Professional Documents
Culture Documents
CMAA Sustainability Guidelines
CMAA Sustainability Guidelines
Guidelines
2016 Edition
ISBN: 978-0-9715612-2-6
Copyright ©2016 Construction Management Association of America. All rights reserved. No part of
this publication may be reproduced or distributed in any form or by any means, or stored in a
database of retrieval system, except as permitted by Sections 107 or 108 of the 1976 United States
Copyright Act, without the prior written permission of the publisher.
Table of Contents............................................................................................................i
Acknowledgements ........................................................................................................ v
Preface.......................................................................................................................... vii
Chapter 1: Introduction .............................................................................................. 1
1.1 Sustainability Objectives ........................................................................................................... 2
1.2 Project Management .................................................................................................................. 3
1.3 Cost Management ...................................................................................................................... 5
1.4 Time Management ..................................................................................................................... 6
1.5 Quality Management ................................................................................................................. 7
1.6 Contract Administration ........................................................................................................... 9
1.7 Professional Practice ............................................................................................................... 10
1.8 Safety.......................................................................................................................................... 12
1.9 Risk Management..................................................................................................................... 13
1.10 Building Information Modeling ............................................................................................. 14
Chapter 2: Energy Efficiency, Energy Conservation, and Renewable Energy ....... 17
2.1 Energy Efficiency..................................................................................................................... 17
2.2 Energy Conservation ............................................................................................................... 17
2.3 Energy Use Intensity ............................................................................................................... 18
2.4 Building Energy Management System/Building Management System/Building
Automation System ................................................................................................................. 20
2.5 Energy Modeling ...................................................................................................................... 21
2.6 Energy Efficiency Assessments ............................................................................................. 22
2.7 Lighting ..................................................................................................................................... 23
2.8 Heating, Ventilation, and Air Conditioning ......................................................................... 24
2.9 Energy Building Terminology ................................................................................................ 25
Current Edition:
Deeta Bernstein, LEED AP BD+C, Cotter Consulting, Inc.
Manish Kalantri, AIA, CCM, CEM, CPMP, LEEDAP New York City Housing Authority
The updated 2016 Sustainability Guidelines is intended to supplement the sustainability chapter
of CMAA’s Construction Management Standards of Practice. It provides practical guidance in
sustainability to construction managers in conducting their responsibilities from project
conception through to post occupancy activities.
Sustainable development is development that meets the needs of the present without
compromising the ability of future generations to meet their own needs.
The most common core concepts of sustainability in construction are utility usage efficiency,
resource and waste management, sustainable site development, stormwater management,
high performance building design and construction, maintenance and operation to
sustainable standards, and indoor air quality for healthy buildings and infrastructure.
These guidelines include new subject matter on energy, climate adaptation, and resiliency
planning. New projects and programs require construction managers to keep current with
the evolution of sustainability and how it may impact their clients, projects, and programs.
The 2016 Sustainability Guidelines reflect the most current changes in the sustainability practice
and will be updated as needed to provide meaningful and practical guidance to construction
managers.
Green Globes and the Green Building Initiative (GBI) are registered trademarks of the
Green Building Initiative.
The Pearl Rating System is the green building rating system developed by the Abu Dhabi
Urban Planning Council as part of their sustainable development initiative, Estidama.
The Sustainability Guidelines are intended is to provide the CM with guidance for
implementing a sustainable, green, or high-performance project. The Sustainability Guidelines
are designed in such a way as to avoid providing a prescriptive approach designed to yield a
sustainable project; there are several sustainability certification systems, products, and
approaches currently available to the CM for both buildings and infrastructure. The intent in
offering these guidelines is to provide context, information, and resources that will enable
the CM to successfully complete a sustainable project.
The first critical step in producing a sustainable project is owner adoption of sustainability as
a guiding principle of design. Thereafter, consistent application of project and construction
management practices, meticulous documentation, common sense, and mindful architectural
and engineering design is likely to yield a sustainable project.
The Sustainability Guidelines provide for the integration of sustainability with other functions
integral to the practice of construction management, and identify key sustainability measures
and opportunities in each phase of the project lifecycle. To successfully implement a project
with sustainability objectives or features, the practitioner must be cognizant of a CM’s key
responsibilities with respect to the sustainability program:
If a sustainable project is defined as a project that conserves natural resources, protects the
natural environment, and provides economic benefits to the owner and the community and
social benefits to the community, such as job creation and community service programs,
then sustainability objectives are met with the successful implementation of CM best
practices on a project that has sustainability as a guiding design principle.
The CM’s primary tools to meet scope, schedule, budget, and quality control objectives
should be clearly articulated in the Project or Construction Management Plan and its
component or subordinate elements. The following strategies for integrating sustainability
requirements are suggested:
Taken as a whole, the guidelines and tools of the CM can be used to guide a project to
successful implementation of sustainability requirements by a skilled and conscientious CM
and team1.
It is important to acknowledge the cost and risk profile of sustainability requirements and
proactively apply cost management systems in a manner that protects and conserves the
features they are designed to articulate.
Implementing an integrated design process may help reduce project costs associated with
sustainable design when viewed as a separate set of “features.” Consider integrated design
process as part of project management plan when an owner places high priority on
sustainable design results, and the stakeholder team is receptive to working more closely
together as opposed to working in silos.
The CM must work with the owner to establish sustainability goals and objectives, which will
drive the design and engineering team’s design development and preparation of contract
documents. Sustainability expectations must be identified and clearly articulated as soon as
1
CMAA Construction Management Standards of Practice; CMAA Project Management Guidelines
For instance, if a project is to be registered with the USGBC as a LEED certified project,
the risk of achieving the prescribed level of certification may be managed by selecting an
experienced design team to develop the engineering process, a commissioning consultant to
manage commissioning and quality processes, and a LEED consultant specifically to manage
LEED paperwork and submissions. The costs of specialty equipment and installation should
be estimated early, and market forces that may impact the project identified, and monitored
with the objective of understanding alternative means to meet sustainability objectives within
the project budget.
The rapid development and evolution of emerging sustainability technologies may require
that certain purchases of highly technical components be postponed so that the latest
technology available is incorporated into the project. Adequate contingency for the owner,
designer, and contractors must be established to allow for potential cost increases for such
items.
Standard cost management systems and fundamental project management best practices
combined with an elevated vigilance of the cost risks related to new technologies and
processes will help a project team meet sustainability goals and objectives within budget
expectations2.
2
CMAA Construction Management Standards of Practice; CMAA Cost Management Guidelines
To be effective, sustainable goals and objectives must be built into the program for the
project and not treated as an add-on feature. This requires defining and including tasks
associated with sustainable objectives in the Master Schedule, and assuring that other tools,
such as Milestone Schedules, reflect activities required to meet sustainability goals.
In construction, time contingencies required for sustainable project elements must be built
into the Master and Milestone Schedules, and the CM must closely monitor the performance
of subcontractors and suppliers responsible for these features. Inspection and verification
practices integral to commissioning and quality management will help identify the need for
intervention and mitigation.
Scheduling techniques range from relatively simple bar charts to Critical Path Method (CPM)
analysis and complex software programs. In general, scheduling software is an effective tool,
but does not replace knowledge of basic planning and scheduling concepts and practices as
means to achieve sustainability goals.
For a project with sustainability features that rely on new technologies, practices, or means
and methods, the CM should thoroughly understand new technology and applications,
performance and installations requirements, staging, phasing considerations, and quality
processes. Nothing can replace a vigilant CM that is thoroughly aware of the manner in
which a project’s execution delivers on the promise of its design principles, including
sustainability 3.
3
CMAA Construction Management Standards of Practice; CMAA Time Management Guidelines
If a project requires attaining a specific sustainable building system rating, such as LEED,
Green Globes, Envison, or ENERGY STAR, procedures are adapted or devised to monitor
the responsibilities and obligations of each project participant involved in the process. This
includes submission and processing of relevant certification documentation, requests for
information reasonably necessary to obtain an appropriate written certification, and
notification by the designating body or organization that the intended certification level or
status is achieved.
