Professional Documents
Culture Documents
SR 34 PDF
SR 34 PDF
SR 34 PDF
625.7 (94)
AUS
(SR 34)
-f .J .
ARRB Group would like acknowledge and thank John R. Argue AO, Adjunct
Professor of Water Engineering, University of South Australia, for allowing
reproduction of Storm Drainage Design in Small Urban Catchments: a
handbook for Australian practice, 1986.
By
John R. Argue
Principal Leeturer,
School of Civil Engineering ,
South Australian Institute of Technology
, 1.0
""'7
l .
REFERENCES 109
DIRECTORS 1986-1987
M .J. Knight, B.Sc.(Eng.), M .Eng .Sc., F.I.E.Aust. , AFAI.M ., M .C.I.T ., Commissioner of
Highways, South Australia
I.F .X. Stoney, AA.S .A. , Dip.Bus.Studies, MAG.I., FAI.M ., Chairman and Managing
Director, Road Construction Authority , Victoria
D.H. Aitken , I.S.0., B.E. , F.I.E.Aust., F.C.I.T., FAI.M ., Commissioner of Main Roads ,
Western Australia
A .S. Blunn, L.L.B., Secretary, Commonwealth Department of Housing and Construction
E.F.F. Finger, B.E. , M.Eng .Sc ., F.I.E.Aust. , Commissioner of Main Roads, Queensland
B.G . Fisk, AR.S.M., B.Sc.(Eng .)(Met.), C .E., M.I.M.M ., Commissioner for Main Roads ,
New South Wales
C .W .M. Freeland, B.E.(Hons) , M .I.E.Aust., Secretary, Commonwealth Department of
Transport
I.D . Gordon, B.E., M.Eng .Sc., M.I.E.Aust., M.C .I.T., Secretary, Department of Transport
and Works, Northern Territory
P.J. Wettenhall, Director of Main Roads , Tasmania
M.G. Lay, B .C .E., M.Eng .Sc ., Ph .D., F.I.E.Aust. , F.C .I.T., M.ASCE, Execut ive Director,
Australian Road Research Board
Chairman: M.J. Kn ight
Deputy Chairman : I.F.X. Stoney
Executive Director: M.G. Lay
Keywo rd s. un less ca rryi ng an asterisk . are from the ' International Road Researc h Documen tati on [lRRD)
Thesau rus. 1983' ,
DECEMBER 1986
Although this report is believed to be correct at the time of its publication , the Australian
Road Research Board does not accept responsibility for any consequences arising from
the use of the information contained in it. People using the information contained in the
report should apply , and rely upon, their own skill and judgment to the particular issue
which they are considering .
Reference to, or reproduction of this report must include a precise reference to the report.
Wholl y set uP. designed and printed at the Australian Road Resea rch Board . Vermont South. Victoria. 1986
ACKNOWLEDGEMENT
The contents of this Report have been strongly influenced by input from engineers and
technical officers employed in local government, consulting practices and government
authorities - Commonwealth and State - and from researchers and academic colleagues.
Each Australian state and territory is represented in this array. In addition , contact has
been made with a number of overseas researchers and authorities active in the urban
storm drai nage field , the majority of whom have responded generously to appeals for data
and advice.
To the following go the author's special thanks :
• Australian Road Research Board and Professor A .P. Mead, Director of S.A. Institute
of Technology for permission to publish the Handbook . Dr M.G . Lay , Executive
Director and Dr J.B . Metcalf, Deputy Director of ARRB for their encouragement and
help throughout the project.
• Mr D.P. Ritchie (Blacktown Council, N .SW.), Mr R.B. Saunders (S.A. Highways
Department) , Messrs B.C . Tonkin and P.K. Read (B.C . Tonkin & Associates,
Adelaide). Mr M.N . Clarke (N.S.W . Public Works Department) , Assoc . Professor
D.H. Pilgrim (U.N.SW.), DrG .G. O'Loughlin (N .S.W.I.T.), Mr R.J. Taylor (Techsearch
Inc .), and members of S.E. Queensland Local Government Engineers' Group for
support and technical advice.
• Mr J . Fox (Plantec Drafting Services, Adelaide) who was responsible for drafting the
bulk of the graphics and tables and an army of long-suffering ladies who helped with
typing, library searches or final editing / production - Mesdames C . Wilson,
R. Mielnik, S. Swann, L. Folland, P. Buxton, A. Girard , M. Holdsworth and J . Symons.
• Finally to my wife Jan and members of the Argue family go my heartfelt thanks for
their patience and support through the many vicissitudes of the 'drains' project.
Cover
The photograph shows Elizabeth Street, Melbourne during the major storm which struck the city in February
1972. The assistance of the Herald and Weekly Times Ltd in providing the photograph is gratefully
acknowledged.
PREFACE
In June 1979 Australian Road Research Board (ARRB) Project 1093 'Urban Stormwater
Collection Systems: A Review ' was commenced . The aims of the project were :
(a) to identify those practices about which there is general consensus among
practitioners and for which there exists a satisfactory data base ;
(b) to identify new procedures to replace existing practices where such new procedures
are considered necessary and/ or appropriate; and
(c) to indicate directions for new or continuing research to improve and/ or expand the
existing data base to a generally satisfactory level.
The report on Project 1093 (Argue 1981) recommended that a handbook be devised
by ARRB for Australia-wide use, bringing together best data and information available on
storm drainage design in small urban catchments . It recommended , also , that the
presentation of this material recognise the particular needs of an expected audience made
up of technical officers, newly graduated engineers and practitioners whose work does
not keep them in constant touch with the problems of urban drainage.
'Storm drainage design in small urban catchments : a handbook for Australian
practice' is the outcome of these recommendations .
The Handbook presentation reflects master drainage planning principles which have
been developed by leading practitioners in North America since the early 1970's. These
include an array of stormwater management options as well as the 'major/ minor'
approach to flood mitigation and stormwater control in urban landscapes. In keeping with
the 'teaching ' role recommended for the Handbook from its conception , this material is
presented in step-by-step form wherever possible, and includes detai led case study
illustrations. By this means, it is hoped , concepts and principles employed at present only
by leaders in the field of urban drainage design will penetrate Australian practice to its
'grassroots' level.
An important aspect of the Handbook's preparation , and a necesary condition for its
success , has been continued liaison with the compilers of other documents on urban
drainage and with potential users - engineers and technical support staff employed in
municipal engineering departments and c;onsulting practices. Draft versions of the
Handbook 's main design procedures have been subject to extensive review and revis ion .
The outcome is a document which offers drainage designers an approach that is in
harmony in all major respects with 'best' Australian practice and which is included among
the Rational Method and hydraulic design procedures advocated in Chapter 14 (Urban
Drainage Design) of the third edition of 'Australian Rainflal and Runoff' (Institution of
Engineers, Australia 1987) .
The procedures offered in the Handbook have wide application and if widely adopted
will introduce a measure of uniformity into small area urban drainage design practice in
Australia . Such standardisation, however, stops with the procedures: no attempt is made
in the Handbook to press for uniformity in the selection of roadside channel forms or
ancillary drainage network components. Nevertheless, hydraulic data for a range of
widely-used channel forms and components are included providing designers with the
opportunity to make their own assessments and comparisons of alternatives.
Such considerations may lead , in time, to some reduction in the variety of channels
and components presently used in Australian practice. While some economies may follow
this outcome, the main advantage would be an eventual improvement in the quality of
hydraulic data available for the most popular channel forms and components as a
consequence of more concentrated and effective research effort.
Introduction
2 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
bridge this gap and provide a full and Goal 3: Ston.water Retention/Detention
systematic account of urban drainage flow Measures
estimation, system design procedures and
stormwater management pract ice needed by Goals 1 and 2 each have readily identifiable
desi gn teams comp ri si ng ju ni or engi neers and targets against which the success or failure
technical officers supervised by experienced of planned or designed d rainage networks can
practitioners. be measured.
ARRB SR 34,1986 3
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
this Handbook for estimating flows in small in the past to produce thei r own manuals
urban catchments and designing major/minor giving details of de sign requirements, stand-
systems to convey them are similar. Differ- ard s , local rainfall data, hydrauli c perform-
ences are listed in Chapter 14 of AR&R. ance data for approved units, etc. Publica-
tion of this Handbook and the third edition
Designs for catchments falling outside of 'Australian Rainfall and Runoff' in 1987
the range covered by this document, i.e. is not expected to end this process and may
medium to large urban catchments requiring very well provide an impetus to it.
hydrograph flow estimation procedures, should
be based on appropri ate methods recommended
in Chapter 14 of AR&R. Both publications should be seen as re-
source documents providing best available pro-
Most State Road Authorit i es, some spec- cedures and data selected from local and
ialised construction authorities, e.g. N.S.W. overseas sources. Their interpretation into
Housing Commission, as well as the works a variety of local contexts municipal,
departments of a number of councils and mun- regional or State-wide - is seen as the valid
icipalities across Australia, have found need next step in the technology transfer process.
4 ARRB SR 34,1986
Frequency and the major/minor
drainage system design concept
Average Recurrence Interval. ARI The time periods mentioned in these two
ill ustrat ions a re referred to in the 1 i tera-
If a long period flood record - say 100 years ture of Engineering Hydrology as 'average
- were available for a gauging station at the return periods' or 'Average Recurrence Inter-
site of a proposed control structure ina vals', ARI, and are employed in Australian
dra i nage channel and an exami nat i on of that practice to cover average recurrence periods
record were conducted, it would reveal that a of 100-years or less. The terminology 'Annual
few very 'large' floods and a great number of Exc eedance Probabi 1 ity', AEP. is app 1 i ed to
'small' floods had occurred in the 100 years flood magnitudes which recur less frequently
peri od • than once in every 100 years (Rowbottom et a 1
1986). Thus, the hospital example given above
Considering the 50th ranked flood in the would be associated with AEP of 'I in 200' or
set, having been equalled or exceeded 50 times perhaps 'I in 500'.
ARRB SR 34,1986 5
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 2.1
A LAND-USE/FLOOD FREQUENCY HIERARCHY FOR AN URBAN COMMUNITY
Flood Design
Security Cl assificatio n Descri pt i on of Components Fl ood
Levels Frequency
Strategi c I Fl oo r leve l s of hospita l s , Civ il Defence HQ Design AEP
; 1 in 500
St rat eg i c II Fl oo r levels of police , ambulance and fire
A st ation s: wat e r and wa stewat er centres: e l ect ri c
power and ga s supply stations
Fl oor levels of conva l escent homes and community
bu ildings whi ch could operat e as dormitory cent r es Desig n AEP
in great flood events ; 1 in 200
()ormito ry 1 Floor l evels of high density resi de ntial
Dormitory 11 Floor l eve l s of l ow-med ium density r esidentia l
P/C II * I Floor l eve l s of esse ntia l f ood , pharmaceutical,
retai 1 and depa rtment stores: centres employ in g
1arge la bou r for ce : community admi ni strat i on and
B educat i on cent re s: cent res for sto r age of rare
artifacts: venues for ent ertainment , di ning or Des i gn ARI
popu lar indoo r sports ;
100 yea r s
PICII * II Floor l evels of facto r ies and outlets supply in g
non-essent ial items: premises of busi nesses and
institutions which involve small numbers of people : Desig n ARI
premises of spo rt or community act ivi ties in- ; 50 years
f reque nt l y used
Ope n space I Grounds of all units be l ong ing to priority A above: Design ARI
outdoo r areas wh ere r are artifac ts are displayed ; 5-10 years
or stored
C Open space II Grounds of a 11 units be l ong ing to priority B 3-5 yea r s
Ope n space III Other open space areas includ i ng ge neral pa rks and
outdoo r spo rt and re creation a rea s 1-3 years
--- -
* Public/Commercial / Industrial
'"
'"
~140
-p .--?"
,.c--
'---v-- ~
ranee
comprehensive i n vestigation of urban drainage
systems, both major and m i ~or, carried out by
bes t val ue for ~ spent Grigg et al (1976), who stress that the
'0 120 I I I benefit/cost outcome in a particular case is
V>
o but one of the many inputs requi red by the
u
100 0 8 10
decis i on-making process. Other inputs include
De sig n avera ge rec urrence in t erval (yea rs) - - unquantifia ble social and environmental
benefits, fund availability and political
Fig. 2. 2 - Cost/frequency re lationships for two categories of pressure.
urban development
One particularly f rustrating (for the
designer) social aspect of the problem is
2.4 TOWARDS DESIGN ARI: THE WATER RESO~CES
'community view' of the importance of flood
APPROACH control and mitigation works relative to other
services. This can be capricious and strongly
The conventiona 1 method used in the water influenced b'y events - or , perhaps, lack of
resources field to select design ARI's is events - of the recent past.
benefit/cost analysis (Linsley and Franzini
1979; I.E. Aust. 1977 and 1987) which Should it even be possible to complete all
requires, as part of its data base, a requ i red ana l'yses and su rveys and reach
compilation of likely benefits. These are concensus among the i nterested parties
1i sted for major systems and minor systems in community representatives, planners , environ-
Table 2.2. mentalists, politicians as well as engineers -
in one place at one time, it would be,
strictly, inappropriate to transl ate the
TABLE 2.2: C(JUtUNITY BENEFITS OF MAJOR OR resulting design ARI findings to what might
MUI1R SYSTEMS appear to be similar developments and systems
elsewhere.
MAJOR SYSTEM ONLY MI NOR SYSTEM ONL Y
On the other hand, it is quite impractical
I. ' Improved aestheti c s
In c rea s ed se ns e o f
sec uri ty
Improved ae stheti c s &
I'
Red uced mi nor traffic
ac ci dent s
I to p.xPp.ct this type of enquiry to be performed
as part of every urban drainage design
r ec rea t i onal benefits I. Reduced health ri sks programme. This is particularly so in the
I . Enhanc e d land value s 1 linked with poor drain- I case of small projects carried out in the
. Red uced injury & l os s 1 ag e ( mo s qu itoes. flie s, 1 smaller municipalities. The larger local
I of life etc .) 1 government authorities should therefore be
I. Reduc e d disr uption of Red uced inconvenience 1 encouraged to conduct such stud i es and
no rma l COfllffill nity in perf orminq day-to- I processes in typical classes of cipvp.lopment,
I activities day activities
at least occasionally, and publish their
Reduced los s of com- Reduce d roadway mai n- 1
mun i ty servi ces I t e nanc e 1
findings for the benefit of all.
(h e alth, wat er, power
an d gas, tr ansporta- I Despite these obstacles and the complex-
ti o n. communication s , I I ities of the question which has been addressed
etc ) • in this section, the urban drainage planner/
Red uced emergency ser-
vi c es and re lief costsl I
designer must at some stage in his or he r
Red uced damage an d I project adopt design ARI's for the system as a
1 iabi 1 ity cos ts I whol e or for indi vidual segments of it. Some
Red uced production 1 more positive suggestions as to how this may
time a nd sales losses I be done are offered in the following sections.
I. Reduced c lean-up costsl
I 1 1
2.5 DESIGN ARI - MAJOR DRAINAGE SYSTEMS
Polin and Cordery (1979) applied benefit/ Determination of design ARI's for major
cost analysis to determine design ARI for a systems following the water resourc e s approach
cul vert on a mi nor waterway. Those who have referred to in Section 2.4 has been generally
applied this approach to urban drainage avoided in developed nations by the i r adoption
problems of broader scope have been frustrat- - nat i ona ll y in some , regionally i n others -
ed, finally, by the high intangible benefits of a common level of flood security in the
content of thei r prob 1ems, 1 ead i ng to i ncon- face of great floods. Thi sis the AR I =
clusive and unsatisfactory outcomes in most 100-years flood, defined in the U.S. National
cases. O'Loughlin and Avery (1980) . reporting Flood Insurance Act of 1968 as ' . .. the minimum
a study of two Campbe 11 town, NSW, subu rban level of flooding to be used by a community in
minor systems, concluded that it is 'impract- its flood- plain management regulat i ons.'
ical to devise a methodology for determining
design average recurrence intervals from Federa 1 , Sta te and 1 oca 1 go vernment
economic and sociological factors such as that authorities in Australia might be described as
developed by Polin and Cordery for culvert moving slowly in the same direction with
design floods. Designers will have to rely on respect to 'mainstream' flooding (Victoria,
Flood Plain Management Act 1982; Australian Engi neeri ng input is important, however,
Water Resources Council 1985). However, and may take one or more of the following
damage to premises as a result of uncontrolled forms:
urban storm runoff is not included in thi s
category of flooding. Initial Cost and Design ARI
Some argue that the entry of mai nstream The procedure for designing minor systems
floodwater to a dwelling is likely to be far presented in Chapter 10 includes provision
more damaging than inundation by urban runoff (STEP lOA) for a range of approximate network
and, hence, that lower standards of protection designs to be costed, each network layout
should be accepted in the wholly urban corresponding to a nominated design ARI. In
landscape. Thei r case rests on the greater the case of residential catchments, design ARI
uncertainty which is associated with flood = 0, I, 2, 5 and 10 years are used; design ARI
(level) prediction for rivers than for urban = 0, 2, 5, 10 and 20 years are recommended for
runoff flows and, also, that river-derived commercial/industrial catchments.
floodwaters are likely to stay longer.
With these data a graph of network initial
Those who oppose such a distinction can cost can be drawn. This is illustrated for
point to the lack of conscious flood-proofing the case of a 12 ha hypothetical residential
evident in much contemporary urban building sub-division in the Adelaide foothills, South
practice e.g. slab-on-ground construction, Australia, in Fig. 2.2 curve 1. Fig. 2.2
and, concerning duration of inundation, floor curve 2 represents the outcome for a typi ca 1
level damage is virtually independent of the commercial/industrial development.
time pa rameter.
This type of representation is valuable
Little case can therefore be made for input to the decision-making process. It
distinguishing between the flood security indicates, in the case of curve I, that 'best
considerations presently afforded floodplain value for $ spent' is obtained when design ARI
properties and those situated beside roadway in the range 2-years to 4-years is used, i.e.
reserves and other urban 1andscape fl ood where the cost/ARI curve is fairly 'flat'.
routes which may become, in the aftermath of
major storm events, torrents of fast-movi ng, A display of even greater value to the
pollution-carrying flow. The devastation decision-maker would be one which converts
which occurred in the Sydney storms of initial cost and ongoing maintenance into
November 1984 (Cameron McNamara 1985) and 'present worth of costs' format (Grigg et al
August 1986 bear witness to this. 1976).
The design ARI recommended for the
pl anning of major storm drainage systems by Initial Cost/Maintenance and Design ARI
this Handbook and considered to be appropriate
in the third edition of AR&R (I.E. Aust. 1987) A report into engineering standards used for a
is the 100-years level. Variation from this range of residential land development
standard should only occur in a particular components, including stormwater drainage, was
case upon the recommendation of a full water prepared in 1984 for the Commonwealth Depart-
resources enquiry. ment of Housing and Construction by Scott and
Furphy (1984). The genera 1 aim of the study
was ' ••• to present a case ••• for the intro-
2.6 DESIGN ARI - MINOR DRAINAGE SYSTEMS duction of more cost appropriate alternatives
Of the five benefits listed under minor for engineering requirements based upon
systems in Table 2.2, only one - 'reduced performance standa rds that are rea 1 i st i c,
roadway maintenance' is quantifiable in achievable and encourage innovation.' The
engineering terms: the others are either study applied four standards of development to
unmeasurable, unquantifiable or both. It is a hypothetical subdivision of 77 residential
therefore not surprising to discover that even allotments and compared their cost/maintenance
greater uncertainty surrounds the question of performance over a 20-year time span. Storm-
ARI and minor system design than is water was managed in a major/minor drainage
encountered with major drainage systems. system whose base standard minor system used
Unl i ke thei r major counterparts, however, . swales designed for ARI = 1 year.
flood security levels applicable to minor
systems are never likely to be the subject of The report concludes that the potential
national or State legislative processes. maintenance cost savings associated with high
engi neeri ng standards ' ••• are so mi nor in
Neverthel ess, it is common for State Road relation to the heavy capital cost burden
Authorities responsible for the oversight of incurred that cost effectiveness improves
drainage cost-sharing schemes, as well as consistently as the base standard regime is
local government bodies, to provide such approached.' In a reference to the cost/
advice (MRD, Queensland 1980). Designers maintenance aspect of the base standard minor
should not be dismayed to discover apparent drainage system, it states that 'the high cost
inconsistencies and even conflict in design of maintaining swale drains means that this
AR I advi ce issued by different autho ri ti es as technique is somewhat less efficient than
it represents · the outcome, in each case, of traditional kerbing. However, this relatively
the complex techni ca 1, socia 1, envi ronmenta 1 , poor performance is more than offset by
political and funding judgements made by those savings in underground drainage services and
authori ti es • maintenance thereof achieved by swales.'
ARRB SR 34,1986 9
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
To explore this, consider the Thp. chanQe in emphasis which has occurred
'inconvenience' suffered when a member of the in urban drainage planning with the intro-
public is discouraged from crossing a street duction of the major/minor concept (see
because there is (nuisance) stormwater moving Section 2.3) has tended to go hand-in-hand
in the roadside channel. The duration of this with a lowering in the standard of convenience
i nconveni ence cannot be long in the types of provided by minor drainage systems (Jones
urban catchments which fall within the scope 1971). In what might appear to be a 'trade
of this Handbook - 10 minutes, perhaps 20 off' that stems from the new goals of urban
minutes at most. If the reason for making the drainage design, this reduced convenience is
crossing - probably in heavy rain - is one of balanced by a primary concern for increased
extreme urgency then the presence of perhaps security against indoor flooding of dwellings,
100 mm depth of water near the gutter is business premises and important public
unlikely to deter our subject as the cover buildings.
photograph of thi s document demonstrates.
Alternatively, a journey of not more than 60 m A table of design ARI values whi ch reflect
will bring him or her to a location where flow thi s ph i 10sophy is presented in Table 2.3.
'spread' is little more than gutter width. They are suggested for use in minor drainage
system components and networks ONLY where
Now the spread of flow which has these are integrated within cor recLly
inconvenienced our subject results from planned/designed major systems.
interact i on between three l11a i n pa rameters -
3.1 THE NATURAL CATCHMENT AND URBAN drought and also provide dry weather flow
DEVELOPMENT upon which the stream ecosystem depends.
In its wil d sta te, the na tura 1 ca tchment or The fi rst impact of development upon such
drainage basin is a complex environment in a balanced system is usually the clearing of
which a range of fauna, flora, geological land for agriculture. This leads to a change
changes and the natural processes of growth in the type of vegetation cover, e.g. from
and decay have established balance. The forest to grassland or crop, and sl ightly
harmony which exists is not, typically, increased flood peak flows with attendant
fragi 1 e for it can wi ths tand the ra vages of increased scour and erosion. Pollution loads
bushfi res and fl oods and can - gi ven time - - ferti lisers, pesticides, etc. - originating
regenerate i tsel f and restore its nat ural in the catchment and carried by streams may be
equilibrium. hig h depending on the type of agricultural
activity involved.
The main properties and characteristics of
a forested catchment which relate to the
changes wrought by later urban development In the next phase of development - the
are: conversion of agricultural land to typical
urban landscape - much of the land is covered
a) natural drainage system The system of by a substantially impervious surface
drainage paths, creeks and streams present interconnected by pipes and formal drainage
in a natural drainage basin is we l l channels. These structures convert the bulk
matched to the rainfall/runoff processes of storm rainfall input to runoff which is
operating in that basin. Generally, less coll ected and which moves rapidly through and
than 20% of storm rainfall on a natural beyond the catchment.
catchment i s discharged from it as surface
runoff. This discharge causes a minimum Where extensive urban development of a
of scou r and eros i on and, con sequent 1y , valley has occurred without sound drainage
carries a relatively low sediment load; it planning, riparian property owners in the
is free of catchment-originating chemical lower reaches of the valley are likely to
pollutants. experience frequent inundation by fl oodwaters
carrying high silt loads and high concentra-
b) water retained by catchment The surface tions of coliform, heavy metal and petroleum
i rregularit ies and vegetation cover hydrocarbons. Furthermore, because of rapid
present in the forested catchment are removal of stormwater from the urban landscape
responsible for retaining and retarding and consequent limited infiltration occurring
overland movement of surface runoff during runoff events, supplementary watering
thereby increasing the potential for is corrmonly undertaken to compensate for low
infiltation. The major portion of water soil moisture levels. The streams and
so ab so rbed is taken up by the roots of waterways of the valley are likely to dry up
indigenous trees and shrubs and eventually compl etely duri ng the summer months and
transpires to the atmosphere or evaporates members of the (stream) biotic communities
from the surface in hot weather. In the which requi re year-round fl ow for thei r
process, seasonal variation in soil survival will vanish (Karr and Schlosser
moisture can lead to significant 1978) •
volumetric changes (expansion and
contraction) in reactive soils.
It is interesting to note that of the
c) groundwater replenishllent and dry weather three mai n envi ronmenta 1 damages whi ch follow
flow That part of the rainfall input poor drainage planning, only the first
which does not leave the catchment as frequent lowland flooding by silt-laden,
di rect surface runoff nor is evaporated polluted water - has impinged on the public
from it, passes to groundwater storage consciousness. The loss of potential infil-
and/or appears as dry weather flow in tration and of dry-weather flow in streams
streams. These processes provide ground- appear to be matters about which the public at
water reserves to support trees and shrubs large is largely either unaware or unconcerned
in the catchment particularly in time of or, perhaps, both.
ARRB SR 34,1986 11
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
It is not surprl s 1 ng, therefore, that ' loss' can be e xpected wi th second grade
urban drainage design practice of the past has pavements (some residential streets, car
tended to concentrate on a percei ved need to parks, etc.) constructed on porous soils
remove runoff as completely and as quickly as ( Ma k in an d Ki dd 1979: Kidd und Lowing
possible. This ' need' manifested itself in 19 79). Numerous materials and open space
networks of slOOoth, interconnected collector surfa ce finishes are available which can
channels within developed catchments and in abstrac t upwards of 50 per cent of
large, lined channels downstream. rainfall applied to them (van Dam and van
de Ven 1984). These include open grade
The tragic loss of life in the Woden bituminous concrete, interlocking paving
Valley (A.C.T.) flood of January 1971, when hlocks - ungrounted and normally laid on
se ven people were swept to their deaths in a sand beds paving slabs, similarly
flooded stormwater drain, led to a questioning constructed, and precast lattice paving
of the 'remove runoff' phi losophy in which presents a block-reinforced grass
Australia. Leading practitioners and local surface to incident rainfall. In general ,
government authorities now advocate an suppl i ers recommend use of these pavi ng
approach to urban drainage practice which can types only on soils which are porous and
be described as a 'hold the water where it stable (Murphy et al 1981).
falls' philosophy. In this, every opportunity
to retain st.orm runoff and delay its movement b) Soakage wells and sumps Where soils are
from the catchment is explored in harmony with very porous and stabl e and the saturdLed
acceptable levels of flood security (Poertner groundwater zone at least 2m below natural
1973: Tourbier and Westmacott 1980). surface, significant quantities of
stormwater runoff can be collected and
Th e broad ai ms of thi s approach as they 5 I owl y trans ferred to the wa ter tab 1e by
relate to an urban development are: way of open soakage wells and sumps. The
technology leading to thi s approach has
1. to retai n wi thi n the ca tchment as much reached an advanced stage in Long Island,
storm runoff as can be tolerated ha vi ng New York (Aranson and Prill 1977) and has
regard for other communi ty needs such as been successfully applied in Perth,
the structural integrity of building Western Austral ia, where much of the
foundations in unstable soil areas: terrain is sandy, similar to that of Long
Island.
2. to so manage stormwater excess flows
within the catchment that minor floods are
fully controlled and the effects of major 'Soak wells' and 'sumps' are widely used
and rare floods mitigated: and, in Perth to store runoff from domesti c or
industrial roofs, carparks and sections of
3. to regulate outflow from the catchment to main roads. installations vary in Lype and
levels which approximate those of its size from pipe-walled pits (perforated pipes,
pre-developed state. diameter 1 m) used in domestic situations to
open pi ts or 'sumps', e.g. 0.25 ha x 2 m deep
The measures whi ch the drainage designer used for large industrial sites and carparks.
can employ to achieve these aims may be class-
ified broadly as retention, detention and For these retention measures to be
retardation systems (after Johnson and Putt successful, site hydraulic conductivity, Kh ,
1977) : should be greater than 5 x 10- 5 m/s. (For I
field measurement of hydrauliC conductivity,
Retention refers to procedures and schemes K , see Jonasson 1984a.)
h
whereby stonnwater is held for considerable
periods causing water to continue in the The Main Roads Department of Western
hydrologic cycle via infiltration, perco- Australia operates about 30 sumps located at
lation, evapotranspiration and not via direct interdunal low points beside main roads where
di scharge to watercourses; they receive runoff piped from roadway surface
drainage collection systems. Brooks and Cocks
Detention refers to the holding of runoff for (1983) have developed a method for sizing
sho rt time pe ri ods to reduc e pea k fl ow ra tes sumps which has been validated by observations
and then later releasing it into natural or made of operating installations in Western
artificial watercourses to continue in the Austral ia. The method appears to have wide
hydrologic cycle. The volume of surface application in the sandy terrain, low rainfall
runoff involved in this process is relatively areas of South Australia, Victoria and
unchanged; Tasmania where significant losses to evapora-
tion - ignored by Brooks and Cocks - can also
Retardation is achieved when flow moving to be expected.
the entry point of an underground drai nage
network passes along a channel of low Where soakage wells and sumps are employed
hydraulic efficiency. Retardation systems to control minor stormwater runoff in elements
which are most effective usually combine this and sub-areas of a developed landscape, they
characteristic with those of retention and should be sized to accept the entire runoff
detenti on. generated in those components in storms of
design ARI equal to that adopted for the
3.2 TERMINAl RETENTION MEASURES genera I mi no r dra i nage system of whi ch they
form a part. Sump retention volumes should be
a) Porous paving British research has shown based on storms of long duration e.g. two or
that at least 30 per cent infiltration more days. It follows that catchment elements
and sub-areas whose minor flows are so or seepage beds (see below). Roof
retained should be excluded from the defined stormwater, temporarily retained by these
catchment contributing to the general minor structures, is released slowly to
system network. groundwater or to maintain soil moisture.
overflow to roadside
channel ,rear of allotment
drain , seepage trench etc,
I
gravel collar width - 300 mm.
internal gravel
bed 300 mm dee p
NOTES :
1. For well volume and site
see Section 3.3
2. Gravel- 20 mm nominal size
Rear Fence
' ,0 m
carriageway
C : : :ater ::from
roo f or overflow deep
from well or seepage
bed.
