Professional Documents
Culture Documents
Site Grading, Subgrade Excavate (Cut & Fill) Excavation (Cut) & Backfilling Compacted To 90% MDD
Site Grading, Subgrade Excavate (Cut & Fill) Excavation (Cut) & Backfilling Compacted To 90% MDD
Pay Item Estimated Total Direct Mark-up in % Total Mark-up VAT (12% DC+Mark
Description Quantity Quantity Unit Direct Unit Cost Total Indirect Cost Total Cost Total Unit Cost
No. Cost OCM Profit % Value up)
2.0 Island 2 (Area=100.00Ha.) 100 100.00 sq.m. 6,767,463,048.08 10 10 20 1,353,492,609.62 974,514,679.00 2,328,007,288.62 9,095,470,337.00 90,954,704.00
3.0 Island 3 (Area=100.00Ha.) 100 100.00 sq.m. 6,490,036,688.65 10 10 20 1,298,007,337.73 934,565,284.00 2,232,572,621.73 8,722,609,311.00 87,226,094.00
Page 6 of 13
H MISCELLANEOUS STRUCTURES
612(1) Reflectorized Thermoplastic Pavement Markings (White) 4,767.00 0.68 3,271.40 sq.m. 887.00 2,901,735.69 10 10 20 580,347.14 417,850.00 998,197.14 3,899,933.00 1,193.00
SPL 620(a) Concrete Barrier (New Jersey Type A) Main Allignment 7,060.00 1.00 4,845.00 l.m. 4,638.00 22,471,110.00 10 10 20 4,494,222.00 3,235,840.00 7,730,062.00 30,201,172.00 6,234.00
SUB-TOTAL (PART H) 25,372,845.69 8,728,259.14 34,101,105.00
Page 7 of 13
407(1) Lean Concrete 18.00 18.00 cu.m. 4,200.00 75,600.00 10 10 20 15,120.00 10,887.00 26,007.00 101,607.00 5,645.00
412(1)a Elastomeric Bearing Pad (350 x 500 x 75mm) 40.00 40.00 each 9,267.00 370,680.00 10 10 20 74,136.00 53,378.00 127,514.00 498,194.00 12,455.00
SPL418(a) Expansion Joint, Type A (M80 Multiplex) 101.00 101.00 l.m. 18,735.00 1,892,235.00 10 10 20 378,447.00 272,482.00 650,929.00 2,543,164.00 25,180.00
SPL419 Premolded Expansion Joint Filler with Sealant (12mmthk), Type B 101.00 101.00 l.m. 810.00 81,810.00 10 10 20 16,362.00 11,781.00 28,143.00 109,953.00 1,089.00
SUB-TOTAL (PART F) 49,046,550.00 16,872,018.00 65,918,570.00
G DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(5) Grouted Riprap, Class A 231.00 231.00 cu.m. 2,019.00 466,389.00 10 10 20 93,277.80 67,161.00 160,438.80 626,828.00 2,714.00
511(1) Gabions (1000mm x 1000mm x 2000mm) 888.00 888.00 cu.m. 1,450.00 1,287,600.00 10 10 20 257,520.00 185,415.00 442,935.00 1,730,535.00 1,949.00
511(2) Mattresses (Boulder Matting) 132.00 132.00 cu.m. 3,000.00 396,000.00 10 10 20 79,200.00 57,024.00 136,224.00 532,224.00 4,032.00
SUB-TOTAL (PART G) 2,149,989.00 739,597.80 2,889,587.00
Page 8 of 13
5.2 Island 2 (Area=119.00Ha.) 119
Excavation (river Rechanneling/Dredging) 199,390.00 4,863.17 578,717.32 cu.m. 255.00 147,572,915.85 10 10 20 29,514,583.17 21,250,500.00 50,765,084.00 198,338,000.00 343.00
Sand Matting 199,390.00 4,863.17 578,717.32 cu.m. 820.00 474,548,200.00 10 10 20 94,909,640.00 68,334,941.00 163,244,581.00 637,792,781.00 1,103.00
Embankment from Dreging/River Rechanneling (Common Material) 2,152,500.00 52,500.00 6,247,500.00 cu.m. 300.00 1,874,250,000.00 10 10 20 374,850,000.00 269,892,000.00 644,742,000.00 2,518,992,000.00 404.00
