Professional Documents
Culture Documents
Replace Crude Oil Samplers at Yanbu North Terminal
Replace Crude Oil Samplers at Yanbu North Terminal
BI-10-02126
Prepared by:
Page 1 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
TABLE OF CONTENTS
1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (AUGUST 29, 2020) .................... 3
1.1 ENGINEERING ................................................................................................................................ 3
1.1.1 PROCESS ........................................................................................................................................ 3
1.1.2 INSTRUMENTATION ...................................................................................................................... 3
1.1.3 PIPING ............................................................................................................................................. 3
1.1.4 COMMUNICATION .......................................................................................................................... 3
1.1.5 STRUCTURAL/CIVIL ...................................................................................................................... 3
1.1.6 ELECTRICAL .................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB) ............................................................................................................. 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP) ........................................................................ 4
1.1.9 MECHANICAL ................................................................................................................................. 4
2.0. AREAS OF CONCERN ................................................................................................................... 4
3.0. ATTACHMENTS .............................................................................................................................. 4
Page 2 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
1.1 ENGINEERING
1.1.1 PROCESS
• Replies for 90% E review for disagreed and implemented reviewer comments
• Incorporation of 90% closed comments for IFB
• Interdisciplinary Inputs to Mechanical
1.1.2 INSTRUMENTATION
1.1.3 PIPING
Prepare the IFB package
Update the piping plans based on approved proposal of Manual sample connection routing
Discussion and meetings
1.1.4 COMMUNICATION
• No activity
1.1.5 STRUCTURAL/CIVIL
1.1.6 ELECTRICAL
Page 3 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
▪ MECHANICAL
• Working on 90% comments implementation
• Working on vendor quotations LOG
• Working on the impact of relocating Skid of berth 64
AREAS OF CONCERN
2.0
. • There is impact of COVID-19 Safety & Health Measures on the project progress.
3.0 ATTACHMENTS
. • Weekly Progress Summary
• Weekly Overall discipline progress
• Weekly Progress Report Details
• Weekly Progress overall S-Curve
Page 4 of 4