Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 )

between KM 229.00 to 248.4 old NH - 4 between Hubli - Darwad from


Hosur at Hubli to Jublee circle at Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR: GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

G S B M i x R e co n c i l i a t i o n
Location Theoretical Qty
S. No Date Side Layer Length Width Thichness Remarks
Layed (m) (m) (m)
From To in Cum. In MT
1 7/6/2012 8.380 8.550 RHS TOP/TEMP DIV 170 3 0.100 51.00 118.73
DENSITY=2.328
2 7/6/2012 6.170 6.280 LHS TOP/TEMP DIV 110 3 0.100 33.00 76.82
3 12/6/2012 7.940 8.270 LHS TOP/MCW 330 11.75 0.150 581.62 1354.02
4 13/6/2012 7.740 7.880 LHS TOP/MCW 140 11.75 0.150 246.75 574.43
5 16/6/2012 7.600 7.710 LHS TOP/MCW 110 11.75 0.150 193.88 451.34
6 19/6/2012 8.550 8.620 RHS TOP/TEMP DIV 70 3 0.100 21.00 48.89
7 5/7/2012 8.330 8.430 LHS TOP/TEMP DIV 100 3 0.100 30.00 69.84
8 7/7/2012 5.800 6.200 RHS TOP/MCW 400 11.75 0.150 705.00 1641.24
9 23/7/2012 8.280 8.330 LHS TOP/MCW 50 11.75 0.150 88.13 205.16
10 30/7/2012 6.200 6.290 RHS TOP/MCW 90 11.75 0.150 158.63 369.28
11 11/9/2012 8.620 9.200 RHS TOP/TEMP DIV 580 2.5 0.150 217.50 506.34
12 12/9/2012 9.620 10.160 LHS TOP/TEMP DIV 540 3 0.150 243.00 565.70
13 13/9/2012 11.560 11.860 LHS TOP/TEMP DIV 300 4.5 0.150 202.50 471.42
14 17/9/2012 11.000 11.300 LHS TOP/TEMP DIV 300 2.5 0.150 112.50 261.90
15 18/9/2012 11.300 11.520 LHS TOP/TEMP DIV 220 4.5 0.150 148.50 345.71
16 26/9/2012 10.200 10.510 LHS TOP/TEMP DIV 310 2.5 0.150 116.25 270.63
17 16/10/2012 7.875 7.916 LHS TOP/MCW 41 11.75 0.150 72.26 168.23
18 17/10/2012 6.290 6.560 RHS TOP/MCW 270 11.75 0.150 475.88 1107.84
19 19/10/2012 8.630 8.820 LHS TOP/MCW 190 11.75 0.150 334.87 780.59
DESITY=2.331
20 19/10/2012 10.150 10.640 LHS TOP/TEMP DIV 490 2.5 0.150 183.75 428.32
21 21/10/2012 10.640 11.030 LHS TOP/TEMP DIV 390 2.5 0.150 146.25 340.91
22 25/10/2012 8.820 9.040 LHS TOP/MCW 220 11.75 0.150 387.75 903.85
23 27/10/2012 9.040 9.240 LHS TOP/MCW 200 11.75 0.150 352.50 821.68
24 3/11/2012 9.600 10.000 RHS TOP/MCW 400 11.75 0.150 705.00 1643.36
25 5/11/2012 11.060 11.300 RHS TOP/MCW 240 12.6 0.150 453.60 1057.34
26 11/11/2012 6.560 6.630 RHS TOP/MCW 70 11.75 0.150 123.37 287.59
27 16/11/2012 11.310 11.690 RHS TOP/MCW 380 12.65 0.150 721.05 1680.77
28 21/11/2012 10.860 11.060 RHS TOP/MCW 200 12.6 0.150 378.00 881.12
29 22/11/2012 10.000 10.150 RHS TOP/MCW 150 12.6 0.150 283.50 660.84
30 27/11/2012 10.580 10.880 RHS TOP/MCW 300 12.6 0.150 567.00 1321.68
31 30/11/2012 10.200 10.260 RHS TOP/MCW 60 12.6 0.150 113.40 264.34
32 1/12/2012 10.260 10.440 RHS TOP/MCW 180 12.6 0.150 340.20 793.01
33 1/12/2012 10.140 10.200 RHS TOP/MCW 60 12.6 0.150 113.40 264.34
34 14/12/2012 9.430 9.500 RHS I/MCW 70 12.9 0.150 135.45 315.73
35 14/12/2012 9.430 9.600 RHS TOP/MCW 170 12.9 0.150 328.95 766.78
36 16/12/2012 9.300 9.430 RHS I/MCW 130 12.9 0.150 251.55 586.36
37 16/12/2012 9.300 9.430 RHS TOP/MCW 130 12.9 0.150 251.55 586.36
38 6/1/2013 11.700 11.870 RHS TOP/MCW 170 12.6 0.150 321.30 748.95
Total Qty 10189.84 23741.42 IN MT
TEMPORARY DIVERSION QTY 1505.25 3505.21
REMARKS:-
MCW QTY 8684.59 20236.21
Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 ) between KM 229.00
to 248.4 old NH - 4 between Hubli - Darwad from Hosur at Hubli to Jublee circle at
Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR : GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

