Petronas FLNG Satu: Engineering and Delivering Malaysia's First FLNG
Petronas FLNG Satu: Engineering and Delivering Malaysia's First FLNG
FLNG Satu
Engineering and delivering Malaysia’s first FLNG
Key figures
� Production capacity: 1.2 Mtpa of LNG
� External turret
� Classification: DNV/GL
A combined effort
to engineer and deliver
Malaysia’s first FLNG
Petronas FLNG Satu Milestones
Petronas � Q4 2010 - FEED
One of the largest LNG producers
in the world, with broad expertise � Q2 2012 - Start of EPCIC
in plant operation and design.
� Q3 2013 - First hull and topsides steel cutting
TechnipFMC � Q1 2014 - Keel laying
A leader in natural gas
liquefaction plants and floating � Q2 2014 - Hull launch
facilities, providing extensive � Q3 2014 - First module lift
industrial engineering, procurement,
and installation experience. � Q1 2015 - Last module lift
Fire and cryogenic risk Exhaust dispersion and helideck Explosion risk
Fire and cryogenic risk analyses availability During engineering, TechnipFMC
developed during engineering ensure We performed CFD dispersion performed numerous flammable gas
that risks are as low as reasonably simulations to study the risk dispersion and explosion simulations
practicable. of helideck impairment by hot using computational fluid dynamics
plumes and derive an estimation simulation. The results were used to
of availability. This study also derive explosion loads for the design
confirmed the acceptability of of safety-critical elements.
pollutant concentration at air
intakes for living quarters.
Jean-Marc Letournel
Tel: +33 1 47 78 35 42
jean-marc.letournel@technipfmc.com
LNG
Philip Hagyard
Tel: +33 1 47 78 27 17
philip.hagyard@technipfmc.com