SR 34 PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 139

S

625.7 (94)
AUS
(SR 34)
-f .J .

Storm drainage design


in small urba AUSTRALIAN ROAD

catchments: RESEARCH BOARD


17 FEB 1987
l lB ? AR Y
a:A) =ve= "- " nmGIlO - nzm .- j ... _

a handbook for Australian practice


This Special Report was originally published in 1986. While the fundamental
design approach described is relevant and current, reference to recent
publications, such as the current revisions of Australian Rainfall and Runoff,
and the Austroads Guide to Road Design Part 5: Drainage: General and
Hydrology Considerations is suggested to ensure the most recent design
inputs and considerations are applied.

ARRB Group would like acknowledge and thank John R. Argue AO, Adjunct
Professor of Water Engineering, University of South Australia, for allowing
reproduction of Storm Drainage Design in Small Urban Catchments: a
handbook for Australian practice, 1986.

ARRB Group, 2013


STORM DRAINAGE DESIGN
IN SMALL URBAN
CATCHMENTS:
A HANDBOOK FOR AUSTRALIAN PRACTICE

By
John R. Argue
Principal Leeturer,
School of Civil Engineering ,
South Australian Institute of Technology

, 1.0
""'7
l .

AUSTRALIAN ROAD RESEARCH BOARD

South Australian Australian Road


Institute of Technology 1111111 11111 11111 11111 11111 111111111111111111 Research Bo~rd
0004077
CONTENTS
1. INTRODUCTION
1.1 Drainage Planning 1
1.2 Scope of this Handbook 2
1.3 Th e Goals of Urban Drainage (Quantity) Management 2
1.4 The Handbook and Goals 1, 2 and 3 3
1.5 Th is Handbook and Other Urban Drainage Publ icatio ns 3

2. FREQUENCY AND THE MAJOR/MINOR DRAINAGE SYSTEM


DESIGN CONCEPT 5
2.1 Introduction 5
2.2 Flood Classification 5
2.3 The Major/ Minor Flood Management Concept 6
2.4 Towards Design ARI : the Water Resources Approach 8
2.5 Design ARI - Major Drainage Systems 8
2.6 Design ARI - M inor Drainage Systems 9

3. RETENTION, DETENTION AND RETARDATION MEASURES IN


URBAN CATCHMENTS 11
3.1 Th e Natural Catchment and Urban Development 11
3.2 T erminal Retention Measu res 12
3.3 Non-Terminal Retention Measures 13
::J .4 Uetentlon Measures 15
3.5 Retardation Measures 16
3.6 I mplementation of Retention/ Detention/ Retardation
Measures in the Urban Environment 18

4. RAINFALl/RUNOFF MATHEMATICAL MODELS 19


4.1 Backgro und 19
4.2 Rational Method 19
4.3 Time-Area Representation 22
4.4 Why a 'New' Rational Method? 22
4.5 The Two-Value Rational Method 23

5. HYDROLOGICAL DATA BASE 25


5.1 Ultimate Development Assessment 25
5.2 Storm Rainfall Intensity-Frequency-Duration Data 25
5.3 Australian Climatic Zones - Urban Drainage 25
5.4 Design Average Recurrence Interval - Major/ Minor Systems 27
5.5 Travel Time Determ ination 28
5.6 Runoff Coefficients for Developed Catchments 31

6. HYDRAULIC DATA BASE 33


6.1 Open Channel Stormwater Drains 33
6.2 Gutter and Sag Inlets 36
CONTENTS Continued
6.3 Guidelines for the Management of Surface-Moving Flows in M inor Systems 39
6.4 Underground Networks : An Overview 39
6.5 Guidelines for the Management of Underground-Moving Flows 41
6.6 Minimum Grade Analysis HydrauliC Data 44
6.7 Hydraulic Grade Line Analysis Hydraulic Data 44
6.8 Tests for Pit Overflow and Pit Obvert Depth 48

7. URBAN DRAINAGE SYSTEMS : STRUCTURE 51


7.1 Introductio n 51
7.2 General Properties of Smal l Urban Catchments 52
7.3 Simple Urban Catchments 52
7.4 Complex Urban Landscapes 54

8. THE MAJOR DRAINAGE SYSTEM - DESIGN


PROCEDURE OUTLINE 57
8.1 Introduction 57
8.2 Major System Planning Procedure 58

9. THE MAJOR DRAINAGE SYSTEM - CASE STUDY


APPLICATIONS / 63
9.1 Introduction 63
9.2 Case 1 and Case 2 Developments: Steps 1-8 63
9.3 Non-Isolated Development Catchments 71
9.4 Concluding Comments and Summary 71

10. THE MINOR DRAINAGE SYSTEM - DESIGN


PROCEDURE OUTLINE 73
10.1 Introduction 73
10.2 Minor System Design Procedure 74

11 . THE MINOR DRAINAGE SYSTEM -


CASE STUDY APPLICATIONS 83

12. CONCLUDING DISCUSSION 105


12.1 Resume 105
12.2 Data Quality and Error in the Design of Min or Dra inage Systems 105
12.3 Stormwater Management Measures and the Illustrative Cases 107
12.4 Research Needs 107
12.5 Future Perspectives 108

REFERENCES 109

APPENDIX A Addit ional Hydraulic Data 115

APPENDIX B Forms for Use by Designers 125

SYMBOLS AND ABBREVIATIONS 129


AUSTRALIAN ROAD
RESEARCH BOARD
ThE: Australian Road Research Board is the focal point of road research in Australia . It
regularly undertakes and arranges road and road transport research over a compre-
hens ive range of subjects . The results of that research are disseminated to appropriate
organisations and to the scientists, engineers and associated special ists involved with the
design , location , construction , upkeep and use of roads. The need for a national research
centre was realised by NAASRA, the National Association of Australian State Road
Authorities , who founded the Board in 1960. In 1965 ARRB was registered as a non-profit
making company financed by Australia's Federal and State Government Road Authorities .
Each member authority is represented by its permanent head on ARRB 's Board of
Directors, whose policies are administered by the Executive Director.
All research is controlled from the Australian Road Research Centre at Vermont in
Victoria , but , since its inception , the Board has sponsored research conducted at
universities and other centres . The 1986-1987 overall program of the Board was budgeted
at $6.4m . The Board also relies on advice from its techn ical committees in Road
Technology , Road User Behaviour, Road Transport and Local Government and its
overseeing Steering Committee.
ARRB disseminates road research information through conferences and symposia and
through its publications . ARRB also maintains a unique library of road literature and
operates an expanding computer-based information service called Australian Road Index
which collects and collates all Australian road research findings. It also operates the
international IRRD data base of OECD in Australia .

DIRECTORS 1986-1987
M .J. Knight, B.Sc.(Eng.), M .Eng .Sc., F.I.E.Aust. , AFAI.M ., M .C.I.T ., Commissioner of
Highways, South Australia
I.F .X. Stoney, AA.S .A. , Dip.Bus.Studies, MAG.I., FAI.M ., Chairman and Managing
Director, Road Construction Authority , Victoria
D.H. Aitken , I.S.0., B.E. , F.I.E.Aust., F.C.I.T., FAI.M ., Commissioner of Main Roads ,
Western Australia
A .S. Blunn, L.L.B., Secretary, Commonwealth Department of Housing and Construction
E.F.F. Finger, B.E. , M.Eng .Sc ., F.I.E.Aust. , Commissioner of Main Roads, Queensland
B.G . Fisk, AR.S.M., B.Sc.(Eng .)(Met.), C .E., M.I.M.M ., Commissioner for Main Roads ,
New South Wales
C .W .M. Freeland, B.E.(Hons) , M .I.E.Aust., Secretary, Commonwealth Department of
Transport
I.D . Gordon, B.E., M.Eng .Sc., M.I.E.Aust., M.C .I.T., Secretary, Department of Transport
and Works, Northern Territory
P.J. Wettenhall, Director of Main Roads , Tasmania
M.G. Lay, B .C .E., M.Eng .Sc ., Ph .D., F.I.E.Aust. , F.C .I.T., M.ASCE, Execut ive Director,
Australian Road Research Board
Chairman: M.J. Kn ight
Deputy Chairman : I.F.X. Stoney
Executive Director: M.G. Lay

J.B. Metcalf, B.Sc ., Ph .D., F.G.S., F.I.E.Aust. , F.I.C.E.,


Deputy Director, Australian Road Research Board
R.J . Membrey, A.A .S.A., A.C. I.S., Secretary, Australian Road Research Board
INFORMATION
RETRIEVAL
AN D ABSTRACT
Th e abstrac ts and keywords o n thi s page are prov id ed in the interests of improved information retri eval. Eac h
refe rence card is designed so th at it c an be cut out and inco rporated in the reader's own file ,

Keywo rd s. un less ca rryi ng an asterisk . are from the ' International Road Researc h Documen tati on [lRRD)
Thesau rus. 1983' ,

ARGUE, J.R. (1986) : STORM DRAINAGE DESIGN IN SMALL URBAN


CATCHMENTS : A HANDBOOK FOR AUSTRALIAN PRACTICE. Australian
Road Research Board. Special Report SR 34. 130 pages including 90 figures and 2
appendices.

KEYWORDS Drainage/urban area/run off/planning/design(overall


design)/discharge(flow)lhydrologylhydraulics*/mathematical model/data base
ABSTRACT: The Handbook is the outcome of ARRB Project 391 and Feasibility
Study 1093 relating to storm drainage flow estimation, collection and disposal in
Australian urban (small) catchments. It reflects master drainage (runoff
qu antity) planning principles including on-site stormwater retention/detention
a nd the 'major/minor' approach to drainage design. Flow estimation procedures
a re based on the Two-Value Rational Method introduced in the Handbook. The
hy drological and hydraulic data bases include information and guidelines needed
to estimate runoff flows and plan/design surface drainage systems and
underground pipe networks for Australian urban sub-divisions. An eight-step
procedure is described for managing major storm runoff flows using such items
as roadway reserves, open space and flood way channels. The procedure is
applied to two 40 ha residential sub-divisions. An eleven-step procedure for
managing minor or nuisance flows is also described. This procedure is applied to
a 6 h a mixed development catchment and to a 12 ha residential sub-division. The
major and minor system design procedures are directly applicable to developed
catchments up to 20 ha. Larger catchments can be accommodated by appropri ate
linking. The appendises of the Handbook include hydraulic data applicable to a
range of gutter/pavement geometries and inlet types widely used in Australian
practice.

*Non IRRD Keywords

ISBN 0 86910 263 X Report


ISBN 0 86910 266 4 Microfiche
ISSN 0572 - 144X

DECEMBER 1986

Although this report is believed to be correct at the time of its publication , the Australian
Road Research Board does not accept responsibility for any consequences arising from
the use of the information contained in it. People using the information contained in the
report should apply , and rely upon, their own skill and judgment to the particular issue
which they are considering .
Reference to, or reproduction of this report must include a precise reference to the report.

Wholl y set uP. designed and printed at the Australian Road Resea rch Board . Vermont South. Victoria. 1986
ACKNOWLEDGEMENT
The contents of this Report have been strongly influenced by input from engineers and
technical officers employed in local government, consulting practices and government
authorities - Commonwealth and State - and from researchers and academic colleagues.
Each Australian state and territory is represented in this array. In addition , contact has
been made with a number of overseas researchers and authorities active in the urban
storm drai nage field , the majority of whom have responded generously to appeals for data
and advice.
To the following go the author's special thanks :
• Australian Road Research Board and Professor A .P. Mead, Director of S.A. Institute
of Technology for permission to publish the Handbook . Dr M.G . Lay , Executive
Director and Dr J.B . Metcalf, Deputy Director of ARRB for their encouragement and
help throughout the project.
• Mr D.P. Ritchie (Blacktown Council, N .SW.), Mr R.B. Saunders (S.A. Highways
Department) , Messrs B.C . Tonkin and P.K. Read (B.C . Tonkin & Associates,
Adelaide). Mr M.N . Clarke (N.S.W . Public Works Department) , Assoc . Professor
D.H. Pilgrim (U.N.SW.), DrG .G. O'Loughlin (N .S.W.I.T.), Mr R.J. Taylor (Techsearch
Inc .), and members of S.E. Queensland Local Government Engineers' Group for
support and technical advice.
• Mr J . Fox (Plantec Drafting Services, Adelaide) who was responsible for drafting the
bulk of the graphics and tables and an army of long-suffering ladies who helped with
typing, library searches or final editing / production - Mesdames C . Wilson,
R. Mielnik, S. Swann, L. Folland, P. Buxton, A. Girard , M. Holdsworth and J . Symons.
• Finally to my wife Jan and members of the Argue family go my heartfelt thanks for
their patience and support through the many vicissitudes of the 'drains' project.

Cover
The photograph shows Elizabeth Street, Melbourne during the major storm which struck the city in February
1972. The assistance of the Herald and Weekly Times Ltd in providing the photograph is gratefully
acknowledged.
PREFACE

In June 1979 Australian Road Research Board (ARRB) Project 1093 'Urban Stormwater
Collection Systems: A Review ' was commenced . The aims of the project were :
(a) to identify those practices about which there is general consensus among
practitioners and for which there exists a satisfactory data base ;
(b) to identify new procedures to replace existing practices where such new procedures
are considered necessary and/ or appropriate; and
(c) to indicate directions for new or continuing research to improve and/ or expand the
existing data base to a generally satisfactory level.
The report on Project 1093 (Argue 1981) recommended that a handbook be devised
by ARRB for Australia-wide use, bringing together best data and information available on
storm drainage design in small urban catchments . It recommended , also , that the
presentation of this material recognise the particular needs of an expected audience made
up of technical officers, newly graduated engineers and practitioners whose work does
not keep them in constant touch with the problems of urban drainage.
'Storm drainage design in small urban catchments : a handbook for Australian
practice' is the outcome of these recommendations .
The Handbook presentation reflects master drainage planning principles which have
been developed by leading practitioners in North America since the early 1970's. These
include an array of stormwater management options as well as the 'major/ minor'
approach to flood mitigation and stormwater control in urban landscapes. In keeping with
the 'teaching ' role recommended for the Handbook from its conception , this material is
presented in step-by-step form wherever possible, and includes detai led case study
illustrations. By this means, it is hoped , concepts and principles employed at present only
by leaders in the field of urban drainage design will penetrate Australian practice to its
'grassroots' level.
An important aspect of the Handbook's preparation , and a necesary condition for its
success , has been continued liaison with the compilers of other documents on urban
drainage and with potential users - engineers and technical support staff employed in
municipal engineering departments and c;onsulting practices. Draft versions of the
Handbook 's main design procedures have been subject to extensive review and revis ion .
The outcome is a document which offers drainage designers an approach that is in
harmony in all major respects with 'best' Australian practice and which is included among
the Rational Method and hydraulic design procedures advocated in Chapter 14 (Urban
Drainage Design) of the third edition of 'Australian Rainflal and Runoff' (Institution of
Engineers, Australia 1987) .
The procedures offered in the Handbook have wide application and if widely adopted
will introduce a measure of uniformity into small area urban drainage design practice in
Australia . Such standardisation, however, stops with the procedures: no attempt is made
in the Handbook to press for uniformity in the selection of roadside channel forms or
ancillary drainage network components. Nevertheless, hydraulic data for a range of
widely-used channel forms and components are included providing designers with the
opportunity to make their own assessments and comparisons of alternatives.
Such considerations may lead , in time, to some reduction in the variety of channels
and components presently used in Australian practice. While some economies may follow
this outcome, the main advantage would be an eventual improvement in the quality of
hydraulic data available for the most popular channel forms and components as a
consequence of more concentrated and effective research effort.
Introduction

1.1 DRAINAGE PLANNING the major/minor concept which recognises the


dual requirements of the drainage system to
When urban development takes place in a provide convenience on a day-to-day basis and
fo rested or rural c atchment significant areas protect i on for 1 i fe and property in major
of 1and and vegetat i on whi ch once absorbed storm events;
inc i dent rainfall and impeded its movement
through the catchment are replaced by
impervious surfaces interconnected by formal 2. Development plan: plans of all existing
networks of man - made surface and underground and proposed developments should be shown and
drainage lines. These changes lead to their relationships to the major/minor net-
works and present or likely runoff character-
increased flood peak flows and increased
istics, both in quantity and quality;
volumes of surface runoff within the catchment
area itself and in the downstream flow paths
taken by floodwater on its way to disposal. 3. Sto,..,ater retention/detention measures:
these should be identified for each land-use
Where such flooding occurs in an un - and group of such areas and should take
prepared urban landscape, distress ranging account of 1 and-use, drainage networks,
from inconvenience and financial loss to terrain and soil characteristics. The reten-
serious injury, possibly death, is exper i enced t i on and detention measures adopted in each
by members of the general public and there is basin sub-catchment should aim to retain,
damage to private property and community wher e appropriate, as much incident storm
facilties and installations. rainfall as possible;

New approaches to reducing the social,


financial and environmental impacts of 4. Sedi.ent and erosion control measures:
flooding resulting from unbridled urban these should be incorporated into the planning
deve 1opment of a basin cent re on the and construction phases of an urban develop-
preparation of a Master Drainage Plan which ment to minimise soil loss and ensure minimum
sets out appropriate and envi romentally- downstream environmental damage from water-
compati ble measures to confine these impacts borne sedi ment;
within acceptable l i mits. It identifies
existing problems and provides a framework 5. Pollution control strategy: this strategy
anticipating solutions to problems likely to should be matched to the particular land-use,
arise in the future. To these ends, the Plan drainage and runoff quality characteristics
should ind i cate existing drainage systems, experienced or likely to be experienced in the
areas sub j ect to development pressure, drain- bas in in the course of futu re deve 1 opment.
age channels subject to erosion, the location The purpose of the strategy is to ensure that
and nature of receiving waters, areas of hi gh runof f entering the recelvlng water domain
recrea t ional value, unique natura l environ - from the basin meets acceptable water quality
ments, significant heritage or cultural loca - criteri a •
tions, installations of strategic importance
for the nation or the local community, Master Drainage Planning principles appear
potential groundwater recharge areas, areas to have been app 1i ed fi rst in the Denver Area
containing soils of high permeability, areas Urban Drainage and Flood Control District,
containing soils which are highly reactive to U.S.A., when an agglomeration of 29 munici-
water (expansive clays), and any other factors palities sought to resolve their common
deemed necessary or appropri ate (Envi ronment problems of urban storm runoff quantity
Canada, 1980a). management (Wright-McLaughlin Engineers 1969).
Concern for the rapid degradati on of water
The f ive action segments of the Master quality in the Great Lakes in the late 1960's,
Drainage Plan are: early 1970's , caused the governments of the
U.S. and Canada to act on th i s problem and to
1. Major/.inor drainage networks: storm incorporate water quality aspects into
drainage systems for existing development basin-wide major drainage planning. The
should be shown together with systems fo r result is the comprehensive Master Drainage
proposed or likely development, at least i n Plan outlined above and well described in
outl ine. These networks should be based on Environment Canada (1980b).

ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

1.2 SCOPE OF THIS HANDBOOK located in f1 ood- prone 1andscapes


occurs on rare occasions only and
Thi s Handbook concerns itself with the water that in such events, velocity/depth
quant i ty aspects of mas ter drainage p1 anni ng conditions in all readily accessible
and considers the water quality aspect only to open channels are below prescribed
offer the following list of selected limits. This goal is identified with
references: the major drai nage networks of the
Master Drainage Plan and is aimed at
(i) sediment and erosion control : Burton achieving a sat i sfactory level of
et a1 (1976); Environment Canada safety and security in communities
(1980b ): Guy and Jones (1972) : Hannam faced wi th potential devastation in
and Hicks (1980): U.S. Environment the wake of major storms.
Protection Administration (1972): U.S.
Dept. of Transportation (1978): Weber Goal 2 : to prov i de convenience and safety for
and Reed (1976): Whipple et a1 (1983): pedestrians and traffic in frequent
Wolman and Schick (1967). or nui sance stormwater fl ows by
controlling such flows within pres-
(ii) pollution control strategy: American cribed limits. This relates to minor
Soc i ety of Ci vi 1 Engi neers (1982): Be 11 drainage networks whose presence in
et a1 (1979): B1i~s et a1 (1979): Bliss the urban landscape brings about a
et a 1 (1983): Cordery (1976a): Cordery reduction in minor accidents and
(1976b): Cordery (1977): Cullen et a1 i nconveni ence whi ch wou1 d be other-
(1978): Finlayson (1983) : Goyen and wise experi enced by members of the
McLaughlin (1978): Goyen et a1 (1985): general public on a day-to-day basis.
Gutteridge Haskins and Davey (1981):
Karr and Schlosser (1978): Moodie Goa 1 3: to reta in wi thi n each catchment as
(1979): Sator et a1 (1974): Walker much incident rai rifall and runoff as
(1979): Wanie1ista (1979): Whipple et a1 is possible and appropriate given the
(1983) • planned use of the catchment terrain
and its bi ot i c and engi neeri ng
The main emphasis of this document lies in characteristics. This is identified
the direction of new networks for small with the retention/detention measures
catchment developments but the concepts, included in master drainage planning
technology and procedures described may be and is aimed at reducing the negative
applied with equal force in the design of impacts of urban development on
rehabilitation and augmentation works for indigenous flora and fauna and pre-
established systems. development groundwater levels
without los s of st ruc tu ra 1 i ntegri ty
The descriptor 'small' is used because the in buildings constructed in areas of
procedures described are based on peak flow or expansive or unstable soil.
the Rational Method rainfall/runoff catchment
model in which the runoff coefficient, C, There is a strong interrelationship
embodies an allowance for hydrograph attenua- between these goals. Goa 1 1 is ach i eved ina
tion as a result of temporary storage routing. particular case using a flood conveyance and
disposal system which embraces its Goal 2
This approach is satisfactory provided that network: it a 1 so benefi ts from the detent ion
the drainage areas involved are not great and measures which are employed to achieve Goal 3.
thei r rai nfa11 /runoff response times are The extent and s i zi ng of components of the
relatively short i.e. less than 30 minutes. A network developed to meet the requi rements of
drainage IJnit upper limit of 20 ha which is Goal 2 are strongly influenced by the type and
appropriate for most local government plann i ng extent of retention/detention measures adopted
purposes has been set to meet thi s requi re- under Goal 3.
ment. However, it is common for Rational
Method assumptions to be applied to areas much Goals such as these have been set and
greater than 20 ha (U.S. Dept. of Transport- achieved overseas since the early 1970's, have
ation 1979; Wright-McLaughlin Engineers 1969: been strongly advocated in Australian tech-
City of Fort Worth 1967). Urban sub-di vi sions nical literature (Bonham 1974: Henkel 1981:
and landscape areas greater than 20 ha are Thompson 1983) and have been put into practice
readily amenable to procedures described in by various local authorities (Dandenong Valley
the Handbook but they need to be divided into Authority 1980: National Capital Development
sub-catchments, each not more than 20 ha, if Commission 1981: Melbourne and Metropolitan
they are to fall withi n the scope of these Board of Works 1981).
procedu res.
They are, however, far from universally
recognised in Australia and are virtually
1.3 THE GOALS OF URBAN DRAINAGE (QUANTITY) unknown at the 'grassroots' level of practice.
MANAGEMENT This is not through any lack of willingness on
the part of novice designers to take on board
The independent goals of urban drainage new ideas or through lack of ability to carry
ma na gement are: them through but, rather, a lack of clear
direction on the 'why' and 'how' of the task.
Goa 1 1: to ensu re that floodwater i nundat ion
of residential, commercial/industrial The aim of ARRB project 391 which has
and important pub1 ic buildings resulted in this publication has been to

2 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

bridge this gap and provide a full and Goal 3: Ston.water Retention/Detention
systematic account of urban drainage flow Measures
estimation, system design procedures and
stormwater management pract ice needed by Goals 1 and 2 each have readily identifiable
desi gn teams comp ri si ng ju ni or engi neers and targets against which the success or failure
technical officers supervised by experienced of planned or designed d rainage networks can
practitioners. be measured.

Goal 3 has no clearly defined target: it


is achieved in a developed landscape when
balance is struck between:
1.4 THE HArtlBOOK Artl GOALS I, 2 Artl 3
a) the social or commercial amenity derived
Goals 1 and 2: The Major and Minor Syste.s from a particular land-use
The major / minor drainage system concept whi ch
b) the en vi ronmenta 1 amenity provi ded ina
is ex[)resserl in Goa l s 1 and 2 i s not new to
Australian practi c e . UrainaQe has heen development by the presence of indigenous
managed s in ce the lQ 50 's hy -many munici- trees and shrubs
palities in 'primary/secondary' systems in
which 'secondary' corr esronds to major and c) the conti nued structural integrity of
components of the built environment.
'primary' to minor. In these cases the design
of pr imarv (und e rground network) systems is
completed and si~ulated, larger-t~an-design The balance which is sought in Goal 3 is
flows are applied to them to check their achieved i n a development when its retained
performance in Qreat storm runoff events. indigenous vegetation is fully supported by a
Adjustments are - made where necessary to stormwater retention/detention strategy that
does not cause conflict with the land-use
preclude the possibility of serious injury to
memhers of the publ ic or se riou s damage to adopted for the a r ea.
rroperty . State Road Authorities' m~nuals
endorse thi s approach and recommend use of a It is appa rent that Goa 1 3 cannot be
rare des i gn fl ood event such as the 'once in achieved by means of a step-by-step design
50-years flood' for checking purposes (Country app roach of the type used in connection wi th
Roads Board Victoria 1982 ; Main Roads Depart- Goal s 1 and 2 . Its importance, however, must
ment, Queensland 1980) . not be unde r estima ted: decisions mad e
conce rnin g the retention/detention strategies
used in a development have a significant v
Despite apparent similarities between this bearing on a ll aspects of the rainfall /runoff
and the master drainage planning approach the processes wh i ch take place wi th in that
latter requires major flood routes through development. Chapter 3 of the Handbook
urban landscapes to be defi ned ahead of thei r discusses this issue.
subsidiary min or stormwater networks. This
confronts the designer with the problem: how
can a major drai nage system whi ch takes
account of its subsidiary minor network be 1.5 THIS HANDBOOK AND OTHER URBAN DRAINAGE
planned be fore detai 1 s of tha t netwo rk are PUBLICA nONS
known?
The full range of flood estimation analysis
and design methods used in Australia is
This aspect of Goa l 1 is addressed in strongly influenced by the Institution of
Chapters 8 and 9 where a simpl e step-by-step Engineers. Australia (1987) publication
procedure is presented for planning major 'Australian Rainfall and Runoff'. Chapter 14
flood drainage systems for small, isolated of AR&R is devoted to a broad coverage of the
urban catchments. The procedure is appl i ed to urban drainage design topic including flow
a hypothetical residential sub-division in the esti mation in urban catchments - small and
Adelaide foothills, South Austr alia. The l arge the hydraulics of urban drainage
further probl em of major fl ood movement systems, performance standards, trunk d r ainage
through succesive, small, slope-aligned including detention and retention basins,
catchments is reviewed and directions for reha bil i tat i on and ma i ntenance, envi ronmenta 1
carrying out this task indicated. and social factors. computer software. The
presentation is directed towards the needs of
Chapters 10 and 11 present a the experienced practitioner.
non-iterative, non-graphical, step - by-step
mi no r d rai na ge network des i gn proc edure in The procedures described in later chapters
which an assumed basic layout 'grows' in of this Handbook cover part only of the range
response to hydrological loads and hydraulic addressed in Chapter 14 of AR&R but do so in
constraints adopted to meet the requirements greater detai 1. Users of the Handbook must
of Goal 2. The outcome in each case is an have access to the current edition of 'Austra-
arrangement of surface and underground network lian Rainfall and Runoff' (I.E. Aust.. 1977 or
components si zed to match the storm frequency 1987), in order to obtain rainfall intensity
selected for design, i.e. 'once in 2-years', frequency duration data required in the flow
'once in 5-years', etc. The procedure is estimation procedures.
applied to a simple sub-area and to a 12ha
hypothetical residential catchment in the The main aspects of the procedures pre-
Adelaide foothills. sented in both the I.E. Aust. publication and

ARRB SR 34,1986 3
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

this Handbook for estimating flows in small in the past to produce thei r own manuals
urban catchments and designing major/minor giving details of de sign requirements, stand-
systems to convey them are similar. Differ- ard s , local rainfall data, hydrauli c perform-
ences are listed in Chapter 14 of AR&R. ance data for approved units, etc. Publica-
tion of this Handbook and the third edition
Designs for catchments falling outside of 'Australian Rainfall and Runoff' in 1987
the range covered by this document, i.e. is not expected to end this process and may
medium to large urban catchments requiring very well provide an impetus to it.
hydrograph flow estimation procedures, should
be based on appropri ate methods recommended
in Chapter 14 of AR&R. Both publications should be seen as re-
source documents providing best available pro-
Most State Road Authorit i es, some spec- cedures and data selected from local and
ialised construction authorities, e.g. N.S.W. overseas sources. Their interpretation into
Housing Commission, as well as the works a variety of local contexts municipal,
departments of a number of councils and mun- regional or State-wide - is seen as the valid
icipalities across Australia, have found need next step in the technology transfer process.

4 ARRB SR 34,1986
Frequency and the major/minor
drainage system design concept

2.1 INTRODUCTION in the 100 years period, it could be described


as (approximately) the average 'once in 2
The problems which stem from attempts to years' flood flow. By a simi 1ar analytical
control and/or mitigate the effects of storm procedure (I.E. Aust. 1987) using data from
runoff movi ng out of control in the urban the 100 years record, it would also be
environment have occupied the minds of possible to assign flow magnitudes to the
drainage designers since the earliest days of average once in 5-years, 10-years, 20-years,
civilisation (Va11entine 1967). 50-years, 100-years and even 200-years floods.
The relatively frequent floods have small
The first step which must be taken by all magnitudes; the rare floods correspond to
who wish to contribute to this field of large flows.
community service is to realise that total
control of all possible levels of flooding and
prevention of all damage and injury is not If the flow control structure referred to
feasible given the limited community resources above had been i nsta 11 ed at the begi nni ng of
of manpower and funds normally avai 1ab1e for the 100 year period and if the drainage
thi s purpose. On the other hand, by careful channe 1 and st ructure had been des i gned to
planning employing modern procedures, soundly (just) convey a flow equal to the average
based data and proven pract ices, it is 2-year flood magnitude determined above, then
possible to use these resources to design and spillage from the drain and inundation of
install drainage systems which fully contain adjacent 1and would have occurred on 49
all minor storm runoff and which provide a occasions in the 100 years period, i.e. once
high level of flood security for the residen- in every 2 years (approxi mate ly and on
tial, commercial/industrial and public average). Similar situations in terms of
building zones of our cities and urban drain conveyance and inundation could be
landscapes. associated with the other flood frequencies
1 i sted •
Before applying these procedures, data and
practices to any practical drainage task, it Th e 1eve 1s of flood cont ro 1 and securi ty
is es sent i a 1 that the des i gner possesses a provided for the community, generally, or for
clear picture of the way in which his or her a particular component of a flood-prone urban
scheme will re1 ate to community needs, what environment are usually expressed by drainage
call it can reasonably make on available engineers in the terms outlined above. Thus a
resources of finance to implement and maintain building or installation of strategic import-
and how it will merge with and funct i on within ance e.g. a hospital, might be located above
the urban complex. the 1eve 1 reached by the 'average once in 200
years' or even rarer flood. Simi 1 arly , a
The following Sections are devoted to a communi ty res ource such as a sports fi e 1d or
discussion of these issues. recreation reserve, because of its nature and
function may be protected against inundation
up to the level of the 'average once in 2
years flood' only.
2.2 FLOOD CLASSIFICATION

Average Recurrence Interval. ARI The time periods mentioned in these two
ill ustrat ions a re referred to in the 1 i tera-
If a long period flood record - say 100 years ture of Engineering Hydrology as 'average
- were available for a gauging station at the return periods' or 'Average Recurrence Inter-
site of a proposed control structure ina vals', ARI, and are employed in Australian
dra i nage channel and an exami nat i on of that practice to cover average recurrence periods
record were conducted, it would reveal that a of 100-years or less. The terminology 'Annual
few very 'large' floods and a great number of Exc eedance Probabi 1 ity', AEP. is app 1 i ed to
'small' floods had occurred in the 100 years flood magnitudes which recur less frequently
peri od • than once in every 100 years (Rowbottom et a 1
1986). Thus, the hospital example given above
Considering the 50th ranked flood in the would be associated with AEP of 'I in 200' or
set, having been equalled or exceeded 50 times perhaps 'I in 500'.

ARRB SR 34,1986 5
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Four Flood Classes An extrelle fl ood is a flood whose


magnitude exceeds the 1i mit adopted for
These concepts of flood frequency are used to purposes of rare flood mitigation and, there-
classify floods into four broad categories: fore, represents a potent i a 1 for seri ous
injury, mental trauma and death as well as
a) minor stormwater flows severe financial loss to wide sections of the
b) major floods community. Such an event is, therefore, a
c) rare floods communi ty emergency call ing for an immediate
d) extreme floods and effective response from civil defence
authorities backed by the continued supply of
A prop ert y, open space doma i n or roadway conmunity essential services hospitals,
is subject to minor stormwater flooding (also electric power, gas, water and wastewater
called 'nuisance flooding') if the flow treatment plants. A level of flood security
carrying capacity of an adjacent or nearby higher than that provided for the general
stormwater drain or roadside drainage channel conmunity should therefore be incorporated
is frequently exceeded leading to overflow into the planning and locating of all
across property boundari es and footpaths and emergency service buildings and installations.
into roadway traffi c lanes. The consequences
of minor stormwater flows moving out of Before leaving this Section, attention is
co ntrol in the urban landscape are, primarily, drawn to the term 'stormwater' which is used
inconve nien ce for members of the public and a to decribe runoff from minor storms. The
sharp increase in the rate of minor traffic terms 'flood' or 'floodwater' are employed,
accidents. The Australian community, in generally, in the context of greater-than-
general, expects such flows to be fully minor storm events.
controlled and overflow to occur from their
drainage channels at ARI's of not less than
two or three years. Uesign Average Recurrence Interval
(Design ARI)
A rare flood is a flood of great magnitude
and therefore infrequent occurrence which It is clear from these descriptions that the
wi 11, if out of control, inundate premi ses limits which define the various flood Cl;I~~PC;
used by members of the general public either are arbitrary and fixed in a particular place
privately or corporately causing indoor damage at a particular time by perceived conmunity
to residential dwellings, work premises and expectations, current 'good practice' National
buildings set aside for education, entertain- or State legislation, local government regula-
ment, recreation and other community activi- tions or the requi rements of a funding
ties. The consequences of an uncontrolled <\tIt hnri t.y.
rare flood can be serious In]Ury, mental
trauma and possibly death to those who suffer Frequency limits or design average
its full impact as well as severe financial recurrence inter va 1s (des i gn AR I' s) such as
loss to householders and to commercial/ those which p1 ace a cei 1 ing on minor storm-
industrial corporations for not only damage to water flows or define rare floods, are there-
buildings, equipment and stock, but also lost fore flexible and may vary across land-use
income and the cusL ur clean-up operations. categories even within flood classes. Table
Reimbursement for these loses cannot, 2.1 il lustrates this for the case of a typical
normally, be recouped from insurance, as rare urban communi ty wi th in whose bounda ri es 1and-
floods are considered to be 'a cts of God' use varies from sport and recreation areas to
which invalidate any claim. It is unfeasible hospitals and other community emergency
to control floods of rare magni tude but thei r installations. The community is located
effects can be mitigated by ensuring that outside the limits of possible mainstream
(river) flooding.
floors of important premises and buildings are
placed out of flood reach and that flow depths In each priority - A, Band C - listed
and velocities are held below certain adopted components would survive, without inundation,
limits. Australian practice, generally, floods of magnitude equal to or smaller than
recognises floods of ARI 50-years or those identified in the Design Flood Frequency
100-years as 'rare' flood events. column. They would sustain significant damage
in greater floods.
A major flood is a flood whose magnitude
falls between the limits adopted for minor The task of planning/designing a single
stormwater flow control on the one hand and drainage system which achieves a complex set
rare fl ood mi ti gati on on the other. The of storm runoff management goals such as
consequences of a major fl ood in a well- implied in Table 2.1 can be accomplished by
planned and well-maintained urban drainage applying the major/minor flood management
scheme may therefore be some damage to outdoor concept.
property and installations, some traffic
acc idents, short-term dis rupt i on of conmuni ty
activities and of some services and, possibly, 2.3 THE MAJOR/MINOR FLOOD MANAGEMENT CONCEPT
a sizeable 'clean-up' bill. There should be
no floor-level inundation of residential, An urban storm runoff management system which
conmercial/industrial or important public has been planned in accordance with the
buildings and depth/velocity conditions in all major/minor concept may be described as a
open channels should be below those likely to 'system within a system' for it comprises two
result in serious injury to pedestrians or distinct but conjunctively-acting drainage
serious damage to motor vehicles. networks (Jones 1967):

6 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 2.1
A LAND-USE/FLOOD FREQUENCY HIERARCHY FOR AN URBAN COMMUNITY
Flood Design
Security Cl assificatio n Descri pt i on of Components Fl ood
Levels Frequency
Strategi c I Fl oo r leve l s of hospita l s , Civ il Defence HQ Design AEP
; 1 in 500
St rat eg i c II Fl oo r levels of police , ambulance and fire
A st ation s: wat e r and wa stewat er centres: e l ect ri c
power and ga s supply stations
Fl oor levels of conva l escent homes and community
bu ildings whi ch could operat e as dormitory cent r es Desig n AEP
in great flood events ; 1 in 200
()ormito ry 1 Floor l evels of high density resi de ntial
Dormitory 11 Floor l eve l s of l ow-med ium density r esidentia l
P/C II * I Floor l eve l s of esse ntia l f ood , pharmaceutical,
retai 1 and depa rtment stores: centres employ in g
1arge la bou r for ce : community admi ni strat i on and
B educat i on cent re s: cent res for sto r age of rare
artifacts: venues for ent ertainment , di ning or Des i gn ARI
popu lar indoo r sports ;
100 yea r s
PICII * II Floor l evels of facto r ies and outlets supply in g
non-essent ial items: premises of busi nesses and
institutions which involve small numbers of people : Desig n ARI
premises of spo rt or community act ivi ties in- ; 50 years
f reque nt l y used
Ope n space I Grounds of all units be l ong ing to priority A above: Design ARI
outdoo r areas wh ere r are artifac ts are displayed ; 5-10 years
or stored
C Open space II Grounds of a 11 units be l ong ing to priority B 3-5 yea r s
Ope n space III Other open space areas includ i ng ge neral pa rks and
outdoo r spo rt and re creation a rea s 1-3 years
--- -
* Public/Commercial / Industrial

Major drainage system: t he arrangement of It is clear from these representations and


pavements, roadway reserves, open space service descriptions that the planning of a
floodway channels, detention basins, lagoons, major system is likely to pose more difficult
etc. planned to convey to disposal a design problems of 'fit', given the great flows
rare fl ood of spec ifi ed frequency (see Goal 1, involved, than are likely to be encountered in
Sect ion 1.3). The consequences of a fl ood of the design of its 'nested' minor system.
magnitude equal to or less than the design Also, the initial planning of a major system,
rare flood are identical to those qiven in the incl uding consideration of tri a1 flood routes,
major flood classification in Section 2.2. occupies much less computation time and effort
than does the preparation of even a 'first
Minor drainage system: the arrangement of approximation' minor system network.
soakage we 11 s , kerbs, gutters, roads ide For these reasons a ma j or-then-minor
channels, swales, sumps, inlets and under- design sequence is recommended and is
ground pipes and junction pits designed to refl ected in the order and deta i 1 s of
fu11y contain and convey to disposal a design procedure s set out in later chapters of this
minor stormwater flow of specified frequency Handbook. Only those aspects of major/minor
(see Goal 2, Section 1 .3 ). design concerned with benefits, costs and
design ARI's are addressed in the remaining
A schematic representation of the sect i ons of this chapter.
relationship between the major and minor
systems and floor 1 evel s of bui ldi ngs in an
urban landscape is presented in Fig. 2.1 (a
'freeboard' of O.3m is suggested in I.E. Aust.
1987). The Flood Security Levels listed in Design Rare Flood Stage
Table 2.1 further illustrate the major/ minor IMajor System)
flood management concept in operation. Level C Freeboard to
enCOOlpasses the cOOlponents whi ch are secure floor level
from flooding in minor or nuisance stormwater
flow events and Level B, those prot e cted from
serious damage in major floods. Level A _ Unde rg round net work ca rrying
represents an above-major standard of f1 ood ® - bUlk of design nu is ance
- stormwater flow IMinor System)
securi ty provi ded for components of strategi c
importance to the community in the event of Fig. 2.1 - Major and minor drainage systems in the urban
extreme or catastrophic flooding. landscape

ARRB SR 34, 1986 7


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

I I I .1\/i(1d~S\rial local custom or on partial socio - economi c


asses sments based on antici pated effects of
l ~~~mer( \i I. I surcharg i ng until further information is
~180 ~~( Curv e 1 - res \de ntia l - I----------c available'.
!.
~ 160 / -- --- A s i milar conclusion may be drawn from the
QI

'"
'"
~140
-p .--?"
,.c--
'---v-- ~

ranee
comprehensive i n vestigation of urban drainage
systems, both major and m i ~or, carried out by
bes t val ue for ~ spent Grigg et al (1976), who stress that the
'0 120 I I I benefit/cost outcome in a particular case is
V>
o but one of the many inputs requi red by the
u
100 0 8 10
decis i on-making process. Other inputs include
De sig n avera ge rec urrence in t erval (yea rs) - - unquantifia ble social and environmental
benefits, fund availability and political
Fig. 2. 2 - Cost/frequency re lationships for two categories of pressure.
urban development
One particularly f rustrating (for the
designer) social aspect of the problem is
2.4 TOWARDS DESIGN ARI: THE WATER RESO~CES
'community view' of the importance of flood
APPROACH control and mitigation works relative to other
services. This can be capricious and strongly
The conventiona 1 method used in the water influenced b'y events - or , perhaps, lack of
resources field to select design ARI's is events - of the recent past.
benefit/cost analysis (Linsley and Franzini
1979; I.E. Aust. 1977 and 1987) which Should it even be possible to complete all
requires, as part of its data base, a requ i red ana l'yses and su rveys and reach
compilation of likely benefits. These are concensus among the i nterested parties
1i sted for major systems and minor systems in community representatives, planners , environ-
Table 2.2. mentalists, politicians as well as engineers -
in one place at one time, it would be,
strictly, inappropriate to transl ate the
TABLE 2.2: C(JUtUNITY BENEFITS OF MAJOR OR resulting design ARI findings to what might
MUI1R SYSTEMS appear to be similar developments and systems
elsewhere.
MAJOR SYSTEM ONLY MI NOR SYSTEM ONL Y
On the other hand, it is quite impractical
I. ' Improved aestheti c s
In c rea s ed se ns e o f
sec uri ty
Improved ae stheti c s &
I'
Red uced mi nor traffic
ac ci dent s
I to p.xPp.ct this type of enquiry to be performed
as part of every urban drainage design
r ec rea t i onal benefits I. Reduced health ri sks programme. This is particularly so in the
I . Enhanc e d land value s 1 linked with poor drain- I case of small projects carried out in the
. Red uced injury & l os s 1 ag e ( mo s qu itoes. flie s, 1 smaller municipalities. The larger local
I of life etc .) 1 government authorities should therefore be
I. Reduc e d disr uption of Red uced inconvenience 1 encouraged to conduct such stud i es and
no rma l COfllffill nity in perf orminq day-to- I processes in typical classes of cipvp.lopment,
I activities day activities
at least occasionally, and publish their
Reduced los s of com- Reduce d roadway mai n- 1
mun i ty servi ces I t e nanc e 1
findings for the benefit of all.
(h e alth, wat er, power
an d gas, tr ansporta- I Despite these obstacles and the complex-
ti o n. communication s , I I ities of the question which has been addressed
etc ) • in this section, the urban drainage planner/
Red uced emergency ser-
vi c es and re lief costsl I
designer must at some stage in his or he r
Red uced damage an d I project adopt design ARI's for the system as a
1 iabi 1 ity cos ts I whol e or for indi vidual segments of it. Some
Red uced production 1 more positive suggestions as to how this may
time a nd sales losses I be done are offered in the following sections.
I. Reduced c lean-up costsl
I 1 1
2.5 DESIGN ARI - MAJOR DRAINAGE SYSTEMS

Polin and Cordery (1979) applied benefit/ Determination of design ARI's for major
cost analysis to determine design ARI for a systems following the water resourc e s approach
cul vert on a mi nor waterway. Those who have referred to in Section 2.4 has been generally
applied this approach to urban drainage avoided in developed nations by the i r adoption
problems of broader scope have been frustrat- - nat i ona ll y in some , regionally i n others -
ed, finally, by the high intangible benefits of a common level of flood security in the
content of thei r prob 1ems, 1 ead i ng to i ncon- face of great floods. Thi sis the AR I =
clusive and unsatisfactory outcomes in most 100-years flood, defined in the U.S. National
cases. O'Loughlin and Avery (1980) . reporting Flood Insurance Act of 1968 as ' . .. the minimum
a study of two Campbe 11 town, NSW, subu rban level of flooding to be used by a community in
minor systems, concluded that it is 'impract- its flood- plain management regulat i ons.'
ical to devise a methodology for determining
design average recurrence intervals from Federa 1 , Sta te and 1 oca 1 go vernment
economic and sociological factors such as that authorities in Australia might be described as
developed by Polin and Cordery for culvert moving slowly in the same direction with
design floods. Designers will have to rely on respect to 'mainstream' flooding (Victoria,

8 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Flood Plain Management Act 1982; Australian Engi neeri ng input is important, however,
Water Resources Council 1985). However, and may take one or more of the following
damage to premises as a result of uncontrolled forms:
urban storm runoff is not included in thi s
category of flooding. Initial Cost and Design ARI
Some argue that the entry of mai nstream The procedure for designing minor systems
floodwater to a dwelling is likely to be far presented in Chapter 10 includes provision
more damaging than inundation by urban runoff (STEP lOA) for a range of approximate network
and, hence, that lower standards of protection designs to be costed, each network layout
should be accepted in the wholly urban corresponding to a nominated design ARI. In
landscape. Thei r case rests on the greater the case of residential catchments, design ARI
uncertainty which is associated with flood = 0, I, 2, 5 and 10 years are used; design ARI
(level) prediction for rivers than for urban = 0, 2, 5, 10 and 20 years are recommended for
runoff flows and, also, that river-derived commercial/industrial catchments.
floodwaters are likely to stay longer.
With these data a graph of network initial
Those who oppose such a distinction can cost can be drawn. This is illustrated for
point to the lack of conscious flood-proofing the case of a 12 ha hypothetical residential
evident in much contemporary urban building sub-division in the Adelaide foothills, South
practice e.g. slab-on-ground construction, Australia, in Fig. 2.2 curve 1. Fig. 2.2
and, concerning duration of inundation, floor curve 2 represents the outcome for a typi ca 1
level damage is virtually independent of the commercial/industrial development.
time pa rameter.
This type of representation is valuable
Little case can therefore be made for input to the decision-making process. It
distinguishing between the flood security indicates, in the case of curve I, that 'best
considerations presently afforded floodplain value for $ spent' is obtained when design ARI
properties and those situated beside roadway in the range 2-years to 4-years is used, i.e.
reserves and other urban 1andscape fl ood where the cost/ARI curve is fairly 'flat'.
routes which may become, in the aftermath of
major storm events, torrents of fast-movi ng, A display of even greater value to the
pollution-carrying flow. The devastation decision-maker would be one which converts
which occurred in the Sydney storms of initial cost and ongoing maintenance into
November 1984 (Cameron McNamara 1985) and 'present worth of costs' format (Grigg et al
August 1986 bear witness to this. 1976).
The design ARI recommended for the
pl anning of major storm drainage systems by Initial Cost/Maintenance and Design ARI
this Handbook and considered to be appropriate
in the third edition of AR&R (I.E. Aust. 1987) A report into engineering standards used for a
is the 100-years level. Variation from this range of residential land development
standard should only occur in a particular components, including stormwater drainage, was
case upon the recommendation of a full water prepared in 1984 for the Commonwealth Depart-
resources enquiry. ment of Housing and Construction by Scott and
Furphy (1984). The genera 1 aim of the study
was ' ••• to present a case ••• for the intro-
2.6 DESIGN ARI - MINOR DRAINAGE SYSTEMS duction of more cost appropriate alternatives
Of the five benefits listed under minor for engineering requirements based upon
systems in Table 2.2, only one - 'reduced performance standa rds that are rea 1 i st i c,
roadway maintenance' is quantifiable in achievable and encourage innovation.' The
engineering terms: the others are either study applied four standards of development to
unmeasurable, unquantifiable or both. It is a hypothetical subdivision of 77 residential
therefore not surprising to discover that even allotments and compared their cost/maintenance
greater uncertainty surrounds the question of performance over a 20-year time span. Storm-
ARI and minor system design than is water was managed in a major/minor drainage
encountered with major drainage systems. system whose base standard minor system used
Unl i ke thei r major counterparts, however, . swales designed for ARI = 1 year.
flood security levels applicable to minor
systems are never likely to be the subject of The report concludes that the potential
national or State legislative processes. maintenance cost savings associated with high
engi neeri ng standards ' ••• are so mi nor in
Neverthel ess, it is common for State Road relation to the heavy capital cost burden
Authorities responsible for the oversight of incurred that cost effectiveness improves
drainage cost-sharing schemes, as well as consistently as the base standard regime is
local government bodies, to provide such approached.' In a reference to the cost/
advice (MRD, Queensland 1980). Designers maintenance aspect of the base standard minor
should not be dismayed to discover apparent drainage system, it states that 'the high cost
inconsistencies and even conflict in design of maintaining swale drains means that this
AR I advi ce issued by different autho ri ti es as technique is somewhat less efficient than
it represents · the outcome, in each case, of traditional kerbing. However, this relatively
the complex techni ca 1, socia 1, envi ronmenta 1 , poor performance is more than offset by
political and funding judgements made by those savings in underground drainage services and
authori ti es • maintenance thereof achieved by swales.'

ARRB SR 34,1986 9
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

If cost considerations alone are to It is certainly possible, in engineering


determine design ARI for the minor component terms, to totally remove inconvenience as the
of a major/minor residential area drainage immediate prospect of our kerb-side subject by
system, then available evidence points to low providing for his or her conveyance across the
values of design ARI being the most cost- street dry-shod. The standard of conveni ence
effective. provided in this event would be regarded as
'very high' and its cost could be prodigious.
Under normal ci rcumstances it would a1 so be
Inconvenience and Suggested Design ARI totally unwarranted. The use of high values
of design ARI for minor drainage systems
The types of engi neeri ng ana lyses descri bed should be questioned on the same ground.
above, being totally cost-oriented, tell us
how cheaply we can 'buy' and maintain a minor So where does the designer draw the line
drainage system and what is the 'best buy' for between over-indulgence in the provision of
our drainage dollar. But they tell us nothing convenience and undersupp1y to the point where
about minor drainage system inconvenience quality of life in the urban landscape is
reduction and the relationship of this degraded? There is no c 1ea r-cut an swe r to
quantity to design ARI. thi s quest i on.

To explore this, consider the Thp. chanQe in emphasis which has occurred
'inconvenience' suffered when a member of the in urban drainage planning with the intro-
public is discouraged from crossing a street duction of the major/minor concept (see
because there is (nuisance) stormwater moving Section 2.3) has tended to go hand-in-hand
in the roadside channel. The duration of this with a lowering in the standard of convenience
i nconveni ence cannot be long in the types of provided by minor drainage systems (Jones
urban catchments which fall within the scope 1971). In what might appear to be a 'trade
of this Handbook - 10 minutes, perhaps 20 off' that stems from the new goals of urban
minutes at most. If the reason for making the drainage design, this reduced convenience is
crossing - probably in heavy rain - is one of balanced by a primary concern for increased
extreme urgency then the presence of perhaps security against indoor flooding of dwellings,
100 mm depth of water near the gutter is business premises and important public
unlikely to deter our subject as the cover buildings.
photograph of thi s document demonstrates.
Alternatively, a journey of not more than 60 m A table of design ARI values whi ch reflect
will bring him or her to a location where flow thi s ph i 10sophy is presented in Table 2.3.
'spread' is little more than gutter width. They are suggested for use in minor drainage
system components and networks ONLY where
Now the spread of flow which has these are integrated within cor recLly
inconvenienced our subject results from planned/designed major systems.
interact i on between three l11a i n pa rameters -

(i ) the magnitude of the stormburst which TABLE 2.3


caused the runoff,
SIJG(';FSTFI1 MINOR DRAINAGE SYSTEM DESIGN ARI
(ii) the ARI adopted by the designer for the
street drainage system, and,
Category of Development Design ARI
(i i i) the adopted desi gn maxi mum spread
cri terion.
Low-medium density residenta1
<15 residences per ha * 1-3 years
There is no universal practice concerning
item (iii): design maximum spreads specified High density residential
by Austral ian authorities include 'half lane >15 residences per ha * 3-5 years
width', 2.5 m, 'shoulder plus 2.0 m', etc.
The variation between these practices is Unit and townhouse deve lop-
a round.±. 10 per cent. ments 5 years

There is, of course, no universal practice Commercial/industrial develop-


concerning minor system design ARI [item (ii) ments
above] and the different design ARI's which city centres 10 years
are presently used yield flow spreads, in suburban centres 5 years
gi ven categori es of development, whi ch also
range up to .± 10 per cent. Open space, recreational areas 1-2 years

The process of selecting a design ARI


should therefore not be conducted in isolation *residentia1 density is based on allotment area
but should be paired with the adoption of an only, i.e. excludes roadway reserves, community
appropriate maximum spread criterion. buildings, open space domains, etc.

There is a final aspect of design ARI


selection which must be recognised, involving
the priorities of urban drainage compared with
other calls on the community purse.

10 ARRB SR 34, 1986


Retention, detention and retardation
measures in urban catchments

3.1 THE NATURAL CATCHMENT AND URBAN drought and also provide dry weather flow
DEVELOPMENT upon which the stream ecosystem depends.

In its wil d sta te, the na tura 1 ca tchment or The fi rst impact of development upon such
drainage basin is a complex environment in a balanced system is usually the clearing of
which a range of fauna, flora, geological land for agriculture. This leads to a change
changes and the natural processes of growth in the type of vegetation cover, e.g. from
and decay have established balance. The forest to grassland or crop, and sl ightly
harmony which exists is not, typically, increased flood peak flows with attendant
fragi 1 e for it can wi ths tand the ra vages of increased scour and erosion. Pollution loads
bushfi res and fl oods and can - gi ven time - - ferti lisers, pesticides, etc. - originating
regenerate i tsel f and restore its nat ural in the catchment and carried by streams may be
equilibrium. hig h depending on the type of agricultural
activity involved.
The main properties and characteristics of
a forested catchment which relate to the
changes wrought by later urban development In the next phase of development - the
are: conversion of agricultural land to typical
urban landscape - much of the land is covered
a) natural drainage system The system of by a substantially impervious surface
drainage paths, creeks and streams present interconnected by pipes and formal drainage
in a natural drainage basin is we l l channels. These structures convert the bulk
matched to the rainfall/runoff processes of storm rainfall input to runoff which is
operating in that basin. Generally, less coll ected and which moves rapidly through and
than 20% of storm rainfall on a natural beyond the catchment.
catchment i s discharged from it as surface
runoff. This discharge causes a minimum Where extensive urban development of a
of scou r and eros i on and, con sequent 1y , valley has occurred without sound drainage
carries a relatively low sediment load; it planning, riparian property owners in the
is free of catchment-originating chemical lower reaches of the valley are likely to
pollutants. experience frequent inundation by fl oodwaters
carrying high silt loads and high concentra-
b) water retained by catchment The surface tions of coliform, heavy metal and petroleum
i rregularit ies and vegetation cover hydrocarbons. Furthermore, because of rapid
present in the forested catchment are removal of stormwater from the urban landscape
responsible for retaining and retarding and consequent limited infiltration occurring
overland movement of surface runoff during runoff events, supplementary watering
thereby increasing the potential for is corrmonly undertaken to compensate for low
infiltation. The major portion of water soil moisture levels. The streams and
so ab so rbed is taken up by the roots of waterways of the valley are likely to dry up
indigenous trees and shrubs and eventually compl etely duri ng the summer months and
transpires to the atmosphere or evaporates members of the (stream) biotic communities
from the surface in hot weather. In the which requi re year-round fl ow for thei r
process, seasonal variation in soil survival will vanish (Karr and Schlosser
moisture can lead to significant 1978) •
volumetric changes (expansion and
contraction) in reactive soils.
It is interesting to note that of the
c) groundwater replenishllent and dry weather three mai n envi ronmenta 1 damages whi ch follow
flow That part of the rainfall input poor drainage planning, only the first
which does not leave the catchment as frequent lowland flooding by silt-laden,
di rect surface runoff nor is evaporated polluted water - has impinged on the public
from it, passes to groundwater storage consciousness. The loss of potential infil-
and/or appears as dry weather flow in tration and of dry-weather flow in streams
streams. These processes provide ground- appear to be matters about which the public at
water reserves to support trees and shrubs large is largely either unaware or unconcerned
in the catchment particularly in time of or, perhaps, both.

