Method Statement For Installation For Curtain Wall (Unitized)
Method Statement For Installation For Curtain Wall (Unitized)
Method Statement For Installation For Curtain Wall (Unitized)
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
METHOD STATEMENT
FOR
FOR
FOR
VENETIAN MACAU
IN
COTAI, MACAU
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 2 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
CONTENTS
1. SCOPE OF WORK
2. WORK METHODOLOGY
3. RESOURCE REQUIRED
6. PROVISION OF INFORMATION
7. VERIFICATION RECORDS
8. APPENDICES
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 4 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
1. SCOPE OF WORK
The curtain wall, aluminium cladding and GRC cladding installation for this project
is independently installed externally as a external façade system and will have no
direct interface with other trade except for internal finishing.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 5 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
2. WORK METHODOLOGY
2.1 Time
The external facade system for L36 ~ Roof will be installed under normal working
hours. Night shift for installation will be required subject to the available of Tower
Crane and actual site progress.
2.2 Duration
The external facade system for L36 ~ Roof will be installed according to approved
installation programme.
2.3 Sequence
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 6 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
a. Clean the top face of pre-cast imbed by wire brush to remove dust and
cement slag.
b. Major Trade Contractor to make-good any uneven concrete surface at
insert location to achieve a smooth bearing surface prior to bracket
installation.
c. Install the bracket onto the embed by fixing.
d. Set the bracket in accurate in and out position and tighten the anchor
bolts.
e. Set the aluminium serrated plate on accurate level and tighten the
anchor bolts.
f. Double check the set curtain wall anchors for accuracy.
g. Torque check of bolts on fixing (As per ITP plan).
a. Curtain wall units are unloaded onto the Loading Platform on 38/F as
for temporary storage until they are required for installation.
b. During storage on site, the units will be covered with plastic sheet.
c. A special custom made double track monorail system will be used and
set up on top of roof parapet wall.
d. An electric chain block of SWL 1.0 will be mounted onto the steel
monorail track. The complete system shall undergo safety load test by
an independent qualified party and test reports/statutory forms are then
submitted to Main Contractor for record.
e. To install fire insulation according to approved shop drawing at top part
of concrete beam surface prior to curtain wall installation.
f. Curtain wall units are then hoisted up from the Loading Platform by
means of this monorail and electric chain block and place in position at
floor edge for fixing to the pre-installed anchor brackets.
g. Upon final adjustment of the units by means of dummy level,
theodolite, and torque checking (as ITP plan), tightening the fixing
bolts to its correct torque by torque check test on site with RE / MTC &
SSC relevant QA personnel to witness of inspection.
h. Proceed with next curtain wall unit installation and seal all gutters as
per approved shop drawings details.
i. A 100% flood test to the gutters shall be carried out by Factory for a
period of no less than 24 hours without water seepage. Take record and
send to site together with unit delivery for site reference.
j. Install EPDM flashing and seal up the curtain wall system as a
waterproof barrier.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 7 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
a. Cast-in Embed
b. Setting Out
Refer to 2.3.1.2
d. Mobilization:
- Once landed on podium, the GRC panel will then be hoisted by Roof
tower crane to the roof level.
- Once landed on tower Roof, the Roof tower crane will help to
distribute the panel to the appropriate location.
- All GRC will be installed by using of Tower Crane from interior of
the parapet wall to the exterior of parapet wall, and drop down for
installation.
e. Installation procedure:
2.4 Location
The curtain wall, aluminium cladding and GRC cladding installation will be carry
throughout the whole external façade of the Hotel building from L36 to R/F.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 10 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
3. RESOURCE REQUIRED
3.1 Personnel
3.2 Plant
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 12 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
3.3 Materials
All materials to be used will be clearly stated in our approved shop drawing.
