Professional Documents
Culture Documents
WTC 2020 - Full Paper 4 (REM Lining) - 414 - Final
WTC 2020 - Full Paper 4 (REM Lining) - 414 - Final
May 2020
Design of Precast Concrete Segmental Lining for the Montreal Express Link (REM)
Airport Tunnel
M. Bakhshi1 and V. Nasri1
1
AECOM, New York, USA
E-mail: mehdi.bakhshi@aecom.com
ABSTRACT: The Réseau Express Métropolitain (REM) will be the fourth largest electric and fully-automated light-rail transit network in
the world designed to facilitate mobility across the Greater Montreal region in Canada. REM will connect downtown Montreal to the airport,
requiring the development of an entirely new 3.6 km long bored tunnel that runs below the international airport runways. This 7m-diameter
tunnel will be excavated by a hybrid TBM that progresses through saturated soft ground and competent rock. Simultaneous installation of
precast fiber-reinforced concrete (FRC) segments provides initial support and final lining for 125-year intended service life of tunnel. This
paper discusses the implementation of the structural and geotechnical analyses on the design of FRC segments for governing load cases
occurring from the time of segment production to the final service stage. Three-dimensional (3D) nonlinear finite element analyses (NFEA)
on TBM thrust jack forces and 3D NFEA TBM excavation simulations are presented. Structural demand is compared with nominal capacity
of FRC segments which is validated by statistical analyses performed on 100s of specimens tested in the segment precast plant.
KEYWORDS: Design, Durability, Finite Elements, Fiber, FRC, Grout, Internal Forces, Jack Force, Lining, Segment, Simulation, TBM
2. SEGMENTAL RING GEOMETRY AND SYSTEMS Longitudinal and circumferential joints were designed as
completely flat joints which are advantageous for load transfer
Based on the geotechnical challenges and evaluation of cost between the segment joints and the rings compared to other types of
estimate and risk mitigation, it was concluded that shielded TBM joints. Also, flat joints have been proven to have a superior sealing
with one-pass lining system is the preferred alternative for the REM performance. Bolt connection was designed for longitudinal joints
airport tunnel. With 6.478 m as the internal diameter of the tunnel,
and dowels were chosen for connecting rings in circumferential
300 mm was selected as the thickness of segments which is the joints as they require less work for the construction of the segment
common value used in practice for this size of tunnel. Lining form and less manpower in the tunnel with the insertion is
thickness was verified during the detailed design. Optimized length automatically performed by the erector when the segment is
of the ring (segment width) was selected as 1700 mm. As shown in positioned.
Figure 2, a 6+1 rhomboidal system assembled ring by ring was For the first time in North America, a new dowel system shown
selected. It consists of a trapezoidal reverse key segment slightly in Figure 3, SOF FAST 60, was designed as the connection device
larger than other five full-size rhomboidal segments and one small system in circumferential joints. This dowel is made with new
trapezoidal key segment, slightly smaller than 1/3rd of length of
plastic materials that have a higher resistance than current dowel
ordinary segments. Ring segmentation into these seven segments systems, is not sensitive to the humidity and consequently reduces
results in segment slenderness/aspect ratio (segment curved length- the displacement as much as possible. Integration of a screwable
to-thickness) of 10.7-11.4 which is near the maximum ratio used in socket on one side of the joint reduces the installation tolerance and
the world for FRC segments (Bakhshi and Nasri 2018). This will provides the workers with a smoother assembly process.