ARRB SR 34,1986 11
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

It is not surprl s 1 ng, therefore, that ' loss' can be e xpected wi th second grade
urban drainage design practice of the past has pavements (some residential streets, car
tended to concentrate on a percei ved need to parks, etc.) constructed on porous soils
remove runoff as completely and as quickly as ( Ma k in an d Ki dd 1979: Kidd und Lowing
possible. This ' need' manifested itself in 19 79). Numerous materials and open space
networks of slOOoth, interconnected collector surfa ce finishes are available which can
channels within developed catchments and in abstrac t upwards of 50 per cent of
large, lined channels downstream. rainfall applied to them (van Dam and van
de Ven 1984). These include open grade
The tragic loss of life in the Woden bituminous concrete, interlocking paving
Valley (A.C.T.) flood of January 1971, when hlocks - ungrounted and normally laid on
se ven people were swept to their deaths in a sand beds paving slabs, similarly
flooded stormwater drain, led to a questioning constructed, and precast lattice paving
of the 'remove runoff' phi losophy in which presents a block-reinforced grass
Australia. Leading practitioners and local surface to incident rainfall. In general ,
government authorities now advocate an suppl i ers recommend use of these pavi ng
approach to urban drainage practice which can types only on soils which are porous and
be described as a 'hold the water where it stable (Murphy et al 1981).
falls' philosophy. In this, every opportunity
to retain st.orm runoff and delay its movement b) Soakage wells and sumps Where soils are
from the catchment is explored in harmony with very porous and stabl e and the saturdLed
acceptable levels of flood security (Poertner groundwater zone at least 2m below natural
1973: Tourbier and Westmacott 1980). surface, significant quantities of
stormwater runoff can be collected and
Th e broad ai ms of thi s approach as they 5 I owl y trans ferred to the wa ter tab 1e by
relate to an urban development are: way of open soakage wells and sumps. The
technology leading to thi s approach has
1. to retai n wi thi n the ca tchment as much reached an advanced stage in Long Island,
storm runoff as can be tolerated ha vi ng New York (Aranson and Prill 1977) and has
regard for other communi ty needs such as been successfully applied in Perth,
the structural integrity of building Western Austral ia, where much of the
foundations in unstable soil areas: terrain is sandy, similar to that of Long
Island.
2. to so manage stormwater excess flows
within the catchment that minor floods are
fully controlled and the effects of major 'Soak wells' and 'sumps' are widely used
and rare floods mitigated: and, in Perth to store runoff from domesti c or
industrial roofs, carparks and sections of
3. to regulate outflow from the catchment to main roads. installations vary in Lype and
levels which approximate those of its size from pipe-walled pits (perforated pipes,
pre-developed state. diameter 1 m) used in domestic situations to
open pi ts or 'sumps', e.g. 0.25 ha x 2 m deep
The measures whi ch the drainage designer used for large industrial sites and carparks.
can employ to achieve these aims may be class-
ified broadly as retention, detention and For these retention measures to be
retardation systems (after Johnson and Putt successful, site hydraulic conductivity, Kh ,
1977) : should be greater than 5 x 10- 5 m/s. (For I
field measurement of hydrauliC conductivity,
Retention refers to procedures and schemes K , see Jonasson 1984a.)
h
whereby stonnwater is held for considerable
periods causing water to continue in the The Main Roads Department of Western
hydrologic cycle via infiltration, perco- Australia operates about 30 sumps located at
lation, evapotranspiration and not via direct interdunal low points beside main roads where
di scharge to watercourses; they receive runoff piped from roadway surface
drainage collection systems. Brooks and Cocks
Detention refers to the holding of runoff for (1983) have developed a method for sizing
sho rt time pe ri ods to reduc e pea k fl ow ra tes sumps which has been validated by observations
and then later releasing it into natural or made of operating installations in Western
artificial watercourses to continue in the Austral ia. The method appears to have wide
hydrologic cycle. The volume of surface application in the sandy terrain, low rainfall
runoff involved in this process is relatively areas of South Australia, Victoria and
unchanged; Tasmania where significant losses to evapora-
tion - ignored by Brooks and Cocks - can also
Retardation is achieved when flow moving to be expected.
the entry point of an underground drai nage
network passes along a channel of low Where soakage wells and sumps are employed
hydraulic efficiency. Retardation systems to control minor stormwater runoff in elements
which are most effective usually combine this and sub-areas of a developed landscape, they
characteristic with those of retention and should be sized to accept the entire runoff
detenti on. generated in those components in storms of
design ARI equal to that adopted for the
3.2 TERMINAl RETENTION MEASURES genera I mi no r dra i nage system of whi ch they
form a part. Sump retention volumes should be
a) Porous paving British research has shown based on storms of long duration e.g. two or
that at least 30 per cent infiltration more days. It follows that catchment elements

12 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

and sub-areas whose minor flows are so or seepage beds (see below). Roof
retained should be excluded from the defined stormwater, temporarily retained by these
catchment contributing to the general minor structures, is released slowly to
system network. groundwater or to maintain soil moisture.

Appropriate sp i ll provisions must be The following design constraints should be


incorporated into all sumps which receive observed in planning on-site retention/
runoff from multi- allotment catchments and overflow well s:
sub-divisions. Sump spillways can be expected
to operate in all major, rare and extreme (i ) site soil hydraulic conductivity, Kb ,
storm events in such catchments. not less than 3 x 10- 6 m/s. Thi s 1 imrt
corresponds to the Kh of very fine
The main disadvantages of the installa- sands.
tions described here are the area which must
be set aside for their use, their decreased (i i ) groundwater 1 evel { 1.0 m below bottom
performance as a result of clogging by fine of well
material, oil, plastic bags, etc. transported
in runoff and their role as breeding places (iii) well to be sited { 5 m from foundation
for mosqui toes. Those experi enced in the use of nearest building
of these installations stress the need for
regular, e.g. annual, maintenance. (iv) recol1111ended well volumes - Table 3.1

Attractive solutions to stormwater TABLE 3.1


management problems can resu 1t from the
diversion of runoff to naturally occurring or STORHWATER RETENTION/OVERFLOW WELLS:
man-made 'sumps' such as abandoned gravel pits
where aquifer recharge and evaporation VOllJ4E PER 100M 2 OF ROOF AREA DRAINED
processes operate to return stored runoff to
the hydrologic cycle. MINOR DRAINAGE SYSTEM
LOCATION DE SIGN AR I
3.3 NON-TERMINAL RETENTION MEASURES 10-years 5-years 2-years
. a) Retention/overflow wells Where soil s are Northern
less porous than the limit advised for Australia * 2.90 m 2.70 m 2.40 m
soakage wells and sumps in Section 3.2, Intermed i a te
retenti on/overfl ow well s of the type Australia see Section 5.3
illustrated in Fig. 3.1 may be used. Southern
These wells are sized (see Table 3.1) to Australia * 1.10 m 0.90 m 0.70 m.
retain a significant portion of roof
runoff before overflowing to the formal
minor drainage system or to Dutch drains * see Figure 5.2
stormwater drainage trom
roof or rainwater tank perforated concrete pipe, minimum diameter
overflow only ~ lO m with fitted cover, 100 mm above
natural surface

overflow to roadside
channel ,rear of allotment
drain , seepage trench etc,
I
gravel collar width - 300 mm.

internal gravel
bed 300 mm dee p

NOTES :
1. For well volume and site
see Section 3.3
2. Gravel- 20 mm nominal size

Fig . 3.1 - On-site retention / overflow well

ARRB SR 34, 1986 13


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Stormwater from roof or


Gutter grating
overflow from well or
seepage bed .

Rear Fence

' ,0 m

pipe ~rface wit h


stormwater drainage Flow
network
DUTCH DRAIN -Rear of Allotment Arrangement

carriageway

C : : :ater ::from
roo f or overflow deep
from well or seepage
bed.
Overflow pipe
Junction pit - - -
Dutch dra in - 400 mm. deep

DUTCH DRAIN - Roadside Swale Arrangement

Overflow to roads ide channe l


SEEPAGE BED or rear of "lIotment drain
NOTES , Geotextile fabric at all gravel/soil interfaces
2 Gravel - 20 mm. nominal size
3 Seepage bed volume - 3M volume from Table 3,'

Fig . 3.2 - Dutch drains and seepage beds - suggested arrangements

b) Dutch (or French) drains and seepage beds A layer of graded filter or geotextile
These operate along similar lines to the material should be placed at all gravel/
open wells and sumps described in Section soil interfaces (see Figs. 3.1 and 3.2).
3.2 but differ from them in the following
respects: Gravel-filled drains and beds are less
prone to clogging than open sumps but are
(i) they are generally non-terminal, virtually impossible to clean. For this
1 .e. they convey f1 ow as well as
reason it is advisable that they receive only
promote its infiltration; roof stormwater or filtered runoff from
(ii) the excavated storage volume is pervious and/or ground-level paved areas.
back-filled with crushed rock or
gravel. 20mm nominal size; Because of the presence of hackfilling,
the volume required for a Dutch drain or
(iii) the drain or bed usually contains a seepage bed, in a given situation, is about
line of perforated pipe; three times that required for a corresponding
(iv) there is provision for outflow of open well or sump. The plan area is.
minor storm drainage to the formal correspondingly, greater by a factor of 2-3.
drainage collection system; The disadvantage of this significantly greater
area is offset by the fact that, with
(v) the gravel backfill is usually covering. the area does not represent a total
topped with paving or grass. loss to develop@Mnt (see Fig. 3.2).

14 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

The perforated pi pe 1 i ne usually inc 1uded b) Rainwater tanks Although any available
is not part of an associated underground storage in urban rainwater tanks causes a
network: its role is, primarily, to ensure an reduction in the runoff passing to drain-
even distribution of stored stormwater along age networks from individual allotments,
the 1ength of the trench or bed. Neverthe- the uncertainty which must necessarily be
less, these installations may properly be associated with this reduct i on dis-
regarded as extensions of the formal under- qualifies it as a dependable component of
ground collecti on system to which they are stormwater drainage planning. The role of
linked at their points of outflow. the rainwater tank is, therefore, almost
totally linked to conservation: it
Seepage trenches and beds, backfilled in enables the householder to use part of a
the manner described here, are employed in natural resource provided di rectly to him
Japan, Sweden and West Germany wi th soi 1 s and reduces hi s dependence on water
ranging from medium sands to loamy sands transferred from catchments outside hi s
(hydrau l ic conductivity, Kh.' range 5 x 10- 4 own.
m/s to 5 x 10-6 m/s); rainfall is similar to
that experienced in Southern Austral i a (see c) 'Mi cropondi ng' The temporary pond i ng of
Fig. 5.2) . See Wanielista 1979; Ichikawa and stormwater on individual ·allotments and
Yamamoto ' 1984; Jonasson _ 1984 (a and b); subdi visions - residential or commercial/
Holmstrand 1984; Sieker 1984. industrial - is a detention measure which
has, to date, found limited application in
c) Off-streaM porous storages It is some- Australia. Some excellent local contribu-
times possible to exploit the advantages tions to this aspect of stormwater manage-
of both retenti on and detent i on by ment have, however, been made by Nicholas
di verting portion of the flood flow and Cooper (1984), Boenisch (1984) and
passing along a natural channel into Phillips (1985). It is an option which,
off-stream storage which may be a nature- gi ven the ri ght soi 1 and topography,
formed reservoir such as an old meander or should not be overlooked in the planning
it may be man-made. Where the storage is of sub-divisions. The hydraulic princi-
in porous bed material - cOl111lOn in such ples upon which microponding is based are
situations - then floodwater disposal in the same of those of 'macroponding' (see
the manner descri bed for 'sumps' in the below) : the difference is a matter of
previous section wi 11 follow. Its design scale. Catchment elements suitable for
must incorporate prOV1Slon. for outflow development as microponds are carparks,
control , e.g. spillways, etc. These sports fields, open space recreational
characteri st i cs qua 1ify off-stream porous reserves, etc.
storages for inclusion among retention/
detention systems (see Fig. 3.3). ( d) Off-line storage This category of storage
may be added to an underground network to
remedy system overload in, usually.
confined situations where downstream
Embankmen t capacity is significantl'y less than that
required to carry upstream-generated flow.
By providing sufficient temporary off-line
storage to accol111lOdate a major portion of
Retention Basin this flow, together with flow control from
storage matched to the downstream
capacity, it is possible to utilise an
existing network and thus avoid the
expense of system enlargement or dupl ica-
t ion.
Fig . 3.3 - Schematic layout of an off-stream storage basin
(after Environment Canada, 1980b) Required off-line storage may be provided
by a run of large-diameter pipe or storm drain
connected into the system at the point of
3.4 DETENTION MEASURES overflow. Outflow control must be provided by
an appropriate 'throttle' connection between
a) Roof storage The use of roof area for the storage and the downstream pipeline (see
temporary storage and slow release of Fig. 3.4). A patented device - the 'Hydro-
rainwater is well known overseas but rare Brake' - has been developed to control outflow
in Austral ian experience. Main applica- in situations of the type described here
tion is with flat-roof commercial (Matthews et al 1983; Murphy et al 1981).
buildings and multi-storey car parks
whi ch, norma lly, impose severe runoff Off-line storages fitted with Hydro-Brakes
loads on city stormwater drainage systems. and cos ti ng 1ess than 50 per cent of
Using roof storage, it is possible to conventional remedies for overloaded systems
convert major or rare storm rainfall on a have been reported from the boroughs of York
building to minor level outflow to the and Scarborough in Metropol itan Toronto,
connected underground network. The roof Canada.
storage average depth needed to achi eve
this ranges from about 70 mm in e) 'Macroponding' The use of stormwater
Australia's most intense rainfall zones to detention basins to temporarily store
around 35 mm in the zones of least runoff from wide areas of urban or rural
intensi ty. 1 andscapes is a tool well known to

ARRB SR 34,1986 15
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

p resent -day d rai nage planners. The In rai nfa 11 /runo f f even ts. s t o rm r unoff
typical fonn taken by such a basin where passes from the urban landscape into the
it is employed in an urban context is that ponding area and on through the culvert
of a small flood control dam. Its outlet. As inflow continues, exceeding the
embankment is normally located in the res tri cted fl ow capacity of the outlet,
flood pla i n of the main drainage path fl oodwater is stored beh i nd the embankment.
carrying stormwater from the urban In major storm events, the spillway operates.
development and it is usually provided
with an ungated cu 1 vert-type ou t 1et and The ponding effect of the basin, coupled
has a spillway (see Fig. 3.5). with the restriction imposed by the culvert,
combine to produce an outfl ow peak from the
basin whi ch is si gni ficantly 1 ess than the
peak of the hydrograph passing to it from the
upstream urbanised catchment. The relation-
ship of these two peak flows, for a typical
case, is shown in Fig. 3.6.

A deta i led account of th e hydrau 1 i cs of


detent i on bas in des i gn and ope rat i on and
review of case study examples are beyond the
scope of thlS Handbook. InformaLiulI UII these
topics may be obtained from the proceedings of
the Institution of Engineers, Australia
'Seminar on Retarding Basins' held in Sydney,
NS\aI, April 1983 (I.E. Aust. 1983) and from
other publ i cati ons which address thi s subject
e.g. American Society of Civil Engineers 1982;
Duru 1982; I.E. Aust. 1977 and 1987.

3.5 RETARDATION MEASURES


Certain of the devices described above, e.g.
Dutch drains (Section 3.3) fit the definition
for retardation systems stated in Section 3.1.
Fig . 3.4 - Detention storage in an overloaded storm drainage However, this category is conmonly understood
network to embrace only channels carrying surface
(after Environment Canada, 1980b)
flows to undergrollncl network entry points.

de si gn rare f lood stage

spill leve l - =;;.....;=---j6...,..,..,...,..,.,~

Temporary Storage

' wet ' storage ----=~~


(semi-perm a nent) \\ 'G:~:m~:'I'7.<~~~

low-leve l ou tlet sys tem

Fig . 3.5 - Main elements of typical urban detention basin


(after Robinson and O 'Loughlin, 1983)

INFL OW HYOROGRAPH
I ./ volu me of runoff held in te mp orary
~ storage at peak of outfl ow

OU TFL OW HYO ROGRAPH

TIME
Fig. 3.6 - Inflow and outflow hydrographs for a typical urban detention basin

16 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Four broad classes of roadside channels find c) swales - well-maintained These are used
wide use in Australian practice - swales, in urban deve 1opment as out 1 i ned above.
blade-cut earth channels and two types of Travel times are about 4-5 times those of
kerb-and-gutter channel s. These are 1 i sted concrete kerb-and-gutter channels, the
below, with comment, arranged in order upper time limit applying to swales which
according to thei r retardi ng effect on are interrupted by driveway crossing. [See
surface-moving flows: Fi g. 3.7 (a) J •
a) sWilles - poorly uinhined Urban use of d) blade-cut earth channels - well-maintained
swales is confined, mainly, to low density These are used in urban development as
residential situations (density eight or outlined above. Travel times are about
less residences per hal where carriageway 2-3 times those of concrete kerb-and-
crown levels are at or slightly above gutter channels, the upper limit applying
local natural surface levels. When poorly to channels which are interrupted by
maintained they become irregular in both driveway crossings. [See Fig. 3.7 (b)].
cross-section and longitudinal grade.
Travel times in these channels are about e) stone pitcher or cobble kerb-and-gutter
5-6 times longer than those of concrete channels These are found in many suburbs
kerb-and-gutter channels owing to inter- of our older cities. They are regular in
mittent grass, weeds, exposed tree roots, both cross-section and longitudinal grade,
driveway crossings, potholes, etc. rSee very rough and more pervious than concrete
Fig. 3.7 (aiJ. kerb-and-gutter channels. Travel times in
these channels are about twice those of
b) blade-cut earth channels - poorly main- concrete channels. [See Fig. 3.7 (c)].
tained These are channel s formed and
maintained by grader operators and tend to
be confined, also, to low density
residential sub-divisions. They are used,
ma in1y. in roadway reserves whose
carriageway crown levels are significantly
below local natural surface and become
irregular in time in both cross-section
and longitudinal grade. Travel times are
about 3-4 times those of concrete
kerb -and -gutter channe 1s. [See Fi g. 3.7
(b)].
lei stone pitcher or co bble kerb and gutter channel

width
/~
~'d'=8

l:1 / O'30-0 '38m '


Idl concrete kerb and gutter commonly used in
Victoria,Queensla nd, S.A . and NT

lal roadside gra ssed swale - with cr ossing

/' lei concrete kerb and gutter used widely in


N.S.W. and Tasmania

~TE: All kerbs, 150mm . high

Ib l blade-cut earth roads ide channel-with cr ossi ng


If I concrete kerb Ino gutter I used extensively in
Fig . 3.7 - Roadside channel forms used in Australian practice W.A ., North America and Europe

ARRB SR 34, 1986 17


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

f) concrete kerb-and-gutter channels approach has proved to be not only psycho-


Roadside channels i ncluded in t his broad logically beneficial and safer for residents,
ca t egory predominate in Australian urban but is less costly compared with more conven-
areas, old and new. [See Fi gs. 3.7 tional patterns of urban development (Colman
(d)-(f)]. Although forms differ , all are 1978; Land Commission, New South Wales 1984).
equally effective in removing stormwate r This type of development lends itself to
quickly with little loss to infiltration informal stor~ater drainage treatments which
and with little peak reduction as a can be integrated into natural drainage lines
consequence of surface storage routing with minimum disturbance to them.
(see 'Macroponding', Section 3.4). They
r e present the most obvious sign of the Unfortunately, the drainage designer does
, 'remove runoff' ph i losophy discussed in not always have the opportunity to determine
Section 3.1 and as such should only be or even influence the direction taken by an
used where necessary e.g. city streets and urban development plan. He is frequently
high (traffic) volume streets in faced with an existing or already planned
industrial suburbs and residential layout for which he is expected to design a
districts. Th eir wholesale deployment sati sfactory stormwater drai nage system. In
throughout the urban 1 andscape should be this event, the demands of sound environmental
questioned. practice should compel him or her to consider
and select from the various measures and
options described in Sections 3 . 2-3.5
inclusive. The following measures are parti-
3.6 IMPLEMENTATION OF RETENTION/DETENTION/ cularly recommended for suitable locations:
RETARDATION MEASURES IN THE URBAN
ENVIROflotENT a) swales in place of concrete kerb-and-
gutter roadside channel s in minor (access
The various ponding and retardation measures roads) residential streets;
desc ri bed in thi s chapter may be implemented
by the drainage designer to partly compensate b) retention sumps and wells (Section 3.2)
for the impact of development on natural where soil hydrauli~ conductivity, K , is
environments. They should not, ideally, be h
greater than 5 x 10 5 m/s (fine sands) :
used in isolation but should complement a
purposeful strategy which seeks to minimise c) on-site retention/overflow wells (Section
urban di sturbance of such pl aces. To thi s 3.3) where soil hydraulic conductivity, Kh
end, the natural drainage network with its is between 5 x 10- 4 m/s and 3 x 10-6 m/s
supporting forest environs should be preserved (clean sands to very fine sands).
as intact as possible and native vegetation
removed from developed allotments on I y whe re Wi th these components installed. peak
absolutely necessary. Smoothing of the flows 30-40 per cent less than those generated
landscape and removal of its natural features in conventional layouts can be expected with
produce not only ba r ren 1 i vi ng envi ronments corresponding cost reductions. Soil moisture
but are also prime causes of increased storm- maintenance is an added benefit but care needs
water flow, scour and blockage of downstream to be exercised to ensure that this character-
drainage strllr.tllrp.s (Brotchie 1977). istic does not lead to buildinq foundation
damage in areas where soils are highly
One planning approach which, broadly, water-reactive. The design ob,iective should
embodies recommended principles in the context always be to maintain uniform soil moisture
of residential development uses cluster states below and around buildings on expansive
hOUSing with an open network of streets. This soi 1 s.

18 ARRB SR 34,1986
4
Rainfall/runoff mathematical models

4.1 BACKGROUND directly to and discharged from 0 [See Fig.


4.1 (a)l. If this cat c hme nt were subject to a
Two stormwater flow estimation methods or rai nstorm event of constant intensity, i mm/h
rainfall/runoff mathemati ca 1 model s are for long duration, then the resulting
reviewed in this chapter: r elationship between discharge, Q, and time
would take the form of the runoff hydrograph
a) conventional Rational Method, and, shown in Fig. 4 .1 (b). Note that the 'time of
ri se' of the hyd rograph is t mi nutes, the
b) the 'Two-Value Rational Method' catchment's time of concentrati8n.
The first of these is familiar to all The peak (steady-state) outflow which
students of Engineering Hydrology. It assumes occurs at 0, Q , must equal the rate at which
a relationship between the duration of precipitation °is being supplied to the
constant intensity rainfall required to catchment during the event since there are no
produce peak outflow from a catchment and the losses. Thus:
longest travel time 'time of concentration',
t , of the catchment. The relationship was =~Lls / (4.1 )
pFoposed fi rst by Mu1 vaney (1851) in hi s study 0.36
of Iri sh agri cu1 tura 1 catchments. The same
concept was applied by Kuich1ing (1889) in an
investigation of the rainfall/runoff behaviour
of urban catchments in Rochester, N.Y.,
U.S.A., and by Lloyd-Davies (1906) in his
para 11 e 1 study of developed 1 andscapes in
Birmingham, U.K.

The basis for method (b), above, is the


rainfall/runotf flow estimation proced ure
developed by Reid (1927), Riley (1932) and
Escritt (1965) in which catchment contributing
areas and their respective response times are
represented on a time - area graph. Rainfall
information from intensity-frequency- duration
charts may be combined with the time-area
catchment representation to yield peak flow
estimates. The Two-Value Rational Method
(Argue, 1984) is a simplified non-graphical (a) Impervious Catchment Draining To 0
version of this method: it is the main
rainfall/runoff mathematical model which is
employed in the design procedures of this
Handbook. --------
00
Both methods rely on the relationship
between storm durati on and catchment travel
time assumed in the Rational Method. The
val idi ty of thi s re1ationshi pis explored in
t
0
the next section using typical rainfall ~

intensity-duration data applied to idealised :.


0
single and multiple land-use catchments. LL.

4.2 RATIONAL METHOD Time, t - - tc


Single land-use Catchments (b) Constant Intensity Storm
Runoff Hydrograph
Consider runoff from a 'plastic-coated' or
impervious catchment of plan area A ha, so Fig . 4.1 - Single land-use catchment and runoff hydrograph
shaped that all surface runoff is conveyed in storm of constant intensity and long duration

ARRB SR 34,1986 19
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

P
This formula will be recogn ised as the
Rational Method formula with
coefficient, C, omitted or, more correctly,
runoff \
with runoff coefficient C = 1.00. This value
of C may therefore be applied to all similar
\ \
i mpervi ous catchments in whi ch there a re no
losses to
evaporation, etc.
infiltration, retention,
"- \ IMPERVIOUS

, \
CATCHMENT

Consider now runoff from Catchment I, a


~ \
AREA= 0·10ha
rectangul ar, impervious catchment of uni form
slope and plan area 0.10 ha, draining to 0, '" ,,\
whose time of concentration i.e. travel time
from point P, is 20 minutes. [See Fig. 4.2
(a)]. Catchment I is located in the climatic
'" ,,\ o
regi on whose ra i nfa 11 average i ntes ity-
duration relationship for frequency ~RI
10-years is presented in Fig. 4.2 (b). (a) Catchment I "
If the following $tormburst cases
(intensity constant), all taken from the Fig.
4.2 (b) curve, are applied to Catchment I the ~ 60
resul ting runoff hydrographs at 0 take the It r\
forms set out in Fig. 4.3. 50
3'
2~ !'-.ARI=10 Years -
Example 1 : intensity i 10 25 rrm/h

-
.........
for duration 60 mi nutes
..........
(hyd rograph 1)
Example 2: i ntens i ty i 10 42 mm/h 1~
for duration 25 mi nutes
(hydrograph 2)
Exampl e 3: intensity i10 48 mm/h
for duration = 20 minutes
(hydrograph 3)
Example 4: i nten s i ty i 10 55 mm/h o 10 20 30 40 50 60
for duration 15 minutp<; Storm Duration (mins)---
(u) Rdinfall Inl"nsity-t ime
(hydrograph 4)
Relationship
In examples 1-3, peak flow rate Q is given by Fig . 4.2 - Catchment I - layout and rainfall intensity-
the Rational Method formul a:
o duration relationship for ARI 10 years =

(CA)i 10 15 r---,----r---.----.---,----r---.--~
- - - LIs (4.2 )
0.36

where C = runoff coefficient (=1.00 in each Note : tc = 20 mins


case)
A = catchment area (ha)
i~= rainfall intensity (mm/h)

~
o
Example 1: Q = (1.0 x 0.10) 25/0.36 6.9 L/s
o ~ 5~~~+_~--_+~4-~--4_--~~.4--~
(4.3 )

Example 2: Q = (1.0 x 0.10) 42/0.36 11.7 L/s


o
(4.4 )
10 20 30 40 50 60 70 80
Time (mins)
Example 3: Q = (1.0 x 0.10) 48/0.36 13.3 L/s
o
Fig . 4.3 - Hydrographs for rainstorm bursts on catchment I
(4.5 )

As storm examples with shorter durations In examples 1-3, the duration of storm
and hence greater average rainfall intensities rainfall is long enough (duration ~ t ) to
are consi dered [represented by poi nts 1-3 in ensure the arrival of runoff from all parts of
Fig. 4.2 (b)], the resulting hydrographs show the catchment at or before the instant the
progressively higher peaks. The hydrographs storm ceases. This is not so in Example 4
are based on the assumpti on that the speed where runoff at outlet 0 has arrived from only
with which runoff elements travel to discharge 15/20 or three-quarters of the catchment at
poi nt 0, is steady i.e. constant at each the time of cessation of rainfall input. (The
location in the catchment throughout each quantit.Y 15/20 arises from 15 minutes storm
runoff event. duration, 20 minutes time of concentration).

20 ARRB SR 34,1986
STORM DRAINAGE DES IGN IN SMALL URBAN CATCHMENTS

Hence: The following example illustrates


conventional application of the Rational
Example 4: 00 = [1.0 x (3/4 x 0.10)J 55/0.36 Method to a mu lt i 1and -use catchment, in thi s
case Catchment II :
= 11.5 LIs
(4.6) impervious area , A. 0 . 10 ha for which
C~ 1.00
The trend displayed in the Fi g. 4.3 1
hydrograph peaks is the usual outcome when pervious area , A 0.20 ha for which
Rational Method assumptions and r ai nf all
intensity-duration relationships ar e p cP 0.40
combined , as above, and it i s thus that travel t ime from poi nt P, t i 20 minut es
Mulvaney's 'hunch' of 1851 :
ston.s which produce peak outflows from a travel t i me from poi nt F, tc 60 mi nutes
catch.ent have durations equal to the
catchllent tillle of concentration, tc, or Hence:
longest travel tille
wei ghted runoff coefficient,
is justified for use in design.
(1.00 x 0.10) +(0.40 x 0.20 )
The application of a runoff coefficient, (0.10 + 0.20)
C, other than 1.00 to take account of losses 0.60 (4.8)
to infiltration, depression storage, etc. in
pervi ous ca tchments has 1 itt 1e i nfl uence on time of concentration must be the greater
the assumed relationship between critical of ti and tc
storm duration and tc stated above.
= 60 mi nutes (4.9)
Before leaving this exploration of the
hydrology of single land-use catchments it rainfall intensity [from Fig. 4.2(b)J
should be noted that the basic assumptions of 25 mm/h (4.10)
the Rational Method, in particular that
relating to the steadiness of runoff travel, Hence :
have long been criticised (McPherson 1969; (C A) i (0 . 60 x 0. 30) 25
w 10
Aitken 1975). However, it was not until the
advent of kinematic wave theory (Lighthill 0. 36 0. 36
and Whitham 1955 : Henderson 1966) that more
convincing though more complex response 12. 5 L/ s (4.11 )
model s could be proposed for catchments of
the type considered above. Such models show But this is less than the peak outflow
that critical storm duration can be signi- rate estimated at 0 for that part of Catchment
ficantly less than time of concentration in I I Previ ous ly cons i dered as Catchment I [see
single land-use catchments (Stephenson 1984). eqn (4.5) J.
This anomaly which often results when
Multi land-use Catchments Mul vaney' s 'hunch ' is app 1i ed to catchments
When flow estimates are required in a multi quite unlike those he studied , became a matter
land-use catchment of the type illustrated in of concern to many practitioners involved in
Fig. 4.4 - Catchment II - conventional use of urban drainage design in the 1920's. They
the Rational Method requires critical storm therefore sought a better rainfal l /runoff
duration to be still set equal to total response model , one which would expose the
catchment longest travel time even though presence of such anomalies should they be
overland flow speed in its various components present. Their deliberations resulted in
may be demonstrably different. Travel time time-area representation of catchment
from point F will therefore over-ride travel components and the various 'Tangent Check'
from poi nt P because runoff movement across procedures.
the pervious surface is much slower than
across the alternative impervious surface. p~--------~--------------------~F

The only concession made in the Rational \ /


I
Method for the composite nature of the I
catchment draining to 0 is in the adopted \ \ /
runoff coefficient. This takes a 'lumped' Imperv iou s Per vio us
value, C , weighted in proportion to the " Catchment I I Catchm ent
areas of rhe land-use components. /
" \
---
- -
Given a catchment containing three ,,\
different land use areas A1 , A2 , and A3 with
correspond i ng runoff coeffi c i ents C1 , C2 and
C3 the lumped or weighted runoff Area
o Area
coeffiCient, C , is: AL= 0· 10 ha. Ap =020 ha
w CL= 100 Cp =0 40

C (4.7) Fig . 4.4 - Catchment II - composite impervious/ pervious


w catchment

ARRB SR 34,1986 21
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

4.3 TIME-AREA REPRESENTATION P Time-Area


representation
A of area Aha.
The basic Rational Method assumption that
_impervious
' ••• the speed with which runoff elements
travel to discharge point, 0, is steady ••• '
stated in the previous section is capable of
11 11- catchm ent
total area
3A
~-- --- Aha.
much wider interpretation than eqn (4.2) might T
suggest, for it implies the existence of a
fixed relationship of proportionality between
catchment area and time. Fig. 4.5 illustrates
thi s for the case of a rectangular (approxi-
t \: J
w
E
1 fA 2
f-- :;: <{
mately) impervious catchment of uni form slope w
and plan area A draining to point O. Time of '"
<{
A
concentration for the catchment is tc minutes. \ \] f j 4"
travel time

t\-\- II
In this catchment, the speed of travel is --L from this
the same at all points at all times (Rational boundary =t
Method assumptions). It follows that runoff area
= 1;. 0 tc tc 3tc tc
from the lowest quarter of area A has either
passed through 0 at time t /4 mi nutes after
4 4zT
TIME -
the commencement of a consta~t intensity storm
0
on the catchment or .iust arrived there. The
area A/4 is described in this situation as the
Fig . 4.5 - Time-area graph fo r simple catchment of area A
'area contributing to runoff at 0 at time and time of concentration te
t /4.' Similarly for the area/time pairs A/2
a~d t /2, 3A/4 and 3t /4, A and t • These
pairs,c plotted in Fig~ 4.5(b), yfeld the
time-area relationship for the catchment.
0 20
Similar graphs can be constructed to
:-
describe the time-area responses of real-world <{
V
catchments which are irregular in shape, I..LI
/" C Ap'0 '40x 0·20
non-uniform in slope and which include a mix '"
<{ rtI
.s:;
,1008ha
Vl / /PE RV IOUS
of pervious and impervious components. :::>
o
Representation of such catchments on simple :; V CATCH MEN
~ 0·10 /
time-area plots requires the 'contributing
are",' of each component to be expressed in
Cl.
~ /
terms of equivalent impervious area i.e. the >--
z <{
II IMPERY lnJ 1<; Ci Ai =lOOxO'10
product of runoff coeffi c i ent and component I..LI U
=0·10ha
area, (CA). The time-area graph of Catchment
-'
;:'!: / CATCHMENT

II, presented in Fig. 4.6, illustrates this


process: basic data for the presentati on are
CI
I..LI V tL{20mins tc=60 mins

o 10 20 30 40 50 60
listed in Section 4.2 in the derivation of TIME (minsl-
eqns (4.8)-(~.11):

The time-area concept which provides the Fig. 4.6 - Time-area graph for catchment II
theoretica 1 base for the ma .iority of present
day urban catchment ra i nfa 11 /runoff response
models was first presented in Austral ia by
Ross (1921) and Hawken (1921) and developed in The earliest published account of Rational
the papers of Reid (1927), Riley (1932) and Method principles being applied in the study
Escritt (1965). of urban catchment rainfall/runoff response is
attributed to Kuichling (1889). In his paper
Ku i ch 1 i ng presents ra i nfa 11 and runoff data
for four developed catchment in Rochester,
4.4 WHY A 'NEW' RATIONAL METHOD? N. Y., and postul ates that peak ~ l ow will be
observed at any point in a s wer)~hetwork when
A 1983 survey by Professor D.H. Pilgrim (UNSW) maximum storm intensity is applied to the
revealed that use by Australian practitioners upstream catchment for duration:
of the Rational Method to estimate urban storm
runoff flows far outweighs use of all other
methods. The su rvey a 1 so showed tha t tabu 1a r ' ••• equal to the time required for the
or 'hand' calculation procedures of the type concentration of the drainage waters from
presented in the Urban Drainage Design chapter the entire tributary area at the point of
of the 1977 version of 'Australian Rainfall observation. '
and Runoff' (I.E. Aust., 1977) were employed
by over 80 per cent of respondents. Lloyd-Davies (1906), in the published
report of his investigation of three Birming-
It seems appropri ate therefore to bri efly ham, U.K., developed catchments adopts a quite
address the question of Rational Method use contrasting position concerning time of
and to explain why a 'new' Rational Method concentration which he saw as involving travel
flow estimation procedure is being proposed from the extremity of the impervious or paved
for use in small urban catchments at this domain only. In a reworking of Kuichling's
time. Rochester data, included in his paper,

22 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Lloyd-Davies assigns new, shorter concentra- drainage unit directly-connected *


tion times intending to r pmove, presumably, impervious or paved area, ha
what he considered to be Kuichling's un-
necessary allowance for pervious area travel drainage unit pervious area
time from the extremity of the 'enti re
tributary area'. (A Ai)' ha
Thus arose the duality of urban drainage where A drainage unit total area, ha
time of concentration interpretations which
persist to this day with neither leading to c) rainfall intensity, i = average intensity,
wholly satisfactory outcomes in every case. duration t , obta i ned from catchment
British practice has tended to follow rainfall i<;'tensity-duration chart for
Lloyd-Davies' interpretation (National Water selected ARlo
Council and U.K. Dept. of Environment 1981;
Hall 1984) while urban drainage designers in The flows calculated by this approach
North America have inclined more towards [using eqn (4.2)J are referred to as
Kuichling's view (ULI/ASCE/NAHB 1979; U.S. 'full-area' flow estimates.
Dept. of Transportation 1979; Environment
Canada 1980b). Practice in Australia has
generally adopted Kuichling's interpretation Part-area Flow Esti.ate
(I. E. Aust., 1977) but a standard 10 mi nutes
time of entry to the first gutter inlet, Peak runoff flows are also determined for the
reflecting the Lloyd-Davies ' approach, is used same catchment units using:
widely in Queensland.
a) critical design storm duration =t., travel
The Two-Value Rational Method flow time from the outer extremity of \he most
estimation procedure described in the next remote, directly-connected paved area
section is uncommitted to either inter-
pretation , an outcome which is achieved by the b) 'part' equivalent impervious area
simple expedient of computing flows 'both
ways' in every case. The decision to adopt
one or other of the alternative estimates (4.12)
which result in a given situation is left in
the hands of the designer.
c) rainfall intensity, i = average intensity,
4.5 THE TWO-VALUE RATIONAL METHOD duration ti ' obta i ned from ca tchment
rainfall intensity-duration chart for
Thi s method combi nes a number of Rational selected ARI
Method and t i me-a rea propert i es 1ead i ng to a
design flow estimation procedure that is The flows calculated by this approach
non-graphical and can be carried out 'by hand' [using eqn (4.2)J are referred to as
(i .e. tabular) or using spread sheet tech- 'part-area' flow estimates.
nology or by computer. It produces two
possible critical design storm outflows The theoretical basis for eqn (4.12)
(constant intensity storms) at the di scharge follows from time-area representation (see
point of each drainage unit. The two design Section 4.3) of the lumped paved and
out flows ari se from 'fu 11 -a rea' and separately lumped pervious components present
'part-area' considerations. in a multi land-use catchment. This is given
in Fig. 4.7, the main elements of which are
repeated from Fig. 4.6.
Full-area Flow Estimate
Strict time-area representation of the
Peak runoff flows are determined for single or paved and pervious components of real-worl d
multiple land-use drainage units in the manner catchments, differs from the simple model
described in Section 4.2 using conventional presented in Fig. 4.7. Justification for its
Rational Method procedures : use is therefore claimed on the grounds of
simpl icity and adequacy. It is simple because
a) critical design storm duration = t , it transl ates into an easi ly-understood
travel time from the outer extremity 8f tabular flow estimation procedure, and
the most remote pervious area

b) 'full' equivalent impervious area,


(CA)full = (CwA) * 'Directly-connected impervious or paved
area', A., is impervious area which contri-
where butes rlmoff di rectly to the drai nage
collection network. Such runoff may be
CiAi + CpAp con veyed by pi pe , channel or i nforma lly across
(see eqn (4.7)) paved surfaces before reaching the formal
Ai + Ap collection system e.g. roadside channels of
various types (see Section 3.5). Impervious
impervious or paved area runoff or paved area whose runoff is not
coefficient 'directly-connected' to the formal collection
system is included with pervious area, Ap (see
Cp pervious area runoff coefficient Table 5.3).

ARRB SR 34, 1986 23


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

adequate because it yields estimates which


involve much the same level of uncertainty as
is associated with more complex and 0·20
time-consuming methods (see Chapter 12). tt, x(p p
F
<l: ! ...V
Exa~le of Two-Value Rational Method ~! ( /
V
Cp Ap =O'OB ha.-
Consider the peak flow estimates (design ARI = 5 "<::
V') '"
\ ~
,,/' Pervi pus
Compo ent
10- years)
'full-area',
which may be derived from the
F, and 'part-area', P, condi ti ons
:>
a:
~ 0·10
:,.../ Xi
which arise in Catchment II, represented in
Fig. 4 . 7. / (CA full

Full-area estimate:
/t
1St.
tICAl
pa r t
(CAl part =

~ Cl , l = 0·10 ha Cl AL{t - Cp Ap]


<.J
= (CwA)
equivalent impervious area
b
= 0.18 ha I tl 20" t, 60"
o ro m ~ ~ ~ W
storm duration (equal to t c ) = 60 minuLe~ 11M!: (mmsl

hence i,o 25 mm/h Fig . 4.7 - T ime-area representation of multi land-use


[from Fig. 4.2 (b)] drainage unit (catchment II) with derivation of
part-area (CA) algori thm

Hence, full-area peak flow estimate,


storm duration (equal to til = 20 minutes
(0 . 18) 25
Qf = 12.5 Lis (4.13) hence i,o 48 mm/ h
0.36
[from Fig. 4.2 (b)]

Part-area estimate: Hence , part-area peak flow estimate,


equ i valent impervious area
(0.13 )48
C.A. +
1 1
ti
[ c·
x CA
p
J
P
0 . 36
17.3 Lis (4.14)

1
20
(1.0 x 0: 10) + -- x (0 . 4 x 0 . 20) RecofTlllendation: outlet works for point 0 in
60 Catchment II should carry a design flow (ARI =
- 0.127 ha 10 years) of 17.3 Lis.

24 ARRB SR 34, 1986


5
Hydrological data base

The hydrological data base comprises six main Sub-divisions are frequently developed without
topics: provision for rear-of-a110tment runoff
collection making the required travel time
a) Ultimate development assessment difficult if not impossible to estimate.

b) Storm rainfa11-frequency-duration data In its 'ultimate' state, such a sub-


division will have evolved. almost certainly,
c) Australian climatic zones - urban drainage an internal drainage network extending that
originally provided. While the peripheral
d) Selection of design average recurrence components of the long-term development, e.g.
intervals rea r-of -a 11 otment dra i nage channels, etc. may
be omitted in the first-stage building
e) Travel time determination programme, it is the c 1ea r respons i bi11ty of
the designer to ensure that the principal
f) Runoff coefficients for developed in-ground components of the required ultimate
catchments dra i nage support system - underground pi pes,
gutter inlets, junction pits, etc. - are there
5.1 ULTIMATE DEVELOPMENT ASSESSMENT and are matched to the stormwater load which
the system will in time be called upon to
Before the task of designing a major/minor carry. The completed drainage network must,
stonnwater drainage scheme for a deve10pi ng of course, be assumed in the design and
urban catchment can be commenced, the designer selection of these components.
must obtain or compile a plan for its ultimate
development. Little firm guidance can be
offered for this task. 5.2 STORM RAINFALL INTENSITY-FREQUENCY-
DURATION DATA
Urban zones can remain remarkably static
for long peri ods, e.g. some rura 1 vi 11 age The storm drainage design procedures described
residential blocks as well as areas which have in this Handbook are 'peak flow' methods which
reached a high level of commercial/industrial employ average stonn rainfall intensities
development. Others - in particular, the low only. Storm temporal patterns are not
and medium density residential suburbs of our appl ied.
cities - frequently experience rapid growth
and change. This may follow land value Designers must therefore consult Chapter 2
increases and consequent rate esc a 1at ions or of the current edition of 'Australian Rainfall
the enactment of by-laws aimed at reducing and Runoff' (I.E. Aust., 1977 or 1987) to
urban sprawl, e.g. Amendment 367 of the obtain required storm rainfall data.
Melbourne Metropolitan Planning Scheme.
A typical rainfall inten sity-frequency-
Des igners faced with dr awing up their own duration chart (I-F-D graph) for an Adelaide
predictions are advised to study local region foothills, South Australia, location is
10ngtenn planning predicitions and development presented in Fig. 5.1. Only data required to
trends taking place in the areas of concern deSign drainage systems for small urban
and in similar areas and derive their ultimate catchments in the regi on are presented i.e.
deve10plllent predictions by extrapolation and storm duration range 5 minutes to 60 minutes.
engineeri ng judgement. The time hori zon for
such deve10ptllent prediciton should be 30-50
years.
5.3 AUSTRALIAN CLIMATIC ZONES URBAN
There is one aspect of drainage design DRAINAGE
uncertainty which can be significantly reduced
by 'ultimate development' considerations. The Australian continent experiences a wide
This relates to the estimation of travel time range of climates which affect significantly
to the first (downstream) gutter inlet of the rainfall/runoff responses of her urban
runoff from the most remote allotment of a catchments. The most obvi ous indicator of
sub-division, where this property is climatic difference is rainfall (see Table
down-slope from its fronting roadside channel. 5.1) •

ARRB SR 34,1986 25
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 5.1
110 1\
\ ADELAIDE FOOTHILLS
Average rainfall intensitie s f or c---
MONTHLY AND ANNUAL RAINFALL (11lT1) -
1\ \ storm s of short durat ion AUSTRALIAN CAPITAL CITIES
100
\ 1\ CITY JAN FEB MAR APL MA Y JNE JLY AUG SEP OCT NOV DEC TOTAL
90
\ \
1\ 1\ Adel a ide 20 21 24 45 69 72 67 62 51 45 30 27 533

80 \ \ \ Br i sbane 167 166 151 BB 69 72 57 47 48 76 95 128 1164


\
1\ Ca nbe r ra 59 55 53 49 52 39 37 43 50 69 63 60 629

70 1\\ 1\ \ \ Oarw i n 398 325 265 97 15 3 1 2 13 54 123 244 1540


\
.c
"-
E
\ 1\ . c--- Hobart 48 41 4 7 55 49 59 53 49 52 64 56 58 63 1
E
60
\\ \ \ \ Melbourne 48 50 53 59 57 50 49 50 59 68 60 58 661
.;:-
.;;;
\ 1\ \ '\.I'\. Perth 8 11 20 46 124 185 174 137 81 55 21 14 876
c: \ \ \ \. ~
'"
""
'"c: SO Sydney 102 114 129 131 123 131 106 81 71 81 78 79 1226
1\ 1 \ \. ~ ""-.... '" .zzc
1
~
c: 40
,,'\
\ \ " I" '-... ~ ~~ ~ So urce : CUII DII UII W~dllh Del-'L. ur
Burea u of Meteorol ogy
~L i e n(e -

.~

~ ~o r---.
0:

"" '"'"
I'.........
I"'--- ~
y,
y;:r-z.-r--.
'" '"
'"~
'"
30
"-.... ~ :;sI-- r- In the sect i on s wh i ch follow , zone-
~

20
..........
r--.........

I'-......
~
~
...:....t..!. ~
-- r- dependent hydrological data are presented for
the Northern Austral i a and Southern Austral i a
zones only: data for Intermediate Austral i a
I-- locations are to be determi ned by interpola-
tion. The recommend ed procedure for inter-
10
polating a value for parameter P at station X
is:
10 20 30 40 SO 60 1. Det e rmi ne Northern Austral i a and Southern
Sto r m Duration (mi nutes ) Australia values for the parameter of
intere st - Pn and Ps , respectively;
Fig. 5.1 - Rai nfall intensity-frequency-duration chart for
Ad elaide Foot hills, Sout h Australia: storms 01 short durati on 2. Determine the 10-year, I-hour average
rainfall inte nsity ilt location X, i.e,.
The main determinant of storm rainfall/ \;
runoff res ponse ina deve loped ca tchme nt is
not mon t hl y rain f all but t he intensity and 3. Compu t e the requ i red value for parameter
du r ation of rainfall experienced during sto r m P: -
bursts. In all centres listed i n Table 5.1, i 25
except Perth , storm bursts occurri ng duri ng x
SUlllllle r' pr od uce highest intensities : this is P (P - P )
x n s
in sharp contrast with monthly rainfall whi ch 70 - 25
may yiel d highest gaugings , as in Adelaide , in
Wi nter. (5.1 )
The need to divi de the Australian
continent into climatic zones whose urban NORTH ERN AUSTRALI A
catchment s respond ins i mi 1a r ways has been 10 yea rs, 1 hour avera ge ra infall
i nte nsi ty , L,0.,:;.70 mm / h £:7)
explored by the AR&R review team led by
Professor D.H. Pilgrim (UNSW). Three zones
have be en de fined on t he basis of average
rain fa 11 i ntens i ty observed in stonn bursts of
design ARI = 10-years an d durat i on I-hour.
The zon es are :
Northern Australia zone
10-year , 60 mi nute avera ge intensity
~ 70 l1lT1/h

Intermediate Austral i a zone


10-year, 60 minute average intensity:
Pert h
range 25-70 mm/h • Sydney

Canber r a
Southern Australia zone 10 ye ars, 1 hour average rainla II
inten sity , L,0,,';;25 mm / h
10-year, 60 minute average intensity
~ 25 mm/h
~Hobart
Approximate boundaries for the three zones are
shown in Figure 5.2 Fig . 5.2 - Austral ian cl imatic zones - urban drainage

26 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Example: In the Adelaide illustration referred to


above. the 100-years ARI fl ood could only be
Find the runoff coefficient for pervious areas successfully conveyed by the dual above-ground
(design ARI = 10-years) i.e. [ClOJ pervious' and underground systems. each des i gned to AR I
for Penrith. N.S.W. = 5 years (approximately) standard. if the
underground system remained unblocked. This
STEP 1: [C,o Jpervi ous for Northern Austral i a raises the practical issue of blockage which
= 0.70 is a necessary ingredient in the definition of
'gap flow':
[C,o J pervious for Southern Austral ia
0.10 Gap flow. Ogap. is the difference between the
design rare flood peak flow estimate at a
(from Table 5.3) particular location in a drainage system
and the peak flow estimated for the under-
STEP 2: the 10-year. 1-hour average rainfall ground network at that location assumed
intensity at Penrith:- unblocked or partly-blocked by the de-
signer. The entire gap flow is carried
44 mm/h in the surface drainage lines of the
Penrith major system.
STEP 3: [c'0 J pervious for Penrith Where major system design is based on
= 0.1 + 0.022 (44 - 25) (0.70 - 0.10) fully operating underground networks. i.e.
unblocked, then gap flow is. simply. the
= 0.35 (5.2) difference between major system desi gn fl ow
and minor system flow.
Taking Y = 100-years and Y = N-years as
the rare and nuisance design frequencies re-
5.4 DESIGN AVERAGE RECURRENCE INTERVAL - spectively in a given case (see Sections 2.5,
2.6) :
MAJOR/MINOR SYSTEMS
FIOO · ilOO(CA)lO
0'00 Lis (5.3)
The two-ti ered nature of the major/mi nor 0.36 .
concept for managing storm runoff in the urban
landscape is described in Chapter 2 and the
F
n i n(CAh a
consequent need for a pair of design ARI's in Lis (5.4)
On
each total system explained in Sections 2.5 0.36
and 2.6. and

0gap 01 00 - On (5.5)
Design ARI recommended for major drainage (CAho
systems is 100-years; design ARI's suggested [FIO O.ilOO - F.i ] - - - Lis
for mi nor drai nage systems 'nested' withi n n n 0.36
major systems are listed in Table 2.3.
which can be restated as :
Fm . im(CAh a
It is clear that in a design rare flood.
say AR I = 100-yea rs. in an urban catchment Lis (5.6)
which incorporates conjuncti ve1y-acti ng 0.36
above-ground and unde r ground drainage net- The frequency conversion factors F '
works. a significant portion of generated IOO
runoff wi 11 be conveyed by the underground t/
Fn and Fm are found from Table 5.5. The fre-
system. It follows that the requi red capaci ty quency M [eqn (5.6)J is found by tria1-and-
of surface channels can be significantly less error ina gi ven situati on and is 1 inked to
than would be required if they alone conveyed the value assigned to N. N-M pairs for
the entire rare storm flow. In the case of catchments in Northern and Southern Australia
short-durat ion s to rms (10 mi nutes-30 mi nutes ) are given in Tables 5.2A and 5.2B (minor
in Adelaide. South Australia. 5-years ARI system, zero blockage).
average rainfall intensities are about half of
those observed in co r responding 100-year In cases where partial blockage is considered
storms. Thus. 100-years ARI floods can . li kely an arbitrary '50 per cent blockage'
theoretically. be conveyed through Adelaide assumption is suggested. This leads to appro-
urban catchments by a combinati on of surface priate modification of the expression for gap
and underground drainage paths. each designed flow. Ogap. given in eqn (5.5):
to carry storm runoff of approximately 5-years
ARI flood magnitude. 0100 - ~n
(CAho
Adoption of an appropriate design ARI for FIOO · i l OO - 0.5F n .;n
- - L/s(S.7)
a catchment minor system therefore opens the 0.36
way to not only its design but also the design This affects the value of M which arises
of the ma jor system which complements it. The in a particular case from the general
latter design procedure employs the 'surface expression, eqn (5.6). Values for Northern
flow' approach described in Chapters 8 and 9. and Southern Austral ia (minor system, 50 per
Frequency aspects, only. of this approach are cent blocked) are also listed in Tables 5.2A
exp 1ored here. and 5.2B.

ARRB SR 34, 1986 27


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 5.2A c) other cases


kerb-and-gutter channels
GAP FLOW (Qgap) underground stormwater drains
DESIGN AVERAGE RECURRENCE INTERVAL allotment drains (surface or
underground)
(M-years) FOR URBAN CATCIt4ENTS IN NORTHERN easement drains (surface or
AUSTRALIA underground)
grassed swa 1es
Minor s yst em under- blade-cut earth roadside channels
ground networ k - 2-yrs 3-yrs 5-yrs 10 -yrs natural channels
des i gn ARI :
N-years ,= Overland Flow
The kinematic wave formulation for runoff
Gap flow moving in overland travel time t developed by Ragan and
surface channels 6-yrs 5-yrs 2 -yrs l-y r Duru (1972) is reconfmended. Appropriate
only : design ARI
with minor system
values for the parameter Manning's 'n' enable
unbloc ked, travel times to be computed for paved surfaces
M- years= and for two categories of grassed surfaces:
( 1n) 0.,6
Gap flow moving in tc = 6.94 minutes (5.8)
surface channels 30 yrs 25 yrs 20 yrs 15 yrs i 0.'+ S0.3
only: design ARI
with minor system
50% blocked, where t overland travel time (minutes)
M-years = lC travel distance (metres)
n 0.015 for paved surfaces
n 0.25 for lawn surfaces
n 0.50 for thickly grassed surfaces
TABLE 5.2B i rainfall intensity (mm/h)
S surface slope (m/m)
GAP FLOW (Qgap)
Correct use of eqn (5.8) normally requires
DESIGN AVERAGE RECURRENCE INTERVAL two or three iterations. However, by applying
the following limitations:
(M-years) FOR URBAN CATCHMENTS IN SOUTHERN
AUSTRALIA s torm d~ration: 15 minutes-3D minutes
desi gn average recurrence interval
Minor system under- lO-years
ground network - 2 -yrs 3-yrs 5-yrs 10-yrs
des ign ARI: it 1s possible to construct a simple nomograph
N-years = which gives approximate overland travel times
directly. Because the computation of t
Gap flow moving in
involves storm intensity, a differen£
surface channels nomograph is required for each climatic zone
only: design ARI 20-yrs 15-yrs 10-yrs 5-yrs (see Section 5.3). Nomographs for the
with minor system Northern and Southern Australia zones are
unblocked, presented in Fig. 5.3. The minimum overland
M-years = flow time which should be used for any
catchment element is 2 minutes, e.g. travel
Gap flow moving in time from crown to gutter ina narrow
surface channels ca rri ageway.
only : desi gn ARI 50-yrs 45-yrs 40-y rs 30-yrs
with minor sys tem The time adopted for travel in a large
50% blocked, pervi ous area such as a major park or urban
M-years = forest must recognise the limits of the
overl and fl ow phenomenon. It is a matter of
field observation that 'sheet' flow rarely
5.5 TRAVEL TIME DETERMINATION progresses more than 200 m before entering a
(!, runnel or ri 11 with travel in the latter mode
Introduction falling into the 'natural channel' category
(see section below). Fig. 5.3 includes a
The following categories of flow travel time boundary (X-X) which f i xes appropriate limits
in developed catchments are recognised : for sheet flow travel in grassed catchments of
various slopes.
a) overland or 'sheet' travel
Because of the uncertainty which must
grassed surfaces surround assessment of overland (pervious
paved surfaces area) travel time to gutter or rear-of-
allotment d ra i nage channel (see Secti on 5.1)
b) roof-to-gutter travel in the most remote allotment of a residential
residential roofs catchment component, a standard 15 minutes is
commercial/industrial roofs suggested for this overland travel element.

