MS-MP00018 Dead Ship Start-Up and Blackout Restart Procedures For BW Joko Tole Revised 10.11.2020

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 16

Dead Ship Start-up and Blackout Restart

Procedures for BW Joko Tole

This document is part of BW Offshore’s Management System,


which holds the complete revision history and electronic versions of
attachments and referenced documentation.

Document ID / Rev. No. / Publish Date:


MS-MP00018 rev. 02 04-11-2013
Document Owner: Approval:
Operation Manager SVP East Fleet
Implementation: Verification:
OIM Operation Manager
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

Table of Contents
1. INTRODUCTION 3
1.1 DEFINITIONS............................................................................................................................ 3
1.2 ABBREVIATIONS...................................................................................................................... 3
1.3 ASSUMPTIONS......................................................................................................................... 4
1.4 SAFETY PRECAUTIONS.......................................................................................................... 4
2 SCOPE 4
3 GENERAL 4
4 STARTING METHODS AND AUXILIARIES REQUIRED FOR GENERATORS 5
4.1 EMERGENCY GENERATOR (84-EG-5001).............................................................................5
4.2 ESSENTIAL DIESEL GENERATORS (82-EG-5501A and 82-EG-5501B)................................6
4.3 STEAM TURBINE GENERATORS (80-EG-9000 and 80-EG-9100).........................................7
5 DEAD-SHIP START-UP SEQUENCE OPERATION 7
5.1 START EMERGENCY DIESEL GENERATOR 84-EG-5001 (Manual Start) AND POWER-UP
EMERGENCY LOADS............................................................................................................... 7
5.2 START ESSENTIAL DIESEL GENERATORS 82-EG-5501A and 82-EG-5501B (Manual/Local
Start) AND POWER-UP ESSENTIAL LOADS...........................................................................8
5.3 ENERGIZING THE NORMAL SWITCHBOARD FROM THE NEW ESSENTIAL
SWITCHBOARD, IF REQUIRED FOR OPERATIONAL REASONS BEFORE MAIN POWER
IS AVAILABLE FROM THE STGs........................................................................................... 10
5.4 START STEAM TURBINE GENERATORS 80-EG-9000 and 80-EG-9100 (Manual-Start) AND
POWER-UP PROCESS LOADS............................................................................................. 11
6 BLACK-OUT RE-START SEQUENCE OPERATION 12
6.1 START EMERGENCY DIESEL GENERATOR 84-EG-5001 (Auto-Start) AND POWER-UP
EMERGENCY LOADS............................................................................................................. 12
6.2 START ESSENTIAL DIESEL GENERATORS 82-EG-5501A and 82-EG-5501B (Auto-Start)
AND POWER-UP ESSENTIAL LOADS...................................................................................13
6.3 START STEAM TURBINE GENERATORS 80-EG-9000 and 80-EG-9100 (Auto-Start) AND
POWER-UP PROCESS LOADS............................................................................................. 13
7 OTHER STARTING PROCEDURES 14
7.1 BASIC PROCEDURE FOR STARTING THE BOILER SYSTEM.............................................14
7.2 ENERGIZATION OF 80-ET-4001A/B and 82-EN-4001A/B NORMAL SWITCHBOARDS.......15
8 SPECIAL RECOMMENDATIONS 15
8.1 Standby Personnel................................................................................................................... 15
8.2 Purge Sequence for running Fuel Gas Compressors..............................................................15
8.3 Black-out /Dead-ship Restart with only one DG available........................................................15

Page 2 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

1. INTRODUCTION
This document covers the requirements for the detailed procedure of the electrical start-up / re-
starts for the FPU BW Joko Tole.

1.1 DEFINITIONS
For purposes of this document, the following definitions apply:

Dead-ship or Black-out A Dead-ship or Black-out refers to the total power outage on the
facility. Cause for total power outage can be attributed to failure of
any component such as protection relay trip, activation of ESD 1 or
ESD 2 , etc. (Black-out) or activation of AVS or ESD 0 (Dead-
ship) in the facility. The main difference between Black-out and
Dead-ship is that during Black-out the UPS System is still available
while it is not during a Dead-ship.
Dead-ship Start-up When AVS or ESD 0 is initiated, the facility will be in total power
outage including the UPS System. Re-instating the electrical
system shall follow a dedicated procedure termed as Dead-ship
Start-up to allow the safe re-start of electrical supply. All start-up
procedures shall be manually initiated.
Black-out Re-start In case of the power outage other than AVS or ESD 0, the
electrical UPS System is still available for the immediate
resumption of electrical supply. Start-up operation shall be
generally initiated automatically through the PMS, assisted by
Operation personnel in case auto function fails.

1.2 ABBREVIATIONS

ACB Air Circuit Breaker


AVS Abandon Ship Shutdown
CCR Central Control Room
DG Essential Diesel Generator
EDG Emergency Diesel Generator
ESD Emergency Shutdown
ESB Emergency Switchboard
FPU Floating Production Unit
F&G Fire and Gas
ICSS Integrated Control and Safety System
LO Lube Oil
LSM Load Sharing Module
LSU Load Sharing Unit
LV Low Voltage
MCC Motor Control Center
MDO Marine Diesel Oil
MV Medium Voltage
NESB New Essential Switchboard
PMS Power Management System
STG Steam Turbine Generator
STG LCP Steam Turbine Generator Local Control Panel
UPS Uninterruptible Power Supply
VCB Vacuum Circuit Breaker

