Professional Documents
Culture Documents
Petroleum Regeneration and Processing Facility - Phase Ii: Employer'S Requirements
Petroleum Regeneration and Processing Facility - Phase Ii: Employer'S Requirements
Petroleum Regeneration and Processing Facility - Phase Ii: Employer'S Requirements
EMPLOYER’S REQUIREMENTS
Prepared For
ECOMAR ENERGY SOLUTIONS FZC
MUCOG-192805-ER-MEC-001 Rev. 1
30th January 2020
"This document contains Confidential/proprietary information belonging to Company (MUCOG) or its affiliated
companies and shall be used only for the purpose for which it was supplied. It shall not be copied, reproduced or
otherwise used, nor shall such information be furnished in whole or in part to others, except in accordance with the
terms of any agreement under which it was supplied and with the prior written consent of Company. MUCOG makes
no representation of the accuracy or reliability of any information or opinion as may be contained in any report that
doesn’t bear the authorized signature and official stamp of the Company.”
I. REVISION HISTORY
30 January Re-Issued
1 N/A 72 MA JF JF
2020 For Tender
14 January Issued For
0 N/A 68 MA JF JF
2020 Tender
Total
Revision Date Description Pages Affected Prepared Checked Approved
Pages
1 Introduction ........................................................................................................................... 7
14 SiTE FACILITIES.................................................................................................................. 21
a) Five Storage tanks with approximate working capacity 47,550 cubic meters.
b) Extension of existing Utilities and Fire Protection for the 5 (five) Tanks.
Phase II facility shall be equipped with all the required safety systems in conformance to applicable
local statutory requirements, applicable international codes / standards and best engineering
practices.
This document gives relevant Project information, functional, quality & performance requirements
and safety & environmental requirements. This document shall be read in conjunction with the
relevant other Project documents such as but not limited to the following: datasheets, technical
specifications, drawings and all reference codes & standards including all local statutory
regulations.
3.1 DEFINITIONS
TERMS DEFINITIONS
The selected party, firm or company awarded and named
Contractor
in the contract to undertake Detailed Engineering,
Employer/Client Procurement
Ecomar Energy andSolutions
Construction
FZC (EPC) of the Project.
Employer’s Engineer MUC Oil and Gas Engineering Consultancy
ITP Inspection & Test Plan
Loading Product transfer from Storage tanks to vessels/trucks
Is to be understood as mandatory in relation to the
Shall
requirements of this specification.
Is a strong recommendation to comply with the
Should
requirements of this Project
ASME B16.20 Ring Joints, Gaskets and Grooves for Steel Pipe Flanges
ASCE/SEI 7-05 Minimum Design loads for buildings and other structures
6.1 General
Scope of works include but not limited to the FEED verification, detailed engineering design (to the
extent as may be required under the provision of the Contract), procurement & supply, safe storage,
erection (including all the temporary works), installation, inspections (including SAT, FAT etc.)
painting, insulation, coating, testing, pre-commissioning, third party inspections and certifications,
third party testing, calibrations of the tanks, calibration of the piping, commissioning assistance, Civil
Defense & local Authority Approval and Certifications, FOIZ QHSEMS regulations and required
document submissions to FOIZ and remedying any defect therein.
Contractor shall conduct a technical survey of site and submit a site survey report for Client’s review
and record.
Contractor shall ensure that a legible copy of each certificate, bearing original signatures (of client /
third party) shall be preserved for incorporation in the mechanical completion dossier.
7 FACILITY DESCRIPTION
The Facility shall be designed to meet the requirements of all the applicable international codes and
standards, local statutory requirements to achieve highest functional performance standards,
including safety & environmental performance, efficient & flexible operations throughout the Facility
life cycle.
The following sections presents synopsis of the respective facilities that shall be considered in the
design by the EPC Contractor.
(*) Properties extracted from Phase I - Process Design Basis for Tank Farm area Doc .No.903-T-R-
121
Storage
Tank Tag Dia. (m) x
Service Type Side Entry Jet Nozzle Capacity per
No. Ht.(m)
mixer Tank (m³)
30-TK-201/
Feedstock 28 × 20 AGDR+IFR Yes No 11,536
202 /203
30-TK-204/
MGO 21 x 20 AGDR No Yes 6,471
205
AGDR – Aluminum Geodesic Dome Roof, IFR – Internal Floating Roof, Dia. – Diameter, Ht. - Height
(*) Extracted from Phase I - Process Design Basis for Tank Farm area Doc .No.903-T-R-121
(**) Extracted from Phase I Piping & Instrumentation diagram for crude feed pumps 172804-SSEW-
PRO-R-048
Existing user tapping connections shall be utilized from Phase I (utilities) compressed air/ instrument
air distribution network for tanks TK-201/202/202/205.Tie-in shall be made from nearest existing
header to supply Plant Air & Instrument Air connection for tank TK-204.
NITROGEN
The existing Phase I nitrogen service connections shall be utilized for the new tanks TK-
201/202/202/205 service needs. Tie-in shall be made from nearest existing header to supply
nitrogen service connection for tank TK-204.
Service water shall be supplied to the Phase II tanks TK-201/202/202/205 by existing Phase I
service water connections. Tie-in from the Phase 1 service water distribution network for tank TK-
204.
SLOP SYSTEM
Pure product drains like from pipelines shall be routed to existing CBD vessel 51-V-601 vide tie-in
with nearest slop header. New tie-in connections shall be made as per requirement during detailed
engineering. TRVs drains provided near tanks shall be routed back to respective tanks.
OWS SYSTEM
Oily water generated by the Feedstock & MGO tanks shall be routed to existing OWS system &
shall align with Phase I philosophy. New tie-in connections shall be made as per requirement during
detailed engineering.
Feedstock /BO and MGO is received from ships through the jetty pipe lines from Fujairah Port
to Phase II facility.
Loading of BO from Phase II tanks 30-TK-201/202/203 to ships is envisaged using existing
Phase I BO ship loading pumps 30-P-101/102.
Loading of MGO from Phase II facility to ships is envisaged using existing Phase I WO ship
loading pumps 30-P-103/104.
The feedstock stored in Phase II tanks shall serve as feed to refinery by using existing Crude
Feed Pumps 20-P-101A/B.
Truck operation with respect to BO from Phase II tanks 30-TK-201/202/203 shall be carried
out using existing pumps 30-P-501/504
Both truck loading and unloading is envisaged for MGO and to be carried out utilizing existing
Truck Pumps 30-P-505/506.
A. The following sections provide overview of the objectives of the Employer’s Requirements for the
Project. The requirements mentioned herein are not exhaustive; hence the Contractor is obliged to
read the provisions and requirements herein mentioned in conjunction with other Contract
Documents.
B. The Employer’s Requirements as furnished in this document set out the functional, safety,
operational, quality and performance requirements for the Works, in addition it defines the primary
criteria for the FEED verification, detailed engineering design, procurement, inspection,
construction, installation, erection, testing, pre-commissioning, commissioning and remedying any
defects therein under the provisions of this Contract including reinstatement or defect replacement
in mechanical completion, punch-listing, pre-commissioning and commissioning stage.
C. Listing of Scope of Works does not necessarily imply completeness of the listing of the work items
to be carried out by the Contractor. The Contractor shall execute the Works in accordance with the
intent and meaning of the Contract Documents and the Employer’s Requirements and shall supply
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
16/72
all accessories and other items including the material essential for the proper execution and
functioning of the Works pursuant to the provisions of sub-clause 4.1 of the Conditions of Contract.
The Contractor shall be responsible for the completeness of the Works in every respect complying-
with engineering design specifications and Scope of Work, up to entire satisfaction to Client and
Clients approval or acceptance/ handover as applicable.
D. The Employer’s overriding requirement is that the Works are fit for the purpose of, and suitable in
all respects for safe, efficient, reliable and continuous and cost effective operation, inspection,
maintenance and repair at all times throughout the design life of the Works, under the prevailing
climatic, environmental and operational conditions.
E. Maximum consideration shall be given to efficient and low-cost operation, maintenance, maximum
durability, robust construction, minimal environmental impact, ergonomically correct, and ease of
construction & operation.
F. The facilities shall be designed to meet all the requirements of the applicable local regulations as
well as general requirements of the prevailing Regional, State and International standards and
codes including industrial best practices prevailing in oil and gas industry and complying with
environmental regulations.
G. The facilities shall be suitable to operate for 24 hours per day, 365 days per year and shall be safe
to operate and maintain. Operations and maintenance at all work places and at all times must be
able to perform in a safe way. Safe access and / or working platforms to / at plant equipment for
both operations and maintenance staff shall be provided.
H. The Contractor shall give full consideration to ensure safety of the Works, minimal impact on the
environment complying to EIA requirements (if any) and all applicable environmental regulations,
norms and standards in the Emirate of Fujairah UAE and abide by International Environmental
Regulations and Industrial best practices as applicable, minimizing operating and maintenance
costs to achieve an optimum lifetime cost and to minimizing the extent / frequency of maintenance
and its disruptive effect on operations.
I. Contractor being fully responsible for all aspects of design, installation, erection, construction,
Installation, testing, calibration, pre-commissioning and commissioning etc. and ensuring safe
operation after commissioning up to stipulated time period as per Contract. Contractor shall abide
by order of precedence to deliver plant, materials, and workmanship and whatever else is necessary
or desirable to meet the Employer's Requirements
11 CONTRACTOR'S OBLIGATIONS
A. This section provides the overview of the Contractor’s responsibilities under the Contract, the details
provides herein are not exhaustive, hence all the provisions herein mentioned shall be read in
conjunction with the provisions of other Contract Documents and the Employer’s Requirements.
C. The Contractor shall be fully responsible for all aspects of the design, installation, erection,
construction ,recertification, installation conforming to Ergonomics, Installation, testing, calibration,
Pre-commissioning and commissioning and remedying any defect of the Works and for providing
such plant, materials, and workmanship and whatever else may be necessary or desirable to meet
the Employer's Requirements.