28 ARRB SR 34, 1986


»
:0
:0
III
U)
:0
x
W NORTHERN AUSTRALIA SOUTHERN AUSTRALIA grassed and paved surfaces
-~
I /'
{ ~-9~ ~
,()''-'
L
~~
;--';t'-.
~ ~4'l: Atv~<?" ~I'- /'/ ./A C/)
{
~~,,~< J'U%~t--... \.o~~ //' ./'/ V -l
o
l:~~"~
y/c: t'... ~J'
At('~~
l"-."-
~c,
,;§
r...1>~
./ " , / / ~V
/' :0
s:
1-~~~ 1>~~ c,;.t:I~'1./' ,/ V/ L</'V/ o
""~"
./
/' :0
-1J'J'~~ ~ ~/)) 1>"'~~ / ,<::iKG/V V /"'L V »
h V <. z
"~ ~ 'O/))~
./ / / ~ V
V ./
~
' / ~i<-~'
,;§ - -
»
G')
'" ~' ::::~ "- V . / / ./.L / ' ~ V ~~o;;,'"
V m
'/v ~1> o
~ ~ ':~ ~ V
V , /V / / ' ~ V m
C/)
,,~
t---.. ~ ~ ~ V ./V , / .// / V G')
Z
~ ~ f~ ~ ..:>. / ./v , / "/ l
Z
~ f7,~ ~
,/
°0 V /' ././ C/)
"./)) /))~/))' V ./ s:
-1 /' »
r
60 50 40 30 20 15 1098 7 6 5 4 3 2 60 50 40 30 20 15 109 8 7 6 5 4 3 2 3 4 5 6 8 10 20 30 4050 100 200 300 r
C
TIME OF TRAVEL OVER SURFA(E, tc (min) TIME OF TRAVEL OVER SURFACE, tc (min) LENGTH OF OVERLAND FLOW, I (metres) :0
III
»
Z
NOMOGRAPH BASED ON : EXAMPLES : NOTE : (')
(In )06
Length of overland flow : 1= 100 m
»
-l
- tc = 6'94 LO'4S0'3 The boundary X X defines the limit for sheet flow
(')
Average slope of surface : 0, 010 path length ( ll i m) on grass or unpaved surfaces, I
- Equation 5,8
Description : sports field, Southern Australia e,g, ll im for 0,20 grassed slopes = 50 m s:
Ragan and Duru (1972) m
(use Residential Lawn) llim for 0' 05 grassed slopes" 120m Z
- L (Northern Aust, ) = 125 mml h -l
C/)
Hence, time of travel , tc = 38 min s, etc
- L(Southern AusU = 50 mm/h
For same field case in Northern Australia Pervious surface flow travel exceeding these l imits
tc = 27 mins, should be treated as "natural channel" flow
Hen { e, sa me case in Penrith ,NSW, (see exa mple (see Figure 5,4)
Section 5,3) tc=38+0,022(44-25)(27-38) =33 mins

I\)
CD Fig , 5,3 - Overland flow travel time (shallow sheet flow only) for Australian urban catchments

l ( ~ 1
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Roof-to-gutter Flow roof-to-drain element only. Allotment drain


travel time should be treated as a separate
Considerable uncertainty must also surround element.
roof -to-gutter flow tra ve 1 time. Two va 1 ues
are recommended: In situations where terminal on-site wells
and sumps are used. components contributing
r e sidential roofs : 5 minutes
runoff to these installations should be
commercial/industrial roofs: 10 minutes excluded from the catchments of associated
minor drainage system networks (see Section
In cases where residential roof water is 3.2) •
conveyed directly to a r ear -of-allotment
drainage channel, the 5 minutes va lue should Non-termina 1 stormwater management
be used for travel time to this collector measures e.g. on-site retention/overflow wells
a 1so. and seepage beds. i ntroduce del ay into
roof-to-gutter runoff travel times . Where
Where commercial/industrial roof water is these measures are employed (see Section 3.3),
discharged to an allotment drain feeding 10 minutes extra travel time should be added
stormwat e r to a fronting gutter or underground to the times listed above. (No other altera-
network pipe. the 10 minutes travel time tions to catchment parameters. e.g. runoff co-
recorrmended above app 1 i es to the d i rec t effiCient, are required.)

30·0 ,--------.----.---,-y-r--r--,--r-r--.-rr~rT"1___r--".----,.____,>rT",_,'V'I

250 t -- ----+- --+- -f\-- t -t---t++-t----t1'-t---f-Ht---T-fI---t-n'j-f-iTfl

200 f--- --l-- --+-++--f---I---t4-+-tf+--I''---If--1-f!---+-+H+f1'--f1'¥J

15 0 f-----l-----+,I~+-+--,i--+--v:-l-+f +t41+IhH-f-Hr--H-~

10 0 f------t-~'---t-___t-it----+ -fl--+.A--tf---1f---+--+-1hH-I-I'-I-lI-H+hH

VI
5·0
~
w
E
40
-'
u.J
z: JO
z
«
OJ:
LJ

u.. 20
<:)

-'
-'
1-5
~

10

0·4 f--1--hr--I--+-I--It--Htf--Ir--f+l~f--fb'-H,-I--If--1f--ftf+---+---H

FLOW DI STANCE (metres)


NOTES :
Ref : Country Roads Board ,
1. Flo w travel time (ap proxi mate) ma y be ob ta i ned direct ly fr om this chart for : Vi ctoria , 1982.
- ker b- and - gutter chann el s
- und erground stormwater channels
-a llotm en t channel s of all types ( su rface and underground)
-drainage easement channels ( surface and underground)
2. A mul tiplier, t. ,s hould be applie d to value s obtai ned di rec t ly fro m the ch ar t in t he
f ollowin g ca ses :
-gra ssed swales, well maintained and without dr iv eway crossin gs t. =4
- blade-cut earth road si de channel s, well main ta ine d and wi thout drivewa y cro ssi ng s t. = 2
- natural channel s t. = 3

Fig . 5.4 - Fl ow travel time in channels

30 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

General Channel Flows 2. second grade paved areas These incl ude
car-park, drive-in cinema and block-paved
All other travel time cases can be found with areas which are, compared with typical
the aid of Fig. 5.4. This chart i s reproduced fi rst grade pa ved areas . re 1ati ve ly
from Chapter 6 of 'Road Design Manual' porous. Runoff from these areas may pass
(Country Roads Board , Victoria 1982). The directly to the formal collection system
chart NY be used directly to determine or to terminal or non-terminal stormwater
approxilllate travel tiMes in a range of rigid management installations;
ch annel types and , with the applicatio n of
multiplier ~, a range of loose-boundary 3. unconnected paved area This category
ch annel forms. includes all paved areas whose runoff
passes to the pervious domain before
reaching the formal collection network.
Mini~ (Total) Flow Travel Ti.e
4. pervious areas This category includes all
Although travel time from elements of networks non- paved areas and areas of similar
may be as short as 2 minutes (see above), nature e.g. lattice-block reinforced
total nominal flow travel time from any grass. Runoff from these areas normally
component to its point of entry into the passes to the collection network by way of
unde rground dra i nage collect i on network must informal paths and drainage lines.
be not less than 5 minutes.
Basic runoff coefficient values for the
All carriageway components up to 200 m in four surfaces are listed in Table 5.3 for
length, regardless of slope, fall withi n this Northern Australia and Southern Australia
provision. Time of entry for these can zones. Values for the Intermediate Australia
therefore be assessed 'by inspection' as 5 zone may be obtained by interpolation (see
minutes. Section 5.3). Good design practice requires
that values such as those listed be applied to
components of the ultimately developed
catchment.
5.6 RUNOFF COEFFICIENTS FOR DEVELOPED Wei ghted runoff coeffi c i ents, C , can be
CATCtKNTS determined for mixed development cat~hments by
inserting appropriate values from Table 5.3
Basic Values for Cl0 into eqn (4.7).
The task of adopt i ng runoff coeffi ci ents for
use in the design of drainage works for urban TABLE 5.3
catchments is made difficult for the designer
by: BASIC RUNOFF COEFFICIENTS (C l0 ) FOR VARIOUS
a) poor or non-existent data base from which DEVELOPED CATCHMENT SURFACES
satisfactory runoff coefficient values can
be derived;
Surface Classification Nort hern Southern
Aust. zone Aust. zone
b) uncerta i nty about the u 1t i mate extent and
type of development likely to occur in a First grade connected paved
catchment during its lifetime; and arpas:
- roadways ) C
l0
= 0.90 C
l0
= 0.90
cl distribution of various area types (roofs, - roofs )
general paved, previous, etc.) in a Second grade connected
catchment. paved areas, e.g.
- sealed carparks, ) IC = 0.75 C
l0
= 0.75
10
Study of aerial photographs of sample dr iveways, paved)
developments can provide useful design outdoor areas, )
information on item (c) above. Such etc. )
measurements, however, overlook the fact that Unconnected paved areas )
runoff f rom po rt ions of many roofs and from and )
some paved areas is diverted to the pervious Pervious areas: )
domain and should therefore be subtracted from - mi xed with paved areas) C = 0.70 C10 = O.~O
as i n residential land) 10
the cont ri but i ng paved a rea (A 11 ey and
Veenhuis 19831. The subtracted element should use )
be added to the contributing pervious area. - ma jo r urban open space)
areas, parks, etc. )

Four di fferent contri but i ng catchment


surface types are recognised:
ClO Values for Specified land Uses
1. fi rst grade paved areas These are hi gh
quality carriageway and roof areas which Study of aerial photographs, referred to
have a low capacity for absorbing water. above, reveals considerable variation in the
They may be connected di rectly to the paved/pervious distribution in such categories
formal runoff collection system or to as industrial, commercial and certain types of
terminal or non-terminal stormwater residential accommodation, e.g. town house and
management installations. strata-title developments.

ARRB SR 34,1986 31
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
/

TABLE 5.4
RUNOFF COEFFICIENTS (~o) FOR VARIOUS DEVELOPED CATCHMENT LAND USES

Land Use Description Nort he rn Australia Southern Au strali a


zone zone

I NDUSTR IAL
. heavy industry 0. 80 -0.90 0.80-0.90
light industry 0 .70-0.90 0 .60-0 . 80

COMMEI{C IAL
. city shopping complexes 0.90 0.90
suburban shopping complexes 0.80-0 . 90 0.70 -0.80
city office blocks 0 .90 0 .90
suburban office blocks 0.80-0.90 0 . 75-0.85

RESIDENTIAL * full-area II part-area ful 1- and part-area


20 residences/ha 0.80 I 0.55 0.45
15 residences/ha 0.78 I 0.50 0.35
10 residences/ha 0 .75 I 0 .43 0.25
5 residences/ha 0.72 I 0.35 0 .1 5
town house developments 0.60-0 .90 0.50-0 . 80

* includes allotment area only, i.e. excludes roadway


reserves, community buildings and open space domains.

Some consistenc'y is apparent, however, in divisions yields the 'P' and 'F' conditions
the general categor'y of Australian fami1'y indicated in Fig. 4.7. Where pervious area
residential accommodation. Measured samples contrihution is low, as in Southern Australia:
from nine Adelaide residential suburbs taken
with the findings of Heeps (1977) and of (CA )fu11 (CA)part
Aitken (1975) 'yield the following (5.10 )
relationship:
and a single ClO suffices. In Northern and
per cent impervious in allotment area
Intermediate Austral ia the pervious ar ea
runoff cont ribution is frequently comparable
3.0 RU - 5.0 to that of its associated paved area and,
(5.9 )
hence, the eqn (5.10) appruxillidtion cannot be
where RD residential densit.Y in justified. Two runoff coefficients
residences per ha of allotment area, i.e. correspondi ng to the fu ll-area and part-area
exc1 udes roadwa'y reserve, nature stri ps, conditions must therefore be entered.
etc.

Eqn (5.9) is satisfactor'y as a per cent Frequency Conversion Factor, F


y
impervious approximation for RD < 20
residences per hectare, but should be applied Derived runoff coefficients such as those
with caution above this limit. Specifically, 1 isted in Table 5.4 should be multiplied by a
it should not be applied to town house or frequency conversion factor, F , where design
strata-title unit t'ypes of development. a ve rage recu rrence i nterva 1, .Y y , other than
10-.yea rs is requ ired. Recommended va 1ues for
Table 5.4 lists runoff coefficients (C,o) Fy are listed in Table 5.5. Application of
for va ri ous 1 and-uses in the Northern these ma.y give C values, in certain
Australia and Southern Australia zones. y
Values listed for the residential categories ci rcumstances, greater than 1.00. A 1 imit
are based on impervious percentages gi ven by va 1ue 0 f Cy = 1 .00 shou1 d be adopted in such
eqn (5.9) reduced b'y one quarter (transferred cases.
to the pervious domain). This follows Alley
and Veenhuis' (1983) finding that significant
segments of residential land-use paved area is TABLE 5.5
'unconnected'.
FREQUENCY CONVERSION FACTOR F
Li sti ng of two C,o values for residential Y
drainage units in Northern Australia compared
with one for Southern Austral ia zone cases ARI (years) 1 2 5 10 20 40 60 80 100
deserves explanation.
Conversion 0.8 0 .85 0.95 1.00 1.05 1.1 3 1.17 1.19 1.20
Strict adherence to the Two-Value Rational factor, Fy
Method · (Section 4.5) in residential sub-

32 ARRB SR 34,1986
6
Hydraulic data base

The hydraulic data base for Handbook design o Manning's formula -


procedures includes eight main sections : -
a) 5tormwater conveyance in open channel (6.1)
drains
b) Gutter inlet hyd raul i cs
c) Guidelines for the management of surface- o Izzard's (1946) triangular flow forfllJla
movi ng f1 ows (modified) -
d) Underground networks: an overview
e) Gui de 1i nes for the management of under-
ground-moving flows
f) Minimum Grade analysis hydraulic data
g) Hydraulic Grade Line analysis hydraulic
data where Vave = channel flow average velocity
h) Tests for pit overflow and pipe obvert (m/s)
depth. n = Manning's 'n'
R hyd raul i c radi us, i.e. flow
area divided by flow boundary
6.1 OPEN CHANNEL STORHWATER DRAINS 1ength (m)
So channel bed slope (m/m)
Three broad categories of formed open channels Ot trian9ular channel total
used to convey stormwater through and beyond flow (Lis)
small urban catchments fall within the scope a shape correction factor
of this section. These are:- l reciprocal of channel cross-
slope
a) roadside unlined table drains and swales d triangular channel flow
[see Figs 3.7{a) and (b)] depth (m)
b) roads i de gutters with kerbi ng [see Fi gs
3.7{c) to (f)] The shape correction factor which
c) drainage easement channels of various should be used in the case of simple
types. triangular channels is a = 0.9
(Clarke et a1 1981).
Information on travel times and, hence,
flow velocities in these classes of channels A special form of Izzard's formula is
are given with Fig. 5.4. This infonnation is, used for composite kerb-and-gutter channel s
generally, satisfactory for flow est i mation whi ch have gutter cross-s lope and roughness
purposes but is inappropriate for use in the different from those of the carriageway pave-
hydraulic design of such channels. Two formu- ment. This formula is:-
lae are offered for these purposes : -

f--- - - spread, W - - -- ----4


. 1. Qfr ( Q t - Q f r) where la, na , d a , lb, nb and db are as de-
fined in Fig. 6.1. In this case the shape
correction factor, a, which should be used
takes a value not greater than 0.8 (Clarke
et a 1 1981).
Manning s n"= nbU

In general , Manning ' s formula is recom-


mended for channels of broadly rectangular
shape including steep-sided trapezoidal chan-
nels and pipes flowing partfu11. The modified
Izzard's formula should be applied in triangu-
Fig . 6.1 - Definition of terms for composite lar channel cases including swales (side slo-
(i.e. ke rb-and-gutter) roadside channels pes 1 in 3 and f1 atter) and kerb-and-gutter

ARRB SR 34, 1986 33


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

composite section channels (see Fig.3.7 for 8 0. 8; Za = 8-10 ; Zb = 25 - 40;


examples). (6.6)
gutter width 0.300 - 0.375 m
Values for Manning's 'n' compiled from
various sources are listed in Table 6.1. concrete, na 0.012; flush seal'l
(6.7}
It is convenient when dealing with compo- nb = 0.01 8; hotmix, nb = 0.014;
site channels to regard the total flow, Ot, as (see Table 6.1)
the sum of two component flows: Ofr or 'fron-
tal flow' moving within the gutter and (Ot - Substitution of values Za = 8; Zb = 30;
Ofr) moving on the pavement (see Fig. 6.1):-
gutter width 0.375 m; nb = 0.014
3758[j~:} dbB/3)Js~/2
B3
0fr (d a / - L/s into eqn (6.3) leads to:-
(6.4)

(6.5)
(6.8)
By assigning a particular value to da and
Eqns (6.3) - (6.5) are used to determine:- hence db (see Fig. 6.1) eqn (6.8) reduces to
the form -
1. fl ow spread, w, in selected channe 1s con-
veying nominated flows; (6.9)
2. flow rate for certain depth and velocity
criteria conditions which form part of for the selected value of da • This relation-
Handbook design procedures; ship may be presented on a graph with values
3. estimates of flows captured by various of da coveri ng the full range of interest.
types of gutter inlets. Graphs representing two of the gutter/pavement
profiles included in eqns (6.6) and (6.7) are
Values for the parameters 8, Za, na , etc . presented in Fi g. 6.2. Note that any roadside
which apply to composite channels of the types channel type (rectangular, triangular , compo-
widely used in residential streets in site, etc.) can be described by a single curve
Victoria, South Australia, Northern Territory, on the depth versus Ot (= K~ plane of Fig.
QllPpnsland and A.C.T. are:- 6.2.

0 0·01 0·02 0·03


Gutter
0·04
Longitudinal
O'OS 0·06
Slope, So ( m/m )
0·07 0·08
-0·09 0·10

0·200
--Criterion 1
A

E
I 0·180
da 1> a·200m cases

Zb = 30 or 40
3
_ _--+--_-=---j-_ ",- 0
rorn
ClJ
L
a.
Vl N
II
Ll

d
D S'Om
..c.- 0·160 3-7Sm
.....a.
o
~
ClJ

0·140
B -- 3-Sm 4'Sm

4'Om
LL 3'Om
ClJ
3-Sm
'" 0·120
Vi
I
Ll
L 3'Om
ClJ da = 0-200m W= 2·5m c. da= 0'118m
~
A {
50 = 0'015m C{ so= 0·020
111
0·1 00 ~---I'-I--++----+-- Ut = 5585 S~I= 684 Lis Ut= 1040 So = 147 LIs 2'Sm

I
, B
{ da =0'150 m
50 = 0'057m T o{
w= 1'Om c. da= 0'06Bm
50 = 0·020 1'Sm
I 2'Om

~I----++----+-h-B- ,:',,~ u,
0t = 170 5~11= 24 L1s
0·080 0,,2300 0 '.Om ;:::

0 ' 060~~--~--~~~~----~~~~--~~~~~----~~~~----~~--~~
o 2000 Sti/2 4000 Sel l2 6000 Sd /2 8000 Sel l2 10000 Sel l2
Half-Carriageway Flow Relationship (Qt=Ks3/ 2)

Fig. 6.2 - Depth versus flow relationship (KSo""l for two gutter/ pavement channel profiles

34 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Subsidiary axes indicating flow spread, Two criteria are recommended -


w, are also included in Fig. 6.2: terminal
values on these axes correspond to half-car- Criteri on 1: fl ow depth in roadway reserves
riageway spread. A separate spread axis is should be not greater than 50 mm
required for each roadside channel profile of above top-of-kerb. This criter-
interest. Although flow spreads greater than ion may be interpreted in terms
an adopted maximum (say 2.5 m, the value used of kerb-side flow depth:
in later design procedures) are outside the
range needed for the design of minor drainage (d a ) > 0.20 m (6.10)
systems, major system use of possibly the
entire roadway reserve flow area requires in- Criterion 2: product of kerb-side depth and
formation from this domain. The depth versus channel flow average velocity
Ot relationships are therefore e xtended to should be limited :
cover flow depths likely during major flood
occupancy of roadway reserves. The need for (6.11)
criteria limiting this use is clearly indica-
ted. The first criterion limits the flood
stage level particularly in terrain of flat
TABLE 6.1 grade. The second 1 imi ts the potentia 1 for
i nju ry to pedest ri ans and damage to vehi c1es
MANNING'S 'n' ROUGHNESS COEFFICIENT resulting from the effects of deep, fast-mov-
i ng fl ood waters (Gordon and Stone 1973)
FIXED BOUNDARY DRAINS this criterion follows National Capital Deve-
lopment Commission practice (N.C.D.C. 1981).
Concrete pipes (flowing part-full):
new condition 0.011 Graphi cal representati ons of these cri-
normal condition 0.013 teria have been added to Fig. 6.2. They show,
poor condition 0.016 for the gutter/ pavement profiles featured,
that -
FRC pipes (flowing part-full):
new condition 0.009 (i) Criterion 1 overrides Criterion 2 in
normal condition 0.011 roadways of flat longitudinal grade (So
poor condition 0.014 < 0.02).

Concrete surfaces: (ii) Criterion 2 overrides Criterion 1 in


steel trowel finish 0.012 roadways of mOderate-steep longitudinal
wood float finish 0.014 grade (So > 0.02).
broom finish 0.016
Th e genera 1 hyd raul i c i nformat i on con-
Corrugated metal : tained in Fig. 6.2 may be applied to a partic-
new condition 0.021 ul ar gutter/pavement profi 1e of interest to
normal condition 0.024 produce a graph of (half) roadway flow, Ot,
poor condition 0.030 versus longitudinal slope, So. The charac-
teristic double-cusp curve which results (see
Rough texture surfaces : Fig. 6.3) reflects the controlling effects of
stone pitchers or cobbles 0.020 - 0.025 Criteria 1 and 2. The derivations of points
A and B on the curve for a 7.5 m carriageway
Pavement: with pavement cross-slope 1 in 30 (Fig. 6.3)
hotmix - highway standard 0.013 are to be found in Fig. 6.2.
hotmix - residential streets 0.014
20 mm flush seal 0.018
Two other items of hydraul i c i nformat-
LOOSE BOUNDARY DRAINS AND SWALES ion, important in the design of minor drainage
systems, have been added to Fig. 6.3. These
Blade-cut earth roadside channels: relate to the Ot versus So relationships for
well maintained maximum allowable spread. Two cases are
(no driveway crossings) 0.025 shown : spread = 2.5 m and spread = 1.00 m.
poorly maintained The derivations of points C and D are also
(no driveway crossings) 0.035 found in Fig. 6.2. The significance of these
data is explained in Section 6.3.
Grassed swales :
well maintained Data similar to those presented in Figs
(no driveway crossings) 0.050 6.2 and 6.3 but determined for other widely
poorly maintained used gutter/pavement profiles are included in
(no driveway crossings) 0.060 Appendix A. The flow derivations reviewed
above have employed Izzard's triangular flow
Natural channels with medium vegetation: formula (modified) and, correctly, apply to
earth bed, normal meander 0.040 half -carriageway channels only. Where the
rock bed, normal meander 0.045 longitudinal slope of a roadway is, general-
coarse gravel bed, normal meander 0. 050 ly, 'down-slope', i.e. crossing contours at
near right angles, it will take a dual-channel
Main references used to prepare this table form making its total capacity double that
are: U.S. Dept. of Transportation (1979) ; indicated in Figs 6.2 or 6.3. Not all road-
Wanielista ( 1979) ; Dowd et al (1980) ways take this dual-channel form.

ARRB SR 34, 1986 35


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

1000 \ Ho t mix pavement

900

Gutter IPavement Prof ile


800

1 700 Zb =40
~ / carriageway half-width
.:=!
/ =50m
0 600
~-
0
Zb =30
u: 500 ~-+-f+----!--+-----l---1----L--=:>'I.....:c--L-./ carri ageway ha If - widt
>-
ro
~
WO =3 ·75m
OJ ENLARGED SCALE
~400
L
L
ro
LJ
300
-;;;
I

200

0J .
~
50
W=1 ·0m Ib= 30 D
100
Zb=40
w~ 1·0m
00 --- .005 010 015 020 025
°0 01 02 ·03 04 05 ·06 ·07
Gutter Longitudinal Slope . So (m / m)
·08
..
·09 ·10 ·11 12

Fig. 6.3 - Hydraulic capacity. Qt. data for two carriageway profiles: Zb = 30 and 40

Lateral streets, i.e. roadways running Much experimental work - the most rel i-
generally parallel to contours, are frequent- able using full-size rigs - has been carried
ly constructed with dual-channel carriageways out on grated inlets of many different types
provided that the terrain cross-slope is not (Department of Main Roads, N.S.W. 1979; Earley
great. A single-channel form is however, 1979; Public Works Department, N.S.W. 1985;
often adopted for residential and/or minor Burgi and Gober 1977). The main finding of
access streets in steep terrain. The critic- this work is that a grated inlet of any type
a 1 slope at whi ch the change inform takes will capture the entire 'frontal flow', Qfr
pl ace appears to be around 3 per cent as shown [Fig. 6.1, eqn (6.4)], presented to it pro-
in Fig. 6.4. vided -

dual-channel carriageway form


1. the grating is long enough
(length> 0.75 m)
2. grating open area is not less than 60 per
cent of total plan area
single channel carriageway form used for
lateral streets in steep terrain 3. bars are longitudinal OR, if bars trans-
verse, gutter longitudinal slope, So, is
not greater than 0.05.
slope usually steeper than 3 %
Two additional but subsidiary conclus-
Fig . 6.4 - Dual-channel and single-channel lateral street
carriageways
ions may be drawn from the referenced studies:
these concern gutter 1 ongitudi nal slope and
'side capture'.
6.2 GUTTER AND SAG INlETS Except for those conditions which lead
to flow 'skip' across the tops of transverse
St ormtlater i s normally call ected and bars and hence decreased performance (So >
conveyed in open channel drains of the types 0.05), gutter longitudinal slope increase
reviewed in Section 6.1 until diverted into leads to slightly improved capture. Also,
associated underground drainage pipelines. flow entering a flat grade grating (So < 0.01)
The structures which 'capture' this flow and along its outer edge i.e. 'side capture', can
transfer it from the surface to the under- be as much as 25 per cent of tota 1 captu red
ground domain may be divided into two broad flow. Thus, flow captured by a grated inlet
categories:- normally exceeds frontal flow, Qfr, the margin
of excess depending on the amount by which the
a) grated inlets length and area limits listed above are ex-
b) side-entry inlets ceeded.

36 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

These 1atter characteri st i cs of gutter side-entry inlets, with and without deflect-
grates are part ly, at 1east, offset by thei r ors, opening lengths Lis = 1.0 m and 2.0 m,
potential for blocking, the two effects tend- has been carried out in connection with the
ing to cancel each other. preparation of this Handbook : results are pre-
sented in Fig. 6.5. See also Hughes (1974),
It is therefore recommended that design- Mills and O'Loughlin (1984) and PWD, N.S.W.
ers adopt performance rel ationships based on (1985).
frontal fl ow, Ofr, capture only used with
constraints 1 to 3 listed above. Frontal The following general conclusions may be
flow should be calculated at the 'normal' drawn from study of these data sources :
gutter/pavement section regardless of inlet
'depression'. The DMR, N.S.W. (1979) study (i) inlet length, Lis, is the most import-
reveals a sl ight performance advantage for ant determinant of capture performance;
depressed grated i nl ets, compared with unde-
pressed inlets. (ii) 'depression' of inlet lip below gutter
alignment level (typically 50 - 60 mm)
Two 'per cent capture' levels are em- leads to significantly improved capture
ployed in the design procedures presented compared with the performance of an un-
later in the Handbook - 95 per cent and 80 depressed inlet;
per cent. Gutter longitudinal flows whose (iii) a side-entry inlet with opening length
frontal fl ows correspond to these percent- Lis > 1.5 m and depressed 50 - 60 mm
ages of total flow are listed, for the Sec- for full inlet length captures signif-
tion 6.1 carriageway illustrations (lb = 30 icantly more than approach frontal
or 40) in Table 6.2. Additional data of fl ow, Ofr;
similar type are presented in Appendix A.
(i v) use of deflectors leads to further im-
provements in performance particularly
TABLE 6.2 in medium-steep longitudinal grade
channels, that is, So > 0.03;
CAPTIilE BY 375 _ GRATED INLETS
(v) little difference in performance re-
(Gutter la = 8 ; pavement lb = 30 to 40, see sults from the use of different types
Figs 6.2 and 6.3) of deflectors (square, saw-tooth,
corrugated,etc.);
(vi) inlets whose trays extend beyond the
95% capture: gutter/ pavement ali gnment perform no
gutter approach flow = 22 L/s better than those with trays equal to
80% capture : gutter width (otherwise same geometry,
gutter approach flow = 43 L/s depreSSion, etc.).
Notes:
o grated inlet - full gutter width Design information similar to that presented
(t ransverse bars) in Fig. 6.5, determined for other carriageway
o 1ength « 0.75 m cross-section profiles, is given in Appendix
o grating open area « 60% of total area A.
I 0 gutter longitudinal grade, So ~ 0.05.
Two levels of 'per cent capture' are pro-
vided in these graphs - 95 per cent and 80 per
Pavement cross-slope, represented by the cent. The higher standard has been adopted in
variable lb, has a significant influence on place of 100 per cent capture because of the
the depth and spread of fl ow approachi ng a uncertai nty inherent in ri g results in the
gutter inlet. Over the range of design in- capture range 97 to 100 per cent : capture/by-
terest (80 - 95 per cent capture), each one pass flow division at the 95 per cent level
per cent change in cross-slope produces a is, by comparison, well defined.
change of more than 10 per cent in total flow,
Ot. For this reason, grating capture data Data for the lower standard - 80 per
should be applied from rig tests (preferable) cent capture - are provided to encourage the
or cal cul ations whi ch incorporate cross- use of systems which employ other than 'full
slopes that differ from design cross-section capture' units. Such systems can requi re
profiles by not more than half of one per less underground pipe than systems using
cent. 'full capture' units. Systems which incor-
porate 70 per cent or 60 per cent capture
The comprehensive report by the Storm units can show even greater economies. The
Drai nage Research Committee (1956) of Johns 80 per cent standard has been adopted in the
Hopkins University, Baltimore, U.S.A., pro- Handbook for reasons of simplicity and because
vides a wealth of design information on side- of its present, although limited, use.
ent ry inlets with and without defl ectors. The
model scale ratio used in this programme was Flow at a grated or side-entry 'sag' in-
1/3 full-size. A similar study conducted at let obeys the laws of weir flow. U.S. Dept.
the University of Newcastle, N.S.W., is repor- of Transportation (1979) offers the following
ted in Henderson et a1 (1980). Flow capture general formula:-
by on-grade side-entry inlets with deflectors
in residential streets in Canberra, A.C.T., 0i = 1.66 Li di 1 • S (6.12)
has been measured and is reported in Willing
and Partners (1978). Testing of full-size where Oi = sag inlet flow (m 3 /s)

ARRB SR 34,1986 37
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Li g length of grating perimeter (m) Figs 6.2, 6.3), sag inlet capacity flows for
excluding side closest to kerb, maximum spread of 2.5 m are:-
or
Lis length of clear opening (m) in 2.0 m grated inlets (undepressed),
the case of side-entry inlets 0i = 69 L/s
di depth of water above inlet lip
(m) 2.0 m side-entry inlets (depressed 50 mm),
Qi = 11 8 L/s
Depth di may be computed from carriageway
geometry, allowable flow spread and depress- (6.13)
ion of inlet lip. In the case of grated (un-
depressed) and side-entry (50 mm depressed) Simi 1 ar data for other gutter/pavement
inlets associated with carriageways of the sag inlet geometries are presented in Appen-
type used to illustrate Section 6.1 (see di x A.

110

100
--...-,
. 1·375mm" 1
Gutter Inlet-
with deflectors
150m~~F""" · ''''''-'''''''''''''''\\'
. o~.. Za= 8 · Zb = 33 '
90 Test Gutter / Pavement
Capture I Profile
r-~\---+---~--~--~~r-~---+---r--'---'-~

I
~
::::!
80 1 Curves ba sed on full size rig tests
conducted at South Australi an
Institute of Technology
2 All inlets depressed 50mm for full
0"'"' 70
inlet length
I- 3 Inlet t ray width equal to gutter width 1375mm )
UJ
--' 4 Test gutter/pavement profile as shown
Z
95% Capture
0 I I
I-
60 Capture
:r
LJ
I---I

, , t- 8~
« Legend
0
a: 2m inl et with deflectors
"-
"-
«
3
50
H--- 2m inlet without deflectors

~
0
--' 1m inlet with deflector s
<L-

40
a:
UJ
l-
I-
@ 1m inlet without deflectors
:::>
'"
30
95 % Capture
-f---j---+- --1

20 I-+-- j - --P.:-:::-'"-:-- t -

1 0 I -- - j ->"-- j - - t - -l-_-+":::::::~"""", -I-_ _


-t._-l--===1~=~9:.:5:....:% Capture
1--t_-If-...;8~0~% Capt ure

1----jr-_+-_+-_+-_+-~9:..:5:...;% Capture
o 0·02 0·04 0·04 0·08 0·10 0·12
GUTTER LONGITUDINAL SLOPE So (m/m) - - - -

Fig. 6.5 - Capture pertormance of 1.0 m and 2.0 m side entry inlets

38 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

6.3 GUIDELIIES FOR THE MNAGEMfJIT OF fl ows in these paths is complex. It is


SlilFACE-MOVIt«i FLOWS IN MIfC)R SYSTEMS therefore recorrmended that the process - in
particular, design of the underground network
The task of managing surface-moving flows - be divided into two tasks:
within an urban minor stormwater drainage
system involves design interaction among the Task 1. approximate network design prepared
various criteria which govern roadside chan- for design ARI = N-years, where N is
nel fl ow spread, kerb-side depth etc. and adopted on the basis of policy or
gutter inlet capture. The designer must public acceptance of similar schemes
formulate or be provided with a set of guide- elsewhere or from Table 2.3, and,
lines similar to those listed in Table 6.3.
These guidelines should not be regarded as Task 2. final network design which takes into
mandatory for use throughout Austra l ian prac- account network interaction with
tice. underground services, pipe cover
requirements, anti-sedimentation re-
Th e tenn 'f avou red gutter/ in 1et' used in qui rements, etc.
Guidelines 1 and 3 of Table 6.3 deserves ex-
planation. The manner in which these tasks are exe-
cuted brings to light two areas of controversy
Australian practice uses a multitude of among practitioners:-
different gutter/pavement profile and gutter
inlet combinations which owe their acceptance a) should the calculation/design procedure
to a variety of factors - local topographic/ commence at the catchment stormwater di s-
environmental conditions, custom, availabil- posal point and progress up the network,
ity, etc. Data are presented in this chapter or should it proceed in the opposite
on a selection from these ' combinations, used di recti on?
widely in South Australia. A 'favoured gutter
/inlet' is the particular gutter/pavement and b) should 'Minimum Grade' or 'Hydraulic Grade
inlet combination(s) preferred by the design- Line' analysis be used? Minimum Grade de-
er and for which at least adequate perfonn- sign considers pipes to be 'flowing full
ance data are available. but not under pressure' and ignores energy
losses at junction pits. Hydraulic Grade
Application of the Guidelines set out in Li ne des i gn cons i ders stormwater fl ow in
Table 6.3 is illustrated in Chapters 10 and underground pipes as conduit pressure flow
11 of the Handbook using infonnation on the and takes account of junct i on pit energy
gutter/pavement profiles and gutter inlets losses.
referred to in Figs 6.2 - 6.5 inclusive.
These issued have been considered and the
It is possible and useful to collate the following practices are recommended:-
technical information pertaining to the main
criteria listed in Guidelines 1 - 3 into a Procedure direction: approximate network
single graph of total flow, Qt, versus long- deSign (Task 1, above) sho,uld be executed in
itudinal slope, So. This brings together the two stages. In the fi rst stage, junction pit
spread relationship data (spread = 2.5 m and water levels are set along all lateral pipe-
1.0 m) presented in Fig. 6.3 and the gutter lines then along main drain pipeline(s) and
inlet performance data of Fig. 6.5. 'first-round' pipe sizes nominated using a
Minimum Grade design approach. This stage of
The collation is presented in Fig. 6.7. Task 1 proceeds in a generally top-to-bottom
With a chart such as this, the designer is di rection. In the second stage, water levels
ab 1e to rapi dly select and locate gutter in successive junction pits are revised by
inlets in the drainage lines of minor stonn- Hydraulic Grade Line analysis commencing at
water drainage systems. Similar information the system outfall or catchment stormwater
on other roadside channel, gutter/pavement disposal pOint (see Chapter 7), working up-
and gutter inlet combinations drawn from stream. This computation leads, normally, to
practice across Australia is presented in changes in some previously nominated pipe
Appendix A. sizes to ensure against pit overflow in design
stonns and junction pits which are unaccept-
ably deep. The outcome of this computation is
the 'approximate network design'.
6.4 UNDERGROUND NETWORKS : AN OVERVIEW Minimum Grade and Hydraulic Grade Line
ana lyses: as i ndi cated above, both ana ly ses
The general and detailed structure of a minor are emp 1oyed - Mi ni mum Grade to fi x fi rst-
system drainage network is dentritic, i.e. round pit water levels and pipe sizes, Hyd-
tree-like. It has a main trunk or 'mainline' raulic Grade Line analysis to arrive at app-
aligned, usually, as close to the direction roximate network design pipe sizes and junc-
of the natural slope as possible, and branch tion pit water levels that are in harmony
lines and/or laterals which may be short or with adopted overflow and pipe depth con-
long dependi ng on the geometry of the catch- straints.
ment and the nature of its contributing sub-
areas. It is clear from this review that design
of an underground network for a minor storm-
Design of a drainage system which is water drai nage system requi res a data base
economical and which successfully integrates comprising the following:-

ARRB SR 34,1986 39
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 6.3
GUIDELINES FOR THE MANAGEMENT OF SURFACE-MOVING
FLOWS IN DEVELOPED CATCHMENTS (MINOR SYSTEMS)
Illustrative e xamples ' of the guidelines are presented in Fig. 6.6

Guideline 1 Flow at 'sag' or tenninal inlets and in roadside channels


near intersections where bypass will cause cro s sflow
which i s unacceptable , must be : -

o not greater than that giving a flow spread (from kerb-


line) of 2 .50 m*, and,

o not greater than the 95 per cent capture approach flow


of the favoured gutter/i nlet.

Guideline 2 Flow in roadside channels at pedestrian crossings must


be not greater than that giving a flow spread, from
kerb-line, of 1.0m.

Guideline 3 Roadside channel flow along surface drainage lines


generally and at non-tenninal inlets must be:-

o not greater than that giving a flow spread (from kerb-


1i ne) of 2.50 m, and,

o not greater than the 80 per cent capture approach flow


of the favoured gutter/inlet.

Guideline 4 A cOncentrated flow may be accepted into the roadside


surface drainage line provided that : -

o it is not greater than 20 lis and,

o the accumulated channel flow at the concentrated flow


outlet meets Guideline 3 above.

Guideline 5 Where a concentrated flow does not meet Guideline 4


above, it must be passed to a junction pit.

* see Secti on 2.6 where the relationship between flow spread and design
AKI 1S discussed.

Guideline 3,case where flow governs :


Q:I> 80% capture approach flow of
"favoured inlet,"
bypass 20%

Guideline 3,case where


spread governs: CROSSFlOW
Dual channel --t---l+..J W:I> 2·5m. - Crossflow permitted at
carr iageway intersections A and C.
(major road) Guideline 4, case where - Cross flow unacceptable
concentrated flow entry at intesection B.
channel
would cause spread> 2·5m.
carriageway
Insert junction pit (G ' line 5)
(minor road)
with gutter inlet loptional ).
Guideline 3, case where
flow governs : Q:> 80%
capture approach flow
of "favoured inlet :'
Bypass 20% Guideline 3, case where
spread governs : W » 2·5m .
Guideline 1, "sag "
provisions ,case where
Guideline 1, two cases where flow
spread governs :
W)2 ·5m governs : Q » 95% capture approach
flow of "favoured inlet:'

Case where flow Guideline 1, case


governs :(~.QR):> where spread
capture of sag governs: W l> 2·5m
inlet.

Fig. 6.6 - Flow management in surface channels: Guidelines 1-5 (Table 6.3) illustrated

40 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

1. set of design guidelines covering items Information and data relating to these
such as pipe locations relative to car- items are presented in the following sections.
riageways, junction pit water levels rel-
ative to gutter levels, inspection pit
minimum spacing, minimum permissible pipe
size, anti-sedimentation provisions, cover 6.5 GUIDELINES FOR THE MANAGEMENT OF
requirements, etc. UNDERGROUND -MOVIr«i FLOWS
2. Minimum Grade analysis pipe flow charts
for vari ous types of pi pes normally em- The task of managing underground-moving flows
ployed in underground networks. within an urban minor stormwater drainage
system involves design of a network whose pipe
3. hydraulic data on pipe friction and junc- sizes and locations are governed by various
tion pit headlosses required for refin- practical and geometrical constraints and
ement of the pipe diameter selection pro- whose junction pit water levels are fixed by
cess and for computation of junction pit associ ated gutter and roadway fi ni shed 1ev-
water levels (Hydraulic Grade Line analy- els. The designer must formulate or be pro -
sis) • vided with a set of guidelines similar to
4. test algorithm for pit overflow. those listed in Table 6.4. These guidelines
shoul d not be regarded as mandatory for use
5. test algorithm for depth of pipe obvert. throughout Australian practice.

110 -
_\11 I Gutter Inlet Hydraulic Data
t- - - + - Capture performance of 1·0m and 2'Om side-entry
inlets with and without deflectors (see figure 6·5)

~ \vii "••-t'~"'«"""'""«""«" "" "


~ "j,7~, . . z~; " 1 ,::;':f.:::i::::;:""'~
". r - :

90 T",

'1 I" ". ~oo % i cap.tiure a~ "sa~" In~


LIS}
1 1/ \ l'...

-Ri ,,
80. 1-'- 1'.0 m Inlets 59 spread
[I [ "" I 2 0 m Inlets 118 LIs w= 2·5m

~ 70 t - .; ::i ~ I I !
I -
u.J
<;: N~
:.
"'" 95% Capture

: 60 r- I-
1\
---+--+--"<-+---1--+--' "~ 0% Capture

; \1\ ' , i'V


~ ~ "r, ! I~~~gure 6.5 - t --. f - -

~ 50 '" -- '-~w
~'\:I:>~
3 \ '" I "" ~'~I:>~~--+--r--t
...
~ 9B
0
...J

a:
u.J
l-
40 .\
I-++--+-'<-\ ~D~
N---- / /x:~~--~~
I-
::>
I!)

1\ ~Li Y~r-~~
30
1\ /[:xV
_---.;If---+_-+-_+-_+---+__ .:= BO% Capture

95 % Capture

20 1l+++~21A:-bL:-+-----+~
------h;:-+--t-- 1----+-----+--+--1
V~ "r--- "'" i'--. I ~
II
/ / 1I\ \ I~......... ~
~ -- mr-. '--
1'-'--' I --, ~ ~5% Capture

10 " !'-hl I~ --t--t----r-_t--I-_-1BO % Capture

~ I 1 --1 ~5 % capture

o 0·02 0·04 0·06 O'OB 0·10 0·12

GUTTER LONGITUDINAL SLOPE So (m/m)

Fig. 6.7 - Collation of spread and gutter inlet hydraulic data

ARRB SR 34,1986 41
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 6.4
GUIDELINES FOR MANAGEMENT OF UNDERGROUND-HOVING FLOWS IN DEVELOPED CATCHMENTS

DEFINITION OF TERMS (see Fig. 6.8)


Main drain pipeline (or '..ainline') conveys flow between sub-a re a nod e pits of
network
lateral pipeline conveys flow co ll ected from, normally. more than one inlet. to
junction pit located on main drain pipeline
Cross-connection pipe co nveys flow from, normally, a singl e inlet to junction
pit located on main drain or latera l pipeline. Cross -connectio n pipes are
usually sho rter t han 10 m.
PART 1

Guideline Main drain o r lateral pipelines should be aligned as follows :


minor roads (carriageways l ess than 10 m): they should connec t
succeeding gutter inlet pits (both side-e ntry and grated in-
let types) located along the drainage path. The alignment
should favour the ca rri ageway 'high side ' in dual-channel
road s and st reets. 'Low side ' inlet s on dual-channel minor
road s shou ld be connected to the pipeline by either inter-
inlet cross-connections or by de viating the alignment if
necessa ry. The alignment should be just within the carriageway
wh er e inlet s are grated and jus t ou tsi de where side-entry
in let s are used.

The al i gnment i n single-channel minor roads shou l d be on the


'lo w side' of the street .
ma j or roads (carriage ways 10 m or gr eate r) : main drai n or
late r al pipelines should be located within carriageways be-
tween 1.5 m and 2 .5 m from the 'high side ' kerb. Gutter inlet
pits should be cr oss -connected t o on-l ine junctions.
The alignment i n si ngl e-chann el maj or r oads shoul d be on the
'l ow side' of the street.
Gu i de lin e 2 Eve ry effo rt shoul d be mad e , including the use of angled
cros s -con nections where other wise unavoidable. to space
on-lin e junction pits as far apart as possibl e.
Gu i de lin e 3 Inspection pits spaceG at intervals of not more than 120 m
shOuld be included in all long. uninterrupted pipelines o r
diarrete r 1050 mm and sma ll er.
Gu i deli ne 4 In all gutter and 'sag' inl et pits and j un ctlo n pit s, design
water l evels assigned to pits should be not hi ghe r than :
(gutter invert level - 0.15 m)
where 'gutter invert le ve l' means the undepre ssed gutter in-
vert l eve l at the roadway section containing the pit. or where
inve r t levels differ, the lower of the t wo .
Guideline 5 Regardle ss of the provi s ions of Guideline 4, design wat er
levels assigned to co~secut iv e pairs of pits on main drain or
lateral pipeli nes shou l d differ by not l ess tha n 0.10 m in
the direction of flow.
Gui de line 6 A 3-poi nt pr iority sequen ce shou ld be followed in assigning
pit design wa ter l evels in accordance wi th Guidelines 4 and 5:
priority 1 : junction pits along lat eral pipelines including
the pits wh ere t hese pipelines join with main
drain pipelines
priority 2: junction pits al ong main pipeline branches. where
the se are present
pr io ri ty 3: junction pit s along the main pipeline trun k
In each priority, ass ignment of pit design water levels
sho uld commence at the upstream extremity in priorities 1 and
2 and at the downstream extremity in priority 3 .
Guideline A minimum pipe size of lJ ; 300 mm should be used in th e de si gn 0/
Guideline 8 As a practical design rule, pipe sizes (diameters) should not
decrease in the direction of flow. v'

42 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

IGUide 1i ne 9 I In order to redu ce the likel i hood of blockage as a result of


sedi mentat io n , flow velocities in pi pes operating under design
conditions should be not less than 0 .5 m/s . Flows which lead
to violations of thi s limit shoul d normally be excluded from
the unde rgr ound network.
Gui de lin e 10 Th e diameter of a cross-connection may be selected from either
th e table below or may be set equal to the diameter of the
pipe con veyi ng flow from the connected mainline or lateral
pipelin e junction pit, 0 , whichever is smaller. In cases
where the tabulated diamgter, 0t' exceed s 0 b'y more than one
increme nt , diameter 00 may be uSed in the c?oss-connection
prov ided pit headloss and water level co nditions at e ither end
are investigated for satisfactory performance.

Flow in nomi na 1 pi pe Flow in nom i nal pipe


cross- diameter, Dt cross - diameter, Dt
connection om connection mm
LIs L/s

< 55 300 180 - 220 675


55 - 80 375 220 - 270 750
80 - 110 450 270 - 320 825
110 - 140 525 320 - 370 900
140 - 180 600 370 - 500 1050

TABLE 6.4 - PART 2

Guidel ine 11 Except for cases where Dt exceeds 0 by more than one pipe
increment (Guideline 10), pit f lo orolevels i n cross-connected
inlet/junction pits should be set at or below -
(gutter invert level - 0.45 m - D ).
Pit floor level should coincide with thg invert.
Guideline 12 Pit floor levels in mainline or lateral pipeline junction pits
receiving flow from cross-connected inlets must allow for
slope of not less than 0.01 m/m in cross-connection pipes.
Pit floor level should coincide with invert of the pipe carry-
ing discharge from a junction.
Guideline 13 Und er ground stormwater network components should be specified
by class in accordance with the techni cal information avail-
able from manufacturers and the provisions of Australian
Standard CA33-1962 'Concrete Pipe Laying Design'.

3m. minimum clearance 1.5 - 2.5 m. from kerbline

LEGENO
Pipes 600mm~ and under
may be placed in footpa Junction pi t IJ .P. I shown , - 0 -
provided that clear space
of 3m . is maintained from
pr operty boundary and
footpath is not requ ired
for elect ri city suppl y
II
'"
Gutter inlets ,-
side entry inlet/J.P ~
grated inlet I J.P.

~I
poles .

cr oss co nnection pIpe


main drain pipeline or -mainline'

'sag' point
pipe lirie

/,
Y./ / --M I~ ROA-O--
/,, ;Z.drainage reserve
/ "
'/ N 5 W Housing Commission 'Road Manual' drawing 9.1 {19761

Fig . 6.8 - Alignment on mderground pipelines - Guideline 1 (Table 6.4) illustrated

ARRB SR 34,1986 43
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Part 1 of Table 6.4 lists guidelines f Darcy-Weisba ch fri ction fact or


which need to be applied to develop an appro x- k pipe boundary roughnes s (m)
imate network desig n. Where a cost/frequency Do pipe diameter (m )
analysis of a proposed scheme is required, a
set of approximate minor system designs which Reynolds Number =
incorporate such network desi gns shoul d be v
prepared and costed for a range of design pipe average velocity (m/s)
average recurrence intervals (see Section kinematic viscosity (water)
2.6). 1.14 x 10~ m2 /s @ 15°C.
Part 2 of Table 6.4 lists gui deline s and Fi gs 6.9(a) and 6.9(b) employ, re s pect-
information which are only applied at the i vely, boundary roughness values -
final network design stage.
k 0.3 mm (concrete pipe - normal condition)
The guidelines have been prepared foll- k 0.6 mm (concrete pipe - poor condition)
owing discussion with a wide range of pract-
itioners and study of the hydraulics of under- Figs 6.10(a) and 6.10(b) boundary rough-
ground systems. They are not all applicable ness values are, respectively, -
to all situations, nor are they 'ironclad'.
The minimum pipe size specified in Guideline k 0.06 mm (FRC pipe - normal condition)
7, for example, is likely to be changed in k 0.15 mm (FRC pipe - poor condition)
Northern Austral i a to 375 mm or 450 mm and
Guideline 8 may be disregarded altogether in These val ues of boundary roughness are
areas where network blockage is rare. offered in preference to 'new pipe' values on
the ground that deteri orati on of pipel i nes
Anti-sedimentation provisions are add- during service life, which may be 30 - 50
ressed in two guidelines, 9 and 12. The years, should be anticipated in network de-
former appl ies a minimum velocity constraint sign.
to the design of the main components of
'approximate' networks. Guideline 12 is em-
ployed at final design stage and applies a
minimum slope constraint to cross-connection 6.7 HYDRAULIC GRADE LINE ANALYSIS HYDRAULIC
pipes only . A more appropriate, though more DATA
comple x guideline on anti-sedimentation re-
quirements for underground storm-water pipe- Application of Hydraulic Grade Line analysis
lines, could be devised using incipient mot-
ion sediment transport theory (Novak anrl in the design procedure of Chapters 10 and 11
Na II uri 1984). (m i nor dr'dindye sysLellls) , ,'e4uin!s d ~iL-Lu ­
pit headloss formulation which is simple and
The pipe class and/or cover which needs yet of sufficient accuracy to enable satis-
to be specified for each component of an factory approximate network designs to be
underground network, as part of the f i nal produced. Total pit-to-pit headloss has two
components:-
design process, is the subject of Guideline
13. In addition to the requi rements of thi s
guideline, designers are advised to also con- a) pipe friction headloss, hf
sult manufacturers' handbooks, in parti cuI ar
'Concrete Pipe Guide' published by the Con- b) junction pit headloss (water level),
crete Pipe Association of Australia (1985), 2
and 'Textbook of Pi pe line Des i gn ' (James Har- Vo
die Pty. Ltd. 1985). Kw( -) (6.15)
2g

where Kw = headloss coefficient which gives


6.6 MINIMUM GRADE ANALYSIS HYDRAULIC DATA pit water level.
Minimum Grade analysis is employed in the The two headloss components are indicat-
minor drainage system design procedure to fix ed in Fig. 6.11.
'first-round' pipe sizes for all mainline and
lateral pipeline components of the under- Approximate friction headloss between
ground network. Two pai rs of charts (after pits may be computed using fixed values for
I.E. Au st. 1977), Fi g. 6.9 (a and b) and Fi g.
6.10 (a and b) for concrete and fi bre-rein- friction factor, f , in the Darcy-Weisbach
formula:
forced cement (FRC) pipes, respectively, are
supplied to enable diameter selections to be l
rapidly made. The charts provide information (_0)
hf = fL
- (6.16)
on 'normal' pipes and pipes in poor condition. Do 2g
The pipe selection charts are based on Values of 'f' corresponding to the values
the Colebrook-White formula which covers cases of 'k ' listed above are : -
in the transition zone between smooth turbu-
lent flow and rough turbulent flow:- f 0.019 (concrete pipe -normal condition)
1
f 0.022 (concrete pipe - poor condition)
- 2 log10 (6.14) f 0.015 (FRC pipe normal condition)
IT f 0.017 (FRC pipe poor cond it ion)

44 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

pipe diameter (mm) pipe diameter (mm) :5


o·100 n-r"r'rTT1r----r-rll"""T-nTrrT-"":;;'-r-r.;:""",.;:.r..;... 0·100 ".,

0·050 0·050

~

o
VI 0

UJ
- VI

Q. W
Q.
o 0
-' -'
VI
VI
-' -'
«
z «
z
Cl O' 010 1----t-+-+--+--+-+-I'f-f+l'-J4-+-f-l Cl 0·010
::> ::>
to- to-
I.:) I.:)
Z Z
o 0
-' -'
0·005 0005

50 50
(Lis) PIPE

(a) roughness k = 0·3 mm.- normal condition pipe (b) roughness k = 0'6mm -poor condition pipe

Fig. 6.9 - Concrete pipes: chart for 'first round ' pipe selection

pipe diameter(mm) c::::


~ ~:5::::~ pipe diameter (mm) :::: ~ ~ :5::::~
0·100 """-"'-'-rT"'---r-r-rir-nfT)ri-rr-r~~"'T"T'O"'OnT"Tl'nrTT1
;:;;: ,.." -..::I- U'"') \0 'Or--...
0·100 r-r-rrrn-rr----.--oorr-r<rnrr-rr-rT7T...,-"rm

0·050 0050
E
E "-
E
"-
.§ '"
.'2-
Cl.fl) 0
'"
.'2-
Cl.fl)
0 VI
VI v:'::: v:':::
Q:fl)
W ..... .::: UJ-
.........
Q:[!!
Q.
0
.... '"
",:::J
Q.
0
-'
.... V)
",:::J
",,,( "'''(
-' VI
0>
VI E:!'c:
..!P '- :o . ~
-'
-' "t> « ;::-"t>
«
z ....
~3
'" z
(3
.f:~
Cl 0·010 ::> 0010
::> t-
t-
I.:)
I.:)
Z z:
0 0
-' -'
0005 0·005

50 10 2
50 10 2 500 10 3 5000 10 4
PIPE PIPE DISCHARGE (L i s)

(a) roughness k =0 ' 06mm -normal condition pipe (b) roughness k =0·15mm- poor condition pipe

Fig. 6.10 - Fibre-reinforced cement pipes: chart for 'first round ' pipe selection

Junction pit head10ss (water level) is


estimated using values for the coefficient Kw
taken from Tables 6.5 and 6.6. Values listed pi -~t-'rr
: ----_._---- v'
~ .
Gutter
in Table 6.5 are based on the research of water leVeT ' I hw=K w(1g) inVert
-
Sangster et a1 (1958), known widely as the
'Missouri Charts', and of de Groot and Boyd IiGT - fh f- _
(1983), Black and Piggott (1983) : this table
covers cases in which pipes connected to
junction pits are either concurrent or they
intersect at right angles. Table 6.6 lists
values of Kw obtained, primarily, from the
research of Hare (1983) who investigated head-
loss at junction pits in which the alignment
of pipes was other than concurrent or at right
angles. Fig . 6.11 - Friction and pit head losses - definitive sketch

ARRB SR 34,1986 45
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 6.5

APPROXIMATE VALUES FOR COEFFICIENT K


PIPES CONCURRENT OR AT RIGHT ANGLES w

1. INTRODUCTION 2. JUNCTION PITS WITHOUT GUTTER FLOW

Figure (a) represents a general, Simple


junction pit layout with upstream, lateral and CODE OESCR IPTION Qu "" Ql "" Qg Kw=
grating inflows, Qu' Q and Qg respecti vely.
l
By assigning val ues to these parameters all J-1 Ju nction pit on through Qo - - 0.2
possible simple junction pit configurations pipeline, i.e. Qu = Qo
can be described. Figure (b) is an elevation
sect i on through the pit taken along the Junction pit on through
alignment of its discharge pipe, diameter [) • pipe with lateral(s)
The K values listed are based on the findin~s
of SaWngster et al (1958 ) known as 'Mi ssouri J-2A • Qu » Ql Qo some - 0.5
Cha rt s " de Groot and Boyd (1983), Bl ack and J- 2B Qu 1.0
Pi ggott (1 YH3) • "" Ql Qo /2 Qo/2 -
J-2C • Qu « Ql some Qo - 2.0

J-3 Junct i on pi t on 'L' pipe - Qo - 2.0


H--"T'~--t!:1 2 ju nct ion, i .e. Qu = 0
' (~ )
• 2g
Junction pit on 'T' pipe
•fiG1~ j unction, i. e . Qu = 0

;: o.a~ J-3A • opposed l ate ral s - Qo - 2.5


Figure (a) "--"---lh::E~f=.tr.: Va J-3B • offset laterals - Qo - 2.0
Figure (b)

4. PART-FULL OUTFLOW FROM JUNCTION PITS

3. INLET/JUNCTION PITS WITH GUTTER FLOW

CODE DESCRIPTION Qu"" Ql "" Qg "" "w=


1-1 Inlet pit with single - - Qo 4.0
pipe outflow
Part-full outflow from a junction pit.
Inlet on through pipeline
- Situations frequently arise, particularly in
I-2A · Qu Q Qo /2 Qo / 2 2.0
"" 9 upper-basin catchments of moderate/steep
I~2B Qo Qo - some 0 .5 grade, where pi pes operate part-full. Water
• Qu "" level bui ld-up in pits supplying these pipes,
is, typically above obvert level (see sketch).
Inlet on through pipe Bannigan and r-tlrgan (1981) have suggested for
with lateral (s)
such situations that the hydraulic grade line
I-3A • Qu » Ql Qo some some 0 .5 be set at (discharge) pipe obvert level and
the hei ght, h , fi xed in the same manner as
I-3B • Qu > Ql Q/2 some Qo/2 1.5 other cases co~sidered in Tables 6.5 and 6.6.
The value of V required in the calculation of
I-3C • Qu Ql Qo/2 Qo / 2 some 1.5
= Q /A where A is
"" h is given °by V
dfscharge pipe full ~rea. 0 0 0
I-3D • Qu « Ql some Qo some 2.0
I-3E • Qu < Ql some Qo/2 Qo/2 2.5 No experimental or field validation of
this has to date been presented. Results of a
pilot study carried out at S.A. Institute of
Technology show water level build-up can be
1-4 Inlet on 'L' pipe junction significantly greater than K (V 2/2g). It is
i.e. Qu = 0 I - Qo some 2.5 0
therefore recommended that 'he Bann i gan and
. . . I Morgan approach be ad opted wi th h fi xed by:

1.5K [V~]
Inlet on 'T ' p' pe J unc t , on -
i.e. Qu = 0
w
I-SA • opposed laterals - Qo some 3.0 w 29
I-5B • offset laterals - Qo some 2.5 The results of current research will in
time yield a more accurate relationship.