Page 3 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

VFD Variable Frequency Drive


[OP-XX] Denotes the Operational Procedure tag reference of the Circuit Breakers
1.3 ASSUMPTIONS
It is assumed that:
 All the FPU utility systems are ready for operation, and complete safety requirements
have been complied with, together with other relevant operational procedures.
 The basic design philosophy of all electrical loads is fail – safe. Feeders from MV and LV
switchgear including MCC shall be tripped to OPEN position.
 All normal Operator Equipment pre-start checks are carried out prior to the
implementation of this procedure.
 No unsafe condition exists.
 All alarms are in their normal state.
 Sufficient competent personnel are available.
 Radio Communications are established.
 All process valves are in their normal position (de-energised, fail-safe)
 Fuel gas and MDO is available
 Main air reservoirs are fully charged at 30 barg

1.4 SAFETY PRECAUTIONS


 Permission to be obtained / information to be passed on to the concerned prior to every
major activity for example switching ON Breaker / Starting of Equipment / Loads.
 The operator involved will exercise caution and safety measures during the operations.
 The entire sequence shall be a coordinated operation.
 Perform tool box meeting prior Start-up.
Competency requirements….

2 SCOPE
The procedure will cover starting-up of the Power Generation, Power Distribution and bringing the
plant operation back in Normal Mode in a safe and logical manner, following a vessel wide total
power outage. The steps and sequences cover but not limited to the following activities:
 Manual/Auto start of the Emergency Power Generation and Distribution System
 Manual/Auto start of the Essential Power Generation and Distribution System.
 Manual start of the Steam Turbine Generators
 Transfer of load from EDG to DG and DG to STG

3 GENERAL
In general terms, the Power Generation and Distribution systems of FPU BW Joko Tole shall be
re-started by use of the following diesel-driven generators:
 84-EG-5001 -250kW/312kVA 440V, 3-ph, 60Hz Emergency Diesel Generator (EDG)
 82-EG-5501A -910kW/1138kVA 440V, 3-ph, 60Hz Essential Diesel Generator No. 1
(DG-1)
 82-EG-5501B -910kW/1138kVA 440V, 3-ph, 60Hz Essential Diesel Generator No. 2
(DG-2)
The steps pre-requisites detailed in Section 1.3the attached checklist are to be followed to restart
power generation onboard. are taken into account prior to re-start in order to fulfil the
requirements of this procedure.
Essentially, a Black-out Re-start shall use the ship’s stand-by diesel generators (EDG and DGs)
to provide power to emergency and essential consumers sufficient to maintain the normal
requirements for safe habitation on board the FPU and to allow the Boiler and STG auxiliary

Page 4 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

equipment to be made available in order to re-start one of the Main Steam Turbine Generators.
Upon restoration of ‘Normal mode of supply’ (MV system), the stand-by diesel generators will be
returned to ‘auto / stand-by mode’. Operation, control and switching of the MV/LV electrical
distribution network, including the Essential Diesel Generators will be carried out through the
PMS. The operation, control and switching of the Emergency Switchboard and Emergency Diesel
Generator will be carried out by the stand alone control system within the Emergency
Switchboard, however, transfer of load from the Emergency Generator back to normal supply is a
manual operation in full controlled manner.

4 STARTING METHODS AND AUXILIARIES REQUIRED FOR


GENERATORS
Dead-Ship Start Up: During initial start-up (Dead-Ship or after AVS/ESD 0), Emergency and both
Essential (x2) Diesel Generators will be started manually from their respective local control
panels and manually closed onto their respective Switchboards in ‘Island Mode’. Ultimately, this
shall lead to the firing of a Steam Boiler and the starting of a Steam Turbine Generator, in order to
bring the facility up to the normal operating condition. Once all stand-by Diesel Generators (DGs
and EDG) have been stopped, they must be returned to ‘Auto Stand-by Mode’.
Black-Out Restart: For a Black-out restart, all stand-by Diesel Generators will start automatically
and supply their respective Switchboards in ‘Island Mode’. Ultimately, this shall lead to the firing
of a Steam Boilers and the starting of a Steam Turbine Generator, in order to bring the facility up
to the normal operating condition.
Emergency Generator: Upon detection of Under Voltage on the Emergency Switchboard (ESB)
via the proprietary Under Voltage relay, the EDG will automatically start and connect to the ESB
upon ‘Dead-Bus’ condition and stabilize the power supply to 440 V / 60 Hz.
Essential Generators: The Black-out restart sequence for the Essential Diesel Generators
(DGs) will be initiated through the PMS, where upon detection of “Under Voltage” and “Under
Frequency” on the New Essential Switchboard (NESB), both DGs will be started sequentially, by
the PMS. When selected for ‘Auto-Synchronize’ the closing of the respective DG Circuit Breaker
will be initiated via each Automatic Synchronizer relay. The DGs shall be connected to the NESB
and stabilize the power supply to 440 V / 60 Hz.
In both starting methods (‘Dead-Ship’ and ‘Black-Out restart’ the stand-by diesel generators will
be operated in ‘island mode’ where the Emergency Generator supply shall be limited to the ESB
and the Essential Generators supply shall be limited to the NESB. The two switchboards (ESB
and NESB) shall be operating in ‘Island Mode’ until such time that the EDG has been
synchronized with the NESB. Upon successful load transfer to the NESB from the EDG to the
DGs, the EDG circuit breaker must be opened immediately or it will automatically open after 30
seconds to avoid the EDG and DGs from running in parallel for prolonged periods, as per Class
requirements.
The next sequence will be starting the auxiliaries, required for the firing of a Steam Boiler. When
normal steam pressure and temperature are stable, one Steam Turbine Generator (STG) will be
started and ‘Dead Bus’ closed onto the 6.6 kV Main Switchboard at rated voltage and frequency.
After successful energized of the 6.6 kV Main SWBD, the DGs will be synchronized through the
secondary breaker of Essential Transformer (80-ET-5501) for transfer of loads. The PMS shall
inhibit the other STG from coming on-line during this load transfer operation. A successful
transfer of load to the operating STG from the operating DGs shall initiate proper disconnection
and shutdown of the running DGs by the PMS.