D. The Contractor shall, using all due skill, care and diligence, verify the design documents provided
by Employer, do necessary engineering, construct, test, pre-commission, rectify defects in, and
complete all facilities and systems, such that the Works are suitable in all respects for the purposes
of meeting Employer's Requirements, complying with all local authorities requirements,
International HSE regulations and industry best practices and the Contract’s requirements.
E. The Contractor shall give full comply with all the environmental regulations as per Fujairah
Municipality Environmental Department regulations, and FOIZ regulations in regard to ambient air
quality monitoring, emission, noise, odor management, waste disposal etc. Contractor shall also
comply to all the regulations of FOIZ HSEMS.
F. Contractor shall be obliged to carryout verification of the design documents provided by the
Employer, perform detailed engineering, development of necessary fabrication / working drawings,
supply all materials such as tools, consumables, maintenance equipment, labor, site offices and
facilities for Contractor’s work force, supervision, fabrication, construction, installation, painting,
testing , precommissioning, commissioning assistance and provide overall site management for the
construction and handing over of the Works.
G. The Contractor shall accept full responsibility for the adequacy of the design, including any design/
details prepared by or on behalf of the Employer. Nothing in the Employer/Employer’s Engineers
reviews, comments or recommendations shall relieve the contractor of any of his obligations under
the Contract.
H. The Contractor, Sub-Contractor, Consultant, Vendor and Sub-Vendor shall notify the
Employer/Employer’s representative of any apparent lack of clarity and/or conflict between this
General Design Specification, Project Specification, Contract Scope, the related data sheets,
drawings, the Codes and Standards and any other specifications noted herein. Unless specifically
stated otherwise, the most stringent requirements shall apply. In case of lack of clarity, the resolution
and/or interpretation precedence shall be obtained from Employer/Employer’s representative in
writing before proceeding with the design, execution or manufacture.
J. The Contractor shall be fully responsible for the construction of the Works to comply with the
requirements of the various relevant local Authorities (Civil Defense, FEWA, Environment Dept
under Fujairah Municipality, Police & UAE Govt., other organizations like FOIZ, POF/FOTT etc. if
any), consents, no objection certificates and the Employer’s environmental commitments.
K. All the relevant information required from any local Authorities, equipment vendors or any third party
shall be obtained by the Contractor. Client / consultant shall provide necessary assistance by
providing vendor details and details of previous communications. Any delay due to the above shall
be under the responsibility of the Contractor, and Contractor shall be responsible to pay for penalty
if any.
L. The Contractor shall not commence any part of the Works until he has obtained or is otherwise
satisfied that written approval has been obtained from all necessary relevant statutory, regulatory
and utilities authorities (keeping Employer informed time-to-time).
M. The Contractor is responsible for providing sufficient manpower for the successful execution of the
Project within the scheduled completion period. Recruitments, mobilizing to the site, transportation,
conveyance, proper accommodation and lodging, food, water, medical, clothing, salary, overtime
payments, other staff benefits, incentives, Workmen’s Compensation, Personal Accident Policy,
PPE etc. for the manpower as necessary shall be under responsibility of the Contractor.
Employment Visas for working in Fujairah shall be arranged and obtained by the Contractor. The
Employer will only provide necessary letter to assist the Contractor, if required.
N. The Employer shall only assign and locate the Lay down area for the Contractor. Any further
responsibility to develop the lay down area and to provide entire infrastructure for the safe
construction of the Works rests with Contractor. Once construction activity of Contractor is over;
taking approval of Employer/Client contractor have to demolish, shift their equipment and keep lay-
down area house kept and clean to entire satisfaction of client and return back the land/ area “as is
where is” condition to Employer/ Client.
O. The Contractor’s choice of equipment and construction methodology shall minimize adverse impact
to the environment.
P. The Contractor shall furnish, erect and maintain all temporary works and equipment, as may be
necessary for carrying out the work. All such items shall be of safe construction, adequate for the
intended purpose and shall not constitute any hazard to persons or property. All construction
equipment shall be valid third party certified complying with UAE Labor Law.
Q. All items of the Works shall be protected against possible damage and shall be provided as
necessary with temporary coverings or with other suitable means which will afford adequate
protection.
R. It shall be Contractor’s obligation and responsibility to satisfy the Employer as to the quality
workmanship, Safety and job completion as per design specs and completeness of the Works as
per the Contractual Terms and Conditions. Failing to meet contractual terms and conditions (delay,
deviation from design specs, and sudden stoppage of job, obstructing other contractors, not
submitting the required HSE studies as required by FOIZ, Civil Defense or any other government
authority, not following Project HSE plan, HSE regulations and safety standards etc.) shall lead to
negative credit to contractor and Employer will penalize and deduct equivalent amount to
compensate. Any deviation / concession / variation to the design specifications and its attachments
including, but not limited to, the Data Sheets, Drawings, Contract Scope of Works, Project
Specification and Narrative Specifications shall be sought by the Contractor, Sub-Contractor,
Vendor and Sub-Vendor only through deviation / concession / variation request format. Any
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
19/72
deviation / concession / variation (through Design & specification Change Authorization) require
Employer / Employers Representative review / approval prior to the implementation of the proposed
changes. Changes implemented prior to Employer / Employers Representative approval are liable
to be rejected at Employer’s sole discretion.
S. Contractor shall be held responsible for disrespect to completion date or delay in the project
schedule if any. Contractor shall have to pay penalty against any unjustified delay from Contractors
side or for any wrong design, engineering and construction works deviating design specs.
12 SITE ACQUAINTANCE
A. The Contractor shall perform site survey(s) in order to fully acquaint himself with the Project facilities
to be provided. Contractor shall identify any services / facilities at Site particularly any infrastructures
likely to be encountered during the execution of the Project, which may not be indicative in the
drawings.
B. It is the responsibility of the Contractor to take effective precautionary measures during construction
in-order to avoid any disturbance / damage to the existing services & facilities. If Contractor
damages any nearby property or asset during the execution of their works, Contractor shall be held
accountable for the rectifications and the cost incurred for the rectification works will be deducted
from the Contractor.
C. The Contractor shall field verify all relevant locations and elevations of the existing services /
facilities and dimensions of the proposed facilities indicated in the drawings before start of the Works
and shall be fully acquainted of complete site characteristics. Piping foundations and some part of
the piping within process area has already been constructed by the Employer.
D. The Contractor shall be responsible to avoid any interference / clash or conflict with any of the
existing facilities; likewise any interface with the existing facilities shall be the responsibility of the
Contractor. Any modification to existing facilities encountered due to the Contractor’s Works during
the Works of the Project shall be under Contractor’s responsibility. In such cases no variation claim
from Contractor will be considered and entertained by the Client.
E. The Contractor is deemed to have satisfied and familiarized himself to local conditions, the nature
and degree of accessibility for his equipment and machines, the nature and extent of the operation,
the conditions affecting labor and the general execution of the Works. No claim shall be accepted
in respect of any of these matters, either due to lack of knowledge or ignorance of conditions.
F. The Site shall be handed over to the Contractor in “as is where is” condition. Any doubts regarding
the site real conditions that are not clear in the contract shall be clarified by contractor by means of
further investigations at his own expense.
16 ACCESS ROUTES
A. The Contractor shall obtain all the consents and approvals necessary for entering and exiting his
plant and equipment to the site. Any equipment/mobile motorized vehicles/cranes/materials shall
be approved by third party authority and shall be fitted with all safety gadgets as per norms.
B. The Contractor shall allow the Employer / Employer’s Representative, his servants, agents and
contractors reasonable access to the Site and the Contractor’s work places.
C. For the avoidance of doubt, transient access to any part or Section of the Works from time to time
by vehicles, plant or personnel of the Employer/ Employer’s Engineer, or any of their employees or
appointed third parties, from time to time shall not constitute ‘Use’ by the Employer in the meaning
of Clause 10 of the Conditions of Contract.
D. Contractors shall issue individual identity card / Security Access card to all their employees.
E. Contractor shall follow the Client Access Control System and Material Incoming and Outgoing
Procedure and System.
B. Contractor shall abide-by all the Client safety requirements, risk assessment points and ensure that
PTW instructions of Client HSE department are strictly followed as per site requirements.
20 CONTRACTOR’S EQUIPMENT
A. The Contractor shall submit to the Employer, within 7 days of the Commencement Date, a
comprehensive Contractor’s Equipment Schedule, which shall include the proposed dates of arrival
on Site of each item. The Contractor shall obtain all the consents and approval necessary for
entering and exiting his plant and equipment to the site.
B. The Contractor shall comply with all the relevant statutory requirements in respect of the use of
noise reduction and pollution-free Contractor’s Equipment.
C. The Contractor shall ensure that damage or contamination to any roads, footpaths and tracks used
by the Contractor’s Equipment proceeding to or from the Site, shall be kept to a minimum. The
Contractor shall be responsible for the cost of all repairs necessary to restore such roads, tracks or
footpaths, including cleaning and clearing of any debris, to the satisfaction of the Employer/
Employer’s Engineer.
D. The Contractor shall develop a Road Traffic Management Plan relevant to his planned operations
for approval by the Employer / Employer’s Representative and the local authorities in line with the
existing traffic system within the site and in accordance with Clause 4.15 of the Conditions of
Contract, Particular Conditions.
E. Contractor shall submit third party Environment monitoring report, on quarterly basis for the Fence
level noise monitoring (Yard & work Site) and emission monitoring (VOC, Ambient monitoring report,
pollution checking) for their DG & Compressor etc. and shall report to Ecomar.
22 PROJECT ORGANIZATION
B. The Contractor shall within 1 week of Award of Contract submit detailed resumes (supporting
documents which may be subsequently required) of respective person deemed as the Key
Personnel by the Employer to be significant within the organizational structure of the Contractor.
Upon the approval of Organization chart and proposed personnel by the Employer, no changes
shall be made without the prior written approval and until a satisfactory replacement has been
approved. The Contractor shall also submit and maintain a holiday schedule for this Site staff for
the approval of the Employer. Contractors key personnel’s leave needs to be approved by Employer
subject to suitable alternate person positioned.