46 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 6.6

APPROXIMATE VALUES FOR COEFFICIENT 'w:


PIPES
NEITHER CONCURRENT NOR MEETING AT RIGHT ANGLES

1. JUNCTION PIT WITH SINGLE ENTRY/EXIT PIPES situation which would otherwise, i.e. using
rectangular pits, fall into the cases
Hare's (1983) research on the hydraulics of considered above.
single entry/exit pits with pipes neither
concurrent nor meeti ng at 90 degrees, shows Internal shaping 'Benching' of pits to
that the pit water level headloss coefficient, provide a curved channel D /2 deep between
. K , which should be applied to the hydraulic ent ry and exit pi pes (see slPetch) can reduce
g~ade line at these structures is dependent on Kw· values obtained in ~ > 45° situations from
two main factors: 2.5 to about 1.5 (Archer et al 1978). It
appears to make no significant improvement in
(i) the location of the entry pipe centreline ~ < 45° situations. Similar findings are
(produced) intersection with pit walls; reported in Dick and Marsalek (1985).
and

(ii) the magnitude of gutter flow, Qg.

For deviation angle, ~ < 45°:

Examples:

exit face

.~OfPit~
Q .
. :::--0"': Benching in a Benching in a
. . e<45· rectangular ci rcul ar
intersection junction pit junction pit
point. Plan View.

2. DROP JUNCTION PITS


For deviation angle, ~ > 45°: It is often necessary in steep terrain or when
an existing service (water main. electricity
Exaqlles: cable, etc.) must be avoided to construct
.i unct i on pit ent ry and exit pi pes at s i gni-
ficantly different levels. Unpublished
research by Black and Piggot (QIl) and Logan
City Council (1983) suggests the following
values for the pit water level headloss
coeffici ent Kw:

intersection ~ < 45° situations:


point. Plan View. rectangular pits, Kw 2.0;
circular pits, Kw 1.5
Kw values recommended are : ~ > 45° situations:
rectangular pits, K 2.5;
~ < 45° : KW = 0.5 for Q = 0 or small W
quantity; g circular pits, K 2.0
w
Use of these values of K is restricted to
installations in which b~h pipe obverts
(ent ry and exit) are submerged under des i gn
2.5 (with or without gutter flow conditions At{) there is no gutter flow.
flow) It is considered unlikely that gutter flow, if
present, will affect the listed values of K ,
Research suggests that hydraulic shaping but this is presently unresearched. w
of pits to assi st the passage of fl ow from
entry to exit can be effective. Some designers prefer to break vertical
alignment and introduce a short length of
Pit diEnsions Small pits, generally. result steeply sloping pipe (slope, say, 1 vertical
in smaller headlosses than large pits. to 4 horizontal). if necessary, in preference
to using a drop pit. They argue that the
Circular pits Results of unpublished research headl os s thus introduced, although un known.
by R.G. Black and T.L. Piggot of Queensland must be less than that occurring at a drop
Institute of Technology. when compared with pi t. Des i gners fo 11 owi ng thi s practice are
the results of Hare (1983), show marginally entitled to use slightly reduced values for
improved performance for circular pits in Kw·

ARRB SR 34, 1986 47


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

3. MULTI-PIPE JUNCTION PITS installations tested und e r design


conditions (see Bates et al 1984), and,
The bulk of practical situations for which pit
headloss values are required can be found from (ii) ina 11 other situations use Kw = 3.0,
Tabl e 6.5 and the above. Cases not covered with or without gutter flow.
are those where flows enter pits from two or
more pipes which are not concurrent with
and/or not at 90 degrees to thei r respecti ve 4. NICHOLS-WATTS FORMULAE
discharge pipes. The multitude of pipe/pit
geometri es met in practi ce and the range of An unpublished report by Nichols, Watts and
flows which would need to be tested to produce Associates, Consulting Engineers of Liverpool
generalised design tables make the full N.S.W., proposes a set of formulae which
research of this topic a mammoth if not enable headlosses to be determined for many
impossible task. arrangements of pipes and full-barrel flows
included in Tables 6.5 and 6.6. Values
The following suggestions are offered to determined by the fonnulae show close agree-
designers who face th i s problem : ment with results obtained by Hare (1983) but
are less satisfactory in their reproduction of
(i) ins ituat ions where the ri s k of property headlosses for the cases investigated by
inundation is highly sensitive to Sangster et al (1958). It is considered that
uncertainty in pit headloss estimates, the Nichols-Watts formulae underestimate
values for K should be obtained from significantly headloss in the more complex
hydraulic wmodels of pipe/pit pipe/pit and multi-pipe geometry cases.

Watts (1983) has establ i shed a set of b) The pipe obvert depth test involves com-
formulae which approximate the results of parison of the quantity (hf + 1.5 Do)
Sangster et al and of Hare. against allowable head difference and is
illustrated in Fig. 6.12(b). This test
By the time Tables 6.5 and 6.6 are used incorporates an arbitrary invert depth
in the des i gn of a typi ca 1 mi nor storlTlHa ter limit of 2.5 Do below AWL. (The 2.5 Do
drainage system, considerabl"e information has value derives from the test conditions
been compiled by the designer concerning flows under which much of the information con-
in all component pipes of the underground tained in Tables 6.5 and 6.6 has been
network as well as gutter capture flows diver- obtained, i.e. pit water level 2.5 Do
ted to the underground system at inlets. The above invert.)
quantities Ou, 01, Og and 00 defined in Table
6.5 are therefore known and its inequalities _-y-_ _ _ Te st fo r ove r flow of upstre am pit - TES T 1
readily assessable.
AWL. ~~~
1
V
Values of Kw selected from Tables 6.5 Ass iqned ~ ~Kwh~ )
and 6.6 and applied in the Hydraul ic Grade water ----'---
Line method, give satisfactory underground le vel ----- ~1-:=::::--_I__"'B.!.!W-L"-
pipe sizes and water levels in mainline and
- Bottom
lateral pipeline junction pits. The resul-
water
ting network designs are acceptably close to leve l
those gi ven by more t i me-consumi ng methods
whi ch use preci se values extracted from the
'Missouri Charts' and Moody (pipe friction)
Chart. This point is revisited in Chapter 12
v1
- Concluding Discussion. (a) U/s pi t overfl ow t est : hf +Kw(2~ )~ (AW L -BWl) Eq.6·17

Te st f or depth of ups t r eam obvert - TE ST 2


6.8 TESTS FOR PIT OVERFLOW AND PIT OBVERT
DEPTH

Two tests need to be executed in the process


of applying Hydraulic Grade Line analysis to
the 'first round' network referred to in 2·500
Section 6.4.

a) The first involves the comparison of cal-


culated total headloss [hf + Kw(V 0 2/2g)]
in each component in turn against the head
difference allowable between pits. This
comparison leads to a test for pit over- (b) U/s obv er t dep t h te st : hf + l5 Do? (AWL - BWl) Eq.6·18
flow, illustrated in Fig. 6.12 (a). 'Al-
lowable' head difference is based on the
recommendations contained in Guidelines 4 Fig . 6.12 - Definition of terms - pit overflow and obvert
and 5 of Table 6.4. depth tests

48 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

The computations for both tests commence pos s ible if it s upstream invert
at the network outfall - a point of fixed (de- is set lower than (AWL - 2.5 Do),
sign) water level - and should be carried out a conditi on which is undesirable.
simultaneously moving from pit-to-pit in an The alternative is to design for
upstream direction. Only pits along the main part-full outflow from the up-
drain pipeline{s) and lateral pipelines are stream pit (s ee Ta ble 6.5). This
considered. Water levels assigned in fixing option leads to pipe invert set
the 'first-round' network (i.e. AWL's) are by eqn (6.21):-
progressively revised to become BWL's (bottom
2
water levels) in the process: the upstream- Vo
moving calculation sequence permits this. pipe invert level ~ AWL - 1.5 Kw(-) - Do
(upstream) (upstream) 2g
Ei ther or both tests can be violated in ( 6.21)
a given situation without an unmanageable
design necessarily resulting. It will be and upstream pit water level
found that the requi rements of the overfl ow (BWL) is the same as that assign-
test [eqn {6.17)J can, generally, be met by ed (AWL) during the 'first-round'
appropriate choice of pipe diameter, Do, and design stage, i.e. BWL (upstream)
this should be the first action of the de- = AWL.
signer.
Outcome l/Outcome 2 situations : normal-
Sat i sfaction of eqn (6.17), i.e. TEST 1 ly, the upstream pipe invert level gi ven by
i n a particular case implies that full-barrel eqn (6.21) is above that given by eqn (6.19).
flow in the discharge pipe, diameter Do, can However, the inter-relationship between these
be achieved without overflow occurring at the levels can sometimes . be reversed. The situa-
upstream pit. It does not disclose, however, t ions wh i ch 1ead to such reversa 1 are those
the depth at which the pipe must be set to where large flows must be passed through
achieve thi s behaviour, and whether the re- mUlti-pipe junction pits or where large flows
quired depth is acceptable : this is the role are subject to severe di rect i on changes at
of eqn (6.1 8), i.e. TEST 2. pits. In cases where upstream i nvert level
given by eqn (6.19) is higher than that given
Two main outcomes of TEST 2 are possible: byeqn (6.21), the former level should be
adopted and BWL (upstream) cOfT1luted by eqn
Outcome 1 : If the eqn (6.18) inequality is (6.20), i.e. treat as Outcome 1 design situa-
satisfied, it follows that the t ion.
invert of the upstream end of the
discharge pipe, diameter Do, may The consequence of this procedure is a
be set above (AWL-2.5 Do) without mainline/lateral pipeline network in which
losing the full-barrel condition. pit water levels have been set by Hydraulic
This elevation is limited by eqn Grade Line analysis taking account of both
(6.19):- full-pipe and part-full operation. Pipe in-
vert and hence junction pit floor levels are,
pipe invert level ~ BWL + hf - Do (6.19) generally, above (AWL - 2.5 Do). The re-
(upstream) (downstream) sulting main network is satisfactory for
'approximate' design purposes and may be ex-
In this case water level in the tended to include the sizes of cross-connec-
upstream pit is given by eqn ted pipes by applying Guideline 10 (Table
(6.20) :- 6.4). This guideline recognises the small
2
minority of cases in which cross-connections
V carry high flows requiring special design
BWL BWL + hf + Kw{~) (6.20) attention.
(upstream) (downstream) 2g
Final design detailing involves applica-
Outcome 2 : If eqn (6.18) fails, it follows tion of Guidelines 11 - 13 together with site
that full-barrel flow in the dis- constraints, underground service avoidance,
charge pipe, diameter Do, is only etc.

ARRB SR 34, 1986 49


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

50 ARRB SR 34. 1986


7
Urban drainage systems:
structure

7.1 INTRODUCTION Imagine the entire landscape upstream of


an identified runoff disposal point, X, having
When urban development ta kes place ina its vegetation cleared and its surface coated
natural basin, the ordered system of drainage with impervious material i.e. 'plastic-
lines present in the landscape uplands - its coated'. A unique boundary called the
runnels, incised channels and minor creeks - watershed can be identified, enclosing all
is replaced by a system of allotment drains, surfaces yielding runoff to X. The path t aken
roadside channels, inlets ' and underground by each runoff element travelling from its
pi pes. Though outwardly different from the poi nt of origin in the catchment to X is along
natural catchment drainage network, the formal the point-to-point locus of steepest topo-
paths of the developed 1andscape displ ay a graphic grade. These items are illustrated
structure which is similar to that of the for a typical rural basin in Fig. 7.1.
drainage system they have replaced.

This observed similarity is exploited here


to introduce and describe the structure of
both simple and complex urban stormwater
drainage systems.

Detai led planning and design of a scheme


to control and/or mitigate the effects of
flooding in a rural catchment can only proceed
from a data base which includes information of
the following:

a) catchment natural drainage direction;

b) runoff disposal point - the channel flow


section through which all runoff origin-
ating in a catchment passes immediately
prior to disposal to a receiving domain
such as a river, stream, temporary
storage pond, estuary etc.;

c) catchment boundary or 'watershed';

d) in terna 1 node poi nts 1ocat i on s of


interest where flood magnitude may be
assessed and interpreted as flood level
or stage height;
Fig . 7.1 - Run off element travel path and watershed of a rural
e) drainage network - the network of surface catchment
channel s which collects and conveys to
disposal all runoff originating in a In rural catchments, node points [item
catchment; (d)] are located, typically, at points on the
basin drai nage network [item (e)J where main
f) catchment sub-areas - internal drainage channels are joined by tributaries. They form
areas from which runoff passes to each a succession of points along the main drainage
node point. lines. The sum of the sub-areas [item (f)J
draining to a particular node point represents
The natural drainage direction [item (a)J the total catchment contributing runoff to
and run 0 ff ' dis po sal poi n t [ item (b) J 0 f a that point. The lowest node point coincides
catchment are determined by inspection and with the identified runoff disposal point, X.
interpretation of the contour plan containing
the catchment. Identi fication of these items An example of a rural catchment drainage
must precede the fixing of the catchment structure which illustrates items (a) to (f)
boundary [item (c)]. is shown in Fig. 7.2.

ARRB SR 34, 1986 51


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

~) ~p)/ "b-"" boO',,,i,,


( \ /~'a j~
\ / / /\ // ')
350 ) I . l { /
( I f\(/ ./'
,,-__1/ t~~7/
{ \ ., \,' internal node poi nt s
"- \ \ , shown : - - _
Cat chment drainage ne~ork ~
show n :
.-/'----r- "
------ -~
X
r-

Catchment main dra in age


Catchment flood network shown : er-----______ -~
disposal poi nt
Fig. 7.2 - Components of a rural catchment drainage stru ct ure

7.2 GENERAL PROPERTIES OF SMALL URBAN points using, primarily, the roadway reserves
CATCtMENTS of its pri nci pa 1 down-s lope st reets • As in
rural catchments, individual drainage areas
A structure similar to that de scribe d above contributi ng runoff to identi fied node points
for rural catchments can also be observed in are termed 'sub-areas'.
urban catchments of any si ze. Di fferences
arise primarily where man-made components of Small urban catchments may be divided into
the built environment interrupt the movement two broad classes sim~e and complex.
of runoff over the natural terrai n forci ng Simple urban catchments are, typically, less
runoff elements to follow point-to-point loci than 20 ha in area and may be analysed as
other than those of steepest topographic single arainagc units. Complex urban
grade. This occurs, typically, where roadways catchments represent collections of drainage
and roadside channel s intersect overland units or sub-catchments each of area less than
drainage paths and where storm drainage is 20 ha: a complex urban catchment may, thus,
carried in underground pipes. enclose a total area considerably greater than
20 ha.
In larqe, totally urbanised landscapes
th i s interference has vi rtua lly no effect on The two classes ur sma 11 deve loped
identified natural drainage directions and catchments are discussed sepa rate ly in the
runoff disposal points and only a marginal following sections.
effect, if any, on boundaries. The watersheds
of large urban developments may therefore be
fixed in the same manner outlined above for
rural catchments. 7.3 SIMPLE URBAN CATCHMENTS
When the detailed drainage design of a An example of a developed landscape which
segment of such a 1andscape is undertaken, presents each of the catchment items reviewed
however, the interference of man-made in Sections 7.1 and 7.2 for a sub-division
components is found to greatly affect its comprising four simple catchments is shown in
boundary and in the matter of runoff disposal, Fig. 7.3(a}. The following items may be
it is not unusual fo r surface -mavi ng and recognised in this example:
underground-moving runoff to be channelled or
piped, respectively, to significantly a) natural drainage direction
different points. Identified natural drainage
d i recti on on the ot her hand is unaltered by b) ca tchment flood and s to rmwa t er d i sposa 1
development. points, L.O, M.O, N.O and P.D

Node points in urban catchments are c) catchment boundaries


usually assigned to principal down-slope
street intersections where (down-slope) d} node poi nts
cross-flow cannot be tolerated, to 'sag'
points and to points where the main drainage e) drainage networks
path changes direction sharply. They may also
be assigned to locations where large runoff f} sub-areas
contributions join main drainage paths from
major sub-divisions or from commercial/ The descri ptors 'flood' and 'stormwater'
industria 1 estates. Drainage network main used in (b) above carry the . same meanings
paths of a catchment 1 ink the assi gned node ascribed to them in Section 2.2. The disposal

52 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

points of the two runoff components from The structure of the .ajor drainage system
IMjor/rare st 0 rills and from minor storms for the illustrated sub-division or any
normally coincide in a simple urban catchment catchment withi n it can be readi ly obtained
e.g. Catchments L, M, Nand P in Fig. 7.3, but from information contained in Fig. 7.3(a).
differ in the case of the complex urban This has been done for Catchment M and is
catchments reviewed in Section 7.4. presented in Fig. 7.3(b). In this figure:

Node points in each simpl e catchment are the disposal point M.O is where major and
coded sequentially up the drainage network rare flood flows generated in Catchment M
conmencing from its flood and stormwater enter a local stream;
disposal point. Indi vidual catchments are
identified by a letter prefix, hence, M.O, the identified node sections on the flood
M.l, M.2, etc. escape network, M.l, M.2 and M.3 etc.,

LEGEND
Catchment stormwater
disposal points shown ' @
Catchment boundaries
shown ,
Node points shown , ......
,y.,?
Drainage network
shown , '. . . •
"ftt.,? 11.
Open space floodways ·3
shown , ======::.=
Contours shown , ----- 112

Scale
100 200
metres

Figure 7.3 (a): 40 ha. sub-division - co tchments L, M, Nand P.

park - -
LEGEND
M.3
-----r'------
I Sub-area boundaries
node I
I shown :
sectn. +-= I ...
C I C
QI I QI
"C I "C Primary drainage area
·in I 00; boundaries shown : ______ _

--
QI I QI
'- I '-
I
I Node pi ts shown :
M.2
_---of M.3
node Main drainage pipeline
sectn. +'
C shown : "M.] "H.3
:I: QI
l:l "C (coincides with primary drainage
'Vi
:I: QI area or sub-area boundaries)
'-

M.1 IQ:~~::! Gu tter inlets shown : 0

M.1 M.4 (IN.P M.4


(T.N.S.) node node pit
sectn.

sub-area boundaries
shown: _ - _ - - - __
- Note: Each terminal gutter
inlet is assumed to receive,
initially. the entire runoff
from its associated primary
drainage area .

flood escape network


shown : I • I
Figure 7.3 (c) : Catchment M
, Figure 7.3 (b) : Catchment M-
structure of major system. structure of minor system

Fig. 7.3 - Stormwater drainage networks in simple urban catchments

ARRB SR 34,1986 53
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

are placed immediately downstream from Note that each sub-area represents a
the node point!. of Fig. 7.3(a). Each collection of priMary drai nage areas.
receives the entire flood flow generated
in its upstream catchment. The lowest With these structures in place in any
node section (M.1 in this case) is simple urban catchment. the analysis and
refer red to as the Ca tchment 'termi na 1 design of its major and minor drainage systeMS
node section' (T.N.S.). Its entire can proceed. Chapters 8 and 9 are devoted to
collected flow is transferred without the procedures involved in major system
addition to the catchment flood disposal planning/design; Chapters 10 and 11 are
poi nt, M. O. The termi na 1 node section concerned wi th the desi gn of mi nor systems.
and flood disposal point of a simple Catchment M of the Fig. 7.3 development is
urban catchment frequently coincide; used as a case study illustration of these
procedures.
the 'flood escape network' is identical
to the drainage network for catchment M
gi ven in Fig. 7 .3(a);

drainage sub-areas are identified.


7.4 C<»4PlEX lIlBAN lAJI)SCAPES

Developed urban landscapes are often more


The .inor drainage syst~ structure for complex than the sub-division illustrated in
Catchment M is shown in Fig. 7.3(c). It is Fi g. 7.3. They may consi st of two or more
typical in that it includes above-ground and slope-aligned catchments, each divided into
underground flow paths which act conjunctively sub-catchments whose main drainage paths are
to convey nuisance or minor stormwater flows parallel. The internal drainage structure of
through and from the catchment. Catchments a sub-catchment is identical to that of the
less complex than those illustrated in Fig. simple catchments discussed above: it has its
7.3 have no underground pipe components. own terminal node point (T.N.S. and T.N.P. are
both located here). drai nage network, node
the disposal point M.O is where minor points, etc. [see Fig. 7.4(a)].
stormwater flows generated in Catchment M
enter a local stream; In complex landscapes major and minor
system drainage is directed, frequently. to
pipeline main junction pits are located different disposal points, a consequence of
at the positions of the node points of the significantly different flow magnitudes
Fig. 7.3(a) and are referred to as node which ilre involved in each 5Y5tcm.
pit s. Each receives the entire minor
stormwater flow generated in its upstream The 1arge, free-surface fl ows which
catchment. The lowest pit (M.1 in this consti tute the bulk of the major flood
case) is referred to as the catchment discharges generated in an urban sub-catchment
'terminal node pit' (T.N.P.). Its entire cannot be eas ily di verted acros s natura 1
collected flow is transferred without drainage slopes to a central flood disposal
addition to the catchment stormwater point for each catchment. The designer must
disposal point M.O. The terminal node therefore give attention to the subsequent
pit and stormwater di sposa 1 poi nt of a down-slope movement of these sub-catchment
si mple urban catchment frequently outfl ows i rrespecti ve of catchment or
coi nci de; municipal boundaries which may lie in their
paths. Fig. 7.4(b) illustrates, schemati-
cally, how major flood runoff might be handled
drainage sub-areas are almost identical in a complex metropolitan landscape comprising
to those of the major system. Compare 'strings' of slope-aligned catchments.
Fig. 7.3(b) and 7.3(c);
In this illustration. the flood escape
The mi nor system network, a 1though based route of each upland sub-catchment is similar
on the drainage network of Fig. 7.3(a) is tot hat show n i n Fig. 7.3 ( b) down to its
more complex than it. All runoff is terminal node section (T.N.S.) only. Its
considered to move in the initial stages route through the lowest sub-catchment of each
of the network analysis/design procedure 'string', however, is identical to that of
descri bed in Chapters 10 and 11 by way of Fig. 7.3 (b) where T.N.S. and flood disposal
surface drainage paths to individual point exist as separate entities.
tenlli na 1 gutter inlets (or 'sags' where
present) located close to the node points
of Fig. 7.3(a). These terminal gutter Management of major flows from sub-
inlets are indicated, for Catchment M, in ca tchment to sub-catchment down the deve loped
Fig.7.3(c). The developed areas landscape, as illustrated in Fig. 7.4(b), may
contributing runoff to these inlets are call for temporary storage or detention basins
ca 11 ed pri .. ry draduge areas and thei r to be installed at or downstream from some
flow paths pr1_ry drainage lines in the sub-catchment termi na 1 node sections to meet
Handbook procedures. Gutter i n1 et pits the overall goals of a Master Drainage Plan.
at the ends of these drainage lines are Where the terrain slope is fairly flat and the
located on or are cross-connected to the receiving domain tidal. the use of flood pumps
pipes of the main underground network is an option which the designer may have to
(see Guideline 1, Table 6.4). explore.

54 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CATCHMENT P
sub -catchments PA & PB

CATCHMENT N
su b- catch ments
NA ,NB& NC Detention basi n
with pipe outlet

CATCHMENT S
L& M

Reserve
catchment or sub-catchment runoff disposal ~v
","- linear park floodways shown ...... =====
node points shown
points shown ..... a
• M·3
prin cipal 5treet floodways shown . ~==:.
main road flood ways shown .
dra in age network shown . •
L-2 •
l ·1 Fig 7.4!b): Integrated major system
Fig 7.4la) : Catchments, main roads & drainage paths
pri ncipal streets

Fig. 7.4 - Schematic representation of storm drainage


networks in a complex urban landscape

The drainage structures sketched in Fig.


7.4 are typical of those used in urban
deve10Plllents and, 1 ike those of the Fig. 7.3
catchments, include above-ground and under-
.ground components in their minor systems.
A1 though flow in an underground pi pe is
subject to the same gravity laws which govern
free-surface flow, the path it may take from a
gi ven poi nt is far 1ess dependent on topo-
graphical considerations than applies in the
case of open channel flow. Fig. 7.4(c)
illustrates this: minor storm runoff conveyed
to each upland sub-catchment terminal node pit
is diverted acros s the na tura 1 drai nage
direction by underground pipe to its catchment
stormwater disposal point (N.O, P.O, etc.).

A singl .e down-slope trunk main linking


these disposal points carries the bulk of the
deve 1opment mi no r sys tern load to fi na 1
di sposal. The only mi nor stormwater excluded
from thi s system is that generated in
catchments which have their own disposal
points, i.e. the lowest slope-aligned catch-
ments in each 'string'. The advantages of
this approach to managing nuisance stormwater
fl ows in the urban envi ronment are consider- node pits shown .......... .
able. Design of the resulting system is, underground network shown ---1.1--.....
-_.-

however, more complex than that of their major


system counterparts.

ARRB SR 34,1986 55
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

56 ARRB SR 34, 1986


8
The major drainage system
design procedure outline
-
8.1 I NTRODUCTIC* 1. a feasible flood escape network, and
2. a peak outflow (design extreme storm)
di scharge rate.
The general storm runoff management des i gn In real world situations, the magnitude
practice proposed in this Handbook is based of thi s di scharge rate determi nes, in each
on the major/minor drainage concept introduc- case, the design of channelling or the hyd-
ed in Section 2.3. Major drai nage systems raulic structure through which major flows
use the roadway reserve, drainage easement pass before entering a natural drainage line
and open space or 'green belt' areas of a or associated open space domain.
developed urban 1andscape to carryall major
runoff flows and a specified level of rare In non-isolated situations, the drainage
f1 oodi ng. designer may be tempted to pass floodwaters
from an upstream drainage unit directly to a
The primary aim of this Chapter is to downstream unit in cases where the computed
describe a procedure for the planning of major peak outflow discharge rate of the former is
systems for small, isolated urban catchments less than the capacity of the receiving flood
: the procedure draws on guidelines and hyd- escape channel of its downstream counterpart.
ro10gi ca1/hydrau1 ic information presented in This ignores the fact that a sub-catchment's
earlier chapters. The procedure is applied response to the stimulus of storm input is not
to a case study sub-division in Chapter 9. a peak discharge rate isolated in time, but,
rather, a complex discharge/time relationship
Isolated and Non-isolated Catchments - a hydrograph (see Fig.8.l). Where two such
hyd rographs interact, as in the case of the
The major/m inor drainage system designed for direct linking suggested above, it is almost
a specific portion of an urban landscape inevitable that the peak discharge rate for
forms part of the Master Drainage Plan for the combi ned hydrograph wi 11 exceed the i n-
the ent ire drai nage bas in withi n whi ch the di vi dua 1 peak rates of the cOl1'4>onent hyd ro-
particular urban unit is located. During graphs as illustrated in Fig. 8.1.
storm events, runoff is collected and con-
veyed along the identified drainage networks There may well be sufficient 'spare'
of each unit. Interaction between slope- capacity in the downstream flood escape path
aligned units or catchments may take place in to accommodate the peak of the combined flows,
this process. Two broad classes of catch- but this must be verified by computation.
ments are recognised:- Alternatively, it may be appropriate and con-
s i stent with other objectives of the urban
a) isolated urban catchments: developed plan, e.g. traffic planning, road hierarchy,
areas, planned or existing, which receive etc., to alter the gutter/pavement profile of
no stormwater input from upstream sources a receiving roadway reserve and, as a result,
and which discharge to open space or 'green provide greater flood escape capacity.
belt' natural drainage lines. The Fig. 7.3
sub-division is an example of this type of hydrogra ph of lower /' - '" combined hydrograph
development. drainage unit // \ in lower dra inage unit
\
b) non-isolated urban catctlnents : developed
\ hydrograph of upper
areas, planned or existing, which receive
drainage unit passing
stormwater input from upstream, slope-
\ to lower unit
aligned developed catchments or which dis-
Flow
charge drainage to downstream, slope- \
aligned developed catchments or both. The \
Fig. 7.4 urban landscape is an example of \
this type of development. \
~

The procedure described in Chapters 8 and


9 for planning major stormwater drainage sys- Time
tems is 1imited to isolated catchments and
yields for eacn:- Fig . 8.1 - Hydrographs for slope-al igned urban drainage units

ARRB SR 34, 1986 57


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

More frequently however, designers are competition with the demands of neighbourhood
forced to reduce the impact of upstream-orig- planning, building aspect, road hierarchy,
i nating storm run off by means such as those traffic management, etc., all of which impinge
described in Chapter 3. daily on the lives of the urban resident, the
needs of a major drainage system, whose pur-
pose rarely becomes apparent, frequently rank
Scope of a Major Drai ..age Systetl well down in the priorities of urban plann ing.
The major drainage system associated with an For this reason drainage designers can-
urban development is the network of surface not expect urban landscape plans to be always
flood paths taken by storm runoff during developed around 'most desirable' flood es -
times when its subsidiary minor system is cape networks. Instead, practitioners must
rendered parti ally inoperable as a result of develop skills enabling them to exploit the
blockage, or when the capacity of the minor potential of given urban layouts and terrain
system has been exceeded. In a properly to achieve their objectives.
planned scheme such occurrences are likely to
cause flooding of open space areas and inun- An ideal situation exists where an urban
dation of the grounds of buildings, but no plan is compiled by a team which includes
indoor damage other than to buildings of hydrological/hydraulic expertise. There is a
secondary importance. perceptible increase in this type of planning.
While the above advantage may be thought
of as primari 1y associ ated with schemes for
new developments, major/minor systems have an
8.2 MJOR SYSTEM P~IIIi PlOCEDlaE
important hindsight role to play in urban
runoff management. Th i s comes about in the
following way:- There are ei ght steps whi ch must be taken to
p1 an or design a major drai nage system for a
For a variety of reasons - the impossi- typical isolated development. They are:-
bi1ity of accurately predicting future deve-
lopment or, perhaps, lack of foresight on the STEP 1: Catchment definition
part of original designers - drainage systems STEP 2: Fi xi ng of roadway reserve capacity
frequently prove to be inadequate after some flows
years of service. The dominant characteris- STEP 3: 'Gap flow' design storm selection
tic of an overtaxed system is its inability STEP 4: System planning table
to contain flows of a given design frequency. STEP 5: Netwo rk revi ew
For example a scheme which was designed orig- STEP 6: System evaluation
inally to overflow in flows greater than STEP 7: Sub-area detailing
those generated ina 5-yea rs AR I storm is STEP 8: Final design detailing.
found, after 20 years of servi ce, to exceed
capacity every two or three years.
STEP 1: CatcMent de11"1 t1 on
Such a scheme may have much to gain from
a reapprai sa 1 based on the maj or/mi nor concept This involves the following set of tasks:-
in which the observed 2-years or 3-years ARI
flood capacity of its existing minor system a) locate development, i.e. climatic region,
is accepted and all augmentation efforts are rainfall relationships, etc.
devoted to providing open-channel f100dpaths
for major storm runoff flows (see Water Re- b) prepare contour map of area(1 or 2 metre
search Foundation 1984). The planning/design contours, or closer spacing if area very
approach which should be followed is identical flat); scale 1:1000 to 1:5000
to that described in this Chapter except for c) define development boundary and boundary
the status of the minor system design ARI = constraints consistent with the Master
N-years (see Section 5.4). In new devel- Drainage Plan (see Chapter 1)
opments thi s quant i ty must be adopted : in
rehabilitation work of the type briefly dis- d) identify pattern of internal roads, rele-
cussed here, it en j oys the status of an vant traffic management information
'observation' • e) identify roads and streets as dual-channel
or potential Single-channel flow paths and
A1 though the cost of 1and and property their hydraulic characteristics (see Sec-
acquisition for drainage easements is likely tion 6.1)
to constitute a major outlay, the total prog-
ramme may well be not only attractive in the f) identify major (common) 1and use areas
financial short run but may also involve g) identify N-years design ARI for underground
minimum public and business i nconvenience in network; is partial blockage likely?
its execution. It is also likely to offer a
higher level of flood security than was pro- h) fix 'natural dra i nage direction'
vided under the original scheme. i) nominate flood disposal points see
j) define internal isolated )
It must be recogni sed by the drai nage catchments and node points )Chapter
designer that sound storm runoff management
practice - important though it is - repres- k) define flood escape networks, nOdej
ents but one of many competing and at times sections and drainage sub-areas of 7
conflicting objectives of the urban plan. In each isolated catchment

58 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Execution of STEP 1 is mainly a routine a) calculate roadway reserve capacity flows,


operation involving much collating and some Oc, for each type of carriageway likely
preliminary assessment. The task is aided - to be used in the catchment
and the whole exercise appreciably shortened
- if information on the likely traffic status b) apply a storage correction to these capa-
of each roadway and street is available at ci ty flows, hence Osc for each type of
carriageway.
the catchnent definition stage. This infor-
mat i on has an important beari ng on the way
the drainage designer fixes the boundaries of The fi rst of these tasks employs the
catchments. It also influences his available procedures and criteria discussed in Section
options when faced with major flood flows in 6.1 for calculating capacity flows in dual-
segments of the catchment where surface move- channel and single-channel roadways. Two
ment of runoff is likely to be obstructed, criteria operate to limit the resulting capa-
city fl ows:-
e.g. roundabouts, street closures, raised
median strips, etc. Criterion 1: maximum flow level 50 mm above
top-of-kerb [see eqn (6.10)J
Ident ifi cat i on of the f1 ood escape net-
work and node sect ions in each catchment is Criterion 2: maximum value of the product
part of the final task of STEP 1 and one which da·V ave = 0.4 m2/s [see eqn (6.11)J
draws together many interacting threads of
catchment data. Catchment and drai nage sub- where Vave = flow mean velocity
area definition both apply two assumptions d a = kerb-side flow depth
relating to the way major floodwater moves
through an urban landscape:- Capacity flows, Oc, corresponding to
each carriageway type likely to be used in
1. flow into and/or out of a sub-area takes the development are calculated for the range
one entry and/or exit path only; of (gutter) longitudinal slopes present in
the catchnent.
2. the path taken by storm runoff at a road-
way intersection is along the roadway A storage-correction is made to these
path of steepest grade. flows on the grounds that temporary or deten-
It is not difficult to ensure, by appro- tion storage of runoff in the surface channels
priate shaping of gutter and roadway profiles, and underground pipes of an urban stormwater
that b<;>th of these assumed behavi ours do in drainage system depresses the peak flow dis-
fact occu r in urban catchment runoff events charge which emerges from the system in much
of small magnitude. It is almost impossible, the same way a f1 ood control dam reduces the
on the other hand, to guarantee similar per- peak of an i ncomi ng fl ood wa vee In the case
formance in major storms. of a major/ minor system which includes under-
ground pipes, the reduction is about 10 per
A satisfactory level of conformity to the cent; where gutter/pavement storage only is
assumed behaviours can be achieved, however, available, the reduction is about 5 per cent
by mak i ng the bu 1k of roadway fl ood escape (Tholin and Keifer 1959; Earley 1979).
paths dual-channel (see Section 6.1). This
has two consequences:- An upwards correct i on may therefore be
applied to .the previously calculated capacity
(i) it maximises available flood escape flows. Values must be increased by 10 per
channel capacity; and cent in catchnents where underground pipes
are emp 1oyed, and by 5 per cent where open-
(ii) it provides, by the presence of the channel drains only are used.
roadway crown, a modest degree of flood-
proofing in the system. The outcome of STEP 2 is a table of
storage-corrected capacity flows, Osc, one
A continuous roadway crown in a street for each carriageway type and longitudinal
which has 'high' and 'low' sides forces an slope occurring in the catchnent.
uneven distribution of flow to occur in its
dua l-channe 1 carri ageway. 'The greate r flow
holds to the high side kerb where it can be STEP 3: 'Gap Flow' desigll sto,.. selection
tolerated - while the lesser flow passes
along the low side kerb where fronting pro- The planning of a major drainage system for
perties are usually more vulnerable to damage an urban development is based on su rvi va 1 of
by roadside channel surcharge. the development in a rare flood of specified
magnitude (see Section 2.5). In STEP 3 the
The single-channel carriageway form (see properties of the storm which produces this
Fig. 6.4) may be used with impunity in upper design rare flood are defined. Four main
and/or remote subareas of catchments. Storm tasks are involved:
runoff contributed from such areas is, typic-
ally, well below the carrying capacities of a) select appropri ate design ARI for the
dual-channel carriageways. storm
b) select appropriate gap flow, Ogap' design
ARI (M-years)
STEP Z: Fixing of roadway reserye capacity .
flows c) select appropriate design storm duration
This step involves two hydraulic calculation d) determi ne average intensity for design
tasks:- storm

ARRB SR 34,1986 59
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

The question of design ARI recol1lllended poss i b 1e to determi ne for each f1 ood escape
for major systems, and the i nterpretat i on of path, its 'tributary (impervious) area' : -
this in terms of the conjunctive use of sur-
face channels and the pipes of the underground The tributary (impervious) area, TAi,
network, if present, is discussed in Section which may be linked to an identified
5.4. The outcome is presented in Tables 5.2A flood escape path, is the impervious
and 5.2B. area which yields, in a storm of average
intensity equal to that selected in STEP
Information obtained from these Tables 3, peak runoff flow matching the storage-
enables the designer to confine his attention corrected capacity flow, Qsc, of that
to that component of the design flood 'gap path.
f1 ow', Qgap, whi ch is movi ng in the surface
channels only of the flood escape network. The table 1 isting values of TAi for the
The designer I1lJst adopt a 1 ikely blockage full range of flood escape paths available in
condition as part of this process. a development constitutes its System Planning
Table.
The third task involved in STEP 3 - that
of fixing design storm duration - may require The table is used inSTEP 5 - Network
one iteration for it to be correctly fixed. Revi ew. The only data whi ch must be brought
This is built into the design procedure (see by the designer to make use of the table
STEP 6 below). However, a fi rst approxima- are:-
tion duration is needed to initiate the cal-
culations. Critical storm duration should be a) flood escape path carriageway width; and,
selected according to the guidance given in
Table 8.1. b) carriageway longitudinal slope.

TABLE 8.1
STEP 5: Network rev; ew
DESIGN STORM DURATIONS* FOR SMALL URBAN
CATCtMENTS Of all the data and component information
contained in the catchment definition (STEP
evelopment) I

~
1), those relating to basic road form
type\ReSidential commercial/I carriageway widths, roadway reserve cross-
roadside ... Sub- Industri al sections, pavement types, etc., - are the
channel divisions develop- most amenable to change. Th e netwo rk revi ew
\ type ~ ments procedure devolves upon this fact, for it
enables a tri al urban pl an to be tested and
kerb-and-gutter 10 - 15 15 - 20 modified, where necessary, without disturbing
roadside channels minutes minutes the plan itself in any basic way or altering
throughout the inter-relationship of its main compon-
grassed swale or
blade-cut road- N.A.
I ents.

With the Sy stem Pl anni ng Tab 1e for the


~sl~·d~e~c~h~a~n~ne~l~s~__~________~__________ particular roadways and longitudinal ~lopc$
of a developed catchment drawn up (STEP 4)
* these storm durations correspond to catch- and using runoff coefficients applicable to
ment impervious area travel times: they in- its likely ultimate development (see Sections
corporate roof-to-gutter travel time of 5 5.1 and 5.6), it is possible to perform a
minutes or 10 minutes for residential or series of systematic 'test-and-modify' calcu-
commercial/industrial developments respec- 1at ions, and thereby assess the performance
tively. of the flood excape networks defined in STEP
1.
The last task in STEP 3 requires consul-
tation of the current edition of 'Australian This review which is amenable to tabu-
Rainfall and Runoff' (I.E. Aust. 1977 or 19- lation is executed in STEP 5.
87) to determine the design average rainfall
intensity which should be used in the STEP 4 The test procedure involves comparing
calculations. Design ARI and storm duration the equivalent impervious area, (CA), compu-
come from selections made in the first three ted at successive node sections (see Chapter
tasks above. 7), along each drainage path, with the value
of TAi 1 i sted for the dra i nage path defi ned
in terms of its width (carriagway) and longi-
STEP 4: Syst.. ,1Anning tAble tudinal slope in the System Planning Table
(STEP 4). At those sections where (CA) is
The table produced in STEP 4 is the central less than TAi, it follows that the flood
feature of the procedure, for it enables the escape path wi 11 sati sfactorily convey flood
designer to evaluate and modify, where neces- runoff in the design storm selected in STEP
sary, his trial major drainage system. 3; where it is greater, then alternative
f1 ood management options mu st be explored by
Knowing the storage-corrected capacity the designer.
flows, Qsc, which can be carried in the range
of flood escape paths available in a catch- The outcome of this process is a 'first
ment (STEP 2) and knowing design storm aver- approximation' major system drainage network
age intensity selected inSTEP 3, it is for the development.

60 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

STEP 6: Syst_ evaluation 1aws of open channel hyd raul i cs to ensure


that storm runoff finding its way to the
The first approximation major drainage system roadway reserves and d ra i nage easement s of
determined in STEP 5 must be evaluated to en- the flood escape network, moves through and
sure that the assumptions made in the course from each sub-area without surchargi ng its
of its derivation - in particular, the assum- defined drainage paths.
ed design storm duration (STEP 3) - are val-
id. This involves estimating a corrected or An example of the type of review referred
'new' flow travel time in each catchment of to here is where a potential single-channel
the development and cOl11>aring it with that lateral street which is not a component of the
adopted from Table 8.1. main flood escape network, is required to con-
vey a flow exceeding its single-channel capa-
Where they differ significantly, i.e. city. Various options must be explored by
'adopted' versus 'new' in a particular catch- the designer, e.g. change to dual-channel
ment, a revised critical storm duration based form, provide some form of flood-proofing
on the 'new' estimate of travel time may be such as raised footpath, etc.
returned to STEP 3 and the subsequent steps
repeated until satisfactory agreement is It must be emphasised that the earlier
reached. STEP 5 network review completely overlooks
such sub-area internal hydraulic detailing.
The qualification 'may' entered here This must be carried out in STEP 7 but only
covers the case where the first approximation after a broadly sat i sfactory major drainage
major system is demonstrably conservative, system has been adopted.
but unalterable for reasons whi ch stem from
the requirements of the road/traffic plan.
This point is examined in more detail in
Chapter 9 (STEP 6). STEP 8: Final design detailing

The outcome of the system evaluation This step involves all detailing necessary to
process is a layout of 'adopted' drainage define the system of open channels - including
networks. ca rri ageways, roadway reserves, f1 ood-proof-
ing, drainage easements, roadway hydraulic
geometries, etc., - which will convey runoff
STEP 1: Sub-area detailing from major system design storms through and
beyond each catchment wi thout indoor damage
Completion of the major drainage system plan- to residential and other important buildings.
ni ng procedu re i nvo 1ves one further step -
the detailed review of flow movement within The resulting plans form the basis for
each sub-area. This calls for careful appli- the design of the minor drainage system to be
cation of the principles of hydrology and incorporated within it.

ARRB SR 34, 1986 61


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

62 ARRB SR 34,1986
9
The major drainage system -
case study applications

9.1 INTRODUCTION traffic d i stributor. All other residential


roads a nd streets wi ll have 'access road'
The step-by-step procedure for planning a status. No ro undabouts or street closures are
ma .ior stormwate r drai nage system for an anticipated during the life of the
isolated urban catchment , desc r ibed in Chapter sub-di vi s ion.
8, is now applied to a 38 ha hypothetical
residential sub-division in the Adela i de Data and information relating to STEPS 1-8
foothills, South Australia. inclus i ve for the t wo cases are presented
below.
The catchment area is bordered on three
sides (north. east and west) by main roads. A
green belt reserve forms its southern
boundary. The catchment t opography slopes 9.2 CASE 1 AND CASE 2 DEVELOPMENTS: STEPS 1-8
generally to the south ma king this the natural
STEP 1: Catc~nt Definition
drainage direction.

Housing density in the sub-d i vision will The follow i ng data and information relating to
catchment definition are ava i lable. Most
be. init i ally, 16 residences per ha of dedi-
items are included in Figs. 9.1(a ) and 9.1(b):
cated area i.e. excluding roadway reserves
etc. Ultimate development (see Sect i on 5.1) (a) catchment location: Adelaide foothills
during the life of the drainage system is lone, Fig. 5.2);
(Southern Australia
est imated to be equ i va 1ent to 20 residences
rainfall . Fig. 5.1
per ha. Some open space park areas are
located within the sub-division. (b) contour map - Fig. 9.1
Two a lternat i ve road 1ayouts are (c) sub-division catchment boundary - Fig. 9.1
considered. The first, Case 1. uses a road
pattern of the conventional grid type; the (d) pattern of internal roads and streets -
second. Case 2, employs a contemporary layout Fig. 9.1
of crescents. cul-de-sacs. etc. and is based
on a plan developed by a leading Canadian (e) dual-channel and potential single-channel
engineer-planner, P.E. Theil (1977). All streets - Fig. 9.1
roads will have sealed pavement carriageways
with concrete kerb-and-gut ter borders. It is (f) major (common) land use areas - Fig. 9.1
anticipated that underground pipes will be
used in the catchment minor drainage ~ystem. (g) an underground network will be
Partial blockage (50 per cent blockage) of incorporated, design ARI = 2-.years; 50
these pipes in major runoff events is con- per cent blockage to be assumed
sidered likely.
(h) natural drainage direction - Fig. 9.1
The Case 1 and Case 2 sub-di vi si ons are
ill ustrated in Fiqs. 9.1(a) and 9.1(b) (i) flood disposal points - Fig. 9.1
respectively. Some aspects of the Case 1
exampl e are discussed in Chapter 7 (see Fig. (j) sub-division internal isolated catchment
7.3). It · is assumed, for purposes of boundaries and node points - Figs. 9.2 and
illustration. that runoff from individual 9.3
residences in the ultimately developed
catchment will be di rectly-channelled to the (k) flood escape networks. node sections and
surface stormwater drainage system. Drainage sub-areas - Figs. 9.2 and 9.3
from positive grade allotments (see Fig. 9.1)
will be conveyed d i r e ct l y to fronting roadways Concerning 'catchment boundary and
and drainage from adverse grade allotments to boundary contraints' [see item (c). STEP 1.
rear-of-allotment channel s or rear access Section 8.2]. there is no inflow to the roads
lanes. and streets of the subdivision from outside
its boundary. The passi ng of stor", runoff to
It may be further assumed that High Street side boundary flood paths (Eastern Highway and
(bot h ca ses) will have the status of 1 oca 1 West Street) should be MiniMised. It is

ARRB SR 34,1986 63
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

positive grade
HIGH
~ l~ ~TREET
TO
allotment

----t:==r----1 ---......
' -96
a dverse grad e
allotmen t

All adverse grade allotments


are provided with rear- of-
allotment drainage .

Fig . 9.1 (a) - Adelaid e fo othills residential subdivision - Case 1

flood disposal
points shown . . .. . . ®
rear of allotment
drains shown . . . . . .
floodways shown ..
dual- channe l r oad-
ways shown .. . . . . . -=i;","_--

p'otential single-
channel roads
shown ...... .
contours shown . . Toe ______
sub-division
boundary .. . .. . .. . . _ _ _

SCALE
, i
100 200
me tres

Fig . 9.1 (b ) - Adelai de fo oth ills residentia l subd ivision - Case 2

assumed that these floo d paths convey sizeable STEP 2: Roadway reserve capacity flows
f1 ows from remote ca tchments and tha t addi-
tional floodwater input in the vicinity of the
recelvlng domain should only occur if The particular roadway forms to be used in the
unavoidable. development have 7.5 m and 10.0 m carriageways
within 16.0 m amd 20.0 m, respectively.
The prelimi nary road hierarchy information roadway reserves. Roadway reserves: kerb-and-
available for the sub-division(s) is gutter 0.375 m profi le and pavement cross-
suf fi c i ent to force a change in one item of slopes (Z = 30 and 40 for the 7.5 m and 10.0
catcn.ent definition data relating to High m carriag~ways, respectively) are the same as
Street in both cases. Its status as a local those used for illustrative purposes in
traffic distributor requires its cross-section Section 6.1 of the text. The 7.5 m
to be changed from potential single - channel carriageway is used for access roads, the 10.0
(north@rn segMent) to dual-channel throughout. m carriageway for local d i stributors.

64 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Flow capacities of these carriageways Taking design ARI 50-years for the
(half-carriageway flows) are presented in Fig. surface system only and storm duration of 10
6.3 and are 1i sted. for the range of 1ongi - minutes, design storm average instensity, from
tudinal slopes present in the sub-division. in Fig. 5.1 is 90 mm/h.
Table 9.1A. The storage-corrected capacities
of these carriageways are listed in Table STEP 4: SysteM Planning Table
9.1B: a 10 per cent correction has been
applied for reasons explained in STEP 2. By bringing together data from STEP 2 and STEP
Sect ion 8.2. 3, it is possible to determine the tributary
(impervious) area, TA., which will yield,
STEP 3: Design ston. selection under design storm conditions, a peak runoff
flow matching the storage-corrected capacity
The recommendation that major drainage systems of any roadway flood escape path likely to be
should be designed generally for ARI used in the Fig. 9.1 developments. The TA .
100-years (see Section 2.5) is adopted and va 1ue requi red in each roadway case can b~
parti a1 blockage (50 per cent) of the found from substitution into the Rational
associated underground network assumed. Since Method formula [eqn (4.2)).
the minor drainage system will be designed
subsequently for ARI = 2-years. it follows (TA;) ;50
Lis (9.1)
that gap flow, Qgap ' design ARI M = 50-years 0.36
should be used (from Table S.2B). where Qsc storage-corrected capacity flow
in flood escape path (from Table
Design storm duration for the particular 9.1B)
conditions which are anticipated for the average rainfall intensity for
ultimately developed catchment (see Section storm of design ARI = 50-years
9.1) may be found from Table 8.1: storm and duration equal to that
duration equal to 10 minutes is adopted. adopted in STEP 3

TABLE 9.tA
CAPACITY FLOMS. Qc ' FOR 7.5 • AID 10.0 • CARRIAGEWAYS

FLOW CAPACITIES, Qc' IN LIs


Longitud i na 1
Slope
So 7.5 m carri agewa.Ys: ~ = 30 10.0 m carriagewa'ys: Zb = 40

single-channel dua 1-cha nne 1 single-channel dual-channel

0.005 3<ll 780 500 1000


0.010 560 1120 700 1400
0.020 780 1560 990 1980
0.030 700 1400 915 1830
0.040 635 1270 830 1660
0.050 580 1160 760 1520
0.060 535 1070 700 1400

TABLE 9.18
STORAGE-CORRECTED CAPACITY FlOMS. Qsc '
FOR 7.5 • All) 10.0 • CARRIAGEWAYS

FLOW CAPACTTTFS, Qsc' TN LIs


Longi tud ina 1
Slope
So 7.5 m carriageways: Zb = 30 10.0 m carriageways: Zb = 40

single-channel dual-channel single-channel dual-channel

0.005 430 860 550 1100


0.010 615 1230 770 1540
0.020 860 1720 1090 2180
0.030 770 1540 1005 2010
0.040 700 1400 915 1830
0.050 640 1280 835 1670
0.060 590 1180 770 1540

ARRB SR 34, 1986 65


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

tributary (imper vious) area i n Roadway r e serves compris e a bout 50 per


ha cent carriagewa'y a rea , 15-30 pe r c ent footpath
and dri veways and the r emainder nat ure st r ips .
From Fi g. 5 .1, i~ = 90 mm / h in 10 min ute Use of a lumped , a r bitrar'y factor, 0. 75 to
storms: con vert roadway r eserve area to equivalent
0.36 Qsc Qsc pa ved area is recol1l!lended. The runoff
= - ha (9.2 ) coefficient wh i ch should be applied to the
90 250 conve r ted area is :
Applying eqn {9.2} to the data in Table
9.1B gi ves a set of tributar'y (impervious) C50 1.15 x 0.90 which exceeds 1.00
areas which can, for design storm conditions , {see Section 5.6}
be serviced within the adopted criteria {see
STEP 2, Section 8.2} by the 7.5 m and 10.0 m hence, use:
roads and streets of the Fig. 9.1 develop-
ments. The values are listed in Table 9.2. 1.00 for roadway reserve
converted areas
(9.5)
STEP 5: Network Review Using these coefficients - eqs (9.3}-{9.5)
it is possible to determine weighted
One final item of information is needed before C50 values which may be applied to each
the network revi ew can be commenced. Thi sis sub-area of the development to determ i ne thei r
the set of runoff coefficients which must be ind i vidual {CA}5o values [see eqn {4 ; 7)J.
applied to convert catchment component . area s
into equi va 1ent impervi ous areas, (CA). Great accuracy is not warranted in
Appropriate factors are to be found in Tables performing this task and the following values,
5.3 to 5.5 inclusive. based on the above, are considered
sat i sfactory:
Three land uses only are included in the
Fig. 9.1 sub-division(s}: residential sub-areas (including
surrounding roads):
(a) residential, 20 residences per ha
{excluding roads, etc.} 0.58 (9.6)
(b) park areas park sub-areas (including surround i ng
roads) :
(c) roadway reserves - 16 m and 20 widths

In the case of residential segments,


C50 = 0.28 (9.7)
C10 = 0.45 (from Table 5.4) and the frequency These coeffi c i ents are incorporated into
conversion factor F = 1.15 (f r om Table 5.5 ) the Network Rev i ew Tabl es (Tabl es 9.3 and
are employed: Y 9.4 ) . The network review follows.
Hence, for residential areas,
C50 - 1.15 x 0.45 Considcr Catchment M in the Casc 1
development (see Fig. 9.2 and Table 9.3). At
= 0.52 node section M.3 the High Street carriageway
(9.3) is of dual-channel type and although likely to
In the case of park areas, take the 10.0 m form in the final urban plan,
C10 = 0.10 and is investigated here as a 7.5 m trial roadway.
hence C50 = 0.12 The longitudinal slope, S , of High Street
(9.4 ) at node section M.3 is appctoximately 0.01.