4.1 EMERGENCY GENERATOR (84-EG-5001)


The Emergency Diesel Generator (EDG) is equipped with a dedicated local control panel (84-EC-
5001) for monitoring and auto-start functions.

Page 5 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

A synchroscope (CSQ-3) is provided at the ESB for paralleling the EDG to New Essential SWBD
during load transfer as well as during regular maintenance routines and testing. Paralleling is
done manually at the ESB and for a short time only.
For starting reliability, the EDG is provided with 2x24Vdc Battery Banks charged by two (2)
dedicated Battery Chargers which are also located in the Emergency Generator Room.
As per Classification requirement, under normal operating conditions, the Emergency Generator
will auto start on detection loss off power/ no voltage at ESB Bus 84-EN-5001, provided that the
EDG is in Auto mode and AVS/ESD 0 has not been activated. If the EDG auto-start fails, it will be
started manually and controlled from its local control panel.
The minimum requirements for starting the EDG are given below.
1 Sufficient fuel in the Emergency Generator Day Tank.
2 Sufficient Lube oil and Coolant level.
3 Battery banks fully charged.
4 Supply air damper to Emergency Generator Room must be open.
For detailed procedure for the safe starting of the EDG, refer to vendor’s operating manual.
After ESB is powered, it is the duty of the operator to ensure that UPS-A and UPS-B are in
normal operating mode and to ensure that the ICSS and all critical / emergency systems are
powered up and operational.

4.2 ESSENTIAL DIESEL GENERATORS (82-EG-5501A and 82-EG-5501B)


The DG is electronically controlled and monitored by an electronic monitoring system A4 ECM. A
fully redundant 24Vdc supply is provided for the DGs control and monitoring system which consist
of a 24Vdc Battery Bank/Battery Charger and an internal 24Vdc supplied by a 220Vac UPS. Each
DG is provided with an air starting motor for starting the diesel engine.
A synchronizer relay is provided at the New Essential SWBD (NESB) for each essential generator
for auto-synchronizing the unit to the bus bar voltage of the New Essential SWBD 82-EN-5501.
When selected to Manual-Local-Remote, synchronizing is carried out by a Check Synchronizing
Relay (CSQ-3) within the Generator Synchronizing Panel. A load sharing module (Woodward
LSM) is also provided for each DG for automatic load sharing paralleled together in ‘Island Mode’.
The DGs are started by compressed air, which is supplied from main air reservoir No 1, 63-VL-
0001. Main air reservoir No 2 is interconnected with Main air reservoir No. 1. Four (4) main air
compressors 63-KB-0001 A, B & 63-KC-0500A, B charge the Main Air Reservoirs. Main air
reservoirs are fully charged at 30 barg. A dedicated Emergency Air Reservoir 63-VL-0004 is also
provided in case facility compressed air is not available. If necessary, the emergency air
reservoir could be charged by a diesel-engine driven emergency air compressor 63-KB-0002 to
30 barg before starting the DG’s.
For detailed procedure for the safe starting of the DGs, refer to vendor’s operating manual.
The pre-requisites for starting the DGs are given below:

1. Sufficient MGO in the Essential Generator Diesel Oil Service Tank.


2. Sufficient Charge in the No.1 Main Air Reservoir 63-VL-0001, to start 1 of 2 Essential Diesel
Generators (DGs) or in the Emergency Air Reservoir 63-VL-0004.
3. One Fire Water Jockey Pump (71-PA-0501A, B, or C) is running.
4. One Diesel Oil Supply Pump is available (62-PE-0005A or 62-PE-0005B)
5. Lube Oil Priming Pump is available.
6. Control Supply to all DG panels available.
7. Emergency Diesel Generator (EDG) is running supplying power to the Emergency SWBD 84-
EN-5001.
8. Cooling system (Coolant level and Sea water cooling) is available.

Page 6 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

4.3 STEAM TURBINE GENERATORS (80-EG-9000 and 80-EG-9100)


The synchronous brushless generator is rated at 5500kW, 6600V, 602A, 4-pole, 1800 rpm, 3-
phase, 60 Hz, 0.8 pf.
The Steam Turbine Generators (STGs) are started by a turning motor when saturated steam at
16 barg is available. The STG Local Control Panels require 220Vac supply from UPS, 440Vac
from the New Essential Switchboard, and 440Vac supply from the Emergency Switchboard.
Engine Room ventilation fans (97-GK-0002, 0003, 0004, and 0005) located at B-Deck must be
available and running before initiating STG start-up sequence.
Instrument Air Compressor(s) are operational and sufficient air reserve is available, it may be
necessary to override the PMS inhibit command. All equipment auxiliaries for the STG to be
started must be available and running including lube and control oil systems. The start-up
sequence for the STG is as per PMS screen.
For detailed procedure for the safe starting of the STG, refer to vendor’s operating manual.
Prerequisites for STG start are:
1 Power supply for STG LCPs 80-EC-9000 or 80-EC-9100.
2 Pre/post lube oil pump motor (supplied via 80-EC-9000/9100).
3 Ventilation system motors –1 (97-GK-0002, 0003).
4 Ventilation system motors –2 (97-GK-0004, 0005).
5 Space heater of generator, motors and enclosures.
6 Battery chargers.
7 Instrument Air Supply.
8 Cooling water supply.
9 Steam at rated pressure and temperature from Boiler.
10 Fuel gas or MDO is available.