B. Contractor’s Key Personnel shall be fluent in English language (spoken & writing).
C. The following designations in the Contractor’s Organization are considered as Key Personnel
having minimum qualifications as defined below.
Project Manager (Contractor’s Representative under Clause 4.3 of Conditions of Contract):
Minimum of 15 years’ experience. Previous assignment as PM of Oil & Gas Projects.
Engineering Graduate from an accredited institution specializing in a relevant field of study.
Construction Manager (CM): Minimum of 10 years’ experience, previous assignments as CM
of Oil & Gas Projects. Appropriate experience in structural engineering. Engineering Graduate
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
25/72
from an accredited institution specializing in a relevant field of study.
QHSE Engineer: minimum of 10 years’ experience, Engineering Graduate from an accredited
institution specializing in a relevant field of study. Must be experienced in the development and
implementation of Project specific Quality Programs, through all Project phases (design,
procurement, construction and commissioning), which align with ISO 9001 requirements. Will
monitor and report on the implementation of the Quality Programme through surveillance and
formal audit activities. Safety Officer to worker ratio, shall be minimum 1:50, however client can
ask for additional safety engineer/ officer depending on Job criticality, e.g. FOTT area).
Project Planning and Control Engineer: A minimum of 5 years’ experience in Programme
management in Oil & Gas contracts and proficient in MS Project and Primavera to undertake
the programming tasks.
D. Employer & Employers Representative holds the right for replacement of deployed staff or remove
any staff due to non-performance, misleading to Employer or any misdeed with suitable
replacement.
23.1 Programme
A. The Contractor shall co-ordinate and Plan / Schedule the Works using MS Project software,
Primavera P6 or other applicable software as may be requested by the Employer.
B. The Program shall mention but not be limited to:
Engineering
Mobilization dates of plant equipment
Completion of the whole of the Works and the Completion of Sections as defined in the
Definition Drawings within the times stated in the Particular Condition of Contract.
The Programme shall clearly identify the delivery requirement of free issue materials /
equipment’s and account for all time requirements for (re)submission of documents, review,
approval, all foreseeable risk, under the Contract.
Programming Software shall be MS Project or Primavera P6.
C. Changes in the network logic may only be made after consultation with the Employer.
D. The Contractor shall provide to the Employer an electronic copy of all Programme details.
24 MEETINGS
A. The Contractor shall attend all meetings where he is requested to do so. In addition, the Contractor
may call any meeting as deems necessary to meet his obligations under the Contract.
Project Manager
QHSE Manager
Safety Engineer
Planning Manager / Engineer
Project Engineers
Site Engineers
QPS for special processes, e.g. Welding, NDE and Post Weld Heat Treatment, shall be
developed in accordance with the relevant codes and standards. All operators involved in the
application of special processes shall be qualified in accordance with the relevant code or
standard. These requirements apply to Temporary Works as well as Permanent Works,
Document control including preparation, checking, approval, updating, receipt and control of
incoming documents, distribution, storage and maintenance of records,
Design control including verification, approval and acceptance by others,
Preparation of material requisitions and approval of purchase orders in accordance with
accepted specifications.
Performance of quality verification reviews
Control and calibration of measuring and test equipment
Monitoring the activities of any consultants, subcontractors, suppliers and sub-tiers thereof, to
ensure their compliance with the Contract.
Review of material suppliers and subcontractors quality verification documentation
Production of weekly reports of quality issues including non-conformity records and kpi’s as
deemed appropriate by the Employer. QC KPI’s shall be reflected in the monthly performance
report.
B. The Contractor and its subcontractors connected with the Works shall develop and maintain
procedures for carrying out checks, reviews and verification activities appropriate for the services
they provide. These procedures shall be subject to the review and acceptance by the Employer /
Employer’s Engineer.
C. All applicable Quality System documentation (except quality records) supporting activities in the
Contractor’s Works shall be reviewed and accepted by the Contractor and then issued to the
Employer’s Engineer for review and acceptance before work starts on the activities. Where these
documents together adequately address on going and imminent Contract works but not the entire
scope of the Contract works, the Employer’s Engineer may give limited acceptance to the
Contractor’s submission.
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
30/72
D. The Contract QAP shall include or reference the controls to be applied by subcontractors, suppliers
and sub-tiers thereof, both directly and by identifying the Quality System documentation that
subcontractors, suppliers and sub-tiers thereof are required to produce. The Contractor shall ensure
that its subcontractors, suppliers and sub-tiers thereof agree to and implement the applicable
controls specified in the Contract QAP and the identified Quality System documentation.
29.1 Introduction
A. The Contractor shall ensure that the Project shall be built, operated and maintained safely and with
the minimum risk to health to the extent that is required in accordance with, and in full compliance
with legislation.
B. The Design and Construction of Works shall have incorporated all safety measures as resulting
from the Health and Safety Risk Assessment, subject to approval of the Employer. The Contractor
cannot, in any case, claim for any variation to costs or Programme under the Contract resulting from
safety measures as taken by the Contractor or ordered by the Employer to be taken by the
Contractor.
C. If appropriate safety, environmental, OH prevention and protection measures are not in place and
the Employer, in line with the Conditions of Contract orders certain construction activities to be
suspended, the Contractor shall immediately stop these and shall not be entitled to any
compensation or variation under the contract.
D. The Contractor shall ensure that all personnel employed on or about the Works receive appropriate
training by way of regular tool-box talks and the like such that they understand the risks involved in
the works being undertaken, the safe use of tools and equipment and the relevance of personal
protective equipment (PPE). All staff shall receive a site HSE induction (by Contractor and Employer
HSSE Department) prior to commencing work on the project outlining the site safety protocol and
risks involved in the works being undertaken. This site induction shall be extended as appropriate
to personnel from other organizations that are given access onto the Site.
A list of the key emergency response personnel showing responsibilities and contact details
including all-hours telephone numbers;
Details of emergency services (e.g. ambulance, fire brigade, spill clean-up);
Communications strategy (internal and external, medical and environmental) including the
reporting of serious environmental incidents or complaints to the regulating authority.
Details of containment measures and remedial action to be taken in the event of emergency
situations that may arise during the work activities; and
29.5 Training
A. The Contractor shall ensure that employees and visitors are aware of these procedures and display,
in prominent positions, posters stating these procedures with emergency telephone contacts. No
unaccompanied allowance to the Site shall be permitted unless the person has been provided a full
Site safety induction course.
B. The Contractor shall record the attendance and topic of discussion for each toolbox talk conducted
and shall produce the records whenever requested by the Employer.
C. The Contractor shall encourage staff to point out any risks on Site in order to take the necessary
actions to mitigate these risks
D. Inspection and Corrective Action for any incidents or Hazards and maintain Hazard / Risk Register.
Contractor shall develop all HSE studies / documentation as listed in the HSE plan including Hazard
/ Risk Register.
E. The Contractor shall ensure that all personnel employed on or about the Works receive appropriate
training by way of regular tool-box talks and the like such that they understand the risks involved in
the works being undertaken, the safe use of tools and equipment and the relevance of personal
protective equipment (PPE). All staff shall receive a site induction prior to commencing work on the
project outlining the site safety protocol and risks involved in the works being undertaken. This site
HSE induction shall be extended as appropriate to personnel from other organizations (including
Ecomar HSSE) that are given access onto the Site.
F. The Employer shall be entitled to audit the compliance by the Contractor with the quality, safety,
work progress, health & environmental plan and/or the safety management plan at such times and
as often as it may reasonably decide. Internal and external audit on quarterly / bi-annual basis as
found feasible shall be conducted. The Contractor shall arrange for all required documents during
the audit and shall provide all the necessary support and assistance, at its own cost, to allow the
Employer to carry out such audits.
G. The Contractor shall immediately notify the Employer if any accident occurs whether on or off Site
in connection with the Services which results in any injury to any person and shall immediately
transfer the injured to hospital and ensure for proper medical treatment till the injured is recovered
and join normal duty as per ERP and Workman’s Compensation Plan whether directly concerned
with the Site or a third party. Such notification may initially be verbal and shall be followed by an
initial written report within 24 hours of the accident. Furthermore, final incident report to be submitted
to Employer within 2-5 working days. Contractor shall develop a HSE management system with
specified HSE procedures, as guided by Client, FOIZ including incident reporting.
H. Where any incident, near miss or unacceptable hazard has been reported or identified, the Health
and Safety Manager shall report immediately to the Employer. Both Employer and Contractor shall
determine the corrective action to be undertaken and the timeframe for incorporation. Near miss
report to be prepared by the Contractor and implement the corrective actions to prevent recurrence.
I. Dependent on the incident the Employer shall have the authority to temporarily suspend parts of
the Works.
J. A second inspection shall be undertaken, allowing for a reasonable time period after the first
inspection, in which the locations of all the previous incidents shall be re-visited.
K. The Employer shall then confirm whether the remedial action from previous report has been
undertaken. If it has not been undertaken or if it has been deemed to be inadequate, the Contractor
shall be given a verbal warning and allowed time, to comply-with recommendations. If contractor
B. Hard hat, safety glass, coverall, reflective vest (except when operating rotating tools), safety
boots/shoes. The Employer will request different color’s for hard hats and reflective vests, Protective
goggles, Hearing Protection.
C. The Contractor may be required to remove from Site any of his personnel who repeatedly ignore
these requirements. Contractor to establish Warning/Penalty policy and repeated defaulters of PPE
shall be removed.
D. The Contractor shall ensure that all personnel employed on or about the Works receive appropriate
training and the like, such that they understand the risks involved in the Works being undertaken,
the safe use of tools and equipment, and the importance of Personal Protective Equipment (PPE).
30 ENVIRONMENTAL MANAGEMENT
30.1 Introduction
A. The Contractor shall develop an Environmental Management Plan (EMP) & Waste Management
Plan that is compliant with the Project framework. The following sections give the requirements for
the Contractor to adhere to under the Contract; however these shall in no circumstance limit the
Contractor’s obligations under the Laws of the Fujairah / UAE that includes of FOIZ, Fujairah
Municipality, Civil Defense, UAE Labor Law and Regulations etc.