D L C M i x R e co n c i l i a t i o n
Location Theoretical Qty Plant Qty
S. No Date Side Layer Length Width Thichness Remarks
Layed (m) (m) (m)
From To in Cum. In MT in Cum.
1 19/6/2012 7.820 7.875 RHS MCW 55 8.25 0.150 68.06 167.23 62
2 20/6/2012 7.600 7.710 LHS MCW 110 8.25 0.150 136.13 334.46 117
3 1/7/2012 7.987 8.215 LHS MCW 228 8.25 0.150 282.15 693.24 236
4 6/7/2012 8.330 8.430 RHS MCW 100 8.25 0.150 123.75 304.05 96
5 8/7/2012 5.800 5.870 RHS MCW 70 8.25 0.150 86.63 212.84 81
6 9/7/2012 5.870 6.030 RHS MCW 160 8.25 0.150 198.00 486.49 154.75
7 10/7/2012 6.030 6.192 RHS MCW 162 8.25 0.150 200.48 492.57 178
8 8/8/2012 7.710 7.765 LHS MCW 55 8.25 0.150 68.06 167.23 62
9 9/8/2012 7.917 7.987 LHS MCW 70 8.25 0.150 86.63 212.84 76
10 9/8/2012 8.165 8.172 LHS MCW 7 8.25 0.150 8.66 21.28 9
11 10/8/2012 8.215 8.289 LHS MCW 74 8.25 0.150 91.57 225.00 92
12 12/8/2012 8.291 8.334 LHS MCW 43 8.25 0.150 53.21 130.74 54
13 16/10/2012 7.875 7.916 LHS MCW 41 8.25 0.150 50.74 124.66 51
14 18/10/2012 6.360 6.550 RHS MCW 190 8.25 0.150 235.13 577.70 220
15 20/10/2012 6.280 6.360 RHS MCW 80 8.25 0.150 99.00 243.24 97
16 22/10/2012 6.192 6.280 RHS MCW 88 8.25 0.150 108.90 267.57 110
17 25/10/2012 8.640 8.913 LHS MCW 273 8.25 0.150 337.84 830.07 320
18 28/10/2012 8.913 8.941 LHS MCW 28 8.25 0.150 34.65 85.14 40
19 30/10/2012 8.941 9.228 LHS MCW 287 8.25 0.150 355.16 872.63 317
20 4/11/2012 9.700 9.820 RHS MCW 120 8.25 0.150 148.50 364.86 140
21 4/11/2012 9.855 9.985 RHS MCW 130 8.25 0.150 160.87 395.27 117
22 10/11/2012 9.820 9.855 RHS MCW 35 8.25 0.150 43.31 106.42 40
23 10/11/2012 9.620 9.700 RHS MCW 80 8.25 0.150 99.00 243.24 95
24 12/11/2012 6.550 6.630 RHS MCW 80 8.25 0.150 99.00 243.24 86
25 16/11/2012 11.425 11.682 RHS MCW 257 8.25 0.150 318.04 781.42 270
26 18/11/2012 11.141 11.425 RHS MCW 284 8.25 0.150 351.45 858.59 332
27 22/11/2012 10.910 11.141 RHS MCW 231 8.25 0.150 285.86 698.36 255
28 28/11/2012 10.590 10.910 RHS MCW 320 8.25 0.150 396.00 967.43 370
29 29/11/2012 10.450 10.590 RHS MCW 140 8.25 0.150 173.25 423.25 173
30 15/12/2012 9.450 9.620 RHS MCW 170 8.25 0.150 210.38 513.95 230
MCW Total Qty 4910.40 12045.02 4480.75
TEMPORARY DIVERSION&Internal purpose QTY 830.00
REMARKS:-
MCW QTY 4910.40 12045.02 4480.75
Total Plant QTY 5310.75
20MM(30%) 10MM(20%) Dust(50%) CEMENT

