Professional Documents
Culture Documents
76 Vol II SEC - STR - 04 PDF
76 Vol II SEC - STR - 04 PDF
SECTION: STRUCTURE
SECTION: STRUCTURE
Table of contents
1.0 GENERAL 1
2.0 DESIGN REQUIREMENTS FOR STRUCTURES NOT 2
COVERED IN STANDARDISED LIST
3.0 DESIGN DRAWINGS, BILL OF MATETRIALS AND 4
DOCUMENTS
4.0 FABRICATION OF STEEL MEMBERS 5
5.0 PROTO-ASSEMBLY 5
6.0 BOLTING 6
7.0 WELDING 6
8.0 FOUNDATION BOLTS 6
9.0 STABILITY OF STRUCTURE 7
10.0 GROUTING 7
11.0 GALVANISING 7
12.0 TOUCH-UP PAINTING 7
13.0 INSPECTION BEFORE DISPATCH 7
14.0 TEST CERTIFICATE 8
15.0 ERECTION 8
16.0 MODE OF MEASUREMENT 8
17.0 SAFETY PRECAUTIONS 8
1.0 GENERAL
1.1 The scope of specification covers fabrication, proto-assembly, supply and erection of
galvanised steel structures for towers, girders, lightning masts and equipment support
structures. Towers, girders and lightning masts shall be lattice type structure
fabricated from structural steel conforming to IS 2062 (latest). All equipment support
structures shall be fabricated from GI pipe conforming to YST 22 or of higher grade
as per IS 806 except for 132kV and below for which the equipment structure shall be
of Lattice type.
Line diagrams of Towers, girders, Lightning mast, equipment support structures for
standard 400kV/220kVstructures are enclosed with the tender document. The
fabrication drawings alongwith BOM shall be provided to the successful bidder after
the award. Contractor shall only use these standard drawings for fabrication. Support
structure for circuit breaker is not standardized and shall be designed by the
Contractor and approved by the owner. Any other structures of 400kV/220kV class
necessary to suit the layout for a particular substation to complete the work in all its
requirements shall be designed by the owner at detailed Engineering stage. Design
& drawing of structure other than 400kV/220kV class shall also be prepared by the
owner at detailed engineering stage.
The scope shall include supply and erection of all types of structures including bolts,
nuts, washers, hangers, shackles, clamps anticlimbing devices, bird guards, step bolts,
inserts in concrete, gusset plates, equipment mounting bolts, structure earthing bolts,
foundation bolts, spring washers, fixing plates, ground mounted marshalling boxes
(AC/DC Marshalling box & equipment control cabinets), structure mounted
marshalling boxes and any other items as required to complete the job.
The connection of all structures to their foundations shall be by base plates and
embedded anchor/foundation bolts. All steel structures and anchor/foundation bolts
2.1 For design of steel structures loads such as dead loads, live loads, wind
loads etc. shall be based on IS:875,Parts I to V.
Other members 4
Redundant members 4
2.4 Maximum slenderness ratios for leg members, other stressed members
and redundant members for compression force shall be as per IS-802.
2.5 Minimum distance from hole center to edge shall be 1.5 x bolt diameter.
Minimum distance between center to center of holes shall be 2.5 x bolt
diameter.
2.6 All bolts shall be M16 or higher as per design requirement.
2.7 Step Bolts
h) Foundation bolts shall be designed for the loads for which the
structures are designed.
3.1.2 Contractor shall however not be relieved of his responsibility for the
safety of the structure and good connections and any loss or damage
occurring due to defective fabrication, erection or workmanship shall be
borne by the Contractor.
3.2.1 The Contractor shall furnish design, drawing and BOMs and shop
manufacturing drawings for every member to the owner after award of the
Contract. The design drawing should indicate not only profile, but
section, numbers and sizes of bolts and details of typical joints. In case
owner feels that any design drawing, BOM are to be modified even after
its approval, Contractor shall modify the designs & drawings and resubmit
3.2.3 Such approval shall, however, not relieve the Contractor of his
responsibility for the safety of the structure and good connections and any
loss or damage occurring due to defective fabrication, design or
workmanship shall be borne by the Contractor.
