Professional Documents
Culture Documents
Change Out Pipe Spinner
Change Out Pipe Spinner
Recommendations to Eliminate or
Work Sequence (Job Steps) Hazards or Potential Incidents
Reduce Hazards
1. Pre job safety meeting. Personal injury. Refer RMS procedure above.
2. Remove hoses & bottom up line. Pressured lines. Bleed down air pressure first, replace.
4. Remove from Rig floor. Caught between objects, falling. Use tag lines and correct pick-up points. Use
crane, one-person give directions, competent
person on tugger.
5.
6.
7.
8.
List Below the Personal Protective Equipment, Special Tools and Other Safety Equipment Required to do this Job
Gloves, Safety glasses, Safety boots/ hardhat.
SIGN-OFF
F0782 (2) Original – Rig Files Copy – Area Office Copy – Houston Office Page 1 of 1