The commissioning agent (CxA) or Green Building Facilitator (GBF) should be a party to
the quality management organization, and the input of the CxA and/or GBF should be
sought and incorporated in quality and project management documents and procedures.
When a project includes sustainability goals or features, contract administration efforts must
include the means to ascertain compliance with sustainability objectives, and control the
outcome to yield a project that complies with contract documents. The CM should develop
or cause the development of submittal procedures early in the project—in the pre-design
4
CMAA Construction Management Standards of Practice; CMAA Quality Management Guidelines
The real and perceived importance of sustainable development, design, and construction
practices nevertheless grows, driven by advances in climate and biodiversity science, and a
growing consensus that responsible development requires the construction industry to
embrace practices that are sensitive to ecological and environmental factors.
Government units with significant interest and influence in sustainability factors include:
• ASTM E2432
• Standard Guide for the General Principles of Sustainability Relative to Building;
• Energy Independence and Security Act (EISA 2007);
• Energy Policy Act of 2005; and
• Executive Order 13423, Strengthening Federal Environmental, Energy, and
Transportation Management.
5
CMAA Construction Management Standards of Practice; CMAA Contract Administration Guidelines
Knowledge of the sustainability domain is essential for a CM. CMAA strongly encourages
professionals to leverage the resources most closely aligned with their professional training
and work assignments, and to take advantage of professional development opportunities
offered by professional societies, regulatory agencies, and certification authorities.
Finally, consensus guidelines for the building industry have been developed by organizations
dedicated to bringing the principles and goals of sustainability to market. These include:
1.8 Safety
Safety management involves anticipating and implementing procedures to protect the health
and safety of all people on a project site: workers, visitors, and the general public. Safety
management is a risk management strategy for loss control that is designed to protect against
the cost of damage, injury, treatment, and remediation of life and property. As such,
standard safety provisions on a construction project include minimum safety education,
training, and insurance.
A safe job is consistent with sustainable practices. Safety applies to the safety of workers and
the public due to the way a job is run during construction. In the case of many projects with
sustainability features, safety also applies to the features that confer a healthy working
environment after construction is complete due, for instance, to protected and cleaned
ductwork, low VOCs, properly functioning air handling, heating, and cooling systems, and
low GHG emissions.
A measure of safety is the Experience Modification Rate (EMR) which is a multiplier used
by the insurance industry to gauge past cost of injuries, risk of future injuries, and determine
the cost of workers’ compensation during construction. An EMR of 1.0 is considered
average; an EMR less than 1.0 is good; an EMR of greater than 1.0 is relatively poor, which
will be reflected in a higher relative construction bid because an insurer’s workers
compensation rates will be elevated. Another measure of safety performance is Occupational
Safety and Health’s (OSHA) incident rate for “recordable injuries” and “lost time injuries.”
OSHA publishes average industry results for these rates annually for various types and
markets of construction.
For projects with sustainability features that involve new or emerging technologies and
contractors with relatively little experience, EMRs and incident rates may be relatively high
as a result of meager data. Special care should be given to all work elements and areas
involving new or emerging technologies or processes, with particular vigilance to the
6
CMAA Construction Management Standards of Practice
7
CMAA Construction Management Standards of Practice
Risk is most effectively managed by reducing uncertainties. The impact of uncertainties that
cannot be eliminated must be managed using contingencies to establish boundary
expectations. Risk can be reduced through investigation, design, and engineering that
reduces uncertainty, or through various means of transfer to another party, including use of
insurance products.
Risk management efforts should be evaluated at meetings throughout each project phase. To
assure adequate vigilance to sustainability objectives, sustainability-specific status and
challenges should be discussed as a separate agenda item 8.
BIM has the potential to reduce the cost of sustainable design by making design and
engineering information routinely available as standard byproduct of the design process.
BIM offers a collaboration and project delivery platform that meets the needs of project
participants across the project lifecycle, including those responsible for assessing whether the
project will meet the criteria of credit-driven sustainability programs like LEED. Because
BIM can incorporate accurate modeling information early in the design process, BIM can
improve coordination and reduce potential errors associated with assessing sustainability
performance. As-built conditions can be incorporated into a project’s BIM to help determine
if it is being built within specified design tolerances and will achieve specified credits.
BIM can be used to model facility orientation, window placement, and lighting long before a
project is built, and is thus well-suited to assess daylight modeling and solar access, both of
which can factor into a project’s LEED credit profile. Furthermore, BIM can play a
8
CMAA Construction Management Standards of Practice
BIM can be used throughout construction to analyze and communicate the building process
in a virtual environment, including sequence of work, means and methods, logistics, and
documentation of as-built conditions. BIM can provide the project team with ongoing
analysis such as:
BIM’s utility continues throughout the life of the facility, with the model serving as a shared
knowledge resource for information about the facility. The model serves as a reliable basis
for decisions throughout a facility’s lifecycle—from inception through design to
construction, occupancy, and operation.
The CM wishing to leverage BIM on a project with sustainability features must take care to
select a system that represents the facility as an integrated database of coordinated
information that meets the team’s expectations for modeling and management of the design
and construction process, including functions that will facilitate the sustainability program. 9i
9
CMAA Construction Management Standards of Practice
A publication on sustainability is not complete without addressing the many facets of energy
usage in the construction industry and in the facilities that we construct. In this publication,
CMAA strives to highlight key areas of sustainability that CM’s need to understand in order
to provide owners and clients the most up to date information on the benefits of sustainable
design and construction implementation. This chapter highlights all areas that CM’s should
be familiar with in implementing energy efficient facilities, energy conservation, and the
many types of renewable energy options available for sustainable structures. This chapter
focuses on the energy subject areas that are most important to CMs and PMs and includes a
resource guide for obtaining additional information on each topic.
As the most essential component of sustainability, CM’s should ensure that energy efficiency
and renewable energy measures, financing, incentives, and related regulatory issues are
reviewed with owners, and that all energy related measures are implemented as approved by
owners.
Most all of the decisions on energy efficiency, and renewable energy are made during the
pre-design phase and developed during the design phase. During procurement and
construction, sustainability features are monitored to assure the specified equipment
is purchased and properly installed. Commissioning should demonstrate that the systems
meet the expected goals. This activity continues into the building operations phase.
There are several pieces of legislation at the federal, state, and local levels that call for energy
use intensity standards for buildings and infrastructure. Some examples of federal legislation
for energy efficiency are as follows:
The Energy Policy Act of 1992 v established regulations requiring certain federal, state,
and alternative fuel provider fleets to build an inventory of alternative fueled vehicles
(AFVs). It was amended several times in the Energy Conservation and Reauthorization Act
of 1998 and in 2005 via the Energy Policy Act of 2005, vi which emphasized alternative
fuel use and infrastructure development.
The American Recovery and Reinvestment Act of 2009 vii appropriated nearly $800
billion towards the creation of jobs, economic growth, tax relief, improvements in education
and healthcare, infrastructure modernization, and investments in energy independence and
renewable energy technologies and fuel tax credits. ARRA legislation was tied to mandatory
adoption of state energy codes—starting with ASHRAE 90.1—2009 with mandatory
“upgrades” every three years. ASHRAE’s goals are to target NET ZERO or energy neutral
construction by 2020.
Executive Order 13693 issued in 2015, raised the bar on energy efficiency and sustainability
measures for federal agencies yet again, including specific goals for energy use reduction and
renewable energy implementation.
California has its own energy efficiency standards in its Title 24, which is updated
periodically to more stringent energy standards. Copies of the most current version of Title
24: www.energy.ca.gov/title24/ x
The Federal Environmental Protection Agency and Department of Energy created the
ENERGY STAR program 1992 under the authority of the Clean Air Act Section 103(g).
Section103(g) of the Clean Air Act directs the Administrator to "conduct a basic engineering
research and technology program to develop, evaluate, and demonstrate non–regulatory
strategies and technologies for reducing air pollution." In 2005, Congress enacted the Energy
Policy Act. Section 131 of the Act amends Section 324 (42 USC 6294) of the Energy Policy
and Conservation Act, and "established at the Department of Energy and the Environmental
Protection Agency a voluntary program to identify and promote energy–efficient products
and buildings in order to reduce energy consumption, improve energy security, and reduce
pollution through voluntary labeling of or other forms of communication about products
and buildings that meet the highest energy efficiency standards."
