Professional Documents
Culture Documents
Agreement and Conditions 0F C0ntracts - JBC PDF
Agreement and Conditions 0F C0ntracts - JBC PDF
OF CONTRACT FOR
BUILDING WORKS
PUBLISHED BY
CLAUSE PAGE
1.11.3 Having arisen, such party could not reasonably have avoided or
Overcome,
1.14 Final account – Means the document prepared by the Quantity Surveyor
The conditions of contract and which in his opinion is the total value of
1.15 Materials and goods – Means things of all kinds and all supplies delivered
1.16 Prime cost sum – Means a sum included in the contract bills for Works
1.17 Provisional sum – Means a sum included in the contract bills for the
1.18 Site – Means the place or places where the permanent Works are
Are being prepared for incorporation in the Works either by the Contractor, sub-contractor or
by others.
1.19 Works – Means the permanent works designed for the Employer by the Architect or
other agents for execution by the contractor and as Described in the contract documents. It
shall include work of all Sub-contractors and suppliers as well as materials and goods supplied
1.20 All reference to days shall mean calendar days of 24 hours duration
And shall include non-working days unless otherwise stated.
1.21 Unless inconsistent with the context, the masculine includes the
Feminine, the singular includes him plural and vice versa.
1.22 Titles and headings are for reference purposes only and do not form
Part of these conditions. They shall not be taken into consideration in The interpretation of
these conditions or the contract.
2.0 ARTICLES OF AGREEMENT
Situated at)…………………………………………………………………………………………………………..
………………………………………………………………………………………………………………………………….
…………………………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………………………
Drawings, bills of quantities and specifications showing and describing the work to be Done to
be prepared by or under the directions of an Architect.
2.3 AND WHEREAS the Contractor has supplied the Employer with a priced copy of the said
…………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………. (Hereinafter)
Referred to as the “the contract drawings”) the contract bills and the specifications have
2.4 For the consideration hereinafter stated, the Contractor shall upon and subject
To the conditions annexed hereto carry out and complete the Works shown upon
The contract drawings and described by or referred to in the contract bills, the
2.5 The Employer shall pay to the Contractor the sum of kshs. (In words)………………….
………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………
Or such sum as shall become payable hereinafter at the times and in the manner
2.6 The Employer shall appoint a representative whose name shall be communicated in
Writing to the Contractor, the Architect and the Quantity Surveyor. The powers and
Duties of the representative shall be deemed to be the same as those of the Employer
…………………………………………………………………………………………………………………………………..
Of……………………………………………………………………………………………………………………………….
And in the event of his ceasing to be the Architect for the purposes of this contract, the
Employer shall appoint another person for that purpose. Such a person shall not be a
Person against whom the Contractor shall object for reasons considered to be sufficient
2.8 No person subsequently appointed to be the Architect under this contract shall be
2.9 The Architect shall appoint a representative whose name shall be communicated in
Writing to the Contractor, the Employer and the Quantity Surveyor. The powers and the
Duties of the representative shall be deemed to be the same as those of the Architect
2.10 The term “the Quantity Surveyor” in this conditions shall mean
…………………………………………………………………………………………………………………………………….
Of………………………………………………………………………………………………………………………………….
And in the event of his ceasing to be the Quantity Surveyor for the purposes of this
Contract, such other person as the Employer shall appoint for that purpose. Such a
Person shall not be a person whom the Contractor shall object for reasons considered
Conditions.
2.11 No person subsequently appointed to be the Quantity Surveyor under this contract
2.12 The Quantity Surveyor shall appoint a representative whose name shall be
Communicated in writing to the Contractor, the Employer and the Architect. The
Powers and duties of the representative shall be deemed to be the same as those
2.13The Employer may appoint Engineers, specialists and other consultants to render
Specialists and other consultants shall be deemed, for the purpose of this contract, to
Engineer or other Specialist (whether named in this agreement or not) the Employer
Shall make such appointment as soon as practicable after the need for such
Appointment arises.
2.15 Where the contract does not incorporate bills of quantities, the terms “contract bills”
And “bills of quantities” wherever appearing shall be deemed deleted and replaced with
………………………………………………………………………………………………………………... (Employer)
………………………………………………………………………………………………………………………………..
Name: …………………………………………………………………………………………………………………….
Address: ……………………………………………………………………………………………………………………
…………………………………………………………………………………………………………… (Contractor)
……………………………………………………………………………………………………………………………….
Name: ……………………………………………………………………………………………………………………
Address: ……………………………………………………………………………………………………………….
2.17 CAUTION
The words ‘Architect,’ ‘Quantity Surveyor’ and ‘Engineer’ are prescribed and protected
by statute for the use of persons registered as such under the relevant laws. If this
document is used by other than such as a registered person, the references appropriate
thereto must be deleted or amended.
2.18 NOTE
2.18.1 When the articles of association of a limited company which is a party to the
contract so require, or
board.
2.18.3 If the contract is to be executed under seal delete “as witness the hands of”
CONDITIONS OF A CONTRACT
Any instructions given given to him by the Architect shall be deemed to have been
9.2 The Contractor shall make his own arrangements for the engagement of all labour
and other workmen, both local or otherwise, required for the Works and shall
comply with statutory, industrial or other rules and regulations governing the
employment and working terms and conditions of labour.
9.3 The Contractor shall be responsible for the observance, by all sub-contractors
(whether nominated or not) of all the foregoing provisions.
9.4 The Architect may (but not unreasonably or vexatiously) issue instructions
requiring the dismissal from the Works of any person employed therein.
10.1 The Employer shall be entitled to appoint a Clerk of Works whose primary
duty shall be to act as inspector of the Works on behalf of the Employer
under the direction of the Architect. The Contractor shall afford every
reasonable facility for the performance of that duty.
10.2 Where a Clerk of Works is appointed, the Employer may also appoint other
persons to assist the Clerk of Works in the exercise of his functions.
directions given by the assistants shall be deemed to be those of the Clerk
of Works unless otherwise stated in writing.
10.3 The employment of a Clerk of Works shall not relieve the Contractor from
any of his duties and obligations under the contract.
10.4 Directions given by the Clerk of Works in writing to the Contractor or to
his site agent shall be deemed to be the Architect’s instructions in respect
of;
10.4.1 The interpretation of Architects instructions, drawings, specifications
or bills of quantities.
10.4.2 The removal from the site of the work, materials or goods which are
in accordance with the contract.
10.4.3 Matters of urgency involving the safety or protection of persons or
property, and
10.4.4 Any other matter in respect of which the Architect is expressly
empowered by these conditions to issue instructions and on which the
Architect has authorized in writing the Clerk of Works so to act.
10.5 Any other directions given by the Clerk of Works to the Contractor or the site
agent shall be of no effect.