3.5 Supervision
a. Our site manger will carry out a briefing to all team members to explain all
working procedures as well as site safety prior to work commencement.
b. Our supervisor will full time supervise the work to ensure all works are done
according to approved shop drawing.
c. Our Safety Supervisor will check the work at the following stages:
i) Stage 1 – before work commencement
l To ensure all workers are equipped with proper personal protective
equipments.
l To ensure the workplace is in a safe working environment with proper
access.
l To ensure all scaffolding and loading platform to be obtained with
valid certificate.
l To ensure all lifting appliances and gears are in a safe order with valid
certificate.
ii) Stage 2 – during working
l To check all workers are wearing proper personal protective
equipments.
l To check all workers are working in a safe manner.
iii) Stage 3 – after work completion
l To ensure all debris are clear off.
l No oil / grease remained in the workplace.
l No fire source left on the workplace.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 13 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
Our Assistant Project Manager and Site Manager together with our Safety Supervisor will
carry out risk assessment to identify the effective procedures and practices and the possible
situations where the plant or associated systems of work may pose hazards.
Risk assessment will be recorded with detailed precautions. It should be used to formulate
clear instructions for all persons involved.
Foreseeable hazardous operations associated with this project are summarized as follows:
4.1 Access/Egress
l All work areas must be kept clean and orderly. Rubbish, debris, waste and
useless material constitute a fire hazard, as well as a potential tripping
hazard on the job, and must be removed from work areas as fast as they
accumulate. Areas for temporary accumulation to be provided by Major
Trade Contractor for dumping of debris.
l All work areas must be kept clean and free from loose material and trash.
Storage and stacking areas must be kept in an orderly condition to allow
safe access to the materials. Access road to site office and site store must be
kept clear and clean.
l Stacking of materials shall be properly arranged and not placed at access
and egress.
l All management and supervisory personnel are required to carry out
continual health and safety surveillance and take immediate steps to remedy
defects or unsafe practices they observed.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 14 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
l Safety Supervisor
l Scaffolding erection and dismantle
l Welding Works
l Gondola regular inspection
l Fork Lift Driver License
l Abrasive wheel
l Cartridge operation
l Test Laboratory for Weld Test/Embed Test
l RPE for checking of Lifting Appliances and Gears
Netfortune will establish and maintain procedures designed to control risks arising
from handling, storage, use and disposal of substances hazardous to health
Netfortune will supervise and monitor the implementation of the procedures which
will include, but may not be limited to:
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 15 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
5.2 Security
All sorts of communication including work instruction and documents will be sent /
received through Major Trade Contractor and Major Trade Contractor will further
distribute / collect to the associated parties.
All co-ordination with other trades will be arranged by Major Trade Contractor for
all interfaced works.
Attend all required meetings with appropriate persons held by Major Trade
Contractor.
Both Netfortune, Major Trade Contractor and associated parties should keep a fast
and close communication to reflect / report all the site conditions such as unsafe
working condition, incidents or accidents to maintain a safe working environment.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 16 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
Work instruction and field control briefing will be carried out to all team leaders by
our Site Manager to explain all the working procedures, installation method,
precautions during working and associated site safety prior to work commencement.
The briefing shall be included for all sequence of work, document / permit required,
special training for particular work, plant & machineries to be used, any dangerous
substances involved, key environment control, significant health & safety hazard
and controls. This briefing shall be acknowledged by all team leaders to realize the
actual site condition and working process as well as site safety in order to ensure all
works to be carried out in a smooth and safe condition.
5.5 Permits
Adequate supplies of suitable PPE will be maintained by the Company and his Sub-
Contractors, who will each ensure that the appropriate PPE is issued to and used by
their respective project personnel and authorized visitors. The provision of PPE
will be in accordance with the relevant statutory requirements contained within, but
not necessarily limited to: -
The Company and each of his Sub Contractors will establish suitable procedures to
record the issue of each item of PPE to an individual. Every person, including
visitors, issued with an item of PPE will be required to sign a receipt, a copy of
which will be retained in a dedicated file by the Company.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 17 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
The Company will provide secure, adequate and sanitary facilities for the storage of
PPE both before and after issue to their respective personnel.
All personnel will be informed at the time of issue, of the need to maintain the
equipment properly and hygienically and to immediately report any defect or
damage of the PPE. They will also be provided with instruction on the proper use
and maintenance of the equipment where appropriate.