Material
consumption for
DLC in MT 3824 2549 6373 850
Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 ) between KM 229.00
to 248.4 old NH - 4 between Hubli - Darwad from Hosur at Hubli to Jublee circle at
Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR : GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

P Q C M i x R e co n c i l i a t i o n
Location Theoretical Qty Plant Qty
S. No Date Side Layer Length Width Thichness Remarks
Layed (m) (m) (m)
From To in Cum. In MT in Cum.
1 20/11/2012 5.800 5.920 RHS MCW 120 7.25 0.320 278.40 746.95 240
2 22/11/2012 5.920 6.020 RHS MCW 100 7.25 0.320 232.00 622.46 240
3 28/11/2012 6.020 6.200 RHS MCW 180 7.25 0.320 417.60 1120.42 430
4 30/11/2012 6.200 6.410 RHS MCW 210 7.25 0.320 487.20 1307.16 463
5 1/12/2012 6.410 6.460 RHS MCW 50 7.25 0.320 116.00 311.23 130
6 2/12/2012 6.460 6.605 RHS MCW 145 7.25 0.320 336.40 902.56 350
7 4/12/2012 7.610 7.750 LHS MCW 140 7.25 0.320 324.80 871.44 367
8 5/12/2012 7.740 7.770 LHS MCW 30 7.25 0.320 69.60 186.74 60
9 612/2012 7.770 7.980 LHS MCW 210 7.25 0.320 487.20 1307.16 500
10 7/12/2012 7.980 8.085 LHS MCW 105 7.25 0.320 243.60 653.58 260
11 8/12/2012 8.085 8.245 LHS MCW 160 7.25 0.320 371.20 995.93 390
12 10/12/2012 8.245 8.420 LHS MCW 175 7.25 0.320 406.00 1089.30 380
13 11/12/2012 8.650 8.770 LHS MCW 120 7.25 0.320 278.40 746.95 260
14 13/12/2012 8.770 8.993 LHS MCW 223 7.25 0.320 517.36 1388.08 536
15 18/12/2012 8.993 9.210 LHS MCW 217 7.25 0.320 503.44 1350.73 490
16 19/12/2012 9.630 9.830 RHS MCW 200 7.25 0.320 464.00 1244.91 449
17 20/12/2012 9.830 9.862 RHS MCW 32 7.25 0.320 74.24 199.19 70
18 22/12/2012 9.870 10.030 RHS MCW 160 7.25 0.320 371.20 995.93 370
19 25/12/2012 10.030 10.305 RHS MCW 275 7.25 0.320 638.00 1711.75 600
20 27/12/2012 10.305 10.610 RHS MCW 305 7.25 0.320 707.60 1898.49 670
21 29/12/2012 10.610 10.935 RHS MCW 325 7.25 0.320 754.00 2022.98 700
22 2/1/2013 10.935 11.270 RHS MCW 335 7.25 0.320 777.20 2085.23 720
23 4/1/2013 11.270 11.485 RHS MCW 215 7.25 0.320 498.80 1338.28 460
24 5/1/2013 11.485 11.655 RHS MCW 170 7.25 0.320 394.40 1058.18 350
Total Qty 9748.64 26155.60 9485
20MM 10MM Sand Dust Cement Admixture

Material Consumption for PQC in


MT 4667 6962 4363 2912 3604.30 25
Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 )
between KM 229.00 to 248.4 old NH - 4 between Hubli - Darwad from
Hosur at Hubli to Jublee circle at Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR : GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