Overflow pipe
Junction pit - - -
Dutch dra in - 400 mm. deep
b) Dutch (or French) drains and seepage beds A layer of graded filter or geotextile
These operate along similar lines to the material should be placed at all gravel/
open wells and sumps described in Section soil interfaces (see Figs. 3.1 and 3.2).
3.2 but differ from them in the following
respects: Gravel-filled drains and beds are less
prone to clogging than open sumps but are
(i) they are generally non-terminal, virtually impossible to clean. For this
1 .e. they convey f1 ow as well as
reason it is advisable that they receive only
promote its infiltration; roof stormwater or filtered runoff from
(ii) the excavated storage volume is pervious and/or ground-level paved areas.
back-filled with crushed rock or
gravel. 20mm nominal size; Because of the presence of hackfilling,
the volume required for a Dutch drain or
(iii) the drain or bed usually contains a seepage bed, in a given situation, is about
line of perforated pipe; three times that required for a corresponding
(iv) there is provision for outflow of open well or sump. The plan area is.
minor storm drainage to the formal correspondingly, greater by a factor of 2-3.
drainage collection system; The disadvantage of this significantly greater
area is offset by the fact that, with
(v) the gravel backfill is usually covering. the area does not represent a total
topped with paving or grass. loss to develop@Mnt (see Fig. 3.2).
The perforated pi pe 1 i ne usually inc 1uded b) Rainwater tanks Although any available
is not part of an associated underground storage in urban rainwater tanks causes a
network: its role is, primarily, to ensure an reduction in the runoff passing to drain-
even distribution of stored stormwater along age networks from individual allotments,
the 1ength of the trench or bed. Neverthe- the uncertainty which must necessarily be
less, these installations may properly be associated with this reduct i on dis-
regarded as extensions of the formal under- qualifies it as a dependable component of
ground collecti on system to which they are stormwater drainage planning. The role of
linked at their points of outflow. the rainwater tank is, therefore, almost
totally linked to conservation: it
Seepage trenches and beds, backfilled in enables the householder to use part of a
the manner described here, are employed in natural resource provided di rectly to him
Japan, Sweden and West Germany wi th soi 1 s and reduces hi s dependence on water
ranging from medium sands to loamy sands transferred from catchments outside hi s
(hydrau l ic conductivity, Kh.' range 5 x 10- 4 own.
m/s to 5 x 10-6 m/s); rainfall is similar to
that experienced in Southern Austral i a (see c) 'Mi cropondi ng' The temporary pond i ng of
Fig. 5.2) . See Wanielista 1979; Ichikawa and stormwater on individual ·allotments and
Yamamoto ' 1984; Jonasson _ 1984 (a and b); subdi visions - residential or commercial/
Holmstrand 1984; Sieker 1984. industrial - is a detention measure which
has, to date, found limited application in
c) Off-streaM porous storages It is some- Australia. Some excellent local contribu-
times possible to exploit the advantages tions to this aspect of stormwater manage-
of both retenti on and detent i on by ment have, however, been made by Nicholas
di verting portion of the flood flow and Cooper (1984), Boenisch (1984) and
passing along a natural channel into Phillips (1985). It is an option which,
off-stream storage which may be a nature- gi ven the ri ght soi 1 and topography,
formed reservoir such as an old meander or should not be overlooked in the planning
it may be man-made. Where the storage is of sub-divisions. The hydraulic princi-
in porous bed material - cOl111lOn in such ples upon which microponding is based are
situations - then floodwater disposal in the same of those of 'macroponding' (see
the manner descri bed for 'sumps' in the below) : the difference is a matter of
previous section wi 11 follow. Its design scale. Catchment elements suitable for
must incorporate prOV1Slon. for outflow development as microponds are carparks,
control , e.g. spillways, etc. These sports fields, open space recreational
characteri st i cs qua 1ify off-stream porous reserves, etc.
storages for inclusion among retention/
detention systems (see Fig. 3.3). ( d) Off-line storage This category of storage
may be added to an underground network to
remedy system overload in, usually.
confined situations where downstream
Embankmen t capacity is significantl'y less than that
required to carry upstream-generated flow.
By providing sufficient temporary off-line
storage to accol111lOdate a major portion of
Retention Basin this flow, together with flow control from
storage matched to the downstream
capacity, it is possible to utilise an
existing network and thus avoid the
expense of system enlargement or dupl ica-
t ion.
Fig . 3.3 - Schematic layout of an off-stream storage basin
(after Environment Canada, 1980b) Required off-line storage may be provided
by a run of large-diameter pipe or storm drain
connected into the system at the point of
3.4 DETENTION MEASURES overflow. Outflow control must be provided by
an appropriate 'throttle' connection between
a) Roof storage The use of roof area for the storage and the downstream pipeline (see
temporary storage and slow release of Fig. 3.4). A patented device - the 'Hydro-
rainwater is well known overseas but rare Brake' - has been developed to control outflow
in Austral ian experience. Main applica- in situations of the type described here
tion is with flat-roof commercial (Matthews et al 1983; Murphy et al 1981).
buildings and multi-storey car parks
whi ch, norma lly, impose severe runoff Off-line storages fitted with Hydro-Brakes
loads on city stormwater drainage systems. and cos ti ng 1ess than 50 per cent of
Using roof storage, it is possible to conventional remedies for overloaded systems
convert major or rare storm rainfall on a have been reported from the boroughs of York
building to minor level outflow to the and Scarborough in Metropol itan Toronto,
connected underground network. The roof Canada.
storage average depth needed to achi eve
this ranges from about 70 mm in e) 'Macroponding' The use of stormwater
Australia's most intense rainfall zones to detention basins to temporarily store
around 35 mm in the zones of least runoff from wide areas of urban or rural
intensi ty. 1 andscapes is a tool well known to
ARRB SR 34,1986 15
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
p resent -day d rai nage planners. The In rai nfa 11 /runo f f even ts. s t o rm r unoff
typical fonn taken by such a basin where passes from the urban landscape into the
it is employed in an urban context is that ponding area and on through the culvert
of a small flood control dam. Its outlet. As inflow continues, exceeding the
embankment is normally located in the res tri cted fl ow capacity of the outlet,
flood pla i n of the main drainage path fl oodwater is stored beh i nd the embankment.
carrying stormwater from the urban In major storm events, the spillway operates.
development and it is usually provided
with an ungated cu 1 vert-type ou t 1et and The ponding effect of the basin, coupled
has a spillway (see Fig. 3.5). with the restriction imposed by the culvert,
combine to produce an outfl ow peak from the
basin whi ch is si gni ficantly 1 ess than the
peak of the hydrograph passing to it from the
upstream urbanised catchment. The relation-
ship of these two peak flows, for a typical
case, is shown in Fig. 3.6.
Temporary Storage
INFL OW HYOROGRAPH
I ./ volu me of runoff held in te mp orary
~ storage at peak of outfl ow
TIME
Fig. 3.6 - Inflow and outflow hydrographs for a typical urban detention basin
Four broad classes of roadside channels find c) swales - well-maintained These are used
wide use in Australian practice - swales, in urban deve 1opment as out 1 i ned above.
blade-cut earth channels and two types of Travel times are about 4-5 times those of
kerb-and-gutter channel s. These are 1 i sted concrete kerb-and-gutter channels, the
below, with comment, arranged in order upper time limit applying to swales which
according to thei r retardi ng effect on are interrupted by driveway crossing. [See
surface-moving flows: Fi g. 3.7 (a) J •
a) sWilles - poorly uinhined Urban use of d) blade-cut earth channels - well-maintained
swales is confined, mainly, to low density These are used in urban development as
residential situations (density eight or outlined above. Travel times are about
less residences per hal where carriageway 2-3 times those of concrete kerb-and-
crown levels are at or slightly above gutter channels, the upper limit applying
local natural surface levels. When poorly to channels which are interrupted by
maintained they become irregular in both driveway crossings. [See Fig. 3.7 (b)].
cross-section and longitudinal grade.
Travel times in these channels are about e) stone pitcher or cobble kerb-and-gutter
5-6 times longer than those of concrete channels These are found in many suburbs
kerb-and-gutter channels owing to inter- of our older cities. They are regular in
mittent grass, weeds, exposed tree roots, both cross-section and longitudinal grade,
driveway crossings, potholes, etc. rSee very rough and more pervious than concrete
Fig. 3.7 (aiJ. kerb-and-gutter channels. Travel times in
these channels are about twice those of
b) blade-cut earth channels - poorly main- concrete channels. [See Fig. 3.7 (c)].
tained These are channel s formed and
maintained by grader operators and tend to
be confined, also, to low density
residential sub-divisions. They are used,
ma in1y. in roadway reserves whose
carriageway crown levels are significantly
below local natural surface and become
irregular in time in both cross-section
and longitudinal grade. Travel times are
about 3-4 times those of concrete
kerb -and -gutter channe 1s. [See Fi g. 3.7
(b)].
lei stone pitcher or co bble kerb and gutter channel
width
/~
~'d'=8
18 ARRB SR 34,1986
4
Rainfall/runoff mathematical models
ARRB SR 34,1986 19
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
P
This formula will be recogn ised as the
Rational Method formula with
coefficient, C, omitted or, more correctly,
runoff \
with runoff coefficient C = 1.00. This value
of C may therefore be applied to all similar
\ \
i mpervi ous catchments in whi ch there a re no
losses to
evaporation, etc.
infiltration, retention,
"- \ IMPERVIOUS
, \
CATCHMENT
-
.........
for duration 60 mi nutes
..........
(hyd rograph 1)
Example 2: i ntens i ty i 10 42 mm/h 1~
for duration 25 mi nutes
(hydrograph 2)
Exampl e 3: intensity i10 48 mm/h
for duration = 20 minutes
(hydrograph 3)
Example 4: i nten s i ty i 10 55 mm/h o 10 20 30 40 50 60
for duration 15 minutp<; Storm Duration (mins)---
(u) Rdinfall Inl"nsity-t ime
(hydrograph 4)
Relationship
In examples 1-3, peak flow rate Q is given by Fig . 4.2 - Catchment I - layout and rainfall intensity-
the Rational Method formul a:
o duration relationship for ARI 10 years =
(CA)i 10 15 r---,----r---.----.---,----r---.--~
- - - LIs (4.2 )
0.36
~
o
Example 1: Q = (1.0 x 0.10) 25/0.36 6.9 L/s
o ~ 5~~~+_~--_+~4-~--4_--~~.4--~
(4.3 )
As storm examples with shorter durations In examples 1-3, the duration of storm
and hence greater average rainfall intensities rainfall is long enough (duration ~ t ) to
are consi dered [represented by poi nts 1-3 in ensure the arrival of runoff from all parts of
Fig. 4.2 (b)], the resulting hydrographs show the catchment at or before the instant the
progressively higher peaks. The hydrographs storm ceases. This is not so in Example 4
are based on the assumpti on that the speed where runoff at outlet 0 has arrived from only
with which runoff elements travel to discharge 15/20 or three-quarters of the catchment at
poi nt 0, is steady i.e. constant at each the time of cessation of rainfall input. (The
location in the catchment throughout each quantit.Y 15/20 arises from 15 minutes storm
runoff event. duration, 20 minutes time of concentration).
20 ARRB SR 34,1986
STORM DRAINAGE DES IGN IN SMALL URBAN CATCHMENTS
ARRB SR 34,1986 21
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
t\-\- II
In this catchment, the speed of travel is --L from this
the same at all points at all times (Rational boundary =t
Method assumptions). It follows that runoff area
= 1;. 0 tc tc 3tc tc
from the lowest quarter of area A has either
passed through 0 at time t /4 mi nutes after
4 4zT
TIME -
the commencement of a consta~t intensity storm
0
on the catchment or .iust arrived there. The
area A/4 is described in this situation as the
Fig . 4.5 - Time-area graph fo r simple catchment of area A
'area contributing to runoff at 0 at time and time of concentration te
t /4.' Similarly for the area/time pairs A/2
a~d t /2, 3A/4 and 3t /4, A and t • These
pairs,c plotted in Fig~ 4.5(b), yfeld the
time-area relationship for the catchment.
0 20
Similar graphs can be constructed to
:-
describe the time-area responses of real-world <{
V
catchments which are irregular in shape, I..LI
/" C Ap'0 '40x 0·20
non-uniform in slope and which include a mix '"
<{ rtI
.s:;
,1008ha
Vl / /PE RV IOUS
of pervious and impervious components. :::>
o
Representation of such catchments on simple :; V CATCH MEN
~ 0·10 /
time-area plots requires the 'contributing
are",' of each component to be expressed in
Cl.
~ /
terms of equivalent impervious area i.e. the >--
z <{
II IMPERY lnJ 1<; Ci Ai =lOOxO'10
product of runoff coeffi c i ent and component I..LI U
=0·10ha
area, (CA). The time-area graph of Catchment
-'
;:'!: / CATCHMENT
o 10 20 30 40 50 60
listed in Section 4.2 in the derivation of TIME (minsl-
eqns (4.8)-(~.11):
The time-area concept which provides the Fig. 4.6 - Time-area graph for catchment II
theoretica 1 base for the ma .iority of present
day urban catchment ra i nfa 11 /runoff response
models was first presented in Austral ia by
Ross (1921) and Hawken (1921) and developed in The earliest published account of Rational
the papers of Reid (1927), Riley (1932) and Method principles being applied in the study
Escritt (1965). of urban catchment rainfall/runoff response is
attributed to Kuichling (1889). In his paper
Ku i ch 1 i ng presents ra i nfa 11 and runoff data
for four developed catchment in Rochester,
4.4 WHY A 'NEW' RATIONAL METHOD? N. Y., and postul ates that peak ~ l ow will be
observed at any point in a s wer)~hetwork when
A 1983 survey by Professor D.H. Pilgrim (UNSW) maximum storm intensity is applied to the
revealed that use by Australian practitioners upstream catchment for duration:
of the Rational Method to estimate urban storm
runoff flows far outweighs use of all other
methods. The su rvey a 1 so showed tha t tabu 1a r ' ••• equal to the time required for the
or 'hand' calculation procedures of the type concentration of the drainage waters from
presented in the Urban Drainage Design chapter the entire tributary area at the point of
of the 1977 version of 'Australian Rainfall observation. '
and Runoff' (I.E. Aust., 1977) were employed
by over 80 per cent of respondents. Lloyd-Davies (1906), in the published
report of his investigation of three Birming-
It seems appropri ate therefore to bri efly ham, U.K., developed catchments adopts a quite
address the question of Rational Method use contrasting position concerning time of
and to explain why a 'new' Rational Method concentration which he saw as involving travel
flow estimation procedure is being proposed from the extremity of the impervious or paved
for use in small urban catchments at this domain only. In a reworking of Kuichling's
time. Rochester data, included in his paper,
Full-area estimate:
/t
1St.
tICAl
pa r t
(CAl part =
1
20
(1.0 x 0: 10) + -- x (0 . 4 x 0 . 20) RecofTlllendation: outlet works for point 0 in
60 Catchment II should carry a design flow (ARI =
- 0.127 ha 10 years) of 17.3 Lis.
The hydrological data base comprises six main Sub-divisions are frequently developed without
topics: provision for rear-of-a110tment runoff
collection making the required travel time
a) Ultimate development assessment difficult if not impossible to estimate.
ARRB SR 34,1986 25
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 5.1
110 1\
\ ADELAIDE FOOTHILLS
Average rainfall intensitie s f or c---
MONTHLY AND ANNUAL RAINFALL (11lT1) -
1\ \ storm s of short durat ion AUSTRALIAN CAPITAL CITIES
100
\ 1\ CITY JAN FEB MAR APL MA Y JNE JLY AUG SEP OCT NOV DEC TOTAL
90
\ \
1\ 1\ Adel a ide 20 21 24 45 69 72 67 62 51 45 30 27 533
.~
~ ~o r---.
0:
"" '"'"
I'.........
I"'--- ~
y,
y;:r-z.-r--.
'" '"
'"~
'"
30
"-.... ~ :;sI-- r- In the sect i on s wh i ch follow , zone-
~
20
..........
r--.........
I'-......
~
~
...:....t..!. ~
-- r- dependent hydrological data are presented for
the Northern Austral i a and Southern Austral i a
zones only: data for Intermediate Austral i a
I-- locations are to be determi ned by interpola-
tion. The recommend ed procedure for inter-
10
polating a value for parameter P at station X
is:
10 20 30 40 SO 60 1. Det e rmi ne Northern Austral i a and Southern
Sto r m Duration (mi nutes ) Australia values for the parameter of
intere st - Pn and Ps , respectively;
Fig. 5.1 - Rai nfall intensity-frequency-duration chart for
Ad elaide Foot hills, Sout h Australia: storms 01 short durati on 2. Determine the 10-year, I-hour average
rainfall inte nsity ilt location X, i.e,.
The main determinant of storm rainfall/ \;
runoff res ponse ina deve loped ca tchme nt is
not mon t hl y rain f all but t he intensity and 3. Compu t e the requ i red value for parameter
du r ation of rainfall experienced during sto r m P: -
bursts. In all centres listed i n Table 5.1, i 25
except Perth , storm bursts occurri ng duri ng x
SUlllllle r' pr od uce highest intensities : this is P (P - P )
x n s
in sharp contrast with monthly rainfall whi ch 70 - 25
may yiel d highest gaugings , as in Adelaide , in
Wi nter. (5.1 )
The need to divi de the Australian
continent into climatic zones whose urban NORTH ERN AUSTRALI A
catchment s respond ins i mi 1a r ways has been 10 yea rs, 1 hour avera ge ra infall
i nte nsi ty , L,0.,:;.70 mm / h £:7)
explored by the AR&R review team led by
Professor D.H. Pilgrim (UNSW). Three zones
have be en de fined on t he basis of average
rain fa 11 i ntens i ty observed in stonn bursts of
design ARI = 10-years an d durat i on I-hour.
The zon es are :
Northern Australia zone
10-year , 60 mi nute avera ge intensity
~ 70 l1lT1/h
Canber r a
Southern Australia zone 10 ye ars, 1 hour average rainla II
inten sity , L,0,,';;25 mm / h
10-year, 60 minute average intensity
~ 25 mm/h
~Hobart
Approximate boundaries for the three zones are
shown in Figure 5.2 Fig . 5.2 - Austral ian cl imatic zones - urban drainage
26 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
0gap 01 00 - On (5.5)
Design ARI recommended for major drainage (CAho
systems is 100-years; design ARI's suggested [FIO O.ilOO - F.i ] - - - Lis
for mi nor drai nage systems 'nested' withi n n n 0.36
major systems are listed in Table 2.3.
which can be restated as :
Fm . im(CAh a
It is clear that in a design rare flood.
say AR I = 100-yea rs. in an urban catchment Lis (5.6)
which incorporates conjuncti ve1y-acti ng 0.36
above-ground and unde r ground drainage net- The frequency conversion factors F '
works. a significant portion of generated IOO
runoff wi 11 be conveyed by the underground t/
Fn and Fm are found from Table 5.5. The fre-
system. It follows that the requi red capaci ty quency M [eqn (5.6)J is found by tria1-and-
of surface channels can be significantly less error ina gi ven situati on and is 1 inked to
than would be required if they alone conveyed the value assigned to N. N-M pairs for
the entire rare storm flow. In the case of catchments in Northern and Southern Australia
short-durat ion s to rms (10 mi nutes-30 mi nutes ) are given in Tables 5.2A and 5.2B (minor
in Adelaide. South Australia. 5-years ARI system, zero blockage).
average rainfall intensities are about half of
those observed in co r responding 100-year In cases where partial blockage is considered
storms. Thus. 100-years ARI floods can . li kely an arbitrary '50 per cent blockage'
theoretically. be conveyed through Adelaide assumption is suggested. This leads to appro-
urban catchments by a combinati on of surface priate modification of the expression for gap
and underground drainage paths. each designed flow. Ogap. given in eqn (5.5):
to carry storm runoff of approximately 5-years
ARI flood magnitude. 0100 - ~n
(CAho
Adoption of an appropriate design ARI for FIOO · i l OO - 0.5F n .;n
- - L/s(S.7)
a catchment minor system therefore opens the 0.36
way to not only its design but also the design This affects the value of M which arises
of the ma jor system which complements it. The in a particular case from the general
latter design procedure employs the 'surface expression, eqn (5.6). Values for Northern
flow' approach described in Chapters 8 and 9. and Southern Austral ia (minor system, 50 per
Frequency aspects, only. of this approach are cent blocked) are also listed in Tables 5.2A
exp 1ored here. and 5.2B.
I\)
CD Fig , 5,3 - Overland flow travel time (shallow sheet flow only) for Australian urban catchments
l ( ~ 1
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
30·0 ,--------.----.---,-y-r--r--,--r-r--.-rr~rT"1___r--".----,.____,>rT",_,'V'I
15 0 f-----l-----+,I~+-+--,i--+--v:-l-+f +t41+IhH-f-Hr--H-~
10 0 f------t-~'---t-___t-it----+ -fl--+.A--tf---1f---+--+-1hH-I-I'-I-lI-H+hH
VI
5·0
~
w
E
40
-'
u.J
z: JO
z
«
OJ:
LJ
u.. 20
<:)
-'
-'
1-5
~
10
0·4 f--1--hr--I--+-I--It--Htf--Ir--f+l~f--fb'-H,-I--If--1f--ftf+---+---H
30 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
General Channel Flows 2. second grade paved areas These incl ude
car-park, drive-in cinema and block-paved
All other travel time cases can be found with areas which are, compared with typical
the aid of Fig. 5.4. This chart i s reproduced fi rst grade pa ved areas . re 1ati ve ly
from Chapter 6 of 'Road Design Manual' porous. Runoff from these areas may pass
(Country Roads Board , Victoria 1982). The directly to the formal collection system
chart NY be used directly to determine or to terminal or non-terminal stormwater
approxilllate travel tiMes in a range of rigid management installations;
ch annel types and , with the applicatio n of
multiplier ~, a range of loose-boundary 3. unconnected paved area This category
ch annel forms. includes all paved areas whose runoff
passes to the pervious domain before
reaching the formal collection network.
Mini~ (Total) Flow Travel Ti.e
4. pervious areas This category includes all
Although travel time from elements of networks non- paved areas and areas of similar
may be as short as 2 minutes (see above), nature e.g. lattice-block reinforced
total nominal flow travel time from any grass. Runoff from these areas normally
component to its point of entry into the passes to the collection network by way of
unde rground dra i nage collect i on network must informal paths and drainage lines.
be not less than 5 minutes.
Basic runoff coefficient values for the
All carriageway components up to 200 m in four surfaces are listed in Table 5.3 for
length, regardless of slope, fall withi n this Northern Australia and Southern Australia
provision. Time of entry for these can zones. Values for the Intermediate Australia
therefore be assessed 'by inspection' as 5 zone may be obtained by interpolation (see
minutes. Section 5.3). Good design practice requires
that values such as those listed be applied to
components of the ultimately developed
catchment.
5.6 RUNOFF COEFFICIENTS FOR DEVELOPED Wei ghted runoff coeffi c i ents, C , can be
CATCtKNTS determined for mixed development cat~hments by
inserting appropriate values from Table 5.3
Basic Values for Cl0 into eqn (4.7).
The task of adopt i ng runoff coeffi ci ents for
use in the design of drainage works for urban TABLE 5.3
catchments is made difficult for the designer
by: BASIC RUNOFF COEFFICIENTS (C l0 ) FOR VARIOUS
a) poor or non-existent data base from which DEVELOPED CATCHMENT SURFACES
satisfactory runoff coefficient values can
be derived;
Surface Classification Nort hern Southern
Aust. zone Aust. zone
b) uncerta i nty about the u 1t i mate extent and
type of development likely to occur in a First grade connected paved
catchment during its lifetime; and arpas:
- roadways ) C
l0
= 0.90 C
l0
= 0.90
cl distribution of various area types (roofs, - roofs )
general paved, previous, etc.) in a Second grade connected
catchment. paved areas, e.g.
- sealed carparks, ) IC = 0.75 C
l0
= 0.75
10
Study of aerial photographs of sample dr iveways, paved)
developments can provide useful design outdoor areas, )
information on item (c) above. Such etc. )
measurements, however, overlook the fact that Unconnected paved areas )
runoff f rom po rt ions of many roofs and from and )
some paved areas is diverted to the pervious Pervious areas: )
domain and should therefore be subtracted from - mi xed with paved areas) C = 0.70 C10 = O.~O
as i n residential land) 10
the cont ri but i ng paved a rea (A 11 ey and
Veenhuis 19831. The subtracted element should use )
be added to the contributing pervious area. - ma jo r urban open space)
areas, parks, etc. )
ARRB SR 34,1986 31
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
/
TABLE 5.4
RUNOFF COEFFICIENTS (~o) FOR VARIOUS DEVELOPED CATCHMENT LAND USES
I NDUSTR IAL
. heavy industry 0. 80 -0.90 0.80-0.90
light industry 0 .70-0.90 0 .60-0 . 80
COMMEI{C IAL
. city shopping complexes 0.90 0.90
suburban shopping complexes 0.80-0 . 90 0.70 -0.80
city office blocks 0 .90 0 .90
suburban office blocks 0.80-0.90 0 . 75-0.85
Some consistenc'y is apparent, however, in divisions yields the 'P' and 'F' conditions
the general categor'y of Australian fami1'y indicated in Fig. 4.7. Where pervious area
residential accommodation. Measured samples contrihution is low, as in Southern Australia:
from nine Adelaide residential suburbs taken
with the findings of Heeps (1977) and of (CA )fu11 (CA)part
Aitken (1975) 'yield the following (5.10 )
relationship:
and a single ClO suffices. In Northern and
per cent impervious in allotment area
Intermediate Austral ia the pervious ar ea
runoff cont ribution is frequently comparable
3.0 RU - 5.0 to that of its associated paved area and,
(5.9 )
hence, the eqn (5.10) appruxillidtion cannot be
where RD residential densit.Y in justified. Two runoff coefficients
residences per ha of allotment area, i.e. correspondi ng to the fu ll-area and part-area
exc1 udes roadwa'y reserve, nature stri ps, conditions must therefore be entered.
etc.
32 ARRB SR 34,1986
6
Hydraulic data base
(6.5)
(6.8)
By assigning a particular value to da and
Eqns (6.3) - (6.5) are used to determine:- hence db (see Fig. 6.1) eqn (6.8) reduces to
the form -
1. fl ow spread, w, in selected channe 1s con-
veying nominated flows; (6.9)
2. flow rate for certain depth and velocity
criteria conditions which form part of for the selected value of da • This relation-
Handbook design procedures; ship may be presented on a graph with values
3. estimates of flows captured by various of da coveri ng the full range of interest.
types of gutter inlets. Graphs representing two of the gutter/pavement
profiles included in eqns (6.6) and (6.7) are
Values for the parameters 8, Za, na , etc . presented in Fi g. 6.2. Note that any roadside
which apply to composite channels of the types channel type (rectangular, triangular , compo-
widely used in residential streets in site, etc.) can be described by a single curve
Victoria, South Australia, Northern Territory, on the depth versus Ot (= K~ plane of Fig.
QllPpnsland and A.C.T. are:- 6.2.
0·200
--Criterion 1
A
E
I 0·180
da 1> a·200m cases
Zb = 30 or 40
3
_ _--+--_-=---j-_ ",- 0
rorn
ClJ
L
a.
Vl N
II
Ll
d
D S'Om
..c.- 0·160 3-7Sm
.....a.
o
~
ClJ
0·140
B -- 3-Sm 4'Sm
4'Om
LL 3'Om
ClJ
3-Sm
'" 0·120
Vi
I
Ll
L 3'Om
ClJ da = 0-200m W= 2·5m c. da= 0'118m
~
A {
50 = 0'015m C{ so= 0·020
111
0·1 00 ~---I'-I--++----+-- Ut = 5585 S~I= 684 Lis Ut= 1040 So = 147 LIs 2'Sm
I
, B
{ da =0'150 m
50 = 0'057m T o{
w= 1'Om c. da= 0'06Bm
50 = 0·020 1'Sm
I 2'Om
~I----++----+-h-B- ,:',,~ u,
0t = 170 5~11= 24 L1s
0·080 0,,2300 0 '.Om ;:::
0 ' 060~~--~--~~~~----~~~~--~~~~~----~~~~----~~--~~
o 2000 Sti/2 4000 Sel l2 6000 Sd /2 8000 Sel l2 10000 Sel l2
Half-Carriageway Flow Relationship (Qt=Ks3/ 2)
Fig. 6.2 - Depth versus flow relationship (KSo""l for two gutter/ pavement channel profiles
900
1 700 Zb =40
~ / carriageway half-width
.:=!
/ =50m
0 600
~-
0
Zb =30
u: 500 ~-+-f+----!--+-----l---1----L--=:>'I.....:c--L-./ carri ageway ha If - widt
>-
ro
~
WO =3 ·75m
OJ ENLARGED SCALE
~400
L
L
ro
LJ
300
-;;;
I
200
0J .
~
50
W=1 ·0m Ib= 30 D
100
Zb=40
w~ 1·0m
00 --- .005 010 015 020 025
°0 01 02 ·03 04 05 ·06 ·07
Gutter Longitudinal Slope . So (m / m)
·08
..
·09 ·10 ·11 12
Fig. 6.3 - Hydraulic capacity. Qt. data for two carriageway profiles: Zb = 30 and 40
Lateral streets, i.e. roadways running Much experimental work - the most rel i-
generally parallel to contours, are frequent- able using full-size rigs - has been carried
ly constructed with dual-channel carriageways out on grated inlets of many different types
provided that the terrain cross-slope is not (Department of Main Roads, N.S.W. 1979; Earley
great. A single-channel form is however, 1979; Public Works Department, N.S.W. 1985;
often adopted for residential and/or minor Burgi and Gober 1977). The main finding of
access streets in steep terrain. The critic- this work is that a grated inlet of any type
a 1 slope at whi ch the change inform takes will capture the entire 'frontal flow', Qfr
pl ace appears to be around 3 per cent as shown [Fig. 6.1, eqn (6.4)], presented to it pro-
in Fig. 6.4. vided -
These 1atter characteri st i cs of gutter side-entry inlets, with and without deflect-
grates are part ly, at 1east, offset by thei r ors, opening lengths Lis = 1.0 m and 2.0 m,
potential for blocking, the two effects tend- has been carried out in connection with the
ing to cancel each other. preparation of this Handbook : results are pre-
sented in Fig. 6.5. See also Hughes (1974),
It is therefore recommended that design- Mills and O'Loughlin (1984) and PWD, N.S.W.
ers adopt performance rel ationships based on (1985).
frontal fl ow, Ofr, capture only used with
constraints 1 to 3 listed above. Frontal The following general conclusions may be
flow should be calculated at the 'normal' drawn from study of these data sources :
gutter/pavement section regardless of inlet
'depression'. The DMR, N.S.W. (1979) study (i) inlet length, Lis, is the most import-
reveals a sl ight performance advantage for ant determinant of capture performance;
depressed grated i nl ets, compared with unde-
pressed inlets. (ii) 'depression' of inlet lip below gutter
alignment level (typically 50 - 60 mm)
Two 'per cent capture' levels are em- leads to significantly improved capture
ployed in the design procedures presented compared with the performance of an un-
later in the Handbook - 95 per cent and 80 depressed inlet;
per cent. Gutter longitudinal flows whose (iii) a side-entry inlet with opening length
frontal fl ows correspond to these percent- Lis > 1.5 m and depressed 50 - 60 mm
ages of total flow are listed, for the Sec- for full inlet length captures signif-
tion 6.1 carriageway illustrations (lb = 30 icantly more than approach frontal
or 40) in Table 6.2. Additional data of fl ow, Ofr;
similar type are presented in Appendix A.