For the CM, the ENERGY STAR program provides direct support in the selection of
energy efficient products in construction, as well as energy efficiency tools for construction:
• For Products: In order to earn the label, ENERGY STAR products must be
third-party certified based on testing in EPA-recognized laboratories. In addition to
up-front testing, a percentage of all ENERGY STAR products are subject to "off–
the–shelf" verification testing each year. The goal of this testing is to ensure that
changes or variations in the manufacturing process do not undermine a product's
qualification with ENERGY STAR requirements.
Both the performance and prescriptive paths require completion of four inspection
checklists:
These checklists include building science practices that promote improved comfort, indoor
air quality, and durability in certified homes. The inspection checklists document contains
the four checklists that every home certified under version 3 must complete.
• For Industrial Plants: A Professional Engineer must certify that the information
used to calculate the plant‘s 75 or higher energy performance score is correct. In
addition, the plant must satisfy EPA environmental compliance criteria screen. xii
In new construction, EMS/BMS/BAS can also monitor security, fire alarms, water flow
alarms, and virtually all other electrical loads in a building, depending the desired level of
control and monitoring required by the owner, and the costs of implementation.
ISO 50001 provides guidance and specifies requirements for establishing, implementing,
maintaining, and improving an energy management system, whose purpose is to enable an
Like other ISO management system standards, certification to ISO 50001 is possible but not
obligatory. Some organizations decide to implement the standard solely for the benefits it
provides. Others decide to to certify to show external parties they have implemented an
energy management system. ISO does not perform certifications. xiii
Many utility companies throughout the US and some international entities have implemented
automated demand reduction (ADR) programs. These programs are intended to notify
building owners of an emergency to shed electricity loads in whatever ways they can to
prevent power requirements from exceeding power supply, such as during extreme heat
waves. The EMS/BMS/BAS play a key role in receiving the notification from the utility, and
then shedding loads in pre-programmed ways as agreed between the owner and the utility,
without significantly impacting the operation of the building.
Energy models typically provide estimated total energy usage of the project that not only
enable the design team and the client to understand what the approximate costs will be to
operate the building’s energy requirements, but also to estimate the energy that may be offset
by on-site renewable energy systems.
Energy modeling and simulation is typically performed by the assigned mechanical engineer
reporting to the A/E team. Energy modeling is an iterative process that should begin in the
pre-design phase to help inform the design team of critical decisions of orientation, siting,
and façade construction. As design progresses, a complete energy model should require the
development of several models in the design process, and should be conducted by the A/E
team frequently enough to validate the design solution.
2.6.1 Benchmarking
Benchmarking is the process of comparing energy performance of the project to something
similar. “Something similar” might be internal, like performance at the same time last year in
a modernization project, or it might be external for a new construction project, like
performance compared to similar facilities elsewhere. In several instances, the owner will
have pre-defined benchmarks that fall into these general categories, however they may
require support from the CM to provide them with guidance in establishing appropriate
benchmarks for their specific needs.
It may be worth noting that a growing number of municipalities are enacting benchmarking
ordinances to promote improvements to energy efficiency of existing building stock. At
minimum, such ordinances serve to raise building owner awareness of the energy efficiency
or lack thereof, of their buildings in comparison with other similar buildings.
The ENERGY STAR program provides free tools to assist in establishing benchmarks:
www.energystar.gov/buildings/about-us/how-can-we-help-you/benchmark-energy-
use/benchmarking xiv
Some sustainability certification systems, such as LEED’s v4, provide additional credits for
sub-metering any load or category of loads that consume more than 10% of the total site’s
electrical consumption and/or demand.
2.7 Lighting
For many buildings constructed around the world, lighting consumes approximately 40% of
the energy of the total site. That estimate is improving based on the development and
implementation of new lighting technologies, particularly Light Emitting Diode (LED)
lighting. As costs for LED lighting continue to drop, and energy prices continue to rise,
adoption rates of LED lights for new construction and modernizations should improve over
current implementation.
Recent advances in newer DX systems now allow the compressors to run more efficiently in
partial load performance modes and allow for the use of variable speed drives and higher
efficiency motors for the supply and return fan motors, improving the energy efficiency of
the total DX system. Although DX systems may not be as efficient as most chilled water
systems, some clients prefer having multiple package units rather than one centralized chiller
system to improve redundancy and more defined zone control.
Variable speed drives, (VSDs), or variable frequency drives, (VFDs) are now commonplace
in most HVAC systems to control fans, pumps, and compressors. Each type of drive serves
to modulate the operation of the motor it serves, making it more efficient if programmed
correctly through an automation system.
The air-side economizer is integrated into a central air handling system with ducting for both
intake and exhaust; its filters reduce the amount of particulate matter, or contaminants, that
are brought into the building. Utilizing free cooling is an important part of the sequence of
operation to either delay or minimize the need for mechanical cooling from compressor or
chillers.
Existing buildings may not have air-side economizers, depending upon the age of the
building, the location, or the building type, thus may not be able use outside air as an
effective cooling method.
Even though the installation price of a geothermal system can be several times that of an air-
source system of the same heating and cooling capacity, the additional costs are recouped in
energy savings.
Some parts of the world are not hospitable to the operation of geothermal heat pumps due
to environmental factors such as high seismic activity and lack of sufficient temperature
transfer due to minimal differences between above ground and below ground temperatures.
A ZEB generates the same total amount of all energy as is used, not just electricity, but all
fuels used on-site including natural gas and propane, and includes the energy used to
transport the energy to the building. A building may be considered a ZEB if 100% of the
energy it purchases comes from renewable energy sources, even if the energy is generated
off-site.
Within the electricity grouping, electricity can be delivered in a number of ways, including
utility provided power, power from third-party off-site energy providers, on-site solar and
wind, and biogas from available on-site digester systems that can be used to power turbines
on site.
2.13.1 Solar
There are three main types of solar collectors:
• Photovoltaic: Photovoltaic (PV) solar panels are those most commonly used in
commercial and residential installations. Pricing for panels has been reduced
significantly since 2008, and installation costs have improved dramatically as well
with improvements in mounting hardware and installation methods. Innovations in
inverters that transform the electricity generated by the panels from direct current
(DC) to alternating current (AC) have resulted in improved cost efficiencies in both
installation and operations.
Photovoltaic panels can be mounted on rooftops, carports, and the ground. They
can be mounted on a fixed tilt system which do not adjust to the movements of the
sun or they can be mounted on single or dual axis trackers that adjust to the
movements of the sun throughout the day.
• Concentrated Solar Power (CSP): Although there are several types of CSP
collectors, most use highly reflective surfaces to collect heat that is transferred to a
fluid which powers a turbine. These systems are highly specialized and are normally
found in utility scale installations generating large numbers of megawatts. The vast
majority of these systems do not lend themselves to installation on buildings or
carports due to their size and heat generation.
• Thermal Solar Collectors: Thermal solar collector technology uses the heat
from the sun to create energy that then is used to heat water or other fluids.
Solar thermal systems differ from solar PV systems, which generate electricity rather than
heat. Some common uses of thermal solar collectors are to provide warmer water for hot
water heaters and swimming pools.
Concentrated thermal solar collectors are capable of reaching higher water temperatures that
may be designed to support absorption chillers and hot water requirements for food and
healthcare.