11.1 The Contractor shall be liable for and shall indemnify the Employer against
any person arising out of or in the course of or caused by the carrying out of
the Works, unless the injury or death is due to any act or neglect of the
11.2 Except for such loss or damage as is at risk of Employer under clause 14.0
or clause 15.0 of these conditions (if applicable), the Contractor shall be liable
for and shall indemnify the Employer against any expense , liability, loss,
by reason of the carrying out of the Works. Provided always that the injury
12.1 Without prejudice to his liability to indemnify the Employer under clause 11.0
of these conditions, the Contractor shall maintain and shall cause any
sub-contractor to maintain;
12.1.1 Such insurances as are necessary to cover the liability of the
Contractor or as the case may be, of such sub-contractor, in respect
of personal injuries or deaths arising out of or in the course of or
caused by the carrying out of the Works, and
12.1.2 Such insurances as are necessary to cover the liability of the
the Contractor or as the case may be, of such sub-contractor, in
respect of injury or damage to property real or personal arising out
of or in the course of or by reason of the carrying out of the Works
and caused by any negligence, omission or default of the
Contractor, his servants or agents or, as the case may be, of such
sub-contractor, his servants or agents.
Contractor shall produce and shall cause any sub-contractor to produce for
occasion, the Employer may require to have produced for his inspection,
12.3 The Contractor shall maintain in the joint names of the Employer and
and 12.3 of these conditions, the Employer may himself insure against
any risk with respect to which the default shall have occurred and may
13.2 Such Insurances shall be with insurers approved by the Employer. The
Contractor shall deposit the policy or policies and the receipts in respect of
premiums paid with the Quantity Surveyor. Should the Contractor make
default in insuring or continuing to insure as aforesaid, the Employer may
himself insure against any risk in respect of which the default shall have
occurred and deduct a sum equivalent to the amount paid by him in
respect of premiums from any money due or to become due to the
Contractor.
13.3 Provided always that if the Contractor shall independently of his
obligations under this contract maintain a policy of insurance which
covers (inter alia) the said work, materials and goods against the aforesaid
percentage, if any), then the maintenance by the Contractor of such policy
shall, if the Employer’s interest is endorsed thereon, be a discharge of
the Contractor’s obligation to insure in the joint names of the Employer
and the Contractor.
13.4 As long as the Contractor is able to produce for inspection
policy or policies and receipts with the Quantity Surveyor but on any
occasion, the Employer may require to have produced for his inspection
13.5 Upon settlement of any claim under the insurance aforesaid, the
Contractor with due diligence shall restore work damaged, replace or
repair any unfixed materials or goods which have been destroyed or
injured, remove and dispose of any debris and proceed with the carrying
out and completion of the Works. All money received from such
insurances ( less only the aforesaid percentage, if any), shall be paid to
the Contractor y installments under certificates issued at the periods of
interim certificates stated in clause 34.0 of these conditions. The
Contractor shall not be entitled to any payment in respect of the
restoration of work damaged, the replacement and repair of any
unfixed materials or goods, and the removal and disposal of debris
other than the money received under the said insurances.
14.3 If any loss or damage affecting the Works or any part thereof, or any
such unfixed materials or goods is occasioned by any one or more of the
said contingencies, then;
14.3.1 The occurrence of such loss or damage shall be disregarded in
computing any amounts payable to the Contractor under or by
virtue of the contract, and
14.3.2 The Contractor with due diligence shall restore work damaged,
replace or repair any unfixed materials or goods which have been
destroyed or injured, remove and dispose any debris and proceed
with the carrying out and completion of the Works.
14.3.3 The restoration of work damaged, the replacement and repair of
unfixed materials and goods and the removal and disposal of
debris shall be deemed to be a variation required by the Architect.
20.1 Within the period stated in the appendix to these conditions, the
Employer, or the Architect on his behalf, shall give possession of
site to the Contractor and such access as may be necessary to enable
the Contractor to commence and proceed with the Works in
accordance with the contract.
20.2 On or before the date for commencement stated in the appendix
to these conditions, the Contractor shall commence the execution of
the Works and shall regularly and diligently proceed with the same
and complete on or before the date stated in the appendix to these
conditions as the date for practical completion.
23.2 The Contractor shall, upon request by the Architect, furnish him
with trade catalogues or manufacture’s brochures to prove that the
materials and goods comply with sub-clause 23.1 of this condition.
23.4 Where not so described, the materials, goods and workmanship shall
be to a standard appropriate to the Works and to the reasonable
satisfaction of the Architect.
23.6 The Architect may issue instructions requiring the Contractor to open
up for inspection any work covered up or to arrange for or carry out
tests of any materials or goods (whether or not already incorporated
in the Works) or of any executed work. The cost of such opening up
testing, together with the cost of making good in consequence
thereof, shall be added to the contract price unless provided for in
the contract bills or unless the inspection or test shows that the work,
materials or goods are not in accordance with the contract.
23.7 Where materials or goods are specified by a trade or band name, the
Contractor shall not be liable for any latent defects therein, if any. The
Contractor shall be deemed to have assigned to the Employer any
right of action that may exist against the supplier or the manufacturer
in case of failure from such defects
23.8 The Architect may issue instructions in regard to the removal from
site of any work, materials or goods which are not in accordance
with the contract.
24.1 The Contractor shall arrange for and furnish to the Architect, samples
of any materials, goods or workmanship and perform any tests that
may be called for by the Architect for his approval. Any samples and
tests approved by the Architect shall be deemed to represent the
minimum standard for the part of the Works to which they apply.
25.1 All royalties or other sums payable in respect of the supply and use
of any patented articles, processes or inventions in carrying out the
Works as described by or referred to in the contract bills and the
specifications, shall be deemed to have been included in the contract
price.
25.2 The Contractor shall indemnify the Employer from and against all
claims, proceedings, damages, costs and expenses which may be
brought or made against the Employer or to which he may be put by
reason of the Contractor infringing or being held to have infringed any
patent rights in relation to any such articles, processes or inventions.
25.3 Where the Contractor shall supply and use in carrying out the Works
any patented articles, inventions or processes in compliance with
Architect’s instructions, the Contractor shall not be liable in respect
of any infringement or alleged infringement of any patent rights in
relation to any such articles, processes and inventions. All royalties,
damages or other money which the Contractor may be liable to pay
to the persons entitled to such patent rights shall be added to the
contract price.
26.0 ASSIGNMENT
26.1 Neither the Employer nor the Contractor shall, without the written
consent of the other, assign this contract. Provided that the approval
of assignment shall not relieve either party of his obligations for the
part of the contract already performed or the part not assigned.
27.0 SUBLETTING
27.1 The Contractor shall not sublet the whole of the Works without the
written consent of the Employer and the Architect. He may sublet
part of the Works upon giving notice to the Architect.
27.2 The Contractor shall remain liable under the contract for all work
sublet under this clause as if he had himself carried out such work.
28.2 The Architect ,ay issue instructions to suspend the carrying out of
any work included in this contract, if;
28.2.1 The Contractor fails to comply with an Architect’s I
instructions requiring the dismissal from the Works
of any person deployed thereon, or
28.2.2 There arises any matters of urgency involving the safety or
protection of persons or property, or
28.2.3 The Contractor fails to comply with the contract provisions
to insure the Works; or
28.2.4 The Contractor fails to comply with an Architect’s
instruction in regard to the removal from the site of any
work, materials or goods which are not in accordance with
the contract, or
28.2.5 The Contractor assigns the contract or sub-lets the whole of
the Works without the written consent of the Employer.
28.3 Except for the suspension under sub-clause 28.2.2, all other
instructions to suspend shall be accompanied by a seven days notice.
28.5 The suspension shall not take effect if the matter occasioning the
notice is rectified within the period of the notice. Such suspension
shall cease immediately the matter occasioning the notice is rectified.