(i v) use of deflectors leads to further im-
provements in performance particularly
TABLE 6.2 in medium-steep longitudinal grade
channels, that is, So > 0.03;
CAPTIilE BY 375 _ GRATED INLETS
(v) little difference in performance re-
(Gutter la = 8 ; pavement lb = 30 to 40, see sults from the use of different types
Figs 6.2 and 6.3) of deflectors (square, saw-tooth,
corrugated,etc.);
(vi) inlets whose trays extend beyond the
95% capture: gutter/ pavement ali gnment perform no
gutter approach flow = 22 L/s better than those with trays equal to
80% capture : gutter width (otherwise same geometry,
gutter approach flow = 43 L/s depreSSion, etc.).
Notes:
o grated inlet - full gutter width Design information similar to that presented
(t ransverse bars) in Fig. 6.5, determined for other carriageway
o 1ength « 0.75 m cross-section profiles, is given in Appendix
o grating open area « 60% of total area A.
I 0 gutter longitudinal grade, So ~ 0.05.
Two levels of 'per cent capture' are pro-
vided in these graphs - 95 per cent and 80 per
Pavement cross-slope, represented by the cent. The higher standard has been adopted in
variable lb, has a significant influence on place of 100 per cent capture because of the
the depth and spread of fl ow approachi ng a uncertai nty inherent in ri g results in the
gutter inlet. Over the range of design in- capture range 97 to 100 per cent : capture/by-
terest (80 - 95 per cent capture), each one pass flow division at the 95 per cent level
per cent change in cross-slope produces a is, by comparison, well defined.
change of more than 10 per cent in total flow,
Ot. For this reason, grating capture data Data for the lower standard - 80 per
should be applied from rig tests (preferable) cent capture - are provided to encourage the
or cal cul ations whi ch incorporate cross- use of systems which employ other than 'full
slopes that differ from design cross-section capture' units. Such systems can requi re
profiles by not more than half of one per less underground pipe than systems using
cent. 'full capture' units. Systems which incor-
porate 70 per cent or 60 per cent capture
The comprehensive report by the Storm units can show even greater economies. The
Drai nage Research Committee (1956) of Johns 80 per cent standard has been adopted in the
Hopkins University, Baltimore, U.S.A., pro- Handbook for reasons of simplicity and because
vides a wealth of design information on side- of its present, although limited, use.
ent ry inlets with and without defl ectors. The
model scale ratio used in this programme was Flow at a grated or side-entry 'sag' in-
1/3 full-size. A similar study conducted at let obeys the laws of weir flow. U.S. Dept.
the University of Newcastle, N.S.W., is repor- of Transportation (1979) offers the following
ted in Henderson et a1 (1980). Flow capture general formula:-
by on-grade side-entry inlets with deflectors
in residential streets in Canberra, A.C.T., 0i = 1.66 Li di 1 • S (6.12)
has been measured and is reported in Willing
and Partners (1978). Testing of full-size where Oi = sag inlet flow (m 3 /s)
ARRB SR 34,1986 37
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
Li g length of grating perimeter (m) Figs 6.2, 6.3), sag inlet capacity flows for
excluding side closest to kerb, maximum spread of 2.5 m are:-
or
Lis length of clear opening (m) in 2.0 m grated inlets (undepressed),
the case of side-entry inlets 0i = 69 L/s
di depth of water above inlet lip
(m) 2.0 m side-entry inlets (depressed 50 mm),
Qi = 11 8 L/s
Depth di may be computed from carriageway
geometry, allowable flow spread and depress- (6.13)
ion of inlet lip. In the case of grated (un-
depressed) and side-entry (50 mm depressed) Simi 1 ar data for other gutter/pavement
inlets associated with carriageways of the sag inlet geometries are presented in Appen-
type used to illustrate Section 6.1 (see di x A.
110
100
--...-,
. 1·375mm" 1
Gutter Inlet-
with deflectors
150m~~F""" · ''''''-'''''''''''''''\\'
. o~.. Za= 8 · Zb = 33 '
90 Test Gutter / Pavement
Capture I Profile
r-~\---+---~--~--~~r-~---+---r--'---'-~
I
~
::::!
80 1 Curves ba sed on full size rig tests
conducted at South Australi an
Institute of Technology
2 All inlets depressed 50mm for full
0"'"' 70
inlet length
I- 3 Inlet t ray width equal to gutter width 1375mm )
UJ
--' 4 Test gutter/pavement profile as shown
Z
95% Capture
0 I I
I-
60 Capture
:r
LJ
I---I
, , t- 8~
« Legend
0
a: 2m inl et with deflectors
"-
"-
«
3
50
H--- 2m inlet without deflectors
~
0
--' 1m inlet with deflector s
<L-
40
a:
UJ
l-
I-
@ 1m inlet without deflectors
:::>
'"
30
95 % Capture
-f---j---+- --1
20 I-+-- j - --P.:-:::-'"-:-- t -
1----jr-_+-_+-_+-_+-~9:..:5:...;% Capture
o 0·02 0·04 0·04 0·08 0·10 0·12
GUTTER LONGITUDINAL SLOPE So (m/m) - - - -
Fig. 6.5 - Capture pertormance of 1.0 m and 2.0 m side entry inlets
38 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
ARRB SR 34,1986 39
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 6.3
GUIDELINES FOR THE MANAGEMENT OF SURFACE-MOVING
FLOWS IN DEVELOPED CATCHMENTS (MINOR SYSTEMS)
Illustrative e xamples ' of the guidelines are presented in Fig. 6.6
* see Secti on 2.6 where the relationship between flow spread and design
AKI 1S discussed.
Fig. 6.6 - Flow management in surface channels: Guidelines 1-5 (Table 6.3) illustrated
1. set of design guidelines covering items Information and data relating to these
such as pipe locations relative to car- items are presented in the following sections.
riageways, junction pit water levels rel-
ative to gutter levels, inspection pit
minimum spacing, minimum permissible pipe
size, anti-sedimentation provisions, cover 6.5 GUIDELINES FOR THE MANAGEMENT OF
requirements, etc. UNDERGROUND -MOVIr«i FLOWS
2. Minimum Grade analysis pipe flow charts
for vari ous types of pi pes normally em- The task of managing underground-moving flows
ployed in underground networks. within an urban minor stormwater drainage
system involves design of a network whose pipe
3. hydraulic data on pipe friction and junc- sizes and locations are governed by various
tion pit headlosses required for refin- practical and geometrical constraints and
ement of the pipe diameter selection pro- whose junction pit water levels are fixed by
cess and for computation of junction pit associ ated gutter and roadway fi ni shed 1ev-
water levels (Hydraulic Grade Line analy- els. The designer must formulate or be pro -
sis) • vided with a set of guidelines similar to
4. test algorithm for pit overflow. those listed in Table 6.4. These guidelines
shoul d not be regarded as mandatory for use
5. test algorithm for depth of pipe obvert. throughout Australian practice.
110 -
_\11 I Gutter Inlet Hydraulic Data
t- - - + - Capture performance of 1·0m and 2'Om side-entry
inlets with and without deflectors (see figure 6·5)
90 T",
-Ri ,,
80. 1-'- 1'.0 m Inlets 59 spread
[I [ "" I 2 0 m Inlets 118 LIs w= 2·5m
~ 70 t - .; ::i ~ I I !
I -
u.J
<;: N~
:.
"'" 95% Capture
: 60 r- I-
1\
---+--+--"<-+---1--+--' "~ 0% Capture
~ 50 '" -- '-~w
~'\:I:>~
3 \ '" I "" ~'~I:>~~--+--r--t
...
~ 9B
0
...J
a:
u.J
l-
40 .\
I-++--+-'<-\ ~D~
N---- / /x:~~--~~
I-
::>
I!)
1\ ~Li Y~r-~~
30
1\ /[:xV
_---.;If---+_-+-_+-_+---+__ .:= BO% Capture
95 % Capture
20 1l+++~21A:-bL:-+-----+~
------h;:-+--t-- 1----+-----+--+--1
V~ "r--- "'" i'--. I ~
II
/ / 1I\ \ I~......... ~
~ -- mr-. '--
1'-'--' I --, ~ ~5% Capture
~ I 1 --1 ~5 % capture
ARRB SR 34,1986 41
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 6.4
GUIDELINES FOR MANAGEMENT OF UNDERGROUND-HOVING FLOWS IN DEVELOPED CATCHMENTS
42 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
Guidel ine 11 Except for cases where Dt exceeds 0 by more than one pipe
increment (Guideline 10), pit f lo orolevels i n cross-connected
inlet/junction pits should be set at or below -
(gutter invert level - 0.45 m - D ).
Pit floor level should coincide with thg invert.
Guideline 12 Pit floor levels in mainline or lateral pipeline junction pits
receiving flow from cross-connected inlets must allow for
slope of not less than 0.01 m/m in cross-connection pipes.
Pit floor level should coincide with invert of the pipe carry-
ing discharge from a junction.
Guideline 13 Und er ground stormwater network components should be specified
by class in accordance with the techni cal information avail-
able from manufacturers and the provisions of Australian
Standard CA33-1962 'Concrete Pipe Laying Design'.
LEGENO
Pipes 600mm~ and under
may be placed in footpa Junction pi t IJ .P. I shown , - 0 -
provided that clear space
of 3m . is maintained from
pr operty boundary and
footpath is not requ ired
for elect ri city suppl y
II
'"
Gutter inlets ,-
side entry inlet/J.P ~
grated inlet I J.P.
~I
poles .
'sag' point
pipe lirie
/,
Y./ / --M I~ ROA-O--
/,, ;Z.drainage reserve
/ "
'/ N 5 W Housing Commission 'Road Manual' drawing 9.1 {19761
ARRB SR 34,1986 43
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
0·050 0·050
~
.§
o
VI 0
UJ
- VI
Q. W
Q.
o 0
-' -'
VI
VI
-' -'
«
z «
z
Cl O' 010 1----t-+-+--+--+-+-I'f-f+l'-J4-+-f-l Cl 0·010
::> ::>
to- to-
I.:) I.:)
Z Z
o 0
-' -'
0·005 0005
50 50
(Lis) PIPE
(a) roughness k = 0·3 mm.- normal condition pipe (b) roughness k = 0'6mm -poor condition pipe
Fig. 6.9 - Concrete pipes: chart for 'first round ' pipe selection
0·050 0050
E
E "-
E
"-
.§ '"
.'2-
Cl.fl) 0
'"
.'2-
Cl.fl)
0 VI
VI v:'::: v:':::
Q:fl)
W ..... .::: UJ-
.........
Q:[!!
Q.
0
.... '"
",:::J
Q.
0
-'
.... V)
",:::J
",,,( "'''(
-' VI
0>
VI E:!'c:
..!P '- :o . ~
-'
-' "t> « ;::-"t>
«
z ....
~3
'" z
(3
.f:~
Cl 0·010 ::> 0010
::> t-
t-
I.:)
I.:)
Z z:
0 0
-' -'
0005 0·005
50 10 2
50 10 2 500 10 3 5000 10 4
PIPE PIPE DISCHARGE (L i s)
(a) roughness k =0 ' 06mm -normal condition pipe (b) roughness k =0·15mm- poor condition pipe
Fig. 6.10 - Fibre-reinforced cement pipes: chart for 'first round ' pipe selection
ARRB SR 34,1986 45
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 6.5
1.5K [V~]
Inlet on 'T ' p' pe J unc t , on -
i.e. Qu = 0
w
I-SA • opposed laterals - Qo some 3.0 w 29
I-5B • offset laterals - Qo some 2.5 The results of current research will in
time yield a more accurate relationship.
46 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
TABLE 6.6
1. JUNCTION PIT WITH SINGLE ENTRY/EXIT PIPES situation which would otherwise, i.e. using
rectangular pits, fall into the cases
Hare's (1983) research on the hydraulics of considered above.
single entry/exit pits with pipes neither
concurrent nor meeti ng at 90 degrees, shows Internal shaping 'Benching' of pits to
that the pit water level headloss coefficient, provide a curved channel D /2 deep between
. K , which should be applied to the hydraulic ent ry and exit pi pes (see slPetch) can reduce
g~ade line at these structures is dependent on Kw· values obtained in ~ > 45° situations from
two main factors: 2.5 to about 1.5 (Archer et al 1978). It
appears to make no significant improvement in
(i) the location of the entry pipe centreline ~ < 45° situations. Similar findings are
(produced) intersection with pit walls; reported in Dick and Marsalek (1985).
and
Examples:
exit face
.~OfPit~
Q .
. :::--0"': Benching in a Benching in a
. . e<45· rectangular ci rcul ar
intersection junction pit junction pit
point. Plan View.
Watts (1983) has establ i shed a set of b) The pipe obvert depth test involves com-
formulae which approximate the results of parison of the quantity (hf + 1.5 Do)
Sangster et al and of Hare. against allowable head difference and is
illustrated in Fig. 6.12(b). This test
By the time Tables 6.5 and 6.6 are used incorporates an arbitrary invert depth
in the des i gn of a typi ca 1 mi nor storlTlHa ter limit of 2.5 Do below AWL. (The 2.5 Do
drainage system, considerabl"e information has value derives from the test conditions
been compiled by the designer concerning flows under which much of the information con-
in all component pipes of the underground tained in Tables 6.5 and 6.6 has been
network as well as gutter capture flows diver- obtained, i.e. pit water level 2.5 Do
ted to the underground system at inlets. The above invert.)
quantities Ou, 01, Og and 00 defined in Table
6.5 are therefore known and its inequalities _-y-_ _ _ Te st fo r ove r flow of upstre am pit - TES T 1
readily assessable.
AWL. ~~~
1
V
Values of Kw selected from Tables 6.5 Ass iqned ~ ~Kwh~ )
and 6.6 and applied in the Hydraul ic Grade water ----'---
Line method, give satisfactory underground le vel ----- ~1-:=::::--_I__"'B.!.!W-L"-
pipe sizes and water levels in mainline and
- Bottom
lateral pipeline junction pits. The resul-
water
ting network designs are acceptably close to leve l
those gi ven by more t i me-consumi ng methods
whi ch use preci se values extracted from the
'Missouri Charts' and Moody (pipe friction)
Chart. This point is revisited in Chapter 12
v1
- Concluding Discussion. (a) U/s pi t overfl ow t est : hf +Kw(2~ )~ (AW L -BWl) Eq.6·17
The computations for both tests commence pos s ible if it s upstream invert
at the network outfall - a point of fixed (de- is set lower than (AWL - 2.5 Do),
sign) water level - and should be carried out a conditi on which is undesirable.
simultaneously moving from pit-to-pit in an The alternative is to design for
upstream direction. Only pits along the main part-full outflow from the up-
drain pipeline{s) and lateral pipelines are stream pit (s ee Ta ble 6.5). This
considered. Water levels assigned in fixing option leads to pipe invert set
the 'first-round' network (i.e. AWL's) are by eqn (6.21):-
progressively revised to become BWL's (bottom
2
water levels) in the process: the upstream- Vo
moving calculation sequence permits this. pipe invert level ~ AWL - 1.5 Kw(-) - Do
(upstream) (upstream) 2g
Ei ther or both tests can be violated in ( 6.21)
a given situation without an unmanageable
design necessarily resulting. It will be and upstream pit water level
found that the requi rements of the overfl ow (BWL) is the same as that assign-
test [eqn {6.17)J can, generally, be met by ed (AWL) during the 'first-round'
appropriate choice of pipe diameter, Do, and design stage, i.e. BWL (upstream)
this should be the first action of the de- = AWL.
signer.
Outcome l/Outcome 2 situations : normal-
Sat i sfaction of eqn (6.17), i.e. TEST 1 ly, the upstream pipe invert level gi ven by
i n a particular case implies that full-barrel eqn (6.21) is above that given by eqn (6.19).
flow in the discharge pipe, diameter Do, can However, the inter-relationship between these
be achieved without overflow occurring at the levels can sometimes . be reversed. The situa-
upstream pit. It does not disclose, however, t ions wh i ch 1ead to such reversa 1 are those
the depth at which the pipe must be set to where large flows must be passed through
achieve thi s behaviour, and whether the re- mUlti-pipe junction pits or where large flows
quired depth is acceptable : this is the role are subject to severe di rect i on changes at
of eqn (6.1 8), i.e. TEST 2. pits. In cases where upstream i nvert level
given by eqn (6.19) is higher than that given
Two main outcomes of TEST 2 are possible: byeqn (6.21), the former level should be
adopted and BWL (upstream) cOfT1luted by eqn
Outcome 1 : If the eqn (6.18) inequality is (6.20), i.e. treat as Outcome 1 design situa-
satisfied, it follows that the t ion.
invert of the upstream end of the
discharge pipe, diameter Do, may The consequence of this procedure is a
be set above (AWL-2.5 Do) without mainline/lateral pipeline network in which
losing the full-barrel condition. pit water levels have been set by Hydraulic
This elevation is limited by eqn Grade Line analysis taking account of both
(6.19):- full-pipe and part-full operation. Pipe in-
vert and hence junction pit floor levels are,
pipe invert level ~ BWL + hf - Do (6.19) generally, above (AWL - 2.5 Do). The re-
(upstream) (downstream) sulting main network is satisfactory for
'approximate' design purposes and may be ex-
In this case water level in the tended to include the sizes of cross-connec-
upstream pit is given by eqn ted pipes by applying Guideline 10 (Table
(6.20) :- 6.4). This guideline recognises the small
2
minority of cases in which cross-connections
V carry high flows requiring special design
BWL BWL + hf + Kw{~) (6.20) attention.
(upstream) (downstream) 2g
Final design detailing involves applica-
Outcome 2 : If eqn (6.18) fails, it follows tion of Guidelines 11 - 13 together with site
that full-barrel flow in the dis- constraints, underground service avoidance,
charge pipe, diameter Do, is only etc.
7.2 GENERAL PROPERTIES OF SMALL URBAN points using, primarily, the roadway reserves
CATCtMENTS of its pri nci pa 1 down-s lope st reets • As in
rural catchments, individual drainage areas
A structure similar to that de scribe d above contributi ng runoff to identi fied node points
for rural catchments can also be observed in are termed 'sub-areas'.
urban catchments of any si ze. Di fferences
arise primarily where man-made components of Small urban catchments may be divided into
the built environment interrupt the movement two broad classes sim~e and complex.
of runoff over the natural terrai n forci ng Simple urban catchments are, typically, less
runoff elements to follow point-to-point loci than 20 ha in area and may be analysed as
other than those of steepest topographic single arainagc units. Complex urban
grade. This occurs, typically, where roadways catchments represent collections of drainage
and roadside channel s intersect overland units or sub-catchments each of area less than
drainage paths and where storm drainage is 20 ha: a complex urban catchment may, thus,
carried in underground pipes. enclose a total area considerably greater than
20 ha.
In larqe, totally urbanised landscapes
th i s interference has vi rtua lly no effect on The two classes ur sma 11 deve loped
identified natural drainage directions and catchments are discussed sepa rate ly in the
runoff disposal points and only a marginal following sections.
effect, if any, on boundaries. The watersheds
of large urban developments may therefore be
fixed in the same manner outlined above for
rural catchments. 7.3 SIMPLE URBAN CATCHMENTS
When the detailed drainage design of a An example of a developed landscape which
segment of such a 1andscape is undertaken, presents each of the catchment items reviewed
however, the interference of man-made in Sections 7.1 and 7.2 for a sub-division
components is found to greatly affect its comprising four simple catchments is shown in
boundary and in the matter of runoff disposal, Fig. 7.3(a}. The following items may be
it is not unusual fo r surface -mavi ng and recognised in this example:
underground-moving runoff to be channelled or
piped, respectively, to significantly a) natural drainage direction
different points. Identified natural drainage
d i recti on on the ot her hand is unaltered by b) ca tchment flood and s to rmwa t er d i sposa 1
development. points, L.O, M.O, N.O and P.D
points of the two runoff components from The structure of the .ajor drainage system
IMjor/rare st 0 rills and from minor storms for the illustrated sub-division or any
normally coincide in a simple urban catchment catchment withi n it can be readi ly obtained
e.g. Catchments L, M, Nand P in Fig. 7.3, but from information contained in Fig. 7.3(a).
differ in the case of the complex urban This has been done for Catchment M and is
catchments reviewed in Section 7.4. presented in Fig. 7.3(b). In this figure:
Node points in each simpl e catchment are the disposal point M.O is where major and
coded sequentially up the drainage network rare flood flows generated in Catchment M
conmencing from its flood and stormwater enter a local stream;
disposal point. Indi vidual catchments are
identified by a letter prefix, hence, M.O, the identified node sections on the flood
M.l, M.2, etc. escape network, M.l, M.2 and M.3 etc.,
LEGEND
Catchment stormwater
disposal points shown ' @
Catchment boundaries
shown ,
Node points shown , ......
,y.,?
Drainage network
shown , '. . . •
"ftt.,? 11.
Open space floodways ·3
shown , ======::.=
Contours shown , ----- 112
Scale
100 200
metres
park - -
LEGEND
M.3
-----r'------
I Sub-area boundaries
node I
I shown :
sectn. +-= I ...
C I C
QI I QI
"C I "C Primary drainage area
·in I 00; boundaries shown : ______ _
--
QI I QI
'- I '-
I
I Node pi ts shown :
M.2
_---of M.3
node Main drainage pipeline
sectn. +'
C shown : "M.] "H.3
:I: QI
l:l "C (coincides with primary drainage
'Vi
:I: QI area or sub-area boundaries)
'-
sub-area boundaries
shown: _ - _ - - - __
- Note: Each terminal gutter
inlet is assumed to receive,
initially. the entire runoff
from its associated primary
drainage area .
ARRB SR 34,1986 53
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
are placed immediately downstream from Note that each sub-area represents a
the node point!. of Fig. 7.3(a). Each collection of priMary drai nage areas.
receives the entire flood flow generated
in its upstream catchment. The lowest With these structures in place in any
node section (M.1 in this case) is simple urban catchment. the analysis and
refer red to as the Ca tchment 'termi na 1 design of its major and minor drainage systeMS
node section' (T.N.S.). Its entire can proceed. Chapters 8 and 9 are devoted to
collected flow is transferred without the procedures involved in major system
addition to the catchment flood disposal planning/design; Chapters 10 and 11 are
poi nt, M. O. The termi na 1 node section concerned wi th the desi gn of mi nor systems.
and flood disposal point of a simple Catchment M of the Fig. 7.3 development is
urban catchment frequently coincide; used as a case study illustration of these
procedures.
the 'flood escape network' is identical
to the drainage network for catchment M
gi ven in Fig. 7 .3(a);
54 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
CATCHMENT P
sub -catchments PA & PB
CATCHMENT N
su b- catch ments
NA ,NB& NC Detention basi n
with pipe outlet
CATCHMENT S
L& M
Reserve
catchment or sub-catchment runoff disposal ~v
","- linear park floodways shown ...... =====
node points shown
points shown ..... a
• M·3
prin cipal 5treet floodways shown . ~==:.
main road flood ways shown .
dra in age network shown . •
L-2 •
l ·1 Fig 7.4!b): Integrated major system
Fig 7.4la) : Catchments, main roads & drainage paths
pri ncipal streets
ARRB SR 34,1986 55
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
More frequently however, designers are competition with the demands of neighbourhood
forced to reduce the impact of upstream-orig- planning, building aspect, road hierarchy,
i nating storm run off by means such as those traffic management, etc., all of which impinge
described in Chapter 3. daily on the lives of the urban resident, the
needs of a major drainage system, whose pur-
pose rarely becomes apparent, frequently rank
Scope of a Major Drai ..age Systetl well down in the priorities of urban plann ing.
The major drainage system associated with an For this reason drainage designers can-
urban development is the network of surface not expect urban landscape plans to be always
flood paths taken by storm runoff during developed around 'most desirable' flood es -
times when its subsidiary minor system is cape networks. Instead, practitioners must
rendered parti ally inoperable as a result of develop skills enabling them to exploit the
blockage, or when the capacity of the minor potential of given urban layouts and terrain
system has been exceeded. In a properly to achieve their objectives.
planned scheme such occurrences are likely to
cause flooding of open space areas and inun- An ideal situation exists where an urban
dation of the grounds of buildings, but no plan is compiled by a team which includes
indoor damage other than to buildings of hydrological/hydraulic expertise. There is a
secondary importance. perceptible increase in this type of planning.
While the above advantage may be thought
of as primari 1y associ ated with schemes for
new developments, major/minor systems have an
8.2 MJOR SYSTEM P~IIIi PlOCEDlaE
important hindsight role to play in urban
runoff management. Th i s comes about in the
following way:- There are ei ght steps whi ch must be taken to
p1 an or design a major drai nage system for a
For a variety of reasons - the impossi- typical isolated development. They are:-
bi1ity of accurately predicting future deve-
lopment or, perhaps, lack of foresight on the STEP 1: Catchment definition
part of original designers - drainage systems STEP 2: Fi xi ng of roadway reserve capacity
frequently prove to be inadequate after some flows
years of service. The dominant characteris- STEP 3: 'Gap flow' design storm selection
tic of an overtaxed system is its inability STEP 4: System planning table
to contain flows of a given design frequency. STEP 5: Netwo rk revi ew
For example a scheme which was designed orig- STEP 6: System evaluation
inally to overflow in flows greater than STEP 7: Sub-area detailing
those generated ina 5-yea rs AR I storm is STEP 8: Final design detailing.
found, after 20 years of servi ce, to exceed
capacity every two or three years.
STEP 1: CatcMent de11"1 t1 on
Such a scheme may have much to gain from
a reapprai sa 1 based on the maj or/mi nor concept This involves the following set of tasks:-
in which the observed 2-years or 3-years ARI
flood capacity of its existing minor system a) locate development, i.e. climatic region,
is accepted and all augmentation efforts are rainfall relationships, etc.
devoted to providing open-channel f100dpaths
for major storm runoff flows (see Water Re- b) prepare contour map of area(1 or 2 metre
search Foundation 1984). The planning/design contours, or closer spacing if area very
approach which should be followed is identical flat); scale 1:1000 to 1:5000
to that described in this Chapter except for c) define development boundary and boundary
the status of the minor system design ARI = constraints consistent with the Master
N-years (see Section 5.4). In new devel- Drainage Plan (see Chapter 1)
opments thi s quant i ty must be adopted : in
rehabilitation work of the type briefly dis- d) identify pattern of internal roads, rele-
cussed here, it en j oys the status of an vant traffic management information
'observation' • e) identify roads and streets as dual-channel
or potential Single-channel flow paths and
A1 though the cost of 1and and property their hydraulic characteristics (see Sec-
acquisition for drainage easements is likely tion 6.1)
to constitute a major outlay, the total prog-
ramme may well be not only attractive in the f) identify major (common) 1and use areas
financial short run but may also involve g) identify N-years design ARI for underground
minimum public and business i nconvenience in network; is partial blockage likely?
its execution. It is also likely to offer a
higher level of flood security than was pro- h) fix 'natural dra i nage direction'
vided under the original scheme. i) nominate flood disposal points see
j) define internal isolated )
It must be recogni sed by the drai nage catchments and node points )Chapter
designer that sound storm runoff management
practice - important though it is - repres- k) define flood escape networks, nOdej
ents but one of many competing and at times sections and drainage sub-areas of 7
conflicting objectives of the urban plan. In each isolated catchment
58 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
ARRB SR 34,1986 59
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
The question of design ARI recol1lllended poss i b 1e to determi ne for each f1 ood escape
for major systems, and the i nterpretat i on of path, its 'tributary (impervious) area' : -
this in terms of the conjunctive use of sur-
face channels and the pipes of the underground The tributary (impervious) area, TAi,
network, if present, is discussed in Section which may be linked to an identified
5.4. The outcome is presented in Tables 5.2A flood escape path, is the impervious
and 5.2B. area which yields, in a storm of average
intensity equal to that selected in STEP
Information obtained from these Tables 3, peak runoff flow matching the storage-
enables the designer to confine his attention corrected capacity flow, Qsc, of that
to that component of the design flood 'gap path.
f1 ow', Qgap, whi ch is movi ng in the surface
channels only of the flood escape network. The table 1 isting values of TAi for the
The designer I1lJst adopt a 1 ikely blockage full range of flood escape paths available in
condition as part of this process. a development constitutes its System Planning
Table.
The third task involved in STEP 3 - that
of fixing design storm duration - may require The table is used inSTEP 5 - Network
one iteration for it to be correctly fixed. Revi ew. The only data whi ch must be brought
This is built into the design procedure (see by the designer to make use of the table
STEP 6 below). However, a fi rst approxima- are:-
tion duration is needed to initiate the cal-
culations. Critical storm duration should be a) flood escape path carriageway width; and,
selected according to the guidance given in
Table 8.1. b) carriageway longitudinal slope.
TABLE 8.1
STEP 5: Network rev; ew
DESIGN STORM DURATIONS* FOR SMALL URBAN
CATCtMENTS Of all the data and component information
contained in the catchment definition (STEP
evelopment) I
~
1), those relating to basic road form
type\ReSidential commercial/I carriageway widths, roadway reserve cross-
roadside ... Sub- Industri al sections, pavement types, etc., - are the
channel divisions develop- most amenable to change. Th e netwo rk revi ew
\ type ~ ments procedure devolves upon this fact, for it
enables a tri al urban pl an to be tested and
kerb-and-gutter 10 - 15 15 - 20 modified, where necessary, without disturbing
roadside channels minutes minutes the plan itself in any basic way or altering
throughout the inter-relationship of its main compon-
grassed swale or
blade-cut road- N.A.
