The document outlines a 7-task project timeline to procure and install a 2.5MWp solar power plant in Bahawalpur, Pakistan from October 2020 to March 2021. Key tasks include placing equipment orders in October, shipments arriving from China in November and at the project site in December, mechanical and electrical installation from December to January, and commissioning/testing from February to March. Local procurement of additional supplies will occur in November.
The document outlines a 7-task project timeline to procure and install a 2.5MWp solar power plant in Bahawalpur, Pakistan from October 2020 to March 2021. Key tasks include placing equipment orders in October, shipments arriving from China in November and at the project site in December, mechanical and electrical installation from December to January, and commissioning/testing from February to March. Local procurement of additional supplies will occur in November.
The document outlines a 7-task project timeline to procure and install a 2.5MWp solar power plant in Bahawalpur, Pakistan from October 2020 to March 2021. Key tasks include placing equipment orders in October, shipments arriving from China in November and at the project site in December, mechanical and electrical installation from December to January, and commissioning/testing from February to March. Local procurement of additional supplies will occur in November.
The document outlines a 7-task project timeline to procure and install a 2.5MWp solar power plant in Bahawalpur, Pakistan from October 2020 to March 2021. Key tasks include placing equipment orders in October, shipments arriving from China in November and at the project site in December, mechanical and electrical installation from December to January, and commissioning/testing from February to March. Local procurement of additional supplies will occur in November.
ID Task Task Name Duration Start Finish September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 Mode 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 1 Placement of Orders 8 days Mon 05-10-20 Mon 12-10-20 2 Shipment from China 6 days Mon 02-11-20 Sat 07-11-20 3 Shipment Arrival at Port 6 days Mon 30-11-20 Sat 05-12-20 4 Shipment Arrival at Site 5 days Sat 05-12-20 Wed 09-12-20 5 Local Procurement 10 days Mon 16-11-20 Wed 25-11-20 6 Mechanical Installation of 21 days Thu 10-12-20 Wed 30-12-20 Equipment 7 Electrical Installation 29 days Sat 02-01-21 Sat 30-01-21 8 Commissioning/ Testing/Online 26 days Mon 01-02-21 Fri 26-02-21 Monitoring/Security Camera Installation