Few projects incorporate small wind turbines adjacent to buildings or on rooftops in urban
areas due to code restrictions and community resistance. Large-scale wind turbines are
installed in rural high wind capacity parts of the world. It is gaining worldwide popularity as a
large-scale energy source, although it still only provides less than 1% of global energy
consumption. xvi
Fuel cells are used in a wide range of applications, including transportation, material
handling, stationary, portable, and emergency backup power applications. Fuel cells have
several benefits over conventional combustion-based technologies currently used in many
power plants and passenger vehicles. Fuel cells can operate at higher efficiencies than
combustion engines and can convert chemical energy in the fuel to electrical energy with up
to 60% efficiency. Fuel cells have lower emissions than combustion engines. Fuel cells are
quiet during operation as they have fewer moving parts. Fuel cells work like batteries, but
they do not run down or need recharging. They produce electricity and heat as long as fuel is
supplied. xvii
2.13.4 Micro-Turbines
Micro-turbines are a distributed generation technology used for stationary energy generation
applications. They are a type of combustion turbine that produces both heat and electricity
on a relatively small scale. These units are capable of running on biogas or natural gas, which
makes them another renewable energy option for projects.
While it is unlikely that a project will have hydro power supplied directly to the site, the
owner may elect to purchase hydro power from their servicing utility in order to satisfy
renewable energy requirements of certification systems or their own sustainability goals.
10 www.pge.com/en/b2b/energytransmissionstorage/newgenerator/netenergymetering/index.page
Project decision making should always include local site conditions and climate
considerations. The CM should support the project planning process by assisting
practitioners in identifying, evaluating, selecting, and implementing design considerations
that take into account local climate conditions and that decrease project vulnerabilities to
extreme weather events. The climate resilient project attributes described in these guidelines
are designed to promote actions by the CM/PM to take into account and include methods
to adapt to climate variability and the safeguarding of people and property.
Resilience is defined in many ways. For the purposes of this guideline, resilience is the
capability of a system to recognize, anticipate, and defend against the changing shape and
timing of risk before adverse consequences occur. It is also to provide the adaptive capacity
to recover quickly and the ability to withstand major disruptions with acceptable levels of
degradation and recovery within acceptable ranges of time, cost, and risk.
3.1 Planning
Planning addresses the plans needed for the prudent protection and upgrading of
infrastructure, critical facilities, systems, and functions before an event occurs to ensure
resiliency, withstand stressors to maintain functionality of operations, and support human
CMs can obtain both historical and projected data for temperature change, precipitation, sea
levels, coastal land subsidence, storm surges, and seismic activity from the United States
Geological Service (USGS), Caltech, NOAA, major universities within the region, the State
Land Commissions, and State Sea Grants. All these attributes may have an impact on
potable water supplies, storm water storage and conveyance, wastewater treatment assets,
electrical, natural gas, and building and transportation assets that are critical to water
protection and conveyance.
There are several tools emerging for conducting resiliency assessments and some are publicly
established such as those developed by the Army Corps of Engineers. These tools were
developed to provide a structured approach to assess water infrastructure assets and to
conduct the risk, hazard, and vulnerability assessments for all other types of assets, buildings,
and systems under the scope of the project.
• Construction Managers
• Adaptation risk analysts
• Emergency response professionals
• Facility managers
Internal risk assessors and insurance industry resources are also needed to conduct the risk
management assessments that will provide the key information regarding probability
projections of potential loss resulting from damage and loss of operations of systems, as well
as their short- and long-term impacts on human health and safety.
1. Estimate the likelihood that a major climate event will affect a specific site.
2. Determine how many times the site was impacted in the past with severe
consequences.
3. Assess recent improvements to the site that may provide protection from future
events.
4. Capture specific lessons learned from prior events.
5. Identify specific weak points in the site that need to be addressed prior to the next
event.
It is important to focus on what makes that site or facility critical, as well as what will happen
if the facility is unable to operate for varying periods of time, and to identify critical
functions within facilities such as:
1. Command centers
2. Data centers
3. Telecom rooms
4. Emergency power
5. Main switchgear
The CM may need to report on the current flow rates and waste produced
throughout the systems being utilized. This report includes identifying
potential for improvements that may lead to energy consumption
reductions, waste utilization, and increased energy production, and
identify any ecological impacts of any project recommendations.
The utilization of LID design and construction methods should be used in any building or
infrastructure project that is targeting resiliency and improving adaptive capacity. Some
examples of LID development design and construction include:
The pre-design phase may be the first opportunity for the CM to apply the construction
management process toward meeting the objectives of a sustainable project. The pre-design
phase is the period before schematic design commences during which the project is initiated
and the program is developed. It is the planning and conceptual stage.
Many conceptual design and estimating iterations may be required before a project meets the
owner’s time, cost, quality, sustainability, and other performance requirements. Once these
requirements are established and approved by the owner, the team must be committed to
completing the project within those requirements.
Sustainability goals, objectives, and requirements vary greatly and can include:
Sustainability goals, objectives, and requirements are also the basis of critical follow-on
activities such as:
Sustainability goals, objectives, and requirements must be incorporated into a document that
describes the sustainability program approach and preliminary sustainability scorecard.
Programming by the designer should include both documents. Time should be allotted for
developing both of these deliverables and to evaluate them as they will influence process and
budget.
Specific guidelines and codes should be referenced and included in contract documents. The
contract documents should include guidance and provisions for identifying project
expectations and participant roles and responsibilities, instituting procedures, and addressing
risk allocation on projects with sustainability requirements.
Depending on the type and complexity of the project and its sustainability features, the
owner should be encouraged to consider design consultants with experience and distinct
responsibilities for the sustainable design and construction program, such as:
Consultants should be selected based on general suitability and verifiable past performance
on work of a similar nature.
Responsibilities and requirements for the sustainability reviews and document preparation
should be clearly articulated in A/E, CM, CxA, and GBF contracts.
For example, federal government agencies have adopted high performance facility
requirements. GSA requires that all new construction projects and substantial renovations
must achieve equivalent LEED Silver certification, although GSA encourages project teams
to exceed LEED Silver and achieve LEED Gold.
4.2.1 Design-Bid-Build
Design-Bid-Build (D-B-B) is a traditional approach that involves design and production of
contract documents by an A/E, followed by competitively bidding the project to a third
party contractor. Risks to realizing the sustainability features of a project can be mitigated
through clear and complete contract and bid documents that clearly identify sustainability
features.
4.2.2 CM-at-Risk
CM-at-Risk is a delivery method in which the CM is contracted to deliver the project within
the owner’s budget, in many cases pursuant to a Guaranteed Maximum Price (GMP). On a
CM-at-Risk project, the CM acts on the owner’s behalf to facilitate and coordinate design,
and continues as the equivalent of a general contractor during the construction phase. To
mitigate the CM’s exposure to risks on a CM-at-Risk project with sustainability features, a
CM must have a thorough understanding of associated cost, schedule, and quality
considerations with a clearly defined certification goal if applicable.
4.2.3 Design-Build
Design-Build (D-B) is a project delivery system characterized by the owner conveying
contractual responsibility for design development, engineering, and construction to a single
entity, thereby enabling overlap of the design and construction phase, and encouraging
collaboration between the builder and the engineer. This system is promoted as a means to
mitigate project risk and reduce the delivery schedule. D-B supports achieving project
sustainability features by bringing the builder’s practical experience to bear on the planning
and design of the sustainability elements at an early stage.
1. A multi-party contract signed by the owner and an architect (or A/E) and a CM (or
general contractor) instead of separate contracts for each. Other key consultants or
subcontractors may be added.
2. A management committee, with representatives from the core team participants,
including the owner.
3. Shared risks and incentives for core team members based on jointly developed goals.
4. Transparent processes and open-book financials.
5. An emphasis on collaborative decision-making.
6. Approaches to reduce litigation such as waivers or dispute resolution ladders.
7. Significant collaboration by the builder(s) in design.
8. Lean construction principles.
9. The use of collaboration software such a BIM and PMIS.
10. Co-location of project teams and open communication.
The first workshop should focus on identifying the project’s high performance goals and
evaluating the site analysis information and findings to incorporate into potential design
strategies. This should include reviewing the viability of green building rating systems and
their prerequisites including identifying any opportunities or challenges in meeting these
requirements.
The Commissioning Plan outlines the organization, schedule, allocation of resources, and
documentation requirements of the commissioning process, which is a quality focused
process for enhancing the delivery of a project. The process focuses upon verifying and
documenting that the facility and all of its systems and assemblies are planned, designed,
installed, tested, operated, and maintained to meet the owner’s project requirements.