result in a smaller number of segment and joints, stiffer segmental The gasket type for sealing joints between segments, as shown
ring, reduced production cost as well as less hardware for segment in Figure 4, was designed as fiber anchored gasket. This new
connection, less gasket length and a smaller number of bolt pockets technology offers additional pull-out resistance comparing to
where leakage can occur. More importantly, the construction speed conventional glued gasket system and has several advantages over
can increase significantly. In addition, advantages of using a
anchored gaskets such as reduced risk of incorrect installation and
rhomboidal system include staggered longitudinal joints, continuous reduced risk of air entrapment in the anchorage area. Gasket Profile
ring building and compatibility with a dowel type connection in is DATWYLER M 802 07 “type South Hartford” providing
circumferential joints, which results in a faster ring assembly watertightness under the maximum expected groundwater pressure
process comparing to bolt type of connection in rectangular systems. of 965 KN/m2 (9.6 bar). This gasket profile guarantees
Universal rings were selected for this project assembled from watertightness for 2.0 times the maximum working water pressure
rings with circumferential joints inclined to the tunnel axis on both considering a combination of gasket differential gap of 5 mm and
sides. Main advantages of this ring system over other systems (e.g. bearing surface offset of 10 mm.
left/right rings) is using only one type of formwork set for segment
production.
(b)
Figure 2 Segmental ring: a) section; b) developed plan on intrados
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020
3. CONCRETE MIXTURE FOR SEGMENTS compressive strengths at stripping age and 28 days are 49 MPa and
13 MPa, respectively.
An optimum concrete mix design was selected for REM tunnel
segments to achieve a high early-age strength as well as a high
performance and a durable concrete lining for 125 years intended
service life of the project. Maximum water cement ratio is set as
0.35 with the addition of silica fume and ground granulated blast-
furnace slag in the level of 5 and 22 percent of cementitious
materials, respectively. Minimum cementitious material content is
selected as 485 kg/m3 and maximum aggregate size as 14 mm while
chloride ion penetrability should be less than 700 coulombs
following ASTM C1202 (2019). Precast segments for REM airport
tunnel are made of FRC which are superior to Reinforced Concrete
in the crack control and are more cost effective.
(a)
4. DETAILED DESIGN PROCEDURE
At the final design stage, segment dimensions are known (Section
2), and the focus is on verification of specified tensile/flexural and
compressive strength of FRC segments. Following ACI 544.7R
(2016) guidelines, the design was carried out using the load and
resistance factor design (LRFD) method. The nominal design
strength of FRC segments (capacity) is compared with required
strengths (demand) for major governing load cases during segment
production, transportation, construction and final service stage. FRC
strength parameters should be specified sufficiently to satisfy
Ultimate Limit State (ULS) design, as well as cracking, and
Serviceability Limit State (SLS) design.
(a) (b)
(c)
Figure 7 (a) Stripping in the segment precast plant; and (b) forces
Figure 6 Nominal results of specified FRC mixture: (a) experiments vs. acting on segments for Load Case 1
simulation for standard beam test response, (b) back-calculated tensile
and compressive responses
Load case 2 in this stage is the segment storage. Segments are
stacked in the precast plant following the stripping process prior to
In summary, Table 2 presents 28-day and stripping strength gaining their specified 28-day strength. Surfaces of precast segments
parameters that are initially specified for the REM Airport Tunnel are covered with curing compound and kept under controlled
segments. Residual flexural strength (fD150 or fR,3k) or residual ambient condition for several days until they reach their specified
tensile strength (s) are the main parameters for Ultimate Limit State strength. All segments of a ring are typically stacked together as a
(ULS) conditions. For Serviceability Limit State (SLS) design, single stack. As shown in Figure 8, wood blocks supporting the
cracking moment is determined based on the parameter ftensile,crack stacks are placed at the ground level and in between each of the
and in case exceeded when the service bending moment (Ma) is too segments. Some eccentricities can occur between the stack supports.