28.6 Should the Works be suspended under this clause, the Contractor
shall be liable for all expenses arising therefrom.
29.1 The Contractor may suspend the carrying out of the Works if;
29.1.1 He has not received a payment certificate which he
applied for in accordance with clause 34.0 of these
conditions and the default continues for thirty days after
expiry of the stated period, or
29.1.2 He has not received payment within the period for
honouring certificates provided in clause 34.0 of these
conditions and the default continues for thirty days after
expiry of the stated period, or
29.1.3 The Contractor notifies the Architect that it has become
impossible or impracticable to procure goods and materials
for the Works for reasons beyond the Contractor’s control
and the Architect has not given appropriate instructions in
accordance with sub-clause 23.2, or
29.1.4 Delays occurs in the nomination or renomination of a sub-
contractor or supplier which delay materially affects the
progress of the Works., or
29.1.5 Delay occurs in the appointment of a replacement Architect
, Quantity Surveyor or Engineer which delay materially
affects the progress of the Works.
29.2 Where the Constructor intends to suspend the carrying out of the
Works, he shall give the Employer a seven days notice in writing to
that effect, with a copy to the Architect.
29.3 The Contractor shall not suspend the carrying out of the Works if
the matter occasioning the notice is rectified within the period of the
notice. Such suspensions shall cease immediately the matter
occasioning the notice is rectified.
29.4 During the period of suspension either under clause 28.0 or herein
the Contractor shall properly protect and secure the Works to the
reasonable satisfaction of the Architect.
30.0 VARIATIONS
30.1 The term ‘variation’ as used in this conditions shall mean the
alteration or modification of the design, quality or quantity of the
Works as shown upon the Contract drawings and described by or
referred to in the contract bills and specifications and includes:
30.1.1 The addition, omission or substitution of any item of work.
30.1.2 The alteration of the kind or standard of any of the materials
or goods to be used in the Works.
30.1.3 The removal from the site of work, materials or goods
brought upon the Works by the Contractor for the
purposes of the Works other than work, materials, or
goods which are not in accordance with the contract.
30.1.4 The issue of instructions by the Architect in regard to the
expenditure of prime cost and provisional sums included in
the contract bills and or prime cost sums which arise as a
result of instructions issued in regard to the expenditure of
provisional sums.
30.2 The Architect may issue instructions requiring a variation and he may
sanction in writing any variation made by the Contractor otherwise
than pursuant to an instruction of the Architect. No variation required
by the Architect or subsequently sanctioned by him shall vitiate this
contract, provided that no such instructions shall substantially change
the scope or object of the contract without the consent of the
Employer and the Contractor.
30.3 If the net value of all variations should equal 15% of the builders
work, the Architect shall not issue any further instructions requiring
a variation for additional work without the consent of the Employer
and the Contractor.
30.6 The valuation of variations and work executed by the Contractor for
for which a provisional sum is included in the contract bills (other
work for which a tender has been accepted as aforesaid) unless
otherwise agreed, shall be made in accordance with the following
rules;
30.6.1 The prices in the contract bills shall determine the valuation
of work of similar character executed under similar
conditions as work priced therein.
30.6.2 The said prices, where work is not of a similar character or
executed under similar conditions as aforesaid, shall be the
basis of prices for the same do far as may be reasonable,
failing which a fair valuation thereof shall be made.
30.6.3 Where work cannot properly be measured and valued, the
Contractor shall be allowed day-work rates on the prices
prevailing when such work is carried out (unless otherwise
provided in the contract bills). The day-work rates will be;
30.6.3.1 Rates, if any, inserted by the Contractor in the
bills or in a schedule of rates, or
30.6.3.2 When no such rates have been inserted, at rates
to be agreed between the Quantity Surveyor and
the Contractor.
30.6.3.3 Vouchers specifying the time daily spent upon the
work (and if required by the Architect, the
workmen’s names) the equipment and the
materials used shall be delivered for verification
to the Quantity Surveyor not later than the end
of the week following that in which the work
was executed.
30.6.4 The prices in the contact bills shall determine the valuation
of items omitted. Provided that if omissions substantially
vary the conditions under which any remaining items of
work are carried out, the prices for such remaining items
shall be valued as set out in sub-clause 30.6.2.
30.12 Except as expressly stated in the contract, the Architect shall have
no authority to alter or amend the terms and conditions of the
contract or to relieve the Contractor of any of his obligations
under the contract.
30.13 Where the Architect, with the consent of the Employer and the
Contractor, issues instructions requiring a variation beyond the
limit provided in sub-clause 30.3, the Employer may require an
additional performance bond over and above that provided under
sub-clause 16.1. The Contractor shall be reimbursed for the
provision of the additional bond pro-rata to the amount priced
for the bond in the contract.
31.0 NOMINATEDSUB-CONTRACTORS
31.1 The following provisions shall apply where prime cost sums are
included in the contract bills or arise as a result of Architect’s
instructions given in regard to the expenditure of provisional sums
in respect of persons to be nominated by the Architect to supply
and fix or install materials or goods or to carry out work.
31.4 The nominated sub-contractor shall carry out and complete the
sub-contract works in every respect to the reasonable satisfaction
of the Contractor and of the Architect and in conformity with all
the reasonable directions and requirements of the Contractor.
31.5 The Contractor and the nominated sub-contractor shall enter into
a sub-contract agreement which provides (inter alia):
31.5.1 That the nominated sub-contractor shall observe, perform
and comply with all the provisions of this contract on the
part of the Contractor to be observed, performed and
compiled with (other than clause 13.0 of these conditions
, if applicable) so far as they relate and apply to the
sub-contract works or to any portion of the same.
31.5.2 That the nominated sub-contractor shall indemnify the
Contractor against the same liabilities in respect of the
sub-contract works as those for which the Contractor is
liable to indemnify the Employer under this contract.
31.5.3 That the nominated sub-contractor shall indemnify the
Contractor against claims in respect of any negligence,
omission or default of such sub-contractor, his servants
or agents or any misuse by him or them of any
scaffolding or other equipment, and shall insure himself
against any such claims and produce the policy or
policies and receipts in respect of premiums paid as
and when required by either the Architect or the
Contractor.
31.5.4 That the sub-contract works shall be completed within
the period or (where they are to be completed in
sections) periods therein specified.
31.5.5 That the Contractor shall not without the written
consent of the Architect, grant any extension of time
for the completion of the sub-contract works or any
section thereof, and that the Contractor shall inform
the Architect of any representation made by the
nominated sub-contractor as to the cause of any delay
in the progress or completion of the sub-contract works
or any section thereof.
31.5.6 That if the nominated sub-contractor shall fail to
complete the sub-contract works or (where the
sub-contract works are to be completed in sections) any
section thereof, within the period therein specified or
within any extended time granted by the Contractor
with the written consent of the Architect and the
certifies in writing to the Contractor that the same ought
reasonably so to have been completed, the nominated
sub-contractor shall pay or allow the Contractor either a
sum calculated at the rate therein agreed as liquidated
damages for the period during which the said works or
any section thereof, as the case may be, shall remain or
have remained incomplete or (where no such rate is
therein agreed), a sum equivalent to any loss or damage
suffered or incurred by the Contractor and caused by
the failure of the nominated sub-contractor as
aforesaid.