Depending on the work activity of each Sub Contractor and their respective
personnel, the types of PPE that will require to be issued on the project will include
but may not be limited to: -
Safety helmets: With the exception of site office compounds, the whole site
is regarded as a hard hat area and the wearing of helmets is
therefore mandatory. All helmets will comply with British
Standard BS 5240 or an equivalent Hong Kong standard
acceptable to the Factory Inspectorate. Where personnel are
exposed to windy conditions their helmets will be fitted with
chin straps.
Reflective Waistcoats: All personnel will be provided with high visibility reflective
waistcoats, vests or belt for the importance that they are
easily seen while working beside the roads. Each holder to
ensure their continued high visibility will regularly clean the
waistcoats.
Every person issued with PPE is initially responsible for using & maintaining the
equipment and inspecting it regularly to ensure that it remains fit for its intended
use. The Company will also ensure that his sub-contractors regularly monitor the
use and condition of PPE issued to project personnel.
The failure of any individual to use the PPE provided as directed by their employer
is subject to disciplinary action, which may result in the offender‘s dismissal from
the site.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 19 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
6. PROVISION OF INFORMATION
The relevant information of changing will immediately inform to MTC and get
approval of relevant parties involved.
Any emergency arrangement / drills received from Major Trade Contractor will be
recorded at once.
Our Site Manager will directly inform all team leaders for such arrangement during
daily briefing and instruct all team members to participate the arrangement on time
and that arrangement will also be announced in our site notice board to recall all
team members.
Any particular briefing held by third party will be announced by our Site Manager
to all team leaders during daily briefing and be recorded in our site notice board to
recall all team members to participate the briefing on time.
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 20 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
7. VERIFICATION RECORDS
The following records will be classified in independent file for future checking and
submission:
– END –
Rev. 0
Netfortune Engineering (FEA) Macau Limited Page : 21 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
8. APPENDICES
8.1 Hazard Identification Sheet
Rev. 0
Netfortune Engineering (FEA) Macau Limited Hazard Identification Sheet Ref. : VHCM/HI/RF – 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 1 of 4
Project : J3039 Venetian Macau in Cotai, Macau
Work Package : 3110 – Hotel Curtain Wall/Glazing & Aluminium Cladding And GRC Cladding Installation Analysis by : Yeung Ka Wah / Ricky Ip
Worst Harm Due to
Item Job Task People Affected Hazard Cause of Hazard Existing Control Measures Remark
Hazard
1 Loading, unloading and Rigger, Labourer Injury caused by Improper Manual Back and Hand - Keep the working area tidy
distribution of materials manual handling handling Method injury - Working with proper manual lifting method
- Wears appropriate PPE e.g. safety shoes
- Supervision frequently
Falling objects due Improper Lifting Fatality - Ensure loading platforms are examined by
to lifting failure method RPE
- Ensure all LA & LG are examined by RPE
- Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
- Assign qualified operator and banksman and
use walkie-talkie for communication.
2 Cast-in embed checking Surveyor Fall from height Working at height Fatality - Ensure the formwork platform is examined
while working on by RPE
formwork platform - Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
Fall from height Working at height Fatality - Ensure the monorail system and gondola are
while working on examined by RPE
gondola - Regular inspection of gondola by competent
person with valid certificate
- Only competent workers can be worked on
gondola
- Wears appropriate PPE and ensure the fall-
arrest safety device to be properly used
- Specific training, tool box talk
Falling objects from Working at height Fatality - All handy tools to have safety loop and tied
platform/gondola to worker’s hand/firm support during
operation
Netfortune Engineering (FEA) Macau Limited Hazard Identification Sheet Ref. : VHCM/HI/RF – 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 2 of 4
Worst Harm Due to
Item Job Task People Affected Hazard Cause of Hazard Existing Control Measures Remark
Hazard
3 To layout reference Surveyor Fall from height Working at height Fatality - Provide proper platform with adequate guard-
lines and level datum for while working near rail
setting out floor edge - Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
Fall from height Working at height Fatality - Ensure the monorail system and gondola are
while working on examined by RPE
gondola - Regular inspection of gondola by competent
person with valid certificate