TABLE 9.2
MAJOR DRAINAGE SYSTEM PLANNING TABLE

TRIBUTARY ( IMP ER VI OUS) AREA TA; WH IC H CAN BE SER VI CED BY


Long ; tud; na 1 ROADWAY FLOOD ESCAPE PATH I N DESIGN STORM
Sl ope
So
7. 5 m car r ;ageways : Zb = 30 10.0 m ca rr;ageways: ~ = 40

s; ng l e- cha nn el dual-c hann el sing l e -channel dua l-chan nel

0. 005 1.72 ha 3.44 ha 2. 20 ha 4 . 40 ha


0. 010 2 .46 ha 4 . 92 ha 3.08 ha 6 . 16 ha
0.020 3. 44 ha 6. 88 ha 4 . 36 ha 8 .72 ha
0.030 3. 08 ha 6.1 6 ha 4. 02 ha 8 . 04 ha
0.040 2. 80 ha 5. 60 ha 3. 66 ha 7. 32 ha
0.050 2 . 56 ha 5. 12 ha 3. 34 ha 6.68 ha
0.060 2.36 ha 4. 72 ha 3 .08 ha 6 . 16 ha

66 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Reference to Table 9.2 (carriageway 7.5 m, S is considered. This proves to be


= 0.01) reveals that it can convey a capacit9 hydraulically satisfactory. However, it is
flow matching the peak generated in 4.92 ha of unlikely than an access road will be built
tributary (impervious) area, TA . . This with 10.0 m carriageway for no reason other
information is surrmarised in Table' 9.3 under than its inability, as a 7.5 m residential
the heading 'flood escape path detail' street, to convey rare storm fl ows. The
(col umns 2-5). designer is forced to explore a range of
alternati ves:
The sub-area which contributes runoff to
node section M.3 is, mainly, a park (total (i) remove roadway L.1-L.2 from the urban
sub-area 2.36 hal for which Cso = 0.28. This plan and extend the f100dway north to
sub-area may therefore be equated to 2.36 x L.2 ;
0.28 = 0.66 ha ' of impervious area, (CA).
These data are listed in columns 6-8 of Table (ii) change gutter/pavement profile in roadway
9.3 under the head i ng 'adjacent contri buti ng L.1-L.2 to one gi ving greater capacity /"
sub-area'. The 'cumulative upstream (CA) "' for within the limits of Criteria 1 and 2 /
the catchment draining to M.3 is, of course, [eqns (6.10) and (6.11), see Appendix AJ.
0.66 ha presented in column 9.
(i i i )retai n roadway L.1-L.2 as a 7.5 m
The flood escape path TEST (column 10) dual-channel carriageway carrying flows
compares the total (CA) contributing to node which exceed the 'kerb-p1us-50 mm'
section M.3 with the tributary (impervious) capacity criterion [see eqn (6.10)J and
area, TA , which could be serviced, under apply local floodproofing measures, e.g.
i
design storm conditions, by the flood escape rai sed footpaths, rai sed floor level s,
path at that section. A successful outcome, etc.
'O.K.', indicating that the trial road /
carriageway is satisfactory, is shown under (iv) adopt design ARI = 10-years for minor
Remarks (column 11). system pi pe 1 i ne L.O-L .1-L.2, hence 'gap
flow', Qgap' design ARI = 30-years (see
The same trial road form is then tested at
node section M.2 where the cumulative upstream Tab 1e 5. 2B) for surface-movi ng flow
(CA), column 9, is the sum of the areas L.2.-L.1-L.O.
draining to M.3 and M.2.
Detailed design relating to these options
Catchment M (Case 1) has a flood escape need not, of course, be undertaken until STEP
path which divides at node M.1 where runoff 7.
from the northern and eastern arms join.
An identical situation arises at point L.2
The tria 1 road form at node section M.4 is in Catchment L, Case 2 (see Fig. 9.3 and Table
a 7.5 m dual-channel carriageway (see Fig. 9.4) •
9.2): the test at this section also succeeds.
The procedure outlined above has been
At node M.1 the flood escape path required fo 11 owed f or each of the fou r catchments of
by storm flows from the two arms of the the Case 1 and Case 2 developments and the
network is checked against the TA . which can results tabulated in Tables 9.3 and 9.4
be serviced by a trial 7.5 m du'a1-channe1 respect i ve 1y. The ei ght i so 1ated catchment s
carriageway. In this case, the cumulative cover, between them, many of the common major
network situations met in contemporary urban
ups tream (CA) is the sum of the equi va 1 ent
drainage practice.
impervious areas at M.2 and M.4 and the
sub-area adjacent to M.1. The test at node
section M.1 shows the 7.5 m carriageway to be
adequate here a 1 so. STEP 6: Syste. evaluation

It is concluded from this analysis that Completion of the above network review
the total runoff generated in Catchment M in a provides the designer with what should be
design storm of ARI = 100-years approximately regarded as a 'first approximation' major
can be contained within the 7.5 m carriageways drainage system. This follows from the fact
of its f1 ood escape network acti ng conjunc- that important design information contained in
tively with its associated underground the System Planning Table (Table 9.2) is based
network, assumed to be 50 per cent blocked. on catchment travel time adopted from the
The likely decision to assign a 10.0 m guidelines of Table 8.1.
carri ageway .to Hi gh St reet for rea sons of good
traffic management practice will not conflict Before the design can progress to STEP 7,
with this conclusion. a check on the suitability of the adopted
catchment travel time must be made in each
Consider now Catchment L in the Case 1 catchment of the derived major system(s).
development (see Fig. 9.2 and Table 9.3). Note that major system catchment travel time
for an urban development is taken as catchment
The analysis and tabulation proceed in impervious area travel time (see Table 8.1).
much the same manner as for Catchment M until
node section L.2 is investigated. Here, the Allowing for roof-to-gutter or
test for a 7.5 m dual-channel flood escape roof-to-easement travel and adding flow time
path fails ('N.G., reconsider' in Remarks along road and street gutters (see Fig. 5.4)
column) and a 10.0 m dual-channel carriageway it will be observed that travel time of 10

ARRB SR 34, 1986 67


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

rHIGH ST REET

2· 32
ha
0·84

f
ha
flood escape
network . 2·27
ha

I N'l- •
M·4

N'O-
MO-
single-channel street sho .... n: =~~=
dual- channel street sho .... n: --===--

Fig . 9.2 - Catchments L, M , Nand P of Adelaide fo othills sUb-division

.
HIGH STREET

/ 1·26 ha

flood escape
network

single-channel street shown


dual - channel street sho .... n

Fig. 9.3 - Catchments L, M , Nand P of Ad elaide foothills sub-division

mi nutes adopted inSTEPS 4 and 5, is, in some The situation in Catchment L at node
catchments, short. A travel time of 15 section L.2 in both the Case 1 and Case 2
minutes for some Case 1 and Case 2 catchments developments, warrants further attention.
might be more appropriate.
Fifteen-minute ARI = 50-years storm bursts
The network review (STEP 5) has shown that in the Adelaide foothills show an average
the flood escape paths of Catchments M and P intensity of 78 mm/h (see Fig. 5.1). Applying
(both Cases) can accommodate the runoff this value into eqn (9.2) yields a new
generated in a 10-minute design storm. relationship for tributary (impervious) area,
Further review of these using a catchment namely:
travel time and, hence, storm duration of 15 0.36 Qsc Qsc
minutes will reach the same conclusion making =- ha (9.8 )
it a redundant exercise. 78 217

68 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TABLE 9.3
NETWORK REVIEW FOR CATCHMENTS, L, M, N AN> P - CASE 1
fl ood escape path detai l adjacent contributing
sub-area clll1ul ative
esca e ath t ri butary weighted upst ream TEST REMARKS
node path 1ongi tud i na 1 (imperv. ) area runoff (CA)50 (CA) 50
section description slope, So a rea, TAi coeff.
(ha) (ha) (ha) (ha)
2 3 4 5 6 8 9 10 11
L L.4 dual-channe l , 7. 5 m 0.03 6.1 6 1.14 0. 28 0.32 0. 32 0. 32 < 6.16 O. K.
L.3 dual-channel, 7.5 m\ 0.02 6. 88 2. 15 0. 58 1.25 1.57 11.57 < 6. 88 O. K.
L.6 dual-cha nnel, 7.5 m\ 0.03 6.16 2.47 0. 58 1.43 1.43 1.43 < 6.16 O.K.
L.5 dual-channel, 7.5 m 0. 005 3.4 4 2. 25 0.58 1.31 2. 74 12.74 < 3. 44 O.K. )
I I L.2 dual-channel, 7.5 m' 0. 01 4. 92 2.15 0. 58 1. 25 5.56 5.56 ( 4. 92 ) N. G.r econsider

~:!~ ,
dual-channel,10.0 m, 0.01 5. 56 15.56 < 6. 16\ O.K .
L.1 floodway, 10. 0 m
,
(roadway) ,
0. 005
2.20 0.58 I 1.28 I
I I 6. 84
\ , , 6.84 , ,
from Table 9.1A fl oodway deiig n flow at L.1 approximately (-- -- ) x 1000 Lis = 1554 Lis, floodway design flow
4.40

M M.3 du a l-channe 1, 7.5 m,1 0. 01 4. 92 2. 36 0.2 8 0. 66 0.66 0. 66 < 4.92 O.K.


M.2 dual-channel, 7.5 m 0. 04 5. 60 2.13 0. 58 1.24 1.90 1. 90 < 5. 60 O. K.
,
M.5
M.4
dual - chann el, 7.5 m/
dual-chan nel, 7. 5 m
0.03
0.005
6.1 6
3.44
2.32
2. 27
0. 58
0.58 I
1.35
1.32 , 1.35
2. 67
1. 35 < 6.16
2.6 7 < 3. 44
O.K .
O. K.
M.I dua l-channel , 7.5 ml 0.02 6.88 2.09 0.28 0. 59 , 5.16 I
5.16 < 6.88 O.K .
Note : These calcul ations demonstrate that a 7. 5 m car riageway in High St. could convey satisfactorily the design
I
rare storm flood f l ow . However, the road hierarchy re uires it to be of width 10. 0 m, therefore O. K.
N N.1 dual-channel, 7.5 m 0.03 6.1 6 0. 63 1.00 0 . 60 0.60 0. 60 < 6.16 O.K.
P P.5 dual-channel, 7.5 m 0. 03 6.1 6 1.16 0. 58 0. 67 0.67 0.67 < 6.16 O.K.
P.4 dual-channel, 7.5 m 0.0 3 6.1 6 1.89 0. 58 1.09 1.76 1.76 < 6.16 O. K.
P.3 dual-c hannel , 7.5 m 0.04 5.60 1. 73 0.58 1.00 2.76 2.7 6 < 5.60 O.K.
P.2 dual-channel, 7. 5 m 0.0 3 6.1 6 1.63 0. 58 0.95 3.71 3.71 < 6.16 O.K.
P.1 fl oodway, 7.5 m 0.04 2.33 0. 58 1.35 5. 06
(ro~~~y)
from Ta Ie 9.1A floodway de ign flow at .1 approxi at ely (~~Q~)
5. 60
x 12 o Lis = 1148 Lis, fl odway design flow.

TABLE 9.4
NETWORK REVIEW FOR CATCHMENTS, L, M. N Aft) P - CASE 2
I flood escape path detail , adjacent contrlbuting ,

I nod e I sub-area
------r'------7es~c~a~p7e~a~t~h----------~'~t~r~lb~u't~a~ry~'------~'~
~l~gh~t~e~d~'------
cumul ative I upstream
II,
TEST REMARKS
:------::p"'="at;'ih?-"""--'::"::"::':':"'l"o=-=n:-:gTit"'u""'d"i""n-:T
a1 , (i mp e r v. ) a rea run 0ff ( CA) 50 (CA) 50
section description slope, So area, TAi coeff .
(ha) (ha ) (ha) (ha)
3 4 5 6 7 8 9 10 11

I ~::: 3~'4g:~: I ~::l I


L L.5 single-channel,7.5m 0. 01 2.4 6 1.62 1.62 < 2. 46 O. K.
L.4 floodway, 7.5 m 0.02 6. 88 3. 64
, (roadway) ,
from Table 9.1A floodway design flow at L 4 appro ximately (-- -- ) x 1560 L Is 825 Li s, fl oodway desi gn flow
L. 3
L.2
dual - channel, 7. 5
dua l - cha nnel, 7. 5
dual-ch annel,10.0
m
m
m ~~~~ . ~~~!"I ~::~ 6'1,88 ~:;~ ~:~~'II II'
4. 45
5. 30
'4 . 45 < 4. 92 O.K .
5. 30 ( 4.92 N. G.reconsider
5.30 < 6. 16 O. K.
L.l floodway, 10.0 m 0.01 6.1 6 2.1 3 0.58 1.24 6.54
(roadway)
6.54
from Table 9.1A floodway design flow approximately 16.16
----) x 1400 Lis = 1486 Lis , floodway design flow
M M.4 slngle-channel,7.5m 0. 02 3.44 LZ6 0 . 28 0 . 35 o~ ro:-rs- <To« O . K.
M.3 single-channel,7.5m 0. 06 2. 36 2.55 0.58 1.48 1. 83 1. 83 < 2.36 O.K.
M.2 dual-channel, 7.5 m 0. 03 6. 16 4.09 0.28 1.15 2.98 2.98 < 6.1 6 O. K.
M.1 dual-channel, 7.5 m 0. 02 6. 88 3.10 0. 58 1.80 4.78 4.78 < 6.88 O.K.
N N.1 dual-channel, 7.5 m 0.02 6. 88 1.50 0.75 1.13 1.13 1.13 < 6. 88 O.K.
P P.4 dual-channel, 7.5 m 0.03 6.16 0.88 0. 58 0.51 0.51 0.51 < 6.16 O. K.
P.3
P.2
dual-channel, 7. 5 m
dual-channel, 7.5 m
0.03
0.04
6.16
5.60
1.49
1.75
0.58
0. 58
0.86
1.02 I 1.37
2. 39
1.37 < 6.16
2. 39 < 5.60
O. K.
O.K .
P.5 s ingle -channel,7 . 5m 0. 005 1.72 1.90 0.58 1.10 1. 10 1.10 < 1. 72 O.K.

P.l floodway, 7.5 ml 0.04 5.60


(roadway)
3. 20 0. 58 1. 86 1 5.35 J
, 5.35'
__JLf_r_om__T_alp_le__9_._lA__f_l_o_od_w_a~y_d_e~fi~gn--f_l-ow__a~p~PLf'0_x_i_m_at_e_l~y~5~=~5~O~)_x_~t27_0__L_/S_~f_l_21_3__LL(S_,~f_l_00_dw
__aY~Le_S_i~gn__f_1_OW__~__________

ARRB SR 34,1986 69
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

There is no need to completely recalculate Consi der desi gn extreme storm runoff
Table 9.2 using the above 'new' expression for joining the major system network from the
TA . in order to further investigate one lateral street leading to node point M.5 in
'd'ouble spot' i.e. node section L.2 when, in catchment M (see Fig. 9.4). The terrain
fact, only the TA . value for a 7.5 m cross-slope in the vicinity is about 5 per
dual-channel carriagJway with S = 0.01 is cent: it is potentially a single-channel
required. Application of eqn (9.g) leads to: carriageway street:
1230 flood path description : single-channel.
TA. = - - = 5.67 ha
1 217 (9.9) 7.5 m longitudinal slope, So = 0.02

for the particular surface channel of t ributary (impervious) area : 3.44 ha


in teres t. Compari son of thi s va 1ue wi th the (from Table 9.2)
cumulative (CA) at node section L.2 (both
cases) leads to the conclusion that the 7.5 m upstream contibuting area* 1.40 ha
carriageway(s) is satisfactory and that no
further consideration need be gi ven to upstream contributing (CA) 1.40 x 0.58
alternatives (i) - (iv) listed in STEP 5. = 0. 81 ha
The above review concerns situations where TFST : O.ill < 3.44 t'hPrpfnre O.K..
the originally adopted (STEP 3) catchment
travel time - 10 minutes - was less than that * 'upstream contributing area' is that
which closer inspection subsequently revealed sub-area portion which yields runoff in a
to be more appropriate. design storm to the channel discharge
section under review.
Of greater concern to the designer is the
reverse situation where the adopted travel
time proves to be the longer of the two.
Catchment N [Fig. 9.1 development(s)] falls
within this category. Recalculation of TA .
for the node section N.1 case, however, i~
unnecessary considering the small cumulative
(CA) which the catchment draining to this
section presents.
If, however, the difference is significant
j node point
M·5
upstream
contributing
area = 1· 40 ha.

and widespread, e.g. affecting all mai n


catchments in a development, th~n thp rlp~ignpr
has no alternative but to return the 'new'
shorter travel time into STEP 3 , recalculate
Table 9.2 and repeat STEPS 5 an d 6. node point
M·4
It is clearly advantageous to adopt travel
times which prove to be short rather than -1-
long. T;!hlp 8 ,1 reflects this philosophy. landscaped levee: ----1
design height = 0 · 13 m.
The above review - while fortuitous in its
outcome for the Case 1 and Case 2 developments
of Fig. 9.1 - highlights the need for close Fig . 9.4 - Drainage detai l. node points M'4 & M ·5 - Case 1
liaison to be maintained between the drainage
system designer and those responsible for
traff i c management, bu il ding approva 1s (floor Investigations carried out on streets
levels) and city planning generally. which deliver storm runoff laterally to major
system networks will almost invariably yield
It should be restated here that the ma .;or similar 'O.K.' results. Experienced drainage
drainage networks identified in Figs. 9.2 and designers are able to recognise the few
9.3 have been shown capable of conveying problem situations by inspection.
des i gn rare s to rm runoff fl ows wi thout
surcharge of their flood escape paths. This Of greater concern are the problems which
does not preclude the possibility of overflow arise at roadway intersections.
from fl ow paths withi n component sub-areas.
This matter is addressed in STEP 7. The need to employ dua l-channe 1 carri age-
ways generally in fl ood escape networks has
STEP 7: Sub-area detailing been stressed (STEP I, Section 8.2). This
precaut i on does not p recl ude, however. the
With a sati sfactory ma.ior flood escape network possibility of surcharge at intersections such
in place in each catchment, the designer's as at node point M.5 in Catchment M (see Fig.
next task is to check flow conditions in all 9.4). Floodproofing in the fonn of a low,
roads and streets which convey flow to the landscaped levee bank within the nature strip
main network. Principal among these are at the south-western corner of the
lateral streets, particularly those which are, intersection may be warranted.
potentially. of the single-channel type. The
check which needs to be carried out is a mini- The channell ing of floodwater mak.i ng its
versi on of the test-and-modi fy procedure of way to node point .... 4 (Fig. 9.4) also needs
Tables 9.3 and 9.4. careful attention. Again, the presence of a

70 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

low, landscaped nature strip levee bank along Further discussion of these matters cannot
the southern boundary of the intersection be justified in the present publication .
would be a valuable safeguard. Calculations Suffice to conclude that with careful
carried out to fix the height of this detail ing, thoughtful planning and the use of
embankment are part of the necessary hydraulic modest flood-proofing measures, it is possible
computations. to handle major flood flows generated in
small, isolated urban catchments wi thout
Some indication of the height required may damage indoors and without inter rupti ng the
be gained from the following: supply of essenti al communi ty services or the
functioning of strategic installations.
If flow moving down-slope towards node
point M.4 were to be abruptly stopped by a
pond of water in the region of the STEP 8: Final design detailing
T-intersection, the maximum height of levee
(approximate) which would be required to The outcome of STEPS 6 and 7 is a ser i es of
contain the pond is given by : deSign and planning decisions and component
detail computations which will, when realised
(9.10 ) in the field, enable the goals of a major
drainage system to be achieved . STEP 8
where h levee height about top-of-kerb i nvolves the process of committing those
decisions and deta i I ing to paper in the form
v = averagevelocity of down-slope of drawings for a works programme .
ave moving flow

g = gravity acceleration (9.81 m/s ) 9.3 NON-ISOLATED DEVELOPED CATCHMENTS

In the vicin i ty of M.4, S for the It is clear from the definitions of isolated
down -s lope roadway is approx i ma te9 y 0.03 and and non-isolated catchments given in Section
average veloci ty approximately 1.6 m/s in a 8.1 that non - isolated catchments give rise to
design flood. Required levee height is, runoff management planning and design problems
therefore, about 0.13 m. Some freeboard would which are Significantly more complex than
need to be added to thi s. those presented by the types of developments
investigated in Section 9.2.
It will be necesary in some of the
hydraulic computations of STEP 7 to find the A variety of solutions to the basic
design flood flow rate at various locations in problems - how can flow peaks be reduced? how
developed catchments. These should be can flow peaks be delayed? - is avai lable to
computed using the principles set out in the designer. These fall into three broad
Chapters 4, 5 and 6 of the Handbook. categori es:

Alternatively, an approximation for these flow retention measures


flows may be calculated by simple proportion
using information from Tables 9.1A and 9.2. flow detention measures, and
Flows at all node sections (Figs. 9.2 and 9.3)
can be computed in the same way catchment flow retardation measures
floodway discharges (approximate) are
calculated in Tables 9.3 and 9.4. A discussion of these topics and a review of
their role in urban storm runoff management is
Where flow at a location other than a node included in Chapter 3.
section is required, for example, the flow
moving west towards node point M.5 in Fig.
9.4, then the following procedure may be used: 9.4 CONCLUDING COMMENTS AND SUMMARY
flood path description single-channel, Validity of the procedure
7.5 carriageway longitudinal slope, S
0.02 0 The des i gn procedure descri bed in Chapters 8
and 9 incorporates some simpl ifications which
upstream contributing area 1.40 ha may attract criticism on the grounds of their
violating recognised hydrological pr i nciples.
upstream contributing (CA) 0.81 ha Most significant among these is the use of a
'blanket' design storm duration to arrive at a
capacity flow, Q , for flood path first approximation major drainage system.
780 Lis (from Ta51e 9.1A) The same Simplification is also used in
revision calculations , where these are needed,
tributary (impervious) area for flood path in catchments (STEP 6) and in sub-areas (STEP
: 3.44 ha 7 , Section 9.2).
required design discharge (approximate)
Strict adherence to the conventional
0.81 Rational Method (see Chapter 4 ) requires that
- - x 780 = 184 LIs (9.11) a series of design storms be applied at
3.44 successi ve node sections down the rnai n
Values computed by this method tend to drai nage path commenci ng at the hi ghest. At
undere st i ma te requ ired flows by about 10 per each node a design storm of duration equal to
cent. contri buting catchment travel time should be

ARRB SR 34,1986 71
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

used to fix average storm intensi t y and to SUI""ary


compute design flood magnitude at that
location. A 'broad brush' procedure for desi~nin~ ma j or
stormwater d rainage sys te ms f or small urban
catchme nts has been described. Th e resulting
Such an analysis leads to stormwater node s y stem sus eon 1y the r 0 a d way r e s e r v e san d
section flows higher than those gi ven by the floodway easements of the urban landscape to
'blanket' design storm procedure. Computed c ontain runoff resulting from major storms up
disparity between the values is greatest in to and including that having a design average
the uppermost sub-areas of each catchment recurrence interval of 100-years (approxi-
tapering t o insignificant near its flood ma t ely ) . The procedure t akes account of flow
disposal point. conveyed in underground pipes of minor system
network s and includes an ar bitrary, optional
allowance for part-malfunction of the minor
A suspicion that the Handbook approach may system network (50 per cent bloc kage ) . Design
the re fore d i sad vantage occupants of premi ses f o r zero blockage follows the same procedure
in the upper sub-areas of catchments therefore but employs different values for gap flow,
needs to be explor ed. Q9ilP' design ARI adopt e d frnm Tables 5.2A
and / or 5. 2B.
Reference to such sub-areas in the Case 1
and Case 2 catchments (Tables 9.3 and 9.4) Th e procedure enable s trial flood escape
reveals flood escape path capacities , net wor ks to be raQidly asse ssed and focuses on
represented by tributary (impervious) areas, those s e gments of the floodpath which require
whi c h are well in excess of demand (see Column particular attention e.g. sp e cial hydraulic
10 in Tables 9.3 and 9.4). Strict hydro- design, building restric t ions, road layout
logical analysis requlrlng significantly modifi c ations, e t c.
increased manual or computing effort would
undoubtedly reduce this gap. Nevertheless, The procedure assumes that, in general.
and as a general rule, major system surcharge ke r bside flow depths up to 0.20 m i.e. 0.050 m
in an upper catchment sub-area is unl ikely above kerb, can be tolerated and incorporates
where the tributary (impervious) area of its a floodpath ma ximum depth/velocity constraint
fl ood path is greater than twi ce the which ensures th e safety of pedestrian and
equivalent impervious area being served. wh eeled traffic during major flood events.

ARRB SR 34, 1986


10
The minor drainage system -
design procedure outline

10.1 INTROOUCTION Design Procedure - Phase


The primary data used in the design of an N-
years ARI mi nor stornwater drai nage system
There are important procedural differences involve three aspects of definition:-
which distinguish the approach used in the
two previous chapters on major system plann- a) catchment definition
ing and that presented here in connection with b) design guidelines for surface-moving
the design of minor drainage systems. The fl ow management
planning procedure described previously is c) design guidelines for underground-
essentially a 'broad brush' operation con- moving flow management.
cerned with the mai ntenance of order in the
face of potentially devastating flood flows. The first of these calls for information
Great precision in predicting flow behaviour on the physical nature and properties of the
in such circumstances is neither possible nor catchment, including, in particular, the lo-
warranted. The aim of the major system plan- cation of existing underground services. It
ner is to provide a scheme which, given the is similar to, though more detailed than, that
great unpredictability of rare storm events, required in STEP 1 of the major system plann-
should operate at least 'satisfactorily'. ing/design process.
The second aspect of definition, that
The minor system, on the other hand, is relating to surface-mov in g flows, arises from
expected to contain and, indeed, control a their being the most obvious manifestation of
prescribed level of flooding: its design storm runoff in a developed catchment. Crit-
therefore calls for a higher level of predict- eria arising from their impact on members of
ability than is required of the major system. the general public both as pedestrians and as
The narrower spectrum of events with which users of vehicles fall within the scope of
the designer must contend, however, - the Design Principle No. 1:-
nuisance or frequent storm - makes this task
achievable. D.P.!. A set of guidelines must be adopted
whose aim is to ensure the orderly
The procedure by which a minor system is movement of stornwater flows in the
designed may be divided into three broad surface channels of developed catch-
phases: - ment minor drainage systems.

Phase Catchment definition and A similar set of criteria must also be


design guidelines; adopted for the management of stormotater
Phase I I Flow estimation and dis- flows moving in underground networks:-
tri but i on; D.P.2. A set of guidelines must be adopted
Phase I II Surface system and under- whose aim is to ensure the orderly
ground network design. movement of flows in underground
networks of developed catchment minor
The aim of this Chapter is to state the drainage systems.
principles and briefly describe the various
steps which must be followed in the design of All aspects of flow estimation and design
an N-years average recurrence interval mi nor which follow rest on the definition and guide-
stormotater drainage system for a corrmercial, line information presented in Phase I.
i ndustri al, residential or mi xed development
sub-division. Following this outline of pro- Des i 911 Procedure - Ph.se I I
cedure, guidelines and hydrological/hydraulic
information presented in earlier chapters are With the catchment defined and design guide-
appl i ed (Chapter 11) to design, fi rstly, a lines identified, the procedure addresses the
mi nor stormwater drai nage system for part of task of preparing a valid hydrological model
a mixed development sub-area, and secondly, a which satisfactorily represents the hydrolo-
minor drainage system for Catchment M in the gical response of the catchment to storm
Fig. 9.1(a) sub-division. input.

ARRB SR 34,1986 73
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

The catchment hydrological model which ture of how and where the stormwater runoff
meets these requirements is defined in Design flows generated in a catchment are disbursed
Principle No. 3:- in either the surface drainage system or its
underground counterpart. .
D.P.3. The hydrological model which forms the
basis of all later stages in the de- Operations in the procedure outlined
sign of a minor drainage system for a above are carried out for each developed
catc hment must descri be it s compon- landscape drainage unit. These may be small
ents (ultimately developed) and yield isolated catchments (see Fig. 7.3) or compon-
a sati sfactory representati on of its ent sub-catchments of complex urban land-
runoff response to rainfall input in scapes (see Fi g. 7.4). In the 1atter case,
all desi gn storms of ARI = N-years Phase I I must inc 1ude a fi na 1 step in whi ch
and smaller. the interaction of flows moving underground
between sub-catchment disposal points towards
Design storm rainfall applied to this their (catchment) central disposal point must
model by way of an adopted rainfall/runoff also be considered.
mathematical procedure yields the required
fl ow est imate( s) at each catc hment reference Design Procedure - Phase III
point. This procedure i s defined in DeSign
Princ.iplp. Nn. 4:- Phase II encompasses the flow estimation/dis-
tribution segment of the total procedure. It
D.P.4. The rainfall / runoff mathematical mod- also includes some elements (surface-to-under-
el which should be used with the ground component selection) which, strictly,
catchmen t hydrological model must be fall into the category of 'design'. Identif-
a valid or acceptable procedure which ication of these components forms the start-
yields the greatest runoff estimate i ng poi nt for Phase I 11. Phase I I I i nvol ves
for each compo nent drai nage unit, the application of Design Principle No. 2
co ns ide red individually, for design guidelines relating to the management of
storms of ARI = N-years and sma ller. underg r ound -movin g stormwater flows to design
an 'approximate ' underground network. Approx-
Application of DeSign Principles 3 and 4 imate pipe headloss values and pit headloss
enables the designer to estimate design flows estimates are employed in the deve lopment of
re su lting fromARI = N-years storms in, first- this design which concludes with a catchme nt
ly, all primary drainage lines (see Chapter Hydraulic Grade Lin e (pit water l eve l s) being
7). With this information and the DeSign declared, satisfying N-years design ARI r e -
Principle No.1 guidelines on surface-moving quirements .
flows, it is possible to select and locate
gutter inlet and concent rated flow entry This network is combined, in each case,
structures needed to transfer surface-moving with the surface drai nage component select-
stormwater to the underground network. The ions made in Phase II to provide an approxi-
stortTlrlate r flows upon which deSigners mu st mate minor stormwater drainage system design.
base their s elections and placements are the
subject of DeSign Principle No. 5:- The fi nal segment of the procedure i n-
volves detailed modification of the approxi-
D.P.S. The components of any primary drainage mate system deSign, as required, in the light
line including its inlet(s) allowing of site constraints forced on the design by
bypass, terminal inlet, concentrated service locations, cover requirements, need
flow entries, branch and lateral un- for additional inspection pits, etc. In cer-
derground pipelines, etc., should tain cases, final deSign detailing may call
co nvey and di scharge the peak fl ow for a re-working of the Hydraulic Grade Line
generated in its catchment c rit i ca 1 computations using accurate pipe and pit head-
desig n storm having ARI = N-years. loss values: some Significant c hanges to the
Surface channel compo nent s shoul d be approximate network may ensue in these ci r-
se 1 ected in accordance with the cumstances.
guide lines of DeSign Principle No.1.

The same flow estimation concept embod-


i ed in D.P.S. is also applied in the cas e of 10.2 MINOR SYSTEM DESIG" PROCEDURE
the catchme nt or sub-catchment main drain
pipeline or 'mainline' (see Table 6 .4). It The outline of procedure which follows has
is expressed in DeSign Prin ciple No . 6: - been prepared for use in the deSign of storm-
water systems for small isolated catchments
D.P.6. The on -line compo nents of any main e.g. the L, M, Nand P catchments of Fi g.
drain pipeline, including its junc- 7.3, and for interconnected sub-cat chments of
tion pit(s), node pit(s), pipes, 1 arge catchments e.g. the drai nage units of
etc ., should convey and discharge catchments Nand Pin Fi g. 7.4. The 1atter
peak flows gene rated at successive cat egory represents, of course, the more gen-
node pits by design storms of N-years eral case.
average recurrence interval which are
c ritical in th e catchments contribut- The basic drainage unit used in the
ing to those stations. following outline is therefore referred to as
a 'sub-catchment' in the interests of gener-
The completion of Phase II of the proce- a 1 ity and interact i on between it and its
dure provides the designer with a c lear pic- fellows reviewed at the appropriate stage

74 ARRB SR 34,1 986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

(STEP 7). Where the outline is to be inter- value for N-years design ARI
preted for isolated urban catchment cases, types of 'preferred inlets' and hyd-
'sub-catchment' should be replaced by 'catch- raulic characteristics of these
ment' and all references to sub-catchment crossflow acceptable or not acceptable
interaction disregarded. at minor street intersections
pipes : concrete or FRC; normal condi-
The three phases into whi ch the mi nor tion or poor condition
system design procedur'e is divided may be
sub-divided into a set of eleven main steps. i) measure, extract or classify and record
These include STEP lOA, an optional cost/ the following for all components contri-
frequency insert, which need only be employed buting runoff to primary drainage lines:
by designers seeking comparative cost data
for networks resulting from design ARI's cov- area
ering a range of values of N (see Section land use
2.6). ' di stri buted' or 'concentrated' fl ow
entry
STEP 1: Sub-catdment defi niti on drainage line characteristics (type,
STEP 2: Design guidelines and data PHASE length, slope, etc.)
(surface-moving flows) I allowable or capacity flow at terminal
STEP 3: Design guidelines and data i nl ets.
(underground-moving flows)
Almost all of items (a) to (f) inclusive
STEP 4: Hydrological model - stage 1 relate to drainage network structure (see
STEP 5: Hydrological model - stage 2 Chapter 7). The following definitions and
STEP 6: Design flow distribution in explanations are needed in order to proceed
primary and main drainage PHASE with STEP 1:-
lines II
STEP 7: Design flow compilation - Component identification code: Node pits in
all components of sub - the mi nor drai nage system network carry the
catchment same identifiers as corresponding node sect-
ions in the major system. A supplementary
STEP 8 : Pit water levels and 'first- codi ng system is requi red to enabl e compon-
round' pipe sizes ents other than node pits to be identified.
STEP 9: H.G.L. and pi pes of approx- The system set out in Fig. 10.1 is used in the
imate network design PHASE Chapter 11 illustrative cases.
STEP 10: Approximate system design - III
ARI = N-years
(STEP IDA: Cost/frequency insert) P7N1E1Nl
STEP 11: Final design detailing P8 P12
M·3Wl
M3
M·3W2
STEP 1: Sub-catc~ent definition M2N2

This involves listing tnformation and data


I p7N1 P·7N1El
)PllNl

comprising that required to plan a major M· 2Nl


drai nage system for the sub-catchment, plus
the following : - M·2E2
M·2 P·7
a) locate sub - catchment s torllWater di sposa 1 M·2El P'7El P' 11
point and terminal node pit, if different
Si mple System Complex System
b) declare design flood level at sub-catch-
ment stormwater disposal pOint
Fig . 10.1 - Component identification code for minor
drainage systems
c) adopt a network of main drain pipeline(s)
and associ ated node pits taki ng account
of the presence of maj or s ervi ces and Commencing from any node pit on the main
other underground installations drain pipeline, subsidiary components - in-
lets, inspection pits, etc. - are numbered in
d) record gutter invert levels at roadway the cardinal directions N, S, E and W along
sections containing node pits all main and lateral pipelines. Simple sub-
catchments draw on only one or two of these
e) define sub-areas draining to identified directions, but the code is capable of exten-
node pits sion to provide systematic identification in
networks of great complexity.
f) identify primary drainage line contribut-
i ng areas and associ ated termi nal gutter 'Distributed' and 'concentrated' flow
in 1ets entries: Distributed flow originates on s ub -
catchment areas such as roadways, unchannell-
g) identify the locations of all significant ed open space areas and residential or com-
pedestrian crossings mercial subdivisions in which mmerous small
units discharge stormwater individually.
h) identify the following as matters of pol- Flows classified as concentrated come from
icy: subsidiary or allotment drains which collect

ARRB SR 34,1986 75
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

runoff from (usually) large-area compo nents, 10.1) and are adopted to ill ustrate the de-
e . g. residential sub-division, dri ve-in sign of minor drainage sy stems in Chapter 11.
ci nema, ca rpark, etc. Stormwater from sllch
a reas enters the system as concent ra ted input OUTCOMES OF STEP 3 (see Table 10.1)
to the main surface rlrainage line or is pass -
ed to the unde rgroun d network via a sump and / 1. Adopt guidelines Table 6.4 or ) TABLE 3
or junction pit. similar )
Allowable or ca pacity flow at a terminal 2. Reference: Sections 6. 4 - 6.8 inclusive.
gutte r inlet can only be found aft e r su rface -
movi ng fl ow ma nag ement gu i de 1i nes have been Adoption of these guidelines, taken with
adopted in STE P 2. This item re la tes to the the data base compiled in STEP 1, completes
hydraulic characteri stics of the catc hment Phase I and provides the foundation for all
roads and streets [item (e), STEP 1, Secti on subsequent stages of the desi gn procedure.
8 . 2J and preferred inlets [i tem (h) aboveJ.
STEPS 4 & 5: Hydrological Models -
OUTCOMES OF STEP 1 (see Table 10.1) Stages 1 and 2
1. Contour map of sUb-catchment,~ By means of the procedure and guidelines re-
boundaries. node pits, FIGURE lA viewed in Phase I, it is possible to convert
terminal gutter inlets, etc. , real-world sub-catchments into mathematical
representations or 'hydrological models'
2. Sub-catchment underground whi ch can be used to yield design flow esti-
network (Stage 1) gutter mates and flow distributions in all drainage
inlets, dimensions, etc. FIGURE 18 path components. Th is i nvo 1ves the app 1 i ca-
tion of Design Principles 3 and 4 (see Sec-
3. Table of sub-catchment TABLE 1 t i on 10.1).
properties
It is assumed in the i nit i a 1 sub-catch-
4. Reference: Chapter 7 and Sections 2.6, ment model (Hydrological Model - Stage 1)
6.1, 6.2, 6.4. that design flows generated in all primary
(surface) drainag e lines fall below the lim-
its set by Guidelines 1, 2 and 4 of Table
STEP 2: Design guidelines and data (surface- 6.3. These are:-
lIIovi ng flows)
a) design flows at terminal gutter inlets
A set of guidelines and associated hydraulic ilrp Ip<;<; th;ln 95 per cent capture approach
information and data must be -adopted for the flow of the preferred inlet AND have flow
management of runoff movi ng in the surface spread less than the adopted limit
channels of minor stormwater drainage systems. (Guidel ine 1)
Listing of these guidelines is required b) design flows at all significant pedestrian
under Design Principle No.1 (Section 10.1 ) . crossings have flow spread less than the
A typical set of guidelines and other related adopted limit (Guideline 2)
information are presented in Section 6.3:
the guidelines playa major role in Phase II c) design flows at all concentrated flow en-
of the design procedure. try poi nts are less than the adopted limit
The Table 6.3 Guidelines and associated (Gu ide 1i ne 4).
data are adopted in the case study examples
of the design procedure (see Chapter 11). Primary drai nage lines which are shown to
conform to this assumed behaviour are called
OUTCOMES OF STEP 2 (see Table 10.1) DETERMINATE drainage lines. Those which fail
one or more of the guidelines or which include
1. Adopt guidelines Table 6 . 3 or ) TABLE 2 significant pedestrian crossings are termed
similar ) INDETERMINATE lines. Testing of the Stage 1
model (Fig. 4A, see Outcomes below) to deter-
2. Reference: Section 6.1 - 6.3 inclusive. mine the classification of each primary drain-
age line is carried out in STEP 4 and present-
ed in Table 4 (see Outcomes below): the tasks
i nvol ved are, for each primary drai nage 1i ne
STEP 3: Design guidelines and data and concentrated flow entry:-
(underground-lIIOying flows)
1) compute design flow (N-years design ARI),
A set of guidelines and associated hydraulic and,
information and data must be adopted for the
management of runoff moving in the under- 2) compare design flow with guideline
ground pipe networks of minor stormwater 1imit(s).
drainage systems. A typical set of guidelines
and other related information are presented Where a drainage line includes one or
in Section 6.5: they playa major role in more concentrated entries, the component flow
Phase III of the design procedure. from each is determined and compared with the
Guideline 4 limit. Guideline 4 violations
The guidelines referred to here are re- lead immediately to change in the Stage 1
quired under Design Principle No.2 (Section network layout (Fi gu re 1B).

76 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Sizes and locations of gutter inlets of to the selection and design of primary drain-
DETERMINATE drainage lines can be declared at age line component s as required by DeSign
this point. Principle No.5 (see Section 10.1).
Those dra i nage 1 i nes found to be I NDE- Flows conveyed by the main pipeline, on
TERMINATE are modified by the addition of the other hand, arise from design storms which
in-path gutter inlets or other means to en- are c ritical in collections of primary drain-
able them to satisfactorily convey and dis- age areas, the aggregate fl ows enteri ng the
charge their design flows without violating mainline at or in the vicinities of its node
Guidelines 1 - 4 inclusive. The process by pits: the catchment area contri buti ng to
which the sizes and locations of additional successive node pits increases with distance
inlets etc. are fixed is graphical and car- down the main drain. Flows determined from
ried out in Fig. 4B (see Outcomes below). these collections of primary drainage areas
Such additions also affect change in the form the basis for the selection and deSign
Stage 1 network layout. of main drain components as required by De-
sign Principle No. 6 (see Section 10.1).
In STEP 5 the modified hydrological model
is presented in its final form, Hydrological To determine these design flows (ARI =
Model - Stage 2. This model is more complex, N-years) requires a set of computations simi-
typically, than its predecessor, contains more lar to those of Table 4 (STEP 4) but reflect-
i nformat i on about the mi nor system d ra i nage ing the collective nature of the contributing
network and has proven ability to satifactor- catchment. Execution of these calculations
ily model design flows (N-years ARI) in all requires the Stage 2 hydrological model to be
primary drainage paths within the constraints interpreted as a system of catchment aggregat-
imposed by Guidelines 1 - 4 (Table 6.3) in- ions (see Fig. 6B, Outcomes below). The flow
clusive. This model forms the basis for all computations are carried out in Table 6 and
subsequent flow estimation computations and the results presented in Fig. 6C (see Out-
is presented in Fig. 5 (see Outcomes below). comes below).
OUTCOMES OF STEPS 4 AND 5 (see Table 10.1) OUTCOMES OF STEP 6 (see Table 10.1)
1. Stage 1 hydrological model FIGURE 4A Primary drainage line flow

l
1.
distributions (design ARI = FIGURE 6A
2. Tabular computation of primary N-yea rs)
drainage line design flows,

~
comparisons, etc. Sizes and TABLE 4 2. Stage 2 hydrological model FIGURE 6B
locations of gutter inlets 'collective' i nterpretat i on
in DETERMINATE drainage Ijnes
drain pipeline design flows ~
3. Tabular computation of main TABLE 6
3. Graphical determination of
gutter inlet positions, etc., FIGURE Main drain pipeline flow

l
4.
in INDETERMINATE drainage 4B distribution (design ARI = FIGURE 6C
1i nes N- years)
4. Stage 2 hydrological model in- 5. Reference: Information transferred from
cluding information on gutter FIGURE the outcomes of STEPS 4 and 5.
inlet locations, types, sizes, 5
concentrated flow entries,etc.
STEP 7: Design flow compilation - all
5. Reference: Chapter 4 and Sections 5.2, components of sub-catc~nt
5.3, 5.5, 5.6, 6.3.
Data and information extracted from Fi gs 6A
and 6C enable the flow distribution compila-
STEP 6: Design flow distribution in pri.ary tion sought in STEP 7 to be determined. The
and .ain drainage lines compilation presents in graphical form the
magnitude of the greater design flow, where
The tasks executed in STEPS 4 and 5 to derive there is choice (Fig. 6A and Fig. 6C values
a valid hydrological model for a given sub- compared), which can occur in each component
catchment lead to design flows being declared surface or underground flow path of a sub-
in all segments of its primary drainage lines. catchment, under design ARI = N-years condit-
These involve both surface and underground ions. The compilation is presented in Fig. 7
flow paths, the latter being introduced as a (see Outcomes below).
consequence of the fai lure of some primary
drainage lines - investigated in STEP 4 as Where the deSign of a mi nor drainage
wholly surface flow conveyors - to meet adop- system for a comp 1ex urban 1andscape of the
ted guideline limits. The primary drainage type illustrated in Fig. 7.4 is required, an
line design flows (ARI = N-years) are present- additional task must be performed. This in-
ed in Figure 6A (see Outcomes below). volves the computation of flows moving under-
ground between sub-catchment di sposal poi nts
Emphasis in the procedure from STEP 3 to towards their (catchment) central disposal
this point is clearly on design flows generat- point (see Design Procedure - Phase II above).
ed in primary drainage lines by design storms The outcomes of these computations are presen-
which are critical in their individual catch- ted in Figs 7A, 7B, etc. (see Outcomes
ment areas. Flows determined in this way lead below).

ARRB SR 34, 1986 77


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

l
OUTCOMES OF STEP 7 (see Table 10.1) 2. First-round pipe sizes are
selected for all lateral and TABLE 8/9
1. Design flow distribution main drain components
compilation for sub-catchment FIGURE 7
(ARI = N-years) 3. Reference: Sections 6.4 - 6.6 inclusive.

2. Design flow distribution FIGURES


compilation for other sub- 7A, 7B, STEP 9: H.G.l. and pipes of approxi.ate
catchments (ARI = N-years) etc. netlIOrk desi gn
N-years)
The tasks of reviewing the first-round selec-
3. Des i gn f1 ows between ter- FIGURES ted pipes and making alterations where neces-
minal node pits of parallel 7A, 7B, sary in the light of Hydraulic Grade line
sub-catchments etc. analysis, is conducted in STEP 9 as a combin-
ed exerci see It is cOlTl11enced at the down-
4. Reference: I nformat i on trans ferred from stream extremity of the sub-catchment and its
the outcomes of STEP 6. main calculations are reported in Table 8/9
(see Outcomes below).
The declaration of these f1 ow compi lations
completes Phase II of the minor system design The tabu1 ar procedure includes two Hyd-
procedure and provides the basis for the raulic Grade line tests, one designed to
underground network design steps and final maintain H.G.l. below assigned pit water
des i gn detailing of Phase III. level (AWL), the other aimed at keeping pit
floor level above (AWL - 2.5 Do). The first
of these a ims can be ach i eved, generally, by
STEP 8: Pit water levels and first-round pipe appropriate pipe diameter selection. The
sizes second can be achieved in the majority of
cases but sometimes fails at locations where
Des i gn of the underground network commences hi gh discharges pass through mUlti-pipe junc-
with the setting of water levels called tion pits or where severe direction change is
'ass i gned water levels' (AWL's) in all junc- forced upon such flows.
tion pits - with or without gutter i nlets -
located on sub-catchment lateral and main In practice, Guidelines 7 and 8 (Table
pi pelines. AWL's are set first along 1ate~al 6.4) often limit options and give rise ' to
pi pelines and ma i n pipeline branches begln- situations where H.G.l. falls significantly
ning at their upstream extremities and then below pipe obvert. In such cases under-
along main pipeline trunks commen cing from ground-moving flows take the part-full or
their discharge points (see Guideline 6, open-channe 1 form and norma 1 p ressu re pi pe-
Table 6.4). line head10ss and pit head10ss (water level)
values cannot be validly applied. A design
In setting pit water levels the designer approach to meet these situations is offered
should observe the requ i rements of Guidel i nes in Table 6.5.
4 and 5 (Table 6.4). EXdlll!lles of such situations occur most
frequently in the upper extremities of moder-
The layout of Table 8/9 (see Outcomes ate and steep grade catchment networks, but
below) enables these opening tasks of STEP 8 they can occur in valley bottoms where there
to be accomplished i n a rapid and orderly is a local increase in terrain slope for one
fashion. reach of pipeline. These are the more serious
cases for the designer since they are likely
These tasks are followed by 'first- to be preceded and followed by reaches which
round' pipe size selection for all components behave as normal pressure pipelines.
of lateral and main drain pipelines. Sizes
are fixed according to Minimum Grade practice The two possible outcomes reviewed here
(see Sections 6.4 and 6.6) using simple - junction pit outflow full or part-full -
cha rts of the type presented in Fi gs 6.9 and lead to different algorithms for fix i ng pipe
6. 10. Pit head10ss is ignored in this pro- inverts and, hence, mainl i ne junct ion pit
cess. Design flows are obtained from the floor levels [see eqns (6.19) and (6.21)].
outcome of STEP 7 (Figs 7, 7A, 7B, etc.). The computations which arise as a co nsequence
of these outcomes are entered in the Remarks
Pri ority shou 1d be observed i n se 1ect- col um n of Table 8/9 (see Outcomes below).
ing sizes for pipe components: lateral pipe-
line components should be selected before Where underground networks are to be de-
pipes of the ma i n drain (see Guideline 8, Signed for catchments cOl1l>rising a number of
Table 6.4). This task is performed using sub-catchments (see Fig. 7.4), then a set of
Table 8/9 which has been designed to facili- tab l es similar to Table 8/9 , one for each
tate the first-round pipe selection procedure. sub- catchment, must be prepared. H.G.l. and
diameters for pipes linking sub-catchment
OUTCOMES OF STEP 8 (see Table 10.1) terminal node pits must al so be determined.

1. Junction pit water levels OUTCOMES OF STEP 9 (see Table 10. 1)


(AWL's) are assigned along
all lateral and main drain TABLE 8/9 1. Hydraulic Grade Line and
pipelines pipe sizes of app roxi mate

78 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

under ground network design ) TA BLE OUTCOMES OF STEP 10 (see Table 10.1)
for s ub-catchment ) 8/ 9
(ARI = N-years) ) l. Schematic representation of )
sub- catchment appro ximate ) FIGURE
2. Junct i on pit outflow pipe ) mi nor storllwater drai nage ) 10
maximum invert levels ) TABLE system for design ARI = N-years)
(appro ximat e network design) ) 8/9
( ARI = N-years) ) 2. Schematic representations of )
parallel sub-catchment approx- ) FIGURES
3. H.G.l. and pipe size s for imate minor system designs ) 10A,10B,
appro ximate underground net - TABLE S (ARI = N-years) including pipes) etc.
work de si gns for other s ub- 8/9A, linking their terminal node )
catchment s (ARI = N-years) 8/9B , pits )
and pipes linking their etc .
terminal node pits 3. Reference: Outcomes of STEPS 5 and 9.

4. Reference : Sections 6.4, 6.5, 6.7, 6. 8.


STEP lOA: Cost/frequency insert
The question of what ARI's should be applied
STEP 10: Approximate syst~ design - in the design of minor stormwater drainage
ARI = N- years systems is revi ewed in Sect ion 2.6. Des i gn
ARI tends to be fi xed by local government
The first task in STEP 10 is t o extract in- policy or the recommendation of a funding
formation on lateral and main pipeline adopted authority or by application of guideline/
pipe diameters (Table 8/9) and present these suggestions such as those listed in Table
on a St age 2 hydrologi cal model network lay- 2. 3.
out. Oiameters of the remaining pipes
cross-connections from gutter and 'sag' in- Use of 'policy' is appropriate provid-
lets, etc., to the lateral and main pipelines ed it is soundly based on assessment of sample
- are fi xed by reference to Guideline 10 developments covering the range of likely land
(Table 6. 4) using design flow information for uses. One item of economic evaluation which
these components gathered from Fig. 7. shoul d be part of any such enqui ry is cost/
frequency analysis.
These data are then collated with infor-
mation on surface drainage comp onents declar- The first task in conducting a cost/fre-
ed in STEP 5 - gutter and 'sag' inlet locat- quency analysis is to assign a range of val-
ions, types, sizes, etc. - to produce an ues to the design ARI parameter 'N'. Typical
appro ximate design for the sub-c atchment values used for N in residential catchments
mi nor d ra i nage system. The des i gn is that are N = 0,1,2,5 and 10-years; values for in-
for ARI = N-years and is presented in schema- dustrial/commercial developments are N = 0,
tic f orm showing:- 2, 5, 10 and 20-years.

a) gutter and ' sag' inlet pits With these values assigned, the proced-
- locations, types, sizes ure described in STEPS 1 - 10 incluSive, must
be carri ed out for each nomi nated non-ze ro
b) combined inlet/ junction pits value of N commencing with the greatest.
locations, types, sizes, pipe This is less repetitive than it may appear
entries and exits since STEPS 1 - 5 inclusive are common to all
designs for a particular sample area.
c) junction and inspection pit s
- locations, pipe entries and e xits The design resulting from the 'O-year'
case is the hypothetical layout of inlets,
d) concent rated fl ow ent ry poi nt s underground pipes and junction pits which
- 1ocat ions satisfied the minimum requirements of the
guidelines adopted in STEPS 2 and 3. It
e) pipe components (all pipes) realises the Stage 1 hydrological model (Fig.
- locations, types, lengths, 4A). All of its gutter inlets are minimum
diameters size, and all of its pipelines are minimum
size (Guideline 7, Table 6.4); discharges
from all concentrated flow entries are accep-
Where catchments comprl S1 ng a number of ted into thei r respective su rface drai nage
sub-cat chments are involved, then a set of lines.
appro ximate minor system designs must be pre-
pared, one for each sub-catchment. Diameters The result of these determinations is a
for pipes linking sub-catchment terminal node set of approximate minor system designs, each
pits (see STEP 9) form part of the out come of one similar in form to that presented in Fig.
STEP 10. 10. Th is const i tutes the ma in part of the
data base for the analysis.
The design is described as 'appro ximate'
on the grounds that its fi nal f orm cannot be The next tas k involves costing the set
determined until site constraints [see item of designs. The level of sophistication em-
(cl, STEP 1, Section 10.2J, and construction ployed here need not be high but should in-
requi rements have been taken into account. cl ude:-

ARRB SR 34,1986 79
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

a} costs of all drainage network ma in com- It is unusual for the Stage A design to
ponents be directly transferrable to site without
- junction pits alterations being required. These may range
- concentrated flow entries from minor changes - small differences in
- gutter inlets of all types pipe lengths and alignments whi ch have no
- pi pes appreciable effect on the design - to major
redesigns. In the latter case, significant
b} excavation and installation costs a lte rat ions to the network, e. g. rep 1acement
of a number of conventional junction pits
c} roadway reinstatement costs. with 'drop ' pits or alternative pipeline mod-
ifications (see Table 6.6) to avoid existing
The outcome of such an analysis is a set underground services, may force recalculation
of minor system network costs, e.g. of some reaches of the netwo r k. Suc h reca 1-
culation should not extend further back into
design ARI 10-years $177,500 the procedure than Table 8/9 .
design ARI 5-years $171,500
design ARI 2-years $156,000 In extreme circumstances, e.g. where pit
design ARI I-year $151,200 overflow appears to be inescapable, pipe dia-
O-year design $136,500 meter selection and Hydraulic Grade Line com-
putations may have to be repeated using more
These cost/frequency data are plotted in Fig. accurate headloss coefficients and pipe fric-
2.2 (curve I) : they apply to a typical 12 ha tion factors than employed in the procedure.
residential sample area in the Adelaide foot- Reference should be made in these circumstan-
hills, South Australia. ces to appropriate texts on hydraulics (for
pipe friction values) and to the referenced
The cost versus design ARI relationship literature on junction pit headlosses. Con-
can take many forms which differ with the type sideration should also be given to the hyd-
of development, unit cost rates used, adopted raulic modelling of particular installations,
guidelines (STEPS 2 and 3), etc. The 'double e.g. multi-pipe junction pits, whose behav-
cusp' form of curve 1 is typical of resident- iour under design flow conditions is crucial
i al catchments : the conI/ex form illustrated to the success or fail u re of a system (see
by curve 2 is obtained, typically, for indus- Table 6.6).
trial/ commercial developments. The conclus- Much of this need for redesign can be
ion whi ch may be drawn from the curve 1 re- pre-empted if thorough site survey and inves-
lationship is that design ARI = 2 - 4 years tigation is carried out as part of catchment
represents 'best value for $ spent'. rlpfinition [item (c), STEP 1J. The designer
who is aware of the locations of all major
These considerations provide designers servi ces and other underground i nsta 11 at ions
with valuable information which aids policy- wi 11 arrange his bas i c netwo rk 1ayout - Fi g.
making. They are urged, however, to resist 1B to a voi d these, and all subsequent seg-
the temptation to adopt deSign ARI's which ments of the design will reflect this know-
have been decided solely on cost considera- ledge. The alternative is a set of major
tions of the type described here. The reader computational difficulties Lu be overcome in
is referred to Chapter 2 for a wider discuss- STEP 11 or, worse still, following the dis-
ion of this subject. covery of an unexpected service line unearth-
ed by a construction crew.

OUTCOMES OF STEP 11 (see Table 10.1)


In STEP 11 the schematic representation of
the sub-catdment mi nor stomwater drai nage 1. Schematic representation of sub-}
system, collated in STEP 10, is converted to catchment final design (Stage A}} FIGURE
a set of working drawings used for construc- minor stormwater drainage system} 11
tion. The conversion is accomplished in two Design ARI = N-years }
stages:-
2. Schematic representation of par-}
allel sub-catchment final design} FIGURES
Stage A: pit floor levels according to eqns (Stage A) minor drainage systems} llA,
(6.19) and (6.21) collated from the including pipes linking their } lIB,
'Remarks' column of Table 8/9, and terminal node pits. Design } etc.
Guidelines 11 and 12 are applied to ARI = N-years }
the approximate design declared in
STEP 10. It is also appropriate 3. Construction drawings of catch- } CON-
for pi pe class and cover requi re- ment minor stormwater drainage }STRUCTION
ments (Guideline 13) to be consid- system (Stage B) for design }DRAWINGS
ered at this stage. ARI = N-years }

Stage B: site constrain t s - service locat- 4. Reference: In situations where fi nal de-
ions in particular - are applied sign calls for refinement of the pipe
to the Stage A design to produce a diameter selection procedure and the
set of working or construction H.G.L. , more precise values for pipe fric-
drawings. Some recalculation may tion factor, f, and pit headloss coeffi-
be involved. ci ents must be sought from the literature.