F. Contractor to prepare Monthly waste report including duly approved Waste Manifest (in compliance
with Fujairah Municipality, Environment Dept.) & submit to employer.
31.1 General
The scope covers the technical requirements of detail design of civil and structural works,
engineering, procurement, supply, manufacture, inspection and testing at manufacturer’s facility and
in site in presence of Employer / Employers representative, dispatch in well packed condition to site,
insurance, receipt at site, proper and safe storage, transport to place of installation, erection,
documentation, warranty, as-built dossiers, pre-commissioning and start-up of the complete system
for the Project, to its satisfactory operation meeting the Employer requirement.
Issued civil and structural documents are intended to assist in the interpretation of the civil and
structural works required for the Project. Full detailed design of the civil and structural works is under
the responsibility of the EPC Contractor.
All works, materials, labor, equipment and services necessary to fully develop the facility shall be in
EPC Contractor’s scope including but not limited to all supports foundations, structures, earthworks,
clearing and grubbing, excavations, imports of material as required, filling and backfilling, dewatering
systems if required, shoring, surfacing, utilities, finished grading, landscaping, barricading etc.
All backfill material shall be free from rock or other unsuitable materials. It shall be sieved to remove
solid materials greater than 50mm size.
The optimal type of structure and material regarding resistance against corrosion, design life, safety,
and especially functional criteria for operation and maintenance shall be provided.
The implementation of the civil works shall follow state-of-the-art technology. All structures shall be
designed to facilitate construction in accordance with the proposed erection sequence. All structures
shall be designed to remain stable at all stages during erection. If necessary, suitable temporary
bracing or supports shall be designed and provided. All temporary works shall be properly designed
and substantially constructed to carry the loads they will be called upon to bear. Calculations,
drawings and particulars of any temporary work whenever required by Employer / Employer’s
Representative shall be furnished.
Civil & Structural works shall be tested by Independent testing laboratory and certified in accordance
to applicable local authority requirements and to the standards adopted for the design.
In addition to the above, all Civil & Structural Works shall be inspected and tested under the
responsibility of the Contractor and in the presence of the Employer / Employers Representative in
order to verify the conformity to the design and the achievement of suitable quality standards.
These tests shall include as a minimum, but shall not be limited to the following:
Inspection of all civil and structures work finalized to verify the conformity to the design.
Material Sampling, testing on site, e.g. conformity of fresh concrete before casting.
31.3 Scope
Civil & Structural scope of works mainly includes the following but not limited to:
Pipe supports
Operating platforms
Cross overs
Valves Pits
Pipe racks shall be considered as per the approved piping general arrangement drawings. Pipe Rack
steel structure shall be in the form of portal frame with strut beams, vertical & horizontal bracings
shall be designed for different type of loadings and industrial requirements.
Pipe supports are steel support which can be T post, goal post, cantilever or other type of support.
Pipe sleepers are RCC supports cast in-situ on the soil. Preliminary Piping supports and sleeper
foundation layout are provided in the contract drawings which shall be finalized by the EPC contractor
during detailed engineering stage.
An insert plate or steel beam shall be fixed on the top of the sleepers to support the pipes and transmit
the load uniformly to the top of their pedestals. Insert plate / base plate shall be provided with air vent
hole.
All the sleepers shall be designed and detailed individually taken into consideration the pipe supports
reactions and the soil bearing capacity and any other soil report recommendations.
All external steel structures (pipe rack, pipe supports, handrails, platform, staircase etc.) shall be hot
dip galvanized and painted and all embedded steel structures shall be hot dip galvanized.
Operating platforms shall be provided for safe operation of the equipment’s installed at heights above
1.5 m such as PLR’s, valves etc.
Cross overs and operating platforms shall be of steel framed structures, hand rails and stairs/ladders
and shall rest over isolated RCC foundations. Number and location of cross over’s & operating
platforms shall be finalized during detailed engineering. Insert plate / base plate shall be provided
with air vent hole. All crossovers and operating platform shall comply with Project specifications and
in line with best industry standards/API/ASME etc.
Flooring of platform and walkways shall be serrated rectangular grid grating. Load bearing bars
of grating panels shall be 30mm minimum depth x 5mm thick at 30 mm cross centers with
serrated top edge.
Lateral restraint shall be provided by 6mm x 6mm twisted cross bars at 100 mm pitch.
Transverse bars shall be welded to the upper edge of the load bearing bars.
Grating shall be attached to the supporting steelwork with clips and bolts.
Removable floor grating shall be arranged in panels, each weighing not less than 36 kg/m².
All external steel structures (pipe rack, pipe supports, handrails, platform, staircase etc.) shall be hot
dip galvanized and painted and all embedded steel structures shall be hot dip galvanized.
Pits
The pits for drainage system, electrical, firefighting etc. shall be designed for the intended purpose.
Underground water, anti- corrosion measures shall be taken into account during the design. Pit
manhole covers shall be epoxy coated with polyurethane.
Miscellaneous Works
Miscellaneous Civil & Structural works which shall be carried out by the EPC contractor include the
following activities (but not limit to);
All the interfacing civil Works required for electrical, instrumentation, piping, mechanical,
firefighting system Works for the successful execution of Project shall be part of the EPC
Contractor’s scope.
All civil Works relating to underground pipe Works for products and fire water pipe lines.
The Structural Works shall be designed and constructed for a design life of 50 years from Takeover
Certificate (TOC). The Works shall remain fully functional for the design life. At the end of the design
life and after taking account of any corrosion and other deterioration, stresses and deflections
under maximum loading conditions shall remain within the limits set down by the specified design
codes. Included in the design life requirements of the Works are routine inspection intervals and
maintenance by the Employer, see also the table below for the elements of the Works:
A. Structures shall be designed to have sufficient structural capacity and integrity to resist safely
and effectively all loads and effects of load combinations that may reasonably be expected.
B. The design loads used for the structures and foundations shall conform to the requirements of
the governing codes and specifications.
C. As a minimum the design loads shall include dead load, operating loads, live load, rain load,
wind load, collateral load, dynamic load and seismic load. Where applicable, the design loads
shall also include thermal load, anchor loads, hydro test load, impact load, vibration load,
surcharge load and bundle pull loads.
31.3.6.1.1 Dead load is defined as the weight of walls, foundations, grating, slab, Chequered plate and ladder
etc. Structural dead loads are the weight of all structural materials that forms a permanent part of the
completed structure. Unit weights of the major construction materials shall be in accordance with the
following table.
Steel 7850
Live Load is defined as the weight of all movable loads, including personnel, tools, miscellaneous
equipment, cranes, hoists, parts of dismantled equipment, and temporarily stored materials.
Generally where applicable, the live loads shall be in accordance with BS or Uniform Building
Code, except otherwise stated in this Design Criteria.
The Live Loads shall be considered as uniformly distributed over the horizontal projection of the
loaded areas, except for the loads with a concentrated nature.
31.3.6.2.2 The following minimum live loads shall be considered for the Detail Engineering of the Project:
Other loads: To be determined in accordance with the Uniform Building Code and or BS 6399.
Wind load shall be designed as per ASCE7-05 or BS 6399-2 as per site data sheet.
Where:
Sb = Terrian and Building factor (refer Cl 2.2.3.3. & table 4 from BS 6399 Part-2-1997)
B. Wind load procedure following ASCE 7 Chapter 6 – Code of practice for Wind loads.
The velocity pressure, qz, evaluated at height “z” shall be calculated from the following formula:
where:
qz = velocity pressure
V = basic wind speed in m/s (As per contract specification and site data sheet, the wind speed to
be considered 45 m/s assuming 3 sec gust.)
Operating Load
31.3.6.4.1 Operating Load shall be the dead load plus the weight of any liquids or solids present within the
vessels, equipment and/or piping during normal operation including the weight of all permanently
stored materials for operation on vessels/structure.
Thermal Load
31.3.6.5.1 Thermal load is defined as the temperature that causes the effect on buildings. The initial temperature
is defined as the temperature which causes no thermal effect on a building. The temperature
difference ΔT has two parts, mean cross-section temperature ΔTd and the temperature gradient in
the cross-section ΔTg / t. Thermal loads should be considered for the following building types:
31.3.6.5.2 For Pipe racks, supporting multiple pipes, 10 % of the total piping weight shall be used as an
estimated horizontal friction load applied only to local supporting beams.
31.3.6.6.1 Seismic loads shall be calculated based on the provisions of cl 1630.2 of Uniform Building Code –
1997 / Eurocode 8.
Where
The Total design base shear need not exceed the following
V = (2.5*Ca*I)*W/R
The total design base shear shall not less than the following
V = (0.11*Ca*I)*W
31.3.6.6.2 The value of base shear obtained shall be distributed at respective floor level as per clause 1630.5
of UBC 1997. The individual floor loads thus computed shall be applied at all the column joints in
proportion to their rigidities as lateral loads. Two cases of loading for seismic condition shall be
considered:
2. The lateral loads acting in global Z direction (Global Y direction is considered vertically
upwards)
31.4 Materials
Cement
Cement shall be selected with consideration for durability and low permeability.
Cement for the structural reinforced concrete and paving shall be Ground Granulated Blast Furnace
Slag Cement GGBS/MSRPC blend with modified C3A at 55% / 45% minimum for all Structural
Concrete Works with fcu = 40 N/mm2 based upon 28 day cube Strength. GGBS shall conform to BS
6699.
Cement used for blinding and mass concrete fill shall be MSRPC type II to ASTM C150 with fcu = 20
N/mm2 based upon 28 day cube strength.
The heat of hydration shall not exceed 325 kJ/kg when tested in accordance with ASTM C 186.
The C3A content shall be a minimum of 8% by weight when tested in accordance with BS 4550.
The magnesia content shall be limited to 4% by weight of cement when tested in accordance
with ASTM C 114.
Table 31.3: Reinforced Concrete grade for design
Reinforced bar
The design shall consider the steel reinforcement complying with BS 4449 and strength
characteristic. Minimum grade shall be Grade 460, and the diameter shall be a minimum of 8 mm.