high, the fD600 or fR,1k parameter can be used as post-crack residual An eccentricity of e = 100 mm is usually recommended for design
strength for the service design. In order to make the design (ACI 544.7R, 2016). In addition to the bending moment caused by
procedure independent of the type of selected code, i.e. ACI 544.7R the self-weight (w = 12 kN/m) of the segment being analyzed, the
(2016) or fib Model Code 2010 (2013), the smaller of f’ D150 and fR,3k weight of the segments above (F1 = 86.26 kN) and the eccentricity
and the smaller of f’D600 and fR,1k are taken into account for the ULS of the upper stack supports (e) must be taken into account. The
and the SLS designs, respectively. worst-case scenario is when the wood blocks supporting the second
Table 2 Specified FRC strength parameters for REM airport segment from bottom is subjected to an inside eccentricity while the
tunnel segments (MPa) weight of segments positioned above (F1 = 86.3 kN) are applied
Age f'tensile f'SLS f'ULS σp f'c with an outside eccentricity with respect to the originally designed
crack wood block location. This results in combining two eccentricities
Stripping Age 1.4 1.7 2.3 0.8 13 and therefore considering a value of e = 2×100 mm or 200mm. This
28 days 2.8 3.8 4.6 1.6 49 stage can be reasonably modeled using a simply supported beam
that is loaded under the forces shown in Figure 8 (b). Similar to
6. DESIGN - PRODUCTION AND TRANSIENT STAGES previous load case, applied load factors for ULS and SLS are 1.4
and 1.0, respectively, according to ACI 544.7R (2016). For ULS,
Load case 1-stripping represents the effect of lifting and stripping of maximum factored bending moment for this load case is calculated
the precast concrete segments from the formwork at the precast as 35.2 kN-m while unfactored bending moment for SLS (Ma) is
plant once specified strength of concrete has been reached. The 25.1 kN-m. As presented in Table 3, these values can be compared
operation method that is used is the mechanical lifting with with the same early-age ULS resistance and SLS cracking moments
clamping (Figure 7). The segments can be modeled as two (Mcr) of 41.8 kN-m and 35.2 kN-m as in load case 1, respectively.
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020
(a)
(a)
(b)
(b)
Figure 9 Load case 3: (a) schematics of segment handling with
the forklift; and (b) forces acting on bottom segment
Figure 8 Load case 2: (a) segments piled up within one stack for factors of 1.4 and 1.0, maximum ULS factored bending moment and
storage; (b) forces acting on 2nd segment from the bottom SLS unfactored bending moment (Ma) are obtained as 27.5 kN-m
and 19.6 kN-m, respectively. As shown in Table 3, these values are
Load case 3 is the segment handling which is carried out in the smaller than the ULS resistance bending moment (82.5 kN-m) and
precast plant and from the stack yard onto trucks and rail cars by SLS cracking moment (70.7 kN-m) at 28 days.
specially designed lifting devices such as forklifts and vacuum
lifters as soon as specified 28-day strength has been achieved. Inside
TBM, segment handling is also typically performed by vacuum
lifters. In this project, the most critical handling load scheme is
handling by forklifts at lift points spanning usually wider than the
stack supports at 1.9 m. As shown in Figure 9 (a), half of the ring’s
segments are picked up together by the forklift within one stack. The
worst-case scenario is for the bottom segment to be subjected to the
weight of segments positioned above (F2 = 45.90 kN) spanned over
1.4 m of projected length of the segment. An unfavorable
eccentricity of 100 mm (ACI 544.7R) is considered for both wood Figure 10 Load case 4: half-ring stack scheme in transportation
blocks and lifting points. A simply supported beam loaded with all
aforementioned forces including the self-weigh (w = 12 kN/m), as 7. DESIGN FOR CONSTRUCTION STAGES
shown in Figure 9 (b), is used to represents this load case. In
addition to the dead load factor of 1.4 and 1.0 for ULS and SLS 7.1 TBM thrust jack forces
respectively, a dynamic shock factor of 2.0 recommended by ACI
After assembly of a complete ring, TBM advances by thrusting
544.7R-16 is considered for the jarring forces acting on segments
against the jacking pads placed along the exposed circumferential
during the handling. The maximum factored bending moment in joints of most recent assembled ring (load case 5). Selected TBM
ULS and unfactored bending moment in SLS (Ma) are calculated as
has a total nominal machine thrust, Fn, of 50,192 kN and total
71.5 kN-m and 51.1 kN-m, respectively. Since segments are only
exceptional machine thrust, Fmax, of 58,796 kN. Total number of
reinforced with fibers, ULS key design parameters of σp (1.6 MPa)
thrust cylinders is 19, and the width and surface area of jack pads
and f’ ULS (4.6 MPa), and SLS key design parameters of ftensile,crack
(Apad) are 150 mm and 119,819 mm2, respectively. Maximum
(2.8 MPa) and f’SLS (3.8 MPa) at 28 days are considered for design.