31.6 The Architect shall direct the Contractor of the total value of the work
, materials or goods executed or supplied by a nominated
sub-contractor included in the calculation of the amount stated as
due in any certificate issued under clause 34.0 of these conditions
and shall forthwith inform the nominated sub-contractor in writing of
the amount of the said total value. The sum representing such total
value shall be paid by the Contractor within fourteen days after
receipt by the Contractor of the sum to which the Contractor shall
be entitled by virtue of the certificate less only;
31.6.1 Any retention money which the Contractor may be entitled
to deduct under the terms of the sub-contract, and
31.6.2 Any sum to which the Contractor may be entitled in respect
of delay in the completion of the sub-contract works or any
section thereof, and
31.6.3 Amounts already paid under previous certificates.
31.7 Before issuing any certificate under clause 34.0 of these conditions,
the Architect may request the Contractor to furnish to him reasonable
proof that all amounts stated as due in previous certificates in respect
of the total value of the work, materials or goods executed or
supplied by any nominated sub-contractor have been duly paid and if
the Contractor fails to comply with any such request the Architect
shall issue a certificate to that effect and thereupon the Employer
may himself pay such amounts to any nominated sub-contractor
concerned and deduct the same from any money due or to become
due to the Contractor.
31.8 The Contractor shall not grant to any nominated sub-contractor any
extension of the period within which the sub- contract works, or
(where the sub-contract works are to be completed without the
written consent of the Architect. Provided always that the Contractor
shall inform the Architect of any representations made by the
nominated sub-contractor as to the cause of any delay in the progress
or completion of the sub-contract works or of any section thereof.
The consent of the Architect shall not be unreasonably withheld.
Any extension of the time granted under this clause shall be copied to
the Employer.
31.11 Where the Contractor in the ordinary course of his business directly
carries out works for which prime cost sums are included in the
contract bills and where he has so informed the Architect, the
Contractor shall be permitted to tender for the same or any of them
but without prejudice to the Employer’s right to reject the lowest or
any tender.
31.12 Where a prime cost sum arises under Architect’s instructions issued
under sub-clause 30.1.4, of these conditions, it shall be deemed for
the purposes of this sub-clause to have been included in the contract
bills.
31.20 Neither the existence nor the exercise of the foregoing powers nor
anything else contained in these conditions shall render the
Employer in any way liable to any nominated sub-contractor.
32.0 NOMINATED SUPPLIERS
32.1 The following provisions shall apply where prime cost sums are
included in the contract bills, or arise as a result of Architect’s
instructions given in regard to the expenditure of provisional
sums in respect of any materials or goods to be supplied by others
and fixed or installed by the Contractor.
32.2 Such sums and the term prime cost, when included or arising as
aforesaid, shall be understood to mean the net cost to be defrayed as
a prime cost after deducting any trade or other discount and shall
include customs duty or other taxes, and the cost of packing, carriage
and delivery. Provided that, where in the opinion of the Architect the
Contractor has incurred expense for special packing or special
carriage, such special expenses shall be allowed as part of the sums
actually paid by the Contractor.
32.4 The Architect shall not nominate as a supplier, a person who will not
enter in to a contract of sale which provides (inter alia):
32.4.1 That the materials or goods to be supplied shall be to the
reasonable satisfaction of the Architect.
32.4.2 That the nominated supplier shall make good by replacement
or otherwise any defects in the materials or goods supplied
which appear within such period as is therein stated and
shall bear any expenses reasonably incurred by the
Contractor as a direct consequence of such defects provided
that:-
32.4.2.1 Where the materials or goods have been used or
fixed such defects are not such that examination
by the Contractor ought to have revealed them
before using or fixing, and
32.4.2.2 Such defects are due solely to defective
workmanship or defects in the materials or
goods supplied and shall not have been caused
by improper storage by the Contractor or by
misuse or by any act or neglect of either the
Contractor, the Architect or the Employer or by
any person or persons for whom they may be
responsible.
32.4.3 That delivery of the materials or goods supplied shall be
commenced and completed at such times as the Contractor
may reasonably direct.
32.4.4 All payments by the Contractor for materials or goods
supplied by a nominated supplier shall be in full and shall be
paid within thirty days of the end of the month during which
delivery is made. Failure by the Contractor to pay the
nominated supplier as stipulated shall entitle the Employer
any money due or to become due to the Contractor.
32.4.5 Where the terms of a contract between the Contractor and a
nominated supplier so require, or the Architect shall so authorize in writing, the Contractor
shall make advance payments to the supplier before delivery of the materials or
goods. The Contractor shall be allowed simple interest for period of such advance payment
calculated at the commercial bank lending rate in force at the time of the
advance until the value of the said materials or goods is included in a certificate in accordance
with clause 34.0.
33.1 The Contractor shall permit the carrying out of work not forming part
of this contract, but described in the contract bills, by the Employer or
by other persons employed or otherwise engaged by him.
33.2 Where the work is not described in the contract bills, the Employer
may arrange the carrying out of such work only with the consent of
the Contractor, which consent shall not be unreasonably withheld.
34.0 PAYMENTS
34.2 Upon receipt of the application and after verifying the amounts, the
Quantity Surveyor shall prepare within seven days an interim
valuation of work done and materials on site during the relevant
period and forward the same to the Architect. The valuation shall be
copied to the Employer.
34.3 The Architect shall issue an interim payment certificate within seven
days from the date of receipt of the Quantity Surveyor’s valuation.
The payment certificate shall be copied to the Employer.
34.4 Neither the Quantity Surveyor nor the Architect shall be bound to
issue a valuation or a payment certificate, as the case may be, whose
value is less than the amount stated in the appendix to these
conditions as the minimum amount of a payment certificate before
the issue of the certificate of practical completion of the whole of the
Works or any section thereof.
34.7 The payment of interest for late payment of certified sums shall not
relieve the Employer from his obligation to honour payment
certificates when due.
34.11 Provided that such interim certificate shall only include the value of
such materials and goods as and from such time as they are
reasonably, properly and not prematurely brought to the Works or
stored as aforesaid and are adequately stored and protected against
weather and other casualties and are covered by proper insurance
and have passed to the legal ownership of the Contractor. There shall
deducted from the amount of the certificate such sums as may be
retained by the Employer as hereinafter provided and less any
amounts previously certified under this clause.
34.12 The Employer may retain the percentage of the total value of the
work,, materials and goods referred to sub-clause 34.9 of this
condition which is named in the appendix to these conditions as
percentage of certified value retained. Provided always that when the
sum of the amounts so retained equals the amount named in the said
appendix as limit of retention fund, or that amount as reduced
pursuant to sub-clause, 31.10, 42.7 and 42.8 of these conditions, as
the case may be, no further amount shall be retained by virtue of this
clause.
34.13 Where any certificate of which the Contractor has received payment
in accordance with sub-clause 34.5 of these conditions, includes the
value of any unfixed materials and goods required for use in the
Works, such materials and goods shall become the property of the
Employer and shall not be removed without the authority of the
Architect except for use upon the Works. The Contractor shall remain
responsible for any loss or damage to such materials and goods
whether the same are stored on site or elsewhere.
34.15 The Employer and the Contractor may agree to open a joint interest
earning bank account where all retention money shall be deposited.
Such account, if opened, shall be operated jointly by the Employer
and the Contractor. All interest accruing to the deposited retention
fund shall be periodically released to the Contractor at the times
agreed between the parties and inserted in the appendix to these
conditions.