I ents.
60 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
The outcome of the system evaluation This step involves all detailing necessary to
process is a layout of 'adopted' drainage define the system of open channels - including
networks. ca rri ageways, roadway reserves, f1 ood-proof-
ing, drainage easements, roadway hydraulic
geometries, etc., - which will convey runoff
STEP 1: Sub-area detailing from major system design storms through and
beyond each catchment wi thout indoor damage
Completion of the major drainage system plan- to residential and other important buildings.
ni ng procedu re i nvo 1ves one further step -
the detailed review of flow movement within The resulting plans form the basis for
each sub-area. This calls for careful appli- the design of the minor drainage system to be
cation of the principles of hydrology and incorporated within it.
62 ARRB SR 34,1986
9
The major drainage system -
case study applications
Housing density in the sub-d i vision will The follow i ng data and information relating to
catchment definition are ava i lable. Most
be. init i ally, 16 residences per ha of dedi-
items are included in Figs. 9.1(a ) and 9.1(b):
cated area i.e. excluding roadway reserves
etc. Ultimate development (see Sect i on 5.1) (a) catchment location: Adelaide foothills
during the life of the drainage system is lone, Fig. 5.2);
(Southern Australia
est imated to be equ i va 1ent to 20 residences
rainfall . Fig. 5.1
per ha. Some open space park areas are
located within the sub-division. (b) contour map - Fig. 9.1
Two a lternat i ve road 1ayouts are (c) sub-division catchment boundary - Fig. 9.1
considered. The first, Case 1. uses a road
pattern of the conventional grid type; the (d) pattern of internal roads and streets -
second. Case 2, employs a contemporary layout Fig. 9.1
of crescents. cul-de-sacs. etc. and is based
on a plan developed by a leading Canadian (e) dual-channel and potential single-channel
engineer-planner, P.E. Theil (1977). All streets - Fig. 9.1
roads will have sealed pavement carriageways
with concrete kerb-and-gut ter borders. It is (f) major (common) land use areas - Fig. 9.1
anticipated that underground pipes will be
used in the catchment minor drainage ~ystem. (g) an underground network will be
Partial blockage (50 per cent blockage) of incorporated, design ARI = 2-.years; 50
these pipes in major runoff events is con- per cent blockage to be assumed
sidered likely.
(h) natural drainage direction - Fig. 9.1
The Case 1 and Case 2 sub-di vi si ons are
ill ustrated in Fiqs. 9.1(a) and 9.1(b) (i) flood disposal points - Fig. 9.1
respectively. Some aspects of the Case 1
exampl e are discussed in Chapter 7 (see Fig. (j) sub-division internal isolated catchment
7.3). It · is assumed, for purposes of boundaries and node points - Figs. 9.2 and
illustration. that runoff from individual 9.3
residences in the ultimately developed
catchment will be di rectly-channelled to the (k) flood escape networks. node sections and
surface stormwater drainage system. Drainage sub-areas - Figs. 9.2 and 9.3
from positive grade allotments (see Fig. 9.1)
will be conveyed d i r e ct l y to fronting roadways Concerning 'catchment boundary and
and drainage from adverse grade allotments to boundary contraints' [see item (c). STEP 1.
rear-of-allotment channel s or rear access Section 8.2]. there is no inflow to the roads
lanes. and streets of the subdivision from outside
its boundary. The passi ng of stor", runoff to
It may be further assumed that High Street side boundary flood paths (Eastern Highway and
(bot h ca ses) will have the status of 1 oca 1 West Street) should be MiniMised. It is
ARRB SR 34,1986 63
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
positive grade
HIGH
~ l~ ~TREET
TO
allotment
----t:==r----1 ---......
' -96
a dverse grad e
allotmen t
flood disposal
points shown . . .. . . ®
rear of allotment
drains shown . . . . . .
floodways shown ..
dual- channe l r oad-
ways shown .. . . . . . -=i;","_--
p'otential single-
channel roads
shown ...... .
contours shown . . Toe ______
sub-division
boundary .. . .. . .. . . _ _ _
SCALE
, i
100 200
me tres
assumed that these floo d paths convey sizeable STEP 2: Roadway reserve capacity flows
f1 ows from remote ca tchments and tha t addi-
tional floodwater input in the vicinity of the
recelvlng domain should only occur if The particular roadway forms to be used in the
unavoidable. development have 7.5 m and 10.0 m carriageways
within 16.0 m amd 20.0 m, respectively.
The prelimi nary road hierarchy information roadway reserves. Roadway reserves: kerb-and-
available for the sub-division(s) is gutter 0.375 m profi le and pavement cross-
suf fi c i ent to force a change in one item of slopes (Z = 30 and 40 for the 7.5 m and 10.0
catcn.ent definition data relating to High m carriag~ways, respectively) are the same as
Street in both cases. Its status as a local those used for illustrative purposes in
traffic distributor requires its cross-section Section 6.1 of the text. The 7.5 m
to be changed from potential single - channel carriageway is used for access roads, the 10.0
(north@rn segMent) to dual-channel throughout. m carriageway for local d i stributors.
64 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
Flow capacities of these carriageways Taking design ARI 50-years for the
(half-carriageway flows) are presented in Fig. surface system only and storm duration of 10
6.3 and are 1i sted. for the range of 1ongi - minutes, design storm average instensity, from
tudinal slopes present in the sub-division. in Fig. 5.1 is 90 mm/h.
Table 9.1A. The storage-corrected capacities
of these carriageways are listed in Table STEP 4: SysteM Planning Table
9.1B: a 10 per cent correction has been
applied for reasons explained in STEP 2. By bringing together data from STEP 2 and STEP
Sect ion 8.2. 3, it is possible to determine the tributary
(impervious) area, TA., which will yield,
STEP 3: Design ston. selection under design storm conditions, a peak runoff
flow matching the storage-corrected capacity
The recommendation that major drainage systems of any roadway flood escape path likely to be
should be designed generally for ARI used in the Fig. 9.1 developments. The TA .
100-years (see Section 2.5) is adopted and va 1ue requi red in each roadway case can b~
parti a1 blockage (50 per cent) of the found from substitution into the Rational
associated underground network assumed. Since Method formula [eqn (4.2)).
the minor drainage system will be designed
subsequently for ARI = 2-years. it follows (TA;) ;50
Lis (9.1)
that gap flow, Qgap ' design ARI M = 50-years 0.36
should be used (from Table S.2B). where Qsc storage-corrected capacity flow
in flood escape path (from Table
Design storm duration for the particular 9.1B)
conditions which are anticipated for the average rainfall intensity for
ultimately developed catchment (see Section storm of design ARI = 50-years
9.1) may be found from Table 8.1: storm and duration equal to that
duration equal to 10 minutes is adopted. adopted in STEP 3
TABLE 9.tA
CAPACITY FLOMS. Qc ' FOR 7.5 • AID 10.0 • CARRIAGEWAYS
TABLE 9.18
STORAGE-CORRECTED CAPACITY FlOMS. Qsc '
FOR 7.5 • All) 10.0 • CARRIAGEWAYS
TABLE 9.2
MAJOR DRAINAGE SYSTEM PLANNING TABLE
It is concluded from this analysis that Completion of the above network review
the total runoff generated in Catchment M in a provides the designer with what should be
design storm of ARI = 100-years approximately regarded as a 'first approximation' major
can be contained within the 7.5 m carriageways drainage system. This follows from the fact
of its f1 ood escape network acti ng conjunc- that important design information contained in
tively with its associated underground the System Planning Table (Table 9.2) is based
network, assumed to be 50 per cent blocked. on catchment travel time adopted from the
The likely decision to assign a 10.0 m guidelines of Table 8.1.
carri ageway .to Hi gh St reet for rea sons of good
traffic management practice will not conflict Before the design can progress to STEP 7,
with this conclusion. a check on the suitability of the adopted
catchment travel time must be made in each
Consider now Catchment L in the Case 1 catchment of the derived major system(s).
development (see Fig. 9.2 and Table 9.3). Note that major system catchment travel time
for an urban development is taken as catchment
The analysis and tabulation proceed in impervious area travel time (see Table 8.1).
much the same manner as for Catchment M until
node section L.2 is investigated. Here, the Allowing for roof-to-gutter or
test for a 7.5 m dual-channel flood escape roof-to-easement travel and adding flow time
path fails ('N.G., reconsider' in Remarks along road and street gutters (see Fig. 5.4)
column) and a 10.0 m dual-channel carriageway it will be observed that travel time of 10
rHIGH ST REET
2· 32
ha
0·84
f
ha
flood escape
network . 2·27
ha
I N'l- •
M·4
N'O-
MO-
single-channel street sho .... n: =~~=
dual- channel street sho .... n: --===--
.
HIGH STREET
/ 1·26 ha
flood escape
network
mi nutes adopted inSTEPS 4 and 5, is, in some The situation in Catchment L at node
catchments, short. A travel time of 15 section L.2 in both the Case 1 and Case 2
minutes for some Case 1 and Case 2 catchments developments, warrants further attention.
might be more appropriate.
Fifteen-minute ARI = 50-years storm bursts
The network review (STEP 5) has shown that in the Adelaide foothills show an average
the flood escape paths of Catchments M and P intensity of 78 mm/h (see Fig. 5.1). Applying
(both Cases) can accommodate the runoff this value into eqn (9.2) yields a new
generated in a 10-minute design storm. relationship for tributary (impervious) area,
Further review of these using a catchment namely:
travel time and, hence, storm duration of 15 0.36 Qsc Qsc
minutes will reach the same conclusion making =- ha (9.8 )
it a redundant exercise. 78 217
TABLE 9.3
NETWORK REVIEW FOR CATCHMENTS, L, M, N AN> P - CASE 1
fl ood escape path detai l adjacent contributing
sub-area clll1ul ative
esca e ath t ri butary weighted upst ream TEST REMARKS
node path 1ongi tud i na 1 (imperv. ) area runoff (CA)50 (CA) 50
section description slope, So a rea, TAi coeff.
(ha) (ha) (ha) (ha)
2 3 4 5 6 8 9 10 11
L L.4 dual-channe l , 7. 5 m 0.03 6.1 6 1.14 0. 28 0.32 0. 32 0. 32 < 6.16 O. K.
L.3 dual-channel, 7.5 m\ 0.02 6. 88 2. 15 0. 58 1.25 1.57 11.57 < 6. 88 O. K.
L.6 dual-cha nnel, 7.5 m\ 0.03 6.16 2.47 0. 58 1.43 1.43 1.43 < 6.16 O.K.
L.5 dual-channel, 7.5 m 0. 005 3.4 4 2. 25 0.58 1.31 2. 74 12.74 < 3. 44 O.K. )
I I L.2 dual-channel, 7.5 m' 0. 01 4. 92 2.15 0. 58 1. 25 5.56 5.56 ( 4. 92 ) N. G.r econsider
~:!~ ,
dual-channel,10.0 m, 0.01 5. 56 15.56 < 6. 16\ O.K .
L.1 floodway, 10. 0 m
,
(roadway) ,
0. 005
2.20 0.58 I 1.28 I
I I 6. 84
\ , , 6.84 , ,
from Table 9.1A fl oodway deiig n flow at L.1 approximately (-- -- ) x 1000 Lis = 1554 Lis, floodway design flow
4.40
TABLE 9.4
NETWORK REVIEW FOR CATCHMENTS, L, M. N Aft) P - CASE 2
I flood escape path detail , adjacent contrlbuting ,
I nod e I sub-area
------r'------7es~c~a~p7e~a~t~h----------~'~t~r~lb~u't~a~ry~'------~'~
~l~gh~t~e~d~'------
cumul ative I upstream
II,
TEST REMARKS
:------::p"'="at;'ih?-"""--'::"::"::':':"'l"o=-=n:-:gTit"'u""'d"i""n-:T
a1 , (i mp e r v. ) a rea run 0ff ( CA) 50 (CA) 50
section description slope, So area, TAi coeff .
(ha) (ha ) (ha) (ha)
3 4 5 6 7 8 9 10 11
ARRB SR 34,1986 69
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
There is no need to completely recalculate Consi der desi gn extreme storm runoff
Table 9.2 using the above 'new' expression for joining the major system network from the
TA . in order to further investigate one lateral street leading to node point M.5 in
'd'ouble spot' i.e. node section L.2 when, in catchment M (see Fig. 9.4). The terrain
fact, only the TA . value for a 7.5 m cross-slope in the vicinity is about 5 per
dual-channel carriagJway with S = 0.01 is cent: it is potentially a single-channel
required. Application of eqn (9.g) leads to: carriageway street:
1230 flood path description : single-channel.
TA. = - - = 5.67 ha
1 217 (9.9) 7.5 m longitudinal slope, So = 0.02
low, landscaped nature strip levee bank along Further discussion of these matters cannot
the southern boundary of the intersection be justified in the present publication .
would be a valuable safeguard. Calculations Suffice to conclude that with careful
carried out to fix the height of this detail ing, thoughtful planning and the use of
embankment are part of the necessary hydraulic modest flood-proofing measures, it is possible
computations. to handle major flood flows generated in
small, isolated urban catchments wi thout
Some indication of the height required may damage indoors and without inter rupti ng the
be gained from the following: supply of essenti al communi ty services or the
functioning of strategic installations.
If flow moving down-slope towards node
point M.4 were to be abruptly stopped by a
pond of water in the region of the STEP 8: Final design detailing
T-intersection, the maximum height of levee
(approximate) which would be required to The outcome of STEPS 6 and 7 is a ser i es of
contain the pond is given by : deSign and planning decisions and component
detail computations which will, when realised
(9.10 ) in the field, enable the goals of a major
drainage system to be achieved . STEP 8
where h levee height about top-of-kerb i nvolves the process of committing those
decisions and deta i I ing to paper in the form
v = averagevelocity of down-slope of drawings for a works programme .
ave moving flow
In the vicin i ty of M.4, S for the It is clear from the definitions of isolated
down -s lope roadway is approx i ma te9 y 0.03 and and non-isolated catchments given in Section
average veloci ty approximately 1.6 m/s in a 8.1 that non - isolated catchments give rise to
design flood. Required levee height is, runoff management planning and design problems
therefore, about 0.13 m. Some freeboard would which are Significantly more complex than
need to be added to thi s. those presented by the types of developments
investigated in Section 9.2.
It will be necesary in some of the
hydraulic computations of STEP 7 to find the A variety of solutions to the basic
design flood flow rate at various locations in problems - how can flow peaks be reduced? how
developed catchments. These should be can flow peaks be delayed? - is avai lable to
computed using the principles set out in the designer. These fall into three broad
Chapters 4, 5 and 6 of the Handbook. categori es:
ARRB SR 34,1986 71
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
ARRB SR 34,1986 73
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
The catchment hydrological model which ture of how and where the stormwater runoff
meets these requirements is defined in Design flows generated in a catchment are disbursed
Principle No. 3:- in either the surface drainage system or its
underground counterpart. .
D.P.3. The hydrological model which forms the
basis of all later stages in the de- Operations in the procedure outlined
sign of a minor drainage system for a above are carried out for each developed
catc hment must descri be it s compon- landscape drainage unit. These may be small
ents (ultimately developed) and yield isolated catchments (see Fig. 7.3) or compon-
a sati sfactory representati on of its ent sub-catchments of complex urban land-
runoff response to rainfall input in scapes (see Fi g. 7.4). In the 1atter case,
all desi gn storms of ARI = N-years Phase I I must inc 1ude a fi na 1 step in whi ch
and smaller. the interaction of flows moving underground
between sub-catchment disposal points towards
Design storm rainfall applied to this their (catchment) central disposal point must
model by way of an adopted rainfall/runoff also be considered.
mathematical procedure yields the required
fl ow est imate( s) at each catc hment reference Design Procedure - Phase III
point. This procedure i s defined in DeSign
Princ.iplp. Nn. 4:- Phase II encompasses the flow estimation/dis-
tribution segment of the total procedure. It
D.P.4. The rainfall / runoff mathematical mod- also includes some elements (surface-to-under-
el which should be used with the ground component selection) which, strictly,
catchmen t hydrological model must be fall into the category of 'design'. Identif-
a valid or acceptable procedure which ication of these components forms the start-
yields the greatest runoff estimate i ng poi nt for Phase I 11. Phase I I I i nvol ves
for each compo nent drai nage unit, the application of Design Principle No. 2
co ns ide red individually, for design guidelines relating to the management of
storms of ARI = N-years and sma ller. underg r ound -movin g stormwater flows to design
an 'approximate ' underground network. Approx-
Application of DeSign Principles 3 and 4 imate pipe headloss values and pit headloss
enables the designer to estimate design flows estimates are employed in the deve lopment of
re su lting fromARI = N-years storms in, first- this design which concludes with a catchme nt
ly, all primary drainage lines (see Chapter Hydraulic Grade Lin e (pit water l eve l s) being
7). With this information and the DeSign declared, satisfying N-years design ARI r e -
Principle No.1 guidelines on surface-moving quirements .
flows, it is possible to select and locate
gutter inlet and concent rated flow entry This network is combined, in each case,
structures needed to transfer surface-moving with the surface drai nage component select-
stormwater to the underground network. The ions made in Phase II to provide an approxi-
stortTlrlate r flows upon which deSigners mu st mate minor stormwater drainage system design.
base their s elections and placements are the
subject of DeSign Principle No. 5:- The fi nal segment of the procedure i n-
volves detailed modification of the approxi-
D.P.S. The components of any primary drainage mate system deSign, as required, in the light
line including its inlet(s) allowing of site constraints forced on the design by
bypass, terminal inlet, concentrated service locations, cover requirements, need
flow entries, branch and lateral un- for additional inspection pits, etc. In cer-
derground pipelines, etc., should tain cases, final deSign detailing may call
co nvey and di scharge the peak fl ow for a re-working of the Hydraulic Grade Line
generated in its catchment c rit i ca 1 computations using accurate pipe and pit head-
desig n storm having ARI = N-years. loss values: some Significant c hanges to the
Surface channel compo nent s shoul d be approximate network may ensue in these ci r-
se 1 ected in accordance with the cumstances.
guide lines of DeSign Principle No.1.
(STEP 7). Where the outline is to be inter- value for N-years design ARI
preted for isolated urban catchment cases, types of 'preferred inlets' and hyd-
'sub-catchment' should be replaced by 'catch- raulic characteristics of these
ment' and all references to sub-catchment crossflow acceptable or not acceptable
interaction disregarded. at minor street intersections
pipes : concrete or FRC; normal condi-
The three phases into whi ch the mi nor tion or poor condition
system design procedur'e is divided may be
sub-divided into a set of eleven main steps. i) measure, extract or classify and record
These include STEP lOA, an optional cost/ the following for all components contri-
frequency insert, which need only be employed buting runoff to primary drainage lines:
by designers seeking comparative cost data
for networks resulting from design ARI's cov- area
ering a range of values of N (see Section land use
2.6). ' di stri buted' or 'concentrated' fl ow
entry
STEP 1: Sub-catdment defi niti on drainage line characteristics (type,
STEP 2: Design guidelines and data PHASE length, slope, etc.)
(surface-moving flows) I allowable or capacity flow at terminal
STEP 3: Design guidelines and data i nl ets.
(underground-moving flows)
Almost all of items (a) to (f) inclusive
STEP 4: Hydrological model - stage 1 relate to drainage network structure (see
STEP 5: Hydrological model - stage 2 Chapter 7). The following definitions and
STEP 6: Design flow distribution in explanations are needed in order to proceed
primary and main drainage PHASE with STEP 1:-
lines II
STEP 7: Design flow compilation - Component identification code: Node pits in
all components of sub - the mi nor drai nage system network carry the
catchment same identifiers as corresponding node sect-
ions in the major system. A supplementary
STEP 8 : Pit water levels and 'first- codi ng system is requi red to enabl e compon-
round' pipe sizes ents other than node pits to be identified.
STEP 9: H.G.L. and pi pes of approx- The system set out in Fig. 10.1 is used in the
imate network design PHASE Chapter 11 illustrative cases.
STEP 10: Approximate system design - III
ARI = N-years
(STEP IDA: Cost/frequency insert) P7N1E1Nl
STEP 11: Final design detailing P8 P12
M·3Wl
M3
M·3W2
STEP 1: Sub-catc~ent definition M2N2
ARRB SR 34,1986 75
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
runoff from (usually) large-area compo nents, 10.1) and are adopted to ill ustrate the de-
e . g. residential sub-division, dri ve-in sign of minor drainage sy stems in Chapter 11.
ci nema, ca rpark, etc. Stormwater from sllch
a reas enters the system as concent ra ted input OUTCOMES OF STEP 3 (see Table 10.1)
to the main surface rlrainage line or is pass -
ed to the unde rgroun d network via a sump and / 1. Adopt guidelines Table 6.4 or ) TABLE 3
or junction pit. similar )
Allowable or ca pacity flow at a terminal 2. Reference: Sections 6. 4 - 6.8 inclusive.
gutte r inlet can only be found aft e r su rface -
movi ng fl ow ma nag ement gu i de 1i nes have been Adoption of these guidelines, taken with
adopted in STE P 2. This item re la tes to the the data base compiled in STEP 1, completes
hydraulic characteri stics of the catc hment Phase I and provides the foundation for all
roads and streets [item (e), STEP 1, Secti on subsequent stages of the desi gn procedure.
8 . 2J and preferred inlets [i tem (h) aboveJ.
STEPS 4 & 5: Hydrological Models -
OUTCOMES OF STEP 1 (see Table 10.1) Stages 1 and 2
1. Contour map of sUb-catchment,~ By means of the procedure and guidelines re-
boundaries. node pits, FIGURE lA viewed in Phase I, it is possible to convert
terminal gutter inlets, etc. , real-world sub-catchments into mathematical
representations or 'hydrological models'
2. Sub-catchment underground whi ch can be used to yield design flow esti-
network (Stage 1) gutter mates and flow distributions in all drainage
inlets, dimensions, etc. FIGURE 18 path components. Th is i nvo 1ves the app 1 i ca-
tion of Design Principles 3 and 4 (see Sec-
3. Table of sub-catchment TABLE 1 t i on 10.1).
properties
It is assumed in the i nit i a 1 sub-catch-
4. Reference: Chapter 7 and Sections 2.6, ment model (Hydrological Model - Stage 1)
6.1, 6.2, 6.4. that design flows generated in all primary
(surface) drainag e lines fall below the lim-
its set by Guidelines 1, 2 and 4 of Table
STEP 2: Design guidelines and data (surface- 6.3. These are:-
lIIovi ng flows)
a) design flows at terminal gutter inlets
A set of guidelines and associated hydraulic ilrp Ip<;<; th;ln 95 per cent capture approach
information and data must be -adopted for the flow of the preferred inlet AND have flow
management of runoff movi ng in the surface spread less than the adopted limit
channels of minor stormwater drainage systems. (Guidel ine 1)
Listing of these guidelines is required b) design flows at all significant pedestrian
under Design Principle No.1 (Section 10.1 ) . crossings have flow spread less than the
A typical set of guidelines and other related adopted limit (Guideline 2)
information are presented in Section 6.3:
the guidelines playa major role in Phase II c) design flows at all concentrated flow en-
of the design procedure. try poi nts are less than the adopted limit
The Table 6.3 Guidelines and associated (Gu ide 1i ne 4).
data are adopted in the case study examples
of the design procedure (see Chapter 11). Primary drai nage lines which are shown to
conform to this assumed behaviour are called
OUTCOMES OF STEP 2 (see Table 10.1) DETERMINATE drainage lines. Those which fail
one or more of the guidelines or which include
1. Adopt guidelines Table 6 . 3 or ) TABLE 2 significant pedestrian crossings are termed
similar ) INDETERMINATE lines. Testing of the Stage 1
model (Fig. 4A, see Outcomes below) to deter-
2. Reference: Section 6.1 - 6.3 inclusive. mine the classification of each primary drain-
age line is carried out in STEP 4 and present-
ed in Table 4 (see Outcomes below): the tasks
i nvol ved are, for each primary drai nage 1i ne
STEP 3: Design guidelines and data and concentrated flow entry:-
(underground-lIIOying flows)
1) compute design flow (N-years design ARI),
A set of guidelines and associated hydraulic and,
information and data must be adopted for the
management of runoff moving in the under- 2) compare design flow with guideline
ground pipe networks of minor stormwater 1imit(s).
drainage systems. A typical set of guidelines
and other related information are presented Where a drainage line includes one or
in Section 6.5: they playa major role in more concentrated entries, the component flow
Phase III of the design procedure. from each is determined and compared with the
Guideline 4 limit. Guideline 4 violations
The guidelines referred to here are re- lead immediately to change in the Stage 1
quired under Design Principle No.2 (Section network layout (Fi gu re 1B).
Sizes and locations of gutter inlets of to the selection and design of primary drain-
DETERMINATE drainage lines can be declared at age line component s as required by DeSign
this point. Principle No.5 (see Section 10.1).
Those dra i nage 1 i nes found to be I NDE- Flows conveyed by the main pipeline, on
TERMINATE are modified by the addition of the other hand, arise from design storms which
in-path gutter inlets or other means to en- are c ritical in collections of primary drain-
able them to satisfactorily convey and dis- age areas, the aggregate fl ows enteri ng the
charge their design flows without violating mainline at or in the vicinities of its node
Guidelines 1 - 4 inclusive. The process by pits: the catchment area contri buti ng to
which the sizes and locations of additional successive node pits increases with distance
inlets etc. are fixed is graphical and car- down the main drain. Flows determined from
ried out in Fig. 4B (see Outcomes below). these collections of primary drainage areas
Such additions also affect change in the form the basis for the selection and deSign
Stage 1 network layout. of main drain components as required by De-
sign Principle No. 6 (see Section 10.1).
In STEP 5 the modified hydrological model
is presented in its final form, Hydrological To determine these design flows (ARI =
Model - Stage 2. This model is more complex, N-years) requires a set of computations simi-
typically, than its predecessor, contains more lar to those of Table 4 (STEP 4) but reflect-
i nformat i on about the mi nor system d ra i nage ing the collective nature of the contributing
network and has proven ability to satifactor- catchment. Execution of these calculations
ily model design flows (N-years ARI) in all requires the Stage 2 hydrological model to be
primary drainage paths within the constraints interpreted as a system of catchment aggregat-
imposed by Guidelines 1 - 4 (Table 6.3) in- ions (see Fig. 6B, Outcomes below). The flow
clusive. This model forms the basis for all computations are carried out in Table 6 and
subsequent flow estimation computations and the results presented in Fig. 6C (see Out-
is presented in Fig. 5 (see Outcomes below). comes below).
OUTCOMES OF STEPS 4 AND 5 (see Table 10.1) OUTCOMES OF STEP 6 (see Table 10.1)
1. Stage 1 hydrological model FIGURE 4A Primary drainage line flow
l
1.
distributions (design ARI = FIGURE 6A
2. Tabular computation of primary N-yea rs)
drainage line design flows,
~
comparisons, etc. Sizes and TABLE 4 2. Stage 2 hydrological model FIGURE 6B
locations of gutter inlets 'collective' i nterpretat i on
in DETERMINATE drainage Ijnes
drain pipeline design flows ~
3. Tabular computation of main TABLE 6
3. Graphical determination of
gutter inlet positions, etc., FIGURE Main drain pipeline flow
l
4.
in INDETERMINATE drainage 4B distribution (design ARI = FIGURE 6C
1i nes N- years)
4. Stage 2 hydrological model in- 5. Reference: Information transferred from
cluding information on gutter FIGURE the outcomes of STEPS 4 and 5.
inlet locations, types, sizes, 5
concentrated flow entries,etc.
STEP 7: Design flow compilation - all
5. Reference: Chapter 4 and Sections 5.2, components of sub-catc~nt
5.3, 5.5, 5.6, 6.3.
Data and information extracted from Fi gs 6A
and 6C enable the flow distribution compila-
STEP 6: Design flow distribution in pri.ary tion sought in STEP 7 to be determined. The
and .ain drainage lines compilation presents in graphical form the
magnitude of the greater design flow, where
The tasks executed in STEPS 4 and 5 to derive there is choice (Fig. 6A and Fig. 6C values
a valid hydrological model for a given sub- compared), which can occur in each component
catchment lead to design flows being declared surface or underground flow path of a sub-
in all segments of its primary drainage lines. catchment, under design ARI = N-years condit-
These involve both surface and underground ions. The compilation is presented in Fig. 7
flow paths, the latter being introduced as a (see Outcomes below).
consequence of the fai lure of some primary
drainage lines - investigated in STEP 4 as Where the deSign of a mi nor drainage
wholly surface flow conveyors - to meet adop- system for a comp 1ex urban 1andscape of the
ted guideline limits. The primary drainage type illustrated in Fig. 7.4 is required, an
line design flows (ARI = N-years) are present- additional task must be performed. This in-
ed in Figure 6A (see Outcomes below). volves the computation of flows moving under-
ground between sub-catchment di sposal poi nts
Emphasis in the procedure from STEP 3 to towards their (catchment) central disposal
this point is clearly on design flows generat- point (see Design Procedure - Phase II above).
ed in primary drainage lines by design storms The outcomes of these computations are presen-
which are critical in their individual catch- ted in Figs 7A, 7B, etc. (see Outcomes
ment areas. Flows determined in this way lead below).
l
OUTCOMES OF STEP 7 (see Table 10.1) 2. First-round pipe sizes are
selected for all lateral and TABLE 8/9
1. Design flow distribution main drain components
compilation for sub-catchment FIGURE 7
(ARI = N-years) 3. Reference: Sections 6.4 - 6.6 inclusive.
under ground network design ) TA BLE OUTCOMES OF STEP 10 (see Table 10.1)
for s ub-catchment ) 8/ 9
(ARI = N-years) ) l. Schematic representation of )
sub- catchment appro ximate ) FIGURE
2. Junct i on pit outflow pipe ) mi nor storllwater drai nage ) 10
maximum invert levels ) TABLE system for design ARI = N-years)
(appro ximat e network design) ) 8/9
( ARI = N-years) ) 2. Schematic representations of )
parallel sub-catchment approx- ) FIGURES
3. H.G.l. and pipe size s for imate minor system designs ) 10A,10B,
appro ximate underground net - TABLE S (ARI = N-years) including pipes) etc.
work de si gns for other s ub- 8/9A, linking their terminal node )
catchment s (ARI = N-years) 8/9B , pits )
and pipes linking their etc .
terminal node pits 3. Reference: Outcomes of STEPS 5 and 9.
a) gutter and ' sag' inlet pits With these values assigned, the proced-
- locations, types, sizes ure described in STEPS 1 - 10 incluSive, must
be carri ed out for each nomi nated non-ze ro
b) combined inlet/ junction pits value of N commencing with the greatest.
locations, types, sizes, pipe This is less repetitive than it may appear
entries and exits since STEPS 1 - 5 inclusive are common to all
designs for a particular sample area.
c) junction and inspection pit s
- locations, pipe entries and e xits The design resulting from the 'O-year'
case is the hypothetical layout of inlets,
d) concent rated fl ow ent ry poi nt s underground pipes and junction pits which
- 1ocat ions satisfied the minimum requirements of the
guidelines adopted in STEPS 2 and 3. It
e) pipe components (all pipes) realises the Stage 1 hydrological model (Fig.