5 DEAD-SHIP START-UP SEQUENCE OPERATION


Prerequisites:
1 Ensure vessel is gas free and safe to start-up.
2 Check UPS batteries: If the batteries are OK, reset/start the UPS on battery power and
provide power to the ICSS and F&G / ESD systems.
3 Ensure ESD system in normal and no alarm interlocking PMS sequence.

5.1 START EMERGENCY DIESEL GENERATOR 84-EG-5001 (Manual Start) AND


POWER-UP EMERGENCY LOADS
1. Verify the minimum requirements in Section 4.1 have been established.
2. Ensure that all the incoming and outgoing feeder breakers on the ESB are open.
3. If ESD has been activated and not reset at ICSS, select ESD key switch (2ESD) to
‘OVERRIDE’ position at the ESB.
4. Open louver intake and exhaust of emergency generator room manually.
5. On Emergency diesel generator, Switch to OPEN position air intake manifold switch (84-
XV-0757).
6. START engine from engine local control panel (84-EC-5001) :
- Select START selector switch to LOCAL
- START Engine by pushing START Button.
7. Allow the engine to stabilize. If necessary adjust EDG speed via a speed control
potentiometer (R21) and the Generator voltage via a voltage trimmer potentiometer (R20)
at the ESB.
8. Once the EDG is operating at the rated speed, voltage and frequency, close EDG
Breaker [OP-01] onto ESB (closing on dead bus) by switching CB Control Selector
Switch (2S1) to ‘CLOSE’. If the breaker cannot be closed from this switch, manually

Page 7 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

charge the spring and close by pressing breaker’s close push button. The ESB is now
energized by power from EDG.
9. Once stabilized, switch ON the feeders to the UPS (Un-interruptible Power Supply) 85-
ER-5001A and 85-ER-5001B [OP-02 and OP-03].
10. Reset all initiated active ESD signals on ICSS/CCR.
11. Switch ON the feeder to the Emergency Transformer 84-ET-5001 [OP-04].
12. Switch ON the MCCB of Fire Water Jockey Pump A, 71-PA-0501A [OP-05]. Start the
pump for the cooling water requirement of the EDG.
13. Switch ON the MCCB of No. 1 Steering Gear, 58-XY-0001A [OP-06]. Ensure its
availability when needed (applicable for sailing scenario only).
14. At the UPS Room located at A-Deck, AFT/ Portside, confirm that both UPS (85-ER-
5001A and 85-ER-5001B) are in normal operating mode. Reset any standing ESD trip
signals to the Battery CBs by selecting ‘BYPASS’ on the ESD Bypass Switch and verify
that the respective Battery Banks in the Battery Room adjacent to the UPS Room have
returned to their normal charging cycle.
15. Confirm that all emergency transformer loads are energized. (Engine Room Emergency
DB 84-EL-5003A [OP-07], E-House Emergency DB 84-EL-4001 [OP- 08],
Accommodation Emergency DB 84-EL-5002 [OP-09], and Decks Emergency DB 84-EL-
5002A [OP-10]).
16. All ESD signals that still exist shall be reset and ESD key switch returned to NORMAL
position at the ESB.
17. The rest of the emergency loads can now be started as required.
18. The EDG shall be put on AUTO MODE after the successful Dead-ship Start-up so that it
will start automatically when Black-out Re-start is initiated by the PMS.

The priority emergency loads at start-up are listed below:

STARTING SWBD LOCATION TAG NUMBER DESCRIPTION


SEQUENCE
1 84-EN-5501-S3-4 85-ER-5001A 220V UPS Unit A
2 84-EN-5501-S3-5 85-ER-5001B 220V UPS Unit B
3 84-EN-5501-S5-5 84-ET-5501 Emergency Lighting Transformer
4 84-EN-5001-S3-1/S3-2/S3-3 71-PA-0501A/BC Fire Water Jockey Pump A/B/C.
5 84-EN-5001-S3-9 58-YX-0001A No.1 Steering Gear (Sailing Only)

5.2 START ESSENTIAL DIESEL GENERATORS 82-EG-5501A and 82-EG-5501B


(Manual/Local Start) AND POWER-UP ESSENTIAL LOADS

1. Verify the minimum requirements in Section 4.2 have been established.

2. At the local control panels of each DG, set the LOCAL/REMOTE start selector switch to
‘REMOTE’ while at the New Essential SWBD Synchronizing Panel set the AUTO/MAN
control selector switch (16S01) to ‘MAN’ (Manual) and the LOCAL/REMOTE control switch
(16S9) to LOC (Local). Switch DG Priority Selection Switch (16S02) to DG-1 at the New
Essential Switchboard (NESB).