34.20 The final account shall be agreed between the Quantity Surveyor, the
Contractor and the Architect. If the Contractor does not assign the
final account within thirty days after being so requested to do, the
Architect may issue the final certificate based on the final account
prepared by the Quantity Surveyor. The final document shall be
copied to the Employer.
34.21 So soon as the Quantity Surveyor has prepared the final account but
before the expiration of sixty days from the end of the defects liability
period stated in the appendix to these conditions, or from completion
of rectification of defects under clause 41.6 of these conditions, or
from receipt by the Quantity Surveyor of the documents referred to in
paragraph 34.18 of this condition, whichever is the latest, the
Architect shall issue the final certificate.
The final certificate shall state;
34.21.1 The sum of the amounts certified to the Contractor under
interim certificates and the amount named in the said
appendix as limit of retention fund, and
34.21.2 The contract price adjusted as necessary in accordance with
the terms of these conditions, and as reflected in the final
account.
34.21.3 The difference (if any) between the two sums shall be
expressed in the said certificate as a balance due to the
Contractor from the Employer or to the Employer from the
Contractor, as the case may be. Subject to any deductions
authorized by these conditions, the said balance as from
the fourteenth day after presentation of the final
certificate by the Contractor to the Employer shall be a
debt payable by the Employer to the Contractor or by the
Contractor to the Employer, as the case may be.
34.24 If the Architect shall delete or reduce any sum in the final certificate
which was previously certified in respect of work done or goods and
materials supplied or services rendered by a nominated sub-
contractor or supplier, which sum has already been paid by the
Contractor to the nominated sub-contractor or supplier, the Employer
shall reimburse the Contractor the amount of any sum so overpaid to
the extent that the Contractor is unable to recover the said
overpayment.
34.25 The Employer shall be entitled to deduct from or set off against any
money due from him to the Contractor in interim certificates any sum
or sums which the Contractor is liable to pay to the Employer arising
under or in connection with the contract.
34.27 All certificates to be issued by the Architect under this conditions shall
be issued to the Contractor except that the Architect may issue a
special payment certificate to others for payment by the Employer
where the Employer;
34.27.1 Engages others to execute work in accordance with sub-
clause 22.2.
34.27.2 Elects to pay nominated sub-contractors or nominated
suppliers direct in accordance with clauses 31.7 and 32.4.4
34.27.3 Elects to pay direct statutory and similar services providers
in accordance with clause 17.2.
35.0 FLUCTUATIONS
35.1 The contract price shall be deemedto have been calculated to include
all duties on materials and goods to be incorporated into the finished
Works unless otherwise stated in the contract. If at any time during
the period of the contract the duties shall be varied and this shall
affect the cost to the Contractor of such materials, then the Quantity
Surveyor shall assess the net difference in cost of such materials. Any
amount from time to time so assessed shall be added or deducted
from the contract price, as the case may be. For purposes of this
clause, ‘duties’ shall include all customs and excise charges, tariffs,
V.A.T and other taxes and duties imposed by statutory authority in
the country where the Works are being carried out.
35.3 Unless otherwise stated in the contract, the contract price shall be
deemed to have been calculated in the manner set out below and in
sub-clauses 35.4 and 35.5 and shall be subject to adjustment in the
events specified thereunder;
35.3.1 The prices contained in the Contract bills shall be deemed to
be based upon the rates of wages and other emoluments
and other expenses as determined by the Joint Building
Council of Kenya (J.B.C) and set out in the schedule of basic
rates annexed to the contract bills.
35.3.2 Upon J.B.C determining that any of the said rates of wages
or other emoluments and expenses are increased or
decreased, then the contract price shall be increased or
decreased by the amount assessed by the Quantity Surveyor
based upon the difference, expressed as a percentage,
between the rate set out in the annexed schedule of basic
rates and the rate published by the J.B.C and applied to the
quantum of labour incorporated within the amount of work
remaining to be executed as the date of publication of such
increase or decrease.
35.3.3 No adjustment shall be made in respect of changes in the
rates of wages and other emoluments and expenses which
occur after the date of practical completion except during
such other period as may be granted as an extension of
time under clause 36.0 of these conditions.
35.4 The prices contained in the contract bills shall be deemed to be based
upon the basic prices of materials to be permanently incorporated in
the Works as determined by the J.B.C and set out in the schedule of
basic rates annexed to the contract bills.
35.5 Upon the J.B.C determining that any of the said basic prices are
increased or decreased then the contract price shall be increased or
decreased by the amount to be assessed by the Quantity Surveyor
based upon the difference between the price set out in the schedule
of basic rates and rate published by the J.B.C and applied to the
Quantum of the relevant materials which have not been taken into
account in arriving at the amount of any interim certificate under
clause 34.0 of these conditions issued before the date of publication
of such increase or decrease.
35.7 The provisions of sub-clauses 35.1 and 35.2 herein shall not apply in
respect of any materials included in the annexed schedule of basic
rates.
35.8 The provision of sub-clause 35.3 to 35.5 shall not apply to nominated
sub-contractors and nominated suppliers except in so far as shall be
specifically provided in any sub-contract agreement.
36.1 Upon it becoming reasonably apparent that the progress of the Works
is delayed, the Contractor shall forthwith give written notice of the
cause of the delay to the Architect with supporting details showing
the extent of delay caused or likely to be caused. Thereafter the
Architect shall evaluate the information supplied by the Contractor
and if in his opinion the completion of the Works is likely to be or has
been delayed beyond the date for practical completion stated in the
appendix to these conditions or beyond any extended time previously
fixed under this clause;