The Commissioning Plan establishes the framework for managing and handling
commissioning. A preliminary Commissioning Plan is essential to all commissioned projects.
It provides the structure for all project participants to anticipate and plan for commissioning
requirements and milestones. The plan is developed during the pre-design phase and is
updated at or near design completion. During the pre-design phase, the Commissioning Plan
focuses on incorporating the owner's performance requirements and integrating them into
the construction documents. Details of systems tests and procedures, assembly specific
checklists, and testing and documentation responsibilities are incorporated in Construction
All project stakeholders should participate in this process and become familiar with the
program. With each subsequent phase, it is the duty of the CxA to verify that the program is
being met or document how the program/scope has changed through change management
procedures, which require sign-off from all stakeholders. For a project to be LEED certified,
commissioning process activities must comply with the prerequisite requirements for
fundamental building commissioning requirements. xxiii
• Sustainability review;
• Configuration or change management;
• Commissioning requirements in all phases;
• C&D waste management requirements
The same features can minimize rework and construction errors. BIM’s data entry into one
model helps manage inconsistency and error due to manual and multiple input. Once
entered or altered, data becomes available in the single current model to all project
participants. BIM can be used to “rehearse” construction processes, including project
sustainability features, and help identify conflicts and their resolution before actual
construction dollars are spent. BIM can also assist in the generation of the data needed to
document project sustainability certification(s).
A decision as to the extent and process of BIM use is critical as soon as possible is the
project so that procedures for BIM use may be communicated to all parties and incorporated
in contractual documents.
The goal of design phase is to turn the owner’s desires and the design team’s proposed
solutions into a detailed set of specifications and drawings. The outcome of the design phase
is a set of documents that describes the project in terms of all requisite parameters, which
can be issued for construction or for bid to a third-party contracting community.
Sustainability goals and objectives are thoroughly subsumed in the design process and
specified as any other program requirement by way of drawings, details, instructions to the
contractor, specifications, and references.
As design proceeds from schematic to final, the team must repeatedly consider lifecycle cost
vs. benefit with respect to the desired or mandated sustainability goals or requirements. The
earlier in the design process that a decision regarding the acceptable first costs of
sustainability features can be made, the more cost effective the design process will be. First
costs of sustainability and lifecycle benefits are optimized through periodic trade-off analysis,
lifecycle and sustainability reviews, value engineering, and alternatives analysis and energy
performance modeling.
Few controls exist for carbon dioxide (CO2), the major greenhouse gas, which has no short-
term damaging effects at ground level. Atmospheric accumulations of CO2 and other GHGs
will have significant effects on global climates and climate cycles, with great uncertainty as to
impact, probable scale, onset, and attenuation.
The availability of these practices and benchmarking systems is ever increasing in number
and depth. Where one might quickly consider LEED or Green Globes, the CM should not
neglect to stay current on other sustainable practices. Not every project is a building project.
Some of these rating systems require registration early in the design process by the party
designated as the project administrator. This could be the CM, A/E, GBF, or CxA.
Responsibility for these tasks should be identified in contract documents and project
management plans. Most rating systems allow project teams to submit design phase
• Conceptual;
• Schematic;
• Design development;
• Construction documents; and
• Support during construction.
The project team should take specific care to review the status of sustainability goals,
objectives, and requirements along with all other project parameters (cost, schedule, quality).
Those parties not directly involved in design development but having a potential significant
contribution to project sustainability goals should be made aware of all progress on the
project and requested to furnish their input. This is especially important as the project nears
the 90% completion of the design phase and bid phase. Any input from the CxA, O&M
forces, facility users, and others may need to be coordinated by the design team prior to the
issuance of bid documents. In some situations, the CM and, possibly the owner, may request
that certain associated parties to the contract sign-off on progress documents and the final
submission of the design to limit any chance that full coordination has not been
accomplished. Involvement of the party designated as the GBF is essential.
The CM should include sustainability in the detailed checklists that confirm or verify the
achievement of design goals in plans, specifications, and estimates at each stage of design
completion.
The cost of the project must be carefully tracked and monitored for every change. When
sustainability is an explicit element of the project, the CM should first assure that appropriate
requirements are included in the design documents, and subsequently, that impacts of
changes on sustainable project features are duly identified and mitigated. Vigilance is
particularly critical to identify the impact of a change on a project’s LEED credit profile,
Green Globes score, or the integrity of any other sustainable design rating system.
When sustainability objectives are jeopardized by a change in scope or design criteria, the
design team must be alerted and allowed sufficient time to mitigate or adjust in response to
the owner’s priorities for the project. All design criteria changes and their impacts must be
communicated to the project team.
Standard formatting from the Construction Specifications Institute (CSI) is used throughout
the construction industry to format construction specifications in building contracts. The
format facilitates location of specific types of information. CSI’s MasterFormat2014 is
organized into 50 divisions, each of which contains a number of sections. Sections are
divided into three parts general, products, and execution. Each part is organized by a
standardized system of articles and paragraphs. Green building specifications can be easily
incorporated into CSI MasterFormat2014 by:
5.4.6 Permits
The CM should assure that a list of project required permits for the project is developed.
The list must include applicable federal, state and local permits and indicate the responsibility
for obtaining the permits. The list should include a submittal schedule for LEED, Green
Globes or another sustainable design or rating system, where applicable.
The CM should periodically determine if relevant and appropriate criteria are well defined in
the construction documents. When the project is expected to meet specific sustainability
thresholds or rating levels, the CM should also verify that the construction documents
accurately identify the certification and necessary documentation, and indicate the party or
parties responsible for associated activities. The A/E contract should specify periodic
MCA and similar complex alternatives analyses may require facilitation by an experienced
consultant. This need should be identified early and anticipated by the budget and design
process.
Like alternative analysis for sustainability projects, LCA may require an experienced
facilitator, who must be identified early in order to anticipate budget requirements and retain
a reliable service provider capable of providing input in a timely fashion. xxiv
The US Department of Energy offers a number of programs free of charge and there are
several software programs available for a fee.
Responsibility for energy modeling and simulation should be assigned to the A/E. Energy
analyses should be conducted by the A/E team frequently enough to validate the design
solution.
Responsibility for realizing energy performance results differs depending on the contracting
strategy and must be addressed in the projects contractual instruments.
Risk management seeks to minimize uncertainty regarding future events. Risk assessment is a
tool to predict the likelihood of future events and the effects of these future events. Risk
mitigation manages risk proactively based on the outcome of the risk assessment. In using
risk assessment and mitigation techniques, the project team should take care to assure
sustainability features and goals are protected and conserved as critical project elements to
be protected and conserved throughout the design and construction process.
The risk of VE to sustainability arises when there are real or perceived additional costs
associated with sustainability features that are not clearly identified as functional
requirements. Clearly articulated energy efficiency goals are effective insurance against VE
exercises that eliminate sustainability features.
Not all sustainable concepts yield the best results at the lowest costs. This is very evident in
the USGBC LEED process where the capturing of many points adds none or very little cost
to the project while others will generate a major premium cost to secure. Trade-off studies
are a traditional part of value engineering and time must be allotted in the schedule to study
the sustainable approach in terms of good value of costs and effectiveness while meeting
5.7 Commissioning
During design, the owner’s project sustainability requirements are translated into
construction documents. Design phase commissioning objectives include verifying that the
owner’s sustainability requirements are captured in the design documents that articulate the
design intent and scope. This should assure that that design processes are leveraged to
include commissioning requirements in construction documents, identifying training and
acceptance requirements, and the performance of a commissioning-focused design review.
The design phase application is normally submitted by the party designated as the agent for
the project. This could be the CM, A/E, the GBF, or CxA. Responsibility for these tasks
should be identified in contract documents and project management plans.
Upon receipt of the preliminary review document from the certifying agency noting the
status of credits achieved, anticipated, pending, and/or denied, the project team will have a
limited period of time to provide corrections and additional supporting documents as a
supplementary submittal for the application for credits.
