Professional Documents
Culture Documents
Turner 102012 08182016feature PDF
Turner 102012 08182016feature PDF
Turner 102012 08182016feature PDF
Commissioning
Design/Build Projects
By Stephen C. Turner, P.E., Member ASHRAE; Mark Hogil Jung; Seung Hwan Hwang apply so clearly to design/build where
T
design and construction overlap.
he commissioning (Cx) process is not one-size-fits-all. For example, LEED and other systems such as the
Collaborative for High Performance
in a design/build1 project, design occurs during the construction Schools (CHPS) view commissioning
as so essential to sustainability that they
phase, requiring changes to the traditional commissioning process. This mandate commissioning.4 The bias to-
ward design/bid/build in the traditional
article discusses these differences in commissioning for a design/build commissioning process is also reflected
in such rating systems. For example,
project vs. a design/bid/build project using examples from practice, LEED credits are designated either
“design” or “construction.” LEED fun-
including an example from a net zero energy school project. damental commissioning focuses on
construction activities, while enhanced
Commissioning Process Guideline 0-2005 and Design/Build commissioning includes design activi-
The commissioning process has The distinguishing characteristic of ties.5
evolved over the last three decades as traditional design/bid/build, at least in Since design/build delivery blurs the
the owners’ quality process focuses theory, is that the design phase ends lines between design phase and con-
on verifying and documenting that prior to the start of construction. The struction phase, the Guideline 0-2005
the final built project meets the own- commissioning process in ASHRAE Cx process can be more costly and less
ers’ project requirements (OPR).2 Guideline 0-2005 follows this sequential effective, diverting Cx resources from
ASHRAE started developing guidance approach to the delivery process (Figure the substantive technical work that is so
on commissioning in 1982, and pub- B.1 of Guideline 0-2005). The design essential to an effective Cx approach.
lished Guideline 0, The Commission- phase and the commissioning activities
ing Process, in 1989. Commissioning conducted during design all occur prior
has proven to be a cost-effective en- to the construction phase2 to ensure the About the Authors
hancement that improves building per- best possible set of bid documents. This Stephen C. Turner, P.E., is president and senior
commissioning authority with Stephen Turner Inc.,
formance, or at least performance of is followed by construction phase com-
in Providence, R.I. Mark Hogil Jung is a project
commissioned systems, with respect to missioning to ensure those documents manager with Cheil Worldwide in Seoul. Seung
energy, sustainability, and indoor envi- are realized in the built project. How- Hwan Hwang is a commissioning analyst with
ronmental quality.3 ever, this traditional approach does not Stephen Turner Inc.
BOD – Basis of design; Specs – Specifications; PFC – Prefunctional checklist; FPT – Functional performance testing; O&M – Operations and maintenance
Figure 2: Se-
quence of com-
missioning tasks
on design/build
projects.
Ideally, the Cx process should be tailored to suit design/build, between design and construction, the project phases as well as
so that it is more effective and less costly to provide than the the commissioning tasks are reordered and overlap. Therefore,
unmodified Guideline 0-2005 process. a series of tasks in a single line sequence, as used for the de-
sign/bid/build process, no longer suffices.
Commissioning Design/Bid/Build Projects The commissioning tasks in Figure 2 are presented in Gantt
Figure 1 shows a simplified time line to illustrate the chart format to clarify the extended time frames and the over-
phases of a design/bid/build project, and the series of tasks lapping of commissioning tasks. “Pre-spec” in this figure is
that make up the commissioning process. With the design an abbreviated reference to the documents used by the owner
completed prior to the construction phase, the project design to solicit design/build proposals, sometimes called bridging
and construction tasks as well as the commissioning tasks documents.
are sequential with little overlap. Because of this, a simple The commissioning process should reflect the realities of
linear flow chart can be used to represent the commissioning design/build in plans and schedules, and also requires non-
process and its sub-tasks. This particular example shows the trivial changes in the commissioning process. For example,
LEED-required approach to design review. The back-check the approach to commissioning design review may require
of the design documents is listed here as “Design Review 2.” substantial revision for design/build projects. Instead of all-
encompassing reviews of complete sets of project documents,
Commissioning Design/Build Projects partial document packages may require phased review over
Figure 2 shows a similar time line to illustrate the simpli- an extended period of time to support a design/build project’s
fied phases of a design/build project. Because of the overlap progress.