36.1.1 By force majeure, or
36.1.2 By reason of any exceptionally adverse weather conditions,
or
36.1.3 By reason of loss or damage occasioned by any one or more
of the contingencies referred to in clauses 13.0, 14.0, or 15.0
of these conditions , or
36.1.4 By reason of civil commotion, strike or lockout affecting any
of the trades employed upon the Works any of the trades
engaged in the preparation, manufacture or transportation
of any of the goods or materials required for the Works, or
36.1.5 By reason of Architect’s instructions issued under clauses
22.0, 28.1 and 30.0 of these conditions, or
36.1.6 By reason of the Contractor not having received in due time
necessary instructions, drawings, details or levels from the
Architect for which he specifically applied in writing on a
date which having regard to the date for practical
completion stated in the appendix to these conditions or to
any extension of time then fixed under this clause was
neither unreasonably distant from nor unreasonably close to
the date on which it was necessary for him to receive the
same, or
36.1.7 By delay on the part of artists, tradesmen or others engaged
by the Employer in executing work not forming part of this
contract, or
36.1.8 By reason of delay by statutory or other services providers or
similar bodies engaged directly by the Employer, or
36.1.9 By reason of the opening up for inspection of any work
covered up or of the testing of any of the work, materials or
goods in accordance with sub-clause 23.6 of these
conditions (including making good in consequence of such
opening up or testing), unless the inspection or test showed
that the work, materials or goods were not in accordance
with this contract, or
36.1.10 By the Contractor’s inability for reasons beyond his control
and which he could not reasonably have foreseen at the date
of this contract, to obtain delivery upon the Works of such
goods or materials as are essential to the proper carrying out
of the Works, or
36.1.11 By reason of carrying out the Works having been suspended
by the Contractor in accordance with clause 29.0, or
36.1.12 By reason of delay in appointing a replacement Architect,
Quantity Surveyor or Engineers, or
36.1.13 By reason of delay caused by the late supply of goods or
materials or in executing work for which the Employer or
his agents are contractually obliged to supply or to execute
as the case may be, or
36.1.14 By reason of delay caused by nominated sub-contractors or
nominated suppliers which delay the Contractor has taken
all reasonable measures to avoid or reduce the effects of, or
36.1.15 By reason of the Contractor’s inability, for reasons beyond
his control, to secure such skilled labour and other workmen
essential to the proper carrying out of the Works. or
36.1.16 By delay arising from the nomination or renomination of a
sub-contractor or supplier, or
36.1.17 By delay in receiving possession of or access to the site.
36.2 Then the Architect shall so soon as he is able to estimate the length of
the delay beyond the date or time aforesaid, but in any case not later
than thirty days after receiving an application for extension of time in
the manner prescribed, make in writing a fair and reasonable
extension of time for the completion of the Works.
36.4 The Contractor shall use constantly his best endeavors to prevent
delay and shall do all that may reasonably be required of him to the
satisfaction of the Architect to proceed with the Works.
36.7 The Architect shall not be bound to evaluate a request for extension
of time which is submitted more than thirty days after the events
listed in sub-clause 36.1 have occurred.
36.8 All applications for extension of time and all decision on the same
shall be copied to the Employer at the time of application or
decision, as the case may be.
WORKS
37.3 Upon the happening of any of the events listed at sub-clause 37.1.1 to
37.1.11, the Contractor shall maintain such records as may be
necessary to support any claim he may wish to make. The Quantity
Surveyor may request any further information as he may deem
necessary for a fair and just assessment of the claim.
37.4 The Contractor shall give written notice to the Architect of his
intention to make a claim within thirty days after the event giving rise
to the claim has first arisen. The claim shall be submitted within thirty
days thereafter.
37.5 Provided always that should the event giving rise to the claim be of
continuing effect, the Contractor shall submit an interim claim within
thirty days and a final claim within thirty days of the end of the event
giving rise to the claim.
37.6 If the Contractor fails to comply with any of the provisions of this
clause in respect of any claim he seeks to make, his entitlement to
payment in respect thereof shall not exceed such amount as the
Quantity Surveyor or any Arbitrator appointed under clause 45.0
shall consider to be verified by contemporary records submitted at
the time the event occurred.
37.7 All applications for the reimbursement of loss and or expense made
by the Contractor, and all assessments of loss and expense made by
the Quantity Surveyor, shall be copied to the Employer.
38.1 Without prejudice to any other rights and remedies which the
Employer may possess, if the Contractor shall make default in any
one or more of the following respects, that is to say,
38.1.1 If he without reasonable cause wholly suspends the carrying
out of the Works before completion thereof, for a period
exceeding fourteen days, or
38.1.2 If he fails to protect regularly and diligently with the Works,
or
38.1.3 If he fails to commence the Works within thirty days of the
date for commencement, or
38.1.4 If he refuses or persistently neglects to comply with a written
notice from the Architect requiring him to remove defective
work or improper materials or goods, and by such refusal or
neglect the Works are materially affected, or
38.1.5 If he fails to comply with the provisions of clause 26.0 and
27.0 of these conditions, or
38.1.6 If despite previous notices from the Architect in writing he
persistently or flagrantly neglects to comply with any of his
obligations under the contract,
38.2 Then the Architect may give to the Contractor a notice by registered
post or recorded delivery specifying the default, and if the Contractor
either shall continue such default for fourteen days after receipt of
such notice or shall at any time thereafter repeat such default then
the Employer may within fourteen days after such continuance or
repetition by notice by registered post or recorded delivery, forthwith
terminate the contract, provided that such notices shall not be given
unreasonably or vexatiously.
38.4 In the event of the contract being terminated as aforesaid and so long
as it has not been reinstated and continued, the following shall be the
respective rights and duties of the Employer and the Contractor;
38.4.1 The carrying out of the Works by the Contractor shall cease
forthwith and the Contractor shall vacate the site thereby
relinquishing possession thereof and the responsibility and
care of the site and the Works shall henceforth pass to the
Employer.
38.4.2 So soon as it is practicable, the Architect shall arrange a joint
inspection with the Contractor and the Quantity Surveyor
for the purpose of taking a record of the work done,
materials and goods delivered on site, the Contractor’s
equipment, and temporary buildings.
38.4.3 The Quantity Surveyor shall, within a reasonable time after
the inspection, prepare a final account for that part of the
Works carried out by the Contractor by the date of
termination of the contract.
38.5 The Employer may employ and pay other persons to carry out and
complete the Works and rectify any defects and he or they may enter
upon the Works and use all temporary buildings, equipment, goods
and materials intended for, delivered to and placed on or adjacent to
the Works, and may purchase all materials and goods necessary for
the carrying out and completion of the Works.
38.7 The Contractor shall as and when required in writing by the Architect
so to do (but not before) remove from the Works any temporary
buildings, equipment, goods and materials belonging to or hired by
him. If within thirty days after any such requirement has been made
or the Contractor has not compiled therewith, then the Employer may
(but without being responsible for any loss or damage) remove and
sell any such property of the Contractor holding the proceeds less all
costs incurred to the credit of the Contractor.
38.8 The Contractor shall allow or pay to the Employer in the manner
hereinafter appearing, the amount of any direct loss or and or
damage caused to the Employer by the termination. Until after
completion of the Works under sub-clause 38.5, the Employer shall
not be bound by any provision of this contract to make any further
payments to the Contractor, but upon such completion and the
verification within a reasonable time of the accounts therefore, the
Quantity Surveyor shall assess the amount of expenses properly
incurred by the Employer and the amount of any direct loss or
damage caused to the Employer by the termination and, if such
amounts when added to the money paid to the Contractor before the
date of termination exceed the total amount which would have been
payable to the on due completion in accordance with this contract,
the difference shall be a debt payable to the Employer by the
Contractor. If the said amounts when added to the money paid to
the Contractor be less than the said total amount, the difference shall
be a debt payable by the Employer to the Contractor.
38.9 The Contractor shall not be relieved of any of his obligations and
liabilities in regard to the part of the Works carried out by him.