82-EG-5501A 82-EG-5501B
S/Switch LOC REM M A LOC REM M A
Engine Control L/R X X
NESB Auto/Man X X

Page 8 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

(16S01)
NESB LOC/REM
X X
(16S9/18S9)
DG Man Start Select
X X
(16S02)

3. With ‘Engine Ready to Start’ pilot lamp (16HE1) ON, start DG-1 locally at the NESB by
switching START/STOP control switch (19S7) to ‘START’. Verify that Generator starts and
runs up to rated speed and voltage by monitoring the panel mounted meters. If necessary
adjust generator speed by switching speed adjuster selector switch (16S8) to either
‘INCREASE’ or ‘DECREASE’ at the New Essential SWBD until a stable speed is achieved.
4. (THIS FUNCTION ONLY APPLIES TO ‘AUTO SYNCH’ MODE VIA 16PP AUTO
SYNCHRONIZER. WHEN IN ‘MAN/LOCAL’ ONLY 16KSYN SYNCHROSCOPE WILL
ENABLE CB TO CLOSE). Confirm the Dual Voltage and Frequency meters are displaying
correctly and that Synchroscope (16KSYN) is activated. On a ‘Dead-Bus’ condition the
Synchroscope will be in the ‘12 o’clock’ position. Close the DG-1 Incomer CB by switching
the corresponding CB control switch (16S1) to ‘CLOSE’. The New Essential Switchboard
(NESB) is now powered by DG-1.
5. Restart the E/R Main seawater cooling pumps after NESB energized by DG1/DG2.
6. Repeat step 3 for DG-2.
7. (THIS FUNCTION ONLY APPLIES TO ‘AUTO SYNCH’ MODE VIA 16PP AUTO
SYNCHRONIZER. WHEN IN ‘AN/LOCAL’ONLY 16KSYN SYNCHROSCOPE WILL ENABLE
CB TO CLOSE). Confirm the Dual Voltage and Frequency meters are displaying correctly
and that Synchroscope (16KSYN) is activated. Monitor the Synchroscope and make
necessary adjustments to DG-2 speed in order to match the system frequency. Initiate a
Close of the DG-2 Incomer CB by switching the corresponding control switch (18S1) to
‘CLOSE’ upon reaching synchronism (when the Synchroscope reaches the 12 o’clock
position). The New Essential SWBD is now powered by both DG-1 and DG-2.
8. Confirm operation status as indicated by the corresponding pilot lamps on the SWBD.

The following priority essential loads can now be started as required:

Utility (Marine) & Safety Systems Equipment


STARTING
SWBD LOCATION TAG NUMBERS DESCRIPTION
SEQUENCE
1 82-EN-5501-S2-1 97-GK-0002 No.1 E/R Ventilation Fan
2 82-EN-5501-S2-2 97-GK-0003 No.2 E/R Ventilation Fan
3 82-EN-5501-S13-1 51-PA-0500A-DE Main Sea Water Cooling Pump A
4 82-EN-5501-S6-10 53-PA-0001-DE No.1 Main Fresh Water Cooling Pump
5 82-EN-5501-S7-1 82-ET-5501 General Lighting Transformer
6 82-EN-5501-S12-1 63-KC-0500A Air Compressor A
7 82-EN-5501-S8-8 97-EC-0900 Chiller Units & CHW Pumps
8 82-EN-5501-S7-6 97-EC-0907 NSR CHW AHU
9 82-EN-5501-S7-7 97-EC-0908 ECR CHW AHU
10 82-EN-5501-S7-3 97-GK-0905 Vent. Fan Group Panel
11 82-EN-5501-S7-2 97-EC-0906 Group CHW AHU & DX A/C Panel

Page 9 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

12 82-EN-5501-S7-10 97-EC-0903 E-Deck CHW AHU & DX A/C Panel


13 82-EN-5501-S7-5 97-EC-0904 B-Deck Mess Room CHW AHU
14 82-EN-5501-S7-8 97-EC-0901 Refrigeration Provision Panel
15 82-EN-5501-S2-3 97-GK-0004 No.3 E/R Ventilation Fan
16 82-EN-5501-S2-4 97-GK-0005 No.4 E/R Ventilation Fan
17 82-EN-5501-S2-5 97-GK-0006 Purifier Space Exhaust Fan
18 82-EN-5501-S2-6 97-GK-0001 Pump Room Exhaust Fan
19 82-EN-5501-S13-3 51-PA-0500B-DE Main Sea Water Cooling Pump B
20 82-EN-5501-S6-6 53-XK-0500 Fresh Water Generator
21 82-EN-5501-S6-5 66-XF-0500 Sewage Treatment
22 82-EN-5501-S6-3 98-EU-0500A ICCP AFT

Boiler & STG Auxiliary Equipment (A System)


STARTING
SWBD LOCATION TAG NUMBERS DESCRIPTION
SEQUENCE
1 82-EN-5501-S11-10 80-EC-9001 STG-A Turbine Control Panel
2 82-EN-5501-S10-1 62-PA-8001 Boiler Feed Water Pump A
3 82-EN-5501-S11-4 62-PG-8001 Boiler MDO Pump A
4 82-EN-5501-S9-3 55-KE-9000 Gland Condensate Fan A
5 82-EN-5501-S8-1 55-PA-9001 No.1 STG-A Condensate Pump
6 82-EN-5501-S11-1 67-KE-8101 Combustion Air Fan A
7 82-EN-5501-S11-9 55-XQ-8101 Boiler A Chemical Dosing Pump

After the successful Dead-Ship start-up, the DGs shall be shutdown normally and their controls
be returned to ‘Auto Standby Mode’.

5.3 ENERGIZING THE NORMAL SWITCHBOARD FROM THE NEW ESSENTIAL


SWITCHBOARD, IF REQUIRED FOR OPERATIONAL REASONS BEFORE
MAIN POWER IS AVAILABLE FROM THE STGs
The incomer CB from the NESB at the Normal Switchboard B can be close only on the following
conditions:
1. The outgoing CB at the NESB to the Normal Switchboard B is closed.
2. Both the incoming CBs from transformers 80-ET-4001A and 80-ET-4001B are open
respectively.
3. PMS permissive command to close the tie breaker is enabled.