Cover to Reinforcement
Impact Loads
Impact loads shall be calculated in accordance with the requirements of AISC Manual of Steel
Construction, 9th Edition, ASD, Part 5, Paragraph A4-2 (page 5-29). Impact loads shall be considered
for local member design & it shall not be used with wind/seismic load cases.
Analysis of steel structure shall be performed using STAAD PRO & PROKON program and native
file shall be provided to Employer / Employer’s representative.
The structures shall be analyzed as a three dimensional frames (space frames). The frames shall be
considered as free standing frames with rigid bases for each column. Generally the concrete beam
members shall be so designed that the span/depth ratio is 10.
The following basic loading combinations, in addition that specified in BS 8110, shall be considered
to determine the maximum stress condition on the structural members.
Table 31.4: Load Combinations for the Ultimate Limit State (ULS as per BS)
LOAD TYPE
LOAD
COMBINATION Dead Load Imposed Load Earth &
Wind Seismic
Adverse Adverse Water
4 1.0 1.4
5 1.0 1.4
Table 31.5: Load Combinations for the Serviceability Limit State (SLS as per BS)
LOAD TYPE
LOAD Dead Load Imposed Load
COMBINATION Earth &
Wind Seismic
Water
Adverse Adverse
The associated values of δm for ULS condition, according to BS 8110, shall be as follows:
Reinforcement 1.05
Concrete in flexure or axial load 1.5
Safety Factors
Foundations
All foundations design shall be based on the designed civil input as specified in soil report.
The minimum width for a strip footing is 1000 mm and the minimum thickness of footing shall be
300mm.
Minimum distance from the centerline of the foundation anchor bolts to the edge of the pedestal shall
be the maximum of the following:-
(a) Clear distance from the edge of the base-plate/base frame to the outer edge of the pedestal shall
be minimum 100 mm or as mentioned in the drawing.
(b) Clear distance from the face of the pocket/edge of pipe sleeve to the outer edge of the pedestal
shall be minimum 100 mm
Generally the distance of the bolt center from the pedestal face shall be 125-150 mm. The center to
center distance between the anchor bolts shall be 8 times bolt diameter and the edge distance from
the bolt center to the face of pocket 4 times bolt diameter.
The top of concrete elevation shall be a minimum of 200 mm above grade for pedestals, piers and
pads and 150 mm above finished floors (concrete grade slabs).
For the support of items at close spacing, such that the footings or pile caps utilize more than 50%
of the gross plan area, it is common to use a mat type of spread footing, or pile cap, that supports
several items.
Design of foundations shall be in accordance with BS 8004:1986. The coefficient of friction between
concrete surfaces and undisturbed soil shall be taken as 0.4.
For structural concrete elements, the following minimum thickness shall be followed:
All steel structures shall be modeled, analyzed in STAAD PRO or any recognized software having
interface and/or can be read or converted to staad pro and designed as per Euro code 3 / AISC
/LRFD as applicable.
All structures shall be framed in transverse direction and braced in longitudinal direction.
Both induced stresses and deflection shall be kept within provisions of BS codes & good engineering
practices.
Steel material
All steel members shall be S275 steel with specified minimum yield strength of 275 N/mm².
Bolts, nuts and washers shall be of the types indicated on the Drawings and shall comply with the
relevant British standard.
Dimensions and tolerances of black hexagon bolts, screws and nuts with ISO metric threads (in dia
5mm to 68mm) shall comply with BS 4190.
High strength friction grip bolts shall comply with BS 4395: Part 1.
Ordinary bolts and high strength bolts shall comply with BS 3692 or BS 4190 for hexagonal head
bolts, or BS 4933 for countersunk or cup head bolts. Nuts shall have a strength grade equal or greater
than the grade of the bolt (or other threaded element) with which they are used. Plain and tapered
washers shall comply with BS 3410 or BS 4320, as appropriate.
All Bolts, Nuts & washers shall be Hot Dip Galvanized as per BS EN ISO 1461 standards.
Trusses/bracings: 6 mm
Purlins, side girts/runners: 6 mm (if hot rolled section)
Columns, beams 7 mm
Gussets in trusses & girders Up to & inclusive of 12 m span: 8 mm
Gussets in trusses & girders above 12 m span: 10 mm
Stiffeners: 8 mm
Base-plates: 12 mm
Chequered plates: 6 mm on plain
Grating 30 mm
Grout for structural columns as required but minimum: 25 mm
Grout for equipment as required but minimum: 40 mm
Steel Staircase
Minimum width of stairs shall be 900 mm. Stairs shall have a maximum riser height of 200mm and a
minimum tread width of 250 mm for equipment support platform, maximum riser height of 175 mm
and a minimum tread width of 300 mm for buildings. Number of risers shall be restricted preferably
to 12 depending on occupancy. At least one staircase shall be provided for access to the roofs for
maintenance. All steel stair cases shall be provided with mid and top rail, and proper landing, shall
also confirm to NFPA 101 and Project specifications.
Stairway in a single run shall have the same slope. The vertical rise of the stairways shall not exceed
2.5 m for a single flight.
Steel bracings
Any steel structure shall be provided by a three directional bracing (two vertical and one horizontal),
and for each direction/plan a physical bracing (X, K, frame bracing type…etc.) shall be placed.
Roof sheeting for structural buildings shall be pre-coated/ corrugated Aluminum sheeting 20 CGI
sheet & 22 CGI sheet (corrugated) for side cladding. Translucent sheet can be used covering 20%-
30% of the area of side sheet & roof sheet with polycarbonate.
Down comer pipes at suitable positions as per design shall be fixed below gutter made of mild steel
of 3.55 mm thickness and minimum 150 mm diameter.
Wind bracing/tie runners of minimum size L50X50X6 shall be provided at 4 points in a truss (one at
each corner) for structural roof system i.e. this shall be designed as structural members for proper
transfer of wind forces to the foundation.
LOAD TYPE
LOAD
Dead Load Imposed Load
COMBINATION Thermal Wind Seismic
Adverse Adverse
1 1.4 1.6
2 1.2 1.2 1.2 1.2
3 1.2 1.2 1.2 1.2
4 1.0 1.4
5 1.0 1.4
6 1.0 1.4
Table 31.6.12.2: Load Combinations for the Serviceability Limit State (SLS as per BS)
LOAD TYPE
LOAD Dead Load Imposed Load
COMBINATION Thermal Wind Seismic
Adverse Adverse
1 1.0 1.0
2 1.0 1.0
3 1.0 1.0
4 1.0 1.0
32 MECHANICAL WORKS
OVERALL REQUIREMENTS
A. All Static Equipment including but not limited to Product Storage Tanks and associated works shall
be Designed/Procured/Fabricated/Manufactured/Inspected/Installed/Tested & Commissioned as
per this document, Project Specifications, Applicable Codes and Datasheets.
B. Any other details which are not covered in the contract documents but required for the successful
completion of the project shall be finalized during the detailed engineering stage with Employer’s
representative’s approval without any additional cost or time impact.
C. Any miscellaneous item or temporary works required for assisting completion of works in a phased
manner shall form part of the Contract.
D. Design Life of Static Equipment shall be 25 years.
STORAGE TANKS
A. Primary code of Design shall be API 650-Latest Edition. Other Codes and standards shall be as per
Equipment Datasheet and Project Specification for Tanks.
B. Determination of Shell thickness for Storage Tanks shall be carried out based on the method
mentioned in the respective data sheet.
C. All Storage Tanks shall be calibrated as per relevant API-MPMS Standard-Latest Edition.
D. API -2000 shall be referred as the design code for the sizing and design of Roof Vents.
E. For the Product Storage Tank provided with Floating Roof all requirements as mentioned in the
Datasheet, Specifications and the code shall be complied. Contractor shall verify the material
compatibility of the floating roof components with the product stored.
F. Foundation for Storage tanks are already constructed at site, same shall be considered during
detailed engineering.
G. All Storage Tank Bottom shall be sloped 1:100 towards the center and shall be provided with center
sump. The details shall be as per API 650.
H. All Storage tanks shall be externally/internally painted. Painting shall be as per with project painting
specification.
I. Surfaces (both underside and top surface) of the Bottom Plate for all Storage tanks shall be painted
in accordance with the Project Painting specification..
J. The base of the Tank at the chime shall be sealed with a reputed Tank boot sealing system in
accordance with Project Painting Specification to prevent corrosion due to the water ingression.
K. Minimum Shell/Bottom/Annular plate/Wind girder plate thickness shall be as per the thickness
mentioned in the respective data sheet.
L. Emergency vent requirement including the size and quantity shall be evaluated by the Contractor
during the detail engineering stage.
M. Stairway type shall be as mentioned in the Equipment Datasheet and where Spiral Stairway is
mentioned as required, it shall be of double stringer type.
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
51/72
N. All Structural support for the Spiral Stairways, Platforms etc. shall be of Bolted Assembly.
O. List of Storage tanks are as given below, further details can be referred to their respective
datasheets:
A. The Scope of Works shall include painting of the Employer company logo on the Storage tanks as
per the Employer’s requirement. Details of the logo shall be finalized with the Employer / Employer’s
representative during the detailed engineering stage.
B. All Firefighting attachments (Foam Pourer Nozzles, Foam Pourers, Diffusers, Spray and Sprinklers
Nozzles, Supports, Valves, Fittings, Gaskets, Fasteners, Foam and firewater piping, and all other
Piping related to Firefighting etc.) on the Storage Tanks as required by the Firefighting design shall
be included in the Scope of Mechanical Works contractor. The battery limit of Mechanical Scope of
Works in this regard shall be to the first bottom flange or up to one meter to the tank foundation
from the nozzle with flange including the gasket, bolts nuts, “U” clamps and anchor bolts.
C. Satisfactory Calculations for any part of the Storage tank including fittings and attachments shall be
included in the Mechanical Scope of Works as and when requested by the Employer/Employer’s
Representative.
D. The tanks shall be provided with minimum 4 no’s of Earthing cleats as required by the API / NFPA
codes. Electrical bonding shall be provided to all movable opening accessories in the Tanks.