- Only competent workers can be worked on
gondola
- Wears appropriate PPE and ensure the fall-
arrest safety device to be properly used
- Specific training, tool box talk
Falling objects from Working at height Fatality - All handy tools to have safety loop and tied
gondola to worker’s hand/firm support during
operation
4 External works for Applicator, Fall from height Working at height Fatality - Ensure the monorail system and gondola are
application of Installer, Caulker while working on examined by RPE
waterproofing, external gondola - Regular inspection of gondola by competent
flashing fixing, fire person with valid certificate
insulation fixing, final - Only competent workers can be worked on
cleaning, water testing, gondola
bracket & sub-frame - Wears appropriate PPE and ensure the fall-
installation arrest safety device to be properly used
- Specific training, tool box talk
Falling objects from Working at height Fatality - All handy tools to have safety loop and tied
gondola to worker’s hand/firm support during
operation
Netfortune Engineering (FEA) Macau Limited Hazard Identification Sheet Ref. : VHCM/HI/RF – 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 3 of 4
Worst Harm Due to
Item Job Task People Affected Hazard Cause of Hazard Existing Control Measures Remark
Hazard
5 Curtain wall installation Installer. Rigger, Falling objects due Improper Lifting Fatality - Ensure the loading platform, monorail system
Labourer to lifting failure method and chain hoist are examined by RPE
- Ensure all LA & LG are examined by RPE
- Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
- Only trained workers can operate the chain
hoist
- Specific training, tool box talk
- Supervision frequently
Fall from height Working at height Fatality - Wear safety harness and ensure safety belt to
while working near be securely fixed to anchorage point
floor edge
Falling objects Working at height Fatality - All handy tools to have safety loop and tied
while working near to worker’s hand/firm support during
floor edge operation
6 Internal works for Installer, Labourer Fall from height Working at height Fatality - Ensure the working platform is erected by
thermal and acoustic while working on competent worker and be inspected by
insulation installation working platform competent person with valid certificate
- Regular inspection of working platform by
competent person
- Wear safety harness and ensure safety belt to
be securely fixed to anchorage point
Netfortune Engineering (FEA) Macau Limited Hazard Identification Sheet Ref. : VHCM/HI/RF – 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 4 of 4
Worst Harm Due to
Item Job Task People Affected Hazard Cause of Hazard Existing Control Measures Remark
Hazard
7 Aluminium and GRC Installer. Rigger, Falling objects due Improper Lifting Fatality - Ensure the loading platform, monorail system
Cladding Installation Caulker, Labourer to lifting failure method and chain hoist are examined by RPE
- Ensure all LA & LG are examined by RPE
- Inspection of the lifting chain and sling are
free of patent defect before commencing of
work
- Only trained workers can operate the chain
hoist
- Specific training, tool box talk
- Supervision frequently
Fall from height Working at height Fatality - Ensure the monorail system and gondola are
while working on examined by RPE
gondola - Regular inspection of gondola by competent
person with valid certificate
- Only competent workers can be worked on
gondola
- Wears appropriate PPE and ensure the fall-
arrest safety device to be properly used
- Specific training, tool box talk
Falling objects from Working at height Fatality - All handy tools to have safety loop and tied
gondola to worker’s hand/firm support during
operation
8 All works All workers Heat stress Overheat of worker Harmful to hearing - Considering worker's age and health
(Summer time) - Drinking water provide
Netfortune Engineering (FEA) Macau Limited Page : 22 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
8. APPENDICES
8.2 Risk Assessment
Rev. 0
Netfortune Engineering (FEA) Macau Limited Risk Assessment Sheet Ref. : VHCM/RA/RF– 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 1 of 4
Project : J3039 Venetian Macau in Cotai, Macau
Work Package : 2120/3110 – Hotel Curtain Wall/Glazing & Aluminium Cladding And GRC Cladding Installation Analysis by : Yeung Ka Wah / Ricky Ip
Item Risk Control Measures Rating of Harm Risk Level3 Recommended Action Remark
Probability1 Consequences2
1 Injury caused by - Keep the working area tidy 3 3 9 (Yellow) Regular inspection
manual handling - Working with proper manual lifting method
- Wears appropriate PPE e.g. safety shoes
- Supervision frequently
Falling objects due - Ensure loading platforms are examined by RPE 3 3 9 (Yellow) Provide specific training and close
to lifting failure - Ensure all LA & LG are examined by RPE supervision
- Inspection of the lifting chain and sling are free of
patent defect before commencing of work
- Assign qualified operator and banksman and use
walkie-talkie for communication.