- locations, types, lengths, 4A). All of its gutter inlets are minimum
diameters size, and all of its pipelines are minimum
size (Guideline 7, Table 6.4); discharges
from all concentrated flow entries are accep-
Where catchments comprl S1 ng a number of ted into thei r respective su rface drai nage
sub-cat chments are involved, then a set of lines.
appro ximate minor system designs must be pre-
pared, one for each sub-catchment. Diameters The result of these determinations is a
for pipes linking sub-catchment terminal node set of approximate minor system designs, each
pits (see STEP 9) form part of the out come of one similar in form to that presented in Fig.
STEP 10. 10. Th is const i tutes the ma in part of the
data base for the analysis.
The design is described as 'appro ximate'
on the grounds that its fi nal f orm cannot be The next tas k involves costing the set
determined until site constraints [see item of designs. The level of sophistication em-
(cl, STEP 1, Section 10.2J, and construction ployed here need not be high but should in-
requi rements have been taken into account. cl ude:-
ARRB SR 34,1986 79
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
a} costs of all drainage network ma in com- It is unusual for the Stage A design to
ponents be directly transferrable to site without
- junction pits alterations being required. These may range
- concentrated flow entries from minor changes - small differences in
- gutter inlets of all types pipe lengths and alignments whi ch have no
- pi pes appreciable effect on the design - to major
redesigns. In the latter case, significant
b} excavation and installation costs a lte rat ions to the network, e. g. rep 1acement
of a number of conventional junction pits
c} roadway reinstatement costs. with 'drop ' pits or alternative pipeline mod-
ifications (see Table 6.6) to avoid existing
The outcome of such an analysis is a set underground services, may force recalculation
of minor system network costs, e.g. of some reaches of the netwo r k. Suc h reca 1-
culation should not extend further back into
design ARI 10-years $177,500 the procedure than Table 8/9 .
design ARI 5-years $171,500
design ARI 2-years $156,000 In extreme circumstances, e.g. where pit
design ARI I-year $151,200 overflow appears to be inescapable, pipe dia-
O-year design $136,500 meter selection and Hydraulic Grade Line com-
putations may have to be repeated using more
These cost/frequency data are plotted in Fig. accurate headloss coefficients and pipe fric-
2.2 (curve I) : they apply to a typical 12 ha tion factors than employed in the procedure.
residential sample area in the Adelaide foot- Reference should be made in these circumstan-
hills, South Australia. ces to appropriate texts on hydraulics (for
pipe friction values) and to the referenced
The cost versus design ARI relationship literature on junction pit headlosses. Con-
can take many forms which differ with the type sideration should also be given to the hyd-
of development, unit cost rates used, adopted raulic modelling of particular installations,
guidelines (STEPS 2 and 3), etc. The 'double e.g. multi-pipe junction pits, whose behav-
cusp' form of curve 1 is typical of resident- iour under design flow conditions is crucial
i al catchments : the conI/ex form illustrated to the success or fail u re of a system (see
by curve 2 is obtained, typically, for indus- Table 6.6).
trial/ commercial developments. The conclus- Much of this need for redesign can be
ion whi ch may be drawn from the curve 1 re- pre-empted if thorough site survey and inves-
lationship is that design ARI = 2 - 4 years tigation is carried out as part of catchment
represents 'best value for $ spent'. rlpfinition [item (c), STEP 1J. The designer
who is aware of the locations of all major
These considerations provide designers servi ces and other underground i nsta 11 at ions
with valuable information which aids policy- wi 11 arrange his bas i c netwo rk 1ayout - Fi g.
making. They are urged, however, to resist 1B to a voi d these, and all subsequent seg-
the temptation to adopt deSign ARI's which ments of the design will reflect this know-
have been decided solely on cost considera- ledge. The alternative is a set of major
tions of the type described here. The reader computational difficulties Lu be overcome in
is referred to Chapter 2 for a wider discuss- STEP 11 or, worse still, following the dis-
ion of this subject. covery of an unexpected service line unearth-
ed by a construction crew.
Stage B: site constrain t s - service locat- 4. Reference: In situations where fi nal de-
ions in particular - are applied sign calls for refinement of the pipe
to the Stage A design to produce a diameter selection procedure and the
set of working or construction H.G.L. , more precise values for pipe fric-
drawings. Some recalculation may tion factor, f, and pit headloss coeffi-
be involved. ci ents must be sought from the literature.
80 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
=~ll:[
[ '"r II
Table Guidel ines Table Guidelines
STEP -- --~ STEP 6.· 3 STEP 64
'~m
Guidelines Table Guidelines Table
1 2 1-5 3 1-1~
2 3
l- I
FIGURE 1A FIGURE 1B TABLE 1
~
STEP
4
, "-
"-
FIGURE 4A
II] TABLE 4
~FIGURE 4B
STEP
5
, "-
"-
FIGURE
St age 2
Hydrological Model
corresponding
sub- compilation
for
STEP STEP other
•
sub-catchments
6 7
I t
FIGURE 6A TABLE 6 FIGURE 6C FIGURE 7
Table 8/9
iii
ii
co lu mns 1-12 T,bl" 12-24
columns /9
STEP commencing
STEP
commencing
8 top of bottom of 9
network network
~ .P ~
~~-
~
STEP
, - " STEP <11
a
W / -
10 "-
10A
"- f/ Frequency
"
FIGURE 10 FIGURE lOA
f-
(Fi nal design Stage Bl
"- ~
" FIGURE 11
INTROOOCTION
The step-by-step procedure for designing Although design of the minor system net-
minor stormwater drainage systems for small work for Case 4 using N = 2-years would,
urhan catchments, rles c ri bed in Chapter 10, is correctly, complement the major system design
applied in Chapter 11 to two hypothetical already prepared, the present illustration
urban developments located in the Adelaide adopts N = 5-years. This level of design ARI
foothills, South Australia. is employed solely to generate a wider range
of design problems forcing solutions which
In the fi rst - Case 3 - a mi nor system demonstrate the scope of the procedure (out-
network is designed for a 6 ha part sub-area lined in Chapter 10) which would not be
catchment of mixed land use. The network revealed by a design at N = 2-years level.
design terminates at a sub-area node pit and
therefore involves no main drain pipeline Both designs - Case 3 and Case 4 - are
considerations. It may be assumed that a intended to fu lfi 1, Pri ma ri ly, a demonst ra-
major system has already been designed for tion role for the novice. This leads, in
the catchment and that, therefore, runoff places, to decisions which may be validly
from storms of AR I = 100-years or 1ess wi 11 questioned by seasoned designers. Discussion
not result in indoor damage. Design ARI used of such poi nts provi des opportuni ty for one
for the minor system is N = 2-years. of the most important benefits likely to flow
The second illustrative design - Case 4 - from the Handbook, the transfer of knowledge,
f ocuses on Catchment, M, a 12 ha portion of skill and experience between the generations
the 38 ha residential sub-division featured in of designers.
Fi g. 7.3. The minor system network for this
catchment includes a branching main drain Each design is presented as a set of
pi peline and four lateral pipelines. A major figures and tables corresponding to those of
system design (ARI = 100-years) is presented Table 10.1 and supported, generally, by add-
for the same catchment in Chapter 9 (Case 1) itional notes. Readers are advised to con-
where a mi nor system desi gn AR I of N = 2-yea rs sult Table 10.1 frequently in their study of
was assumed. This led to a 'gap flow' design the Chapter 11 designs as well as appropriate
ARI of M = 50-years for the surface-moving sections of Chapter 10 when the need tor
system. further explanation arises.
l Residential
(outside catchment)
I f I'l-- . -7m----t------+-t---~
Ch-
Ch. 56 2 m.
Ch. 00 ~ gutter inl et inv. R.l. 111·20
node pit inv. R.l.100 ·10
ADDITIONAL NOTES
1. Ca tchm ent Location , Ad ela ide foothilis, South Australia Isee Fig.5.21 ; Raintall chart Fig.5.1
2. Roads : 20m . roadwa y reserves,10m dual ch anne l carri ageway. kerb .and gutter,
concrete width=375 mm ; Za=8, pavement,hotmix ; cross slope,Zb=40.
hydraulics, Fig.6·3I1ext)
3. Storm wa ter Disposal, XA-4 - XA·3- XA-2-XA-1- X·0 Imainlin el
design flood level at XA- 3, R.L. 99'85
4. Policy Items : adopt design ARI::2 years for minor system
" preferred in let", side entry inlets 1m & 2m wi th and without deflectors
hydraulics, Fig. 6.71 text)
pipes : concr ete pipes throughout; normal condition
CATCHMENT AND BASIC DESIGN DATA
ARRB SR 34,1986 83
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
~I ~I
(from carpark)
11
t
termjnal XA ·3E1R
I
t
gutter inlet R.L.10010
1It------f
L ker b line
lr ~ node
XA-3
RL 100.00 XA-3E1
!2 'Om
CP
~t 70m I 180m
:I
RL.IOO ·)O
-e
~
~I ~I I. 200. .1
NOTE ' Pipe location fixed by Guideline 1, Table 6·4 (major roads)
Z
o DRAINAGE LINE CONVEYING FLOW
5<n
«1 a:: TO TERMINAL INLET
l-
I-
ii: .....
Z ..... I- z: a:: ci
u.J o a::
..... --'
« -a « I - I- -s' ~
E
I
o
Z
I-
Z > . I-
z
a w !;;: I-
ZVl
0- ;: 01 ., .,
~
",-
>- ., :.--'
I-
w « z: --' z: t:l w z: w D 01 '"
~.,
C
~~
'"
c:~ '" 0.. ~r-.,
Z
..... I-
« u.J ~ - 0: u.J
z:
I-
el.
0 ..... -
--' w u.
u.J
a::--, u.a:: C '"
., ., .,-
:. 0
a::
-2~~.,
0-
E a:: a 0«;;; 0« 00
E co'" >-c
:=:.=
w , >
- Vl.,o..E.-'" .-'"~ '"'"'
--
>- E
'"Vl
u.J --'
I
<f- I- u.J el. w a::u. Vl «~ u.JU :.;:.
u _
C
u ., REMARKS
w
I-
,« ,
<n
=>
<n
=>
'"
I-
,.,
Z
I-
=>
>
u.J
E
,a , .....
,.,
Da::«
>-=>--,
u.J=>
" '0
el.z
>-0 o
E
' ,:",
., ., o ~ ~
'"
0
~
"'"0
0.. .-
4 6 7 8 9 10 11 12 13 14 15 16
x A ·3 node 1100·00
pavee
E1 R 1100·10 I road 1 st Qradel 0·49 I 0 680 I 13-5
residentiall15 res/ ha. 1 1·00 I 0 I 200 I 4·0
identification-see note 1 Figure 1A and Section 5·6 see see see note 4 see Figure1A see
note 2 note 3 note 5 note 6
ADDITIONAL NOTES
l.Identification of primary drainage area terminal gutter inlets X A·3E1R and XA3E1L applies code described
in STEP1, Section 10·2 ;'R" and "L"signify dghj or left looking in directi on of flow.
2. Area or equivalent area : measured from catchment pla n, factor of 0·75 used to convert roadway res er ve into
road equ ivalent paved area .
3. Concentrated ," c;'or distributed ,"O '; contribution : all carpark run off co nsidered co ncentrated at drain discharge
point ; factory roo f stormwater fed to dra i nage l i ne from many outl ets, hence "dist r i buted "
4. 0ra inage line total length and fall : drainage line length conveying run off from mos t re mote element of
component; "fall "o f drainage line over thi s l ength .
5. Effect iv e length of dra i nage line, Leff : length over whi ch the bulk of co n t ribution enter s dr ainage line ;
con t ribution from upper 118 m. of road component terminat ing at XA· 3E1R is s ma ll , hence effective length
is 562m-7m=555m.
6. Capac i ty fl ow, Gu i deline 1 (Tab le 6' 3, te xfloap pr oach flow for 95% ca pture (la rgest preferred inle t ) or
2·5m spread , which ever is lesser ( Figure 6-7. t ext)
TABLE 2 TABLE 3 c:
I D
gutter inlets
XA ·3E1R and XA ' 3E1L.
~I XA'3E1L road : 0· 44 ha I
C" concentrated entry.
D" distributed entry.
~70 qf,:75
246 2 h 07 2Ch 207
.... ....
- ....
--
Vl
--'
OJ 200
.... ....
....
.~ 1
-'
OJ
Resid ntial I
0'1
/U
c:
.iii
0 145
1
L I 101 L s concentrated
J from carpark
~ r~
~"
I
c: I
c:
....
.2
/U 100
~ I
I
Roof
:;
~- -85
94-
E OJ
<-
::J
u
u
~
70 I........ i
/U .,,, Kv<,> Park
:.
0
~o~ ..... ~ captu e~. ('oj
u: 45 0
'0 -.D
01
7m
I
I by ass 19 {
100
~ ++-.E Ponlln~
200 300
017
400
-
Chainage (metres)
~~
500
..c:
LJ
600
ADDITIONAL NOTES
1 Flow is considered to accumulate in the drainage line commencing ch 562 ("effective length" 555m l.
Road component flow represents base contribution reaching 45 LIs at ch 07 : other contributions
(e xt ract from Table 4) are added.
2 Carpark (concentrated) flow must be diverted underground requiring kerbs ide junction pit at ch 207.
Surface flow accumulated at ch 207 is 94 LIs which can be 80% captured by 2m gutter inlet
without deflectors (see Fig. 6'7, text . ). Both requirements are served by combined gutter
inlet I J.P. at ch 207.
3 Surface flow at ch 07 is 70 LIs which can be 95 % ( or better) captured by 2 m gutter inlet
without deflectors .
ARRB SR 34,1986 85
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
L
0
0::
LJ
V1
w
IY. LL V1 '+-
0
>-
0::
:::> ---l
0_
0-
<X: '--
0
n:l
..c
CJ1
C
-- QJ
Cl.
0
QJ
E
..,.
--
'
CJ1
c - E
.~
I QJ -+- I QJ
-
CJ1
c -
I
E
-+-
-
CJ1 I
c - E tc
QJ
ti
LJ
1 2 3
V1 Vl ll..I
4
LJ
5
0 :r: V1 L.J
6
min. - VI -+-
7
QJ .
- QJ fU ·
'+- -+-
-
- QJ
8 9 10 11 12 13 14 15 16 17 18 19 20
'+-
--
n:l .- QJ n:l .-
- '+- -+- min. min.
21
pav ea sec -
x A .3 EIR ca I"park olld arade - 70 .03 5 200 1.' 4 - - - 200 4 3 12 12
10 m road pa ved - 8 .02 2 - - - 673 13l 6 - - - 8 9
first arade
residential 15 res/ha 5 nomi al 15 - - - 200 4 3 - - - 18 8
factory roof Raved
fi rs t grade 10 - - - - - - 400 8 4 - - - 14 14
pa rk pervious - 140 .0 35 - - - 450 9 5 - - - 40 14 ~
CRITICAL STORM DURATION 40 147
ElL 10 m road ~l~~1 orade - 8 .0, 2 - - - 563 11 5 - - - 7 7
Identification see Note 1 Data from Figure 1A, Table 1, and see Note 3
ex. columns Section 5'5, text;see Note 2
1-4, Table 1
:3 ~ DETERMINATE
analysis analys is rn
r---~----~--~--~~ .
o::--D Ii nes included
<x: OJ
Ln for Ln for 0.. - here)
E~
N=2years N=2years Ot-
u-
~------~------~ ~------~-------~-----'r---~
CD
der ived from column c ~ see Note 4 see Notes 5 - 7 co see Note 9
E~LJ-+-
20&21andSection ~OJOJx OJ
~
5'2 text 8::OVl~ z
. roL.. _ OJ
x~OJ--D OJ
OJ ~th Vl
L..
6. Concentrated flow entri es to the surface drainage line which violate Guideline 4, Tabl e 6.3, text,
are excluded from surface drainage considerations. Note that on ly surface drainage contributing
areas and flows are i nc1urlerl in 'totals' shown in columns 26/27 and 29/30 respectively .
7. Full li st of component surface flows are needed only in cases where drainage lines prove to be
INDETERI-1INATE.
8. Comparison with guideline limits: values li sted in column 31 come fro m two sources:
o Guidel ine 4 limit, applied to concentrated flow entries
o column 15, Table 1, app li ed to total surface drainage flows
Comparison is between the adopted design flow (larger of co lumns 29 and 30) and appropriate
guideline limit. The outcome decides the issues of acceptance into the surface drainage line
or not in the case of concentrated flow entries and DETERMINANCY in other surface drainage
lines. . .
9. Remarks column is used for any relevant comment, in particular, those relating to the consequences
of the column 31 comparisons. In drainage lines which prove to be DETERMINATE, it i s possible
to immediately fix the type and size of required gutter inlet. This can be done by applying the
design flow together with data from column 13, Table 1, to Fig. 6.7, text. The result may be
shown in column 32 , 'Remarks' (see corresponding column in Case 4) .
ARRB SR 34,1986 87
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
! 1
I
t7\ 70 75
\../ ~y pa ss\.. ,/
road :0·49ha.; factory 19
roof:0'64 ha.; re sidential: 70 176
XA3E1 If' flows : Li s
lOO ha.; park : 1-50 ha. XA· 3
XA ·3 ....-It--.,....--. .I;.:.P;..
. _ _..... 287 176 XA3E 2 176 XA· 3E3
XA3E1 XA3E2 XA·3E3
I 55
NOTE :
Fl ows presented in th is figure
same as those shown in Fig. 6A.
3. tab l e 6'4. text . FIGURE 7: DESI GN FLOW - ALL COMPONENTS; N=2 YEAR S
<i.
x
* E'"
Nt"--
(T'\
t1 7m 100m 100m
XA .3 E52~5.-~:;:::-"'-~~- XA.3E3
t
17\ 70 XA·3E3R 75 375 375
IP
\....J ';tpa s~ ,.J
70 19 176 Notes :
tlows : Li s E
XA ·3E1. I.P. "' C>
u
XA·.:l (T'\
1. All pipes concrete .
e
287 176 XA:'3E2 176 XA·3E3
2. 2m side - entry gutter inlet wi thout
NOTE : Strict. adherence to t he Rat ional
deflectors shown or @
I {\
55
55
Methodl see Chapter 4} requ ires that
de si gn fl ows tra m inlet XA·3E3R be
based on trave l time t o that point.
The procedu re di sregards such
considerations within primary drainage
3. Pipe diameters for cross- connec tions
found from Guide line 10, Table 6.4 ,
text ; for design flows see Figure 7.
4. Headloss, pi t water levels and
pit f loor level s for pipe marked *
areas . Rational Method the ory is
\.V applied in pipes which carry combined
require further inves t igalion .
See Guideline 10 , Table 6.4 , text .
flows to a node pit.
Hence-critical storm charac t er is tics at XA '3E1 :- FIGURE 10' APPROXIMATE NETWORK DESIGN N= 2 YEARS
northern area : duration 14 mins, L2 = 43 mm / h.
southern area : duration 7 min s, L2 = 58 mm / h.
tlow in pipe XA' 3E1- XA·3 : 170+176} Lis + ~~ x55L / s = 287L/ s CASE 3 : STEP 11, FIGURE 11
FIGURE 6A :DE SIGN FLOWS IPRIMARY DRAIN LI NE S} N= 2 YEARS XA .3E1R
pi t f loor level
RL. 99·20 XA .3E3R
2 pi t f loor lev el
R.L. 102.92
~
X A .3E2 >
I ~
XA.3E1L
pit f loor level
Not es :
1. Pipe inverts at pi ts
I
R L. 99 20 coincide with pit f loor
levels .
FIG URE 68 TABLE 6 FIGURE 6C
2. Pi t floor levels fixe d by
Gu idelines 11 - 13 and
Remarks column , Table 8/9.
3. Pipe class - Guideline 13
FIGURE 11 ' APPROX IMATE NETW OR K - PI T FLOO R
LEVEL S AND PIPE CLASS ES
~~~
z
V1
-"
«
G'LlNE G' LlNE ASS' NO
DIAM. dl~
~
.. CASE Kw VJ
2g
? -'" hf+K W
[*] minus
BWl
hf + 1'50 0 «
0
HYDRAULIC
GRAD E
AW L " ASSIGNED I PIT) WATER LEVEL
>- i5
;:s
>: 3 «
:3
ex:
z >- ex: ~~
w>-
~ E
Z
0
4 5 WATER
lEVEL >-' ~I
000 ->
NO
N
"'" ""
0
~
Q.
LINE BWl" BOTTOM IPITI WATER l EVEL
i5
, ,
0::>
El:)~
z"O
1r5
-"
3
:t:
>-
:::l
'::: IAWLI
>-
W
'"J!". - IAWL- BWLJ IAWL - BWLI 0
0
«
~>
:>
CD 3
<D
::>
<D
::>
~~~
>:V1
OW
~ '"~ '"5
z Table
6'4
Table
6-4 RL m
Tables
6·5 & 6·6 m ""
m
Eq6'17
m m
Eq. 6·18
m m IPit W.L:s I
(Xl V1 Vl ~o
m
O'l 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
LATERAL PIPELINES (j)
X A ·3 "l" junco --i
E3
104'10 pit 103 ' 95 n.a. 103-95 RL10H5 o:::IJ
- TEST 1 O.K. for Do " 0.3 75 , fails TEST 2
s:
li }
pipe J-3 2·0 0·64
~
~ first round - 0·300 2·49 0 32 2·03 2-67 Pipe invert (upstream) fi xed by eq uation 6. 21:-
E3 to 176 100 0·02 0· 375 1·59 0·13 0·65 0·26 0·91 2 00 1· 21 0·375 max . inv. leve l. E3 "Rl 103 . 95 -{ 1.5 x . 26) - 0. 375
E2 • RL 103.18 o
water level, E3 . f ix ed at AWl. :::IJ
E2 Insp. ~
102 ·10 pi t 101 '95 103-85 101·95 R.L 101 ·95
Z
-
li }
TEST 1 O.K . (fo r Do • 0.3751, fails TEST 1
~
pipe ~ first round - 0·300 2-49 J -1 0·2 0·32 2'03 0·06 2-09
1·59 0·13 0· 66 0·03 0·69 2·01 1· 22 0·375 Pipe invert (upstream) fixed by equ ation 6.21:- ~
E2 to 176 100 0·02 0· 375
E1
max . ;nv . level , E2 = RL 101.95-(1.5 x . 03) - 0.375
• RL 101.53 I Gl
m
r
water level , E2 , fi xed at AWL.
E1 J.R with
o
100 ·10
{>
late ra ls
pi pe
El to
node
287 7 0·02 --T
99 ' 95 101-85
first
99 ·95
nd
~ 0·375
0· 450
0·525
2-60
1· 81
1'32
J-
2A/2B
0·8 0·34
0·17
0·09
0·12
0·05
0·02
0·27
0·1 4
0·07
0·39
0·19
0·09
0·10
-
-
0'81 0'525
R.L. 99 '94
li }
TESTS 1 and 1 O. K. for DQ • 0.515
Pipe invert (ups tream) f1Xed by equation 6.19:-
max. inv . level, El = RL 99.85 + 0.02 - 0.525
• Rl 99 .34
m
(j)
Gl
Z
.
water level, El, fixed by equation 6 .20 :-
II
node
100·00
mul t i -pipe
J.p. DES1IG N Ft OD ILEV EL 1
R 99 '85' B.t
I I I I I I
R.L. 9985
aWL at El • RL 99.85 + 0.09 • RL 99 .94
Z
(j)
MAIN DRAI N PIPELINES s:
~
(Xl
CD
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
M .3=r~
(node pit) I
/ II-
r
I
I
-
road , 0·18 ha,
I I
So = 0·03
",0 I '"
110
~
,.,
:1~
10m dual channel "'I ~ .. : .. ~ I~ .. I is 0 7.5 m single channel carriage .... ay
carr iage .... ay in ~'I :;; ~
I ~ '" I :;; ~ I~ ~ in 16m road .... ay reserve
20m road reserve .
Pavement cross
~ I ;;:-
·· 1 ~ 'E
1 .~ ~ 1~ :: I~ ~ 1 16m . I
slope Zb = 40
_
]:
•
oJ
i
road , 0 ' 16h a
1: ~ f ~
ro.irQ.l~6;:-:h.,--~~
II //~
cross slope Zb = 30
M '2 ~ 1 So=0·03 M. 5 I So= 0' 02
I
LEGEND
(node pit) I 1 node pIt)
1 I I sub-area boundaries
I :;; ;' % I sho .... n - - - - -
primary drainage area
I ~o i~ II ;, ~ I ~ boundaries shown - - - - --
%1 Vl 6 ~ I ~
~ '~ ~~ / ~ 6 I 0 terminal gutter inlets
~ "'J ~ / ~~ I ~ shown .. : 0
~ ~I / .. ~ ~ I - h
I :;;I ~ / ~ ~ ~ .~ I '~ 7·5m dual cannel carriage .... ay
l!) '1 ~ / 0.6 J in 16m roadway reserve
:c ~~I i'-' / / ro.d , 024 h. I 0 08h. , I I 16 m
i7:sm1 I
r-
'l ~
r"":;
ro.d
N
M·3N1R
M·3E1
E
C>
~
Iii
.....
c
Inspection Pit OJ
"0
(see Guideline 3, Table 6·4 text) VI
OJ
r"
UJ ."0 "0<-
r
:?:
E
~ 15m ~
-'
~\\..
"'
.!: ~
..... <- <- c
~.1: c
~~\ ~ ..... OJ
OJ ~ ~. OJ >- E
M· 2N1R 13m g.3 M' SN1R 0 < - .....
c ..... 0
0 ..... 12m 0 c :::
4Sm 0 40m u OJ '"
---- -----
::.::
7m
M'2E1L
M·2E2
:z:
UJ
:?:
Sm M'S~ E
E
C> :z:
::>
<i: -' C>
~ et:
et: UJ
a.. ~
0
l- ii:
1. P. I.P.
I
(J "0
-r~ r~
:z: E
E <i: et: '" .....
<- C
V"I
~
V"I L Il) 1:: QJ
~
M·4N1, M' 4E1 ~~
100m Sm 40m 8 .....
-----
M·4 7m
Sm M·4E1L lM .4E2
E
C>
~
NOTE : Pipe location fixed by
Guidel ine 1, Table 6·4 (text)
1.p.
major and minor roads
E
C>
C> Drawing not to scale
.
0 I- Z I- zV> ~
> w
E
Z Z I- ~ -<::J < I-
8 0
.s::;
'"
c:
C:c >-ai ~ --'
.. .. . .. - .. . - ·w
~ '"
l- I ~
!'" > .. V> -
Z
zW w
< 0 ..J
c:r
z
W
I-
ow -
w
o::W
0>
c '"
..
~
0-
0
~
.-
:= REMARKS
- ..
W V> do:: E
I- en en l- I-
> l:
0 W
<
>-::J --'
w ::J Cl.Z O-E
o ~ ~
~ 0 a..~
< ::J ::J Z ::J W 0::0 o -
>-0 1---' ~ ::>
w V> V> W <::J --' w 0 IV> w <w I- w u.. V>_ w u W <::J
W --'
1 2 3 4 5 6 7 6 9 10 11 12 13 14 15 16
M 5 node 110·30
N1R 11065 7Sm road ls~a~~~de 0·12 D 200 4·5 200 ·03 30 65
pa vee
Nl 110·65 7·5m rOJd h I. Yld U ~ 0·19 D 290 50
}180 ·03 30 65
resi dential 20res / ha 066 D 160 4·0
E1 110·40 7·5m road ls r.ave_a"
qrade 012 D 90 2·0 see mi n i mu m trave I ti me
} 90 ·02 30 76
residential 20 res/ ha. 0·60 C 40 1-0 provisio n, sec tion 5'5, ltext }
M ·4 node 103·00
Nl 103·15 7·5m road 1 s~a~~~de 0·13 D 200 7-0
~ 185 ·03 30 65
residential 20 res/ha 0 89 D 165 6·0
pavee,
El 10303 7·5m road 1 st grade 006 D 90 OS
residential 20 res / ha. 060 C 40 0·2
~ 90 ·005 30 75 min imum travel time Iroad}
Ell 103'03 7·5m road lsa~~~e 0·06 D 90 OS 90 ·005 30 75 minimum travel time
M ·3 node 11420
N1R 114·25 10m road 1 s~a;~~e 0·07 D 70 07 70 ·01 40 70 minimum travel time
Nll 114·25 10m road lsa;~a~e 0·25 D 310 60
park
pervious 0·38 D 0
~ 60 01 40 70
pavee.
114·40 7-5m road 1 st. 0·14 4·0
El D 250
grade
park pe rvio us 1-26 D 0
~ 250 ·03 30 65
M ·2 node l OBO
pavee
N1R 107·80 10m road 1st. grade 0'15 D 200 55 200 ·04 40 65
pavee, 0·21 8·0
Nll 107-60 10 m road 1sl. gra de D 260
f.,id ~ "lid l 20 1l:!:.l lld. 0·77 D 180 5'5
~ 160 ·04 40 65
M 1 node 102·20
N1R 102-30 10m road ls~a;~~de 0'15 D 200 4S 200 ·02 40 76
Nll 102'30 10m road 1 S~agVr~~e 0'15 D 200 45
par k pervious 0·84 D 0
~ 200 ·02 40 76
TABLE 2 TABLE 3
~~.
C MSN1 C OJ
M·2E1 4Sm. M2E2 M'SE1 40 m • c::
M·5 . - - - - { - - - - - - -, M·5E2
I.P.
IRoad Reserve : 0·06 ha.1 o IRoad Reserve
1'1 ·0 I 0 06 ha
FIGURE 4A : STAGE 1 HYDROLOGICAL MODEL
I I t
~-5~1~ .
Q 31I 100 .
90 93
flows which can be 80% captured in drainage
lines having 50 =0'03 &0 '04,re spectively, in their
::s
120
1--
,- .'27 m
110r-tj:~ I;::!z
~I
u-II
.IOJ
c
:.: :;
VI
'-
.~
u::
Ff-'
80
70
i"""'- ::;::85 Lis
I ........