80 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Table 10·1: Schematic representation of the minor drainage system design


procedure
The following diagrams present in schemafic form an ordered account of the main com putati onal and graph ical components of the
minor dra inage system design procedure .
The composition of each component and its role in the procedure are described in general terms in Section 10 2.

I Phase 1- Catchment definition & design gu idelines

=~ll:[
[ '"r II
Table Guidel ines Table Guidelines
STEP -- --~ STEP 6.· 3 STEP 64

'~m
Guidelines Table Guidelines Table
1 2 1-5 3 1-1~
2 3
l- I
FIGURE 1A FIGURE 1B TABLE 1

Phase II - Flow estimation & distribution


Stage 1 Hydrological Model

~
STEP
4
, "-
"-

FIGURE 4A
II] TABLE 4
~FIGURE 4B
STEP
5
, "-
"-

FIGURE
St age 2

Hydrological Model

corresponding
sub- compilation
for
STEP STEP other


sub-catchments
6 7

I t
FIGURE 6A TABLE 6 FIGURE 6C FIGURE 7

Phase III - Surface system & underground network design

Table 8/9
iii
ii
co lu mns 1-12 T,bl" 12-24
columns /9
STEP commencing
STEP
commencing
8 top of bottom of 9
network network

~ .P ~

~~-
~
STEP
, - " STEP <11
a
W / -
10 "-
10A
"- f/ Frequency

"
FIGURE 10 FIGURE lOA

Final design I"


Stage A
~ V
Constructi on dra wings
STEP
11
, "-
I"-

f-
(Fi nal design Stage Bl

"- ~
" FIGURE 11

ARRB SR 34,1 986 81


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

82 ARRB SR 34, 1986


The minor drainage system -
case study applications

INTROOOCTION

The step-by-step procedure for designing Although design of the minor system net-
minor stormwater drainage systems for small work for Case 4 using N = 2-years would,
urhan catchments, rles c ri bed in Chapter 10, is correctly, complement the major system design
applied in Chapter 11 to two hypothetical already prepared, the present illustration
urban developments located in the Adelaide adopts N = 5-years. This level of design ARI
foothills, South Australia. is employed solely to generate a wider range
of design problems forcing solutions which
In the fi rst - Case 3 - a mi nor system demonstrate the scope of the procedure (out-
network is designed for a 6 ha part sub-area lined in Chapter 10) which would not be
catchment of mixed land use. The network revealed by a design at N = 2-years level.
design terminates at a sub-area node pit and
therefore involves no main drain pipeline Both designs - Case 3 and Case 4 - are
considerations. It may be assumed that a intended to fu lfi 1, Pri ma ri ly, a demonst ra-
major system has already been designed for tion role for the novice. This leads, in
the catchment and that, therefore, runoff places, to decisions which may be validly
from storms of AR I = 100-years or 1ess wi 11 questioned by seasoned designers. Discussion
not result in indoor damage. Design ARI used of such poi nts provi des opportuni ty for one
for the minor system is N = 2-years. of the most important benefits likely to flow
The second illustrative design - Case 4 - from the Handbook, the transfer of knowledge,
f ocuses on Catchment, M, a 12 ha portion of skill and experience between the generations
the 38 ha residential sub-division featured in of designers.
Fi g. 7.3. The minor system network for this
catchment includes a branching main drain Each design is presented as a set of
pi peline and four lateral pipelines. A major figures and tables corresponding to those of
system design (ARI = 100-years) is presented Table 10.1 and supported, generally, by add-
for the same catchment in Chapter 9 (Case 1) itional notes. Readers are advised to con-
where a mi nor system desi gn AR I of N = 2-yea rs sult Table 10.1 frequently in their study of
was assumed. This led to a 'gap flow' design the Chapter 11 designs as well as appropriate
ARI of M = 50-years for the surface-moving sections of Chapter 10 when the need tor
system. further explanation arises.

CASE3 : STEP 1, FIGURE1A


boundary of northern primary
Node X~ '--_ _ _ _ _ _-+-_d_ra_in_ag_e_a_re_a_ _ _ _ _-'

l Residential
(outside catchment)

Node Xk3 I Res identia l


in< R.l.10~ 10-_1_5 r_e_sJ_h_a.

I f I'l-- . -7m----t------+-t---~
Ch-
Ch. 56 2 m.
Ch. 00 ~ gutter inl et inv. R.l. 111·20
node pit inv. R.l.100 ·10

ADDITIONAL NOTES
1. Ca tchm ent Location , Ad ela ide foothilis, South Australia Isee Fig.5.21 ; Raintall chart Fig.5.1
2. Roads : 20m . roadwa y reserves,10m dual ch anne l carri ageway. kerb .and gutter,
concrete width=375 mm ; Za=8, pavement,hotmix ; cross slope,Zb=40.
hydraulics, Fig.6·3I1ext)
3. Storm wa ter Disposal, XA-4 - XA·3- XA-2-XA-1- X·0 Imainlin el
design flood level at XA- 3, R.L. 99'85
4. Policy Items : adopt design ARI::2 years for minor system
" preferred in let", side entry inlets 1m & 2m wi th and without deflectors
hydraulics, Fig. 6.71 text)
pipes : concr ete pipes throughout; normal condition
CATCHMENT AND BASIC DESIGN DATA

ARRB SR 34,1986 83
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 3 : STEP 1, FIGURE 1 B


concentrated entry

~I ~I
(from carpark)

11
t
termjnal XA ·3E1R

I
t
gutter inlet R.L.10010

1It------f
L ker b line

lr ~ node
XA-3
RL 100.00 XA-3E1
!2 'Om
CP

~t 70m I 180m

XA3E1L kerb line

:I
RL.IOO ·)O
-e
~

~I ~I I. 200. .1
NOTE ' Pipe location fixed by Guideline 1, Table 6·4 (major roads)

FIGURE 1B ' TERMINAL INLETS AND BASIC UNDERGROUND NETWORK LAYOUT

CASE3 : STEP 1, TABLE 1

Z
o DRAINAGE LINE CONVEYING FLOW
5<n
«1 a:: TO TERMINAL INLET
l-

I-
ii: .....
Z ..... I- z: a:: ci
u.J o a::
..... --'
« -a « I - I- -s' ~
E
I
o
Z
I-
Z > . I-
z
a w !;;: I-
ZVl
0- ;: 01 ., .,
~
",-
>- ., :.--'
I-
w « z: --' z: t:l w z: w D 01 '"
~.,
C
~~
'"
c:~ '" 0.. ~r-.,
Z
..... I-
« u.J ~ - 0: u.J
z:
I-
el.
0 ..... -
--' w u.
u.J
a::--, u.a:: C '"
., ., .,-
:. 0
a::
-2~~.,
0-
E a:: a 0«;;; 0« 00
E co'" >-c
:=:.=
w , >
- Vl.,o..E.-'" .-'"~ '"'"'
--
>- E
'"Vl
u.J --'
I
<f- I- u.J el. w a::u. Vl «~ u.JU :.;:.
u _
C
u ., REMARKS
w
I-
,« ,
<n
=>
<n
=>
'"
I-
,.,
Z
I-
=>
>
u.J
E
,a , .....
,.,
Da::«
>-=>--,
u.J=>
" '0
el.z
>-0 o
E
' ,:",
., ., o ~ ~

'"
0
~
"'"0
0.. .-

--' T V'lil 4 •• 1 I- ' , 1---' . ~---1 V) ~ ,_, II '" :J


wt:l
'" Vl

4 6 7 8 9 10 11 12 13 14 15 16
x A ·3 node 1100·00
pavee
E1 R 1100·10 I road 1 st Qradel 0·49 I 0 680 I 13-5
residentiall15 res/ ha. 1 1·00 I 0 I 200 I 4·0

t------jt-----t-----t---+--I---r:~=_i~~~+_-=-=--.J_=--j._=.=-=--I..___:~ > 5551 002 I 40


75

park I pervious I 150 I 0 I 457 I 9' 0


E1L 110010 I road 1 1S~agV~el 0441 0 I 56 2 1 11·0 I 555 I 002 I 40 75

identification-see note 1 Figure 1A and Section 5·6 see see see note 4 see Figure1A see
note 2 note 3 note 5 note 6

ADDITIONAL NOTES
l.Identification of primary drainage area terminal gutter inlets X A·3E1R and XA3E1L applies code described
in STEP1, Section 10·2 ;'R" and "L"signify dghj or left looking in directi on of flow.
2. Area or equivalent area : measured from catchment pla n, factor of 0·75 used to convert roadway res er ve into
road equ ivalent paved area .
3. Concentrated ," c;'or distributed ,"O '; contribution : all carpark run off co nsidered co ncentrated at drain discharge
point ; factory roo f stormwater fed to dra i nage l i ne from many outl ets, hence "dist r i buted "
4. 0ra inage line total length and fall : drainage line length conveying run off from mos t re mote element of
component; "fall "o f drainage line over thi s l ength .
5. Effect iv e length of dra i nage line, Leff : length over whi ch the bulk of co n t ribution enter s dr ainage line ;
con t ribution from upper 118 m. of road component terminat ing at XA· 3E1R is s ma ll , hence effective length
is 562m-7m=555m.
6. Capac i ty fl ow, Gu i deline 1 (Tab le 6' 3, te xfloap pr oach flow for 95% ca pture (la rgest preferred inle t ) or
2·5m spread , which ever is lesser ( Figure 6-7. t ext)

84 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 3: CASE 3: CASE 3: STEP 4/ FIGURE 4A


STEP 2; STEP 3/ Stage 1 Hydrological Model
r--

TABLE 2. TABLE 3. '"


..c
""
""
~
road : 0·49 ha
residential : 1·00 ha t:
Table 6· 3, text Table 6' 4, text factory roof : 0·64 ha '"<-Cl.

Guidelines Guidelines I XA3E1R


park : 1·50ha '"
u
I--
1 - 5 1 - 13 .~ ~------------ C
and and 1:1 200m CP
Sect ion 6· 3, text Se ction 6'5, text Note : In this model, all
XA·3 ~ XA·3E1 runoff is considered to
pass to terminal

TABLE 2 TABLE 3 c:
I D
gutter inlets
XA ·3E1R and XA ' 3E1L.

~I XA'3E1L road : 0· 44 ha I
C" concentrated entry.
D" distributed entry.

CASE 3 : STEP 4 / FIGURE 4B


Flow accumulation in drainage line terminating at inlet XA · 3E1R

~70 qf,:75
246 2 h 07 2Ch 207
.... ....
- ....
--
Vl

--'
OJ 200
.... ....
....
.~ 1
-'
OJ
Resid ntial I
0'1
/U
c:
.iii
0 145
1

L I 101 L s concentrated
J from carpark

~ r~
~"
I
c: I
c:
....
.2
/U 100
~ I
I
Roof
:;
~- -85
94-
E OJ
<-
::J
u
u
~
70 I........ i
/U .,,, Kv<,> Park
:.
0
~o~ ..... ~ captu e~. ('oj

u: 45 0
'0 -.D

01
7m
I
I by ass 19 {
100
~ ++-.E Ponlln~

200 300
017

400
-
Chainage (metres)
~~
500
..c:
LJ

600

ADDITIONAL NOTES
1 Flow is considered to accumulate in the drainage line commencing ch 562 ("effective length" 555m l.
Road component flow represents base contribution reaching 45 LIs at ch 07 : other contributions
(e xt ract from Table 4) are added.
2 Carpark (concentrated) flow must be diverted underground requiring kerbs ide junction pit at ch 207.
Surface flow accumulated at ch 207 is 94 LIs which can be 80% captured by 2m gutter inlet
without deflectors (see Fig. 6'7, text . ). Both requirements are served by combined gutter
inlet I J.P. at ch 207.
3 Surface flow at ch 07 is 70 LIs which can be 95 % ( or better) captured by 2 m gutter inlet
without deflectors .

ARRB SR 34,1986 85
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 3: STEP 4, TABLE 4


TIME OF ENTRY COMPONENT
PRIMARY DRAINAGE COMPONENT TRAVEL CHANNEL OR U/G TOTAL
CONTRIBUTING AREA TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL
I- UNDERGROUND PIPE ENTRY POINT TIME TO
a... overland allotment guTTer or u/ground ENTRY
w
0
-+- c
natural pipe POINT
I-
z Cl z: '-- '- flow drain channel travel
---l
0 0 o n:l
UJ
L: z I- z:
<t:
LJ
-
I - ,--"0
"-
(analysis)
I Z
-0
I- - <X: __
QJ
l-
:z LJ <X: :z I0-- L:J LJ -- c
-+- E
W
w I - 0:: a... W 0 lJJ -LL ~ E "-.. C E .-
c E c E
.-c full- part-
<X:
L: LJ :z a... ---l LJ
-
QJ
I E '- .- I
<t: - <X: V1 ~~ E I · E I
:r: >- 0 0 I I ..r E I E E ..c E EI arpi1 i1rf~a
LJ
I-
<X:
I
en en
=> =>
I
0::
I-
z
(\

L
0
0::
LJ
V1
w
IY. LL V1 '+-
0
>-
0::
:::> ---l
0_
0-
<X: '--
0

n:l
..c
CJ1
C
-- QJ
Cl.
0
QJ

E
..,.
--
'
CJ1
c - E
.~
I QJ -+- I QJ
-
CJ1
c -
I

E
-+-

-
CJ1 I
c - E tc
QJ
ti
LJ

1 2 3
V1 Vl ll..I

4
LJ

5
0 :r: V1 L.J
6
min. - VI -+-
7
QJ .
- QJ fU ·
'+- -+-
-
- QJ

8 9 10 11 12 13 14 15 16 17 18 19 20
'+-
--
n:l .- QJ n:l .-
- '+- -+- min. min.
21
pav ea sec -
x A .3 EIR ca I"park olld arade - 70 .03 5 200 1.' 4 - - - 200 4 3 12 12
10 m road pa ved - 8 .02 2 - - - 673 13l 6 - - - 8 9
first arade
residential 15 res/ha 5 nomi al 15 - - - 200 4 3 - - - 18 8
factory roof Raved
fi rs t grade 10 - - - - - - 400 8 4 - - - 14 14
pa rk pervious - 140 .0 35 - - - 450 9 5 - - - 40 14 ~
CRITICAL STORM DURATION 40 147
ElL 10 m road ~l~~1 orade - 8 .0, 2 - - - 563 11 5 - - - 7 7

~--------v- ______ ~A~ __~___________

Identification see Note 1 Data from Figure 1A, Table 1, and see Note 3
ex. columns Section 5'5, text;see Note 2
1-4, Table 1

ADDI TIONAL NOTES


1. Data for co l umns 5 and 6 are transferred directl y fro m co l umns 6 and 7 of Tabl e 1.
Components of mu l ti -component drain age lines may be li sted in any order except for
pervious components whic h should be listed l ast.
2. Th e decisio n to di scharge a concentrated flow, e . g. that from th e carpark in Case 3,
directly underground cannot, strictl y , be made until the result of the col umn 31
compariso n is known . The entries in co l umns 17, 18 and 19 above should therefore
appea r , more correct ly, in co l umns 14, 15 and 16 respectively pending this outcome.
Component tota l trave l time (col umns 20 and 21) is the same for either listing.
With experience , des i gners wil l freque nt l y be abl e to cor rectl y prej udge the
co l umn 31 result and may use colu mns 17, 18 and 19 as i n th e above illu stratio n.
3. Total travel time: two travel times corresponding to the ' F' and 'P' co nd itions
of Fi g. 4.7, text, are shown for eac h component . Where components are paved , both
times are the same. The value of ti shown for pervious components can only be
fi xed after all other ti values have been found: i t i s set equal to the greatest
of these. Two criti ca l s torm durations are shOlvn, each equal to t he greatest
1isted valu e .
4. Component (CA ) : va lue s in columns 26 and 27 are derived, generally, from col umns
24 and 25. The entry for pervious components in column 27 is given by :
t.
~ X CpAD (see Section 4. 5, text )
c .
5. Component flows, columns 29 and 30, are derived from co lumns 22/26 and 23/27
respectively inserted into Eq n. (5.4), text. This decides the full-area versus
part-area issue in each case.

86 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

FLOW ESTI MATI ON IN PRIMARY DRAINAGE LINES .: N = 2 -YEARS


-+-
RAIN FALL x PRIMARY
OJ ~
INTENSITIES Lnmm/h. ::!::: CONTRIBUTING AREA Z
--D
FOR STORM th TOTAL FLOW -l
~ VI
c AT NOMINATED REMARKS
DURATIONS WHICH 0 0"-
- -l
ARE CRITICAL -+- ENTRY POINT ::>
\.:Jt- {Gutter inlet
On = {C
Lis I E selections for
t- -
full-area part-area - --I

:3 ~ DETERMINATE
analysis analys is rn
r---~----~--~--~~ .
o::--D Ii nes included
<x: OJ
Ln for Ln for 0.. - here)
E~
N=2years N=2years Ot-
u-

~------~------~ ~------~-------~-----'r---~
CD
der ived from column c ~ see Note 4 see Notes 5 - 7 co see Note 9
E~LJ-+-
20&21andSection ~OJOJx OJ
~
5'2 text 8::OVl~ z
. roL.. _ OJ
x~OJ--D OJ
OJ ~th Vl
L..

6. Concentrated flow entri es to the surface drainage line which violate Guideline 4, Tabl e 6.3, text,
are excluded from surface drainage considerations. Note that on ly surface drainage contributing
areas and flows are i nc1urlerl in 'totals' shown in columns 26/27 and 29/30 respectively .
7. Full li st of component surface flows are needed only in cases where drainage lines prove to be
INDETERI-1INATE.
8. Comparison with guideline limits: values li sted in column 31 come fro m two sources:
o Guidel ine 4 limit, applied to concentrated flow entries
o column 15, Table 1, app li ed to total surface drainage flows
Comparison is between the adopted design flow (larger of co lumns 29 and 30) and appropriate
guideline limit. The outcome decides the issues of acceptance into the surface drainage line
or not in the case of concentrated flow entries and DETERMINANCY in other surface drainage
lines. . .

9. Remarks column is used for any relevant comment, in particular, those relating to the consequences
of the column 31 comparisons. In drainage lines which prove to be DETERMINATE, it i s possible
to immediately fix the type and size of required gutter inlet. This can be done by applying the
design flow together with data from column 13, Table 1, to Fig. 6.7, text. The result may be
shown in column 32 , 'Remarks' (see corresponding column in Case 4) .

ARRB SR 34,1986 87
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 3 : STEP 5, FIGURE 5 CASE 3: STEP 7, FIGURE 7

! 1

I
t7\ 70 75
\../ ~y pa ss\.. ,/
road :0·49ha.; factory 19
roof:0'64 ha.; re sidential: 70 176
XA3E1 If' flows : Li s
lOO ha.; park : 1-50 ha. XA· 3
XA ·3 ....-It--.,....--. .I;.:.P;..
. _ _..... 287 176 XA3E 2 176 XA· 3E3
XA3E1 XA3E2 XA·3E3

I 55
NOTE :
Fl ows presented in th is figure
same as those shown in Fig. 6A.

Note : I nspec tion pit


included,see gu idel ine -
/G) 55

3. tab l e 6'4. text . FIGURE 7: DESI GN FLOW - ALL COMPONENTS; N=2 YEAR S

Ch.207 CASE 3; STEPS 8&9, TABLE 8/9


STAGE 2 HYDROLOGICAL MODEL
next page •

CASE 3 : STEP 10 , FIGURE 10

CASE 3: STEP 6, FIGURE 6A N


u.J
(T'\

<i.
x
* E'"
Nt"--
(T'\

t1 7m 100m 100m
XA .3 E52~5.-~:;:::-"'-~~- XA.3E3

t
17\ 70 XA·3E3R 75 375 375
IP
\....J ';tpa s~ ,.J
70 19 176 Notes :
tlows : Li s E
XA ·3E1. I.P. "' C>
u
XA·.:l (T'\
1. All pipes concrete .

e
287 176 XA:'3E2 176 XA·3E3
2. 2m side - entry gutter inlet wi thout
NOTE : Strict. adherence to t he Rat ional
deflectors shown or @
I {\
55

55
Methodl see Chapter 4} requ ires that
de si gn fl ows tra m inlet XA·3E3R be
based on trave l time t o that point.
The procedu re di sregards such
considerations within primary drainage
3. Pipe diameters for cross- connec tions
found from Guide line 10, Table 6.4 ,
text ; for design flows see Figure 7.
4. Headloss, pi t water levels and
pit f loor level s for pipe marked *
areas . Rational Method the ory is
\.V applied in pipes which carry combined
require further inves t igalion .
See Guideline 10 , Table 6.4 , text .
flows to a node pit.
Hence-critical storm charac t er is tics at XA '3E1 :- FIGURE 10' APPROXIMATE NETWORK DESIGN N= 2 YEARS
northern area : duration 14 mins, L2 = 43 mm / h.
southern area : duration 7 min s, L2 = 58 mm / h.
tlow in pipe XA' 3E1- XA·3 : 170+176} Lis + ~~ x55L / s = 287L/ s CASE 3 : STEP 11, FIGURE 11
FIGURE 6A :DE SIGN FLOWS IPRIMARY DRAIN LI NE S} N= 2 YEARS XA .3E1R
pi t f loor level
RL. 99·20 XA .3E3R
2 pi t f loor lev el
R.L. 102.92

~
X A .3E2 >

E}- pit fl oor level ;


N ~ R.L.101.30 ~ ~
7m 100m 100m
CASE 3: STEP 6, FIGURE 68, TABLE 6, FIGURE 6C XA. 3 ~5~
2 5"'(
-::3=
7 5~c~la::!.ss-:y-:-II1-=:
37~5~Cil.l:
lasu..S~y:"""4Il
' Y'
XA .3E3
>- XA.3E1 pit floor level
~ ~ ~~f~~o~Olevel RL 102 .90

I ~
XA.3E1L
pit f loor level
Not es :
1. Pipe inverts at pi ts

I
R L. 99 20 coincide with pit f loor
levels .
FIG URE 68 TABLE 6 FIGURE 6C
2. Pi t floor levels fixe d by
Gu idelines 11 - 13 and
Remarks column , Table 8/9.
3. Pipe class - Guideline 13
FIGURE 11 ' APPROX IMATE NETW OR K - PI T FLOO R
LEVEL S AND PIPE CLASS ES

88 ARRB SR 34, 1986


CASE 3: STEPS 8 & 9/ TABLE 8/9 PIT WATER LEVELS , PIPE DIAMETERS & H.G.L. AN ALYSIS: N = 2 - YEARS
>- w
a. PIT WATER LEVEL TRIAL E
~
PIT - TEST 1 TEST 2 BWl REMARKS
0:
5 PIPE lOSS '"
N
AWL ,: &
>-
z
~
W
0
0

~~~
z
V1

-"
«
G'LlNE G' LlNE ASS' NO
DIAM. dl~
~
.. CASE Kw VJ
2g
? -'" hf+K W
[*] minus
BWl
hf + 1'50 0 «
0
HYDRAULIC
GRAD E
AW L " ASSIGNED I PIT) WATER LEVEL

>- i5
;:s
>: 3 «
:3
ex:
z >- ex: ~~
w>-
~ E
Z
0
4 5 WATER
lEVEL >-' ~I
000 ->
NO
N

"'" ""
0
~
Q.
LINE BWl" BOTTOM IPITI WATER l EVEL

i5
, ,
0::>
El:)~
z"O
1r5
-"
3
:t:
>-
:::l
'::: IAWLI
>-
W
'"J!". - IAWL- BWLJ IAWL - BWLI 0
0
«
~>
:>
CD 3
<D
::>
<D
::>
~~~
>:V1
OW
~ '"~ '"5
z Table
6'4
Table
6-4 RL m
Tables
6·5 & 6·6 m ""
m
Eq6'17
m m
Eq. 6·18
m m IPit W.L:s I
(Xl V1 Vl ~o
m
O'l 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
LATERAL PIPELINES (j)
X A ·3 "l" junco --i
E3
104'10 pit 103 ' 95 n.a. 103-95 RL10H5 o:::IJ
- TEST 1 O.K. for Do " 0.3 75 , fails TEST 2
s:
li }
pipe J-3 2·0 0·64

~
~ first round - 0·300 2·49 0 32 2·03 2-67 Pipe invert (upstream) fi xed by eq uation 6. 21:-
E3 to 176 100 0·02 0· 375 1·59 0·13 0·65 0·26 0·91 2 00 1· 21 0·375 max . inv. leve l. E3 "Rl 103 . 95 -{ 1.5 x . 26) - 0. 375
E2 • RL 103.18 o
water level, E3 . f ix ed at AWl. :::IJ
E2 Insp. ~
102 ·10 pi t 101 '95 103-85 101·95 R.L 101 ·95
Z
-
li }
TEST 1 O.K . (fo r Do • 0.3751, fails TEST 1

~
pipe ~ first round - 0·300 2-49 J -1 0·2 0·32 2'03 0·06 2-09
1·59 0·13 0· 66 0·03 0·69 2·01 1· 22 0·375 Pipe invert (upstream) fixed by equ ation 6.21:- ~
E2 to 176 100 0·02 0· 375
E1
max . ;nv . level , E2 = RL 101.95-(1.5 x . 03) - 0.375
• RL 101.53 I Gl
m

r
water level , E2 , fi xed at AWL.
E1 J.R with
o
100 ·10

{>
late ra ls
pi pe
El to
node
287 7 0·02 --T
99 ' 95 101-85

first
99 ·95
nd
~ 0·375
0· 450
0·525
2-60
1· 81
1'32
J-
2A/2B
0·8 0·34
0·17
0·09
0·12
0·05
0·02
0·27
0·1 4
0·07
0·39
0·19
0·09
0·10
-
-
0'81 0'525
R.L. 99 '94

li }
TESTS 1 and 1 O. K. for DQ • 0.515
Pipe invert (ups tream) f1Xed by equation 6.19:-
max. inv . level, El = RL 99.85 + 0.02 - 0.525
• Rl 99 .34
m
(j)

Gl
Z
.
water level, El, fixed by equation 6 .20 :-
II
node
100·00
mul t i -pipe
J.p. DES1IG N Ft OD ILEV EL 1
R 99 '85' B.t
I I I I I I
R.L. 9985
aWL at El • RL 99.85 + 0.09 • RL 99 .94
Z
(j)
MAIN DRAI N PIPELINES s:
~

pi t ident i ficat ion ;


. .
ex. Fig. 7
~ .
See Note 1
NIL
"---r--' . .
ex. Tables
. .~ .
derived
.
.
~
. ... . .
derived see
.
see Note 7
,
r
r
C
gutter invert 6·5.6·6
""> - ... ""'"
"'-vi
column s
"" - col umns Notes 5 & 6 :0
!~
~m

levels ex . Fig. 1A ~2! .l; 17&18 12&17 OJ


~8 ~ 0
~z ~8 ~
Z
ADD IT IONAL NOlES 4. Pi pe fri ct i on head l oss : see equati on 6.16, text, nonna 1 concrete
o
~
roughness, f = 0.019. --i
Pit water l eve l s are fixed according to the pr i ority set dow n i n
1.
Guide l ine 6 Tab l e 6 . 4, text. In pr i ori t i es 1 and 2 assig ned 5. Hydrau li c gr ade li ne is ca l cul ated f rolll co l um ns 23 and 19 (adop -
o
water l eve l' i s the LOWER of t he competing l eve l s (Gu i de li nes 4 ted va l ue) i. e . eq uation 6 . 20, text, except where TEST 2 f ai l s. I
and 5); in pri ority 3 , the HI GHER of t he competi ng . l eve l s is
assigned . Th e Ca se 3 development i nvo l ves on l y pnonty 1 pl pe
See remarks, co lumn 24. s:
m
compone nts . The Case 4 deve l opment, fo 11 owi ng, inc lu des compon- 6. H,G .L. pit water l eve l s li sted in column 23 are max i mum design Z
ents from all t hree priorities. l eve l s s ubject to, possib l y , two DOWNWARDS revis i ons: --i
(j)
2. First round pipe diameters: data from co lu mns6a ndB are app l ied a) Guide l ine 10 cas e s (cross-connections) in which Dt » Do '
to Figure 6.9 (concrete pipes) or Fi gure 6. 10 (FRC pipes) . Pipe
s i zes are set 'in directio n of flow' throughout network. Gu i de - b) Gu i deline 13 : cases where equation 6.21 has been used in
l ines 7 and B, Table 6.4 are observed here . Later tria l s are Tab l e B/9 (part - fu ll outf low from pits) and where cover
li s t ed be l ow first round diameters . requi rements detenni ne 1eve 1 of pi pe invert.
3. Velocity s hou l d be computed using area of pipe nom i na l diamete r 7. Pit f l oor l eve l s : remarks co l umn 24 i ncl udes data used i n final
(co l umn 12) . des i gn deta il i ng, STEP 11.

(Xl
CD
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4 STEP 1. FIGURE 1A


-
par k , 1' 28 ha

M .3=r~
(node pit) I
/ II-
r
I
I
-
road , 0·18 ha,

I I
So = 0·03

1-7·5m dual channel ---.J


I carr iage .... ays
:1 1
I
,
f
I----=---tl/ I ... : ~ I~ :
1 ~ ~ I ~ I
I
~
1
20 m
10 m
I ...
61 vf
I~ ,.,~
.c
I i
ttl

",0 I '"
110

~
,.,

:1~
10m dual channel "'I ~ .. : .. ~ I~ .. I is 0 7.5 m single channel carriage .... ay
carr iage .... ay in ~'I :;; ~
I ~ '" I :;; ~ I~ ~ in 16m road .... ay reserve
20m road reserve .
Pavement cross
~ I ;;:-
·· 1 ~ 'E
1 .~ ~ 1~ :: I~ ~ 1 16m . I
slope Zb = 40

_
]:


oJ
i
road , 0 ' 16h a
1: ~ f ~
ro.irQ.l~6;:-:h.,--~~
II //~
cross slope Zb = 30
M '2 ~ 1 So=0·03 M. 5 I So= 0' 02
I
LEGEND
(node pit) I 1 node pIt)
1 I I sub-area boundaries
I :;; ;' % I sho .... n - - - - -
primary drainage area
I ~o i~ II ;, ~ I ~ boundaries shown - - - - --
%1 Vl 6 ~ I ~
~ '~ ~~ / ~ 6 I 0 terminal gutter inlets
~ "'J ~ / ~~ I ~ shown .. : 0

~ ~I / .. ~ ~ I - h
I :;;I ~ / ~ ~ ~ .~ I '~ 7·5m dual cannel carriage .... ay
l!) '1 ~ / 0.6 J in 16m roadway reserve
:c ~~I i'-' / / ro.d , 024 h. I 0 08h. , I I 16 m
i7:sm1 I
r-
'l ~

r"":;
ro.d

_ /~( So = 0·005 So = , ;~ ~ c=-pe Z = 30


/ , r n ~ r1 . o·nRh~ (rn~r1 n nR h" b
M·1.,..' S = 0·005 S = 0 005 SCAL E
terminal 0 0 0 100m
node pit M·4 I I
(node pit)
ADDITIONAL ' NOTES
1. Catchment location: Adelaide foothills South Australia
(see Figure 5,2; Rainfall Chart - Figure 5.1 )
2. Contour plan of catchment - see Figure 7.3 text.
3. Roads : 16m and 20m roadway reserves
7.5m and 10 m carriage .... ays
kerb-and -gutter, concrete; .... idth = 375mm; Za = B
pavement, hotmi x; cross slopes Zb = 30 and 40
longitudinal slopes, So' are at rece iving inlets
hydraulics, Figure 6.3 text.
4. Stormwater disposal point : M.O(see Figure 7.3,text.)
design flood level at M.O, RL 100 ·00
Figure 1A: 5. Residen t ial land use areas (see section 9.1, text. )
des ign res idential dens ity, 20 res I ha .
Catchment data- stormwater passes to fronting gutters or rear of
Case 4 allotment drainage easements.
6. Policy items :
adopt design ARI = 5 years for minor system;
"preferred inlet" : side-entry inlets 1m , 2m .... ith and
without deflectors; hydraul ics, Figure 6.7, text.
pipes : FRC pipes throughout , poor condition.

90 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4 : STEP 1 , FIGURE 1B

N
M·3N1R
M·3E1

E
C>
~
Iii
.....
c
Inspection Pit OJ
"0
(see Guideline 3, Table 6·4 text) VI
OJ

r"
UJ ."0 "0<-

r
:?:
E
~ 15m ~
-'
~\\..
"'
.!: ~
..... <- <- c
~.1: c
~~\ ~ ..... OJ
OJ ~ ~. OJ >- E
M· 2N1R 13m g.3 M' SN1R 0 < - .....
c ..... 0
0 ..... 12m 0 c :::
4Sm 0 40m u OJ '"
---- -----

::.::
7m
M'2E1L
M·2E2
:z:
UJ
:?:
Sm M'S~ E
E
C> :z:
::>
<i: -' C>
~ et:
et: UJ
a.. ~
0
l- ii:

1. P. I.P.
I
(J "0

-r~ r~
:z: E
E <i: et: '" .....
<- C
V"I
~
V"I L Il) 1:: QJ
~
M·4N1, M' 4E1 ~~
100m Sm 40m 8 .....
-----
M·4 7m
Sm M·4E1L lM .4E2
E
C>
~
NOTE : Pipe location fixed by
Guidel ine 1, Table 6·4 (text)
1.p.
major and minor roads

E
C>
C> Drawing not to scale

Stormwater disposal point


M'O- Design flood level : RL 100·00

Figure 1 B : Ter minal inlets and basic underground network layout

ARRB SR 34, 1986 91


STORM DRA INAGE DESIGN IN SMALL URBAN CATC HMENTS

CASE 4: STE P 1, TAB LE 1


CATCH MENT DEFINIT IO N DATA - CASE 4
z DRAINAGE LINE CONVEY ING FLOW
;....
I-
< ::J TO TERMINAL INLET
0: W en
I- I- Z 0:: Ci:ci
... -.. -
::
Z W 0:: --'
W 0 W < ~ < 1-1- .0
~
N

.
0 I- Z I- zV> ~
> w
E
Z Z I- ~ -<::J < I-
8 0
.s::;
'"
c:
C:c >-ai ~ --'
.. .. . .. - .. . - ·w
~ '"
l- I ~
!'" > .. V> -
Z
zW w
< 0 ..J
c:r
z
W
I-
ow -
w
o::W
0>
c '"
..
~
0-
0
~

.. . .. :::.. :::.. .. .- ... '"'"' .... ..


I- Cl. Cl. --' w u.. 0 --' u..o:: 0 _>- ..
c:
0 < -V>
E < W 0:: Z
< 00 -!:
I
w
w
, 0::
'f- >-
a:
W
I- --'
0
Cl.
0::
w 0:: LL
V> «~ Wu
E ~ E_ c:
",'"

.-
:= REMARKS

- ..
W V> do:: E
I- en en l- I-
> l:
0 W
<
>-::J --'
w ::J Cl.Z O-E
o ~ ~
~ 0 a..~
< ::J ::J Z ::J W 0::0 o -
>-0 1---' ~ ::>
w V> V> W <::J --' w 0 IV> w <w I- w u.. V>_ w u W <::J
W --'

1 2 3 4 5 6 7 6 9 10 11 12 13 14 15 16
M 5 node 110·30
N1R 11065 7Sm road ls~a~~~de 0·12 D 200 4·5 200 ·03 30 65
pa vee
Nl 110·65 7·5m rOJd h I. Yld U ~ 0·19 D 290 50
}180 ·03 30 65
resi dential 20res / ha 066 D 160 4·0
E1 110·40 7·5m road ls r.ave_a"
qrade 012 D 90 2·0 see mi n i mu m trave I ti me
} 90 ·02 30 76
residential 20 res/ ha. 0·60 C 40 1-0 provisio n, sec tion 5'5, ltext }
M ·4 node 103·00
Nl 103·15 7·5m road 1 s~a~~~de 0·13 D 200 7-0
~ 185 ·03 30 65
residential 20 res/ha 0 89 D 165 6·0
pavee,
El 10303 7·5m road 1 st grade 006 D 90 OS
residential 20 res / ha. 060 C 40 0·2
~ 90 ·005 30 75 min imum travel time Iroad}

Ell 103'03 7·5m road lsa~~~e 0·06 D 90 OS 90 ·005 30 75 minimum travel time
M ·3 node 11420
N1R 114·25 10m road 1 s~a;~~e 0·07 D 70 07 70 ·01 40 70 minimum travel time
Nll 114·25 10m road lsa;~a~e 0·25 D 310 60
park
pervious 0·38 D 0
~ 60 01 40 70

pavee.
114·40 7-5m road 1 st. 0·14 4·0
El D 250
grade
park pe rvio us 1-26 D 0
~ 250 ·03 30 65

M ·2 node l OBO
pavee
N1R 107·80 10m road 1st. grade 0'15 D 200 55 200 ·04 40 65
pavee, 0·21 8·0
Nll 107-60 10 m road 1sl. gra de D 260
f.,id ~ "lid l 20 1l:!:.l lld. 0·77 D 180 5'5
~ 160 ·04 40 65

E1 10750 7-5m road 1 s~a;r~ade 0·12 D 90 2·0


residential 20 res/ha . 0·60 C 45 1·0
~ 90 03 30 65 minimum trave l time Iroad }

M 1 node 102·20
N1R 102-30 10m road ls~a;~~de 0'15 D 200 4S 200 ·02 40 76
Nll 102'30 10m road 1 S~agVr~~e 0'15 D 200 45
par k pervious 0·84 D 0
~ 200 ·02 40 76

102·25 7- 5m roa d 1 s~a;r~ede 0·15 290


~
El D 7'0
90 ·005 30 75
par k pervious 0·66 D 0
Ell 102·25 7·5m road ls ~ave_a"
. grade · 0'06 D 90 0·5 90 005 30 75 min imum travel time
M ·0 flood ~isposa point
des igr water evel R.L. 10000

CASE 4: STEP 2 , TABLE 2 CASE 4 : STEP 3, TABLE 3

Table 6' 3, text Table 6' 4, text


Guideli nes 1- 5 Gui delines 1-13
and and
Section 6'3, text Sec t ion 6· 5, t ext

TABLE 2 TABLE 3

92 ARRB SR 34,1 986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4 : STEP 4, FIGURE 4A


Road 10
IIReserve
LA - 0 LR-,o,-,ad::..:..:.;.Re-,s=-er::..:v:....:e",,
Park:038ha.
I
: 0,-2_5_h-la
Drainage Network Components
LE..G.It:ID

I 007ha. 1'13 concentrated gutter inlets ... ...... ...... ....... 0-


M3E1 o
IRoad : 0·14ha.1 contribution ..... C junction pits .. ...... .. ........... - - -
Park: 1-28ha.1 distributed combined inlet/J.P' . --O-
contri bution ...... D concentrated flow en try ..... .. .. ~
Road Res: 0 21 ha I main drain pipel ine ....~ •
"'"Ro-a-cd,----, l. P. Residential:077 hal cross connection ......... ~
Reserve ~ I=-
to .
I 015 ha.
Residential Road 1 0 o IRoad
Res: 0·19 ha. ~ .2!
o o I 0·80 ha. Reserve
0·12 ha.
Resident ia1:0'86 ha. ~~
Vl6

~~.
C MSN1 C OJ
M·2E1 4Sm. M2E2 M'SE1 40 m • c::
M·5 . - - - - { - - - - - - -, M·5E2

o IRoad Reserve : 0·12 ha.1


oIRoad Res: 0·12 hal
I.P
Inspection Pit

I.P.
IRoad Reserve : 0·06 ha.1 o IRoad Reserve
1'1 ·0 I 0 06 ha
FIGURE 4A : STAGE 1 HYDROLOGICAL MODEL

CASE 4 : STEP 4, FIGURE 4B


FLOW ACCUMULATION & CAPTURE GRAPHS FOR DRAINAGE LINES TERM INATING AT -
M' 5N1, M4N1 & M·2N1
~ Inlet ~
Inlet
M·2N1L\.
- 32 m
-t M·4N1 1
~
,t Additional Notes
1.The values 85 Lis and 79L / s are obtained from
Figure 6'7, text . They represent gutter(approach)

I I t
~-5~1~ .
Q 31I 100 .
90 93
flows which can be 80% captured in drainage
lines having 50 =0'03 &0 '04,re spectively, in their

::s
120
1--
,- .'27 m

110r-tj:~ I;::!z
~I

u-II
.IOJ
c
:.: :;
VI
'-

.~
u::
Ff-'
80

70
i"""'- ::;::85 Lis
I ........

6O!
68 Li s
..... ~
.....

I
terminal inlet vicinities(see column 13,Table 1)
2.The flow accumulation graphs for lines terminating
at M·5N1 & M·2N1L are plotted together becau se

I
'-......(
the ir effective drainage line lengths are , by
co inc idence ,both equal to 180m (see
~ 100ts::::1;:- 96i: I± SOIl I, I " ............column 12, Tab le 1)
OJ 9O~L..... I .- 40 M·4N1 Line
en ........ N...-85L/s I
(So=0 ' 03)l r---.....
~ 80 ~~ -7QLAr30~~~~-t-r~~'r- I t-II-t-t-j~~........~-
.~
'C 70 ~ I.~
I1"":::::::-- I 25
-....:::::~fttSl--'-k~+I-
""
. -r-+--+y=p-:':-: asc::-
s-\erl..,..,L-'-:
./C'!S +-+-+-+--t--t--P-..I-
I .....
-t- I
............ I I
.; 60r-r- '~ I~ - -ftt<, 4'7 (.s,-,,"+--+--
I I--I--I--I--I--I--I--t--I--I--I--I--~'t-....
f---11f---1!
~ 50 ~I u 4'7.: 0'0 .,--+-~-+--t--i'--+-~-+----'.-'---'--~--'----'-
I ~--""~
:; ~ ~ ([0""0 '.J 50 100 150 185
~ 40~~2 ~II~ .I I 'O~) ~
~
.3;i
~
30 ."
20
10 '
M·5N1 & M· 2N1L Line
17,L/s~.- bypass 16L / s
I
3. Gutter inlet selections/placements '
shown here are not necessarily " best
~ solutions ",man y sat isfactory
""'~
.....
Dra i nage l ine length (m)

~arrangements are po ssible


°0~L--'--L~~5~0-L~~-~1~00~-'---'---'-~15~0~~~180
Drainage line length fr om terminal i nlet (m)

ARRB SR 34,1986 93
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4: STEP 4, TABLE 4


TIME OF ENTRY COMPONENT
PRIMARY DRAINAGE COMPONENT TRAVEL CHANNEL OR U/G TOTAL
CONTRIBUTING AREA TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL
f- UNDERGROUND PIPE ENTRY POINT TIME TO
-
0...
overland allotment gutter or u/ground ENTRY
f- w
0
+- c natural pipe POI NT
z D Z .- flow dra in channel travel
--l '-
w 0 0 ro
« - 0 '-
(analysis)
E Z I-
z LJ f- '- U
Z I- - «
f- I
z LJ « -a z 0
- L:J
w -LJ +- c
Q)
+- +- E
w I- W 0.... W f- a LJ E '-....
.-c c E E c full- part-
.-
.-c
Q) ~ E
E « ~ z 0...
-
--l LL E .-
LJ «1 >- a a « -Vl ~£ 1 E 1 E 1
E E
1
E E area area
I
LJ
I-
«
1
eo co
~ ~
Ii:
l-
z
0...
E
a
~
LJ
Vl
w
fY
0
>-
LL
a:
~
Vl '+:-
«
u _n
0-
'- ro
-'=
-<-
0\
c
1
Q)
a..
E
1
Q)
-'=
-+'-
0\
c
E

--ro
1
1
Q)
E
- --
-'=
0\
c
1
I
Q)
-'=
-+-
0\
c --ro
I
1
Q)
E tc t ·I
- - ro .-E
--l 0
.-
LJ Vl l/) W LJ 0 I Vl LJ
min.
Q)
Vl -+-
-Q)
'+-
.-
-+- -Q)
'+- -+- -Q)
'+-
.-
-+-
min. min.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Raved -
M .5 NIR 7 . 5 m road first Qrade - - - -- - 2 200 4. 3 - - 5 5
NI 7.5 In road ditto - 2 - - -- - 290 5 4 - - - 6 6
. _----- f - - - - - - - - - - - -- - - 1- -_ . -- -- - ---- - .- -_.
res i dent i a 1 20 res/ha 5 i5 mi 5 - - - 180 4 2 - - - 17 7
~

CRITICAL STORt1 DURATION - 17 7


El 7.5 In road
vaved --
. i~SUlr:<l~ I -
I--
-'by i sp cti pn, 5 l1li r S ( ee S ct i on . 5) - -- - -- 5 5
-- ' - - -_.-
r es id e nt ia l 20 I-es/ ha 5 15 mi s 180 3 3 - - - 40 I 1 19 9
paved
M .4 NI 7.5 In road fil-s t grade - - - 2 - - - 200 7 2 - - - 5 5

residential 20 re s/ ha 5 15 mi s - - - 185 6 2 - - - 17 7
CRITICAL S TOR~l DURATION- 17 7
pavea
El 7 . 5111 road first grade ------ -- -- -- --- -- 5 , -mi s - - --- -- --- ---- -- --- f-,-
5 5
- f- - I- I - --
r es identia l 20 r es/ ha 5 15 l1li s 185 7 2 - - - 40 .2 1 18 8
n~ve?
Ell 7 .5 m r oad f irs t grade ------ ----- -- --- -- 5 l1l i s - --- - -- -- - ---- -- -- - 5 5

M .3 NIR 10 m road ditto --- --- - -- -- -- -- - -- 5 mi s - --- - - - --- --- - -- --- 5 5


i~ 11 10 m rnilrl d it to - - - 3 - - - 310 6 4 - - - 7 7
--
pa rk pe rv i ous - 11 0 2! 32 - - - - - - - - - 32 7 ~
CRITICAL STOR r~ DURATION - 32 7 J
El

NIR 10 m road
7.5 m road
park
raved
i rst~~ _

perv i ous

paved
-
-
-
110
-
2~· 32
2 -

-
-
-+ -
250
-
CRITI CAL STORMDURATION
4
-
4
-
-
-
~
-
-
-
-
-
6
32
32
6
6~
6- J

r~ .2 first Qrade - - - 3 - - - 200 5 . 5 2 - - - 5 5

NIL 10 m road ditto - - - 3 - - - 280 8 3 - - - 6 6


-- -------- --- ---- - ----
r es ide ntial 5 15 ~i n - - - 180 5.5 2 - - - 17 7
CRIT ICAL STORM DURAT ION - 17 7
p.ilved - --- -- ---
El 7.5 m road flr s t -.9rade ------ - ---- - - - -- -- 5 mi s - -- -- -- --- 5 5

residential 20 r es/ha 5 15 mi 5 180 5 2 - - - 45 1 1 18 8

M .1 NIR 10 m road ~m~ a r ade - - - 3 - - - 200 4.5 3 - - - 6 6


NIL 10 m road ditto - - - 3 - - - 200 4.5 3 - - - 6 6
f- - - - 1-
park pervious - 175 3 40 - - - - - - - - - 40 6"
CR ITICAL STORM DURATION - 40 67
El 7. 5 m road r ve u
irs t grade - - - 2 - - - 290 7 3 - - - 5 5

par k perv i ous - 175 3 40 - - - - - - - - - 40 S~


CRITICAL STORM DURAT ION - 40 57

Ell 7.5 m road ff~~~ Qrade --- --- ---- - -- -- - -- : mir s +---+----+---+-- -- 5 5

94 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

FLOW ESTIMATION IN PRIMARY DRAINAGE LINES: N = 5-YEARS


:;:'
RAIN FALL >< PRIMARY
(lJ
INTENSITIES Lnmm/ h ~
z: CONTRIBUTING AREA zw
'-0
FOR STORM If)
OMPON 0 TOTAL FLOW ---1
t- wI/)
DURATIONS WHICH c
...
0
(C A) n
=>
ro
AT NOMINATED
ENTRY POINT
-
=>
0"
---1
REMARKS
ARE CRITICAL
l:Jt- (Gutter inlet
LJ
(lJ 0::
Vl t- Qn=(CA)nLn LI
Z IL:
<t: (lJ
0 O· 36 S t- ----1 selections for
full-area part-area UJ
(lJ (analysis) LJ
_

0::
Vl
3 _ DETERMINATE
analysis analysis <t:
u...
0
".,
UJ .

UJ
0::'-0 lines included
Ln for Ln for n... Qn for Q n for <t:
n... -
(lJ

area >- here)


t- N=5 years N=5years L:~
N = 5 years N=5years o t-
Lis Li s LJ -

29 30

ARRB SR 34, 1986 95


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4 : STEP 5, FIGURE 5


lli.EJiQ
refer Case 4, Step 4, Figure 4A .

Road Reserve : 0·14ha.


Park : 1· 28 ha.
Road Res.: 0·19 ha.
Re sidential: 0·86ha
Road Res : 0·21 ha.
Residential:077ha

Residentia I
0·80 ha.

45m. M5 __---1~---'4'-"0...:.:m"-.---J M 5E2


Road Res: 0 ·12 ha.
Road Reserve :0·12 ha. Inspection
I.P Pit
r-::R-oa-d~ Road Reserve : 015 ha. M4N2 .~ ,,;
Reserve Park : 0·84 ha.
0·15 ha .
-'C..c:
0.10
"0 co
Road Reserve:0·15 ha. "Via
0.1
Park : 0·68 ha. 0::

Road Reserve :0·06 ha


FIGURE 4A STAGE 2 HYDROLOGICAL MODEL

CASE 4: STEP 6, FIGURE 6A


LEGEND
refer Case 4 , Step 4, Figure 4A
28

LP 68

60
~62 1
21 21

62 60

Pi t
All flows Li s
I. P
derived from Table 4
62
1

81 62

I. P
62+(gx 22) = 81
76
see note re combined flows in
.
M·4
]
J 11

M·O Ca se 3, Step 6, Figure 6A


FIGURE 6A : DESIGN FLOWS IN PRIMARY DRA IN AGE LINES OF CASE 4 -N = 5 YEARS

96 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4: STEP 6 - ADDITIONAL NOTES TABLE 6

The Case 4 network involves an extensive Table 6 relates to Fig. 6B in the same way
system of main and lateral pipelines. Its Table 4 relates to Fig. 4A and includes many
des i gn mus t therefore cons i der 'tota 1 catch- items transferred di rectly from the earlier
ment' aspects of flow estimation which were tabulation. With the aid of Table 6, the
avoided in designing the Case 3 network al- designer is able to execute the required
ready reviewed. These aspects find express- sub-area gathering and storm duration com-
ion in Fig. 6B, Table 6 and Fig. 6C of STEP parison processes, and consequently determine
6. design flows in each segment of the main
pipeline network. The origins of the follow-
ing notes are found in Table 6.
FIGURE 68

The interpretation of the Stage 2 Hydrologi- 1. The 'from upstream' component entered
cal Model presented in Fig. 6B shows, schema- under node pit M.4 is that cont ri buted
tically, how catchment sub-areas are gathered from its adjacent (u pstream) sub-area,
at successive node pits - commencing at the M.5. Thus, the value for (CA)s= 1.07 ha
most remote - to provide the hydrological entered in columns 28 and 29 has been
basis for flow estimation in successive rea- transferred directly from columns 30 and
ches of main drainage pipelines. Where main- 31 respectively.
1 i nes are branche d, as inCase 4, then the
two (or more) branches must be considered
separately down to their point of bifurcation. 2. Critical storm durations shown at node
pit M. 5 are:
The design flow conveyed from such a
junction must be determined for the total tc 19 mins and ti = 9 mins
catchment co ntributing to that point. Appli- (columns 22 and 23)
cation of the Two-Value Rational Method (see
Chapter 4) to determine this flow requires Because travel time between M.5 and
that critical storm durations in the contrib - M.4 is 2 minutes (see Fig. 6B), travel
uting branches be evaluated and compared. times for sub-area M.5 relative to node
Node-to-node travel times are shown in Fig. pit M.4 are 21 mi nutes and 11 mi nutes
6B to enable these durations to be determined. respectively (columns 20 and 21).

CASE 4: STEP 6, FIGURE 6B


LEGEND
refer Case 4, Step 4, Figure 4A .
Note : All main pipeline travel times are for lengths
from node to node

N I I
11'------' ~
'----------I] kf I
I
t7
6l(f
I
()+ I r('
M2E1 L - - - - i J' M5E1
~.~:--------{ 45 m ~ ___-{ 40 m.