The goal of the procurement phase is to conduct the procurement process in a manner that
will comply with sustainability goals, objectives, and requirements, and secure service
providers and suppliers capable of satisfying the contract documents, and result in the
successful and timely award of contracts for construction.
Sustainability in the procurement phase will have limited effect on the schedule, though an
added layer of complexity in the contract documents may result in a larger number of bid
questions, which may lead to larger or additional addenda. The design and CM team
experiences in resolving bid issues related to sustainable work scopes should be factored in
bidding, bid evaluation, and award durations.
The procurement planning phase should also take into account the project delivery method
chosen, which may be as follows:
• Design-Bid-Build allows the owner and CM to consider not only the initial cost
of the project during the design phase, but it also provides the opportunity to analyze
the impact of return on investment of the energy efficiency or sustainable building
The CM should participate in all pre-bid meetings, site visits, and addenda preparation to
clarify features of the project that are associated with sustainability goals, objectives, and
requirements.
The goal of the construction phase is to complete construction in accordance with the
requirements of the contract documents, applicable codes and regulations, and the
sustainability goals, objectives, and requirements embedded in the contract documents.
If the contractor is required to provide inspection and testing services, the contractor should
include a list of testing consultants (with appropriate level of experience working on projects
involving sustainability) in the QC program, along with credentials and certifications for
each.
12 For more details on the 5 goals, see ASTM Greener Cleanup Guide E2893-13
• Review roles and responsibilities during the construction phase of each project team
member (A/E, CM, contractor, owner, and others if applicable) should be
designated as responsible to meet sustainability certification/green cleanup effort and
compliance.
• Identify documentation submittal requirements such as:
o Contractor Sustainability Plans;
o Material and equipment submittal requirements for sustainablilty;
documentation;
o MOntly or other reporting requirements;
o Waste manifest detail;
o Local suppliers detail; and
o Recycled material detail.
• Identify required sustainable practices on site, such as:
o Deconstruction vs. demolition;
o Waste Management Plan;
o Material reuse;
o No idling;
o Noise mitigation;
o Minimal waste;
o No smoking; and
The CM must be aware of various elements in the project requiring special operations
control including sustainability elements particularly if the project seeking sustainability
certifications or green cleanup standards. These elements may be related to heavy
construction field activities as well as those associated with manufacturing facilities,
treatment plants, operations control centers, and other facilities dealing with instrumentation
and control systems or other systems as required by the contract. To provide for an
acceptable level of quality in the project for these facilities, the CM should review the
specification requirements for the work with the contractor to confirm that the contractor
and its suppliers are focused on quality and the specific requirements as noted by the
contract. Attention should be paid to the impact on the environment and any sustainable
requirements. They should recognize the need to install these elements in the completed
project in a manner that allows them to be utilized for their intended purpose.
The schedule submitted by the contractor should include activities related to sustainability
and should anticipate additional material lead time requirements or extended construction
durations. For example, adaptive reuse of building and components and reusing existing
materials will add a level of complexity to construction. Securing products from a regional
source may place limitations on material sourcing that can impact the schedule as certain
sustainable products may prove to have a longer lead period for acquisition and longer
installation periods than more familiar products.
While equipment start-up is technically part of commissioning, it can often occur well before
project completion and must be coordinated with the design engineering and commissioning
team. Enhanced commissioning and other quality focused programs may also call for other
interim inspections, testing, and documentation submittals that must be coordinated with the
construction schedule.
If one of the goals of the project was to achieve a certain level of 3rd party verification
sustainability, the schedule should include an activity with a duration reflecting the time
needed between final assembly of documentation and receipt of the decision from the
certifying entity. This could take several months or even a year. The owner should be made
aware of this timeframe in order to align expectations with reality. Active management of the
effort is the key to minimizing its duration.
The contract documents set forth specific requirements to document and obtain approval by
the owner of any changes in the work. The contractor’s QA/QC program should outline
procedures that staff must follow when changes occur. The CM is routinely charged with the
responsibility to evaluate any changes, deletions, or additions to the work under the contract
as to its effect on construction time, cost, quality, and sustainability.
When the contractor performs work without using the current applicable design, the
contractor is at risk for the work not being accepted. The CM should review or audit the
contract document control section of the contractor’s QA/QC manual to determine if the
program is in conformance. The audit should include a check of document holders at the
construction site to determine that they have, and are using the latest drawings,
specifications, and other appropriate information.
Documentation requirements for 3rd party verification may likewise be strict, which makes
proper documentation control and distribution important. The parties responsible for
sustainability certification, along with key designated team members, must receive all current
documents in a timely manner. Document control and distribution procedures should
include requirements regarding distribution to the firm responsible for the 3rd party
sustainability certification.
The CM must verify that the contractor’s QC program adequately addresses the requirement
to ensure that the products submitted and approved are the products utilized on site.
Attention to detail is paramount as products viewed as least critical are most important when
volatile organic compounds (VOC) limits are concerned. Such products include but are not
limited to PVC glues, construction adhesives, primers/sealers, glues for finish installation,
and paints/coatings.
The CM should review the contract documents for indications that appropriate test and
measurement devices are identified, properly calibrated, and properly used. The CM should
also review contractor procedures by auditing to observe that the program is satisfactorily
implemented.
The CM should ask the commissioning agent, consultants, and contractors responsible for
testing and monitoring to verify calibration of controlled testing instruments per the
established schedule for the item.
Payments for sustainable equipment and installations may be tied to the contractor providing
the proper sustainable documentation for that equipment and installation, to ensure that the
documentation is kept current.
When the contractor has specific obligations to meet sustainability goals, a schedule of
values must identify the value and sufficient funds must be withheld until the sustainability
goal is achieved.
The CM should not recommend beneficial occupancy to the owner until the project
punchlist is prepared by the project team, accepted by the CM and owner, and all areas are
available for use. If the project is to be certified under any sustainability program, all open
review comments related to sustainability features should be included.
This may be particularly difficult for a CM-at-Risk that may be under pressure to secure a
substantial completion certificate in order to facilitate occupancy in accordance with
contractual deadlines. The CM and owner should be mindful that punchlist activities
following owner occupancy often result in disputes requiring differentiation of punchlist
work from damage or changed conditions due to the owner’s use of the property.
7.4.14 Training
Within a reasonable period of training, project maintenance trainees should be provided with
pertinent information required to operate and maintain the facility per the owner’s
requirements, and maximize the project’s sustainability features.
Providing the project management staff with digital records of the training sessions can
significantly increase the value of the training by providing staff with a reference for future
post-project training of new personnel, as well as for future reference for procedures that
may not be used frequently.
Typically, all punchlist work must be completed to the satisfaction of the owner, A/E, CM,
and CxA prior to final acceptance (and associated payment). A project with sustainable
certification requirements may have a few activities that must be completed many months
past the completion of typical punchlist work, such as off-season commissioning or receipt
of notification of the final certification. This can be addressed contractually by creating items
in the schedule of values associated with late-breaking requirements.
The post-construction phase provides the opportunity to evaluate the results of the
sustainability efforts, adjust assumptions and systems operation to improve the accuracy of
modeling, and improve efficiency of systems operations. Strategies may include a 3rd party
review, evaluation of systems performance through measurement and verification, gathering
of lessons learned from building operators, and a post occupancy evaluation based on
occupant experience.
The extent of the CM’s post-construction phase responsibilities will vary based on owner
goals established early in the project. Third party review, lessons learned, measurement and
verification, and commissioning, may be part of the project, even if longer term assessments
are not.
8.2 Commissioning
Commissioning of a new construction project begins before the post-construction phase. It
may entail reviews during the design phase and will include pre-functional review during
construction. Exact requirements for the relationship between commissioning and
substantial completion may vary, however the functional testing part of commissioning is
8.2.1Re-Commissioning or Ongoing/Recurring
Commissioning
The performance of dynamic systems and equipment, as well as static systems, assemblies,
and components will tend to degrade from an as-installed condition over time. In addition,
the needs and demands of facility users and processes typically change during the course of a
facility’s use. Maintaining the sustainability features of a project may require periodic
evaluation and adjustment. Re-commissioning processes have the main objectives of
assuring that an owner’s project requirements reflect changes in use and operation of the
facility:
8.2.2 Retro-Commissioning
Retro-commissioning is when an owner adopts commissioning on a project during the
operation stage of the facility lifecycle. While it accomplishes commissioning process
activities, it is sufficiently different from the commissioning process that it is considered a
separate process.