Page 10 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

4. Verify that all CBs at the Normal Switchboards A and B are open.
5. With a permissive command from the PMS is enabled, close the incoming tie breaker at the
Normal Switchboard.
6. Closed the CBs permitted by the PMS (such as feeders for Mid-ship Crane and Normal
Lightings Transformers, and Subsea lightings) as may be required by the Operation. The rest
of the loads shall be inhibited by the PMS.
7. The incoming tie breaker at the Normal Switchboard will be open before synchronising the
DGs to the STG.

5.4 START STEAM TURBINE GENERATORS 80-EG-9000 and 80-EG-9100 (Manual-


Start) AND POWER-UP PROCESS LOADS
Prior to starting the Steam Turbine Generator confirm all preparations on the 6.6kV Main
Switchboard are complete sufficient to receive voltage/power (i.e. initially racking-in VCB into
‘SERVICE’ position - STG-A (80-EG-9000) at 80-EH-5001A, Cubicle 9.). This decreases the risk
of a potential ‘flash-over’ by minimizing the amount of ‘intrusive’ activities on a potentially live
system and thus ensures increased safety for personnel.
E&I Supv/Electrician is to carryout pre-check of all circuit breaker status/alarms prior to starting
STG.
The Turbine Generators onboard the FPU shall be started following manufacturers
design/recommended starting procedure. The following procedure (assuming STG-A shall be
started) shall be implemented in accordance with the manufacturer’s operating manual.Verify the
minimum requirements in Section 4.3 have been established.

Page 11 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

1. Confirm that all alarms, if any, have been investigated, cleared and reset.
2. Check steam turbine generator lube oil reservoir level ensuring it is free of contaminants i.e.
water or other foreign bodies. Replenish the lube oil system if level is less than normal
operation.
3. Start the lube oil priming pump from the local station (COS-PR set to ‘START’ position) and
check the lube oil pressure.
4. Confirm that the STG oil system has available lube oil pressure of 1.0 ~ 1.5 barg and control
oil pressure of 7.0 ~ 9.0 barg. Change the priming oil pump to ‘Auto Mode’ (COS-PR set to
‘AUTO’).
5. Switch Emergency Oil Pump change-over switch (COS-EQP) to AUTO so that it will
automatically starts when oil pressure drops below 0.2barg.
6. If required, the Turning Gear Motor can be manually started when lube oil pressure is above
0.5barg by activating the push-button PB-TM. This will initiate ‘barring over’ of the STG at
speed specified by the manufacturer (refer to manufacturer’s operating manual) while the
start-up operation is in-progress.
7. Confirm vacuum condenser (55-HE-9001) condensate to be at normal level ½ level (refer to
manufacturer’s operating manual). Start STG-A Condensate Pump Motor No. 1 (55-PA-
9001A). Switch the pump to ‘Auto Mode’ to ensure that the level is maintained all the time.
8. Start Engine Room Main SW Cooling Pump Motor A (51-PA-0500A-DE). Confirm that cooling
water to the vacuum condenser is available at the required pressure min 0.5 bar (refer to
manufacturer’s operating manual). Confirm sea water valves for gland steam condenser are
opened. Confirm sea water cooling/fresh water cooling valve for STG LO Cooler, STG
Generator air cooler are opened.
9. Start vacuum the Vacuum condenser (55-HE-9100/55-HE-9001) by open steam supply valve
to Vacuum condenser steam ejector, and confirm that vacuum are increased at normal value
- 0.9 bar. And open condensate valve from Steam ejector to Vacuum condenser.
10.Confirm Gland Condenser (55-HE-9000) condensate to be at normal level (refer to
manufacturer’s operating manual). Start the Gland Condenser Fan (55-KE-9000) and bring up
the vacuum in the Gland Condenser to normal pressure – 0.05 bar (refer to manufacturer’s
operating manual).
11.Confirm that turbine casing drains and drains on the steam line going to the turbine are all
open. This is to drain any condensed water from the steam line to avoid excessive hammering
and vibration while starting the steam turbine generator.
12.Fully open the main steam inlet valve for the steam turbine generator.
13.Adjust the gland steam pressure to normal level 0.01-0.2 barg (refer to manufacturer’s
operating manual).
14.Confirm that the condensate vacuum, gland steam pressure, steam inlet pressure, and lube oil
pressure are normal.
15.Start the steam turbine generator from the local station and close the drain in the steam lines.
16.Check steam pressure.
17.Check condenser vacuum and water level.
18.Check lube oil pressure and vibration levels.
1. Once STG is at rated speed 1800rpm and handed over from Utility Operations, check turbo
generator speed, voltage, frequency, vacuum, condenser level and other parameters.
2. Transfer control from local control panel (STG-A TCP) to remote station MV Switchboard (80-
EH-5001A).
3. Confirm all other parameters by checking the panel-mounted meters.