Containment
1. Steel Sheet Piles - l.m. 582,784.44 - 10 10 20 - - - - #DIV/0!
2. Armor Rock-Road Side
Core Gravel (10mmØ-150mmØ) 2865 201,800.00 4,921.95 57,300.00 cu.m. 820.00 46,986,000.00 10 10 20 9,397,200.00 6,765,984.00 16,163,184.00 63,149,184.00 1,103.00
Underlayer Rock Armor 18,300.00 446.34 2,292.00 cu.m. 3,000.00 6,876,000.00 10 10 20 1,375,200.00 990,144.00 2,365,344.00 9,241,344.00 4,032.00
Upper Rock Armor 34,290.00 836.34 859.50 cu.m. 2,500.00 2,148,750.00 10 10 20 429,750.00 309,420.00 739,170.00 2,887,920.00 3,360.00
3. Soil Improvement
Vertical wick drain 1,785,000.00 l.m. 235.00 419,475,000.00 10 10 20 83,895,000.00 60,404,400.00 144,299,400.00 563,774,400.00 316.00
Surcharge 595,000.00 cu.m. 800.00 476,000,000.00 10 10 20 95,200,000.00 68,544,000.00 163,744,000.00 639,744,000.00 1,076.00
Geotextile or Sand Filter 34,780.00 848.29 100,946.83 sq.m. 396.00 39,974,944.39 10 10 20 7,994,988.88 5,756,392.00 13,751,381.00 53,726,326.00 533.00
Embankment from Selected Borrow 512,500.00 12,500.00 1,487,500.00 cu.m. 423.00 629,212,500.00 10 10 20 125,842,500.00 90,606,600.00 216,449,100.00 845,661,600.00 569.00
Structural Concrete Class A, for Minor Structures 3,200.00 78.05 9,287.80 cu.m. 5,321.00 49,420,409.76 10 10 20 9,884,081.95 7,116,540.00 17,000,622.00 66,421,032.00 7,152.00
Reinforcing Steel Bars, Grade 60 319,310.00 7,788.05 926,777.80 kgs 50.00 46,338,890.24 10 10 20 9,267,778.05 6,672,801.00 15,940,580.00 62,279,471.00 68.00
TOTAL ISLAND 2 4,212,803,610.24 1,449,204,446.00 5,662,008,058.00
Page 9 of 13
Project: PROPOSED CALAMBA TO LOS BAÑOS BYPASS ROAD
Subject: ESTIMATED CONSTRUCTION COST
Option: Densification (using admixture) (with 5% factor)
Page 10 of 13
612(1) Reflectorized Thermoplastic Pavement Markings (White) 4,767.00 0.68 3,271.40 sq.m. 887.00 931.35 3,046,822.48 10 10 20 609,364.50 438,743.00 1,048,107.50 4,094,930.00 1,252.00
SPL 620(a) Concrete Barrier (New Jersey Type A) Main Allignment 7,060.00 1.00 4,845.00 l.m. 4,638.00 4,869.90 23,594,665.50 10 10 20 4,718,933.10 3,397,632.00 8,116,565.10 31,711,231.00 6,546.00
SUB-TOTAL (PART H) 26,641,487.98 9,164,672.60 35,806,161.00
Page 11 of 13
407(1) Lean Concrete 18.00 18.00 cu.m. 4,200.00 4,410.00 79,380.00 10 10 20 15,876.00 11,431.00 27,307.00 106,687.00 5,928.00
412(1)a Elastomeric Bearing Pad (350 x 500 x 75mm) 40.00 40.00 each 9,267.00 9,730.35 389,214.00 10 10 20 77,842.80 56,047.00 133,889.80 523,104.00 13,078.00
SPL418(a) Expansion Joint, Type A (M80 Multiplex) 101.00 101.00 l.m. 18,735.00 19,671.75 1,986,846.75 10 10 20 397,369.35 286,106.00 683,475.35 2,670,323.00 26,439.00
SPL419 Premolded Expansion Joint Filler with Sealant (12mmthk), Type B 101.00 101.00 l.m. 810.00 850.50 85,900.50 10 10 20 17,180.10 12,370.00 29,550.10 115,451.00 1,144.00
SUB-TOTAL (PART F) 51,498,877.50 17,715,618.50 69,214,501.00
G DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(5) Grouted Riprap, Class A 231.00 231.00 cu.m. 2,019.00 2,119.95 489,708.45 10 10 20 97,941.69 70,519.00 168,460.69 658,170.00 2,850.00
511(1) Gabions (1000mm x 1000mm x 2000mm) 888.00 888.00 cu.m. 1,450.00 1,522.50 1,351,980.00 10 10 20 270,396.00 194,686.00 465,082.00 1,817,062.00 2,047.00
511(2) Mattresses (Boulder Matting) 132.00 132.00 cu.m. 3,000.00 3,150.00 415,800.00 10 10 20 83,160.00 59,876.00 143,036.00 558,836.00 4,234.00
SUB-TOTAL (PART G) 2,257,488.45 776,578.69 3,034,068.00
Page 12 of 13
3. Soil Improvement
Vertical wick drain 1,785,000.00 l.m. 235.00 246.75 440,448,750.00 10 10 20 88,089,750.00 63,424,620.00 151,514,370.00 591,963,120.00 332.00
Surcharge 595,000.00 cu.m. 800.00 840.00 499,800,000.00 10 10 20 99,960,000.00 71,971,200.00 171,931,200.00 671,731,200.00 1,129.00
Geotextile or Sand Filter 34,780.00 848.29 100,946.83 sq.m. 396.00 415.80 41,973,691.61 10 10 20 8,394,738.32 6,044,212.00 14,438,951.00 56,412,643.00 559.00
Embankment from Selected Borrow 512,500.00 12,500.00 1,487,500.00 cu.m. 423.00 444.15 660,673,125.00 10 10 20 132,134,625.00 95,136,930.00 227,271,555.00 887,944,680.00 597.00
Structural Concrete Class A, for Minor Structures 3,200.00 78.05 9,287.80 cu.m. 5,321.00 5,587.05 51,891,430.24 10 10 20 10,378,286.05 7,472,366.00 17,850,653.00 69,742,084.00 7,509.00
Reinforcing Steel Bars, Grade 60 319,310.00 7,788.05 926,777.80 kgs 50.00 52.50 48,655,834.76 10 10 20 9,731,166.95 7,006,441.00 16,737,608.00 65,393,443.00 71.00
TOTAL ISLAND 2 4,423,443,790.76 1,521,664,670.00 5,945,108,463.00
Page 13 of 13