E. The tanks shall be provided with adequate number of permanent settlement markers in accordance
with API 650 attached to the tank shell.
F. Inlet Diffuser shall be provided for all Product Storage tanks to limit the velocity of the product inlet
flow to less than 1 m/s.
G. The accessories like gauge hatch, vents, goose neck, PVRV, breather valves, blind flanges for
spare nozzles etc. with necessary bolts nuts and gaskets as required by the drawings, data sheets
& specification shall be in the scope of Mechanical Works contractor.
A. Contractor’s Scope of Works shall include the certification of all Storage tanks and associated works
in all aspects which typically includes design calculations, drawings, materials, construction,
painting, non-destructive examinations, hydrostatic test etc. by a TPI agency. The Contractor’s
Scope of Works shall include carrying out the Tank Calibration by the TPI Agency.
B. The TPI Agency shall be approved by the Employer/Employer’s representative prior to employing
them for the works.
A. All Structural items which includes but not limited to Access platforms, Stairways, pipe racks, base
plates etc., shall be under the Mechanical Scope of Works and this shall meet the requirements
mentioned in the Project Structural Specifications.
B. Double Stringer type Spiral stairway with intermediate landing platforms, tank shell top walkway,
wind girders, roof center access walkways, gauging platform and supports for light poles on the
stairway/platforms and other necessary fittings as deemed shall be included in the Mechanical
Scope of Works.
C. Unless otherwise specified elsewhere in the contract documents, all structural steel work such as
operating platforms, crossovers, walkways, handrails, stairs, pipe supports etc. shall be hot dip
galvanized as per applicable codes such as BS 729 and painted as per the technical specification
for general protective coating.
D. Any cutting, drilling or welding shall not be performed after galvanizing without the express approval
of the Employer/Employer’s representative.
E. All damaged galvanized surfaces and edges exposed by cutting after galvanizing shall be treated
with two coats of zinc, sprayed in accordance with BS 2569.
GENERAL
A. Contractor / Vendor shall be responsible for the design, engineering, procurement, fabrication,
testing, supply, installation and commissioning of rotary equipment and packages which include
Side Entry Mixer and accessories required for safe and reliable operation.
B. Contractor shall ensure that equipment supplied shall be from approved Vendor list provided with
the Tender. Product shall be from vendor’s established product range. Prototype shall not be offered
by the vendor and shall not be selected by the Contractor.
C. The Employer requirement shall be read in conjunction with the datasheets and technical
specifications. Contractor shall review and verify all the information given here or elsewhere related
to the design, fabrication, manufacturing, procurement, testing and installation of equipment.
D. Any exceptions or deviations from Employer requirements, Technical Specifications, Data Sheets
or applicable codes and standards shall be written to the attention of Employer / Employer’s
Representative.
E. Rotary equipment shall be selected as per following criteria:
Suitability of equipment for the specified operating conditions
Simplicity of maintenance & operation without compromise on safety. Equipment shall
require minimum personnel for operation & maintenance
Economic usage of fuel & utilities
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
53/72
Standard models from Vendor’s established product range.
F. Preliminary data is provided in the data sheets and related documents, during detail engineering
phase provided data shall be evaluated, verified and optimum operating condition required for
operation shall be determined.
G. Weather / environmental conditions specified shall cover the full range of ambient and climatic
conditions in which the equipment must be operated.
H. Rotary equipment shall be suitable for all the specified extremes of process; utility and ambient
conditions including those at start up and shut down.
I. Design of rotary equipment shall take into account the need to operate at less than rated condition.
J. All rotating equipment & drivers (including gear units and couplings if any) shall be designed to
perform satisfactorily under specified start up conditions, part load operation and up to full
speed/maximum conditions speed.
K. All rotating equipment shall be balanced as per ISO 1940.
L. Noise level shall not exceed 85dbA, when measured at a distance of 1m from skid in any direction.
M. Couplings for rotary equipment with driver rating higher than 160 KW shall be designed in
accordance with API 671.
N. Material selected for the construction/fabrication of equipment shall be in accordance with the
ASTM specification.
O. Material selection shall be optimized and provide acceptable safety and reliability. As a minimum
following shall be considered in material selection:
Resistance to corrosion under specified operating conditions, including those at start up and
shut down.
Consequences for human health, environment and equipment in case of material failure.
P. All rotary equipment shall be packed and preserved, to make them suitable for long term storage in
dusty and marine environment.
A. Side entry mixers shall be provided for the control of bottom sludge and water (BS&W) in tanks 30-
TK-201 / 30-TK-202 & 30-TK-203.
B. The complete assembly of motor, side entry mixer and transmission shall be suitable for hazardous
area application and it shall be suitable for operation in marine environment.
C. Contractor / vendor shall provide gear driven units with high efficiency impeller. Provision shall be
provided for manual and automatic adjustment of angle (swivel angle).
D. Contractor / Vendor shall optimize the spacing requirement (spacing between the side entry mixers)
for the control of sediment suspension and prevention of wax deposition.
E. Contractor / Vendor shall provide suitable control system for mixer operation / shutdown in case of
low liquid level in the tank.
F. Side entry mixers shall be provided with swivel joints, range of operation of side entry mixer shall
be within +30 degree to -30 degree, with an increment of at least 10 degree.
G. Contractor / Vendor shall provide manual and an automatic swivel actuator, which shall allow the
mixer movement within the specified range. It shall have a provision of fixing impeller angle at 10,
20 and 30 degrees on both sides from impeller center line.
H. Contractor / Vendor shall ensure to maintain a suitable distance between the tip of impeller and
bottom plate. CFD analysis shall be provided for the selected model and arrangement of side entry
mixers.
33 PIPING WORKS
33.1 General
A. Scope shall include verification of the FEED documents provided along with this Employer
Requirement, detailed engineering including but not limited to piping stress analysis, evaluation of
nozzle for external loading from piping system, preparation of isometrics and other fabrication
drawings, supply of materials, fabrication, / painting / coating / wrapping, inspection, non-destructive
testing, pressure testing, calibration, pre-commissioning and commissioning of pipe works including
pipe supports and accessories as per developed piping system from final P&IDs. Piping shall be
complete with isolation valves, non-return valves, flanges, fittings, process drains and vents, hydro
test drains and vents, pressure and thermal relief systems, instrument connection works, etc.
B. The entire piping shall be designed, constructed and tested in accordance with the latest edition of
ASME B31.3 and other relevant codes. Any additional code requirements for specific areas may be
followed as applicable.
C. Piping materials selection shall be from the appropriate sections of the piping classes detailed in
the provided Piping Materials Specification (PMS) along with their calculated schedules and
material grades
D. The Contractor shall run a design check of the Hydraulics to finalize all FEED parameters before
commencing any related work.
E. Pipe supports and platforms indicated on the piping plans are indicative and the contractor shall
provide additional pipe supports and platforms upon detailing. Anchors and guides are to be
provided subject to flexibility analysis.
F. Platforms shall be available to access all areas around the tanks and piping as well as access,
maintain and operate all valves. Hand wheels shall not exceed 1.5m (max.) from the operating level.
G. Third party certification shall be carried out for all aspects of the work, i.e. prefabrication, fabrication,
construction, non-destructive testing, internal and external painting/coating, hydro-testing and
calibration.
H. In addition to the normal submission, all drawings shall be provided in “dwg” format; line lists, tie-in
lists, valve lists and other lists shall be submitted in MS Excel format; and all analyses and
calculations shall be submitted in their native file formats.
I. All analyses shall be carried out using the latest version of their respective applications.
J. All other works under project scope, deemed necessary by the Contractor, required for the full
functionality of the entire system shall be under the full responsibility of the Contractor.
K. The Contractor shall engage a design specialist who shall ensure technical harmony and
compliance between design and construction/installation of the works including stress analysis,
supports configuration, fabrication and installation etc.
A. Tanks (5 Nos. under this phase) piping shall be carefully routed aboveground. The products,
recirculation/receiving/discharge lines from respective tank nozzles to the headers along with other
utility lines shall be routed to selectively connect to the existing headers at their respective tie-in
points in line with the process schemes and operational requirement of the project.
A. The Plant Utility lines which include Service Water, Nitrogen, Plant Air shall be routed from the
existing headers tie-in points to the tanks utility points to meet the project service needs.
B. The FEED documents along with this Employer requirement shall be for guidance, exact number
of tie-ins and utility connection points shall be finalized during detailed engineering by the
Contractor.
A. The firewater/foam solution piping system provided in Phase I is a loop system. Firewater /Foam
water ring mains and headers are already routed around the Phase II tanks with provision for taking
tapping from the existing headers. Tie-in shall be made from existing fire water and foam solution
headers & routed to Phase II tanks for exposure protection & coverage for the required cooling of
nearby tanks in case of a fire situation. Foam pourers shall be considered for each tank for “tank on
fire” protection.
B. The ring mains shall be provided with sufficient manual isolation valves so that a small section of
the ring mains can be taken out of service without interruption and guarantee water supply through
adjacent sections to protect other installations.
34 ELECTRICAL WORKS
34.1 Reference documents, codes and standards
The electrical systems, equipment, materials, components and functions shall be designed, built,
rated and tested to perform in accordance with the following respective codes and standards:
The electrical requirements and equipment considered for the development of this project are as
listed below:
Due consideration shall be given to ensure that the new upcoming electrical system is aligned and
harmonious with the existing facility and/or system.
Site Condition
The complete electrical system design and selection will be carried out as per the prevailing site
conditions specified in the site datasheet.
However, following information of the project site required for detailed design shall be collected by
the contractor:
All equipment shall be considered, selected and installed as per the hazardous area, prepared in
accordance with the American Petroleum Institute API 505.
Enclosure Protection
All electrical equipment shall be selected based on the minimum ingress protection, as IP 42 for
indoor and IP 66 for outdoor. Mechanical impact resistance for all such electrical equipment shall
be of IK 10.
- Continuous duty (C):- loads that may continuously be required for normal operation.