P C C M i x R e co n c i l i a t i o n
Plant Qty
Date
S. No Location Side Description Remarks
in Cum.
1 19/4/2012 8+290 LHS BOX CULVERT 6
2 4/5/2012 7+918 LHS BOX CULVERT 8
3 29/5/2012 7+722 LHS BOX CULVERT 10.5
4 16/10/2012 6+255 RHS P.C UTILITY 5
5 19/10/2012 6+255 RHS P.C UTILITY 17
6 31/10/2012 10+204 RHS BOX CULVERT 11
7 3/11/2012 6+600 RHS P.C UTILITY 6
8 17/11/2012 9+431 RHS BOX CULVERT 6
9 29/11/2012 8+472 LHS BOX CULVERT 11
10 9/12/2012 11+913 RHS BOX CULVERT 15
Total Site Qty 95.5
Internal Purpose & Lakshemeshwar site Purpose QTY 24.5
Total Qty 120.00
40 MM 20 MM 10 MM Dust Cement Admixture

Material
Consumption for
PCC in MT 67.20 47.76 47.88 99.36 30.00 0.30
Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 )
between KM 229.00 to 248.4 old NH - 4 between Hubli - Darwad from
Hosur at Hubli to Jublee circle at Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR : GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

M-25 M i x R e co n c i l i a t i o n
Plant Qty
S. No Date Location Side Description Remarks
in Cum.
1 29/4/2012 8+290 LHS B.C RAFT 23
2 3/5/2012 8+290 LHS B.C HAUNCH 3
3 10/5/2012 8+290 LHS B.C WALL'S 6.5
4 12/5/2012 7+918 LHS B.C RAFT 15
5 16/5/2012 7+918 LHS B.C HAUNCH 2.5
6 19/5/2012 7+918 LHS B.C WALL'S 5
7 23/5/2012 8+290 LHS B.C SLAB 12
8 30/5/2012 7+918 LHS B.C SLAB 15
9 5/6/2012 7+722 LHS B.C RAFT 23.5
10 9/6/2012 7+722 LHS B.C HAUNCH 5
11 14/6/2012 7+722 LHS B.C WALL'S 13.5
12 25/6/2012 7.722 LHS B.C SLAB 28.5
13 5/11/2012 10+204 RHS B.C RAFT 32
14 10/11/2012 10+204 RHS B.C WALL'S 5
15 11/11/2012 10+204 RHS B.C HAUNCH 5
16 19/11/2012 10+204 RHS B.C SLAB 13.5
17 22/11/2012 9+431 RHS B.C RAFT 25.75
18 24/11/2012 9+431 RHS B.C HAUNCH 2
19 26/11/2012 9+431 RHS B.C WALL'S 6.5
20 1/12/2012 9+431 RHS B.C SLAB 13
21 7/12/2012 8+473 LHS B.C RAFT 25
22 10/12/2012 8+473 LHS B.C HAUNCH 3.5
23 12/12/2012 8+473 LHS B.C WALL'S 12
24 13/12/2012 11+913 RHS B.C RAFT 24
25 17/12/2012 8+473 LHS B.C SLAB 15
26 18/12/2012 11+913 RHS B.C WALL'S 12
27 21/12/2012 11+913 RHS B.C WALL'S 8.5
28 26/12/2012 11+913 RHS B.C SLAB 13.5
Total Site Qty 368.75
LAKSHEMESHWAR SITE & INTERNAL PURPOSE QTY 51
Total Plant Qty 419.75

20MM 10 MM Sand Dust Cement Admixture

Material Consumption
for PQC in MT 216 319 128 194 143 1
Construction of 4 - Laning of Mangsuli - Lakshmeshwar( SH - 73 ) between KM 229.00 to 248.4
old NH - 4 between Hubli - Darwad from Hosur at Hubli to Jublee circle at Dharwad.

AUTHORITY : Karnataka Road Development Corporation Limited


CONTRACTOR : GVR Infra Projects Ltd.
CONSULTANTS : M/s Willbersmith Associates Pvt Ltd.

ALL Material Consumption Report


SI.NO TYPE OF MATERIAL QUANTITY(IN MT)
1 40 MM 67
2 20 MM 8755
3 10 MM 9878
4 SAND 4491
5 DUST 9578
6 CEMENT 4627
7 ADMIXTURE 26.3
8 GSB 23741
9 DLC(Cum) 5311
10 PQC(cum) 9485
11 M-15 or PCC(cum) 120
12 M-25(cum) 420