Revised runway
alternation programme
9 Nov 2020 to Runway alternation
28 Feb 2021* Date (week If on westerly If on easterly
commencing) operations operations
As a result of the unprecedented impact that the Coronavirus
(COVID-19) outbreak is having on Heathrow’s operation, we 9 Nov 27L 09R
have temporarily moved to single runway operations,
alternating which runway we use on a weekly basis in order 16 Nov 27R 09L
to ensure our local communities continue to get respite
periods. 23 Nov 27L 09R

30 Nov 27R 09L


We will continue to review this situation and will look to
revert to our usual operation when the number of daily 7 Dec 27L 09R
aircraft movements significantly increases.
14 Dec 27R 09L
Due to the significantly lower number of aircraft operating
from the runway we will also be able to provide alternation
21 Dec 27L 09R
on easterly operations – something we can’t provide during 28 Dec 27R 09L
our usual schedule.
4 Jan 27L 09R
The direction planes fly at Heathrow depends on the
direction of the wind. During westerly operations the wind 11 Jan 27R 09L
usually blows from the west and aircraft arrive from the east
18 Jan 27L 09R
over London. During easterly operations the wind blows from
the east and aircraft arrive from the west over Berkshire. 25 Jan 27R 09L

Runway codes 1 Feb 27L 09R


The schedule uses the runway codes 09L, 27R, 09R and 27L.
8 Feb 27R 09L

15 Feb 27L 09R

22 Feb 27R 09L

Please note: The weekly runway alternation will take place at 00:01
each Monday. However, in the event of a late running aircraft on a
Sunday evening, alternation will be delayed. This temporary runway
alternation pattern replaces both our regular daytime and night-time
alternation schedules.

09L = aircraft approaching the northern runway from the west * This schedule runs to 28 February 2021 but this is not an indication
27R = aircraft approaching the northern runway from the east of how long we expect to be on single runway operations. It is not
possible for us to predict when operations will return to normal.
09R = aircraft approaching the southern runway from the west
27L = aircraft approaching the southern runway from the east