nominal eccentricity, en, and maximum exceptional eccentricity,
Following Equation (1) and using a strength reduction factor of 0.7,
emax, of jack pads in the radial direction are considered 30 mm and
ULS resistance bending moment and SLS cracking moment (Mcr) at 40 mm, respectively. This load case is simulated by three-
28 days are obtained as 82.5 kN-m, and 70.7 kN-m, respectively.
dimensional non-linear finite element method (3D NLFEM) using
Therefore, as shown in Table 3, the capacity of FRC segment is
DIANA FEA considering exact parallelogram shape of segments
greater than the structural demand.
with longitudinal joint tapering angle of 8.5o, and exact locations of
Load Case 4 is segment transportation. Segments are transported
thrust pads in actual non-symmetric pattern with respect to the
to the jobsite after specified strength have been achieved in the
segment centerline and segment edges. As shown in Figure 11 (a),
precast yard. During transportation, the segments generally undergo
recesses in the segment joints due to the gasket and stress relief
various types of dynamic shock loading. In this project, half of the
grooves were also accurately modeled. Considering recesses,
segments comprising one ring are transported in one stack to the
available width of segments for contact with thrust pads at the
construction site and then to the TBM trailing gear (Figure 10).
circumrenal joints is only 200 mm. Therefore, extreme eccentricities
Wood blocks are used between the segments as stack support. The
may result in a reduced contact area with segments and
worst-case scenario is when the bottom segment, in addition to self-
consequently an increased pressure on the contact zone that has been
weight (w = 12 kN/m), is subjected to the eccentric (e = 10 mm)
considered in this design. All possible combinations of maximum
dead weight of segments positioned above (45.9 kN). This stage can
nominal and maximum exceptional values of eccentricities and
be reasonably modeled using a simply supported beam similar to
thrust jack forces result in overall 10 jack force scenarios, each
schemes of loads shown in Figure 8(b). Considering a dynamic
defined by appropriate load factors of 1.0, 1.05, 1.2, which basically
shock factor of 2.0 (ACI 544.7R-16), and ULS and SLS dead load
present the likelihood of each scenario. Nominal stress-strain
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020
Table 3 FRC segments design checks for various load cases during the production and transient stages
Dynamic ULS SLS
Load
Case
Phase Shock MU, f'ULS, fMn, Ma, ftensile, crack Mn,
Factor kN.m MPa kN.m kN.m MPa kN.m
1 Stripping (5-6 h) - 13.1 2.3 41.8 9.4 1.4 35.2
2 Storage (5-6 h) - 35.2 2.3 41.8 25.1 1.4 35.2
3 Handling (28 d) 2 71.5 4.6 82.5 51.1 2.8 70.7
4 Transportation (28 d) 2 27.5 4.6 82.5 19.6 2.8 70.7
responses of FRC segments in compression and tension, as joints, and with joints modeled by the Janssen model (Figure 12(a)).
presented in Figure 6, are introduced to the FEM software as the Because the lining is surrounded completely by a semi-liquid fresh
material model. As shown in Figure 11(b), the circumferential grout with negligible interaction with the ground, an interface
bursting and spalling stresses under exceptional thrust jack forces element with a very low (practically zero) spring stiffness was used
and eccentricities reach the tensile strength of FRC segments. for simulation of this interaction. As results of analysis, significant
Therefore, cracking under such extraordinary conditions are axial forces and limited bending moments (Figure 12(b)) are
inevitable. However, as shown in Figure 11(c), due to high residual developed in the lining. The self-weight of the lining and the
(post-cracking) strengths of FRC, maximum crack width is below grouting pressure are the only loads applied to the tunnel lining at
0.2 mm criteria set by Project’s technical requirement. this stage, and therefore a load factor of 1.25 (ACI 544.7R 2016) is
applied on the axial forces and bending moments. As shown in
Figure 12 (c), for the design checks, these results are compared with
the axial force-bending moment (M-N) interaction diagram that was
constructed using σp and f’c at 28 days (Table 2).