39.1 Without prejudice to any other rights and remedies which the
Contractor may possess, if:
39.1.1 The Contractor does not receive a payment certificate
which he applied for in accordance with clause 34.1 of these
conditions within fourteen days of the application and the
default continues for sixty days after expiry of that period,
or
39.1.2 The Employer does not pay to the Contractor the amount
due on any certificate within the period for honouring
certificates named in clause 34.5 of these conditions and
continues such default for sixty days after expiry of that
period, or
39.1.3 The Employer interferes with or obstructs the issue of any
certificate due under this contract, and continues such act
for sixty days after a notice of default has been issued by the
Contractor, or
39.1.4 The carrying out of the whole or substantially the whole of
the uncompleted Works (other than the execution of work
required under sub-clause 41.6 of these conditions) is
suspended for a continuous period of sixty days by reason of;
39.1.4.1 Delay in receiving possession of or access to the
site, or
39.1.4.2 Architect’s instructions issued under clauses 22.0,
28.1, or 30.0 of these conditions, or
39.1.4.3 The Contractor not having received in due time
necessary instructions, drawings, details or levels
from the Architect for which he is specifically
applied in writing on a date which having regard
to the date for practical completion stated in the
appendix to these conditions, or to any extension
of time granted under clause 36.0 of these
conditions, was neither unreasonably distant
from nor unreasonably close to the date on which
it was necessary for him to receive the same, or
39.1.4.4 Delay in appointing a replacement Architect,
Quantity Surveyor or Engineer, or
39.1.4.5 Delay on the part of Artistes, tradesmen or
engaged by the Employer in executing the works
not forming part of this contract, or
39.1.4.6 Delay by statutory or other services providers or
similar bodies engaged directly by the Employer,
or
39.1.4.7 Delay due to the opening up for inspection of
any work covered up or the testing of any of the
work, materials or goods in accordance with
sub-clause 23.6 of these conditions (including
making good in consequence of such opening
up or testing) unless the inspection or test
showed that the work, materials or goods were
not in accordance with contract, or
39.1.4.8 The Contractor having suspended the carrying
out of the Works in accordance with clause 29.0
of these conditions, except under sub-clause
29.1.3, or
39.1.4.9 Delay arising from the nomination of a sub-
contractor or supplier.
39.3 Then the Contractor may give the Employer a notice by registered
post or recorded delivery with a copy to the Architect specifying the
default and should continue foe fourteen days after receipt of such
notice, the Contractor may forthwith terminate the Contract.
39.4 Upon such termination, then without prejudice to the accrued rights
or remedies of either party or to any liability mentioned in clause 11.0
of these conditions which may accrue either before the Contractor or
any sub-contractors shall have removed their temporary buildings,
equipment, goods or materials or by reason of their so removing
the same, the respective rights and liabilities of the Contractor and
the Employer shall be as follows, that is to say;
39.4.1 The carrying out of the Works by the Contractor shall cease
forth and the Contractor shall vacate the site thereby
relinquishing possession thereof and the responsibility and
care of the site and the Work shall henceforth pass to the
Employer.
39.4.2 So soon as it is practicable, the Architect shall arrange a joint
inspection with the Contractor and the Quantity Surveyor for
the purpose of taking a record of the work done, materials
and goods delivered on site.
39.4.3 Thereafter the Contractor shall with all reasonable dispatch
and in such manner and with such precautions as will prevent
injury, death or damage in respect of which before the date
of termination he was liable to indemnify the Employer under
clause 11.0 of these conditions, remove from the site all his
temporary buildings, equipment, goods and materials and
shall give facilities to his sub-contractors to do the same, but
subject always to the provisions of sub-clause 39.5.4 of this
condition.
39.5 After taking into account amount s previously paid under this contract
, the Contractor shall be paid by the Employer;
39.5.1 The total value of work completed at the date of
termination.
39.5.2 The total value of work begun and executed but not
completed at the date of termination, the value being
assessed in accordance with clause 30.6 of these conditions
as if such work were a variation required by the Architect.
39.5.3 Any sum assessed in respect of direct loss and or expense
under clause 37.0 of these conditions (whether assessed
before or after the date of termination).
39.5.4 The cost of materials or goods properly ordered for the
Works which the Contractor shall have paid or which the
Contractor shall be legally bound to pay, and which have
been recorded in accordance with sub-clause 39.4.2, and on
such payment by the Employer, any materials or goods so
paid for shall become the property of the Employer and shall
not be removed from the site without the authority of the
Employer.
39.5.5 The reasonable cost of removal under sub-clause 39.4.3
39.5.6 Any direct loss and or damage caused to the Contractor by
the termination.
40.1 If during the progress of the Works the Government and people of
the country in which the site is located shall become engaged in war,
warlike operations or hostilities or kindred activities which either
directly or indirectly involve or would involve either party in loss or
expense beyond that provided for in or reasonably contemplated by
this contract, the contract may be terminated by either party giving
to the other fourteen days notice by registered post or recorded
delivery. Upon termination the Contractor shall be paid by the
Employer in respect of the work carried out before such termination
in accordance with the provisions of sub-clauses 39.5.1 to 39.5.5 of
these conditions.
40.2 In the event of the Works or any goods or materials brought on the
site for use in the Works being destroyed or damaged by war, warlike
operations or hostilities or kindred activities as the case may be, the
Contractor shall be under no liability whatsoever to repair, reinstate
or make good the destruction or damage so caused and shall be
entitled;
40.2.1 To be paid the full value of the work carried out before such
event and for all materials on the site for use in the works
(including the work or materials so damaged or destroyed),
and
40.2.2 To be paid for any work done and materials or goods
supplied in the reinstatement or making good of any
destruction or damage so caused upon such terms as may
be agreed between the parties, and in default of agreement
, upon the basis of prime cost plus a reasonable profit to be
assessed by the Quantity Surveyor.
40.4 If the carrying out of the whole or substantially the whole of the
uncompleted Works (other than the execution of work required
under sub –clause 41.6 of these conditions) is suspended for a
continuous period of sixty days by reason of;
40.4.1 Force majeure, or
40.4.2 Loss or damage occasioned by any one or more of the
contingencies referred to in clauses 13.0 and 14.0 of these
conditions (if applicable), or
40.4.3 Loss or damage arising from nuclear activity.
40.5 Then either party may, upon giving a fourteen days notice by
registered post or recorded delivery, terminate the contract,
provided that such notice shall not be given unreasonably or
vexatiously. Upon such termination, the Contractor shall be paid by
the Employer in respect of the work executed before such
termination in accordance with the provisions of clauses 39.5.1 to
39.5.5.
41.1 When in the opinion of the Contractor the whole of the Works are
practically complete, he shall give a notice in writing to the Architect
to that effect. The notice shall be accompanied by an undertaking to
complete any outstanding work within a reasonable time or within
such times as the Architect may direct.
41.2 Within fourteen days of the issue of such notice, the Architect shall
inspect the Works and if in his opinion the works are practically
complete, he shall issue the certificate of practical completion, and
the defects liability period shall be deemed to commence on the date
of issue of the said certificate. If the Works are not practically
complete, he shall specify in writing to the Contractor the work which
in his opinion requires to be completed before the certificate can be
issued.
41.3 The Contractor shall retain possession of the site of the Works up to
and including the date of issue of the certificate of practical
completion and subject to clause 42.0 hereof, the Employer shall not
be entitled to take possession of any part or parts of the Works until
the date.
41.4 Upon the Employer taking possession of the whole or any part of the
Works, (hereinafter referred to as the relevant part), the relevant part
of the Works taken over shall be at the sole risk of the Employer in
every respect as from the date of such taking over.
41.5 Should the Employer take over the whole or any part of the Works
before the issue of a certificate of practical completion, practical
completion shall be deemed to have taken place on the date of
taking over of the whole or any part of the Works.
41.6 Any defects, shrinkages or other faults which shall appear within the
defects liability period stated in the appendix to these conditions, and
which due to materials or workmanship not being in accordance with
the contract shall be specified by the Architect in a schedule of
defects which he shall deliver to the Contractor not later than thirty
days after the expiration of the said defects liability period. Within a
reasonable time after receipt of such schedule, the defects,
shrinkages and other faults therein specified shall be rectified by the
Contractor and (unless the Architect shall otherwise instructs,)
entirely at his own cost. If the Architect so instructs, then an
appropriate deduction shall be assessed by the Quantity Surveyor and
made to the contract price in respect of any such defects, shrinkages
or other faults not rectified.