3.3 The Mass fabrication work shall start only after the final approval to the
proto corrected Fabrication drawing is accorded by the owner. Proto-
assembly shall be required to be carried out only for those structures that
have not been proto-assembled by the same fabricators for this contract or
for earlier contracts from POWERGRID. Wherever proto-assembly is not
to be repeated, proto-corrected drawings shall be submitted directly with a
note on the drawing stating that proto-assembly has been carried out under
a particular previous contract.
4.1 The fabrication and erection works shall be carried out generally in
accordance with IS 802. A reference however may be made to IS 800 in
case of non-stipulation of some particular provision in IS 802. All
materials shall be completely shop fabricated and finished with proper
connection material and erection marks for ready assembly in the field.
5.0 PROTO-ASSEMBLY
6.0 BOLTING
i) Every bolt shall be provided with a washer under the nut so that no
part of the threaded portion of the bolt is within the thickness of
the parts bolted together.
ii) All steel items, bolts, nuts and washers shall be hot dip galvanised.
iii) 2.0% extra nuts and bolts shall be supplied for erection.
7.0 WELDING
The work shall be done as per approved fabrication drawings which shall
clearly indicate various details of joints to be welded, type of weld, length
and size of weld, whether shop or site weld etc. Symbols for welding on
erection and shop drawings shall be according to IS:813. Efforts shall be
made to reduce site welding so as to avoid improper joints due to
constructional difficulties.
8.1 Foundation bolts for the towers and equipment supporting structures and
elsewhere shall be embedded in first stage concrete while the foundation
is cast. The Contractor shall ensure the proper alignment of these bolts to
match the holes in the base plate.
8.2 The Contractor shall be responsible for the correct alignment and leveling
of all steel work on site to ensure that the towers/structures are plumb.
8.3 All foundation bolts for lattice structure, pipe structure are to be supplied
by the Contractor.
8.4 All foundation bolts shall be fully galvanised so as to achieve 0.61 kg. per
Sq.m. of Zinc Coating as per specifications.
8.5 All foundation bolts shall conform to IS 5624 but the material, however
The Supplier shall be responsible for the stability of the structure at all
stages of its erection at site and shall take all necessary measures by the
additions of temporary bracings and guying to ensure adequate resistance
to wind and also to loads due to erection equipment and their operations.
10.0 GROUTING
11.0 GALVANISING
11.1 All structural steel works and pipe supports shall be galvanised after
fabrication.
The touch up primers and paints shall consist of Red Oxide / Zinc
chromate conforming to the requirements of IS:2074 with a pigment to be
specified by the owner.
Each part of the fabricated steel work shall be inspected as per approved
quality plans and certified by the owner or his authorised representative as
satisfactory before it is dispatched to the erection site. Such certification
shall not relieve the Contractor of his responsibility regarding adequacy
and completeness of fabrication.
15.0 ERECTION
The Contractor should arrange on his own all plant and equipment,
welding set, tools and tackles, scaffolding, trestles equipments and all
other accessories and ancillaries required for carrying out erection without
causing any stresses in the members which may cause deformation and
permanent damage.
The measurement of the standard lattice and pipe structures for towers,
beams, equipment support structure etc. shall be made in numbers for each
type of structures. This will include foundation bolts and nuts and
therefore no separate payment shall be made for the same. The unit rate
quoted for each type of structure shall be inclusive of supply, fabrication,
galvanizing, erection, nuts, bolts, wastages etc. complete. Nothing extra
shall be payable for substitution necessitated due to non-availability of
sections indicated in the standard drawing. Nothing extra shall be payable
for modifications or steel added to suit the contractors fixing arrangements
for accessories etc.
18.0 All tests mentioned in standard field quality plans have to be carried out
and conformity of materials and workmanship shall be ascertained.