Environmental Management: Specification 204
Environmental Management: Specification 204
ENVIRONMENTAL
MANAGEMENT
Copyright MAIN ROADS Western Australia
Specification 204 Environmental Management Major Works – 04/10095 Issued 06/08/2020
REVISION REGISTER
Clause Authorised
Description of Revision Date
Number By
CONTENTS
Clause Page No
GENERAL .................................................................................................................... 5
204.01 Scope ............................................................................................................... 5
204.02 References ....................................................................................................... 5
204.03 Definitions ......................................................................................................... 5
204.04 – 204.05 NOT USED ........................................................................................ 6
PLANNING ................................................................................................................... 7
204.16 Legal and Other compliance Requirements ...................................................... 7
204.17 Risks and Opportunities.................................................................................... 8
204.18 Construction Environmental Management Plan ................................................ 8
204.19 – 204.20 NOT USED ........................................................................................ 8
IMPLEMENTATION ..................................................................................................... 9
204.21 Roles and Responsibility................................................................................... 9
204.22 Training and Competency ............................................................................... 10
204.23 Communication ............................................................................................... 11
204.24 Documentation ............................................................................................... 11
204.25 Construction Environmental Operational Controls .......................................... 12
204.26 Emergency Preparedness and Response....................................................... 12
204.27 Environmental Incidents ................................................................................. 13
204.28 – 204.30 NOT USED ...................................................................................... 14
GENERAL
204.01 SCOPE
1. The work under this specification consists of setting out the
Principal’s minimum environmental and heritage requirements for the
work under the Contract, through the development and implementation
of a Construction Environmental Management Plan (CEMP).
2. This Specification is based on AS/NZS ISO 14001.
204.02 REFERENCES
204.03 DEFINITIONS
ENVIRONMENTAL POLICY
204.06 MAIN ROADS ENVIRONMENTAL POLICY
https://www.mainroads.wa.gov.au/community-environment/environment/
https://www.mainroads.wa.gov.au/technical-commercial/contracting-to-
main-roads/
PLANNING
204.16 LEGAL AND OTHER COMPLIANCE REQUIREMENTS
1. The Contractor must identify and have access on site to all Legal and
relevant legal and other requirements that are applicable to the Other
Requirements
environmental aspects of the activities associated with the works
undertaken in the Contract.
4. The Contractor must determine how any other relevant legal Legal and
and other requirements apply to the environmental aspects of the Other
Requirements
activities associated with the Works undertaken in the Contract.
IMPLEMENTATION
204.21 ROLES AND RESPONSIBILITY
3. The CEMP must detail the procedures and processes that Sub-
the Contractor must implement to ensure subcontractors at all times contractors
comply with the requirements of the approved CEMP.
204.23 COMMUNICATION
1. The Contractor must detail in the CEMP the procedures that Communication
will ensure that personnel are suitably consulted and communicated with
during the planning and application of work activities associated with the
Contract (e.g. pre start meetings).
2. The Contractor must detail in the CEMP the procedures for Risks
the identification, assessment and control of the risk associated with the
day-to-day work activities. These procedures must include
requirements for consultation with personnel involved in the work
activity.
204.24 DOCUMENTATION
3. The CEMP must address all the work under the Contract CEMP
and must detail all procedures, processes, work practices and
information required by the Contract.
1. The Contractor must ensure that their Emergency Response Spec 203
Plan and emergency procedures are in accordance with the requirement
of Specification 203 OCCUPATIONAL HEALTH AND SAFETY.
1. The CEMP must detail who will be responsible for notifying CEMP
and the reporting and submitting of environmental incident
notifications to Main Roads. The CEMP must also detail the
Contractor’s investigation procedures. The procedures must ensure
that corrective and preventative actions are implemented in a timely
manner to prevent a recurrence.
3. The Contractor must utilise the Main Roads EQSafe for all EQSafe
environmental incident reporting.
https://www.mainroads.wa.gov.au/technical-commercil/contracting-
to-main-roads/
incident.
https://www.mainroads.wa.gov.au/technical-commercial/contracting-to-
main-roads/
MANAGEMENT REVIEW
204.41 REVIEW
d) audit results;
e) resources;
f) relevant communication from interested parties
including complaints; and
g) opportunities for continual improvement.