Page 12 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

4. At the MV SWBD Busbar Metering Panel-A (80-EH-5001A, Cubicle 8) set


AUTO/OFF/MANUAL selector switch SMA to ‘MANUAL’.
5. Set LOCAL/REMOTE (S41, Cubicle 9) selector switch
to ‘LOCAL’.
6. With the STG running at stable voltage and frequency, close the generator vacuum breaker on
dead bus by switching the CB Control TRIP/N/CLOSE switch (CS1) to ‘CLOSE’ at 80-EH-
5001A , Cubicle 9. The MV SWBD 80-EH-5001A is now powered from the STG-A (80-EG
9000). This will also energize MV SWBD 80-EH-5001B since the MV Bus Coupler (80-EH-
5001A/B is normally open.
7. Switch ON feeder to Distribution Transformer (80-ET-5501) to New Essential SWBD and
confirm its secondary voltage at 440Vac at the New Switchroom (NSR).
8. At the New Switchroom (NSR) switch the LOCAL/REMOTE selector switch (19S01) at panel
S-19 (Incomer from Transformer 80-ET-5501) to ‘LOCAL’.
9. Synchronized 80-ET-5501 secondary voltage to New Essential Switchboard (82-EN-5501)
voltage by switching TRIP/CLOSE CB Control switch to ‘CLOSE’ when the paralleling relay
(HAS-111DG) SYNC lamp turns green.
10. Transfer loads from the Essential Generators (DG-1 and DG-2) to STG-A (80-EG-9000).
load transfer is completed, open the DG CBs and stop the engines normally.
11. Energize the distribution transformers (refer to Section 7.2) and proceed in normalizing
process loads manually or through the PMS.

6 BLACK-OUT RE-START SEQUENCE OPERATION


6.1 START EMERGENCY DIESEL GENERATOR 84-EG-5001 (Auto-Start) AND
POWER-UP EMERGENCY LOADS
1. The EDG shall be in AUTO MODE to perform auto-start during a black-out re-start.
2. When the minimum requirements in Section 4.1 have been established, a ‘start permissive’
signal will start the EDG automatically.
3. Once rated speed, voltage & frequency are establish and the interlocking parameters on
incoming tie-breaker from essential switchboard are satisfied as pre-loaded in PMS, a
permissive signal will close the EDG’s breaker. The ESB is now powered by EDG.
4. If auto function fails, operator and E&I shall perform the necessary sequence manually.
5. After a successful start-up of the EDG, a ‘start permissive’ signal will be available to the DGs
to commence auto-start sequence as programmed in the PMS.
6. The required emergency loads connected to the ESB can now be switched ON as permitted
by the PMS.

6.2 START ESSENTIAL DIESEL GENERATORS 82-EG-5501A and 82-EG-5501B


(Auto-Start) AND POWER-UP ESSENTIAL LOADS
1. The DGs shall be in AUTO MODE to perform auto-start during a black-out re-start.
2. When the minimum requirements in Section 5.2 have been established and a ‘start
permissive’ signal is available the pre-selected DG will start automatically.

Page 13 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

3. Once rated speed, voltage & frequency are establish and the interlocking parameters on
incoming breaker from MV switchboard and the pre-selected DG are satisfied as pre-loaded
in PMS, a permissive signal will close the DG breaker. The NESB is now powered by DG-1 or
DG-2 whichever is selected. The second DG will auto start after 10 seconds depending on
load requirement as determined by PMS
4. Restart the E/R Main seawater cooling pumps after NESB energized by DG1/DG2
5. If auto function fails, operator shall perform the necessary sequence manually.
6. After a successful start-up of the DGs, the outgoing ESB Feeder CB at the NESB shall be
closed manually, and then the EDG will be manually synchronized to the DG supply by
closing the incomer No. 2 CB at the ESB.
7. By default both DGs when in ‘Island Mode’ (single/parallel) will be operating in isochronous
mode and automatically share load between them. The operation mode can be switched to
droop mode through the PMS.
8. Item 8 in Section 5.2 will be performed manually or as permitted by the PMS.

6.3 START STEAM TURBINE GENERATORS 80-EG-9000 and 80-EG-9100 (Auto-


Start) AND POWER-UP PROCESS LOADS
One STG is sufficient for normal plus off-loading operation. The standby STG shall be started
only if PMS finds it necessary due to start-up of large motors, operational activities which require
additional power, etc. When both the STGs are running, their digital excitation controls shall be
set for parallel operation by opening the unit/parallel contact at terminal A35-A36.
The steam turbine is started only manually (refer to Section 6.3, items 1~20), but the main
vacuum breaker can be closed manually at local (refer to Section 6.3, items 21~23) or remotely at
the MV SWBD automatically as described below. The procedure below refers to STG-A which is
also applicable to STG-B.
E&I Supv/Electrician is to carryout pre-check of all circuit breaker status/alarms prior to carrying
out any switching operation below.

Page 14 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

1. With steam turbine in normal operation turn selector switch SMA at the MV SWBD-A (Cubicle 8)
to ‘AUTO’. (At cubicle 13 for STG-B).
2. Select ‘REMOTE’ for the LOCAL/REMOTE selector switch S41 at the MV SWBD-A (Cubicle 9).
(At cubicle 12 for STG-B).
3. The STG-A (80-EG-9000) main circuit breaker will close automatically with a ‘close’ order from
the generator protection relay SEPAM G87 via PMS directly on ‘dead bus’ (or through a
synchronizer on ‘live bus’). This will power up 80-EH-5001A including 80-EH-5001B through a
normally close MV bus coupler 80-EH-5001A/B.
4. Switch ON feeder to Distribution Transformer (80-ET-5501) to New Essential SWBD and confirm
its secondary voltage of 440Vac at the New Switchgear Room (NSR).
5. At the New Switchgear Room (NSR) the LOCAL/REMOTE selector switch (19S01) at panel S-19
(Incomer from Transformer 80-ET-5501) shall be in ‘REMOTE’ position for auto-closing of the
transformer secondary breaker.
6. Upon issuance of close command from PMS, the NESB Transformer (80-ET-5501) Incomer CB
will close automatically on ‘dead bus’ (via DG incoming CB’s interlock – 16KDG or ‘dead bus’
functionality of paralleling relay HAS-111DG). On ‘live bus” it will close through a paralleling relay
(HAS-111DG) on synchronism.
7. Transfer of loads from the Essential Generators (DG-1 and DG-2) to STG-A (80EG-9000) will be
executed automatically upon initiation of the ‘AUTO LOAD TRANSFER’ sequence from the PMS.
8. Once auto load transfer of the DGs is completed, the PMS opens the DG air circuit breakers and
put the DGs off-line. Once off-line, the control of the DGs must be manually returned into AUTO
STANDBY condition.
9. The network is now configured in Normal Operating mode of supply.
10. Process loads (Normal Consumers) can now be put on line manually or through the PMS (refer to
section 8.2 below).