Improvements in major energy consuming features such as HVAC systems, lighting, and
communications are happening at increasing speeds. “State of the art” five years ago may
now be obsolete. Retro-commissioning of a five or 10-year-old building, along with updating
of equipment or components may result in a substantial reduction in energy use. This may
incentivize an owner to revisit commissioning frequently. xxv
8.3Asset/Facilities Management—Lifecycle
Monitoring
Technology is progressing at an incredible rate. Five-year-old fluorescent light tubes and
fixtures may be energy wasters compared to current technologies. Such developments may
dramatically alter a lifecycle analysis after a few years. Monitoring efficiency improvements
of building components can be a worthwhile method to increase savings for older facilities.
8.3.1 Training
Training the owner’s operation and maintenance staff ideally occurs during construction.
Some training is best deferred until the owner has assumed responsibility for the building
and its sustainability features. Such training should be identified in the Commissioning Plan,
and the CxA may be responsible for vetting the training plan and implementation. Training
should clearly define maintenance required for continued function of sustainability features.
Such requirements should be reflected in the Operation and Maintenance Manual (by
contractor) and Systems Manual (by CxA). Some contracts call for recording the training
process to ensure the material is available for future reference.
For equipment and building components that are critical to the operation of the building,
designated contacts should be reachable. Many building management systems are monitored
by an external, independent third party; these firms should also be provided with the names
and contact information of the various contractors whose work is under their monitoring
efforts.
The owner should provide a similar point of contact, available 24 hours/day, to enable a
contractor to enter the facility to rapidly correct or mitigate a problem and avert potential
environmental damage and minimize waste.
8.5 Deconstruction
At the end of the building’s useful life, the owner should identify potential re-use for the
building components. This could include structural components, furniture, and recyclable
materials. Through thoughtful deconstruction, the owner can minimize the building’s
contribution to landfill waste and continue to contribute to sustainable construction projects.
Acceptance Testing
When a full commissioning program is not justified, specific pieces of equipment or systems
can be subject to “acceptance testing” for purposes of owner acceptance. Acceptance testing
requirements are clearly identified in contract documents. Training owner personnel in
operation and maintenance is typically part of the acceptance test.
Adaptive Capacity
The capacity of a system to adapt if the environment where the system exists is changing.
ASHRAE
American Society of Heating, Refrigerating, and Air-Conditioning Engineers, founded in
1894. ASHRAE’s mission is to advance “heating, ventilation, air conditioning and
refrigeration to serve humanity and promote a sustainable world through research, standards
writing, publishing and continuing education.” ASHRAE offers definitive guidance on
energy load calculations, equipment performance, commissioning and many other topics
central to design, engineering and construction of sustainable facilities. www.ashrae.org xxvi
BREEAM
Building Research Establishment Environmental Assessment Methodology is the world's
foremost environmental assessment method and rating system for buildings, with 425,000
buildings with certified BREEAM assessment ratings and two million registered for
assessment since it was first launched in 1990.
BREEAM sets the standard for best practice in sustainable building design, construction,
and operation and has become one of the most comprehensive and widely recognized
measures of a building's environmental performance. It encourages designers, clients, and
others to think about low carbon and low impact design, minimizing the energy demands
created by a building before considering energy efficiency and low carbon technologies.
A BREEAM assessment uses recognized measures of performance, which are set against
established benchmarks, to evaluate a building’s specification, design, construction, and use.
The measures used represent a broad range of categories and criteria from energy to ecology.
They include aspects related to energy and water use, the internal environment (health and
well-being), pollution, transport, materials, waste, ecology, and management processes.
Carbon Footprint
The overall volume, over a specified period, of greenhouse gas (GHG) emissions caused by
an organization, event or product.
Commissioning
ASHRAE defines commissioning as “a quality-oriented process for achieving, verifying, and
documenting that the performance of facilities, systems, and assemblies meets defined
objectives and criteria.” According to the National Institute of Building Sciences,
commissioning is “an all-inclusive process for the planning, delivery, verification, and
managing risks to critical functions performed in, or by, facilities.” Commissioning is
intended to improve building quality via peer review and in-field or on-site verification and
heighten energy efficiency, environmental performance and occupant safety. Commissioning
can improve indoor air quality by making sure building components work correctly. It
provides a system for documenting project implementation as a function of design intent. xxviii
Credentials for commissioning professionals are offered by ASHRAE and the Building
Commissioning Association. ASHRAE: www.ashrae.org
Contingency
Contingency is an amount of money reserved by a party for unforeseen changes in the work
or increases in cost.
Deconstruction (building)
Selective dismantling of building components specifically for C&D waste management
strategies such as re-use and recycling. Deconstruction differs from demolition, which values
the expedient clearing of a building from its site.
ENERGY STAR
A joint program of the US Environmental Protection Agency (EPA) and the US
Department of Energy introduced in 1992 by the EPA as a voluntary labeling program
designed to identify and promote energy-efficient products to reduce greenhouse gas
emissions. EPA recently extended the ENERGY STAR label to cover new homes and
commercial and industrial buildings. xxx ENERGY STAR Program: www.energystar.gov
Estidama
A building design methodology for constructing and operating buildings and communities
more sustainably. The program is a key aspect of the "Abu Dhabi Vision 2030" drive to
build the Abu Dhabi emirate according to innovative green standards. "Estidama" is the
Arabic word for sustainability. The program is not itself a green building rating system like
LEED or BREEAM, but rather a collection of ideals that are imposed in an elective building
code type of format.
Within Estidama is a green building rating system called the Pearl Rating System that is
utilized to evaluate sustainable building development practices in Abu Dhabi.
The system can be applied to communities, buildings, and villas, with different requirements
for each. http://estidama.upc.gov.ae
Green Globes
The Green Building Initiative (GBI) Green Globes is a development and management tool
that includes an assessment protocol, a rating system, and guide for integrating
environmentally friendly design into both new and existing commercial buildings.
GBI: www.greenglobes.com
Greywater System
Greywater is wash water: bath, dish, and laundry water excluding toilet wastes and garbage.
A greywater system is designed to assure isolation of greywater collection and treatment
from blackwater (sewage), which contains higher concentrations of nitrogen and bacteria.
ISO 14000
The International Organization for Standardization (ISO) is a non-governmental
organization and the world's largest developer and publisher of voluntary International
Standards. ISO is a network of the national standards institutes of 159 countries, one
member per country, with a Central Secretariat in Geneva, Switzerland, that coordinates the
system. The US is represented by the American National Standards Institute (ANSI). The
ISO 14000 family of standards provides practical tools for companies and organizations of
all kinds to manage their environmental responsibilities. The very first two standards, ISO
14001:2015 and ISO 14004:2004 deal with environmental management systems (EMS). ISO
14001:2015 provides the requirements for an EMS and ISO 14004:2004 gives general EMS
guidelines. Other ISO 14000 standards and guidelines address issues including labeling,
performance evaluation, lifecycle analysis, communication and auditing. xxxii International
Organization for Standardization: www.iso.org
LEED AP
LEED Accredited Professional, the professional credential awarded to an individual that has
demonstrated a thorough understanding of the LEED green building rating system by
successfully passing the LEED AP examination. The LEED professional credential program
is administered by the Green Building Certification Institute, an independent organization
that provides third-party certification. xxxiii Green Building Certification Institute: www.usgbc.org
Lifecycle
The consecutive, interlinked stages of a product’s production and use, beginning with raw
materials acquisition and manufacture and continuing with its fabrication, manufacture,
construction, use, and depletion, concluding with any of a variety of recovery, recycling, or
waste management options.