6O!
68 Li s
..... ~
.....
I
terminal inlet vicinities(see column 13,Table 1)
2.The flow accumulation graphs for lines terminating
at M·5N1 & M·2N1L are plotted together becau se
I
'-......(
the ir effective drainage line lengths are , by
co inc idence ,both equal to 180m (see
~ 100ts::::1;:- 96i: I± SOIl I, I " ............column 12, Tab le 1)
OJ 9O~L..... I .- 40 M·4N1 Line
en ........ N...-85L/s I
(So=0 ' 03)l r---.....
~ 80 ~~ -7QLAr30~~~~-t-r~~'r- I t-II-t-t-j~~........~-
.~
'C 70 ~ I.~
I1"":::::::-- I 25
-....:::::~fttSl--'-k~+I-
""
. -r-+--+y=p-:':-: asc::-
s-\erl..,..,L-'-:
./C'!S +-+-+-+--t--t--P-..I-
I .....
-t- I
............ I I
.; 60r-r- '~ I~ - -ftt<, 4'7 (.s,-,,"+--+--
I I--I--I--I--I--I--I--t--I--I--I--I--~'t-....
f---11f---1!
~ 50 ~I u 4'7.: 0'0 .,--+-~-+--t--i'--+-~-+----'.-'---'--~--'----'-
I ~--""~
:; ~ ~ ([0""0 '.J 50 100 150 185
~ 40~~2 ~II~ .I I 'O~) ~
~
.3;i
~
30 ."
20
10 '
M·5N1 & M· 2N1L Line
17,L/s~.- bypass 16L / s
I
3. Gutter inlet selections/placements '
shown here are not necessarily " best
~ solutions ",man y sat isfactory
""'~
.....
Dra i nage l ine length (m)
ARRB SR 34,1986 93
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
--ro
1
1
Q)
E
- --
-'=
0\
c
1
I
Q)
-'=
-+-
0\
c --ro
I
1
Q)
E tc t ·I
- - ro .-E
--l 0
.-
LJ Vl l/) W LJ 0 I Vl LJ
min.
Q)
Vl -+-
-Q)
'+-
.-
-+- -Q)
'+- -+- -Q)
'+-
.-
-+-
min. min.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Raved -
M .5 NIR 7 . 5 m road first Qrade - - - -- - 2 200 4. 3 - - 5 5
NI 7.5 In road ditto - 2 - - -- - 290 5 4 - - - 6 6
. _----- f - - - - - - - - - - - -- - - 1- -_ . -- -- - ---- - .- -_.
res i dent i a 1 20 res/ha 5 i5 mi 5 - - - 180 4 2 - - - 17 7
~
residential 20 re s/ ha 5 15 mi s - - - 185 6 2 - - - 17 7
CRITICAL S TOR~l DURATION- 17 7
pavea
El 7 . 5111 road first grade ------ -- -- -- --- -- 5 , -mi s - - --- -- --- ---- -- --- f-,-
5 5
- f- - I- I - --
r es identia l 20 r es/ ha 5 15 l1li s 185 7 2 - - - 40 .2 1 18 8
n~ve?
Ell 7 .5 m r oad f irs t grade ------ ----- -- --- -- 5 l1l i s - --- - -- -- - ---- -- -- - 5 5
NIR 10 m road
7.5 m road
park
raved
i rst~~ _
perv i ous
paved
-
-
-
110
-
2~· 32
2 -
-
-
-+ -
250
-
CRITI CAL STORMDURATION
4
-
4
-
-
-
~
-
-
-
-
-
6
32
32
6
6~
6- J
Ell 7.5 m road ff~~~ Qrade --- --- ---- - -- -- - -- : mir s +---+----+---+-- -- 5 5
94 ARRB SR 34,1986
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
0::
Vl
3 _ DETERMINATE
analysis analysis <t:
u...
0
".,
UJ .
UJ
0::'-0 lines included
Ln for Ln for n... Qn for Q n for <t:
n... -
(lJ
29 30
Residentia I
0·80 ha.
LP 68
60
~62 1
21 21
62 60
Pi t
All flows Li s
I. P
derived from Table 4
62
1
81 62
I. P
62+(gx 22) = 81
76
see note re combined flows in
.
M·4
]
J 11
The Case 4 network involves an extensive Table 6 relates to Fig. 6B in the same way
system of main and lateral pipelines. Its Table 4 relates to Fig. 4A and includes many
des i gn mus t therefore cons i der 'tota 1 catch- items transferred di rectly from the earlier
ment' aspects of flow estimation which were tabulation. With the aid of Table 6, the
avoided in designing the Case 3 network al- designer is able to execute the required
ready reviewed. These aspects find express- sub-area gathering and storm duration com-
ion in Fig. 6B, Table 6 and Fig. 6C of STEP parison processes, and consequently determine
6. design flows in each segment of the main
pipeline network. The origins of the follow-
ing notes are found in Table 6.
FIGURE 68
The interpretation of the Stage 2 Hydrologi- 1. The 'from upstream' component entered
cal Model presented in Fig. 6B shows, schema- under node pit M.4 is that cont ri buted
tically, how catchment sub-areas are gathered from its adjacent (u pstream) sub-area,
at successive node pits - commencing at the M.5. Thus, the value for (CA)s= 1.07 ha
most remote - to provide the hydrological entered in columns 28 and 29 has been
basis for flow estimation in successive rea- transferred directly from columns 30 and
ches of main drainage pipelines. Where main- 31 respectively.
1 i nes are branche d, as inCase 4, then the
two (or more) branches must be considered
separately down to their point of bifurcation. 2. Critical storm durations shown at node
pit M. 5 are:
The design flow conveyed from such a
junction must be determined for the total tc 19 mins and ti = 9 mins
catchment co ntributing to that point. Appli- (columns 22 and 23)
cation of the Two-Value Rational Method (see
Chapter 4) to determine this flow requires Because travel time between M.5 and
that critical storm durations in the contrib - M.4 is 2 minutes (see Fig. 6B), travel
uting branches be evaluated and compared. times for sub-area M.5 relative to node
Node-to-node travel times are shown in Fig. pit M.4 are 21 mi nutes and 11 mi nutes
6B to enable these durations to be determined. respectively (columns 20 and 21).
N I I
11'------' ~
'----------I] kf I
I
t7
6l(f
I
()+ I r('
M2E1 L - - - - i J' M5E1
~.~:--------{ 45 m ~ ___-{ 40 m.
~~ .~ ~
2 E2
.1'2 ____ M2E Ll=====M=5=::::::J
1(N) catchment.1 L J ';;; r - 5-
.~ "DO' ~ "c; ~ r-
'-----Ii ~ .,"'~f=-r--'
-----,1 ~I \
; , 0: U/)'~r-------'--------' ~1 ~ 1(E) "\ r-
"?'7(NJ- M'L- ~rY tra ve l ti me 3 mlns
node to node
-
1 ~
I
2; I J.
catchment M·4
\~
}-_4:..;:.O..::.m:.:...
. ---JM .4E2
trave I 2 mi ns.
~
....;==~'s;+....4~.~1~(El)::::::::~;;JtiT"""""f;i:fi'"HMFN"'f"":=='
... TOTAL CATCHMENT
~===:::!.-=======~
FIGURE 6B : "SUB-AREA GATHERING " SCHEMATIC HYDR OLOGIC AL MODEL
ARRB SR 34,1986 97
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
b-+-1--1 ~~d
7.5 m road ~m~ qrade Table 6 5 5
N2 res i de nt i a 1 20 res/ ha 17 .7
El 7. 5 m roa d ~m~ or ad e 5 5
El r es i de ntia l 20 r es/ ha 19 9
El L 7 . 5 m road ~m~ grade 5 5
21 11
M .1 from up£tream 24 14
El 7. 5mroad ~1~~~ orade
ElL 7.5 m road ditto
El park pervious 40 14
40 14 J
BRANCH Ml + M. O
Contributio n from branch M.5 + ~L4 + M.l at M. l 40 14
Contribution from bra nch M.3 + f1.2 + M.l a t M.l 40 11
40 14
M .0 from ups tream 42 16
NIL
42 16
--
45 63 1.07 1.07 134 187 desig n f l ow at M.5
1. 07 1. 07 Isee Note N'· j I ( 172)
0 .11 0. 11 I Table 6 I input to M.5/M.4 :
0 . 49 x 58 ; 79 LI
0 . 38 0.38 see Note N°· 4 ."..,...- 0.36 s
0 . 05 0 . 05 Table 6
0 . 34 0 . 34 see Note Nq 5 ~ i nput at M.4 ; 71 Lis
0 . 05 0 . 05 Table 6
42 58 2 . 00 2.00 233 322 desig n f l ow at M.4
2 . 00 2 . 00 (288)
0.13 0 . 13
0.05 0.05 in put at M. 1E1 ; 30 Lis
0 . 07 ~ x .0
29 52 2 .25 2.20 181 318 design flow to M.1
0 . 06 0 . 06
0.2 1 0.2 1
0. 12 0. 12
0. 04 b'2- x .04
0 .1 3 !b- x .1
33 68 0.56 0 .4 3 51 81 des ign flow at M. 3
0 .5 6 0 . 43 (7 5)
0 .1 3
0. 18
0.33
0. 13
0 .18
0 . 33
-
r input at M. 2 ; 23 Lis
nput to M. 3/ M. 2 :
0 . 51 x 63 - 89 LI
0 . 36 - s
0 .1 0 0 . 10
' ~i nput at M. 2 ; 77 Lis
0 . 34 0 . 34
32 63 1. 64 1. 51 146 264 des i gn flow at M. 2
1.64 1. 51 (2 43)
0.13 0 .13 input at M.1 ; 21 Lis
0. 13 0 .1 3
}i nput at 14.1 ; 24 Lis
0 . 08 ~x . 08
29 58 1.98 1. 79 160 288 design flow to M. I
2 . 25 2 . 20
1. 98 1. 79
29 52 4 . 23 3 . 99 34 1 576 desig n flow from fl. 1
4 . 23 3 . 99 (543 )
0 0
28 49 4. 23 3.99 329 543 desig n flow at M.O
INLET ~ 0 INLET
M4N1 \l} \.1J M·4N2 NOTES :
1. All flo\ols derived from Table 6
2. Flo\ol accumulation relationsh ips
superimposed on Figure 49
INLET INLET
M·2N1 L M·2N2L
@ @ 60
32m flo\ol accumulation in drainage line
~ VI
"- terminating at M·4N1 (So = 0·03)
:::: 100 -'
'"
c
~I~
ClI o "
en
to
c
""
20 -14/
~ ClI
'"c -......,J-7 L1s (bypass)
~~
60
:. 00 20 40 60 80 100 120 140
....
.9
40 ~ I~ Dra inage line le ngt h (m)
o ""
'"
2!
to
::>
27 ~I " f lo \ol acc umulati on in drainage l i ne
E
::>
u
u
20 ............
'-.J- 11 Lis (byp ass)
r terminat ing at M·2N1 L (So =0·04 )
«
00 20 40 60 80 100 120 140 160 180
Drainage line length from term inal inlet (m)
'To tal catc hm ent ' flo w acc umu lation in drai nage lines M·S/ M·4 & M ·3/ M ·2
CA SE 4 : STEP 6, FIGURE 6C
DRAINAIGE NETWORK COMPONENTS
Main dra in pipeline .. .. . ........ ~
Cross-c onnections .. . .. ......... W
Conc entrated flow entry .. . ,
LP. M·2N3
Junction pit .. •
(75) 62
Al l flows LIs
derived f rom TAB LE 6
1
BO M'2 E1 62 M·2E2 M'SE2
264
All flows Lis
M·1N2 Inspection derived from
pit Figures 6A and 6C
243
M·1N1R M·1N1L
~ M·4E1
N
1
322 M·4 81 62 M·4E2
FIGURE 7 : DESIGN FLOWS IN ALL 1
PIPE COMPONENTS OF M·4E1L
M'O CASE 4-N=5 YEARS
543
P IT
0
WATER LEVEL 0
l-
lLJ a::
lLJ
~
E
- en
TE S T 1 TE ST 2
a::
V)
'-'
~$
D :..J a.. a:: I- lLJ -
a.. 0
hf+KW[~Jg]
0 -'
ci w lLJ
Kw \,20 hf +1 5 0 0 I-
~
Z -' lLJ ::::>
l- L: > -'
I- w <! Vl - ~
3 L: <!
z D I-
a::
<!-
3-, -<! a lLJ -
Vl-D 2g 0 en «
-
a:: REM ARKS (j)
~-
w 0 I-
lLJ
-' D « -0 D w -l
L: Z z ~ 3 " ~ 0
>-- -z
a.. > I-
«
z
LI1
w .y LJ
~ 0\ ~ V)
AWL=assi gned (p it) wa te r leve l o
I- I Z
- Z
0
- V)
E -D - - D<!
lLJ ~ a.. ::J I -' :D
~
LJ <! Z w w - LJ"I r- D
Z
lLJ I -
W W I- "- ~
Z
~
Z 0.. >--- Vl .--<
C
w BWL= boHom (pit) water level s:
<! a::
L: LJ <!
0
-
I-
a:: z 0..
-
-'
I
::::>
I-
-Z
-'
-0 -
-'
-0 L:J - '
- w -'
I-
-
Vl
0
-0
v,
a
~o
AWL- BWU E (AWL - BWU I- cd W
0 o
I
lLJ 0 a:: l- - w w LJ -' a > 0..
-'
D ~
Vl > <! -' <!
LJ
I
en en z
I LJ I-
I-
0..
L:
LJ
Vl
3 L:J L:J D ~
- .D - .D Vl lLJ -
a::
0
-'
OJ
- ' II
'+-
~
:J
Eq .6· 17
3
Eq . 6·18 0
D 3 a::
:D
~
I- 0 Z Z <! --l I - .D en L:J
<! ::::> ::::> ::::> ::::> 0 lLJ
-' lLJ 0 ::::> ro ::::> ro I- lLJ - It> .c ::.::: <! <!
-. L:J I - Z
LJ Vl Vl L:J '-' D lL -' -' L:J I -
- ~
RL m
> 0.. I -
- m m m m m m mm (Pit Wl:s) ~
G)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 m
lATERAL PIPELINES
o
m
(j)
M . 5 111. 35 [pit --
l junctio n 111. 7.0 n.a. 111 .20 111.20 TEST 1 OK for 00 - 300; fails
TEST 2; u/s inv . max . Rl 110.79 G)
plpe
E2 ., E1 60 40 .024 .300 .35 J -3 2.0 .04 . 08 .07 0.15 0.97 0.5 3
100 t b( egn ~8'P) m~t· BWl at E2,
R..111'-- _ = AWL
Z
JP with TESTS 1 and 2 OK for Do = 300 ; Z
~: 5:40 au tter flOl' 110 .25 111.10 11 0.25 11 0.23
upstream inv. max. Rl 109.87 (f)
~lpe .306 11. 09
~A/ 2B
. VO . Vi .Vb v.08 0.47 s:~
-
1 -+ j.j, 5 77 5 .020 i.O 0. 10 300 by eqn (6. 19 ) ; max. BHl at E1,
Rl 110.23 by eqn (6 . 20 )
'iVFJ.£b·· l ~iiunct1on B·.il r
•
IT N:
JP with
111.30 [qutter fl o~
110 . 15
111. 15
110 . 15 110.15
n.a . 111.1 5
FROr~ MA IN PIPELIN E (BRANCH) COMPUTATIONS 110 . 15
111.1 5 TEST 1 OK for Do - 300; fails
TEST 2; u/s inv. max. Rl 110.5E
r
C
:D
oipe bl' eq n (6·P) A m~x . BWl at N2 ,
~1
IN~ -> in
JP, gutter
68 27 . 024 .300 .96 1- 1 4.0 05 .07 .1 9 0.26 0.68 0.52
30n t Rill 15 = Wl
III
~
11 0.65 flow lat' 11 0.50 111. 05 110.50 110 . 47 TESTS 1 and 2 OK for Do = 300; Z
oipe .300 1.68 0.32 300
upstream i nv. max. Rl 109.95 o
t~ i -> r,1. 5 119 12 . 029 1B/3C 1. 5 .14 .lD .22 0.35 0.55 by eqn (6.19); max. B,il at N1, ~
-l
rWDE n. 5I~iiunction prev~g~aly__ 11 0. 15 Rl 110.47 by eqn (6.20)
110 .30 ISS ' 110 .40 110 .1 5 Bi·; l FROn ~1AIN PIPELINE (BRANCH) COMPUTATIONS 110.1 5 o
-2 TEST 1 OK for Do = 300; fails I
L ~unctio n
M .4 10j.25 [oi 103.10 n.a. 103 . 10 103.10 TEST 2; u/s inv. max Rl 102. 68 s:
~lpe
2 -, E1 62 40 .006 . 300 .88 J - 3 2.0 ,U4 .U'J .UB 0.17 0.58 U.04
300 _t _bl' egn (6'P)A m~ x . BWl at E2,
R 1 3.1 0 = Wl
m
z
-l
E1 JP , gu t ter 102 .88 103.00 102.88 102.52 TESTS 1 and 2 OK for Do = 300;
~
I.. 103 .03 f l ow l at'
u.uo upstream i nv . max. Rl 102 . 19
(f)
:D
Ol pe 81 5 .006 . JUU 11.10 I - 3A 0.5 ,VI .Ui . UJ 0.41 U.41
by eqn (6.19); ma x. BHl at El,
~1 -> M.4 300
:D Rl 102 . 52 by eq n (6 . 20)
III NODE 1U t hro ' pi~e 102.85 102 .78 102.78 BWl FRor,1 r1A I N PIPELINe: (BRANCH) Cor·IPUTATIONS 102.47
103 . 00 with 1at s
(j)
:D M "2
. 2 108 .40 [pi
l ~ u nction 108.25 n.a. 108 . 25 108 . 25 TEST 1 OK for Do = 300' fai l s
TEST 2; u/s inv . max. Rl 107. 8
w
•.po cE~pe-> -c 1
62 45 .020 . 300 .88 J-3 2.0 . U4 .10 .UB U.H1 1.00 U.~~
300 t ~y iR2'~~ ' 7 ~ )Aw~~x. BWl at E2,
...... El JP with
<D
CO ~ 107 . 50 :qutter f l ow
107 . 35 108.15 107 . 35
. 30U 1.13
107.25 TESTS 1 and 2 OK for Do = 300;
upstream i nv. max. Rl 106. 88
~A/2B 1.0 . UI .UJ .UI U. 1U 0. 2e U. 4tl
OJ
\OgFJij
~ l pe
2 JP
1 -> ~1. 2
multi -pi pe
80 7 .029
107 . 15 107.25 107.15 BHl FROrl: 1,1AW °1 PELIN E (TRUNK) COl1PUTATIONS
300
.. 107.15
by eqn (6 . 19); max . BWl at E1,
Rl 107.25 by eqn (6.20)
» MAIN PIPE LI NE : BRANCH M.5-M.4-M.1
:D
:D
M .4 N.UPE M.: t~ro ' pi ~e ~revioualY TEST 1 OK for Do = 300; fails
CD 110.30 with 1at s sS l gne 110.15 110 .15 TEST 2; u/s inv. max Rl 109.31
(f)
I ~~~e.. N3
187 100 .036 .300 2.64 J-2B 1. 0 . 36 2.02 .36 2.38 3.60 2. 47 egn:i6,p)Awr~x,
b{ 110 BWl at M.4
:D 1nn R 5 -
w N3 j~ro' pi pe 106.55 110.05 106.55 106.55 lEST 1 OK for Do = 300; fai l s
-~ 106 :70 TEST 2; u/s inv. max Rl 106 . 16
~1P! N2 . 300 2.43 J -1 0. 2 . 30 1.42 .06 1.48 1. 87 ~( i32:~~ ' n) Awr~x , Bl~l at N3,
-'
<0
CO
O'l
iT• N2 JP with
103.70 I qutter flol'l
172 83 .036
103 . 55 106.45 103.55
3.00 300
103.55 TEST 1 OK .for Do - 375; fails
TEST 2; u/s inv. max Rl 102.99
1 3. ~6'P)A
5 = Wl~r' BWl at N2,
n
~~P! N1 237 17 .032 .375 2.1 5 I- 2B 0. 5 . 24 .18 .12 0.30 0.89 0.74
375 t b{ e3
R
T~STS 2 O~ f?5 D? = 375;
(f)
-I
1O~:15 I ~~t~~~hfl Oil 103. 00 103.45 103.00 1
102. 66 u s lnv. max& l 2. 5 b~ eqn o:D
(6 .1 9) ; max . B~l at N1, l
~lpe
, 1 .. t~4 251 5 .03C .3 75 2.27 I- 2B 0.5 .26 . 06 .13 0.1 9 0.53 0. 62
375 102 . 66 by eon 6. 20) s:
M .1 I N1U~J. 6'1i ~ with
t~ro pl ~e ~revioualY..... 102.78
lat s sSlgne 102.90 102 .78 102 . 47 TESTS 1 & 2 OK for Do - 525; o
u/s inv. max Rl 101. 72 by eqn :D
oi~e
M.II .. E1 322 100 . 008
.450 2. 02 J- 2C
.525 1.48 2. 0 ..11
21 .79 .42
.36 . 22
1. 21
0.58 0.8, -
1.15 525 t (6 .1 9); max . B~ l a~)M.4, Rl
102.47 bv eon '6 . 20
»
E1 JP, gutter Z
101. 89 TESTS 1 and 2 OK for 0 = 525; »
iT• 102 . 25 flow l at ' s
~lpe
1 .. M.1 318 8 .006
102 . 10 102 .68 102.10
. 5<,5 1.4 I- 3A 0.5 .11
. Uj .Ub U.U~
0. 3C U.8<'
525
upstream inv . max Rl 181 . 30 by
eqn (6 . 19); max. BWl at E1,
G)
m
~tU,!Jnt _M_. mU ltl-p l pe
102 . 05 102 . 00 102.00
~
BWl FROn i·1AIN PI PELINE (TRUNK) COMPUTATIONS 101.80 Rl 101.89 by eqn (6.20)
o
102.20 JP m
(f)
MAIN PIPELINE: TRUN K M. 3-M.2-M.1 -M.0 G)
M . 2 NODE M. multi -ri pe 114.05 11 0.55 11 4.05 114.05 TEST 1 OK for Do - 300 ; fails Z
114 . 20 JP TEST 2; u/s inv. max Rl 113.45
oi~e
M. .. N3 81 100 .036 .300 1.1! lulti - 3. 0 .07 .38 .20
pi pe JP
0.58 3.60 0.83
300 ~{ in :bf7~ )Awr~x, BWl at M.3 Z
(f)
... N3
110.60 JP
thro' pi pe 110.45 108 . 35 110.45 110.45 TEST 1 OK for 0 - 300; fails
TEST 2; u/s inv~ max Rl 110.13
s:
»r
• N2
~3P! N2
thro' pi~e
75 68 .03;;
108.25 107.25 108 . 25
.300 l.Ot J -1 0.2 .06 .20 .01 0.21 2.20 0.65
300
108 . 25
~( n8:i~'7~) Aw~~x. BWl at N3,
TEST 1 OK for Do - 300 ; fails
r
C
108. 40 with lat s TEST 2; u/ s inv. max Rl 107 .66 :D
~~P! M 2 137 44 .025
• .lUU 1. ~,
J - 2B 1. 0 .1 9 .48 .19 0. 67 1.4 1 0.93
t ~r f~2'~~ ' 7~) Awr~x, BWl at N2, CO
preylous Y__
300 »
. 1 N1U~7t. 3O';; JP ltl- plpe asslg ned
M mU 107 . 15 104 .75 107.15 TEST 1 OK for Do - 375; fai l ~ Z
.
M 106. 84 TEST 2; u/s inv. max Rl 105.60
.j/ L . j~ mu lti - 3. 0 .,,9 Il. 3~ . 8/ ".19 l. 88 ~( eqn (6.19); max. BWl at M. 2
()
~~ ~e.. N2 264 100 .025 pi pe JF 2.5C 375 * 106 .84 by eqn (6.20) »
-I
N2 thro ' pi pe 104.65 102.10 104 .65 104.65 TEST 1 OK for Do = 375; fai l s ()
104. 80 JP TEST 2; u/s inv. max Rl 104 .1 9 I
~ ip e
, 2 .. M, 1 243 105 . 025 . 375 2. 2 J-1 0.2 . 25 1.1 .05 1.22 2.8: 1. 73
375 ~r f~a' ~~. 7~) A'Jr~x , BWl at N2, s:
o NODE M. mu lti -p ipe prevlo u s l~ 102 . 00 101.80 TESTS 1 & 2 OK for Do 600; m
M assigned 100. 85 102.00 Z
. 102. 20 JP uls inv. max Rl 100.57 by eqn
6;
mu ltl- u/j - (6.19 max. B~~ a )M.1, Rl -I
~ l pe
1.1 .. N1
576 100 . 01 :~5_~ ~ :8~ pijJ_e JP 3.0 : ~~ I ~ 66 1
1:
63 f:g 1.43
1.50 600 t 101. 8 bv eon 6. 20 3 (f)
10~ ~ 90 J~ro plpe 100.10 100.75 100.57 TESTS 1 & 2 OK for D~ - 600;
:t 100.75
. 60C 1.9 J -1 0.2 .i9 . 53 . 04 0. 57 1.43
~/S inv. max Rl 99.9 by eqn
6 . 19~; max. B~~ a~)N1, Rl
M.O
~lpe
1 .. M. O 543 100 .OOS
DESI GN FLOOD LEVEL RL 100.000 = BWl
0.75
..
600
100.00
00.5 bv eon 6.20
*Design of t hi s pipe falls into the ' Outcome 110utcome 2' situati on
-'
descri bed in Section 6.8 of text
o
w
CASE 4: STEP 7 - ADDITIONAL NOTE (water level) value, Kw, which should be used
at the junction pit, and are:
The design flow distribution set out in Fig.
7 uses the greater flow where there is 251 Lis from the northern pipe ; and
choi ce - shown for each component in Fi gs 6A 71 Lis from pipe M.4E1 + M.4.
and 6C. While this gives appropriate values
for use in the design of the components them- The procedure adopted in the Handbook
selves, it represents a loss of data which for selecting values for Kw (see Tables 6.5
may be of importance in some design practices. and 6.6) is an approximate one which is in-
sensiti ve to the difference di scussed here.
Consider the alternative flows presented Designers who employ the full 'Missouri
for pipe M.4E1+M.4 : Charts', however, should be aware of the
difference and should use the correct (alter-
from Fi g. 6A (primary drai nage considera- native) values in their appropriate contexts .
tions) flow 81 Lis
from Fig. 6C ('total catchment' considera- A further interpretation which has been
tions) flow 71 Lis made in preparing Fig. 7 should be observed:
this concerns the aspect discussed in STEP 6,
Pipe M.4El + M.4 should be designed to Table 6, Note 3, above.
convey a design flow (N = 5 years, ARI) of 81
Lis. Pi pes ca rry i ng discharge direct ly from
node pits are shown with the appropriate val-
The design of mai nl i ne component M.4 + ues collated from Fig. 6C. Flows from the
M.1El, however, involves not only its design 1ocat ions whe re these pi pes are interrupted
flow of 322 Lis but also the flows entering downstream by a junction pit, inspection pit,
node M.4 under corresponding design condit- etc., use the 'relative flow' value (shown
ions. These flows determine the pit headloss bracketed in Fig. 6C).
,
M.2N1R /s~ ::. g ~ ~\El1oR
PIT FLOOR °0 M-S ~,..., Rl109 ·67
Rll07' 05 Ptl FLOOR Sm l.Om
M·2 RL109 31 e 0'300 300 _
M SE2
PIT FLOOR ~ :g PIT FLOOR
Rl 10560 E "" PIT flOOR Pil flOOR M·4N3 RL110J9
I.p. M·4N3 ~:;; RL 106 88 Rll0783 loP Pil FLOOR
:;, 8 Rl 106-00
M·1N2 ~ ~ M 4N2
loP M·1N 2 I.P. PIT FLOOR 2 PIT FLOOR
Rl 104 00 Rll02 99
M·1N1R
PIT FLOOR
RL 10155 M·1N1L M·4N 1
PIT FLOOR 1
RL1 0215
~~
~""";;:-~_ _ _-7.'0".
0"m -_ _:-:-:-....,5"'m,-f-'+-~"--.. M.4E2 100m
525 M.4 300 525 lOO
M·4
PIT flOOR
RL 10172
M·1E1L M· 4E1 L
Eo
PI T FLOOR PIT FLOOR
0 0 RL10150 Rl 1022 8
"'~
MoliI~
M '~5IGN FIGURE 10 : APPR OXI MATE NETW ORK FIG URE 11 : APPROX IMATE NETWORK
~R
'LOOO ~O_[_S I~N FLOOD
~ WATER LEVEL : RL 100 00 DESIG N· N =5-YE AR S LEVEl RL100 OQ DESIGN WITH PIT FLOOR LEVELS
whi 1 e the remai nder are data transfers between Oesp ite these advantages, comp rehens i ve
steps. Correspondi ng numbers for the other testing of many components used in Australia,
categories listed above are: b), c) and e) in particular various gutter inlets (gratings,
about ten acts each, and d), 20 acts. side-entry inlets), junction pit configura-
tions, underground network flow conditions,
While the potential for error is undeni- etc., has never been undertaken. Enough is
ab ly great the use of hydrau 1 i c data from known from experimental work carri ed out on
tested components only and careful execution simi lar units, however, to partly overcome
of the design processes by hand or with com- this deficiency by providing 'first approxi-
petent software should restrict the overall mat ion' data of the type presented in some
error likely in the bulk of these acts to Appendix A cases. While this is satisfactory
between 5 and 10 percent. The error poten- as a stop-gap measure, it should be replaced
tial of the remaining acts, drawn mainly from by a programme of systematic testing of units
categories b), c) and e) above is reviewed in used widely in Australian practice.
the following sub-sections.
One of the main issues which the design-
er of urban drai nage networks in small urban
Error in peak flow estimation in s.all urban catchments must decide is the use to be made
catcMents of available data on the junction pit headloss
pilrilmpt.pr Kw ilnrl on thp. Oarcy-Weisbach fri-
The two main catchment characteristics upon ction factor, f. Should accurate values for
which the simple mathematical models of urban these parameters be obtained from the Missou-
hydrology devolve are (see Chapter 4):- ri and Moody charts, respectively, or are
approximate values satisfactory?