2 Fall from height - Ensure the formwork platform is examined by RPE 2 3 6 (Yellow) Provide tool box talk
while working on - Wear safety harness and ensure safety belt to be
formwork platform securely fixed to anchorage point
Fall from height - Ensure the monorail system and gondola are 2 3 6 (Yellow) Provide specific training
while working on examined by RPE
gondola - Regular inspection of gondola by competent person
with valid certificate
- Only competent workers can be worked on
gondola
- Wears appropriate PPE and ensure the fall-arrest
safety device to be properly used
- Specific training, tool box talk
Falling objects from - All handy tools to have safety loop and tied to 2 3 6 (Yellow) Provide specific training
platform/gondola worker’s hand/firm support during operation
Note: 1. Probability or Likelihood Rating: Almost Certain (5) Probable (4) Possible (3) Remote (2) Impossible (1)
2. Consequence Rating: Very High (5) High (4) Medium (3) Low (2) Very Low (1)
3. Risk Level: (RED) (ORANGE) (YELLOW) (GREEN)
Netfortune Engineering (FEA) Macau Limited Risk Assessment Sheet Ref. : VHCM/RA/RF– 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 2 of 4
Item Risk Control Measures Rating of Harm Risk Level3 Recommended Action Remark
Probability1 Consequences2
3 Fall from height - Provide proper platform with adequate 2 3 6 (Yellow) Provide tool box talk
while working near guard-rail
floor edge - Wear safety harness and ensure safety
belt to be securely fixed to anchorage
point
Fall from height - Ensure the monorail system and gondola 2 3 6 (Yellow) Provide specific training
while working on are examined by RPE
gondola - Regular inspection of gondola by
competent person with valid certificate
- Only competent workers can be worked
on gondola
- Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
- Specific training, tool box talk
Falling objects from - All handy tools to have safety loop and 2 3 6 (Yellow) Provide specific training
gondola tied to worker’s hand/firm support during
operation
4 Fall from height - Ensure the monorail system and gondola 2 3 6 (Yellow) Provide specific training
while working on are examined by RPE
gondola - Regular inspection of gondola by
competent person with valid certificate
- Only competent workers can be worked
on gondola
- Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
- Specific training, tool box talk
Falling objects from - All handy tools to have safety loop and 2 3 6 (Yellow) Provide specific training
gondola tied to worker’s hand/firm support during
operation
Note: 1. Probability or Likelihood Rating: Almost Certain (5) Probable (4) Possible (3) Remote (2) Impossible (1)
2. Consequence Rating: Very High (5) High (4) Medium (3) Low (2) Very Low (1)
3. Risk Level: (RED) (ORANGE) (YELLOW) (GREEN)
Netfortune Engineering (FEA) Macau Limited Risk Assessment Sheet Ref. : VHCM/RA/RF– 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 3 of 4
Item Risk Control Measures Rating of Harm Risk Level3 Recommended Action Remark
Probability1 Consequences2
5 Falling objects due - Ensure the loading platform, monorail 2 3 6 (Yellow) Provide training and close supervision
to lifting failure system and chain hoist are examined by
RPE
- Ensure all LA & LG are examined by
RPE
- Inspection of the lifting chain and sling
are free of patent defect before
commencing of work
- Only trained workers can operate the
chain hoist
- Specific training, tool box talk
- Supervision frequently
Fall from height - Wear safety harness and ensure safety 2 3 6 (Yellow) Provide tool box talk
while working near belt to be securely fixed to anchorage
floor edge point
Falling objects - All handy tools to have safety loop and 2 3 6 (Yellow) Provide tool box talk