Commissioning Authority (CxA) is first consultant hired by owner and approved submittals prior to delivery or start of installation
(prior to developing bridging documents or issuing design/build of each system or component
RFP)
Engineer of record required to attendance of at least six Cx
meetings during construction
CxA develops OPR prior to Design/Build team selection
Design/build team required to review draft PFCs and FPTs
CxA performs initial design review of Design/Build bridging docu- prior to implementation
ments prior to bid
Requirements to perform & document start-up, TAB, & con-
CxA performs phased design review of Design/Build packages as trols point to point checks prior to FPTs
they are issued throughout the project Required response in the event of repeated failures of FPTs on
major components
Cx specifications are issued with bridging documents and include:
Cx schedule, required to be incorporated into master project Required response in the event of numerous failures of FPTs
schedule on repetitive components such as VAV boxes
Formal Cx notifications protocol, while reserving the right to Requirements to provide As-Builts, O&Ms, final controls pro-
communicate informally with sub-consultants and sub-con- gramming and setpoints, and other detailed information to CxA
tractors when expeditious
Draft PFCs and FPTs before construction, and finalize based on
Requirements for formal submittals from trade contractors for approved submittals after construction start
review by engineer of record
All related submittals required prior to review, i.e., controls Single Cx issues log includes all issues whether from design re-
product data will not be reviewed by CxA until controls engi- view, construction, FPTs, or other source
neering drawings are provided
CxA provides monthly briefing to owner’s project manager sum-
Requirements for timely responses to Cx design issues by en- marizing Cx status and noting Cx issues where owner’s help to
gineer of record expedite Design/Build team response is requested
Requirements for CxA to receive reviewed design package
Design Review design review could not be performed until two months prior
Planning commissioning design reviews so that they occur to completion of construction. The resulting discontinuity in
at the appropriate phase of design is complicated by the de- the commissioning design reviews from the bridging docu-
sign/build approach, since design is occurring well into the ments to construction diminished the impact of the second
construction phase. Since the bridging documents set the bar design review, since the ability to influence the design had
for the quality that the design/build team will have to deliver, dropped so far by the time the review was performed.
commissioning review is very important. On a recent simple Another approach is to offer a phased design review pro-
dormitory project, a small, fast track LEED-NC 2009 project cess, with necessary fee adjustments to cover the additional
with simple MEP systems, the second design review was co- effort. This allows timely commissioning review of each as-
ordinated with the design/build team to occur near the end of pect of the design as it is completed, before it is too late to
coordination when the MEP design was “locked down.” This influence that area of the design.
was effective because the design of the commissioned systems
were all completed around the same time. Submittal Review
The commissioning authority will often have to perform
Phased Design Review submittal review in phases over an extended period of time
On more complex design/build projects, the design does not on design/build projects. This is particularly true when differ-
typically become fixed early in the construction phase. To fur- ent aspects of the design are completed early on, while other
ther complicate planning the commissioning process, different aspects of design are still in flux. In some cases, it may be
aspects of the design may be completed early on, while other appropriate to insist on waiting to perform commissioning
aspects of design are still not fixed. This can delay the second review if related submittals have not yet been received. For
commissioning design review and, as shown previously, also example, controls product submittals are rarely reviewed prior
diminishes the extent to which the commissioning review can to receipt of the controls engineering plans, since it is typi-
influence the design. cally infeasible to review the product submittals without the
To address this complication on a recent college athletics controls plans in hand.
center with natatorium, a large, complex project with exten- Design/build bridging documents should clearly require a
sive MEP and on-site renewable energy systems, the second formal submittal review process. On projects without this, de-
64 A S H R A E J o u r n a l October 2012