(a)
(a) (b)
(b)
(c)
the primary hardened grout is modeled using radial springs with the sections along the entire alignment were selected and subjected to
segments supported radially. Considering a primary grout with f’c of this simulation. Figure 14(a) presents a typical result of this 3D
3 MPa and modulus of elasticity of 300 MPa, radial spring stiffness NFEA simulations in the format of internal bending moments in the
of 100,000 kN/m3 seems to be reasonable while tangential spring segmental rings. Since applying different load factors (ACI 544.7R
stiffness has taken practically zero. This load case as shown in 2016) for groundwater, to FE analysis is not viable, maximum load
Figure 13(b) results in very small axial forces with large bending factor of 1.35 has been applied on internal forces as results of
moments. Applying a load factor of 1.25 to these results, all points simulations. As shown in Figure 14(b), internal forces are compared
fall inside the designed M-N interaction diagram which validates the with structural capacity of FRC segments in the format of M-N
design for this load case. interaction diagrams which validate design of the segments.
(a) (b)
(a)
(c)
9. CONCLUSIONS
The structural analyses summarized in this report cover all main
load cases during the service life of precast segments from the
stripping from the formwork at early age production to the final
service stage. Reported results indicate that concrete segments
reinforced with 42 kg/m3 of double hooked-end high-strength steel
fiber provide sufficient strength and satisfy serviceability
requirements for the one-pass TBM-bored tunnel lining of REM
Airport Tunnel.
10. REFERENCES
ACI 544.7R. (2016) Report on Design and Construction of Fiber-
Reinforced Precast Concrete Tunnel Segments. American
Concrete Institute (ACI).
ACI 544.8R. (2016) Report on Indirect Method to Obtain Stress-
Strain Response of Fiber-Reinforced Concrete (FRC).
American Concrete Institute (ACI).
ASTM C1609 (2019). Standard Test Method for Flexural
Performance of Fiber-Reinforced Concrete (Using Beam with
Third-Point Loading). American Society for Testing and
Materials (ASTM).
Bakhshi, M., and Nasri, V. (2018) “Guide for Optimized Design of
Tunnel Segmental Ring Geometry”. North American
(a) Tunneling 2018 Proceedings, Washington DC, pp 541-549.
Bakhshi, M., and Nasri, V. (2017) “Design of Steel Fiber-
Reinforced Concrete Segmental Lining for the South Hartford
CSO Tunnel”. Rapid Excavation Tunneling Conference 2017
Proceedings, San Diego, CA, June 4–7, 2017, pp 706–717.
Conforti, A., Minelli, F., Plizzari, G.A. and Tiberti, G. (2018)
“Comparing test methods for the mechanical characterization
of fiber reinforced concrete”. Structural Concrete, 19, Issue 3,
pp 656–669.
Diana FEA. 2019. User's Manual – Release 10.3.
https://dianafea.com/
fib Model Code 2010 (2013). Model Code for Concrete Structures.
International Federation for Structural Concrete (fib).
Groeneweg, T. (2007) “Shield Driven Tunnels in Ultra High
Strength Concrete: Reduction of the Tunnel Lining
Thickness”. MSc Thesis, Delft University of Technology, the
Netherlands.
Nasri, V., De Nettancourt, X., Patret, P. and Mitsch, T. (2019)
“Design and construction of Montreal express link tunnels
and underground stations”. Rapid Excavation and Tunneling
Conference 2019 Proceedings, Chicago, pp 166-177.
(b)
Figure 15 Load case of longitudinal joint bursting: a) FEM model
representing governing cases, b) ULS bursting stresses