~~ .~ ~
2 E2
.1'2 ____ M2E Ll=====M=5=::::::J
1(N) catchment.1 L J ';;; r - 5-

.~ "DO' ~ "c; ~ r-

'-----Ii ~ .,"'~f=-r--'
-----,1 ~I \
; , 0: U/)'~r-------'--------' ~1 ~ 1(E) "\ r-
"?'7(NJ- M'L- ~rY tra ve l ti me 3 mlns

node to node
-
1 ~
I
2; I J.
catchment M·4
\~
}-_4:..;:.O..::.m:.:...
. ---JM .4E2

trave I 2 mi ns.
~
....;==~'s;+....4~.~1~(El)::::::::~;;JtiT"""""f;i:fi'"HMFN"'f"":=='
... TOTAL CATCHMENT
~===:::!.-=======~
FIGURE 6B : "SUB-AREA GATHERING " SCHEMATIC HYDR OLOGIC AL MODEL

ARRB SR 34,1986 97
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

CASE 4: STEP 6, TABLE 6


TIME OF ENTRY COMPO NENT PROGRESSIVE
SUB -AREA COMPONENT . CO MPO NENT TRAVEL CHANNEL OR U/G TOTAL CRITICAL
TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL STORM
UNDERGROU ND PIPE NODE PIT TIME TO . DURATION
o overland allot ment gutter or u/ground NODE PIT IN TOTAL
-'
:z -: C flow drain natural pipe UPSTREAM
f- « ~ 0 ' ;0 (hannel travel AREA
:z :z LJ f- ~ ~~~-'~~-r~~---r-r-+--.--r-+----,-~--+----7~--~
f-
:z o « 2 'D analy si s analysis
~~-+- c
1
l:J E
w o w E cE
:z -' LJ ~ ~ ~ E ~ C E ._ .-C E tu l l- part- tull- part-
>- o a:: o
a::
«LL Vl ~ ~":::, E":::EE ..::: E E
a:: a.. LJ Vl co-+- Wi -- I I -+- I ' -+- , I area area area .area
CJ a:: « 01 _ OJ
f-
:z
L
o
Vl
>- :::>
0==
~ . ro
Olo.aJ
~
CT\ _ O J
~ ro g'~E C - t( ti t( t i
ro E
W -' 0 E E
w LJ CJ :r: Vl aJ ro . _ QJ
LJ min. V) +- __ ....... +- - '+- +- - ..... +- min. min. min. min .
1 2 3 4 5 6 7
8 9 10 11 12 13 14 15 16 17 18 19 23 20 21 22
BRANCII IU -, 1-1.4 ' 11.1 same values as listed Table 4 but
b-.-.--r--~----------~~r-------I--~ Hr~~1-~--r_--~----~
M .5 NIR 7 . 5 m r oad ~~~~~ ora cl e results only ((olumns 20 & 21) needed. 5 5
1--t--1-+-I- --t-.- 5- m
--ro- a-d----+'--'-'-"'-d,'--.t-"-to'-"-"-"----t- ----f Trave I time en try poin t - nod e =7 ER0 1+---6- --1-- -
6- -1-----+- -- --1
N 7
1--t--1--\ and
N2 residentia l 20 res/ha 17 7
El 7. 5 m road ~~~~~ grade 5 5
El residential 20 res/ ha 19 9
see add itional see Note NC! 2 .". 19 9
I-
M-t--1-.4+ ---+------"7f-r o-m- u...i.p-s t,.-r-ea-m-------II-
_ ----1
_ Not e N°.1 - i-r-- Tab Ie 6 1E~...~-2:-1-+--1-
1 --j-----+---\

b-+-1--1 ~~d
7.5 m road ~m~ qrade Table 6 5 5
N2 res i de nt i a 1 20 res/ ha 17 .7
El 7. 5 m roa d ~m~ or ad e 5 5
El r es i de ntia l 20 r es/ ha 19 9
El L 7 . 5 m road ~m~ grade 5 5
21 11
M .1 from up£tream 24 14
El 7. 5mroad ~1~~~ orade
ElL 7.5 m road ditto
El park pervious 40 14
40 14 J

BRANCH M.3 -> M. 2 -> M. l


I~ .3 NI R 10 "' "udcl ~1~~t qrade
NIL 10 m road ditto
EI 7. 5 m road ditto 6 6
NI L park pe rvio us 32
El park. ditto 32
32 7
M .2 from ups tream 34 9
NI R 10 m road V1 ~~¥ qrade 5 5
NI L 10 m road ditto 6 6
1-+-1--1 and ~r-e-
s i-d-
e n-t-ia-l--~2-
0-r-e-
s/-h-a----+---~ ·---·r-T-~-.r-r-+-~--tL-r--+~-.r-~1~
7 ~--~7,...-r--~~~--I
N2L
7. 5 m road ~1~~¥ orade 5 5
EI res i dent i al 20 res/ ha 18 8
34 9
M .1 f r om ups tream 36 11
NI R 10 m r oad ~~~~~ orade 6 6
NIL 10 m road ditto
NIL park pe rvio us see Note N°· 6 40 11 ~
b-r-+-+_--~---------+----------r_--+_~--~ Table 6 r-r-+--+~~~---+----+--4~0--~~
1 1~

BRANCH Ml + M. O
Contributio n from branch M.5 + ~L4 + M.l at M. l 40 14
Contribution from bra nch M.3 + f1.2 + M.l a t M.l 40 11
40 14
M .0 from ups tream 42 16
NIL
42 16

98 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

FLOW ES TI MATION IN MAIN DRAIN PIPELINES : N=5-YEARS


RAINFALL INTENSITIES CUMULATIVE
Ln mm/h FOR MAINLINE FLOWS
PROGRESSIVE CR IT I CAL COMPONENT CUMULATIVE FROM TOTAL
STORM DURATION IN UPSTREAM
TOTAL UPSTREAM (CAln (CAln CATCHMENT
CATCHME NT AREA
<t Q = (CAln Ln Li s
u.J n 0.36 REMAR KS
a:::
full-area part- area <t ~
0 anal ysis ana lysis full-area part-area
LJ
analys is analysis c:: tull - . .part - f ull- part-
analysis analysis
u..
Ln for Ln for II area area area area Qn for Qn for
c::
N=5years N=5years LJ N=5 yea rs N=5 year s
ha. ha . ha. ha. ha. Lis Lis
24 25 26 27 28 29 30 31 32 33 34
see note resu I ts
only (col 's 28 & 29l 0 .1 0 0 .10
needed 0 .1 6 0.16
0.37 0.37
0 .1 0 0.10
0.34 0.3 4

--
45 63 1.07 1.07 134 187 desig n f l ow at M.5
1. 07 1. 07 Isee Note N'· j I ( 172)
0 .11 0. 11 I Table 6 I input to M.5/M.4 :
0 . 49 x 58 ; 79 LI
0 . 38 0.38 see Note N°· 4 ."..,...- 0.36 s
0 . 05 0 . 05 Table 6
0 . 34 0 . 34 see Note Nq 5 ~ i nput at M.4 ; 71 Lis
0 . 05 0 . 05 Table 6
42 58 2 . 00 2.00 233 322 desig n f l ow at M.4
2 . 00 2 . 00 (288)
0.13 0 . 13
0.05 0.05 in put at M. 1E1 ; 30 Lis
0 . 07 ~ x .0
29 52 2 .25 2.20 181 318 design flow to M.1

0 . 06 0 . 06
0.2 1 0.2 1
0. 12 0. 12
0. 04 b'2- x .04
0 .1 3 !b- x .1
33 68 0.56 0 .4 3 51 81 des ign flow at M. 3
0 .5 6 0 . 43 (7 5)
0 .1 3
0. 18
0.33
0. 13
0 .18
0 . 33
-
r input at M. 2 ; 23 Lis
nput to M. 3/ M. 2 :
0 . 51 x 63 - 89 LI
0 . 36 - s
0 .1 0 0 . 10
' ~i nput at M. 2 ; 77 Lis
0 . 34 0 . 34
32 63 1. 64 1. 51 146 264 des i gn flow at M. 2
1.64 1. 51 (2 43)
0.13 0 .13 input at M.1 ; 21 Lis
0. 13 0 .1 3
}i nput at 14.1 ; 24 Lis
0 . 08 ~x . 08
29 58 1.98 1. 79 160 288 design flow to M. I

2 . 25 2 . 20
1. 98 1. 79
29 52 4 . 23 3 . 99 34 1 576 desig n flow from fl. 1
4 . 23 3 . 99 (543 )
0 0
28 49 4. 23 3.99 329 543 desig n flow at M.O

ARRB SR 34, 1986 99


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

3. The fl ow '(172 Lis)' listed in column 33 Th e fl ows requi red i n Task 1 fo r t he


is the design flow contributed f rom sub- M. 5/ M. 4 an d M. 3/ M. 2 pipe line segments can
area M.5 relat i ve to node pi t M. 4. It be deriv ed from inf ormat ion contained in
can only be determined after all entri es lab le b : the re sul ts are repor! ed under
under M.4 have been evaluated to find 'Remarks' , co lumn 34. They ar e :
critical storm durations (tc and til an d,
hence, design rainfall intensities. Thus o segment M.5 / M.4
the 172 Lis listing is derived from {CA) s
= 1.07 ha and \ 58 mmlh :- (0.11 + 0.38 ) x 58 0.49 x 58 79 Li s
0.36 0. 36
1.07 x 58
172 Lis o segment M.3 / M. 2
0. 36
(0.1 8 + 0. 33) x 63 = 0.51 x 63 = 89 Lis
The flow '1 87 Li s ' shown in column 0. 36 0.36
33 is th e design flow (N = 5 years) into
and from node pit M.5, and should only be The distribution of these flows
used for design in th e immediate vicinity (Task 2) and, consequent ly, the magn i-
of M.5. Where flows in pipe segments tudes of flows passing to the main pipe-
near node pit M.4 are required, the sub- liners) at the points of interest, are
area M.5 'relative flow' 172 Lis found by a procedure similar to that
should be applied (see Fig. 6C). (using the same graphs) employed in Fi g.
4B (see figure below).
4. In general, entry of fl ow to mai n drai n
pipelines takes place at or near node 5. Flow input to the main drain pipelines at
pits. This is not always the case, e.g.: ot her s i gnifi cant 1ocat ions can be fou nd
in the manner indi cated above (Task 1).
o segment M.5+M.4 : flow entries at M.4N1 Results of these computations, derived
and M.4N2 from the data presented in Table 6 are
also listed under 'Remarks', column 34.
o segment M.3+M. 2 : f low entry at M.2N2
6. Flow estimation in Branch M.5+M.4+M.1
Determination of flows input at concludes with branch design input to
these points in design storms which are node pit M.1 of 318 Lis. Corresponding
critical for mainlines involves two tasks : input from Branch M.3+M.2+M.1 to M.1 is
288 Lis. These flows arise from design
Ta sk 1. Fi nd the fl ows cont ri buted from storm durations which are critical in
their connected primary drainage their individual catchments and hence
areas in such design storms; storm rainfall intensities which are sig-
and, n ifi cant ly different (52 mmlh versus 58
mm/h). The storm duration and hence in-
Task 2. Find the distribution of these tensity which is critical in the remai-
flows, including gutter inlet ni ng segment of the network (Branch M.1
capture, in the respective + M.O), must be resol ved in accordance
drainage lines. with Rational Method theory (Chapter 4)

INLET ~ 0 INLET
M4N1 \l} \.1J M·4N2 NOTES :
1. All flo\ols derived from Table 6
2. Flo\ol accumulation relationsh ips
superimposed on Figure 49
INLET INLET
M·2N1 L M·2N2L
@ @ 60
32m flo\ol accumulation in drainage line
~ VI
"- terminating at M·4N1 (So = 0·03)
:::: 100 -'

'"
c
~I~
ClI o "
en
to
c
""
20 -14/
~ ClI
'"c -......,J-7 L1s (bypass)
~~
60
:. 00 20 40 60 80 100 120 140
....
.9
40 ~ I~ Dra inage line le ngt h (m)
o ""
'"
2!
to
::>
27 ~I " f lo \ol acc umulati on in drainage l i ne
E
::>
u
u
20 ............
'-.J- 11 Lis (byp ass)
r terminat ing at M·2N1 L (So =0·04 )
«
00 20 40 60 80 100 120 140 160 180
Drainage line length from term inal inlet (m)

'To tal catc hm ent ' flo w acc umu lation in drai nage lines M·S/ M·4 & M ·3/ M ·2

100 ARRB SR 34,1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

before the flow estimation procedure can FIG ~ E 6C


cont i nue .
As a result of the flow estimation computa-
Resolution is achieved in a short tions carried out in or derived from Table 6
tabular entry at the commencement ' of (see 'Remarks', Column 34 and Note 4 above),
Br anch M.l + M.O flow estimation comput- it is possible to declare a design flow (N =
ations . Thereafter the procedure con- 5 years) in each segment of the main pipeline
tinues in the manner set out for catch - network of Cat chment M. These flows are pre -
ment upper branches. sented in Fig. 6C : only flows essential to
mainline segment design are included.

CA SE 4 : STEP 6, FIGURE 6C
DRAINAIGE NETWORK COMPONENTS
Main dra in pipeline .. .. . ........ ~
Cross-c onnections .. . .. ......... W
Conc entrated flow entry .. . ,
LP. M·2N3
Junction pit .. •
(75) 62

Al l flows LIs
derived f rom TAB LE 6

(2ee) 322 M·4 71


FIGURE 6C : DESIGN FLOWS IN
8
Design Flood Level MAIN PIPELINES OF
R.L .100·00 CASE 4-N= 5 YEARS

CASE 4 STEP 7, FIGUR E 7

See Add it ional Note


r e STEP 7

1
BO M'2 E1 62 M·2E2 M'SE2
264
All flows Lis
M·1N2 Inspection derived from
pit Figures 6A and 6C
243
M·1N1R M·1N1L
~ M·4E1
N
1
322 M·4 81 62 M·4E2
FIGURE 7 : DESIGN FLOWS IN ALL 1
PIPE COMPONENTS OF M·4E1L
M'O CASE 4-N=5 YEARS
543

AR RB SR 34,1 986 101


CASE 4 : STEPS 8 &9, TABLE 8/9 PIT wATER LEV ELS, PIPE DIAMETER S & H.G.L. ANALYS IS : N = 5 -YEARS

P IT
0
WATER LEVEL 0

l-
lLJ a::
lLJ
~
E
- en
TE S T 1 TE ST 2
a::
V)
'-'
~$
D :..J a.. a:: I- lLJ -
a.. 0

hf+KW[~Jg]
0 -'
ci w lLJ
Kw \,20 hf +1 5 0 0 I-

~
Z -' lLJ ::::>
l- L: > -'
I- w <! Vl - ~
3 L: <!
z D I-
a::
<!-
3-, -<! a lLJ -
Vl-D 2g 0 en «
-
a:: REM ARKS (j)

~-
w 0 I-
lLJ
-' D « -0 D w -l
L: Z z ~ 3 " ~ 0
>-- -z
a.. > I-
«
z
LI1
w .y LJ
~ 0\ ~ V)
AWL=assi gned (p it) wa te r leve l o
I- I Z
- Z
0
- V)
E -D - - D<!
lLJ ~ a.. ::J I -' :D
~
LJ <! Z w w - LJ"I r- D
Z
lLJ I -
W W I- "- ~
Z
~
Z 0.. >--- Vl .--<
C
w BWL= boHom (pit) water level s:
<! a::
L: LJ <!
0
-
I-
a:: z 0..
-
-'
I
::::>
I-
-Z
-'
-0 -
-'
-0 L:J - '
- w -'
I-
-
Vl
0
-0
v,
a
~o
AWL- BWU E (AWL - BWU I- cd W
0 o
I
lLJ 0 a:: l- - w w LJ -' a > 0..
-'
D ~
Vl > <! -' <!
LJ
I
en en z
I LJ I-
I-
0..
L:
LJ
Vl
3 L:J L:J D ~
- .D - .D Vl lLJ -
a::
0
-'
OJ
- ' II
'+-
~

:J
Eq .6· 17
3
Eq . 6·18 0
D 3 a::
:D
~
I- 0 Z Z <! --l I - .D en L:J
<! ::::> ::::> ::::> ::::> 0 lLJ
-' lLJ 0 ::::> ro ::::> ro I- lLJ - It> .c ::.::: <! <!
-. L:J I - Z
LJ Vl Vl L:J '-' D lL -' -' L:J I -
- ~

RL m
> 0.. I -
- m m m m m m mm (Pit Wl:s) ~
G)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 m
lATERAL PIPELINES
o
m
(j)
M . 5 111. 35 [pit --
l junctio n 111. 7.0 n.a. 111 .20 111.20 TEST 1 OK for 00 - 300; fails
TEST 2; u/s inv . max . Rl 110.79 G)
plpe
E2 ., E1 60 40 .024 .300 .35 J -3 2.0 .04 . 08 .07 0.15 0.97 0.5 3
100 t b( egn ~8'P) m~t· BWl at E2,
R..111'-- _ = AWL
Z
JP with TESTS 1 and 2 OK for Do = 300 ; Z
~: 5:40 au tter flOl' 110 .25 111.10 11 0.25 11 0.23
upstream inv. max. Rl 109.87 (f)
~lpe .306 11. 09
~A/ 2B
. VO . Vi .Vb v.08 0.47 s:~
-
1 -+ j.j, 5 77 5 .020 i.O 0. 10 300 by eqn (6. 19 ) ; max. BHl at E1,
Rl 110.23 by eqn (6 . 20 )
'iVFJ.£b·· l ~iiunct1on B·.il r

IT N:
JP with
111.30 [qutter fl o~
110 . 15
111. 15
110 . 15 110.15
n.a . 111.1 5
FROr~ MA IN PIPELIN E (BRANCH) COMPUTATIONS 110 . 15
111.1 5 TEST 1 OK for Do - 300; fails
TEST 2; u/s inv. max. Rl 110.5E
r
C
:D
oipe bl' eq n (6·P) A m~x . BWl at N2 ,
~1
IN~ -> in
JP, gutter
68 27 . 024 .300 .96 1- 1 4.0 05 .07 .1 9 0.26 0.68 0.52
30n t Rill 15 = Wl
III
~
11 0.65 flow lat' 11 0.50 111. 05 110.50 110 . 47 TESTS 1 and 2 OK for Do = 300; Z
oipe .300 1.68 0.32 300
upstream i nv. max. Rl 109.95 o
t~ i -> r,1. 5 119 12 . 029 1B/3C 1. 5 .14 .lD .22 0.35 0.55 by eqn (6.19); max. B,il at N1, ~
-l
rWDE n. 5I~iiunction prev~g~aly__ 11 0. 15 Rl 110.47 by eqn (6.20)
110 .30 ISS ' 110 .40 110 .1 5 Bi·; l FROn ~1AIN PIPELINE (BRANCH) COMPUTATIONS 110.1 5 o
-2 TEST 1 OK for Do = 300; fails I
L ~unctio n
M .4 10j.25 [oi 103.10 n.a. 103 . 10 103.10 TEST 2; u/s inv. max Rl 102. 68 s:
~lpe
2 -, E1 62 40 .006 . 300 .88 J - 3 2.0 ,U4 .U'J .UB 0.17 0.58 U.04
300 _t _bl' egn (6'P)A m~ x . BWl at E2,
R 1 3.1 0 = Wl
m
z
-l
E1 JP , gu t ter 102 .88 103.00 102.88 102.52 TESTS 1 and 2 OK for Do = 300;
~
I.. 103 .03 f l ow l at'
u.uo upstream i nv . max. Rl 102 . 19
(f)

:D
Ol pe 81 5 .006 . JUU 11.10 I - 3A 0.5 ,VI .Ui . UJ 0.41 U.41
by eqn (6.19); ma x. BHl at El,
~1 -> M.4 300
:D Rl 102 . 52 by eq n (6 . 20)
III NODE 1U t hro ' pi~e 102.85 102 .78 102.78 BWl FRor,1 r1A I N PIPELINe: (BRANCH) Cor·IPUTATIONS 102.47
103 . 00 with 1at s
(j)
:D M "2
. 2 108 .40 [pi
l ~ u nction 108.25 n.a. 108 . 25 108 . 25 TEST 1 OK for Do = 300' fai l s
TEST 2; u/s inv . max. Rl 107. 8
w
•.po cE~pe-> -c 1
62 45 .020 . 300 .88 J-3 2.0 . U4 .10 .UB U.H1 1.00 U.~~
300 t ~y iR2'~~ ' 7 ~ )Aw~~x. BWl at E2,
...... El JP with
<D
CO ~ 107 . 50 :qutter f l ow
107 . 35 108.15 107 . 35
. 30U 1.13
107.25 TESTS 1 and 2 OK for Do = 300;
upstream i nv. max. Rl 106. 88
~A/2B 1.0 . UI .UJ .UI U. 1U 0. 2e U. 4tl
OJ

\OgFJij
~ l pe

2 JP
1 -> ~1. 2
multi -pi pe
80 7 .029
107 . 15 107.25 107.15 BHl FROrl: 1,1AW °1 PELIN E (TRUNK) COl1PUTATIONS
300
.. 107.15
by eqn (6 . 19); max . BWl at E1,
Rl 107.25 by eqn (6.20)
» MAIN PIPE LI NE : BRANCH M.5-M.4-M.1
:D
:D
M .4 N.UPE M.: t~ro ' pi ~e ~revioualY TEST 1 OK for Do = 300; fails
CD 110.30 with 1at s sS l gne 110.15 110 .15 TEST 2; u/s inv. max Rl 109.31
(f)
I ~~~e.. N3
187 100 .036 .300 2.64 J-2B 1. 0 . 36 2.02 .36 2.38 3.60 2. 47 egn:i6,p)Awr~x,
b{ 110 BWl at M.4
:D 1nn R 5 -
w N3 j~ro' pi pe 106.55 110.05 106.55 106.55 lEST 1 OK for Do = 300; fai l s
-~ 106 :70 TEST 2; u/s inv. max Rl 106 . 16
~1P! N2 . 300 2.43 J -1 0. 2 . 30 1.42 .06 1.48 1. 87 ~( i32:~~ ' n) Awr~x , Bl~l at N3,
-'
<0
CO
O'l
iT• N2 JP with
103.70 I qutter flol'l
172 83 .036
103 . 55 106.45 103.55
3.00 300
103.55 TEST 1 OK .for Do - 375; fails
TEST 2; u/s inv. max Rl 102.99
1 3. ~6'P)A
5 = Wl~r' BWl at N2,
n
~~P! N1 237 17 .032 .375 2.1 5 I- 2B 0. 5 . 24 .18 .12 0.30 0.89 0.74
375 t b{ e3
R
T~STS 2 O~ f?5 D? = 375;
(f)
-I
1O~:15 I ~~t~~~hfl Oil 103. 00 103.45 103.00 1
102. 66 u s lnv. max& l 2. 5 b~ eqn o:D
(6 .1 9) ; max . B~l at N1, l
~lpe
, 1 .. t~4 251 5 .03C .3 75 2.27 I- 2B 0.5 .26 . 06 .13 0.1 9 0.53 0. 62
375 102 . 66 by eon 6. 20) s:
M .1 I N1U~J. 6'1i ~ with
t~ro pl ~e ~revioualY..... 102.78
lat s sSlgne 102.90 102 .78 102 . 47 TESTS 1 & 2 OK for Do - 525; o
u/s inv. max Rl 101. 72 by eqn :D
oi~e
M.II .. E1 322 100 . 008
.450 2. 02 J- 2C
.525 1.48 2. 0 ..11
21 .79 .42
.36 . 22
1. 21
0.58 0.8, -
1.15 525 t (6 .1 9); max . B~ l a~)M.4, Rl
102.47 bv eon '6 . 20
»
E1 JP, gutter Z
101. 89 TESTS 1 and 2 OK for 0 = 525; »
iT• 102 . 25 flow l at ' s
~lpe
1 .. M.1 318 8 .006
102 . 10 102 .68 102.10
. 5<,5 1.4 I- 3A 0.5 .11
. Uj .Ub U.U~
0. 3C U.8<'
525
upstream inv . max Rl 181 . 30 by
eqn (6 . 19); max. BWl at E1,
G)
m
~tU,!Jnt _M_. mU ltl-p l pe
102 . 05 102 . 00 102.00
~

BWl FROn i·1AIN PI PELINE (TRUNK) COMPUTATIONS 101.80 Rl 101.89 by eqn (6.20)
o
102.20 JP m
(f)
MAIN PIPELINE: TRUN K M. 3-M.2-M.1 -M.0 G)
M . 2 NODE M. multi -ri pe 114.05 11 0.55 11 4.05 114.05 TEST 1 OK for Do - 300 ; fails Z
114 . 20 JP TEST 2; u/s inv. max Rl 113.45
oi~e
M. .. N3 81 100 .036 .300 1.1! lulti - 3. 0 .07 .38 .20
pi pe JP
0.58 3.60 0.83
300 ~{ in :bf7~ )Awr~x, BWl at M.3 Z
(f)

... N3
110.60 JP
thro' pi pe 110.45 108 . 35 110.45 110.45 TEST 1 OK for 0 - 300; fails
TEST 2; u/s inv~ max Rl 110.13
s:
»r
• N2
~3P! N2
thro' pi~e
75 68 .03;;
108.25 107.25 108 . 25
.300 l.Ot J -1 0.2 .06 .20 .01 0.21 2.20 0.65
300
108 . 25
~( n8:i~'7~) Aw~~x. BWl at N3,
TEST 1 OK for Do - 300 ; fails
r
C
108. 40 with lat s TEST 2; u/ s inv. max Rl 107 .66 :D
~~P! M 2 137 44 .025
• .lUU 1. ~,
J - 2B 1. 0 .1 9 .48 .19 0. 67 1.4 1 0.93
t ~r f~2'~~ ' 7~) Awr~x, BWl at N2, CO
preylous Y__
300 »
. 1 N1U~7t. 3O';; JP ltl- plpe asslg ned
M mU 107 . 15 104 .75 107.15 TEST 1 OK for Do - 375; fai l ~ Z

.
M 106. 84 TEST 2; u/s inv. max Rl 105.60
.j/ L . j~ mu lti - 3. 0 .,,9 Il. 3~ . 8/ ".19 l. 88 ~( eqn (6.19); max. BWl at M. 2
()
~~ ~e.. N2 264 100 .025 pi pe JF 2.5C 375 * 106 .84 by eqn (6.20) »
-I
N2 thro ' pi pe 104.65 102.10 104 .65 104.65 TEST 1 OK for Do = 375; fai l s ()
104. 80 JP TEST 2; u/s inv. max Rl 104 .1 9 I
~ ip e
, 2 .. M, 1 243 105 . 025 . 375 2. 2 J-1 0.2 . 25 1.1 .05 1.22 2.8: 1. 73
375 ~r f~a' ~~. 7~) A'Jr~x , BWl at N2, s:
o NODE M. mu lti -p ipe prevlo u s l~ 102 . 00 101.80 TESTS 1 & 2 OK for Do 600; m
M assigned 100. 85 102.00 Z
. 102. 20 JP uls inv. max Rl 100.57 by eqn
6;
mu ltl- u/j - (6.19 max. B~~ a )M.1, Rl -I
~ l pe
1.1 .. N1
576 100 . 01 :~5_~ ~ :8~ pijJ_e JP 3.0 : ~~ I ~ 66 1
1:
63 f:g 1.43
1.50 600 t 101. 8 bv eon 6. 20 3 (f)

10~ ~ 90 J~ro plpe 100.10 100.75 100.57 TESTS 1 & 2 OK for D~ - 600;
:t 100.75
. 60C 1.9 J -1 0.2 .i9 . 53 . 04 0. 57 1.43
~/S inv. max Rl 99.9 by eqn
6 . 19~; max. B~~ a~)N1, Rl

M.O
~lpe
1 .. M. O 543 100 .OOS
DESI GN FLOOD LEVEL RL 100.000 = BWl
0.75
..
600
100.00
00.5 bv eon 6.20

*Design of t hi s pipe falls into the ' Outcome 110utcome 2' situati on
-'
descri bed in Section 6.8 of text
o
w
CASE 4: STEP 7 - ADDITIONAL NOTE (water level) value, Kw, which should be used
at the junction pit, and are:
The design flow distribution set out in Fig.
7 uses the greater flow where there is 251 Lis from the northern pipe ; and
choi ce - shown for each component in Fi gs 6A 71 Lis from pipe M.4E1 + M.4.
and 6C. While this gives appropriate values
for use in the design of the components them- The procedure adopted in the Handbook
selves, it represents a loss of data which for selecting values for Kw (see Tables 6.5
may be of importance in some design practices. and 6.6) is an approximate one which is in-
sensiti ve to the difference di scussed here.
Consider the alternative flows presented Designers who employ the full 'Missouri
for pipe M.4E1+M.4 : Charts', however, should be aware of the
difference and should use the correct (alter-
from Fi g. 6A (primary drai nage considera- native) values in their appropriate contexts .
tions) flow 81 Lis
from Fig. 6C ('total catchment' considera- A further interpretation which has been
tions) flow 71 Lis made in preparing Fig. 7 should be observed:
this concerns the aspect discussed in STEP 6,
Pipe M.4El + M.4 should be designed to Table 6, Note 3, above.
convey a design flow (N = 5 years, ARI) of 81
Lis. Pi pes ca rry i ng discharge direct ly from
node pits are shown with the appropriate val-
The design of mai nl i ne component M.4 + ues collated from Fig. 6C. Flows from the
M.1El, however, involves not only its design 1ocat ions whe re these pi pes are interrupted
flow of 322 Lis but also the flows entering downstream by a junction pit, inspection pit,
node M.4 under corresponding design condit- etc., use the 'relative flow' value (shown
ions. These flows determine the pit headloss bracketed in Fig. 6C).

CASE 4: STEP 10, FIGURE 10 CASE 4 STEP 11, FIGURE 11


NOTES : M·3N1R M·3N1L NOTES :
PIT flOOR PIT FLOO R
t All pi pes FRC Rl 1n SO ItL 11) SO t Pipe Inverts at Pits coin cide with
7 Pipp rli<:lmptprc:. in mm pit inverts.
3.Gutter inlets : see legend Fig. 6·5 2. Pit floor levels -see Table 8/9
~o", 'o~,,(fI M·3E1
4. Pipe diarreters for cross-connections and Guidelines 11 - 13.
M.3 7m PIT FLOOR 3. All pipes FRC- classes X and Y
found f r om Guideline 10, Table 6.4 PIT FLOOR E 300 RL 113 65
5. For de si gn f lows see Fig. 7 Rl 11) i.0 ~ g
I.P. M·2N3 ~?~L~R I.P. M·5N2
Rl l09·9Q ~ ~ PIT FLOOR
2 Rll10 56
2m
M2N2 2m
M·2N2L M·5N1R
r" '2N2 300
flIT flOOR
300
PI1 ~VV1 U
Rl 10763 Rl 10765

,
M.2N1R /s~ ::. g ~ ~\El1oR
PIT FLOOR °0 M-S ~,..., Rl109 ·67
Rll07' 05 Ptl FLOOR Sm l.Om
M·2 RL109 31 e 0'300 300 _
M SE2
PIT FLOOR ~ :g PIT FLOOR
Rl 10560 E "" PIT flOOR Pil flOOR M·4N3 RL110J9
I.p. M·4N3 ~:;; RL 106 88 Rll0783 loP Pil FLOOR
:;, 8 Rl 106-00

M·1N2 ~ ~ M 4N2
loP M·1N 2 I.P. PIT FLOOR 2 PIT FLOOR
Rl 104 00 Rll02 99
M·1N1R
PIT FLOOR
RL 10155 M·1N1L M·4N 1
PIT FLOOR 1
RL1 0215

~~
~""";;:-~_ _ _-7.'0".
0"m -_ _:-:-:-....,5"'m,-f-'+-~"--.. M.4E2 100m
525 M.4 300 525 lOO
M·4
PIT flOOR
RL 10172

M·1E1L M· 4E1 L
Eo
PI T FLOOR PIT FLOOR
0 0 RL10150 Rl 1022 8
"'~
MoliI~
M '~5IGN FIGURE 10 : APPR OXI MATE NETW ORK FIG URE 11 : APPROX IMATE NETWORK
~R
'LOOO ~O_[_S I~N FLOOD
~ WATER LEVEL : RL 100 00 DESIG N· N =5-YE AR S LEVEl RL100 OQ DESIGN WITH PIT FLOOR LEVELS

104 ARRB SR 34,1986


1Z
Concluding discussion

12.1 RESlME etc., can be carried out swiftly by hand us-


ing the procedure described in Chapters 8 and
Three aspects of master drainage planning 9. There is little need for computer assist-
(runoff quantity) have been addressed in the ance.
Handbook -
A well-planned minor drainage system, on
o
stormwater retention/detention/retard- the other hand, should be designed to control
ation measures, a specified level of storm runoff identi -fied
in terms of an adopted design ARlo Although
o
major drainage system planning, not a high precision task, it is multi-faceted
and time-consuming to execute by hand. The
o
minor drainage system design need for machine assistance by way of spread
sheets or appropriate software in all but the
and information provided and procedures des- simplest networks is therefore indicated.
cribed enabling these categories of works to
be incorporated into Australian urban land- The acceptance of computer i nvo 1 vement
scapes. in thi s aspect of master drainage pl anni ng
ra i ses important quest ions of data qua 1ity
In Chapter 3, designers are urged to input and expected error in mi nor d ra i nage
select from a wide range of retention/deten- system design procedures. What level of model
tion/retardation measures which offer the sophistication and/or computational precision
following benefits for urban drainage systems: is warranted by the quality of the technical
data base and by the procedures used to esti-
o
reduced cost of works mate flows in ungauged catchments and to de-
sign appropriate minor drainage system net-
o
increased on-site soil moisture works?
o
reduced ri sk of i nju ry, drown i ngs, etc.
12.2 DATA QUALITY AND ERROR IN THE DESIGN OF
o
improved living environment. MINOR DRAINAGE SYSTEMS

Caution is advised, however, in locating DeSign of a minor stormwater drainage system


on-site retention/detention structures near for a small ungauged urban catchment involves:
buildings and in areas where soils are un-
stable. a) data extraction from plans, field surveys
and technical information,
Chapters 4 - 7, inclusive, provide the
hydrological/ hydraulic data base for the b) classification of components into categ-
major and minor drainage system design proced- ori es for whi ch data from a vari ety of
ures of Ch apters 8 - 11. Th e close i nter- related and unrelated sources are avail-
relationship which must exist between these able,
networks within a Master Drainage Plan is em-
phasised throughout. While this link must be c) interpretation and adoption of appropri-
constantly recognised by designers, they ate data values,
should also be aware of important differences
arising from the contrasting goals of each d) application of data into mathematical
system and the ways in which these goals are models (computation process), and,
achieved.
e) revi ew and judgement.
Major drainage system planning employs
a I broad brush I approach to achi eve its goal Tasks arising from these sub-sets of the
- that of mitigating the effects of runoff design process are performed many times in
generated in the wake of great storms. Pre- each design. For example, there are at least
cision in the prediction of flow quantities 30 measurement and data transfer acts [i tem
and behaviour in such events is neither pos- (a) above] involved in the deSign of even the
sible nor warranted. Major system planning, simplest segment of a main drainage pipeline.
including the checking of alternative routes, About two-thirds of these are new data inputs

ARRB SR 34, 1986 105


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

whi 1 e the remai nder are data transfers between Oesp ite these advantages, comp rehens i ve
steps. Correspondi ng numbers for the other testing of many components used in Australia,
categories listed above are: b), c) and e) in particular various gutter inlets (gratings,
about ten acts each, and d), 20 acts. side-entry inlets), junction pit configura-
tions, underground network flow conditions,
While the potential for error is undeni- etc., has never been undertaken. Enough is
ab ly great the use of hydrau 1 i c data from known from experimental work carri ed out on
tested components only and careful execution simi lar units, however, to partly overcome
of the design processes by hand or with com- this deficiency by providing 'first approxi-
petent software should restrict the overall mat ion' data of the type presented in some
error likely in the bulk of these acts to Appendix A cases. While this is satisfactory
between 5 and 10 percent. The error poten- as a stop-gap measure, it should be replaced
tial of the remaining acts, drawn mainly from by a programme of systematic testing of units
categories b), c) and e) above is reviewed in used widely in Australian practice.
the following sub-sections.
One of the main issues which the design-
er of urban drai nage networks in small urban
Error in peak flow estimation in s.all urban catchments must decide is the use to be made
catcMents of available data on the junction pit headloss
pilrilmpt.pr Kw ilnrl on thp. Oarcy-Weisbach fri-
The two main catchment characteristics upon ction factor, f. Should accurate values for
which the simple mathematical models of urban these parameters be obtained from the Missou-
hydrology devolve are (see Chapter 4):- ri and Moody charts, respectively, or are
approximate values satisfactory?
1) runoff coefficient, C, and
This question has been decided in the
2) critical storm duration, tc or tie Handbook procedures in favour of fi xed values
(Tables 6.5, 6.6 and Section 6.7) selected on
Schaake et al (1967) showed in an experi- the 'high' side of average in each category
ment-based study of the Rational Method app- leading to 5 - 8 less minor computations and
lied to small urban catchments, that errors two less chart consultations per pipe, com-
made by experienced practitioners are 1 i kely pared with procedures requiring full Missouri
to exceed ± 10 per cent in estimating C and ± / Moody consultation. This tally applies only
30 per cent in estimating critical storm dur- where tri al pi pe si ze proves to be sati sfac-
ation. Flow estimation errors of more than ± tory. The saving on computations/consultat-
20 per cent can be expected. Argue (19 82) ions where trial and final sizes differ is,
rnnfirmp.rl this finding for a hypothetical ur- of course, qreater.
ban subdivision in which critical storm dura-
tion was set equal to tc and showed that in The criticism that accuracy has been
cases where critical storm duration equalled compromised in the interests of developing a
ti - paved area travel time - flow estimate simple procedure can be partly answered by
variation was reduced by about one third. reference to the Case 3 and Case 4 illustra-
This is explained by the lower level of un- tions presented in Chapter 11. Reworking
certainty that deSigners face in estimatin~ TARIF R/g in p.ilr.h r.ilSP. with headlosses deter-
ti in urban catchments and, to some extent, .mined by reference to Missouri and Moody
by its magnitude compared with tc. Chart data yields the following outcome:-
Overall variation in design peak flows Case 3:
estimated for ungauged urban catchments by
experienced practitioners uSing the Two-Value pipe network - no change in component sizes
Rational Method of Chapter 4 is likely to pit water levels (H.G.l.) -
fall within the range ± 15 per cent to ± 25 pit XA.3El maximum water level reduced
per cent. by 0.03 m
other pits : no change
Corresponding flow estimates produced by
more sophi st i cated and t i me-consumi ng models
such as IlllJOAS (Terstriep and Stall 1974), Case 4:
IllUOAS-SA (Watson 1981) and IlSAX (O'lough-
lin 1986) applied to Australian catchments pipe network - no change in component sizes
show much the same range of variation. The pit water level (H.G.l.) -
great value of these models resides in their 50 per cent no change;
abi 1 ity to generate runoff hydrograph data. 50 per cent lowered by maximum of 0.20 m

The apparent oversizing produced by the


Error in network hydraulics of s.all urban Handbook procedure reflected in elevated pit
catchlllents water levels and, in other cases, a small
percentage of oversized pipes, provides a
Hydraulic phenomena, unlike their hydrologic- margin for unknown headloss discrepancies
al counterparts, are uni versal in thei r be- arising from laboratory-to-field transfer of
haviour, and are reproducable and repeatable data as well as unknown gap and misal ignment
in full-size or scale laboratory rigs. Hyd- headlosses in pipes.
raulic data deficiencies can therefore be
overcome by short-term relatively low cost It is concluded from these observations
field and laboratory studies and can be and from the design flow error assessment
transferred from anywhere in the world. conducted in the previous sub-section, that

106 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

design outcomes produced by the Handbook pro- Urban catcn.ent hydrology


cedure are well-matched to input data quality
and that therefore the procedure is appropri- The runoff coefficients presented in Tables
ate for the range of urban catchment cases 5.3 and 5.4 are based on records from six
for which it is intended. gauged urban catchments - four in Melbourne,
Victoria, one in Canberra, A.C.T., and one in
Sydney, N.S.W. The foremost need in urban
12.3 STORMWATER MANAGEMENT MEASURES AND THE catchment hydrology is for a greatly increas-
ILLUSTRATIVE CASES ed and representative network of gauging sta-
tions to provide data for improved design in-
Extensive use of formal runoff collection and formation and for testing of alternative
conveyance networks has been made in the four rainfall/ runoff mathematical models.
case examples which illustrate the design
procedures of Chapters 8 - 11. Some may in- Other aspects of catchment hydrology
terpret this as a denial of the use of on- whi ch are imperfectly understood and whi ch
site retention/detention measures and inform- would benefit from association with an expan-
al drainage line treatments recommended in ded gauging network are:-
Chapter 3.
1. per cent impervious area measurements in
No such retreat is intended. The net- the full range of land uses (see Section
works have been adopted, primarily, to demon- 5.6)
strate the Handbook's planning/design proced-
ures in circumstances which involve large 2. fraction of paved area which is directly-
storm runoff flows. co nnected to the formal collection system
in different land uses (see Section 5.6)
Use of the stormwater retention/detent-
ion measures and swales recommended in Sect- 3. field values for the overland shallow
ion 3.6 (soil hydraulic conductivity, Kh > flow parameter llim (see Fig. 5.3).
3 x 10-6 m/s) in the Case 4 catchment, for
example, would reduce design flows in all
drainage paths by at least 30 per cent, with Storm runoff manage.ent
consequent network initial cost savings of
over 10 per cent. Thi s illustrates one of Research on aspects of storm runoff management
the main benefits which follow the use of is needed to provide:-
s tormwater management measures, where appro-
priate, in urban landscapes. l. appropriate parameters to assist design-
ers in their prediction of 'ultimate de-
velopment' likely in catchments (see
Sect ion 5.1)
12.4 RESEARCH NEEDS
2. information on design ARI for a wide range
Average annual expendi ture in Au stra 1 i a on of land uses based on case studies which
urban storm drainage works has bee n estimated have given adequate consideration to tech-
by Profess or D. H. Pil grim (U.N. S.W.) at nical, cost-sharing (developer/council),
around $150,000,000. With the cost of damage community, political and environmental
suffered by the community in the wake of inputs (see Sections 2.4, 2.5 and 2.6)
major storms in urban areas added to this, a
total cost may be declared which significant- 3. advice to designers on the use and siting
ly exceeds annual expendi ture on all maj or of retention/detention installations tak-
dams and flood mitigation schemes. ing account of building proximity and
soil characteristics (see Sections 1.3,
By contrast, the sum invested annually 3.3 and 3.6)
in research on urban storm drainage, is un-
documented but is certainly less than 0.1 per 4. information and advice to deSigners on
ce nt of the -above total. performance and public acceptance of in-
formal drainage channel treatments (see
Some of the consequences of this poor Sections 3.5 and 3.6).
re search support are revealed in Section
12.2. Expected error in urban catchment flow
estimation procedures can ran ge to ± 25 per Drainage networks: surface hydraulics
ce nt and in the a rea of d ra i nage netwo rk
hydraulics, many structures (gutter inlets, The main roadside channel kerb-and-gutter
junction pits, etc.) in common use have not profiles used in the various Australian
been adequately tested an d there are pipeline states fall into three categories:-
flow conditions for which no satisfactory de-
sign data exi st. 1. 150 mm kerb, 450 mm gutter, Za 12
Res earch needs may be separated into N.S.W. and Tasmania
four domains:-
2. 150 JTI1l kerb, 300-375 JTI1l gutter, Za =
a) urban catc hment hydrology 8- 10: Victoria, S.A., N.T., Queensland
b) storm runoff management aspects and A.C. T.
c) drainage network surface hydraulics
d) drainage network underground pipeline 3. 150 mm kerb, no gutter Western
hyd raul i cs. Australia.

ARRB SR 34, 1986 107


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

Within each of these categori e s there is 2. drainage pipeline headlos s e s ca used by


a range of gutter inlet types and geometries gaps and misalignment at joints
to be found, some used widely by main road
authorit i es, others found only in their muni- 3. junction pit headloss coefficients (water
cipalities of origin. level) for configurations having two or
three inflow pipes making angle s other
Of the total number of gutter/inlet com- than 'in line' or at right angles to the
binations present in this array, relatively dis c harge pipe alignment.
few have been the subject of comprehensive
model tests, and of these only a handful have
been tested in the field or in full-size
ri gs.

Whi le the advantages of uniformity may


be appa rent to all tak i ng a nat i onwi de per- 12.5 FUTURE PERSPECTIVES
spective, the realities of local custom and
fami 1 i ari ty are advanced as strong arguments The data, guidelines, design steps and tas ks
against standardisation. For this reason a described in the Handbook have been compiled
programme of testing is recommended, whose from manuals of leading local government,
aim is to elevate to the highest quality level urban drainage and State Road authorit i es,
possible, the data bases of the principal from Australian and overseas research liter-
roadside channel types and inlets now accepted ature and from consultations and discussions
in Australia. These are presented with, main- with numerous practitioners and researchers.
ly, 'first approximation' flows for roadside The data base and mai n procedures have been
channel, carriageways, etc., and capture per- the subject of open forlJT1s and have been re-
formance (i nlets) information, respecti vely, viewed by a wide range of potential users.
in Appendix A.
Despite this background, the doclJT1ent
should not be regarded as a final and 'iron-
Drainage networks: underground pipeline clad' textbook of practice but, rather, a
hydraul ics first statement subject to revision and fine-
tuning as a consequence of its use in the
Of the four research domai ns 1 i sted above, fi e 1d.
that of underground pipeline hydraulics has
the most satisfactory data base. This may be It is intended that the project which
accounted for partly by the long interest has resulted in this document be ongoing, and
which hydraulicians have had in conduit flow that it wi 11 be the repository of case study
phenomena, and partly by the substantial pro- information drawn from the full range of
gramme carried out by Sangster et al (1958) Australian e xperience and will include com-
which yielded the 'Missouri Charts'. Later ment on the performance of systems, info r ma-
research has built on these foundations. t i on on the consequences of cost and cost-
sharing initiatives, shortcomings of proced-
There are three areas of research in ures, review of guidelines, updating of re-
underground network~ which de~erve ilttention: search data, etc. Contributions on all of
these aspects will be welcomed by Australian
1. headwater build-up in junction pits dis- Road Research Board and the author, and will
chargi ng under the part-full conditi on form the extended data base for future revis-
(see Table 6.5) ions and editions.

108 ARRB SR 34,1986


References

AITKEN, A.P. (1975). Hydrologic investigation BATES, M.A., NOLAN, C. and O'LOUGHLIN, G.G.
and design of urban stormwater drainage (1984). Physical modelling and decision
systems. Aust. Water Resources Council making for an urban drainage problem.
Tech. Paper No. 10. (AGPS: Canberra.) Proc. I.E. Aust. Conf. on Hydraulics in
Civil Engineering, Adelaide, pp. 40-43.
ALLEY, W.M., and VEENHUIS, J.E. (1983).
Effective impervious area in urban run- BELL, P.R., BROWN, J.D., GORONSZY, M.C. and
off mode 11 i ng. ASCE Hyd raul i c En g. 109 LACEY, D.T. (1979). Measurement and
(2), pp. 313-19, February. analysis of the effects of stormwater
on the Lane Cove estuary. Proc. I.E.
AMERICAN SOCIETY OF CIVIL ENGINEERS (19 82). Aust. Hydrology and Water Resources
Stormwater detention facilities. Proc. Symposium, Perth, September, pp.254-58.
Conf. co-sponsored by ASCE Urban Water
Resourced Research Council and Enginee- BLACK, R.G. and PIGGOTT, T.L. (1983). Head
ring Foundation. B.Urbonas, editor. losses at two pipe stormwater junction
(ASCE : New York.) chambers. Proc. I.E. Aust. Second
Nat. Local Govt Eng. Conf. Brisbane,
ARANSON, D,A. and PRILL, R.C. (1977). Analy- September, pp. 219-23.
sis of the recharge potential of storm-
water basins on Long Island, New York. BLISS, P.J., BROWN, J.D. and PERRY, R. (1979).
Res, U.S. Geological Survey 5(3) pp. Impact of storm runoff from urban areas
305-18. on surface water quality. Proc. I.E.
Aust. Hydrology and Water Re .:; .)ur ces
ARCHER, B., BETTESS, F. and COLYER, P.J. Symposium, Perth, September, pp. 249-53.
(1978 ). Head losses and air entrainment
at surcharged manholes. Hydraulics Re- BLISS, P.J., RILEY, S.J. and ADAMSON, D.
search Station, Wallingford, Oxon, Rep. (1983). Towards rati onal guidel i nes for
IT 185, 11 pp. urban stormwater disposal into flora
preservation areas. Shi re and Munic-
ARGUE, J.R. (1981). Urban storrTWater collec- i pal Record, July, pp. 181-85.
t i on systems - a revi ew. Aust ra 1 ian
Road Research Board. Internal Report, BOENISCH, M.E. (19 84) On-site detention -
AIR 1093-1. e xperience at Wollongong. Proc.
Seminar on Problems of Existing Storm-
water Drainage Systems. N.S.W. Commit-
ARGUE, J.R. (198 2). Stormwater fl ow estimat-
ion in small ungauged urban catchments. tee, Water Research Foundation of
Australia. G.G. O'LolJghlin, ed itor.
Proc. 11th ARRB Conf. 11(2), pp. 193- Sydney, 28 pp.
205.
BONHAM, A.J. (1974). Storm drainage deSign
ARGUE, J.R. (1984). Design flow estimation in and new city planning. I.E. Aust.
small ungauged urban catchments. Proc. Ci v. Eng. Trans. CEI6( 1), pp. 67-70.
Thi rd Int. Conf. Urban Storm Drainage,
Gotenborg, Sweden, June, pp. t~~-64. BROO KS , L.G. and COC KS, G.C. (19 83). A rat-
Reprinted as ARRB Internal Report, ional approach to the design of storm-
AIR 391-1. wat e r sumps. Main Roads Dept, Western
Au s tra li a , Ma t erials Rep. 8 3/42M.
AUSTRALIAN WATER RESOURCES COUNCIL (19 85). BROTCHIE, J.F. (1977). Urban development
Guidelines for floodplain management in without spoiling creeks. Habitat Aust.
Au st ra 1 i a. Wa ter Ma nagement Se ri es No. Conservation Foundation, 5(1), June,
6. (AGPS: Canberra.) pp. 8 -13.

BANNIGAN, J.M. and MORGAN, D. B. (19 81). BURGI, P.H. and GOBER, D.E. (1977). Bicycle-
Hydraulic design of piped stormwater safe grate inlets study. Rep. No.
systems. Proc. I.E. Aust. Conf. on FHWA-RD-77-24. U.S. Dept. Transp. Nat.
Hydraulics in Civil Engineering, Sydney, Tech. Info. Service, Springfield,
pp. 49-53. Virginia.

ARRB SR 34,1986 109


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

BURTON, T.M., TURNER, R.R. and HARRISS, R.C. DEPTARTMENT OF MAIN ROADS, NEW SOUTH WALES
(1976). The impact of highway construc- ( 1979) . Model analysis to determine
tion on a North Florida watershed. hydraulic capacities of kerb inlets and
Water Resour. Bull. 12, New York, pp. gully pit gratings.
529-38.
DOWD, B.P., IOAKIM, R. and ARGUE, ,l .R. (lq811).
CAMERON McNAMARA (1985). Kensington flooding The simulation of gutter/pavement flows
drainage works investigation. Report on Sou th Australian urban roads. Proc.
to Public Works Dept, N.S.W. Civ. Eng. 10th ARRB Conf. 10(2), pp. 145-52.
Div. Rep. 84030, January.
DURU, J .O. (1982) . On-site detention a
CITY OF FORT WORTH (1967). Storm drainage s tormwater management or mi sma nagement
criteri a and des i gn manua 1 • Prepa red tech nique? Urban Stormwater Qu ality,
by Knowlton-Ratcliff-English, Consult- Management and Planning. B. C.Yen,
ing Engineers, Fort Worth, Texas, editor. Water Resources Pub., Colorado,
December. U.S.A., pp. 341-49.

CLARKE, W.P., STRODS, P.J. and ARGUE, J.R. EARLEY, P.C. (1979). Gully inlet spac ing de-
(19 81). Gutter/pavement flow relation- sign. ' Faculty of Eng. Univ. Western
c;hirc; for rOilrlwilY rhilnnpls of mQriprilt.p Austral i a.
or steep grade. Proc. I.E. Aust. Fi rst
Nat. Local Govt. Eng. Cont., Adelaide, ENVIRONMENT CANADA (19811a) . Proposed rnodel
pp 130-37. policies for urban drainage ma nagement.
Report of the Urban Drainage Policy
COLMAN, J. (1978). Streets for 1ivi ng. Aust- Committee to the Urban Drainage Sub-
ralian Road Research Board. Special cornmi t tee, Envi ronrnenta 1 Protection
Report, SR 17. Servi ce, Envi ronment Canada. Research
Repor t No. 102.
CONCRETE PIPE ASSOCIATION (1985). Concrete
pipe guide. Concrete Pipe Association ENVIRONMENT CANADA (1980b). ManlJ dl of pr'iC-
of Australia, Elsternwick. ti ce for urban drai nage. Envi ronment
Protection Service, Environment Canada.
CORDERY, I. (1976a). Some effects of urban- Research Report No. 104.
isation on streams. I.E. Aust. Civ.
Eng. Trans. CE18(1), pp. 7-11. ESCRITT, L.B. (1965). Sewerage and Sewage
Di sposal. 3rd Ed. (CR Books/Appl ied
CORDERY, 1. (19760). PuLeliLidl vdlue ur Science Publishers: London.)
treatment of urban stormwaters. I.E.
Aust. Ci v. Eng. Trans. CE18(2), pp. FINLA YSON , C.M. (1983). Use of aquatic plants
60 -63. to treat wastewater in irrigation areas
of Austral ia. Proc. 10th Federal Con-
CORDERY , I. (1977). Quality characteristics vention Aust. Water and Wastewater
of urban storm water in Sydney, Austra- Assoc., Session 22, Sydney, 10 pp.
l ia. Water Resour. Res. 13, \pp. 197-
202. ' FORllES, H.J.C. (1976). Capac ity of 1 atera 1
stormwater iql ei:,> . i, ivil I:: ng. South
COUNTRY ROADS BOARD, VICTORIA (1982). Road Africa, 18(9), pp. 195-205. Discussion,
deSign manual. Chapter 6 : Drainage. 19(5), pp. 95-99.

CU LLEN, P., ROSICH, R. and BEK, P. (1978). GORDON, A.D. and STONE, P.B. (1973). Car
A phosphorous budget for Lake Burley stabi 1 ity on road fl oodways. Univ. of
Griff in and management implications for New South Wales, Water Research Labor-
urban lakes. Aust. Water Resources atory, Rep. 73/12.
Council Tech. Paper No. 31. (AGPS:
Canberra. )
GOYE N, A.G. and McLAUGHLIN, D.A. (197 8) . Can
we afford to treat urban stormwater
DANDENONG VALLEY AUTHORITY (19 80) . Melton runoff? Proc. I.E. Aust. Hydrology
drainage study. Master drainage plan Symp. Canberra, pp. 57-61.
prepared for Melton-Sunbury Management
Committee by Dandenong Valley Author-
i ty, March. GOYEN, A.G., MOODIE , A.R. and NUTTALL, P.M.
(1985) . Enhancement of urban runoff
de GROOT, C.F. and BOYD, M.J. (1983). Exper- quality. Proc. I.E. Aust. Hydrology
imental determindtion of head losses in and Water Resources Symp. Sydney, pp.
stormwat er systems. Proc. I.E. Aust. 202 -08.
Seco nd Nat. Conf. on Local Govt. Eng.
Brisbane, September, pp. 214-1 8. GRIGG, N.S., BOTHAM, L.M., RICE, L., SHOE-
MAKER, W.J. and TUCKER, L.S. (1976).
DICK, T.M. and MARSALEK, J. (1985). Manhole Urban drai nage and fl ood control proj-
head losses in drainage hydraulics. ects, economic, legal and financial
Proc. 21st Congo Int. Assoc. Hydraul i c aspects. Hydrology paper, Colorado
Res. Melb ourne, August, Vol. 0, pp. State Univ., Fort Collins, Colorado,
123-31. U.S.A.

110 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

GUTTERIDGE, HASKINS AND DAVEY PTY. LTD. INSTITUTION OF ENGINEERS, AUSTRALIA (1987).
(1981). Characteristics of urban Australian rainfall and runoff. 3rd ed.
stormwater runoff. Aust. Water Resourc- (I.E. Aust: Canberra) (i n press).
es Council. Tech. Paper No. 60. (AGPS:
Canberra. ) IZZARD, C.F. (1946). Hydraulics of runoff
from developed surfaces (and discuss-
GUY, H.D. and JONES, D.E. (1972). Urban sed- ion). Proc. Highway Res. 26, pp.
imentation in perspective. ASCE J. 129-50.
Hydraulics Div., 98(HY 12), pp. 2099 -
116. JAMES HARDIE PTY LTD (1985). Textbook on
Pipeline Design. (James Hardie,
HALL, M.J. (1984). Urba n Hydrology. (Elsevier Sydney)
Applied Science Publishers: Essex, U.K.)

HANNAM, I.D. and HI CKS, R.W. (1980). Soil JOHNSON, R.L. and PUTT, R.A. (1977). Storm
conservation and urban land use plann- wate r retent i on and detent ion. Leh i gh
i ng. Soil Conse rvation Service of Univ. Fritz Eng. Laboratory Report No.
N.S.W. Soil Conser vation, 36, pp . 134- 426 .2 , December, 35 pp.
4S.
JONASSON, S.A. (1984a). Determi nati on of i n-
HAWKEN, H.W. ( 1921) . An analysis of maximum filtration capacity and hydraulic con-
runoff and rainfall intensity, Trans. ducti vity. Proc. 3rd Int. Conf. on
I.E. Aust. 2, pp. 193 - 215. Urban Stonn Drain., Goteborg, Sweden,
June, pp. 1073- 82 .
HEEPS, D.P. (1977). Efficiency in ind ustr ial,
municipal and domestic water use . Aust. JONASSON, S.A. (19 84b). Dimensioning methods
Water Resources Council. Tech. Paper for stormwater infiltration systems.
No. 20 . (AGPS: Ca nberra.) Proc. 3rd Int. Conf. on Urban Storm
Drainage, Gotebo rg, Sweden, June, pp.
HENDERSON, F.M. (1966). Open Channel Flow. 1037-46.
(MacMillan: New York.)
JONES, E.D. (1967). Urban hydrology, a r e-
HENDERSON, F .M., FIELD, W.G. and WILLIAMS, dir~ction. ASCE Civ. Eng. 37(8),
B.J . ( 19 80) . Urban Drainage. Notes for August, pp. 58-61.
a refresher course, Dept. Civ. Eng.
Un i v. Newc a s t 1e , N. S • W. JONES, E.D. (1971). Where is urban hydrology
p ra ct ice today? ASCE Hyd raul i cs Di v.
HENKEL, G.G . (19 81) . Land-use planning must 97(HY2), pp. 257 - 64.
relate to drainage. Proc. I.E. Aust.
First Nat . Local Govt . Eng. Co nf., KARR, J .R. and SCHLOSS ER, I.J. (197 8) . Water
Adelaide, pp. 83 - 89 . re sources and the land-wat er interface.
Science 201, pp. 229-34.
HOLMSTRAND, O. (1984) . Infi ltration of s torm-
water : Research at Chalmers Unive r sity KIDD, C.H.R. and LOWING, M.J. (1979). The
of Technology, results and examples of Wal ingford urban subcatchment model.
application. Proc. 3rd Int. Co nf. on U.K. Inst. Hydrol ogy Report No. 60,
Urban Sto rm Drainage, Goteborg, Sweden, November.
June, pp. 1057 -7 2.
KUICHLING, E. (1889). The relation between
HUGHES, H. (1974). Road surface drainage - a rainfall and the discharge of sewers in
revi ew . Austral i an Road Res earch Board . populous districts . Trans. ASCE 20 , pp.
Research Report, ARR No. 33. 1-60.
ICHIKAWA, A. and YAMAMOTO, T. (1984) . Experi - LAND COMMISSION, NEW SOU TH WALES (1984).
mental field for the quantitative ana- The streets where we live - a ' manual
lysis of the pervious pavement at the for the design of safer residential
baseball field, University of Tokyo. estates.
Proc. 3r d Int . Conf . on Urban Storm
Drainage, Goteborg, Swede n, June, pp. LIGHTHILL, M.J. and WHITHAM, G.B. (1955). On
1009-1 8 . ki nemat i c waves : I. Flood movement in
IN ST ITUTION OF ENGINEERS, AUSTRALIA (1958) . long ri vers. Proc. Royal Soc. Se ri es
Austral ian rai nfall and runoff. Fi rst A, Vol. 229, pp. 281-316.
report of the I. E. Aust. StorllMater
Standards Comm ., Sydney . LINSLEY, R.K. and FRANZINI, J. (1979). Water
resources Engineering, 3rd edition.
INSTITUTION OF ENGINEERS, AUSTRALIA (1983). (McGraw-Hill Kogakusha, Tokyo).
Seminar on retarding basins. Proc. of
seminar organised by Syd ney Division LLOYD-DAVIES,D.E. (1906). The elimination
Water Resources Panel. G.G . O'Loughlin, of storm water from sewerage systems .
editor, 19 April, Sydney . Proc. Inst. Civ. Eng. 164, pp. 41-67.