- Intermittent duty (I):- loads that only operate a fraction of a 24 hour period.
- Standby duty (S):- loads are those that are on standby or rarely operate under normal conditions
The following values of the diversity factors x, y and z, will be used for initial load assessments,
Based on the above voltage level selection, system voltage for tank farm power distribution shall be
as follows:
DESCRIPTION DETAIL
Frequency 50Hz ± 5%
DESCRIPTION DETAIL
Voltage ±10%
TRANSIENT STEADY STATE
Frequency ±5%
LIMITS
Frequency ±5%
Refer MUCOG-192805-ELC-RP-001 - Electrical Supplies Tie in Schedule Rev. A for power supply
and tie-in details.
AC UPS
Existing 230V AC UPS located inside terminal substation will be utilized to feed the new PLC load.
New loads of TGS system shall be verified and accordingly the circuit breakers shall be replaced if
required. Existing CCTV cabinet fed from this existing AC UPS DB will be used to feed one new
proposed CCTV.
Lighting System
Tank farm area shall be considered as per the present scope of work.
All outdoor lighting shall be automatically controlled to switch-on & off; these fittings will have
photocell with timer controlled facility.
Uniformity ratio shall be maintained as a minimum of 0.85 for indoor and 0.4 for outdoor location.
LED type fixtures is used and shall be handrail mounted on 2.5m pole with sufficient height as per
lux level calculation.
Emergency lighting shall be provided in all access ways to permit the safe movement and egress of
people in the event of loss of power to normal lighting. The number of emergency luminaires as a
percentage of the total number of fixtures will be 20% for tank farm area, pump area & utility area,
50% for control room and 30% for electrical switchgear / panel room. Emergency fixtures shall be
equipped with minimum 2 hrs. battery backup.
Power receptacles shall be provided for portable equipment and for power equipment requiring
frequent removal for maintenance. In tank farm, 63 A, 400 V welding receptacles with disconnect
switches shall be provided where welding activities are envisaged. They shall be installed on the
basis of adequate coverage using 15 m extension leads. These sockets shall be feed from existing
903-T-PLDB spare feeders.
New loads for Motor operated Valve (MOV’s) shall be connected to new outdoor (near the tank farm)
MOV-DB-04 and shall be feed from existing feeder (13F3) at panel 903-T-MLTP inside substation,
necessary modification in the existing circuit breaker shall be done after finalizing the total load.
Mixer motors shall be feed from the existing MCC located at terminal substation (903-T-MCC-01),
spare feeders (3R3, 3R4, 4R1, 4R4 & 5F2) shall be used for new loads. Necessary modification in
the existing starters/circuit breakers shall be done after finalizing the load for each Motor.
Motor starters will be verified (existing star-delta) and shall be selected in order to minimize voltage
fluctuation-perturbation (lower inrush currents), increase system reliability and smooth start-up of
the pump. Motors above 11kW will be considered with reduced voltage starting.
Star- delta and DOL will be considered based on the application and rating of the motors.
An underground earth ring shall be laid around the tank farm and pump-motors. All non-current
carrying metallic components of equipment viz. MCC body, distribution boards, cable trays, MOVs,
pumps, terminal box, junction box etc. steel structures, pipe supports, tanks and cable systems shall
be bonded to this ring.
Tank earthing shall be provided by connecting the tanks to stand alone dedicated earth pits installed
around the tank and interconnected to form an earth ring. Each such earth ring around the tanks
The complete earthing system shall have a maximum earth resistance value of 1 (one) ohm or less
when measured at any point of the system.
Lightning protection system shall be considered for protection against atmospheric discharges on
all tanks.
Separate earthing system shall be considered for lightning system and shall be bonded to the main
earth ring in accordance with international standards/codes of practice. Earth resistance for lightning
system shall be less than 5 ohms when measured at any point of system.
Clean earth or instrument earth shall be considered and installed in accordance with international
standards/codes of practice.
Cable type is selected depending on the application and location of the installation, indoors or
outdoors and shall comply with relevant standards.
Conductors shall be circular or sector shaped plain annealed stranded copper in accordance with
IEC 60228.
Low smoke cables shall have galvanized steel round wire armor with outer sheath UV stabilized,
flame retardant, anti-rodent and anti-termite protection.
Control and power cables shall be laid separately in order to avoid the signal interference.
Cable carrier shall be provided for routing all the cables. Cable carrier system comprise of – direct
buried cable trench, concrete duct banks for road crossing, cable perforated / ladder tray, cable
trunking, steel conduit etc.
Allowable voltage drop in various sections of electrical system shall be limited to the following:
However, total voltage drop from Substation to any terminal load shall be less than 5%.
35 INSTRUMENTATION WORKS
The Instrumentation & Control system shall be considered to meet the requirements of Ecomar
Phase II. It shall be independent, reliable and redundant system complete with interface to existing
control systems to provide operation, control and monitoring from the control room.
The following sections of this document outline the Instrumentation & Control Scope of works to be
executed for the Ecomar Phase II Fujairah, UAE. This document is to be read in conjunction with all
issued Instrumentation and other discipline documents, datasheets and drawings.
Contractor shall be deemed responsible to completely understand the scope of works intended for
this project and be thoroughly familiar with the existing facility. Any doubt or ambiguity in interpreting
the project requirements shall be clarified via a Technical Query to the Client/Client representative
during bidding stage. Any failure in complying with the requirement or later asking for Variation Order
shall not be acceptable.
The scope includes Detail Design, Engineering, Procurement, Supply, Installation, inspection and
testing at manufacturer’s work and at site including Site Acceptance tests and Site Integration tests
in presence of Employer/ Employer's representative, preparation for shipment, Dispatch in well
packed condition to site, Receipt and inspection at site, Proper and safe storage, Documentation
and manuals of all equipment / items, installation, termination, testing, commissioning, start up,
Warranty, providing required spares, accessories, special tools, Personnel training, Software
Configuration, Licensing, interface to existing control systems and required modifications in existing
control systems, SCADA Screens development, PLC/DCS Logic Testing, Process Interlocks testing,
ESD Shutdown test, all other related works for the satisfactory operation of complete
Instrumentation, Control and Automation System Works successfully meeting the employer’s
requirement.
The Contractor is responsible to verify the adequacy of the FEED documents enclosed along with
this Employer Requirement. If it is found inadequate by any means, contractor shall bear the
responsibility to verify the engineering and highlight suitable additions or modifications.
The Contractor shall indicate any addition or omission of items / equipment noticed during the pricing
to the Employer/Employer’s Representative before award of Contract. All such items which
contractor deems necessary for the successful completion of the project but not included in the
FEED documents enclosed along with Employer Requirement shall be listed, notified and priced
during Contract finalization stage. Further variation or any financial implication to the Employer shall
not be acceptable.
After award of contract no extra claims or delays shall be entertained otherwise. Contractor shall
take full responsibility of the complete design, schedule and execution henceforth.
Contractor is responsible for any interfacing requirement with other concerned parties for the
successful completion of the project. Any information transferred i.e. received or conveyed shall be
clearly documented for the information of the Employer/Employer’s Representative.
Contractor shall carry out complete Instrumentation system design, selection and installation as per
site conditions specified in Tender documentation.
A new PLC Control system shall be considered for Phase II scope of works. It is preferred to be of
same make as the existing PLC/DCS control systems.
The Phase II PLC shall be interfaced with existing PLC and DCS control systems through redundant
Ethernet network.
The PLC cabinet shall be installed in the Marshalling Room to interface the Phase II signals, the
PLC shall be in redundant hot standby configuration with all the required components such as
Chassis, redundant Power Supply Unit, I/O Cards (DI, DO), Communication Modules for Modbus,
Ethernet, etc. and all the required hardware and software modifications in the existing Control
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
61/72
system shall be considered. PLC Logics and SCADA HMI modifications shall also be considered to
meet the project requirements. Addition of HMI screens for Phase II and modifications in existing
Phase I HMI operator workstations shall also be considered.
The DI cards for Level Switch and ESD Push Buttons, DO Cards for ESD Sounders and MOV
Shutdowns, Modbus communication modules for MOV Master Station shall be considered. Network
modules for Ethernet, control system interface shall be provided. Minimum 20% spare I/Os and
terminations shall be considered in the control system.
The PLC Logics shall be developed and modified for Interlock, Alarm and Trips as per P&IDs,
Process Cause & Effect Matrix and ESD Cause & Effect Matrix.
The emergency shutdown of the terminal pumps and ESD closure of MOVs shall be considered
manually during abnormal conditions like tank overfill, leakage in pipes, high equipment sound or
vibrations, fire scenario, smoke.
Field mounted ESD push buttons and sounders shall be provided outside the bundwall of Feedstock
tank farm and MGO Tank farm at strategic and accessible locations. For field mounted ESD push
buttons, IP 66 rating shall be followed.
The existing ESD Annunciator panel installed in the control room shall be modified with required
ESD push buttons and indication lamps for the phase II requirements.
DI/DO cards in the Phase II PLC system shall be provided for the ESD signals.
Refer Control System Architecture 192805-700-001, ESD Cause & Effect Matrix MUCOG-192805-
INS-CE-001 and Datasheet for ESD Push Button & Sounder MUCOG-192805-INS-DS-005 for
further details.
Tank Gauging is considered for the quantity assessment of liquid products and to determine the
inventory of liquid storage tanks. System design shall be in accordance with API MPMS 3.1B -
Standard Practice for Level Measurement of Liquid Hydrocarbons in Stationary Tanks by Automatic
Tank Gauging. The Tank Gauging system is also considered as primary layer of overfill protection
in the tanks.
The tank gauging system (TGS) shall consist of highly accurate radar level transmitter, multi probe
temperature transmitter (with water bottom sensor) and pressure transmitter for density
measurement. The new Redundant Field Interface units for the Phase II Tank gauging
instrumentation shall be installed in the existing TFMS Cabinet (By Honeywell). It shall be interfaced
with existing Tank Gauging system.
All the required Hardware and components for Phase 2 modifications shall be considered. Signal
Junction Box, cables, Power isolators shall be provided as part of TGS system.