1) runoff coefficient, C, and
This question has been decided in the
2) critical storm duration, tc or tie Handbook procedures in favour of fi xed values
(Tables 6.5, 6.6 and Section 6.7) selected on
Schaake et al (1967) showed in an experi- the 'high' side of average in each category
ment-based study of the Rational Method app- leading to 5 - 8 less minor computations and
lied to small urban catchments, that errors two less chart consultations per pipe, com-
made by experienced practitioners are 1 i kely pared with procedures requiring full Missouri
to exceed ± 10 per cent in estimating C and ± / Moody consultation. This tally applies only
30 per cent in estimating critical storm dur- where tri al pi pe si ze proves to be sati sfac-
ation. Flow estimation errors of more than ± tory. The saving on computations/consultat-
20 per cent can be expected. Argue (19 82) ions where trial and final sizes differ is,
rnnfirmp.rl this finding for a hypothetical ur- of course, qreater.
ban subdivision in which critical storm dura-
tion was set equal to tc and showed that in The criticism that accuracy has been
cases where critical storm duration equalled compromised in the interests of developing a
ti - paved area travel time - flow estimate simple procedure can be partly answered by
variation was reduced by about one third. reference to the Case 3 and Case 4 illustra-
This is explained by the lower level of un- tions presented in Chapter 11. Reworking
certainty that deSigners face in estimatin~ TARIF R/g in p.ilr.h r.ilSP. with headlosses deter-
ti in urban catchments and, to some extent, .mined by reference to Missouri and Moody
by its magnitude compared with tc. Chart data yields the following outcome:-
Overall variation in design peak flows Case 3:
estimated for ungauged urban catchments by
experienced practitioners uSing the Two-Value pipe network - no change in component sizes
Rational Method of Chapter 4 is likely to pit water levels (H.G.l.) -
fall within the range ± 15 per cent to ± 25 pit XA.3El maximum water level reduced
per cent. by 0.03 m
other pits : no change
Corresponding flow estimates produced by
more sophi st i cated and t i me-consumi ng models
such as IlllJOAS (Terstriep and Stall 1974), Case 4:
IllUOAS-SA (Watson 1981) and IlSAX (O'lough-
lin 1986) applied to Australian catchments pipe network - no change in component sizes
show much the same range of variation. The pit water level (H.G.l.) -
great value of these models resides in their 50 per cent no change;
abi 1 ity to generate runoff hydrograph data. 50 per cent lowered by maximum of 0.20 m
AITKEN, A.P. (1975). Hydrologic investigation BATES, M.A., NOLAN, C. and O'LOUGHLIN, G.G.
and design of urban stormwater drainage (1984). Physical modelling and decision
systems. Aust. Water Resources Council making for an urban drainage problem.
Tech. Paper No. 10. (AGPS: Canberra.) Proc. I.E. Aust. Conf. on Hydraulics in
Civil Engineering, Adelaide, pp. 40-43.
ALLEY, W.M., and VEENHUIS, J.E. (1983).
Effective impervious area in urban run- BELL, P.R., BROWN, J.D., GORONSZY, M.C. and
off mode 11 i ng. ASCE Hyd raul i c En g. 109 LACEY, D.T. (1979). Measurement and
(2), pp. 313-19, February. analysis of the effects of stormwater
on the Lane Cove estuary. Proc. I.E.
AMERICAN SOCIETY OF CIVIL ENGINEERS (19 82). Aust. Hydrology and Water Resources
Stormwater detention facilities. Proc. Symposium, Perth, September, pp.254-58.
Conf. co-sponsored by ASCE Urban Water
Resourced Research Council and Enginee- BLACK, R.G. and PIGGOTT, T.L. (1983). Head
ring Foundation. B.Urbonas, editor. losses at two pipe stormwater junction
(ASCE : New York.) chambers. Proc. I.E. Aust. Second
Nat. Local Govt Eng. Conf. Brisbane,
ARANSON, D,A. and PRILL, R.C. (1977). Analy- September, pp. 219-23.
sis of the recharge potential of storm-
water basins on Long Island, New York. BLISS, P.J., BROWN, J.D. and PERRY, R. (1979).
Res, U.S. Geological Survey 5(3) pp. Impact of storm runoff from urban areas
305-18. on surface water quality. Proc. I.E.
Aust. Hydrology and Water Re .:; .)ur ces
ARCHER, B., BETTESS, F. and COLYER, P.J. Symposium, Perth, September, pp. 249-53.
(1978 ). Head losses and air entrainment
at surcharged manholes. Hydraulics Re- BLISS, P.J., RILEY, S.J. and ADAMSON, D.
search Station, Wallingford, Oxon, Rep. (1983). Towards rati onal guidel i nes for
IT 185, 11 pp. urban stormwater disposal into flora
preservation areas. Shi re and Munic-
ARGUE, J.R. (1981). Urban storrTWater collec- i pal Record, July, pp. 181-85.
t i on systems - a revi ew. Aust ra 1 ian
Road Research Board. Internal Report, BOENISCH, M.E. (19 84) On-site detention -
AIR 1093-1. e xperience at Wollongong. Proc.
Seminar on Problems of Existing Storm-
water Drainage Systems. N.S.W. Commit-
ARGUE, J.R. (198 2). Stormwater fl ow estimat-
ion in small ungauged urban catchments. tee, Water Research Foundation of
Australia. G.G. O'LolJghlin, ed itor.
Proc. 11th ARRB Conf. 11(2), pp. 193- Sydney, 28 pp.
205.
BONHAM, A.J. (1974). Storm drainage deSign
ARGUE, J.R. (1984). Design flow estimation in and new city planning. I.E. Aust.
small ungauged urban catchments. Proc. Ci v. Eng. Trans. CEI6( 1), pp. 67-70.
Thi rd Int. Conf. Urban Storm Drainage,
Gotenborg, Sweden, June, pp. t~~-64. BROO KS , L.G. and COC KS, G.C. (19 83). A rat-
Reprinted as ARRB Internal Report, ional approach to the design of storm-
AIR 391-1. wat e r sumps. Main Roads Dept, Western
Au s tra li a , Ma t erials Rep. 8 3/42M.
AUSTRALIAN WATER RESOURCES COUNCIL (19 85). BROTCHIE, J.F. (1977). Urban development
Guidelines for floodplain management in without spoiling creeks. Habitat Aust.
Au st ra 1 i a. Wa ter Ma nagement Se ri es No. Conservation Foundation, 5(1), June,
6. (AGPS: Canberra.) pp. 8 -13.
BANNIGAN, J.M. and MORGAN, D. B. (19 81). BURGI, P.H. and GOBER, D.E. (1977). Bicycle-
Hydraulic design of piped stormwater safe grate inlets study. Rep. No.
systems. Proc. I.E. Aust. Conf. on FHWA-RD-77-24. U.S. Dept. Transp. Nat.
Hydraulics in Civil Engineering, Sydney, Tech. Info. Service, Springfield,
pp. 49-53. Virginia.
BURTON, T.M., TURNER, R.R. and HARRISS, R.C. DEPTARTMENT OF MAIN ROADS, NEW SOUTH WALES
(1976). The impact of highway construc- ( 1979) . Model analysis to determine
tion on a North Florida watershed. hydraulic capacities of kerb inlets and
Water Resour. Bull. 12, New York, pp. gully pit gratings.
529-38.
DOWD, B.P., IOAKIM, R. and ARGUE, ,l .R. (lq811).
CAMERON McNAMARA (1985). Kensington flooding The simulation of gutter/pavement flows
drainage works investigation. Report on Sou th Australian urban roads. Proc.
to Public Works Dept, N.S.W. Civ. Eng. 10th ARRB Conf. 10(2), pp. 145-52.
Div. Rep. 84030, January.
DURU, J .O. (1982) . On-site detention a
CITY OF FORT WORTH (1967). Storm drainage s tormwater management or mi sma nagement
criteri a and des i gn manua 1 • Prepa red tech nique? Urban Stormwater Qu ality,
by Knowlton-Ratcliff-English, Consult- Management and Planning. B. C.Yen,
ing Engineers, Fort Worth, Texas, editor. Water Resources Pub., Colorado,
December. U.S.A., pp. 341-49.
CLARKE, W.P., STRODS, P.J. and ARGUE, J.R. EARLEY, P.C. (1979). Gully inlet spac ing de-
(19 81). Gutter/pavement flow relation- sign. ' Faculty of Eng. Univ. Western
c;hirc; for rOilrlwilY rhilnnpls of mQriprilt.p Austral i a.
or steep grade. Proc. I.E. Aust. Fi rst
Nat. Local Govt. Eng. Cont., Adelaide, ENVIRONMENT CANADA (19811a) . Proposed rnodel
pp 130-37. policies for urban drainage ma nagement.
Report of the Urban Drainage Policy
COLMAN, J. (1978). Streets for 1ivi ng. Aust- Committee to the Urban Drainage Sub-
ralian Road Research Board. Special cornmi t tee, Envi ronrnenta 1 Protection
Report, SR 17. Servi ce, Envi ronment Canada. Research
Repor t No. 102.
CONCRETE PIPE ASSOCIATION (1985). Concrete
pipe guide. Concrete Pipe Association ENVIRONMENT CANADA (1980b). ManlJ dl of pr'iC-
of Australia, Elsternwick. ti ce for urban drai nage. Envi ronment
Protection Service, Environment Canada.
CORDERY, I. (1976a). Some effects of urban- Research Report No. 104.
isation on streams. I.E. Aust. Civ.
Eng. Trans. CE18(1), pp. 7-11. ESCRITT, L.B. (1965). Sewerage and Sewage
Di sposal. 3rd Ed. (CR Books/Appl ied
CORDERY, 1. (19760). PuLeliLidl vdlue ur Science Publishers: London.)
treatment of urban stormwaters. I.E.
Aust. Ci v. Eng. Trans. CE18(2), pp. FINLA YSON , C.M. (1983). Use of aquatic plants
60 -63. to treat wastewater in irrigation areas
of Austral ia. Proc. 10th Federal Con-
CORDERY , I. (1977). Quality characteristics vention Aust. Water and Wastewater
of urban storm water in Sydney, Austra- Assoc., Session 22, Sydney, 10 pp.
l ia. Water Resour. Res. 13, \pp. 197-
202. ' FORllES, H.J.C. (1976). Capac ity of 1 atera 1
stormwater iql ei:,> . i, ivil I:: ng. South
COUNTRY ROADS BOARD, VICTORIA (1982). Road Africa, 18(9), pp. 195-205. Discussion,
deSign manual. Chapter 6 : Drainage. 19(5), pp. 95-99.
CU LLEN, P., ROSICH, R. and BEK, P. (1978). GORDON, A.D. and STONE, P.B. (1973). Car
A phosphorous budget for Lake Burley stabi 1 ity on road fl oodways. Univ. of
Griff in and management implications for New South Wales, Water Research Labor-
urban lakes. Aust. Water Resources atory, Rep. 73/12.
Council Tech. Paper No. 31. (AGPS:
Canberra. )
GOYE N, A.G. and McLAUGHLIN, D.A. (197 8) . Can
we afford to treat urban stormwater
DANDENONG VALLEY AUTHORITY (19 80) . Melton runoff? Proc. I.E. Aust. Hydrology
drainage study. Master drainage plan Symp. Canberra, pp. 57-61.
prepared for Melton-Sunbury Management
Committee by Dandenong Valley Author-
i ty, March. GOYEN, A.G., MOODIE , A.R. and NUTTALL, P.M.
(1985) . Enhancement of urban runoff
de GROOT, C.F. and BOYD, M.J. (1983). Exper- quality. Proc. I.E. Aust. Hydrology
imental determindtion of head losses in and Water Resources Symp. Sydney, pp.
stormwat er systems. Proc. I.E. Aust. 202 -08.
Seco nd Nat. Conf. on Local Govt. Eng.
Brisbane, September, pp. 214-1 8. GRIGG, N.S., BOTHAM, L.M., RICE, L., SHOE-
MAKER, W.J. and TUCKER, L.S. (1976).
DICK, T.M. and MARSALEK, J. (1985). Manhole Urban drai nage and fl ood control proj-
head losses in drainage hydraulics. ects, economic, legal and financial
Proc. 21st Congo Int. Assoc. Hydraul i c aspects. Hydrology paper, Colorado
Res. Melb ourne, August, Vol. 0, pp. State Univ., Fort Collins, Colorado,
123-31. U.S.A.
GUTTERIDGE, HASKINS AND DAVEY PTY. LTD. INSTITUTION OF ENGINEERS, AUSTRALIA (1987).
(1981). Characteristics of urban Australian rainfall and runoff. 3rd ed.
stormwater runoff. Aust. Water Resourc- (I.E. Aust: Canberra) (i n press).
es Council. Tech. Paper No. 60. (AGPS:
Canberra. ) IZZARD, C.F. (1946). Hydraulics of runoff
from developed surfaces (and discuss-
GUY, H.D. and JONES, D.E. (1972). Urban sed- ion). Proc. Highway Res. 26, pp.
imentation in perspective. ASCE J. 129-50.
Hydraulics Div., 98(HY 12), pp. 2099 -
116. JAMES HARDIE PTY LTD (1985). Textbook on
Pipeline Design. (James Hardie,
HALL, M.J. (1984). Urba n Hydrology. (Elsevier Sydney)
Applied Science Publishers: Essex, U.K.)
HANNAM, I.D. and HI CKS, R.W. (1980). Soil JOHNSON, R.L. and PUTT, R.A. (1977). Storm
conservation and urban land use plann- wate r retent i on and detent ion. Leh i gh
i ng. Soil Conse rvation Service of Univ. Fritz Eng. Laboratory Report No.
N.S.W. Soil Conser vation, 36, pp . 134- 426 .2 , December, 35 pp.
4S.
JONASSON, S.A. (1984a). Determi nati on of i n-
HAWKEN, H.W. ( 1921) . An analysis of maximum filtration capacity and hydraulic con-
runoff and rainfall intensity, Trans. ducti vity. Proc. 3rd Int. Conf. on
I.E. Aust. 2, pp. 193 - 215. Urban Stonn Drain., Goteborg, Sweden,
June, pp. 1073- 82 .
HEEPS, D.P. (1977). Efficiency in ind ustr ial,
municipal and domestic water use . Aust. JONASSON, S.A. (19 84b). Dimensioning methods
Water Resources Council. Tech. Paper for stormwater infiltration systems.
No. 20 . (AGPS: Ca nberra.) Proc. 3rd Int. Conf. on Urban Storm
Drainage, Gotebo rg, Sweden, June, pp.
HENDERSON, F.M. (1966). Open Channel Flow. 1037-46.
(MacMillan: New York.)
JONES, E.D. (1967). Urban hydrology, a r e-
HENDERSON, F .M., FIELD, W.G. and WILLIAMS, dir~ction. ASCE Civ. Eng. 37(8),
B.J . ( 19 80) . Urban Drainage. Notes for August, pp. 58-61.
a refresher course, Dept. Civ. Eng.
Un i v. Newc a s t 1e , N. S • W. JONES, E.D. (1971). Where is urban hydrology
p ra ct ice today? ASCE Hyd raul i cs Di v.
HENKEL, G.G . (19 81) . Land-use planning must 97(HY2), pp. 257 - 64.
relate to drainage. Proc. I.E. Aust.
First Nat . Local Govt . Eng. Co nf., KARR, J .R. and SCHLOSS ER, I.J. (197 8) . Water
Adelaide, pp. 83 - 89 . re sources and the land-wat er interface.
Science 201, pp. 229-34.
HOLMSTRAND, O. (1984) . Infi ltration of s torm-
water : Research at Chalmers Unive r sity KIDD, C.H.R. and LOWING, M.J. (1979). The
of Technology, results and examples of Wal ingford urban subcatchment model.
application. Proc. 3rd Int. Co nf. on U.K. Inst. Hydrol ogy Report No. 60,
Urban Sto rm Drainage, Goteborg, Sweden, November.
June, pp. 1057 -7 2.
KUICHLING, E. (1889). The relation between
HUGHES, H. (1974). Road surface drainage - a rainfall and the discharge of sewers in
revi ew . Austral i an Road Res earch Board . populous districts . Trans. ASCE 20 , pp.
Research Report, ARR No. 33. 1-60.
ICHIKAWA, A. and YAMAMOTO, T. (1984) . Experi - LAND COMMISSION, NEW SOU TH WALES (1984).
mental field for the quantitative ana- The streets where we live - a ' manual
lysis of the pervious pavement at the for the design of safer residential
baseball field, University of Tokyo. estates.
Proc. 3r d Int . Conf . on Urban Storm
Drainage, Goteborg, Swede n, June, pp. LIGHTHILL, M.J. and WHITHAM, G.B. (1955). On
1009-1 8 . ki nemat i c waves : I. Flood movement in
IN ST ITUTION OF ENGINEERS, AUSTRALIA (1958) . long ri vers. Proc. Royal Soc. Se ri es
Austral ian rai nfall and runoff. Fi rst A, Vol. 229, pp. 281-316.
report of the I. E. Aust. StorllMater
Standards Comm ., Sydney . LINSLEY, R.K. and FRANZINI, J. (1979). Water
resources Engineering, 3rd edition.
INSTITUTION OF ENGINEERS, AUSTRALIA (1983). (McGraw-Hill Kogakusha, Tokyo).
Seminar on retarding basins. Proc. of
seminar organised by Syd ney Division LLOYD-DAVIES,D.E. (1906). The elimination
Water Resources Panel. G.G . O'Loughlin, of storm water from sewerage systems .
editor, 19 April, Sydney . Proc. Inst. Civ. Eng. 164, pp. 41-67.
INSTITUTION OF ENGINEERS, AUSTRALIA (1977). LOGAN CITY COUNCIL (1983). Standard - Storm-
Australian rainfall and runoff. 2nd ed. water Drainage Manhole losses. Chart
(I.E. Aust: Canberra.) A, Chart B, date 11/1/83.
McPHERSON, M.B. (1969). Some notes on the O'L OUG HLIN, G. G. an d AVE RY , (i. C. ( 198 0) . Re -
rational method of storm dra inage de - cu rre nce i nt e rval s fo r mi no r urb an
si gn. ASCE Urban Water Resources Re- drain d~e ;%r ~5 . Proc . I.F.. Ao.J5t. Hyd-
s earch Program, Tech. Memor. No. 6 , rology and Water Res ources Symp. Ade l-
New York, January. ai de, pp. 39-4 3.
MAKIN, I.W. and KIDD, C.H.R. (1979). Urban O'LOUGHLIN, G.G. ( 1986 ). The IL SAX program
hydrology project: collection and ar- for urban d rain age desi gn a nd ana lysis.
chive of U.K. hydrological data. Inst. School of Civ. Eng. N. S.W. Inst. Tp' (I I-
Hydrology Report No . 59, October. no l., Sy dnp.j .
MATTHEWS, T.M., PITTS, J.R., LARLHAM, R.C.
PHILLIPS, D.I. (19 85) . An e valu at ion of the
and KOCSAN, J. C. (19 8 3). Hyd ro-brake performan ce of an on-site st o rmwater
regulated storage system for storm- detention storage. Proc. I.E. Aust.
water management. Snell Envi ronmental
Hydrology and Water Resources Symp.
Group Inc. for Cleveland Dept. Public
Utilitie s , Ohio. Sydney, May, pp. 197-201.
MELBOURNE AND METROPOLITAN BOARD OF WORKS POLIN, M.J. and CORDERY, I. (1979). An eco-
(19 81). Interim drainage basin manage- nomic approa ch t o t he -;,~ l ect i o n o f a
ment criteria manual. design flood. Proc. I.E. Aust. Hydro-
logy and Water Resources Symposium,
MILLS, S.J. and O'LOUGHLIN, G.G. (19 84). Perth, September, pp. 194-98 .
Workshop on urban piped drainage sys-
tems. Swinburne Inst. Technol./N.S.W. POERTNER, H.G. (197 3). Pract ices in deten-
Inst. Technol., Melbourne. tion of urban s torm water runoff. U.S.
Dept Interior, Washington, D.C.
MOODIE, A.R. (1979). Modelling of water
quality and hydrology in an urban PUBLI C WORKS OEPARTMENT, NEW SOUTH WALES
watercourse. Aust. Water Resources (1985). Hydraulic capacities of gutter
Counci 1 Tech. Paper No. 45. (AGPS : inlets for N.S.W. Housing Commission.
Canberra. )' Manly Hydraul ics Laboratory Rep. 419,
January.
MAIN ROADS DEPARTMENT, QUEENSLAND (1980) .
Urban road design manual. RAGAN, R.M. and DURU, J.O. (1972). Kinematic
wave nomograph for time s of concentra-
MULVANEY, T.J. (1851). On the use of self tion. Proc. ASCE, J. Hydraulics Div.
registerinq rain and flood gaugps in 98(HY10), October, pp. 1/6~-/1.
making observations on the relation of
rainfall and of flood discharges in a REID, J. (1927). The estimation of stormwater
given catchment. Trans. Inst. Civ. discharge. J. Inst. Municipal County
Eng., Ireland, 4(2), pp. 18-31. Eng. (U.K.) 53(23), pp. 997-1021.
MURPHY, C.B., MacARTHUR, D.A., CARLEO, D.J., RILEY, D.W. (1932). Notes on calculating the
QUINN, T.J. and STEWART, J.[. (1981). t low of surface water in sewers. J.
Best management practices implementa- Inst. Municipal and County Eng. (U.K.)
tion : Rochester, New York. U.S. Env. 58(20), pp. 1483-95.
Protection Agency Report PB-82-171-067,
Chicago IL, April. ROBINSON, D. and O'L OUGHLIN, G. G. (19 83).
Introduction - what is a retarding
NATIONAL CAPITAL DEVELOPMENT COMMISSION basi n? Proc. I.E. Aust. Semi nar on
(1981). Guidelines on engineering and Re ta r d i ng ~a., i 11 ') . Organi sed by Sydney
environmental practices - hydraulics. Division Water Resources Panel. G.G.
O'Loughlin, editor, Sydney, April.
NATIONAL WATER COUNCIL AND U.K. DEPARTMENT OF
ROSS, C.N. (1 921). The calculation of flood
THE ENVIRONMENT (1981). Design and
analysis of urban storm drainage, the discharges by the use of a time contour
Wallingford procedure. National Water plan. Trans. I.E. Aust. 2, pp. 85-92.
Council, Vol. 1-5, London. ROWBOTTOM, I.A., PILGRIM, D.H. a nd WRIGHT,
G.L. (19 86). Estimation of rare floods
NEW SOUTH WALES HOUSING COMMISSION (1976). (between the probable ma ximum flood and
Road manual. the 1 in 100 flood). I.E. Aust. Civ.
Eng. Trans. CE2 8(1), pp. 92-105.
NICHOLAS, 0.1. and COOPER, G. ( 1984). On- s ite
detent ion - experi ence in Ku ri ng-Ga i • SANGSTER, W.M., WOOD, H.W., SMERDON, E.T. and
Proc. Seminar on Problems of Existing t3 0SS Y, H. G. ( 19'18) . P r ~ssu re c hanges
Stomwater Drainage Systems, N.S.W. at stormwater drain junctions, Bull.41,
Committee, Water Research Foundation of Eng. Experiment Station, Univ . Missouri,
Australia. G.G. O'Loughlin, editor, U.S.A.
Sydney, 21 pp.
SATOR, J.D., BO YD, G. B. and AGA RDY, F.J.
NOVA K, P. and NULLURI, C. (1984). Incipient ( 1974). Water pollution aspe cts of
motion of sediment particles over fixed stree t su rfa ce c ontami nants. .J. Water
beds. J. Hydraul ic Res. 22(3), pp. 181- Pollution Control Federation 46, Wash-
97. ington D.C., pp. 458-67.
SCHAAKE, J.C., GEYER, J.C. and KNAPP, J.W. UNITED STATES ENVIRONMENT PROTECTION ADMINIS-
(1967). Experimental examination of TRATION (1972). Guidelines for erosion
the rational method. ASCE J. Hydraul- and sediment control planning and
ics Div. 93(HY 6), pp. 353-70. implementation. U.S. Env. Protect.
Admin., Washington.
SCOTT AND FURPHY PfY LTI) (1 9fl4). Eng i neeri ng
standards for residential land develop- VALLENTINE, H.R. (1967) . Water in the Service
ment. Report prepared in association of Man. (Pengui n Books: Hamondsworth.)
with Coopers & Lybrand Services for
Dept Housing and Construction. (AGPS:
Canberra. ) van DAM, C.H. and van de VEN, F.H.M. (1984).
Infiltration in the pavement. Proc.
SIEKER, F. (1984). Storrrwat er infiltration in 3rd Int. Conf. on Urban Storm Drainage,
urban areas. Proc . 3rd Int. Conf. on Goteborg, Sweden, June, pp. 1019-28.
Urban Storm Drainage, Goteborg, Sweden,
June, pp. 1083-91. WALKER, J.H. (1979). Characteristics of
pollution in urban stof'mllater runoff.
STEPHENSON, D. (1984). Stof'mllater hydrology Proc. I.E.Aust. Hydrology and Water
and drainage. (Elsevier Applied Science Resources Symp . Perth, pp. 244 - 48.
Pub Ii shers: Jlms terdam. )
STORM DRAINAGE RESEARCH COMMITTE E (1956). The WANIELISTA, M.P. (1979). Stormwater Manage-
deSign of stormwater inlets. Report of ment - Quantity, Quality. (Ann Arbor
the Storm Drainage Research Committee Science, Michigan).
of Dept. of Sanitary Eng . and Water
Resources, Johns Hopkins Univ. Balti- WATER RESEARCH FOUNDATION (1984). Seminar on
more, Maryl and, June. problems of existing stormwater drain-
age systems. Proc. Seminar organised
TERSTlUEP, M.L. and STALL, J.B. (1974). The by N.S.W. Committee of WRF of Austral-
Illinois urhan drainage Mea -; i.nulator, ia, 28 November. G.G. O'Loughlin, edit-
ILLUDAS. Bull. 58, Illinois State Wat- or, Sydney.
er Survey, Urbana, U.S.A.
THEIL, P.E. (1977). Urban drainage design for WATSON, M.D. (1981). Application of ILLUDAS
new deve I opnent. Proc. Urban Dra i nage to stormwater drai nage desi gn in South
Conf. Organi sed by the Urban Drai nage Africa. Rep. 1/81, Hydrological Re-
Subcommittee, Environment Protection search Unit, Univ. Witwatersrand,
Servi ce, Envi ronment Canada, Toronto, Johannesburg.
March.
WATTS, B.A. (1983). Hydraulic losses in
THOLIN, A.L. and KEIFER, C.J. (1960). Hyd- stormwater pits.
rology of urban runoff. Trans. ASCE
125, pp. 1308-79. WEBER, W.G. and REED, L.A. (1976). Sediment
runoff during highway construction. J.
THOMPSON, D.G. (1983). The one percent prob- ASCE Civ. Eng. 46(3), pp 76-9.
ability flood as a basic drainage de-
sign criterion. Proc. I.E. Aust.
Second Nat. Conf. on Local Govt. Eng. WHIPPLE, W., GRIGG, N.S., GRIZZARD, T., RAN-
Brisbane, September, 1983, pp. 207-13. DALL, C.W., SHUBINSKI, R.P. and TUCKER,
L.S. (1983). Stormwater Management in
TOUBIER, J.T. and WESTMACOTT R. (1980). Urbanising Areas. (Prentice Hall,
Stormwater management alternatives. Englewood - Cliffs)
Water Resources Centre, Univ. Delaware,
Apri 1.
WILLING AND PARTNERS PTY LTD (1978). Canberra
ULI/ASCE/NAHB (1979). Residential storm water stormwater system: side entry pit cap-
management. Report by Urban Land In- acities - field assessment. Final draft,
stitute/Am. Soc. Civ. Eng/Nat. Assoc. July. National Capital Development
of Home Builders, Washington, March. Commission, A.C.T.
UNITED STATES OEPARTMENT OF TRANSPORTATION WOLMAN, M. and SCHICK, A.P. (1967). Effects
(1978). Best management practices for of construction on fluvial sediment,
erosion and sediment control. U.S. urban and suburban areas of Maryland.
Dept. Trans. Fed. Hi ghw. Admin., Wash- Water Resources Res. 3, pp. 451-64.
ington.
UNITED STATES DEPARTMENT OF TRANSPORTATION WRIGHT-McLAUGH LIN, ENGINEERS (1969). Urban
(1979). Design of urban highway drain- storm drai nage. Cri teria manual, Vol s
age - the state of the art. U.S. Dept. 1 and 2. Denver Regional Counci I of
Trans. Fed. Highw. Admin., Washington. Govts, Denver, U.S.A., March.
The gutter/pavement and inlet exampl es used LEVEL 1 Flow/capture relationships formed
in the body of the Handbook to illustrate from at least two independent sets
major and minor storm drainage design pro- of test results obtained for inlet
cedures are not employed universally in Aus- cases (models or prototypes) having
tralian practice. Additional hydraulic in- identical or similar geometries.
formation for other widely used gutter/pave- Unbroken 1ines or curves are used
ment geometries and inlet types is therefore to present Levell data in Appendix
needed. Appendix A presents hydraulic data A.
for four roadway reserve and i nl et combi na-
tions which, together, account for the bulk LEVEL 2 Flow/capture relationships derived
of Australian practice. from one set of test results ob-
tained for a particular inlet case
In most cases the following data are (model or prototype) supported by
presented:- results obtained for inlet cases
(models or prototypes) having diff-
(a) roadway reserve (half-carriageway) flow, erent geometries. Broken lines or
Ot, versus longitudinal slope, So, limit- curves with long intervals between
ed by Criteria 1 and 2 of Section 6.1, breaks are used to present Level 2
text (see eqns 6.10 and 6.11). Data are data in Appendix A.
presented for carriageway half-widths of
4.0 m and 5.0 m, Zb = 25 - 30-40. These LEVEL 3 Flow/capture relationships inferred
data are needed to pl an major drai nage from test results obtained for
systems (see Chapters 8 and 9). inlet cases (models or prototypes)
having different geometries.
(b) half-carriageway flow, Ot, versus longi- Broken 1i nes or cur ves wi th short
tudinal slope, So' for spreads of 1.0 m, intervals between breaks are used
2. 0 m and 2.5 m, Zb = 25-30-40. to present Level 3 data in Appendix
A.
(c) grat ed inlet data , Zb = 25-30-40 :
In short, Level 1 data may be regarded
o on-grilc1f' inlets, full gutter wi dth as 'dependable', Level 2 data as 'satisfac-
(undepressed), capture 80% and 95%. tory' and Level 3 data as 1 ittle better than
informed guesses. A side benefit of Appendix
o sag inlets,Lig = 1.0 m, 2. 0 m (un- A is its indication of the directions which
depressed), capture 100%. inlet test programmes should take in order to
improve the reliability of urban drainage de-
(d) side-entry inlet data, Zb = 25-30-40 : sign in Australian practice.