ANNEXURE 204A
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN TEMPLATE
ANNEXURE 204B
PRINCIPAL ENVIRONMENTAL MANAGEMENT REQUIREMENTS
DURING WORKS
Insert text from Aboriginal Heritage PEMR
POST WORKS
Insert text from Aboriginal Heritage PEMR
204B.2 ACID SULFATE SOILS - PUT NOT USED IF NOT APPLICABLE AND
DELETE TABLES
DURING WORKS
Insert text from Acid Sulfate PEMR
POST WORKS
Insert text from Acid Sulfate PEMR
204B.3 CAMPS AND SITE OFFICES - PUT NOT USED IF NOT APPLICABLE AND
DELETE TABLES
DURING WORKS
Insert text from Camp and Site Office PEMR
POST WORKS
Insert text from Camp and Site Office PEMR
Locations of Approved Camps and Site Offices are within Specification 100
204B.4 CLEARING - PUT NOT USED IF NOT APPLICABLE AND DELETE TABLES
DURING WORKS
Insert text from Clearing PEMR
POST WORKS
Insert text from Clearing PEMR
DURING WORKS
Insert text from Dewatering PEMR
POST WORKS
Insert text from Dewatering PEMR
DURING WORKS
Insert text from Contaminated Sites PEMR
POST WORKS
In Insert text from Contaminated Sites PEMR
DURING WORKS
Insert text from Dewatering PEMR
POST WORKS
Insert text from Dewatering PEMR
DURING WORKS
Insert text from Dewatering PEMR
POST WORKS
Insert text from Dewatering PEMR
DURING WORKS
Insert text from Contaminated Sites PEMR
POST WORKS
In Insert text from Contaminated Sites PEMR
DURING WORKS
Insert text from Contaminated Sites PEMR
POST WORKS
In Insert text from Contaminated Sites PEMR
DURING WORKS
Insert text from Dust Management PEMR
POST WORKS
Insert text from Dust Management PEMR
DURING WORKS
Insert text from Dust Management PEMR
POST WORKS
Insert text from Dust Management PEMR
DURING WORKS
Insert text from Erosion and Sedimentation Control PEMR
POST WORKS
Insert text from Erosion and Sedimentation Control PEMR
DURING WORKS
Insert text from Contaminated Sites PEMR
POST WORKS
In Insert text from Contaminated Sites PEMR
DURING WORKS
Insert text from Contaminated Sites PEMR
POST WORKS
In Insert text from Contaminated Sites PEMR
DURING WORKS
Insert text from Fencing Installation PEMR
POST WORKS
Insert text from Fencing Installation PEMR
204B.17 FIRE MANAGEMENT - PUT NOT USED IF NOT APPLICABLE AND DELETE
TABLES
DURING WORKS
Insert text from Fencing Installation PEMR
POST WORKS
Insert text from Fencing Installation PEMR
DURING WORKS
Insert text from Fencing Installation PEMR
POST WORKS
Insert text from Fencing Installation PEMR
DURING WORKS
Insert text from Machinery and Vehicle Management PEMR
POST WORKS
Insert text from Machinery and Vehicle Management PEMR
204B.22 MULCH AND TOP SOIL MANAGEMENT - PUT NOT USED IF NOT
APPLICABLE AND DELETE TABLES
DURING WORKS
Insert text from Mulch and Topsoil Management PEMR
POST WORKS
Insert text from Mulch and Topsoil Management PEMR
DURING WORKS
Insert text from Noise Management PEMR
POST WORKS
Insert text from Noise Management PEMR
204B.24 PEGGING AND FLAGGING - PUT NOT USED IF NOT APPLICABLE AND
DELETE TABLES
DURING WORKS
Insert text from Pegging and Flagging PEMR
POST WORKS
Insert text from Pegging and Flagging PEMR
DURING WORKS
Insert text from Pre Coating PEMR
POST WORKS
Insert text from Pre Coating PEMR
DURING WORKS
Insert text from Pre Coating PEMR
POST WORKS
Insert text from Pre Coating PEMR
DURING WORKS
Insert text from Property Condition Survey PEMR
POST WORKS
Insert text from Property Condition Survey PEMR
DURING WORKS
Insert text from Property Condition Survey PEMR
POST WORKS
Insert text from Property Condition Survey PEMR
204B.30 ROAD MARKING - PUT NOT USED IF NOT APPLICABLE AND DELETE
TABLES
DURING WORKS
Insert text from Road Marking PEMR
POST WORKS
Insert text from Road Marking PEMR
DURING WORKS
Insert text from Sealing Priming and Sweeping PEMR
POST WORKS
Insert text from Sealing Priming and Sweeping PEMR
DURING WORKS
Insert text from Sidetracks and Temporary Access Tracks PEMR
POST WORKS
Insert text from Sidetracks and Temporary Access Tracks PEMR
DURING WORKS
Insert text from Demarcating and Protecting Special Environmental Areas PEMR
POST WORKS
Insert text from Demarcating and Protecting Special Environmental Areas PEMR
DURING WORKS
Insert text from Spills PEMR
POST WORKS
Insert text from Spills PEMR
DURING WORKS
Insert text from Spoil PEMR
POST WORKS
Insert text from Spoil PEMR
DURING WORKS
Insert text from Property Condition Survey PEMR
POST WORKS
Insert text from Property Condition Survey PEMR
DURING WORKS
Insert text from Traffic Management PEMR
POST WORKS
Insert text from Traffic Management PEMR
DURING WORKS
Insert text from Vibration Management PEMR
POST WORKS
Insert text from Vibration Management PEMR
DURING WORKS
Insert text from Water Abstraction PEMR
POST WORKS
Insert text from Water Abstraction PEMR
DURING WORKS
Insert text from Water Abstraction PEMR
POST WORKS
Insert text from Water Abstraction PEMR
DURING WORKS
Insert text from Surface Water Drainage Management PEMR
POST WORKS
Insert text from Surface Water Drainage Management PEMR
DURING WORKS
Insert text from Water Abstraction PEMR
POST WORKS
Insert text from Water Abstraction PEMR
DURING WORKS
Insert text from Water Abstraction PEMR
POST WORKS
Insert text from Water Abstraction PEMR
All edits to downloaded TDP documents shall be tracked (most word processing
software allows this to be done automatically). Deletions shall be struck through e.g.
example. Insertions shall be in italics e.g. example. If all information relating to a clause
is deleted then the clause number should be retained and the words "NOT USED"
should be inserted.
The proposed documents with tracked changes shall be submitted to the Project
Manager for review, prior to printing the final batch of documents. When this final
printing is carried out, the tracked changes option is to be turned off.
Main Roads Specification 204 requires the Contractor to develop and implement a
CEMP. This Specification lays out the Principal’s minimum environmental and heritage
requirements that the Contractor must develop and detail in the CEMP to deliver the
Works. The CEMP template will assist the Contractor in developing a CEMP for the
works under the Contract.