Lifecycle Cost
All costs incident to the planning, design, construction, operation, maintenance, and
demolition of a facility, or system, for a given life expectancy, all in terms of present
value. xxxiv
Net Zero
Net zero energy building refers to a facility with zero net energy consumption and zero
carbon emissions annually.
Similar to LEED, the Pearl Rating System has various levels of certification, ranging from
one to five pearls. For all new development projects within the emirate of Abu Dhabi, a
minimum certification of one pearl is required (two pearls for government buildings). This
certification requirement was mandated by the Executive Council of Abu Dhabi and went
into effect Autumn 2010.
There are three stages of certification associated with the Pearl Rating System. The first stage
is the Pearl Design Rating, success of which is tied to the building permit. The second stage
is the Pearl Construction Rating, success of which is tied to the certificate of completion.
The third, and yet to be developed stage, is the Pearl Operations Rating.
Training seminars of various lengths and technical depths are available for all of the Pearl
Rating Systems. Training seminars are currently being delivered by the WSP Group and
Oger International on behalf of the Urban Planning Council, Abu Dhabi.
Individuals interested in working on Pearl Rated projects should become Pearl Qualified
Professionals (PQPs); at least one PQP is required per project planned for development
within the emirate of Abu Dhabi. The PQP test was developed by Prometric and is
administered at the CERT center in Abu Dhabi and the AMIDEAST testing center in
Dubai.
Based on review by Abu Dhabi’s Urban Planning Council (UPC), up to five pearls can be
awarded. One pearl is mandatory for all developments and is based on the building code. As
per Information Bulletins No. 1 dated 6 December 2010 all Abu Dhabi government projects
are required to achieve two pearls. Two pearls include all the mandatory requirements as well
as additional optional credits.
To date the only projects to achieve three pearls include the Abu Dhabi Midfield Terminable
Building and ten unspecified Abu Dhabi Education Council (ADEC) schools.
http://estidama.upc.gov.ae/pearl-rating-system-v10.aspx?lang=en-US
Renewable Energy
Energy generated from renewable resources such as sunlight, wind, rain, tides, and some
geothermal applications, which are naturally and readily replenished, or renewable. xxxv
Resilience
The capability of a system to survive, adapt, and grow in the face of unforeseen changes
(climate variability), and/or even catastrophic incidents. A system that provides the adaptive
capacity to recover quickly and to withstand major disruptions with acceptable levels of
degradation and recovery within acceptable time frames, costs, and risks.
Retro-commissioning (RCx)
A systematic process that identifies operational and maintenance improvements in existing
buildings with the objective of improving energy performance. RCx typically focuses on
mechanical equipment, lighting and controls and usually optimizes existing system rather
than replacing equipment. RCx typically includes an energy audit, diagnostic monitoring and
functional tests. EPA offers guidance on Retro-commissioning through its ENERGY STAR
program.
Sustainable
The condition of being able to meet the needs of present generations without compromising
resources for future generations.
CDA is the first in the nation to develop sustainable guidelines for design and construction
at airports. The Sustainable Airport Manual was created as an integral part of Chicago’s
Sustainable Development
A pattern of resource use that aims to meet human needs while preserving the environment
so that these needs can be met not only in the present, but also for future generations.
Sustainable development, as a goal, aims to reconcile the carrying capacity of natural systems
with the physical, social and cultural demands of the system’s occupants. As defined by the
Brundtland Commission in 1983, sustainable development is “development which meets the
needs of the present without compromising the ability of future generations to meet their
own needs.”
Sustainable Materials
Sustainable building materials are composed of renewable, rather than nonrenewable
resources. Sustainable materials are environmentally responsible when their impacts are
considered over the life of the product. Use of sustainable building materials can help reduce
the environmental impacts associated with the extraction, transport, processing, fabrication,
installation, reuse, recycling, and disposal of these source materials. xxxviii
Sustainable Remediation
Sustainable Remediation is a term adopted internationally and encompasses sustainable
approaches, as described by the Brundtland Report, to the investigation, assessment, and
“Sustainable Remediation protects human health and the environment while maximizing the environmental,
social, and economic benefits throughout the project lifecycle”
SURF promotes the use of sustainable practices during the investigation, construction,
remediation, redevelopment, and monitoring of environmental cleanup sites, with the
objective of balancing economic viability, conservation of natural resources, biodiversity, and
the enhancement of the quality of life in surrounding communities.
www.sustainableremediation.org
iv ENERGY STAR:
www.energystar.gov/buildings/facility-owners-and-managers/existing-
buildings/use-portfolio-manager/understand-metrics/what-energy
xiii ISO:
www.iso.org/iso/home/standards/management-
standards/iso50001.htm
xxiii ASHRAE:
www.ashrae.org
US GBC LEED:
www.usgbc.org
NIBS National Performance Building Design Guide:
www.npbdg.wbdg.org
ASHRAE Guideline-0-2005, “The Commissioning Process”:
www.ashrae.org/publications/page/1279
xxvi ASHRAE:
www.ashrae.org
xxix ASHRAE:
www.ashrae.org/certification/page/2086
Building Commissioning Association:
www.bcxa.org/
xxxi GBI:
www.thegbi.org
xxxv NIBS:
www.wbdg.org/resources/lcca.php
xxxvii US EPA:
www.epa.gov/greenpower/gpmarket/rec.htm
xxxix US EPA:
www.epa.gov/epp
NIBS:
www.wbdg.org/resources/greenproducts.php
National Institute of Standards and Testing (NIST):
www.bfrl.nist.gov/oae/software/bees
A
C
Acceptance, 80, 89
Acceptance Testing, 79 C&D Waste Management, 59, 90
Advertisement and Solicitation of Bids, 68 Carbon footprint, 90
Air-Side Economizer, 24 Changes in Design Scope or Criteria, 58
Alternative Fuels, 27 Changes in Work, 75
Alternative Studies, 61 CHPS. See Collaborative for High
American Society of Heating, Performance Schools
Refrigerating, and Air-Conditioning CMAA Standards of Practice, 5, 6, 9, 10
Engineers. See ASHRE CM-at-Risk, 46, 80
ASHRAE, 89, 90, 91, 108 Collaborative for High Performance
Asset/Facilities Management, 85 Schools, 11, 56, 90, 108
Commissioning, 6, 7, 8, 41, 44, 45, 50, 51,
B 53, 64, 68, 74, 75, 77, 78, 79, 81, 83, 84,
85, 89, 90, 91, 95
Benchmarking, 22 Commissioning Agent, 8, 44, 74, 77, 91
Beneficial Occupancy, 79 Commissioning Agent Qualifications, 45
Building Automation System, 20 Commissioning Plan, 4, 8, 50, 77, 85, 91
Building Commissioning, 90, 108 Commissioning Plan Schedule, 78
Building Commissioning Association, 45, Concentrated Solar Power, 28
91, 108 Constructability review, 61
Building Commissioning Process, 44 Construction Management and
Building Energy Management System, 20 Administration, 75
Building Envelope, 27 Construction Management Plan, 3, 9, 42,
Building Information Modeling, 14 48, 67, 71, 76
Building Information Modeling (BIM), 41, Construction Phase, 51, 71
52, 53 Construction Planning and Scheduling, 74
Building Management System, 20 Construction Procurement Plan, 4
Contingency, 91
xiv The ENERGY STAR program provides free tools to assist in establishing benchmarks:
www.energystar.gov/buildings/about-us/how-can-we-help-you/benchmark-energy-use/benchmarking
xv US DOE / Evaporative cooling: energy.gov/energysaver/articles/evaporative-coolers
xviii National Institute of Buidling Sciences; Whole Building Design Guide: https://www.wbdg.org/resources/microturbines.php
ASHRAE: www.ashrae.org
US GBC LEED: www.usgbc.org
NIBS National Performance Building Design Guide: www.npbdg.wbdg.org
xxiii ASHRAE Guideline-0-2005, “The Commissioning Process”: www.ashrae.org/publications/page/1279
US EPA: www.epa.gov/nrmrl/lcaccess
xxv ASHRAE Guideline 0-2013: https://www.ashrae.org/standards-research--technology/standards--guidelines/titles-purposes-and-scopes#Gdl0