Data items (b), (c) and (d) above are The mai n di fferences between the four
needed to design minor drainage systems (see roadway reserve and inlet combinations add-
Chapters 10 and 11). ressed in Appendix A relate to their roadside
channel geometries (see Fig. 3.7). These
The data relating to inlets are not of are: -
equal quality. Some graphs and tables present
results obtained from substantial test pro- TYPE 1 concrete gutter, 300 mm wi de, cross-
grammes conducted on full-size models while slope Za = 10
others present information inferred from
tests on mOdels having different geometry.
Three levels of data qua lity have been recog- TYPE 2 conc rete gutter, 375 mm wide, cross-
nised:- slope Za = 8
TYPE 3 concrete gutter, 450 mm wi de, cros s- N.S . W. (l979); Earley (l979); Burgi and Gober
slope Za .. 12 (1977); Storm Drai nage Research Committee of
John Hopki ns Uni versity (l956) ; Henderson et
TYPE 4 : no gutter, pavement carried to kerb al (1980) ; Willing and Partners (l978); Hughes
(1974); Public Works Department, N.S.W.(1985} ;
All data for each type and combi nat i on Forbes (1977) ; United States Department of
are presented together. Transportati on (l979). Additi onal data have
been obtained from full-size rig tests conduc-
The following references form the liter- ted in connection with preparation of the
ature data base for the graphs and tables set Handbook at S.A. Institute of Technology in
out in Appendix A : Department of Main Roads, Adelaide.
Zb = 25 - 30 Zb = 30 - 40
95% capture : 95% capture:
gutter approach fl ow, Qt = 10 Lis gutter approach fl ow, Ot= 8 Lis
TABLE Alb
CAPTURE AT 1.0. AND 2.Dm SAG INlETS (GUTTER 300..)
(DATA QUALITY - LEVEL 2)
-- -
DESCR I PTI ON Zb = 25 - 30 Zb = 30 - 40
loOm grated inlets (undepressed)
allowable spread = 2.0 m 40 Lis 29 Lis
allowable spread = 2.5 m 59 Lis 42 Lis
Notes:
1. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.
1100
Kerb&Gutter I: . ,: ~
_\ ;:::2:::]' Zb = 25,30 or 40
--,
i 1100
Kerb& Gu lle ; 1
_:;:;:2:::'::f
--
Zb = 25,30 or 40
J
I
f/ ""r--, Za = 10
(each casel Gutter/ Pavemen t Profile jj ~ Za=10
(each case) Gutter/Pavement Profile
g ""'-
~ J WI'\. ~
~ /
900 900
J / "'" .......... ~ ~
'"
..........
II/I ~ "'"
IIrl ~,~
i'-.
~
.............
I'----
~
~
b r!-.J t:
~,
~
r--
Ci 800
~
U:: 700
~
lg'600 'I I
i'--
I II ~ " ~ ~
~
.............
""
-............
r. -
7~
~ 'O 2 ~-
200 0 -01
I
-02 -03 -04 -05 -06 -07 -08 -09 -10 -11 -12 01 02 -03 -04 -05 -06 -07 -08 -09 -10 -11 -12
Gu ller Longitudinal Slope, So Im/ml Guller Long itud inal Slope, So Im/ml
Figure Al a : Hydraul ic ca pacity, Q.t , data for 8-0 m carri agewa y - Figure Al b: Hydraul ic capacity, Q.t, data for 10 -0 m carriageway
with 300 mm gutter with 300mm gutter
120 120
Gutter Inlet Hydraulic Oata Gutter Inlet H ~rau1i c Dat a
Capt ure performance of lOrn and 2-0m side- entry Capture per formance of "O m and 2 'Om side-entry
in le ts 'W it h and with out deflectors inlets with and without def lectors
11 0 110
~
,.I i
N
TYPE 1
"
I .~
N
E 150mm
:_:~ .. --~
Za =10 -'l
100 100
:;'" Zb= 30-40
Gutter/Pavement Profile Gutter/ Pavement Profile
~OTES NOTES
90 90
!L~ l.Inlets without deflectors ; lip deprf'ssed SOmm bet o...
gutter invert fel" fu ll length.li.s.
0 1.lnlets wit hout deflectors ; lip depressed 50mm be 10'"
gutter invert for full length.li.s.
H-I'+-I""--t--t- - t---
J ~_ N 2. lnlels witI'! def lectors: lip depressed SOmm, deflector
IL~
2. lnlets with def lectors : lip depressed SOmm, deflector
base depre ssed 100 mm below gutter invert . E fI base depressed 100 mm below gutter inver t .
1 1
60 80
IJ.: [ :7 3. App roach flow,Ot for inlet 21ength , Lis. other than 1·0 m
'"" €/ 3. Approach flo .... Ot for inle t 1lenqth . Lis. other than ' ,0 m
I-tHr"
I--f"I'--+ - +--I an d 2·0 m varies as ILL s t, appro)o mately.
<::
~
I! 4. tnle t widt h equals gutter width in all oases . <:: ~/I~
and 2·0 m va r ies as Ills l, approximaiely.
4. tnle l ... idth equals gutter width in all cases .
70 70
<0>
~ f c;
~
'Ii
3:
~ z
60 60
~ ~
r r
'<t
&'
:l: 50 0% Captu le
'<t
&'
:l: 50 .1
.:! .:!
'#-.
~ ~ W '"..-- :-
~
40 , ~
40 - f__- I-- f - f-- - ~O% aptu
~
~
-,
~
30
~
30
"'" I~ I
20 I
t
b :Z
........ ,
~~
"-
,,~
~ ~ "-
' . iX
~~
....11,
Q~
-- r - r-
--
\:,v-- 8O~ c.-=- :::-:... :::::-::.
-'-- BO,
""""" .!!CL
~
~
-
10
1/ ~- -....§. % (a
-:-!.: ..£a.2,!
~ I!!.J, ~ '- '- '-
- L ~ ~o/'!... a1!!.ur n-~-~---_ L _r-_=- _I- I \: ~ --
~
2l~ ~t!!! e _ ;;1Z --
o o~-'--:-,:-:--\-,,",V~-'----'--...l:..-~-,-r_---L-_--1
-_-'-_-_-"-'-
~ -.:..:::.cf--=-.=l
-=-:..
- -:::L:..::..;.J o --=- r - - r- - --- =-
0-02 0-04 0-06 008 0-1, Q 11 0-", o 0-02 0-04 0-06 0-06 0-10 0-12 0-14
Figure : A1c Collation of spread and gutter inlet hydra uli c Figure : A1d Collation of spread and gutter in let hydrau li c
data - 300 mm gutters, Za =10 data - 300 mm gutters, Za = 10
TABLE A21
CAPTURE BY 37~ GRATED IILETS ZI .. 8
(DATA QUALITY - LEVEL 2)
Zb = 25 - 30 Zb = 30 - 40
95% capture:
I 95%capture :
gutter approach flow, Qt 24 LIs I gutter approach flow, Qt 22 LIs I
80% capture:
gutter approach flow, Qt = 52 LIs
80% capture:
gutter approach flow, f)t 43 LIs I
Notes: 1. grated inlet - full gutter width with transverse bars
2. length not less than 0.75 m
3. grating open area not less than 60% of total area
4. gutter longitudinal grade, So, not greater than 0.05
5. grated inlet not depressed ; no kerb opening
6. Listed flow values are conservative but make no allowance
for blockage.
TABLE A2b
CAPTlItE AT 1.0. AND 2.0. SAG IILETS (GUTTER 31.>
(DATA QUALITY - LEVEL 2)
DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undepressed)
allowable spread = 2.0 m 40 LIs 30 LIs
allowable spread = 2.5 m 61 LIs ~~ L/5
2.0 m grated inlets (undepressed)
I
allowable spread = 2.0 m 63 LIs 47 LIs
allowable spread = 2.5 m 96 LIs I 69 LIs
Notes:
l. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage . I
2. Grated inlets - 375mmwide
3. Grated open area not less than 60% of total area.
I
I
1~r-~--~--~--r-~-----37-
5-------
3 -
61-
5m--to--l----I--~ 1300
375mm H15m to l J
1100 ~_-i-_+_+_-L_--' "., J mm Hotmix pavement 1200
Concrete-+'; ~J Hotmix pavement
i
Concrete --+,:
Kerb&Gutter ;' ...-<:+--:===::;;:;;~:::::::::==:i
,., I Kerb&Gutfe, .';fg . I I
1100 - - ---I-- . :i.,::22:::J Zb = 15,30 or 40 1100 Zb = 15,30 or 40
~
_
900 ~~/ . ~"
_ '"
-
"""
-. ~TE ~l~-;.;b
l carriapeways. redu ce
·ind ic at .d flow values by 1, % 5
900 -
!/ "-
l/ \ \.
~DTE , or ttu h sea carri geway reducF
ndicat d flow values by 15 ~.
---r----- ---- -
500~~~~·~~~---~1-·~~-+--~~~---+---r---F~~ ~
__ 500 ~ '-----4 -30
' ---
~
400 --
I! --~Rl--r--r--..
__ ___ 400
1//, ------
~
~ t--
Ii I I --r--....L. I
'/ ! r--
I
- - r-.
300 f i 300
I
100 0 . 01 ·01 03 ·04 ·05 ·06 ·07 ·08 ·09 ·10 11 ·11 01 01 03 04 05 06 07 08 09 ·10 ·11 11
Gutter Longifudinal Slope, So Im/ml Gutter Longitudinal Slope, So (m/ m)
Figure A2a : Hydraulic capacity. Ut. data for 8·0 m carriageway Figure A2b : Hydraulic capacity, Ut. data for 10 ·0 m carriageway
with 375 mm gutter with 375 mm gutter
TYPE 1 TYPE 1
"I i
1S0m~_.".;.._ _ _ _ _ _ _ __
::. ~;;? 'I Zb=25-30 Zb~ 30 - 40
Gutter / Pavement Pro f ile Gutter/Pavement Prof de
N T IiQlI.S
180 0
tlnlets 'WItt-out deflect ors : lip de;l;;~~ed 50mm bel o.... . ~ : . Inlets without deflect"" lip dep'essed SOmm belCl'"
gutter invert for 1ull length.li.s . gu tter invert for full l ength.l~s .
12 Inlets with de1iectors : lip dep ressed I)Omm, defl ec tor [2. lnlets wi!h deflectors : li p depressed SOmm, deflec tor
base depressed 100 mm bel ow gutter IO vert base depressed 100 mm belo.... gutter in vert
160 0
1
3. Approach ftow: Qt. for Inlet ie ngth, l i s. other than 1-0 m
and 2·0 m vanes as Ills l. app rOXImately.
4. lnle t WIdth equals guller Width in all cases .
0 ~/
z
110 ~ 120
ff
~
or
,~ :
<{
:;'" ~
I 100
I fI
"""'"
~
80 '" 80
I IAr;; "" """ .......
i I '-V
I 'ii'",
,
~ =>
'" I ,,' <:> V"
~~
~
2~
ani,
:::::::::: 95% (aptu e
60
60
b$ .:..~ """
"'"
11<_
'-.... ~
40 ff "- --........ ~
.........
11/ . ~
~ ~ ~", 'E ~
10
/
'>t ~~.......
K J-.ZS· \: t} -- t--
~ K:" r--- N % Ca
~
~ ~~
0
0 0·01 0·04 rJ06 OOb rJ1f. (J1l (I V.
o
o 0·01
--- L
\.
0·04
" 5% a fur
0·06
'-1.
0·08 0·10 0·11 0·14
Figure : A2c Collation of spread and gutter inlet hydraulic Figure : A2d Collation of spread and gutter inlet hydrauli c
data - 375 mm gutters, Za =8 data - 375 mm gutters, Za = 8
TABLE A3a
CAPTURE BY 4~ GRATED INlETS Z. 12
(DATA QUALITY - LEVEL 1)
1
Zb = 25 - 30 Zb = 30 - 40
95% capture: 95% capture:
gutter approach fl ow, Qt = 23 Lis gutter approach flow, Qt = 22 Lis
TABLE Alb
CAPTURE AT 1.Om AND 2.0. SAG INLETS (GUTTER 45nm.)
(DATA QUALITY - LEVEL 2)
DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undepressed)
allowable spread = 2.0 m 41 Lis 29 Lis
allowable spread = 2.~ m 63 L/~ 45 Lis
Notes:
1. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.
2. Grated inlets - 450 mm wide
3. Grated open area not less than 60% of total area.
________________________________________________ 1
1200
(o ner.t,
Kerb & Gu tt , ; ;
.T J "" .'
Hotmix pa ve ment
i
I
1200
(o ner.t • .'iC J Hotmix pa vement
i
1100 ;i~' Zb ~ 25,30 or 40 1100 --,.1'" Kerb & Gutt';1 :1¢ v
Zb:25 , 30 or 40
I
!::~ '\
Ii?
Za ~ 12 Za = 12
Ji {each casel Gutter/Pavement Profil e l each case I Gutter/Pave ment Pro file
900 ~
§
"'~" ~ ~
- --r= 900
iJ
'" r-.....
~
~ iI ~ I ~ "-
(
1 7b600
l/;'/ ~
-"-
~<'
~-4.« ~
~V
~
'ru--
----- -
u:,.. 700
~
~ 600 Lrl "" "'" ~ "'-
~
'6_
'0"--£. ~
-----
--
"'- .......
~
5 f//
500
V ---+- - ;----
500
ij
...............
'--.......<' < ><
---- -----
r---
-r--
400 f-- f-- -
NO TE , For fl sh sea carri eways redu(
----- - ; - - - 400 -
NOTL For fl sh sea carri gewa ys reduc
r----
300
I indica ed flo va lue by 1 %
300
ndica d flo value by 1 V.
TYP E 3 TYP E 3
1
' 60
1; '40
?j 3. Approach flo lo', Qt. for inle t llength,l i s . ot her than 1-0 m
and 2·0 m varies as ILL \ 1, apprOlO mate\y.
4. lnle t width equals gutter width in all oa ses.
.
~
' 40
;I'l
3. App roach flow, Qt, for inlet 2lenqfh, Li..s , other than ' ,0 m
and 2·0 m vari es as IL L 5 I, ap pr oXI mately.
4. lnl et WIdt h equals gutter width in all cases.
i5 :>:JI i5
1
z
120
,;t- hL 80"1. Capt re ~
z
120
q
::"
o/l ............. ~ ::"
r;..........
r
i --- h
I
1lO'I. aotur
~"""II
I
--
';;/. 80~ Ca ur ......... W
f 100
I~
S
100
:---
S
l :if II ~
I it '" 8• Ca otu e ~
~ 1'.§
~ ~
I il~ ~
cr 80 cr 80
=>
'"
60
I I 'if- r--
'j~
1/ , .... ,
-- 95·
95·~
Ca ure
Ca ure "\
~
-:u
~ =>
'"
60
I fIJi
I [I
ff ,;¥
---
'.i !
I I--.
,95%
9 • Ca
(, ptu
ur.
\.L.
~
~2_
-- -- --
'/ kV ~
...... - "---> 2b!r ~~~
/ V..-:1 .....
- "- --''- ~I!i.' --
~
20
2. ~ -- -- -- r=::;. --¢. ~
......
.LI 20
.,/.~ ~'"
'* 1' ...... --'" ~£,
o
o 0·02
-- tt bQ" - --
0-04
- -
€Q.~ Coot
- ~.~ ~~ .~\
0·08 0" 0
95% ~t u
0·12
-
e
c--- f-- -
~'4
o
o 0'02
-R:; 0·04
1- _ ~ % C.ot
0·08
~e
~ r - -- - - - - -
-::::!",-
-~ ~
0" 0 0·12
~
~' 4
GUTT ER LONGIT UO INAL SLOPE So {mimI GUT TE R LONG IT UO INAL SLO PE So (mimi
Figure: A3c (ollation of spread and gutter inlet hydraulic Figure : A3 d (ollation of spread and gutter inlet hydraulic
data - 450 mm gutters, Za = 12 data - 450 mm gutters, Za = 12
TABLE A4A
CAPTURE BY soo. GRATED I ...ETS : NO GUTTER
Zb = 25 - 30 Zb = 30 - 40
95% capture : 95% capture:
gutter approach fl ow, Qt = 10 Lis gutter approach fl ow, Ot = 6 Lis
80% capture: 80% capture :
gutter approach fl ow, Qt = 26 Lis gutter approach fl ow. Ot = 17 Lis
TABLE A4b
CAPTURE AT 1.0. Aft) 2.0. SAG INlETS (NO GUTTER)
I I
DESCRIPTION Zb = 25 - 30 Zb = 30 - 40
l.Om grated inlets (undep ressed)
allowable spread = 2.0 m 41 Lis 30 Lis
allowable spread = 2.5 m 63 Lis 45 I I"
2.0 m grated inlets (undepressed)
allowable spread = 2.0 m 62 Lis 44 Lis
allowable spread = 2.5 m 95 Lis 68 Lis
l.Om side-entry inlets (depressed 50 mm)
I
allowable spread = 2.0 m 31 Lis 23 Lis
allowable spread = 2.5 m I 44 Lis 31 Lis
2.0 m side-entry inlets (depressed 50 mm)
allowable spread = 2.0 m 62 Lis 46 Lis
allowable spread = 2.5 m 88 Lis 62 Lis
Notes :
l. Flows listed above have been calculated using eqn (6.12), text,
modified by behaviour observed in full-size rig tests. Listed values
are conservative but make no allowance for blockage.
2. Grated inlets - 500 mm wide
3. Grated open area not less than 60% of total area. I
I
-:J
i
i
1400
~ ~
(omret~l
Kerb -:'.
Hotmlx pavement
S i
i
1300
~
" /r Zb : 25 , 30 or 40 1300
- ;:1" Zb,25,300r40
Gutter / Pavemen t Prof il e
1200 -~j
"'- Gutter /Pavement Profile
"
~I / "
"'" I\.
~
"'~ ~
/
1100 fl !\
/
~
~
'/\ '"
I'-.....
0- 1000 0-1000
r-- ~ -l-ffu
lo'
u:
~
~
~
900
// I
I~
~
~
--- ~ ~n
<0 '
r,_
0 """'- ~
r-
lo'
u:
~
~
~
900 P I"'~" ~ ~
~
l b' 6-" ,
---
g. 800 " ~ 800
~ 700
;;;
x
600
I
I
~
'--
~
. 2'
%
-
-----
r---
I--
--
-
~ 700
600
1/
'" i"--.
by 2 %
~
'25
I-
- ---
I-- I---
I--
I-
SOO SOO
-12 01 -12
Gu tter Longitudinal Slop e . So Imlm) Gutter longit udinal Sto pe , So (m/m)
Figure A4a : Hydraulic capacity, at , data for 8-0 m carriageway Figure A4b : Hydrau li c capacity, at, data for 10 -0 m carriageway
no gutter no gutter
12() 120
Gutter Inlet H~rauli c ·Oata 1 Gutter In tet H~raul ic Data
~
N
~ TYPE 4 d TYPE 4
~ F~
N
lS0 mm "> :
100
e
N
" ~
II ;r Zb,25-30
-, 100
'"" >r lb ,30-4O
-:J
- -- ""f
1m II
90
y r-...!.
90
- - - - m
m
(I I 1m/ , / " If r--.. r-,3
SO SO
'0.
I "~ I ~ f'.... m VI ~ :---..... 4m
• I'---
,
-.......
5 70 L leulter
ngt of d press d
up str amI.
5 70
/ / 'P llJr
I'--- ........
~
eng! of d press d
c;
7!1
" II ~e fer o Fig bela
...........
~
~
a
WI; fc-- ~utt.r upstrami
-
0k
~
IRe or o Fi He ...........
3
60
;! It z
60
<-< -
-
m ~
~ ~!It;;
i3
lm
WV ;S; r- ur. r-.,41n
i3
1m 3m
4
r-- r--
IV
--I--. ----
X-
~ 5m ~
lm. /
./ c plur. ~
~
g' 6m
Q. 50
• ....6m 50
«
Om I ' -Om
«
ltv
~
~
L /5=2 Om
'" 11 '/
40 40
'"w I ~ 300m nl '"w /I W
-
~ ~
10 m
4
~
:>
G
'" r- ;
30 I n??:,,:/
75 mm depressio n
:--==
Zb ,00\
~a~t.
..
~ \ - 30
/
Sectio n at inlet -
20 ./ ~ 10
/ -
- '\: ;)Y ;'Y- ~ ~ /
- --
~ y NOTES
.'~"'
!iQ.ill
o o
o 0-02 0-06 O{)S 0-10 0-12 0-14 o 0-02 006 O{)S 0-10 0-11 0-14
Fi gure : A4c Collation of hydraulic data for 2-0m inle ts in single Figure : A 4d Collation of hydraulic data for 2-0m inlets in single
cross slope (no gutter) carriageways - Zb =25- 30 cross slope (no gutter) carriageways- Zb = 30-40
DESCRIPTION
Catchment data transferred from Table 1 to
n
Table 4 form the base for cal culating maximum
des i gn flows in all primary drainage lines.
HYDROLOGICAL ....»-
n
-J SURFACE
The table also includes provision (Remarks :I:
co lumn) for listing gutter inlet type/ s ize CLASSIFICATION 3:
rrI
selections made for DETERMINATE drainage
lines. Catchments in Northern and Intermed- (J)
AREA. OR . ....z
iate Australia (see Section 5.3, text) which EQUIVALENT AREA
0
include residenti al components show two run- TYPE OF CONTRIBUT'N .,.,
rrI
design
Table 8/9 brings together catchment data sel-
ected from Table 1 and design flows collated
from Tables 4 and 6. Its layout enbles pipe
sizes to be selected and hydraulic grade line ,.,.,
~
..... 3:
computations to be performed. The Remarks 0-
»-
column is used to record junction pit invert ~
;>0;;
levels subject to possible downwards correct- VI
ion as part of the final design process. De-
signers must select an appropriate value for
the Darcy-Weisbach friction factor, f, to be
inserted into the heading of Column 17.
Values of f are listed in Section 6.7, text.
-:i
('I)
a:
TABLE 6 FLO.... ESTIMATION IN MAIN DRAIN PIPElINES: N~ -YEARS en
TIME OF ENTRY (OMPONENT PROGRESSNE IRAINFALL INTENSITIES
CO
(OMPONENT TRAVEL (HANNEL DR U/G i.n mm/h FOR
CUMULATIVE a:
SUB-AREA COMPONENT TOTAL CRITICAL MAINLINE FLOWS a:
TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL STORM PROGRESSNE CRITICAL COMPONENT UMULATNE FROM TOTAL <{
en ..... UNDERGROUND PIPE . NODE PIT TIME TO DURATION STORM URATION IN
UPSTREAM
t- a. overland allotment ~utter or u/ground NODE PIT IN TOTAL TOTAL UPSTREAM (CA)n
Z .2 (CA)n (ATCHMENT
w
~
.....
z<:l
.... 0
:l:;z
'"
.....
-'
-<
z
<:I
.....
~ c
0'-
~ ~
. flow drain natural pipe
channel travel
UPSTREAM
AREA
CATCHMENT AREA ct
'"
0:
Qn= ((~)~6ln Us
REMARKS
I ..... :r «
z t-
zuJ
Z
2 -o
u
-<
-u... --
.!'''C (analysis) (analysis) 1ull-area part- area ct ~ (analysis) (anal sis) full-area part-area
'" ..... ....
z .U (5 \:> U
E u
() t- c e c E, c tull- part- tull- part- analysis analysis
a. :> c e
.- ., E ·E , full- .part- full- part- analysis analysis
uJ
, 'E, c ...•
--.
c.. E c
t- :l:;« 0: Z
- -' u ""QI
E ·e
:r u «,
<{
() ueri CD . 0:
r
.....
0
a.
:l:; . U
c:: 0
c::
<:I
-<
u...
VI
VI
«
'E
00 ~ .. . E .z::
' c. ' ' "" ~ , , .z::
E E
QI c. - '
area
' lc area area area In for In for
Uc
.area area ar~a area Qn tor On for
-
0:
c o E c ~~
VI 0> c.QI
r 0=
c QI
tc t N= years N= years
3~ ~ z o . ~ ~ E c - E li i N= years N= years
.... ~
uJ -'
Z VI U <:I :r VI u
min .!!! ,..;;:;:: t.!!.;: QI QI .!!;
min. min min. min. ha. ha. ha. ha. ha. LIs lis
<{ 24
1 2 3 4 5 6 7 8 911 11 12 13 14 15 16 17 18 19 20 21 22 23 25 26 27 28 29 30 31 32 33 34
co
a:
:::J
~
~
<{
~
en
z
z
Cl
en
w
o TABLE 4 FLOW ESTIMATION IN PRIMARY DRAINAGE LINES: N,. -YEARS
w
Cl TIME OF ENTRY COMPONENT RAINFALL 4-
)( PRIMARY
<{
z PRIMARY DRAINAGE COMPONENT TRAVEL CHANN.EL OR U/G TOTAL INTENSITIES Lnmmlh. GI
CONTRIBUTING AREA ....
TIME TO CHANNEL OR PIPE TRAVEL TO TRAVEL ==
..0 z
COMPONENl e
z
~ CONTRIBUTING AREA FOR STORM .r.
~
TOTAL FLOW ::i
....
a: t- UNDERGROUND PIPE ENTRY POINT TIME TO DURATIONS WHICH c
::l AT NOMINATED c'-
."
REMARKS
o .E (CAIn
overland allotment gutter or IU/gr~und 3~
ENTRY CD
Cl. ARE CRITICAL 4-
ENTRY POINT
~ w 0
..... co flow . drain natural pipe POINT
u
GI c: an = (CAIn Ln LI
l:)t- (Gutter inlet
a: t-
C
Z e Z '- .- channel travel VI t-
z :z::1:
ot- w
:1: z t- Z
-J
< 0
o '- '" (analysisl full-area part-area ....< GI
ell (analysisl e
U
0.36 s t -~
- selections for
- ~
U ,-'0
z ell VI full-area part-area
en t-:I:
zu < -0 t-
zW 0
- l:)
..............
u ..... co
o u .... ::> GI e ~E .-c e c e analysis analysis 0:
< .... analysis analysis ~-
.... .DETERMINATE
....L U c: E, e (T'I
W t-
, .~ full- part- $2
~ 0: Cl.
z -0:
Cl. -'
, E , . 'E
E, .c. e
, u
.... 0:..0 lines included
..... ell GI, .c.
<, >- ~~ 'E .c. E E area area tull- part-
, ell C. , , .....0> , '
e u..
< V) ....
:I: , 0
Cl. u 0: 0 .c.
..... ion for ion for .E Cl. Cn for <ell
an for Cl.
-
V) 0 _
-_
'-'CD CD 0:
:1: C 0: < 0 - 0>
:g - ell c -- ell tc t ·I area area >- N= years N= years L~ - here I
t-:J :;:) t-
z 0
V)
u.J >- :J -J '- nl co
0>
E cIII ==E ..... c - E ell '" .- E N= years N= years "c . t-
;:)V) V) u.J U c :z: V) u
min. ~ 0;; .....
1'0 .-
~ ~z
- ..... min min. ha
u
ha. ha. borC LIs LIs
Ot-
'-'-
1 2 3 4 5 6 7 8 9 10 11 1213 14 15 16 17 1819 20 21 22 23 24 25 26 27 28 29 30 31 32
<D
C\J
STORM DRAINAGE DESIGN IN SMALL URBAN CATCHMENTS
-lo
N
I CATCHMENT
SUB- CATCHMENT
\JJ SUB-AREA NODE PIT
JUNCTION PIT AND
~I
GUTTER INVERT R.L's
COMPONENT
t..nl
DESCRIPTION
~ 3 Kw ( 0/'2g J ,
-
):>
~
-..::r
..
,.."
<
,
, -4 ,.."
rn
~ ;:0: rn
~ 13 0- I //\ ~ V1 V1
. CD -4
:j
,~ "'Icf=
0.0
'-----'
Io.l
-0
-u
~ 13 AWL :nus BWL
rn
o
};
~ 13
~
rn
0-
.
l>
,
~
I
CD .\V
-......
::r
Vi
-4
rn
V1
-4
~
rn
-4
,.."
::0
0; ~ · 0 V1
0 '" QO
-<
,~ ,~
III In
V1
r=r OJ Vl
o VI
~ VI
~ _ . ::0
o 0.0 ,.."
Z
3 ~ 15 II
N -S~):> I
~ =+"0
. =+ ::0
;:0: -<
I'T1
~ - Vl ):>
OJ .:
~ OJ ::0
...,
m m
-..., V1
iii' ro
< m
m <
Ao junction pit outflow pipe area junction pit headloss (water level)
(= 1TD~/ 4)
H.G.L. hydraulic grade line
pervious drainage unit area
average rainfall intensity (mm/h)
AEP annual exceedence probability (years)
average rainfall intensity,
ARI average recu rrence i nterva 1 (yea rs) ARI = V-years
AR&R 'Australian Rainfall and Runoff' i average rainfall intensity,
10'1
ARI = 10-years, duration = 1 hour
AWL junction pit assigned water level
(see Fig. 6.12) k pipe boundary roughness (mm or m)
BWL junction pit bottom water level 1/2
(see Fig. 6.12) K coefficient of So in eqn (6.9),
Fig. 6.2
C runoff coefficient
hydraulic conductivity (m/s)
Ci runoff coefficient - impervious area
junction pit headloss coefficient
runoff coefficient - pervious area (water level)
weighted runoff coefficient length of overland travel as shallow
[see eqn (4.7) ] sheet flow (m) (see Fig. 5.3)
Cy runoff coefficient, ARI = V-years limit of overland travel as shallow
sheet fl ow
(CA) equivalent impervious area (ha)
L carriageway or pipe length (m)
d triangular channel flow depth (m)
Leff effective length of drainage path
kerb-side flow depth (see Table 1, Chapter 11)
pavement edge flow depth Lig grating inlet perimeter (m),
excluding kerb
di gutter sag inlet water depth above
lip side-entry inlet opening length (m)
D pipe diameter (mm or m)
M-years design ARI for major system 'gap
junction pit outflow pipe diameter flow' (see Table 5.2 A & B)
Og gutter flow to junction pit via inlet T.N.P. terminal node pit (see Section 7.1)
T.N.S. terminal node section
Ogap 'gap flow' (see Section 5.4) (see Section 7.1)