1. Lead-time demand for a product is normally distributed with a mean of 12 and a standard deviation of 4.
If the store manager wants the probability of a stock out to be no more than 2.5% what should the
reorder point be? [Both A & B] [02]
2. Use congruential method and generate 4 random integers. Also mention the longest possible period for
a=9, c=35, Xo =13; m=25; [Both A & B] [03]
3. Test whether the 3rd, 8th, 13th and so on numbers in the sequence given below are auto correlated at
α=0.05. [Note: XX-last 2 digits of your roll no.] [06]
0.30 0.48 0. XX 0.01 0.54 0.34 0.96 0.06 0.61 0.85 0.48 0.86 0.14 0.86 0.89 0. XX 0.49
0.60 0.04 0.83 0. XX 0.83 0.37 0.21 0.90 0.89 0.91 0.79 0.57 0.99 0.95 0. XX 0.41 0.81
0.96 0. XX 0.09 0.06 0.23 0.77 0.73 0.47 0.13 0.55 0.11 0.75 0.36 0.25 0.23 0. XX 0.60
0.84 0.70 0.30 0.26 0.38 0.05 0.19 0. XX 0.44