Suitable modification shall be considered in the existing TGS System Workstation and Software to
incorporate the Phase 2 requirements. System shall be capable to handle the addition of new tanks
Refer Tank Gauging System Architecture 192805-700-002, and Datasheet for Tank Gauging
System MUCOG-192805-INS-DS-001 for further details.
The product tanks will be provided with a secondary layer of overfill protection through an
independent Level Switch for High High Level alarm and interlocks. Level switch for Low Low Level
alarm and interlock is also provided.
The Leak detection pit for storage tanks is also provided with Level Switch for High Level alarm.
A new MOV SIMA Master Station shall be provided for Phase II MOV Controls. The Master Station
shall be installed inside the Phase II PLC Cabinet in the Marshalling Room. Master station shall be
provided for open/close of MOVs from control room HMI along with status monitoring and advanced
diagnostics.
The new MOVs shall be connected to the Master Station via redundant Modbus Ring network. Wire
breakage or loss of communication at one end shall not affect the Loop integrity.
The Master station shall be connected to the Phase II PLC by redundant Modbus. The Phase II
MOVs shall be controlled from HMI Workstations in the control room. Interlocks and MOV
Operations shall be configured between the PLC and Master Station.
Hardwired connection of MOVs to the Phase II PLC for MOV Closure during ESD Shutdowns shall
also be provided.
Dedicated 6 MOV Loop shall be provided for the 3 Nos. of Feedstock Tanks.
Dedicated 4 MOV Loop shall be provided for the 2 Nos. of MGO Tanks.
Local Control Station (LCS) shall be considered in the field for the Side Entry Mixers with all the
required push buttons and status indications for control and monitoring.
Refer Datasheet for Local Control Station MUCOG-192805-INS-DS-003 for further details.
As per the CCTV Coverage Study Report by the Vendor Access Star Technologies, Doc No.
SD-102 Rev B (snap shots below), the CCTV-1 & CCTV-2 are covering the MGO Tanks TK-204 &
TK-205 and CCTV-4 & CCTV-6 are covering the Feedstock Tanks TK-201, TK-202 & TK-203
respectively.
One New CCTV camera near CCTV-03 south-east of manifold wall shall be provided. This new
camera must be facing towards the Phase–II Feedstock Tanks TK-201, TK-202 & TK-203. Because
MUCOG-192805-ER-MEC-001 Rev 1 Employer Requirement’s 30 January 2020
63/72
after construction, there shall be blind spots in between TK-101, 102, 103 and new tanks.
The location for the new CCTV camera shall be finalized during detail engineering based on
maximum coverage.
The new CCTV Camera shall be interfaced to existing CCTV System. The existing CCTV system
shall be modified to suit Phase 2 requirements, suitable hardware and software modifications,
additional components, etc shall be considered.
TK-201
The existing firefighting control system consists of PLC based Firefighting deluge control panel in
the control room with interface to the FACP. Suitable hardware and software modifications shall be
considered in the existing system for phase II requirements. Minimum 20% spare I/Os and
terminations shall be considered in the control system.
Contractor shall design the system as per the current Fire & Life Safety code of Fujairah, Civil
Defense and Contractor shall submit a provisional design document / drawing to Civil defense
approval prior to start EPC for fire system.
The Push buttons and indication lamps for the Firewater and foam deluge valve controls shall be
provided on the deluge control panel. Indication lamps for the ‘Tank on fire’ activated through
Pressure switch shall be provided on the deluge control panel.
Firefighting System instrumentation like Quartzoid Bulb detectors (QBD), deluge valves (including
all trim and accessories), pressure switches and pressure gauges shall be considered. Deluge valve
shall have Provision for manual operations in field and also from control room.
The Phase II Deluge Valves and Pressure Switches shall be connected to the existing firefighting
deluge control panel. Suitable modifications and related hardware (I/O Cards, terminal blocks,
relays, cables, push buttons, indication lamps, etc) shall be considered.
The systems shall be installed as needed to protect personnel and the facility by minimizing,
The designed fire water pumping system in phase I shall be dedicated for both phase-I, phase-II
tank farms and processing area. Fire water demand shall be calculated for the largest fire scenario
which requires highest water demand considering the entire Phase-I & Phase-II tank farms. The fire
water / foam solution rings shall be designed as per the demand calculations and the hydraulic
calculation performed based on the worst case demand during Phase I. The fire water demand for
Phase II tanks shall be verified and the existing fire water system shall be adequate to cater the
Phase II tanks demand.
The ring mains provided with sufficient manual isolation valves, so that a small section of the ring
main can be taken out of service and the grid can supply water through adjacent sections to protect
other installations.
Contractor shall verify the surge analysis, check for hydraulic calculations for adequate flow,
pressure at all nodes, and suggest if any pressure release/ control valve needs to be installed, to
avoid u/g HDPE pipe failure.
Design density of 2 lpm / sq. m shall be considered as per IP-19 Fire Precautions at petroleum
Refineries and Bulk Storage Installations. The shell areas for the nearby tanks which falls within
heat radiation contours, shall be considered for cooling during the worst case fire scenario. Cooling
shall not be considered for the tank on fire.
Spray system shall be automatically / remote manually operated from the control room. As soon as
the foam system for a particular tank is activated by the operator from the panel or from the field,
cooling system for the adjacent tanks according to pre-determined segments shall be automatically
activated. In addition, the deluge valve shall be opened manually by the release valve associated
with the deluge valve trim assembly in the field. Provision for manual operations shall also be
provided at field by the manual release valve associated with the deluge valve trim assembly in the
field. QB detectors to operate at a temperature of 93deg.C shall be placed around all the storage
tanks. Contractor shall confirm the requirement of QB detectors or LHD (as per Civil defense
requirement) during detailed engineering. The “Tank on Fire” alarm from QB Detection system and
“Deluge Valve Open” status indication shall be transmitted to dedicated ‘Fire Fighting Deluge Control
Panel’ located at control room.
All tie-in connections shall be made from existing firefighting system. The tie-in connections needed
for Phase II tanks firefighting shall be tie-in from Phase I and confirmed at site during detailed
engineering. In case tie-in connections are not available, new tie-in connections shall be made as
per Phase II demand during detailed engineering
37.1 Drawings
37.2 Datasheets
Sl. No DESCRIPTION DOCUMENT NO:
Product
1 Product Datasheet 192805-PRC-PDS-001
Mechanical
Technical Data Sheet Feedstock Storage Tank
1 MUCOG-192805-MEC-DS-001
30-TK-201, 30-TK-202 & 30-TK- 203
Technical Data Sheet MGO Storage Tank 30-
2 MUCOG-192805-MEC-DS-002
TK-204 & 30-TK- 205
3 Technical Data Sheet Side Entry Mixers MUCOG-192805-MEC-DS-003
Electrical
Technical Data Sheet Low Voltage Electrical
1 MUCOG-192805-ELC-DS-001
Cable
Technical Data Sheet Low Voltage AC
2 MUCOG-192805-ELC-DS-002
Distribution Board
Instrumentation
Technical Data Sheet Tank Gauging System
1 MUCOG-192805-INS-DS-001
Radar Level Transmitter
2 Technical Data Sheet Level Switch MUCOG-192805-INS-DS-002
3 Technical Data Sheet Local Control Station MUCOG-192805-INS-DS-003
4 Technical Data Sheet MOV Actuator MUCOG-192805-INS-DS-004
Technical Data Sheet ESD Push Button &
5 MUCOG-192805-INS-DS-005
Sounder
Technical Data Sheet Instrument Junction Box &
6 MUCOG-192805-INS-DS-006
Cable Gland
Technical Data Sheet Instrument Signal &
7 MUCOG-192805-INS-DS-007
Control Cables
8 Technical Data Sheet Pressure Gauge MUCOG-192805-INS-DS-008
9 Technical Data Sheet Pressure Switch MUCOG-192805-INS-DS-009
10 Technical Data Sheet CCTV System MUCOG-192805-INS-DS-010
Firefighting
1 Datasheet for Spray Nozzle MUCOG-192805-FF-DS-001
2 Datasheet for Deluge Valve MUCOG-192805-FF-DS-002
3 Datasheet for Foam Chamber MUCOG-192805-FF-DS-003
4 Datasheet for Quartzoid Bulb Detector (QBD) MUCOG-192805-FF-DS-004
Piping
1 Technical Data Sheet Gate Valve ( 2" - 24" ) MUCOG-192805-PIP-DS-001
Piping
1 Piping Material Specification MUCOG-192805-PIP-TS-001
2 Technical Specification for Valves MUCOG-192805-PIP-TS-002
3 Technical Specification for Fittings MUCOG-192805-PIP-TS-003
4 Technical Specification for Flanges MUCOG-192805-PIP-TS-004
5 Technical Specification for Pipes MUCOG-192805-PIP-TS-005
Technical Specification for Standard Pipe
6 MUCOG-192805-PIP-TS-006
Supports
7 Technical Specification for Stress Analysis MUCOG-192805-PIP-TS-007
Piping Fabrication And Examination
8 MUCOG-192805-PIP-TS-008
Specification
9 Technical Specification for Piping Leak Testing MUCOG-192805-PIP-TS-009
Mechanical
1 Technical Specification for Storage Tank MUCOG-192805-MEC-TS-001
2 Technical Specification for Internal Floating Roof MUCOG-192805-MEC-TS-002
Technical Specification for Aluminum Geodesic
3 MUCOG-192805-MEC-TS-003
Dome Roof
4 Technical Specification For Side Entry Mixer MUCOG-192805-MEC-TS-004
Electrical
Technical Specification for Low Voltage
1 MUCOG-192805-ELC-TS-001
Electrical Cables
Technical Specification for Earthing & Lightning
2 MUCOG-192805-ELC-TS-002
Protection System
Technical Specification for Electrical Bulk
3 MUCOG-192805-ELC-TS-003
Material
4 Technical Specification for Electrical Installation MUCOG-192805-ELC-TS-004
Technical Specification for Low Voltage AC
5 MUCOG-192805-ELC-TS-005
Distribution Board