while working near tied to worker’s hand/firm support during
floor edge operation
6 Fall from height - Ensure the working platform is erected 2 3 6 (Yellow) Provide tool box talk
while working on by competent worker and be inspected by
working platform competent person with valid certificate
- Regular inspection of working platform
by competent person
- Wear safety harness and ensure safety
belt to be securely fixed to anchorage
point
Note: 1. Probability or Likelihood Rating: Almost Certain (5) Probable (4) Possible (3) Remote (2) Impossible (1)
2. Consequence Rating: Very High (5) High (4) Medium (3) Low (2) Very Low (1)
3. Risk Level: (RED) (ORANGE) (YELLOW) (GREEN)
Netfortune Engineering (FEA) Macau Limited Risk Assessment Sheet Ref. : VHCM/RA/RF– 001
Activity : Curtain Wall, Aluminium Cladding And GRC
Review No. 01 Date 31 Aug, 2006 Cladding Installation for L36 ~ Roof Page 4 of 4
Item Risk Control Measures Rating of Harm Risk Level3 Recommended Action Remark
Probability1 Consequences2
7 Falling objects due - Ensure the loading platform, monorail 3 3 9 (Yellow) Regular inspection
to lifting failure system and chain hoist are examined by
RPE
- Ensure all LA & LG are examined by
RPE
- Inspection of the lifting chain and sling
are free of patent defect before
commencing of work
- Only trained workers can operate the
chain hoist
- Specific training, tool box talk
- Supervision frequently
Fall from height - Ensure the monorail system and gondola 2 3 6 (Yellow) Provide specific training
while working on are examined by RPE
gondola - Regular inspection of gondola by
competent person with valid certificate
- Only competent workers can be worked
on gondola
- Wears appropriate PPE and ensure the
fall-arrest safety device to be properly
used
- Specific training, tool box talk
Falling objects from - All handy tools to have safety loop and 2 3 6 (Yellow) Provide specific training
gondola tied to worker’s hand/firm support during
operation
8 Heat stress - Considering worker's age and health 2 2 4 (Green) Provide tool box talk
(Summer time) - Drinking water provide
Note: 1. Probability or Likelihood Rating: Almost Certain (5) Probable (4) Possible (3) Remote (2) Impossible (1)
2. Consequence Rating: Very High (5) High (4) Medium (3) Low (2) Very Low (1)
3. Risk Level: (RED) (ORANGE) (YELLOW) (GREEN)
Netfortune Engineering (FEA) Macau Limited Page : 23 of 24
Method Statement for Hotel Curtain Wall/Glazing & Doc. No. : VHCM/MS/RF/001
Aluminium Cladding And GRC Cladding Issue : 001
Installation for L36 ~ Roof Date : 31-Aug-2006
8. APPENDICES
8.3 Sketches
A. Sketch No. 29 – GRC Cladding Installation (Stage 1)
B. Sketch No. 30 – GRC Cladding Installation (Stage 2)
C. Sketch No. 31 –GRC Cladding Installation (Stage 2) Zig-zac Side Set Gondola
Rev. 0
Venetian Hotel in Cotai, Macau
Workage Package : 2120/3110 Curtain Wall,
SKETCH 29
Aluminium Cladding & GRC Cladding Installation
GRC Cladding Installation at L36 ~ R/F (Stage 1)
Support Frame
(with Two Tracks)
Bearing Wall
Roof
L39
L38
L37
L36
Venetian Hotel in Cotai, Macau
Workage Package : 2120/3110 Curtain Wall,
SKETCH 30
Aluminium Cladding & GRC Cladding Installation
GRC Cladding Installation at L36 ~ R/F (Stage 2)
Support Frame
(Tracks Removed)
Bearing Wall
Gondola Wire
Roof Parapet Wall
L39
GRC Column
L38
L37
L36
Venetian Hotel in Cotai, Macau
Workage Package : 2120/3110 Curtain Wall,
SKETCH 31
Aluminium Cladding & GRC Cladding Installation
GRC Cladding Installation at L36 ~ R/F (Stage 2)
Temporary Gondola
GRC Column under Installation
Temporary Gondola
8. APPENDICES
8.4 ‘Evercrete’ Method Statement for Waterproofing
Application
Rev. 0