INSTITUTION OF ENGINEERS, AUSTRALIA (1977). LOGAN CITY COUNCIL (1983). Standard - Storm-
Australian rainfall and runoff. 2nd ed. water Drainage Manhole losses. Chart
(I.E. Aust: Canberra.) A, Chart B, date 11/1/83.

ARRB SR 34, 1986 111


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

McPHERSON, M.B. (1969). Some notes on the O'L OUG HLIN, G. G. an d AVE RY , (i. C. ( 198 0) . Re -
rational method of storm dra inage de - cu rre nce i nt e rval s fo r mi no r urb an
si gn. ASCE Urban Water Resources Re- drain d~e ;%r ~5 . Proc . I.F.. Ao.J5t. Hyd-
s earch Program, Tech. Memor. No. 6 , rology and Water Res ources Symp. Ade l-
New York, January. ai de, pp. 39-4 3.
MAKIN, I.W. and KIDD, C.H.R. (1979). Urban O'LOUGHLIN, G.G. ( 1986 ). The IL SAX program
hydrology project: collection and ar- for urban d rain age desi gn a nd ana lysis.
chive of U.K. hydrological data. Inst. School of Civ. Eng. N. S.W. Inst. Tp' (I I-
Hydrology Report No . 59, October. no l., Sy dnp.j .
MATTHEWS, T.M., PITTS, J.R., LARLHAM, R.C.
PHILLIPS, D.I. (19 85) . An e valu at ion of the
and KOCSAN, J. C. (19 8 3). Hyd ro-brake performan ce of an on-site st o rmwater
regulated storage system for storm- detention storage. Proc. I.E. Aust.
water management. Snell Envi ronmental
Hydrology and Water Resources Symp.
Group Inc. for Cleveland Dept. Public
Utilitie s , Ohio. Sydney, May, pp. 197-201.

MELBOURNE AND METROPOLITAN BOARD OF WORKS POLIN, M.J. and CORDERY, I. (1979). An eco-
(19 81). Interim drainage basin manage- nomic approa ch t o t he -;,~ l ect i o n o f a
ment criteria manual. design flood. Proc. I.E. Aust. Hydro-
logy and Water Resources Symposium,
MILLS, S.J. and O'LOUGHLIN, G.G. (19 84). Perth, September, pp. 194-98 .
Workshop on urban piped drainage sys-
tems. Swinburne Inst. Technol./N.S.W. POERTNER, H.G. (197 3). Pract ices in deten-
Inst. Technol., Melbourne. tion of urban s torm water runoff. U.S.
Dept Interior, Washington, D.C.
MOODIE, A.R. (1979). Modelling of water
quality and hydrology in an urban PUBLI C WORKS OEPARTMENT, NEW SOUTH WALES
watercourse. Aust. Water Resources (1985). Hydraulic capacities of gutter
Counci 1 Tech. Paper No. 45. (AGPS : inlets for N.S.W. Housing Commission.
Canberra. )' Manly Hydraul ics Laboratory Rep. 419,
January.
MAIN ROADS DEPARTMENT, QUEENSLAND (1980) .
Urban road design manual. RAGAN, R.M. and DURU, J.O. (1972). Kinematic
wave nomograph for time s of concentra-
MULVANEY, T.J. (1851). On the use of self tion. Proc. ASCE, J. Hydraulics Div.
registerinq rain and flood gaugps in 98(HY10), October, pp. 1/6~-/1.
making observations on the relation of
rainfall and of flood discharges in a REID, J. (1927). The estimation of stormwater
given catchment. Trans. Inst. Civ. discharge. J. Inst. Municipal County
Eng., Ireland, 4(2), pp. 18-31. Eng. (U.K.) 53(23), pp. 997-1021.
MURPHY, C.B., MacARTHUR, D.A., CARLEO, D.J., RILEY, D.W. (1932). Notes on calculating the
QUINN, T.J. and STEWART, J.[. (1981). t low of surface water in sewers. J.
Best management practices implementa- Inst. Municipal and County Eng. (U.K.)
tion : Rochester, New York. U.S. Env. 58(20), pp. 1483-95.
Protection Agency Report PB-82-171-067,
Chicago IL, April. ROBINSON, D. and O'L OUGHLIN, G. G. (19 83).
Introduction - what is a retarding
NATIONAL CAPITAL DEVELOPMENT COMMISSION basi n? Proc. I.E. Aust. Semi nar on
(1981). Guidelines on engineering and Re ta r d i ng ~a., i 11 ') . Organi sed by Sydney
environmental practices - hydraulics. Division Water Resources Panel. G.G.
O'Loughlin, editor, Sydney, April.
NATIONAL WATER COUNCIL AND U.K. DEPARTMENT OF
ROSS, C.N. (1 921). The calculation of flood
THE ENVIRONMENT (1981). Design and
analysis of urban storm drainage, the discharges by the use of a time contour
Wallingford procedure. National Water plan. Trans. I.E. Aust. 2, pp. 85-92.
Council, Vol. 1-5, London. ROWBOTTOM, I.A., PILGRIM, D.H. a nd WRIGHT,
G.L. (19 86). Estimation of rare floods
NEW SOUTH WALES HOUSING COMMISSION (1976). (between the probable ma ximum flood and
Road manual. the 1 in 100 flood). I.E. Aust. Civ.
Eng. Trans. CE2 8(1), pp. 92-105.
NICHOLAS, 0.1. and COOPER, G. ( 1984). On- s ite
detent ion - experi ence in Ku ri ng-Ga i • SANGSTER, W.M., WOOD, H.W., SMERDON, E.T. and
Proc. Seminar on Problems of Existing t3 0SS Y, H. G. ( 19'18) . P r ~ssu re c hanges
Stomwater Drainage Systems, N.S.W. at stormwater drain junctions, Bull.41,
Committee, Water Research Foundation of Eng. Experiment Station, Univ . Missouri,
Australia. G.G. O'Loughlin, editor, U.S.A.
Sydney, 21 pp.
SATOR, J.D., BO YD, G. B. and AGA RDY, F.J.
NOVA K, P. and NULLURI, C. (1984). Incipient ( 1974). Water pollution aspe cts of
motion of sediment particles over fixed stree t su rfa ce c ontami nants. .J. Water
beds. J. Hydraul ic Res. 22(3), pp. 181- Pollution Control Federation 46, Wash-
97. ington D.C., pp. 458-67.

112 ARRB SR 34,1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

SCHAAKE, J.C., GEYER, J.C. and KNAPP, J.W. UNITED STATES ENVIRONMENT PROTECTION ADMINIS-
(1967). Experimental examination of TRATION (1972). Guidelines for erosion
the rational method. ASCE J. Hydraul- and sediment control planning and
ics Div. 93(HY 6), pp. 353-70. implementation. U.S. Env. Protect.
Admin., Washington.
SCOTT AND FURPHY PfY LTI) (1 9fl4). Eng i neeri ng
standards for residential land develop- VALLENTINE, H.R. (1967) . Water in the Service
ment. Report prepared in association of Man. (Pengui n Books: Hamondsworth.)
with Coopers & Lybrand Services for
Dept Housing and Construction. (AGPS:
Canberra. ) van DAM, C.H. and van de VEN, F.H.M. (1984).
Infiltration in the pavement. Proc.
SIEKER, F. (1984). Storrrwat er infiltration in 3rd Int. Conf. on Urban Storm Drainage,
urban areas. Proc . 3rd Int. Conf. on Goteborg, Sweden, June, pp. 1019-28.
Urban Storm Drainage, Goteborg, Sweden,
June, pp. 1083-91. WALKER, J.H. (1979). Characteristics of
pollution in urban stof'mllater runoff.
STEPHENSON, D. (1984). Stof'mllater hydrology Proc. I.E.Aust. Hydrology and Water
and drainage. (Elsevier Applied Science Resources Symp . Perth, pp. 244 - 48.
Pub Ii shers: Jlms terdam. )
STORM DRAINAGE RESEARCH COMMITTE E (1956). The WANIELISTA, M.P. (1979). Stormwater Manage-
deSign of stormwater inlets. Report of ment - Quantity, Quality. (Ann Arbor
the Storm Drainage Research Committee Science, Michigan).
of Dept. of Sanitary Eng . and Water
Resources, Johns Hopkins Univ. Balti- WATER RESEARCH FOUNDATION (1984). Seminar on
more, Maryl and, June. problems of existing stormwater drain-
age systems. Proc. Seminar organised
TERSTlUEP, M.L. and STALL, J.B. (1974). The by N.S.W. Committee of WRF of Austral-
Illinois urhan drainage Mea -; i.nulator, ia, 28 November. G.G. O'Loughlin, edit-
ILLUDAS. Bull. 58, Illinois State Wat- or, Sydney.
er Survey, Urbana, U.S.A.
THEIL, P.E. (1977). Urban drainage design for WATSON, M.D. (1981). Application of ILLUDAS
new deve I opnent. Proc. Urban Dra i nage to stormwater drai nage desi gn in South
Conf. Organi sed by the Urban Drai nage Africa. Rep. 1/81, Hydrological Re-
Subcommittee, Environment Protection search Unit, Univ. Witwatersrand,
Servi ce, Envi ronment Canada, Toronto, Johannesburg.
March.
WATTS, B.A. (1983). Hydraulic losses in
THOLIN, A.L. and KEIFER, C.J. (1960). Hyd- stormwater pits.
rology of urban runoff. Trans. ASCE
125, pp. 1308-79. WEBER, W.G. and REED, L.A. (1976). Sediment
runoff during highway construction. J.
THOMPSON, D.G. (1983). The one percent prob- ASCE Civ. Eng. 46(3), pp 76-9.
ability flood as a basic drainage de-
sign criterion. Proc. I.E. Aust.
Second Nat. Conf. on Local Govt. Eng. WHIPPLE, W., GRIGG, N.S., GRIZZARD, T., RAN-
Brisbane, September, 1983, pp. 207-13. DALL, C.W., SHUBINSKI, R.P. and TUCKER,
L.S. (1983). Stormwater Management in
TOUBIER, J.T. and WESTMACOTT R. (1980). Urbanising Areas. (Prentice Hall,
Stormwater management alternatives. Englewood - Cliffs)
Water Resources Centre, Univ. Delaware,
Apri 1.
WILLING AND PARTNERS PTY LTD (1978). Canberra
ULI/ASCE/NAHB (1979). Residential storm water stormwater system: side entry pit cap-
management. Report by Urban Land In- acities - field assessment. Final draft,
stitute/Am. Soc. Civ. Eng/Nat. Assoc. July. National Capital Development
of Home Builders, Washington, March. Commission, A.C.T.
UNITED STATES OEPARTMENT OF TRANSPORTATION WOLMAN, M. and SCHICK, A.P. (1967). Effects
(1978). Best management practices for of construction on fluvial sediment,
erosion and sediment control. U.S. urban and suburban areas of Maryland.
Dept. Trans. Fed. Hi ghw. Admin., Wash- Water Resources Res. 3, pp. 451-64.
ington.
UNITED STATES DEPARTMENT OF TRANSPORTATION WRIGHT-McLAUGH LIN, ENGINEERS (1969). Urban
(1979). Design of urban highway drain- storm drai nage. Cri teria manual, Vol s
age - the state of the art. U.S. Dept. 1 and 2. Denver Regional Counci I of
Trans. Fed. Highw. Admin., Washington. Govts, Denver, U.S.A., March.

ARRB SR 34, 1986 113


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

114 ARRB SR 34,1986


Appendix A

Additional hydraulic data

The gutter/pavement and inlet exampl es used LEVEL 1 Flow/capture relationships formed
in the body of the Handbook to illustrate from at least two independent sets
major and minor storm drainage design pro- of test results obtained for inlet
cedures are not employed universally in Aus- cases (models or prototypes) having
tralian practice. Additional hydraulic in- identical or similar geometries.
formation for other widely used gutter/pave- Unbroken 1ines or curves are used
ment geometries and inlet types is therefore to present Levell data in Appendix
needed. Appendix A presents hydraulic data A.
for four roadway reserve and i nl et combi na-
tions which, together, account for the bulk LEVEL 2 Flow/capture relationships derived
of Australian practice. from one set of test results ob-
tained for a particular inlet case
In most cases the following data are (model or prototype) supported by
presented:- results obtained for inlet cases
(models or prototypes) having diff-
(a) roadway reserve (half-carriageway) flow, erent geometries. Broken lines or
Ot, versus longitudinal slope, So, limit- curves with long intervals between
ed by Criteria 1 and 2 of Section 6.1, breaks are used to present Level 2
text (see eqns 6.10 and 6.11). Data are data in Appendix A.
presented for carriageway half-widths of
4.0 m and 5.0 m, Zb = 25 - 30-40. These LEVEL 3 Flow/capture relationships inferred
data are needed to pl an major drai nage from test results obtained for
systems (see Chapters 8 and 9). inlet cases (models or prototypes)
having different geometries.
(b) half-carriageway flow, Ot, versus longi- Broken 1i nes or cur ves wi th short
tudinal slope, So' for spreads of 1.0 m, intervals between breaks are used
2. 0 m and 2.5 m, Zb = 25-30-40. to present Level 3 data in Appendix
A.
(c) grat ed inlet data , Zb = 25-30-40 :
In short, Level 1 data may be regarded
o on-grilc1f' inlets, full gutter wi dth as 'dependable', Level 2 data as 'satisfac-
(undepressed), capture 80% and 95%. tory' and Level 3 data as 1 ittle better than
informed guesses. A side benefit of Appendix
o sag inlets,Lig = 1.0 m, 2. 0 m (un- A is its indication of the directions which
depressed), capture 100%. inlet test programmes should take in order to
improve the reliability of urban drainage de-
(d) side-entry inlet data, Zb = 25-30-40 : sign in Australian practice.

o on-grade inlets, Lis = 1.0 m, 2 . 0 m, Performance data presented in Appendix A


depressed 50 mm, with and without for side-entry inlets with deflectors assume
deflectors, capture 8 0% and 95%. deflectors similar to those illustrated in
Fig. 6.5, text. Minor departures from this
o sa(] inlets, lis = 1.0 m, 2.0 m, de- arrangement will result in marginal changes,
pressed 50 mm, capture 100%. only, to indicated performance.

Data items (b), (c) and (d) above are The mai n di fferences between the four
needed to design minor drainage systems (see roadway reserve and inlet combinations add-
Chapters 10 and 11). ressed in Appendix A relate to their roadside
channel geometries (see Fig. 3.7). These
The data relating to inlets are not of are: -
equal quality. Some graphs and tables present
results obtained from substantial test pro- TYPE 1 concrete gutter, 300 mm wi de, cross-
grammes conducted on full-size models while slope Za = 10
others present information inferred from
tests on mOdels having different geometry.
Three levels of data qua lity have been recog- TYPE 2 conc rete gutter, 375 mm wide, cross-
nised:- slope Za = 8

ARRB SR 34. 1986 115


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 3 concrete gutter, 450 mm wi de, cros s- N.S . W. (l979); Earley (l979); Burgi and Gober
slope Za .. 12 (1977); Storm Drai nage Research Committee of
John Hopki ns Uni versity (l956) ; Henderson et
TYPE 4 : no gutter, pavement carried to kerb al (1980) ; Willing and Partners (l978); Hughes
(1974); Public Works Department, N.S.W.(1985} ;
All data for each type and combi nat i on Forbes (1977) ; United States Department of
are presented together. Transportati on (l979). Additi onal data have
been obtained from full-size rig tests conduc-
The following references form the liter- ted in connection with preparation of the
ature data base for the graphs and tables set Handbook at S.A. Institute of Technology in
out in Appendix A : Department of Main Roads, Adelaide.

TYPE 1 GUTTER/PAVEMENT PROFILE


TABLE Ala
CAPTURE BY ~ GRATED INLETS : Za = 10
(DATA QUALITY - LEVEL 2)

Zb = 25 - 30 Zb = 30 - 40
95% capture : 95% capture:
gutter approach fl ow, Qt = 10 Lis gutter approach fl ow, Ot= 8 Lis

80% capture : 80% capture :


gutter approach flow, Qt = 22 Lis gutter approach fl ow, Qt '= 18 Lis

Notes: 1. grated in 1et - full gutter width with transverse bars


2. length not less than 0.75 m
3. grating open area not less than 60% of total area
4. gutter longitudinal grade, So, not greater than 0.05
5. grated inlet not depressed; no kerb opening
6. Listed flow values are conservative but make no allowance
for blockage.

TABLE Alb
CAPTURE AT 1.0. AND 2.Dm SAG INlETS (GUTTER 300..)
(DATA QUALITY - LEVEL 2)
-- -
DESCR I PTI ON Zb = 25 - 30 Zb = 30 - 40
loOm grated inlets (undepressed)
allowable spread = 2.0 m 40 Lis 29 Lis
allowable spread = 2.5 m 59 Lis 42 Lis

2.0 m grated inlets (undepressed)


allowable spread = 2.0 m 65 Lis 47 Lis
allowable spread = 2.5 m 96 Lis 68 Lis

1.0m side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 46 Lis 37 Lis
allowable spread = 2.5 m 60 Lis 47 Lis

2.0 m side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 92 Lis 74 Lis
allowable spread = 2.5 m 120 Lis .94 Lis

Notes:
1. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.

2. Grated inlets - 300 mm wide


3. Grated open area not less than 60% of total area.

116 ARRB SR 34,1986


STORM DRAINAG E DESIGN IN SMALL URBAN CATCHMENTS

TYPE 1 GUTTER/PAVEMENT PROF ILE


1300 1300
300mm 3-70m 10 l .1 300mm 4}Om to l J
1200
~U Hotmix pavement
i 1200
-T:'U Hotmix pa ve ment
i
J~
(oncrete4 Contrete

1100
Kerb&Gutter I: . ,: ~
_\ ;:::2:::]' Zb = 25,30 or 40
--,
i 1100
Kerb& Gu lle ; 1
_:;:;:2:::'::f
--
Zb = 25,30 or 40
J
I
f/ ""r--, Za = 10
(each casel Gutter/ Pavemen t Profile jj ~ Za=10
(each case) Gutter/Pavement Profile

g ""'-
~ J WI'\. ~
~ /
900 900

J / "'" .......... ~ ~
'"
..........

II/I ~ "'"
IIrl ~,~
i'-.
~
.............
I'----
~
~
b r!-.J t:
~,

~
r--
Ci 800
~
U:: 700
~

lg'600 'I I
i'--
I II ~ " ~ ~
~
.............
""
-............
r. -
7~
~ 'O 2 ~-

?iJ~.3, ---- r---- -


- r-- ----
'-...... K r---- ~ 500 'IL '-...... ---..,
/// I-- --.1.t, '2<
---- r---
11....,25
-----
400
f
/--- Co-.

NOTE , For fI ~sh se I car iagewa s red ce


indica ed flo val u s by 8%
r--- 400
'I
I
NOTE , For II sh 5e I carri geway redu e
indica ~ d /1 0 v alu~ s by 1 %
--- r-- --- -
300 300

200 0 -01
I
-02 -03 -04 -05 -06 -07 -08 -09 -10 -11 -12 01 02 -03 -04 -05 -06 -07 -08 -09 -10 -11 -12
Gu ller Longitudinal Slope, So Im/ml Guller Long itud inal Slope, So Im/ml
Figure Al a : Hydraul ic ca pacity, Q.t , data for 8-0 m carri agewa y - Figure Al b: Hydraul ic capacity, Q.t, data for 10 -0 m carriageway
with 300 mm gutter with 300mm gutter

120 120
Gutter Inlet Hydraulic Oata Gutter Inlet H ~rau1i c Dat a
Capt ure performance of lOrn and 2-0m side- entry Capture per formance of "O m and 2 'Om side-entry
in le ts 'W it h and with out deflectors inlets with and without def lectors
11 0 110
~

,.I i
N
TYPE 1
"
I .~
N

E 150mm
:_:~ .. --~
Za =10 -'l
100 100
:;'" Zb= 30-40
Gutter/Pavement Profile Gutter/ Pavement Profile
~OTES NOTES
90 90
!L~ l.Inlets without deflectors ; lip deprf'ssed SOmm bet o...
gutter invert fel" fu ll length.li.s.
0 1.lnlets wit hout deflectors ; lip depressed 50mm be 10'"
gutter invert for full length.li.s.
H-I'+-I""--t--t- - t---
J ~_ N 2. lnlels witI'! def lectors: lip depressed SOmm, deflector
IL~
2. lnlets with def lectors : lip depressed SOmm, deflector
base depre ssed 100 mm below gutter invert . E fI base depressed 100 mm below gutter inver t .

1 1
60 80
IJ.: [ :7 3. App roach flow,Ot for inlet 21ength , Lis. other than 1·0 m
'"" €/ 3. Approach flo .... Ot for inle t 1lenqth . Lis. other than ' ,0 m
I-tHr"
I--f"I'--+ - +--I an d 2·0 m varies as ILL s t, appro)o mately.
<::
~
I! 4. tnle t widt h equals gutter width in all oases . <:: ~/I~
and 2·0 m va r ies as Ills l, approximaiely.
4. tnle l ... idth equals gutter width in all cases .

70 70
<0>
~ f c;
~
'Ii
3:
~ z
60 60
~ ~
r r
'<t
&'
:l: 50 0% Captu le
'<t
&'
:l: 50 .1
.:! .:!
'#-.
~ ~ W '"..-- :-
~
40 , ~
40 - f__- I-- f - f-- - ~O% aptu
~
~
-,
~

30
~

30
"'" I~ I

20 I
t
b :Z
........ ,

~~
"-
,,~

~ ~ "-
' . iX
~~
....11,
Q~
-- r - r-

--
\:,v-- 8O~ c.-=- :::-:... :::::-::.
-'-- BO,
""""" .!!CL
~

~
-
10

1/ ~- -....§. % (a
-:-!.: ..£a.2,!
~ I!!.J, ~ '- '- '-
- L ~ ~o/'!... a1!!.ur n-~-~---_ L _r-_=- _I- ­ I \: ~ --
~
2l~ ~t!!! e _ ;;1Z --
o o~-'--:-,:-:--\-,,",V~-'----'--...l:..-~-,-r_---L-_--1
-_-'-_-_-"-'-
~ -.:..:::.cf--=-.=l
-=-:..
- -:::L:..::..;.J o --=- r - - r- - --- =-
0-02 0-04 0-06 008 0-1, Q 11 0-", o 0-02 0-04 0-06 0-06 0-10 0-12 0-14

GUTfEr, LONGITUOI NAL SL OPE So I mimi GUTTER LONGITUDINAL SLOPE So I mimi

Figure : A1c Collation of spread and gutter inlet hydra uli c Figure : A1d Collation of spread and gutter in let hydrau li c
data - 300 mm gutters, Za =10 data - 300 mm gutters, Za = 10

ARRB SR 34,1 986 117


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 2 GUTTER/PAVEMENT PROFILE

TABLE A21
CAPTURE BY 37~ GRATED IILETS ZI .. 8
(DATA QUALITY - LEVEL 2)

Zb = 25 - 30 Zb = 30 - 40
95% capture:
I 95%capture :
gutter approach flow, Qt 24 LIs I gutter approach flow, Qt 22 LIs I
80% capture:
gutter approach flow, Qt = 52 LIs
80% capture:
gutter approach flow, f)t 43 LIs I
Notes: 1. grated inlet - full gutter width with transverse bars
2. length not less than 0.75 m
3. grating open area not less than 60% of total area
4. gutter longitudinal grade, So, not greater than 0.05
5. grated inlet not depressed ; no kerb opening
6. Listed flow values are conservative but make no allowance
for blockage.

TABLE A2b
CAPTlItE AT 1.0. AND 2.0. SAG IILETS (GUTTER 31.>
(DATA QUALITY - LEVEL 2)

DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undepressed)
allowable spread = 2.0 m 40 LIs 30 LIs
allowable spread = 2.5 m 61 LIs ~~ L/5
2.0 m grated inlets (undepressed)
I
allowable spread = 2.0 m 63 LIs 47 LIs
allowable spread = 2.5 m 96 LIs I 69 LIs

l.Om side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 57 LIs 47 LIs
allowable spread = 2.5 m 72 LIs 59 LIs

2.0 m Side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 114 LIs 94 LIs
allowable spread = 2.5 m 144 LIs 118 LIs

Notes:
l. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage . I
2. Grated inlets - 375mmwide
3. Grated open area not less than 60% of total area.
I
I

118 ARRB SR 34. 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 2 GUTTER/PAVEMENT PROFILE

1~r-~--~--~--r-~-----37-
5-------
3 -
61-
5m--to--l----I--~ 1300
375mm H15m to l J
1100 ~_-i-_+_+_-L_--' "., J mm Hotmix pavement 1200
Concrete-+'; ~J Hotmix pavement
i
Concrete --+,:
Kerb&Gutter ;' ...-<:+--:===::;;:;;~:::::::::==:i
,., I Kerb&Gutfe, .';fg . I I
1100 - - ---I-- . :i.,::22:::J Zb = 15,30 or 40 1100 Zb = 15,30 or 40

11000 _ _ .--k ------ .. Za = 8


_. Ieach casel Guttir/Pavement Prof il e /\
Za = 8
leach easel Gutter/ Pavement Profile

~
_
900 ~~/ . ~"
_ '"
-
"""
-. ~TE ~l~-;.;b
l carriapeways. redu ce
·ind ic at .d flow values by 1, % 5
900 -

!/ "-
l/ \ \.
~DTE , or ttu h sea carri geway reducF
ndicat d flow values by 15 ~.

~800 --1 / K - ;- I I 5 800


'" - 1 --+-1- i II / ~ '" ~
(//~ "'~~d-
· ~"l , . III u:: 700
~

i -{(! ~::~ =:~~1}-<.k!'-4.""·i~ "" """'" ~


:700
b, "<
~;-'I:--+I--
-+--+--l ~ II /
I~-
600 ~600
"'-.. ~
"Z
~

---r----- ---- -
500~~~~·~~~---~1-·~~-+--~~~---+---r---F~~ ~
__ 500 ~ '-----4 -30
' ---
~
400 --
I! --~Rl--r--r--..
__ ___ 400
1//, ------
~
~ t--
Ii I I --r--....L. I
'/ ! r--
I
- - r-.
300 f i 300

I
100 0 . 01 ·01 03 ·04 ·05 ·06 ·07 ·08 ·09 ·10 11 ·11 01 01 03 04 05 06 07 08 09 ·10 ·11 11
Gutter Longifudinal Slope, So Im/ml Gutter Longitudinal Slope, So (m/ m)

Figure A2a : Hydraulic capacity. Ut. data for 8·0 m carriageway Figure A2b : Hydraulic capacity, Ut. data for 10 ·0 m carriageway
with 375 mm gutter with 375 mm gutter

Gutter Inlet Hydraulic Dah Gutter Inlet Hydraulic Oata


Capture performance of 1'Om and 2'Om side-entry CC!pture performance of lOm and 2·0m side-entry
inl eis with and without de flectors inlets with and withou t deflectors

TYPE 1 TYPE 1

"I i
1S0m~_.".;.._ _ _ _ _ _ _ __
::. ~;;? 'I Zb=25-30 Zb~ 30 - 40
Gutter / Pavement Pro f ile Gutter/Pavement Prof de
N T IiQlI.S
180 0
tlnlets 'WItt-out deflect ors : lip de;l;;~~ed 50mm bel o.... . ~ : . Inlets without deflect"" lip dep'essed SOmm belCl'"
gutter invert for 1ull length.li.s . gu tter invert for full l ength.l~s .
12 Inlets with de1iectors : lip dep ressed I)Omm, defl ec tor [2. lnlets wi!h deflectors : li p depressed SOmm, deflec tor
base depressed 100 mm bel ow gutter IO vert base depressed 100 mm belo.... gutter in vert
160 0

1
3. Approach ftow: Qt. for Inlet ie ngth, l i s. other than 1-0 m
and 2·0 m vanes as Ills l. app rOXImately.
4. lnle t WIdth equals guller Width in all cases .

~ 140 140 / ...

0 ~/
z
110 ~ 120
ff
~

or
,~ :

<{
:;'" ~
I 100
I fI
"""'"
~
80 '" 80
I IAr;; "" """ .......
i I '-V

I 'ii'",
,

~ =>
'" I ,,' <:> V"
~~
~
2~
ani,
:::::::::: 95% (aptu e
60
60
b$ .:..~ """
"'"
11<_
'-.... ~
40 ff "- --........ ~
.........
11/ . ~
~ ~ ~", 'E ~
10
/
'>t ~~.......
K J-.ZS· \: t} -- t--
~ K:" r--- N % Ca
~
~ ~~

0
0 0·01 0·04 rJ06 OOb rJ1f. (J1l (I V.
o
o 0·01
--- L
\.
0·04
" 5% a fur

0·06
'-1.
0·08 0·10 0·11 0·14

GU [[,, ' LONGITUDINAL SL OP E S, I mimi GUTTER LONGITUD INAL SLOPE So I mimi

Figure : A2c Collation of spread and gutter inlet hydraulic Figure : A2d Collation of spread and gutter inlet hydrauli c
data - 375 mm gutters, Za =8 data - 375 mm gutters, Za = 8

ARRB SR 34, 1986 119


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 3 GUTTER/PAVEMENT PROFILE

TABLE A3a
CAPTURE BY 4~ GRATED INlETS Z. 12
(DATA QUALITY - LEVEL 1)

1
Zb = 25 - 30 Zb = 30 - 40
95% capture: 95% capture:
gutter approach fl ow, Qt = 23 Lis gutter approach flow, Qt = 22 Lis

80% capture: 80% capture:


gutter approach fl ow, Qt = 54 L/s gllt.ter approach fl ow, Qt - 47 Lis

Notes: l. grated inlet - full gutter width with transverse bars


2. length not less than 0.75 m
3. grating open area not less than 60% of total area
4. gutter longitudinal grade, So, not greater than 0.05
5. grated inlet not depressed; no kerb opening
6. Listed flow values are conservative but make no allowance
for blockage.

TABLE Alb
CAPTURE AT 1.Om AND 2.0. SAG INLETS (GUTTER 45nm.)
(DATA QUALITY - LEVEL 2)

DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undepressed)
allowable spread = 2.0 m 41 Lis 29 Lis
allowable spread = 2.~ m 63 L/~ 45 Lis

2.0 m grated inlets (undepressed)


allowable spread = 2.0 m 63 Lis 45 Lis
allowable spread = 2.5 m 95 Lis 68 Lis

l.Om side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 47 Lis 39 Lis
allowable spread = 2.5 m 61 Lis 50 Lis

2.0 m side-entry inlets (depressed 50 mm)


allowable spread = 2.0 m 94 Lis 78 Lis
allowable spread = 2.5 m 122 Lis 100 Lis

Notes:
1. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.
2. Grated inlets - 450 mm wide
3. Grated open area not less than 60% of total area.
________________________________________________ 1

120 ARRB SR 34,1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 3 GUTTER/PAVEMENT PROFILE


1300 1300
45 0mm 3' 55 m to l 450mm 4·55 m 10 l [

1200
(o ner.t,
Kerb & Gu tt , ; ;
.T J "" .'
Hotmix pa ve ment
i
I
1200
(o ner.t • .'iC J Hotmix pa vement
i
1100 ;i~' Zb ~ 25,30 or 40 1100 --,.1'" Kerb & Gutt';1 :1¢ v
Zb:25 , 30 or 40
I

!::~ '\
Ii?
Za ~ 12 Za = 12
Ji {each casel Gutter/Pavement Profil e l each case I Gutter/Pave ment Pro file

900 ~
§
"'~" ~ ~
- --r= 900
iJ
'" r-.....

~
~ iI ~ I ~ "-
(

5 80Or-- ""- 5- 800 ~


~~ ~
N ~
~
~ ~ / // ~o
u:,.. 700
~

1 7b600
l/;'/ ~
-"-
~<'
~-4.« ~
~V
~
'ru--
----- -
u:,.. 700
~
~ 600 Lrl "" "'" ~ "'-
~
'6_
'0"--£. ~

-----
--
"'- .......
~
5 f//
500
V ---+- - ;----
500
ij
...............
'--.......<' < ><

---- -----
r---
-r--
400 f-- f-- -
NO TE , For fl sh sea carri eways redu(
----- - ; - - - 400 -
NOTL For fl sh sea carri gewa ys reduc
r----
300
I indica ed flo va lue by 1 %
300
ndica d flo value by 1 V.

~ M ~ ffi ~ ~ .~ " 10 ·11 12 01 0 20304ffi~07 08 09 ·10 ·11 ·12


Gutter Long itudinal Slop., So (mi mI Gutter Longitudinal Slop. , So [mi mi
Figure A3a: Hydrau li( (apacity, a.t , data for 8·0 m carriageway Figure A3b : Hydraul ic capacity, a.t, data for 10 ·0 m carriageway .
wi th 450 mm gutter with 450mm gutter

Gutter Inlet Hydraulic Oata Gutter Inlet Hydraulic Oat a


Capture performancE! of 1·0m an d 2'Om side - entry Capture performance 01 l'Om and 2'Om side - entry
inl ei s with and without defledor s inlets .... ith and without de1 1edors

TYP E 3 TYP E 3

Gutter/ Pavement Profile Gutte r/ Paveml!nt Pro fde

180 =S 180 IiIlill


1. Inlets without defl ectors : lip dep ressed 50 mm below llnlels without de f lectors ' lip de press ed SOmm be low
I gu tter in vert for f ll ll length .li.s. gutter invert for fu ll length , Li.s

160 I 2. lnle ts with deflectors : lip de presse d SOmm, de f lector


base depressed 100 mm be low gutt er invert
2. lnle t s wit h de flect or s : li p dep ressed ~ Omm , deflect or
base de pre ssed ' 00 mm below gutter inve rt

1
' 60

1; '40
?j 3. Approach flo lo', Qt. for inle t llength,l i s . ot her than 1-0 m
and 2·0 m varies as ILL \ 1, apprOlO mate\y.
4. lnle t width equals gutter width in all oa ses.
.

~
' 40
;I'l
3. App roach flow, Qt, for inlet 2lenqfh, Li..s , other than ' ,0 m
and 2·0 m vari es as IL L 5 I, ap pr oXI mately.
4. lnl et WIdt h equals gutter width in all cases.

i5 :>:JI i5
1
z
120
,;t- hL 80"1. Capt re ~
z
120
q
::"
o/l ............. ~ ::"
r;..........
r

i --- h
I
1lO'I. aotur
~"""II
I
--
';;/. 80~ Ca ur ......... W
f 100
I~
S
100
:---
S
l :if II ~
I it '" 8• Ca otu e ~

~ 1'.§
~ ~
I il~ ~

cr 80 cr 80

=>
'"
60
I I 'if- r--
'j~
1/ , .... ,
-- 95·

95·~
Ca ure

Ca ure "\
~
-:u
~ =>
'"
60
I fIJi
I [I

ff ,;¥
---
'.i !

I I--.
,95%

9 • Ca
(, ptu

ur.
\.L.
~
~2_

1/ .... , "- .....


ff:! K
.....
40
' )1f
;:,.-. .... - -- -- 40
/11 "
r--.. .
..... 1'-

-- -- --
'/ kV ~
...... - "---> 2b!r ~~~
/ V..-:1 .....
- "- --''- ~I!i.' --
~
20

2. ~ -- -- -- r=::;. --¢. ~
......
.LI 20

.,/.~ ~'"
'* 1' ...... --'" ~£,

o
o 0·02
-- tt bQ" - --
0-04
- -
€Q.~ Coot

- ~.~ ~~ .~\
0·08 0" 0
95% ~t u

0·12
-
e
c--- f-- -
~'4
o
o 0'02
-R:; 0·04
1- _ ~ % C.ot

1-- <.2",,- ~!!!!


0-06
-
Ir--..

0·08
~e

~ r - -- - - - - -
-::::!",-
-~ ~

0" 0 0·12
~

~' 4

GUTT ER LONGIT UO INAL SLOPE So {mimI GUT TE R LONG IT UO INAL SLO PE So (mimi

Figure: A3c (ollation of spread and gutter inlet hydraulic Figure : A3 d (ollation of spread and gutter inlet hydraulic
data - 450 mm gutters, Za = 12 data - 450 mm gutters, Za = 12

ARRB SR 34,1 986 121


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 4 GUTTER/PAVEMENT PROFILE

TABLE A4A
CAPTURE BY soo. GRATED I ...ETS : NO GUTTER

(DATA QUALITY - LEVEL 1)

Zb = 25 - 30 Zb = 30 - 40
95% capture : 95% capture:
gutter approach fl ow, Qt = 10 Lis gutter approach fl ow, Ot = 6 Lis
80% capture: 80% capture :
gutter approach fl ow, Qt = 26 Lis gutter approach fl ow. Ot = 17 Lis

Notes: 1. grated inlet - bars transverse


2. length not less than 0.75 m
3. grating open area not less than 60% of total area
4. gutter longitudinal grade, So, not greater than 0.05
5. grated inlet not depressed; no kerb opening
6. Listed flow values are conservative but make no allowance
for blockage.

TABLE A4b
CAPTURE AT 1.0. Aft) 2.0. SAG INlETS (NO GUTTER)

(DATA QUALITY - LEVEL 2)

I I
DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undep ressed)
allowable spread = 2.0 m 41 Lis 30 Lis
allowable spread = 2.5 m 63 Lis 45 I I"
2.0 m grated inlets (undepressed)
allowable spread = 2.0 m 62 Lis 44 Lis
allowable spread = 2.5 m 95 Lis 68 Lis
l.Om side-entry inlets (depressed 50 mm)
I
allowable spread = 2.0 m 31 Lis 23 Lis
allowable spread = 2.5 m I 44 Lis 31 Lis
2.0 m side-entry inlets (depressed 50 mm)
allowable spread = 2.0 m 62 Lis 46 Lis
allowable spread = 2.5 m 88 Lis 62 Lis

Notes :
l. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.
2. Grated inlets - 500 mm wide
3. Grated open area not less than 60% of total area. I
I

122 ARRB SR 34, 1986


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

TYPE 4 GUTTER/PAVEMENT PROFILE


1500 1500
4-0 m tQ t I 5-0 m to l I
I !\
1400
Conc rete
Kerb -
.q
..'
Hotmix pavement

-:J
i
i
1400

~ ~
(omret~l
Kerb -:'.
Hotmlx pavement

S i
i
1300

~
" /r Zb : 25 , 30 or 40 1300
- ;:1" Zb,25,300r40
Gutter / Pavemen t Prof il e
1200 -~j
"'- Gutter /Pavement Profile

"
~I / "
"'" I\.
~
"'~ ~
/
1100 fl !\
/
~
~

'/\ '"
I'-.....
0- 1000 0-1000
r-- ~ -l-ffu
lo'
u:
~
~
~
900
// I
I~
~
~
--- ~ ~n
<0 '
r,_
0 """'- ~
r-
lo'
u:
~
~
~
900 P I"'~" ~ ~
~
l b' 6-" ,

---
g. 800 " ~ 800
~ 700
;;;
x
600
I
I
~
'--
~

NOTE, For Uu h sea carria eways


I--
educe ind ie ted fl o vatu 5 by
I'--
---- --.l
?.Q., 30

. 2'

%
-
-----
r---
I--
--
-
~ 700

600
1/
'" i"--.

NOTE, or fl u h seal carr I ge way


educ e indicat 1d flo value
~
~
~

by 2 %
~
'25

I-
- ---
I-- I---
I--

I-
SOO SOO

-12 01 -12
Gu tter Longitudinal Slop e . So Imlm) Gutter longit udinal Sto pe , So (m/m)
Figure A4a : Hydraulic capacity, at , data for 8-0 m carriageway Figure A4b : Hydrau li c capacity, at, data for 10 -0 m carriageway
no gutter no gutter

12() 120
Gutter Inlet H~rauli c ·Oata 1 Gutter In tet H~raul ic Data

110 1 Ca pture performance of Z-Om side-entry


inle ts without de fl ectors
110 1
Capture perfor mance of Z Om side-entry
in lets Wit hout def lectors

~
N
~ TYPE 4 d TYPE 4

~ F~
N
lS0 mm "> :
100
e
N
" ~
II ;r Zb,25-30
-, 100
'"" >r lb ,30-4O
-:J

Kerb / Pavement Prof ile Kerb / Pavement Profi le

- -- ""f
1m II
90
y r-...!.
90

- - - - m

m
(I I 1m/ , / " If r--.. r-,3
SO SO
'0.
I "~ I ~ f'.... m VI ~ :---..... 4m
• I'---

,
-.......
5 70 L leulter
ngt of d press d
up str amI.
5 70
/ / 'P llJr

I'--- ........
~
eng! of d press d
c;
7!1
" II ~e fer o Fig bela
...........
~
~
a
WI; fc-- ~utt.r upstrami
-
0k
~
IRe or o Fi He ...........
3
60
;! It z
60
<-< -

-
m ~
~ ~!It;;
i3
lm
WV ;S; r- ur. r-.,41n
i3
1m 3m
4
r-- r--
IV
--I--. ----
X-
~ 5m ~
lm. /
./ c plur. ~
~
g' 6m
Q. 50
• ....6m 50
«
Om I ' -Om
«
ltv
~
~
L /5=2 Om
'" 11 '/
40 40
'"w I ~ 300m nl '"w /I W
-
~ ~
10 m
4
~
:>
G
'" r- ;
30 I n??:,,:/
75 mm depressio n
:--==
Zb ,00\

~a~t.
..
~ \ - 30

/
Sectio n at inlet -
20 ./ ~ 10
/ -
- '\: ;)Y ;'Y- ~ ~ /
- --
~ y NOTES
.'~"'
!iQ.ill

10 ~'r-.\·' Unlet lip and upstream extended gutter both


depressed 75mm bel ow kerb- sldellong rtudinall Invert. 10
l.Il Unlet lip and ups tream ex tended gutter bo th
. depressed 75 mm. bela"" kerb-slde llongrtudlnalJ Invert.
:/ 2. For information on mlet lengths greater than 2 Om,
on, II Forbes 11' 771 _
!. 'tI ~ '
./
Pf: 2. :g~~l:~rf~~~~~ (~977}~et leng th s greater than 2 Om,

o o
o 0-02 0-06 O{)S 0-10 0-12 0-14 o 0-02 006 O{)S 0-10 0-11 0-14

GUTTER LONGIT UDINAL SLOPE So (m imi GUTTER LONGITUDINAL SLOPE So (mimi

Fi gure : A4c Collation of hydraulic data for 2-0m inle ts in single Figure : A 4d Collation of hydraulic data for 2-0m inlets in single
cross slope (no gutter) carriageways - Zb =25- 30 cross slope (no gutter) carriageways- Zb = 30-40

ARRB SR 34, 1986 123


-
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

124 ARRB SR 34, 1986


Appendix B

Forms for use by designers

Heading bl ock s for the f our main f orms used


in th e minor drainage system de s i gn procedure ..... CATCHMENT
a re provided in this appendi x. Desi gners may
copy the bloc ks and incorporate them into
blank forms appr opriate to their needs without to.)
SUB - CATCHMENT
penalty unde r Section 40 of the Copyright Act
1968. ·w SUB-AREA NODE PIT
TABLE 1 : Catchment definition data
......
This table lists all basic catchment data ~ ENTRY POINT l>-
CD
needed for the design process. The requi red r-
data are drawn from development plans, topo- GUTTER INVERT rT1
V'I
graphic surveys and hydraulic charts. LEVEL R.L. -A

TABLE 4 : Flow estimation in primary drainage COMPONENT


lines 0-

DESCRIPTION
Catchment data transferred from Table 1 to
n
Table 4 form the base for cal culating maximum
des i gn flows in all primary drainage lines.
HYDROLOGICAL ....»-
n
-J SURFACE
The table also includes provision (Remarks :I:
co lumn) for listing gutter inlet type/ s ize CLASSIFICATION 3:
rrI
selections made for DETERMINATE drainage
lines. Catchments in Northern and Intermed- (J)
AREA. OR . ....z
iate Australia (see Section 5.3, text) which EQUIVALENT AREA
0
include residenti al components show two run- TYPE OF CONTRIBUT'N .,.,
rrI

off coefficients in Column 25 - one for full- -0


CONe. OR DISTR. -z
area analysis and one for part-area analysis
..... Total length,
....-
as explained in Section 5.6, text. 0 0 0
L, metres ~
z
TABLE 6 : Flow estimation in main drain pipp- ~
1i nes .....
..... Fa II, metres .... »-
:;1!:
0
o Cl »-
Hydrological data transferred from Table 4 to
..... Effective length,
....
rrI!::
rrI -4
»-
Table 6 provide the base for calculating max- to.)
~ z
imum design flows in all main drain pipelines. L eff, metres 3:rrI

The layout of the table aids the sub-area


-z n
..... Slope So near
w
»-0
'gathering' process undertaken in STEP 6. terminal inlet r- z
Provision ' is made in Column 27 for the inclus- <
zrrl
ion of two runoff coefficients i n the case of .....
~
Carriageway r-~
rrlz
residential components in Northern and Inter- cross -slope, Zb -4Cl
mediate Australia. ..... Capacity flow
.,.,
r-
V'I 0
TABLE 8/9 Underground network hydraulic Guideline 1: Lis ~

design
Table 8/9 brings together catchment data sel-
ected from Table 1 and design flows collated
from Tables 4 and 6. Its layout enbles pipe
sizes to be selected and hydraulic grade line ,.,.,
~

..... 3:
computations to be performed. The Remarks 0-
»-
column is used to record junction pit invert ~
;>0;;
levels subject to possible downwards correct- VI
ion as part of the final design process. De-
signers must select an appropriate value for
the Darcy-Weisbach friction factor, f, to be
inserted into the heading of Column 17.
Values of f are listed in Section 6.7, text.

ARRB SR 34,1986 125


<D
co
0>

-:i
('I)
a:
TABLE 6 FLO.... ESTIMATION IN MAIN DRAIN PIPElINES: N~ -YEARS en
TIME OF ENTRY (OMPONENT PROGRESSNE IRAINFALL INTENSITIES
CO
(OMPONENT TRAVEL (HANNEL DR U/G i.n mm/h FOR
CUMULATIVE a:
SUB-AREA COMPONENT TOTAL CRITICAL MAINLINE FLOWS a:
TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL STORM PROGRESSNE CRITICAL COMPONENT UMULATNE FROM TOTAL <{
en ..... UNDERGROUND PIPE . NODE PIT TIME TO DURATION STORM URATION IN
UPSTREAM
t- a. overland allotment ~utter or u/ground NODE PIT IN TOTAL TOTAL UPSTREAM (CA)n
Z .2 (CA)n (ATCHMENT
w
~
.....
z<:l
.... 0
:l:;z
'"
.....
-'
-<
z
<:I
.....
~ c
0'-
~ ~
. flow drain natural pipe
channel travel
UPSTREAM
AREA
CATCHMENT AREA ct
'"
0:
Qn= ((~)~6ln Us
REMARKS
I ..... :r «
z t-
zuJ
Z
2 -o
u
-<
-u... --
.!'''C (analysis) (analysis) 1ull-area part- area ct ~ (analysis) (anal sis) full-area part-area
'" ..... ....
z .U (5 \:> U
E u
() t- c e c E, c tull- part- tull- part- analysis analysis
a. :> c e
.- ., E ·E , full- .part- full- part- analysis analysis
uJ
, 'E, c ...•
--.
c.. E c
t- :l:;« 0: Z
- -' u ""QI
E ·e
:r u «,
<{
() ueri CD . 0:
r
.....
0
a.
:l:; . U
c:: 0
c::
<:I
-<
u...
VI
VI
«
'E
00 ~ .. . E .z::
' c. ' ' "" ~ , , .z::
E E
QI c. - '
area
' lc area area area In for In for
Uc
.area area ar~a area Qn tor On for

-
0:
c o E c ~~
VI 0> c.QI
r 0=
c QI
tc t N= years N= years
3~ ~ z o . ~ ~ E c - E li i N= years N= years
.... ~
uJ -'
Z VI U <:I :r VI u
min .!!! ,..;;:;:: t.!!.;: QI QI .!!;
min. min min. min. ha. ha. ha. ha. ha. LIs lis
<{ 24
1 2 3 4 5 6 7 8 911 11 12 13 14 15 16 17 18 19 20 21 22 23 25 26 27 28 29 30 31 32 33 34
co
a:
:::J
~
~
<{
~
en
z
z
Cl
en
w
o TABLE 4 FLOW ESTIMATION IN PRIMARY DRAINAGE LINES: N,. -YEARS
w
Cl TIME OF ENTRY COMPONENT RAINFALL 4-
)( PRIMARY
<{
z PRIMARY DRAINAGE COMPONENT TRAVEL CHANN.EL OR U/G TOTAL INTENSITIES Lnmmlh. GI
CONTRIBUTING AREA ....
TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL ==
..0 z
COMPONENl e
z
~ CONTRIBUTING AREA FOR STORM .r.
~
TOTAL FLOW ::i
....
a: t- UNDERGROUND PIPE ENTRY POINT TIME TO DURATIONS WHICH c
::l AT NOMINATED c'-
."
REMARKS
o .E (CAIn
overland allotment gutter or IU/gr~und 3~
ENTRY CD
Cl. ARE CRITICAL 4-
ENTRY POINT
~ w 0
..... co flow . drain natural pipe POINT
u
GI c: an = (CAIn Ln LI
l:)t- (Gutter inlet
a: t-
C
Z e Z '- .- channel travel VI t-
z :z::1:
ot- w
:1: z t- Z
-J
< 0
o '- '" (analysisl full-area part-area ....< GI
ell (analysisl e
U
0.36 s t -~
- selections for
- ~
U ,-'0
z ell VI full-area part-area
en t-:I:
zu < -0 t-
zW 0
- l:)
..............
u ..... co
o u .... ::> GI e ~E .-c e c e analysis analysis 0:
< .... analysis analysis ~-
.... .DETERMINATE
....L U c: E, e (T'I
W t-
, .~ full- part- $2
~ 0: Cl.
z -0:
Cl. -'
, E , . 'E
E, .c. e
, u
.... 0:..0 lines included
..... ell GI, .c.
<, >- ~~ 'E .c. E E area area tull- part-
, ell C. , , .....0> , '
e u..
< V) ....
:I: , 0
Cl. u 0: 0 .c.
..... ion for ion for .E Cl. Cn for <ell
an for Cl.

-
V) 0 _

-_
'-'CD CD 0:
:1: C 0: < 0 - 0>
:g - ell c -- ell tc t ·I area area >- N= years N= years L~ - here I
t-:J :;:) t-
z 0
V)
u.J >- :J -J '- nl co
0>
E cIII ==E ..... c - E ell '" .- E N= years N= years "c . t-
;:)V) V) u.J U c :z: V) u
min. ~ 0;; .....
1'0 .-
~ ~z
- ..... min min. ha
u
ha. ha. borC LIs LIs
Ot-
'-'-

1 2 3 4 5 6 7 8 9 10 11 1213 14 15 16 17 1819 20 21 22 23 24 25 26 27 28 29 30 31 32

<D
C\J
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

-lo

N
I CATCHMENT
SUB- CATCHMENT
\JJ SUB-AREA NODE PIT
JUNCTION PIT AND
~I
GUTTER INVERT R.L's

COMPONENT
t..nl
DESCRIPTION

0- I FLOW ' Lis


-.l I LENGTH m
CD I LONGITUDINAL SLOPE
-0 I GUIDELINE 4 ~
):>
(Table 6, 4.) -4
rn
::0-0
<51 GUIDELINE 5 --l
(Table 6·4)
,-4
rn
»
< OJ
.... ,;0 ASSIGNED WATER ,
rn I
rn
..... :- LEVEL (AWl) (X)

N 13 TRIAL PIPE DIAMETER Do "-


~

. ~ 1 VELOCITY, Vo= ano m/s


..... PIT LOSS CASE
~ I !Tables 6'5 & 6'6)
.....
V1
;:0:
.:
-0
-4
-lo
0- 3 "'10<
0.0 ..., ~
):>
..... -4
-.l 3 hf= Yoo(VO/2 ,.."
::0

~ 3 Kw ( 0/'2g J ,
-
):>
~
-..::r
..
,.."
<
,
, -4 ,.."
rn
~ ;:0: rn
~ 13 0- I //\ ~ V1 V1
. CD -4
:j
,~ "'Icf=
0.0
'-----'
Io.l
-0
-u
~ 13 AWL :nus BWL
rn
o
};

~ 13
~
rn
0-
.
l>
,
~

I
CD .\V
-......
::r

Vi
-4
rn
V1
-4
~
rn
-4
,.."
::0
0; ~ · 0 V1
0 '" QO

~ I~ ADOPTED DIAMETER ;::x:


Cl
r
N I~ BWL & HYDRAULIC ):>
\JJ ~ GRADE LINE z
CD ):>
,
):>

-<
,~ ,~
III In
V1

r=r OJ Vl
o VI
~ VI
~ _ . ::0
o 0.0 ,.."
Z
3 ~ 15 II

N -S~):> I
~ =+"0
. =+ ::0
;:0: -<
I'T1
~ - Vl ):>
OJ .:
~ OJ ::0
...,
m m
-..., V1

iii' ro
< m
m <

ARRB SR 34, 1986 127


STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS

128 ARRB SR 34, 1986


Symbols and abbreviations

A drainage unit area (ha) g gravitational acceleration, 9.81 m/s2

Ai impervious drainage unit area hf pipe friction headloss

Ao junction pit outflow pipe area junction pit headloss (water level)
(= 1TD~/ 4)
H.G.L. hydraulic grade line
pervious drainage unit area
average rainfall intensity (mm/h)
AEP annual exceedence probability (years)
average rainfall intensity,
ARI average recu rrence i nterva 1 (yea rs) ARI = V-years
AR&R 'Australian Rainfall and Runoff' i average rainfall intensity,
10'1
ARI = 10-years, duration = 1 hour
AWL junction pit assigned water level
(see Fig. 6.12) k pipe boundary roughness (mm or m)
BWL junction pit bottom water level 1/2
(see Fig. 6.12) K coefficient of So in eqn (6.9),
Fig. 6.2
C runoff coefficient
hydraulic conductivity (m/s)
Ci runoff coefficient - impervious area
junction pit headloss coefficient
runoff coefficient - pervious area (water level)
weighted runoff coefficient length of overland travel as shallow
[see eqn (4.7) ] sheet flow (m) (see Fig. 5.3)
Cy runoff coefficient, ARI = V-years limit of overland travel as shallow
sheet fl ow
(CA) equivalent impervious area (ha)
L carriageway or pipe length (m)
d triangular channel flow depth (m)
Leff effective length of drainage path
kerb-side flow depth (see Table 1, Chapter 11)
pavement edge flow depth Lig grating inlet perimeter (m),
excluding kerb
di gutter sag inlet water depth above
lip side-entry inlet opening length (m)
D pipe diameter (mm or m)
M-years design ARI for major system 'gap
junction pit outflow pipe diameter flow' (see Table 5.2 A & B)

Dt diameter, cross-connection pipe n Manning's 'n' (see Section 5.5,


(see Table 6.4) Table 6.1)

f Darcy-Weisbach friction factor Manning's 'n' - gutter


[see eqn (6.14) ]
% Manning's 'n' - pavement
Fy frequency conversion factor
(see Table 5.5)
Reynold's Number =
FRC fibre-reinforced cement (pipes) \J

ARRB SR 34,1986 129


N- yea rs design ARI for minor system drainage channel longitudinal slope
(see Table 5.2 A & B) (m/m) .

o discharge rate (m 3 /s or Lis) t time (mins)

Oc roadway reserve capacity flow time of concentration or travel time


(see Table 9.1A) from extremity of pervious area
discharge rate - full area t i travel time from extremity of
(see Section 4.5) impervi ous area
triangular channel gutter flow com- TAi tri butary (impervi ous) area
ponent or "f ronta 1 fl ow" (s ee Td b I e ~ . 2)

Og gutter flow to junction pit via inlet T.N.P. terminal node pit (see Section 7.1)
T.N.S. terminal node section
Ogap 'gap flow' (see Section 5.4) (see Section 7.1)

Oi gutter sag inlet flow v velocity (m/s)


Vave channel flow average velocity
01 lateral pipe flow to junction pit
peak discharge rate, ARI = N-years junction pit outflow pipe average
On velocity (= Oo/Ao)
00 outflow discharge from catchment or
from junction pit w width of flow spread from kerb (m)

Op discharge rate - part area V-years general ARI expression


(see Section 4.5)
peak discharge rate Z reciprocal of channel cross-slope
Opeak
Osc roadway reserve storage-corrected Za reciprocal of gutter cross-slope
flow (see Table 9.1B)
reciprocal of pavement cross-slope
Ot triangular or composite channel
total flow
B triangular flow correction factor
Ou upstream pipe flow to junction pit (see Section 6.1)

Oy peak discharge rate, ARI = V-years channel flow multiplier


(st:!t:! Fi y. 5.4)
R hydraulic radius (m)
(see Section 6~1) e upstream-downstream pipe deviation
angle at junction pit (see Table 6.6)
RD residential density (residences/ha)
v kinematic viscosity (water)
S slope of natural surface (m/m) 1.14 x 10-6 m2 /s at 15°C

130 ARRB SR 34, 1986

You might also like