41.9 When in the opinion of the Architect any defects, shrinkages or other
defaults which he may have required to be rectified under sub-clause
41.6 of this condition shall have been rectified shall issue a certificate
to that effect, the completion of rectification of defects shall be
deemed for all the purposes of this contract to have taken place on
the day named in such certificate.
42.2 Within fourteen days from the date on which the Employer shall have
taken possession of the relevant part, the Quantity Surveyor shall
prepare a valuation stating his estimate of the approximate total
value of the said part. The Architect shall thereafter issue a certificate
for the relevant part and for all the purposes of this condition (but for
no other) the value stated in the certificate shall be deemed to be the
total value of the said part.
42.3 For the purposes of sub-clauses 41.2, 41.6 and 41.7 of these
conditions, practical completion of the relevant part shall be deemed
to have occurred and the defects liability period in respect of the
relevant part shall be deemed to have commenced on the date on
which the Employer shall have taken possession thereof.
42.4 When in the opinion of the Architect any defects, shrinkages or other
faults in the relevant part which he may have required to be rectified
under sub-clause 41.6 and 41.7 of these conditions shall have been
rectified he shall issue a certificate to that effect.
42.5 The Contractor shall reduce the value insured under sub-clause 13.1
of these conditions (if applicable) by the full value of the relevant part
, and the said relevant part shall as from the date on which the
Employer shall have taken possession thereof, be at the sole risk of
the Employer as regards any of the contingencies referred to in the
said sub-clause.
42.7 Within thirty days of the date on which the Employer shall have taken
possession of the relevant part, there shall be paid to the Contractor
from the sums then retained under clause 34.0 of these conditions
(if any), one half of such amount as bears the same ratio of the
unreduced amount named in the appendix to these conditions as
limit of retention fund as does the total value of the said relevant part
to the contract price, and the amount named in the appendix to these
conditions as limit of retention fund shall be reduced by the amount
so paid to the Contractor.
43.1 If the Contractor fails to complete the Works by the date for practical
completion stated in the appendix to these conditions, or within any
extended time fixed under clause 36.0 of these conditions, and the
Architect certifies in writing that in his opinion the same ought
reasonably so to have been completed, then the Contractor shall pay
or allow to the Employer a sum calculated at the rate stated in the
said appendix as liquidated damages for the period during which the
Works shall so remain or have remained incomplete, and the
Employer may deduct such sum from any money due or to become
due to the Contractor under the contract or recover the same from
the Contractor as a debt.
43.2 The payment or deduction of such damages shall not relieve the
Contractor from his obligations to complete the Works or any
part thereof or from any other obligations and liabilities under the
contract.
44.1 All fossils, antiquities and other objects of interest or value which may
be found on the site or in excavating the same during the progress of
the work, shall become the property of the Employer. The Contractor
shall carefully take out and preserve all such objects and shall
immediately or as soon as convenient after the discovery of such
articles, deliver the same into the possession of the Architect or of the
Clerk of Works unclean and as excavated.
45.1 In case any dispute or difference shall arise between the Employer
or the Architect on his behalf and the Contractor, either during the
progress or after the completion or abandonment of the Works,
such dispute shall be notified in writing by either party to the other
with a request to submit it to arbitration and to concur in the
appointment of an Arbitrator within thirty days notice. The
dispute shall be referred to the arbitration and final decision of a
person to be agreed between the parties. Failing agreement to concur
in the appointment of an Arbitrator, the Arbitrator shall be appointed
by the Chairman or Vice Chairman of The Architectural Association of
Kenya, on the request of the applying party.
45.5 In any event, no arbitration shall commence earlier than ninety days
after the service of the notice of a dispute or difference.
45.7 All other matters in dispute shall only be referred to arbitration after
the practical completion or alleged practical completion of the Works,
or abandonment of the Works, or termination or alleged termination
of the contract, unless the Employer and the Contractor agree
otherwise in writing.
45.8 The Arbitrator shall, without prejudice to the generality of his powers,
have powers to direct such measurements, computations, tests or
valuations as may in his opinion be desirable in order to determine
rights of the parties and assess and award any sums which ought to
have been the subject of or included in any certificate.
45.9 The Arbitrator shall, without prejudice to the generality of his powers,
have powers to open up, review and revise any certificate, opinion,
decision, requirement or notice and to determine all matters in
dispute which shall be submitted to him in the same manner as if no
such certificate, opinion, decision, requirement or notice had been
given.
45.10 The award of such Arbitrator shall be final And binding upon the
parties.
APPENDIX CLAUSE
Name of the bank for purposes of interest calculation 31.14, 32.4.5, 34.6
……………………………………….
of……………………………………………………………………………………………………………………………………………….
…………………………………………………………………………………………………………(Ksh………………………………….)
…………………………………………………………………………………………………………………………...(CONTRACTOR)
to carry out and complete the works therein stated in the manner and by the time therein
specified all in accordance with the provisions of the said contract, namely; (description of
Works)
…………………………………………………………………………………………………………………………………………………….
Now the condition of the above written bond is such that if the said Contractor his executers,
administrators, successors or assigns shall duly perform his obligations under the contract, or if
on default by the Contractor the Surety shall satisfy and discharge the damages sustained by
the Employer thereby up to the amount of the above written bond, then this bond shall be
void, otherwise it shall remain in full force and effect. Upon default, and without prejudice to
his other rights under the contract, the Employer shall be entitled to demand forfeiture of the
bond and we undertake to honour the demand in the amount stated above.
PROVIDED always and it is hereby agreed and declared that no alteration in the terms of the
said contract or in the extent or nature of the Works to be carried out and no extension of time
by the Architect under the contract shall in any way release the Surety from any liability under
the above written bond.
IN WITNESS whereof we have set our hands this…………………………………….day of…………………………
…………………………………………………………... ……………………………………………………….
Surety Witness
of………………………………………………………………………………………………………………………………………………..
………………………………………………………………………………………………..(Ksh…………………………………………)
…………………………………………………………………………………………………………………………….(CONTRACTOR)
to carry out and complete the works therein stated in the manner and by the time therein
specified all in accordance with the provisions of the said contract, namely; (description of
Works)
…………………………………………………………………………………………………………………………………………………….
NOW the condition of the above written bond is such that if the said Employer his executors,
administrators, successors or assigns shall duly perform his payment obligations under the
contract then this bond shall be void, otherwise it shall remain in full force and effect. That is to
say, should the Contractor terminate the contract under clause 39.1.1., 39.1.2 or 39.1.3 of the
contract or should the final certificate remain unpaid beyond the period stated in clause
34.21.3, then without prejudice to his other rights under the contract, the Contractor shall be
entitled to demand forfeiture of the bond and we undertake to honour the demand in the
amount stated above.
PROVIDED always and it is hereby agreed and declared that no alteration in the terms of the
said contract or in the extent or nature of the works to be carried out and no extension of time
by the Architect under the contract shall in any way release the Surety from any liability under
the above written bond.
……………………………………………………….. …………………………………………………………………………..
Surety Witness