THE PROVISION OF PIPELINE INSTALLATION

SERVICES

SMG1 FLOWLINE PROJECT

JSA
CONTRACT N°……………………………………………………………….. Rev: 0
Page: 1 of 2

JOB SAFETY ANALYSIS (JSA)


Location: Person in charge: Date:
Work activity (Job): backfilling
Work team:
Potential accidents or hazards Recommendations to eliminate or reduce potential hazards associated
Sequence of basic job steps
associated with each step with each step
Backfilling and Compacting Soils Slips, Trips, Falls • Clear walkways, work areas of equipment, tools, construction
debris and other materials
• Mark, identify, or barricade other obstructions

Handling Heavy Objects • Observe proper lifting techniques


• Use mechanical lifting equipment (hand carts, trucks) to move
large, awkward loads

Struck by/ Against Heavy • Wear reflective hi-vis vests when exposed to vehicular traffic
Equipment, Flying Debris, • Isolate equipment swing areas
Protruding Objects • Barricade or enclose the work area
• Restrict work area entry to authorized personnel only during
construction activities
• Understand and review hand signals

Vibration • Rotate compaction tasks to minimize worker exposure to


equipment vibration
• Use compactors with vibration dampening devices

High Noise Levels • Use hearing protection when exposed to excessive noise levels (greater
than 85 dB over an 8-hour work period)
THE PROVISION OF PIPELINE INSTALLATION
SERVICES

SMG1 FLOWLINE PROJECT

JSA
CONTRACT N°……………………………………………………………….. Rev: 0
Page: 2 of 2

• Assess noise level with sound level meter if possibility exists that level
may exceed 85dBA TWA