUT
correct. Load Screw
MID
4. Additionally (R) | | | | | | (L) Inches
a. On dual carbureted Vee engines, verify banks are balanced OUT
mechanically. ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐
b. On turbocharged engines, verify wastegate’s establish sufficient Stepper Position Range H/L
boost (but not excessive boost) over manifold differential pressure. Current O2 Value O2 Target
c. On electronically controlled engines, verify A3, ESM, CEC, or other
controller is correctly programed. LEFT BANK
5. Verify stepper motors are functioning and near mid-range Manifold Pressure
a. IF NOT tune power screws (and sequentially A Regulator(s)) if needed
“A” Regulator Setting
to center range.
6. Verify emissions using an Exhaust Gas Analyzer, gradually adjust carburetor Power Screw Position or Inches OUT
power screw to obtain desired emissions- CO, NOx, O2. Load Screw
MID
7. Verify ARF controls can “swing” to handle Fuel BTU changes (R) | | | | | | (L) Inches
8. Record final Settings (as applicable) OUT
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 27 of 28
Operation & Maintenance Management System
PM Plan: PM-GC-9000HR-WAUK-VHP-S4
PM Description: PM Gas Comp 9000HR/1YR WAUK VHP-S4 6-16Cyl
PM Estimated Time: 12 Hours
PM-GC-9000HR-WAUK-VHP-S4-R1-20161030 Page 28 of 28