JOB SAFETY ANALYSIS (JSA)

Country / Location: ALGERIA Date


Description of Job Ref.: RMS 4 Level 3 Tab-16 OPS-038-5.4 Rig:
or Work Activity: Change Out Pipe Spinner JSA # 0014

Recommendations to Eliminate or
Work Sequence (Job Steps) Hazards or Potential Incidents
Reduce Hazards
1. Pre job safety meeting. Personal injury. Refer RMS procedure above.

2. Remove hoses & bottom up line. Pressured lines. Bleed down air pressure first, replace.

3. Attach tugger. Fall, pinching. Use stepladder and fall arrestor.

4. Remove from Rig floor. Caught between objects, falling. Use tag lines and correct pick-up points. Use
crane, one-person give directions, competent
person on tugger.
5.

6.

7.

8.

List Below the Personal Protective Equipment, Special Tools and Other Safety Equipment Required to do this Job
Gloves, Safety glasses, Safety boots/ hardhat.

SIGN-OFF

JSA Written By: JSA Approved By:

Job Title: Job Title: RIG MANAGER

F0782 (2) Original – Rig Files Copy – Area Office Copy – Houston Office Page 1 of 1