7 OTHER STARTING PROCEDURES


7.1 BASIC PROCEDURE FOR STARTING THE BOILER SYSTEM
The following are basic steps that must be followed in accordance with the manufacturer’s
recommended procedures (MB902923-800 / 4059-FD-00206699) for starting with reference to
STARBOARD Boiler, 55-FB-8101 (Applicable also for PORT Boiler, 55-FB-8201):
1. Ensure that the vent valve on the boiler (55-FB-8101) is open and check there is no pressure
in the boiler.
2. Check that the steam stop valve (55-GB-8134) is closed.
3. Check that all the valves for fuel are open and let the fuel circulate through the system (refer
to doc. nos. 4059-XB-00191528.001/00191648.001) until it comes to the required
temperature (MDO: ambient / Fuel Gas: 30~40°C).
4. Check and open the feed water valves (55-GB-8131 & 55-GB-8132) to the boiler and fill the
water inside the boiler drum to just above the low water level. This is done because it is not
possible to start the boiler below the low water level due to safety feature which prevent boiler
from starting. Also, the level is not filled much because if filled too much, the water inside the
boiler might expand and over pressurize the boiler.
5. Start the boiler in automatic mode. The Combustion Air Fan (67-KE-8201) will start the
purging cycle which will remove any gases present in the furnace by forcing it out through the
funnel.
6. After the pre-set purge time (not less than 5 minutes) the pilot burner (55-IG-8101) will ignite.
The pilot burner consists of two electrodes, through which a large current is passed, via a
high-voltage step-up transformer, producing the spark between the electrodes. The pilot
burner will ignite on a pre-selected fuel (either MDO or Fuel Gas or both).

Page 15 of 16
Dead Ship Start-up and Blackout Restart Procedures for
BW Joko Tole
Doc. no: DOCID

7. The main burner which is supplied by a pre-selected fuel catches fire with the help of pilot
burner after which the Boiler will operate automatically according to the selected mode of
operation.
8. Check the combustion chamber from the sight glass (as well as in the Boiler Control System
screen) to ensure the burner has lit and the flame is satisfactory.
9. Keep a close eye on the water level (55-LT-8101/8102) as the pressure increases and open
the feed water when the level of water inside the gauge glass is stable.
10. Close the vent valve after the steam starts coming outside.
11. Open the steam stop valve (55-GB-8134).
12. Once the working steam pressure is reached, blow down the gauge glass and float chambers
to check for the alarms.

7.2 ENERGIZATION OF 80-ET-4001A/B and 82-EN-4001A/B NORMAL


SWITCHBOARDS
1. At 82-EN-4001A/B 440 V Normal Switchboard, confirm all ACB’s are in the ‘OPEN’ position
(including the Bus-tie and the Tie Feeder Breaker to the New Essential SWBD).
2. Close 80-EH-5001A-cub.7 – Out-going Feeder to Transformer 80-ET-4001A. Confirm
energizing of the Transformer by monitoring correct secondary bus voltage on the PMS
graphic.
3. Close 80-EH-5001B-cub.14 – Out-going Feeder to Transformer 80-ET-4001B. Confirm
energizing of the Transformer by monitoring correct secondary bus voltage on the PMS
graphic.
4. Close 82-EN-4001A-S7-1 via the PMS, Confirm INC.1 closes by verifying the change in state
on the PMS graphic and monitoring the bus-volts.
5. Close 82-EN-4001B-S9-1 via the PMS, Confirm INC.2 closes by verifying the change in state
on the PMS graphic and monitoring the bus-volts.

The 440Vac Normal Switchboards 82-EN-4001A/B are now independently available. Normal
consumers for the Process Systems can be started.

8 SPECIAL RECOMMENDATIONS
8.1 Standby Personnel
In the event of a power system outage and where intervention from the ICSS is not immediately
available, it is recommended that Operations EIT personnel shall be on stand-by to provide
additional support in order prevent prolonged delays to the re-starting of equipment.
8.2 Purge Sequence for running Fuel Gas Compressors
The Fuel Gas Compressors are equipped with a ‘Thermal Lock-out’ protection scheme which
when activated will prevent the machines from being re-started for 4-hours unless the Purge
sequence is initiated. If not available within the ICSS, this function shall be manually activated.
8.3 Black-out /Dead-ship Restart with only one DG available
This scenario is foreseen when one of the two DGs is under maintenance. The largest motor to
be started during the restart is the 150kW Boiler Combustion Air Fan. The starting of this motor
was simulated with all possible non-essential loads shedded but the voltage dip (22%) during
starting exceeds the Class requirement of 20% or less.
To make this scenario possible, soft-starter was provided for each of the two Boiler Combustion
Air Fans (67-KE-8101 and 67-KE-8201). With soft-starter, simulation shows that voltage dip
during starting was less than 18%. The simulation was done using ETAP Electrical Engineering
Software version 7.5.0C.

Page 16 of 16

You might also like