Tugas 2

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

TUGAS 1

FONDASI DALAM

Disusun oleh :
NAMA : JIHAN SAPUTRA
NPM : G1B017039

TEKNIK SIPIL
UNIVERSITAS BENGKULU
2020
A. PENYELIDIKAN TANAH
Jenis tanah ditentukan dari data CPT yang dikoverensikan ke data N-SPT.
Tahap perencanaan Pondasi Dalam :
1. Nilai korelasi data CPT ke N-SPT
Qc = 4N
Maka,
N = qc/4

2. N terkoreksi

3. Nilai N60

KAPASITAS DAYA DUKUNG TIANG BOR


 Untuk tiang bor menahan beban tekan:

Dimana :
Qs = As.Fs
a. Tanah Lempung
Fs =α.Cu

b. Tanah Pasir
Fs = μN

Berat sendiri tiang:


Wp = As x BJ x L

 Daya dukung izin :

 Kapasitas ujung :

Dimana nilai qe :
Tabel jenis perlapisan tanah
qc N rata
Depth jenis N-SPT N Koreksi Cu α σ
(kg/cm2) rata

0,0 0,0 Silty clay to clay 0 7,50


0,4 5 Silty clay to clay 1,25 8,13
6 8,23 5 0,7 25,3
0,8 Silty clay to clay 1,5 8,25
1,2 8 Silty clay to clay 2 8,50
1,6 10 Silty clay to clay 2,5 8,75
2 14 Clayey silt to silty clay 3,5 9,25
2,4 14 Clayey silt to silty clay 3,5 9,25 9,42 6 0,7 38,7
2,8 18 Clayey silt to silty clay 4,5 9,75
3,2 23 Silty Sand/Sandy Silt 5,75 10,38
3,6 36 Silty Sand/Sandy Silt 9 12,00
4 32 Silty Sand/Sandy Silt 8 11,50
4,4 31 Silty Sand/Sandy Silt 7,75 11,38
4,8 40 Silty Sand/Sandy Silt 10 12,50
5,2 45 Silty Sand/Sandy Silt 11,25 13,13 12,81 8 0,6 110,5
5,6 49 Silty Sand/Sandy Silt 12,25 13,63
6 52 Silty Sand/Sandy Silt 13 14,00
6,4 59 Silty Sand/Sandy Silt 14,75 14,88
6,8 52 Silty Sand/Sandy Silt 13 14,00
7,2 48 Silty Sand/Sandy Silt 12 13,50
7,6 70 clean sand to silty sand 17,5 16,25
26,57 17 0,4 297,2
8 80 clean sand to silty sand 20 17,50
8,4 90 clean sand to silty sand 22,5 18,75
8,8 110 clean sand to silty sand 27,5 21,25
9,2 125 clean sand to silty sand 31,25 23,13
9,6 140 clean sand to silty sand 35 25,00
10 142 clean sand to silty sand 35,5 25,25
10,4 140 clean sand to silty sand 35 25,00
10,8 160 clean sand to silty sand 40 27,50
11,2 172 clean sand to silty sand 43 29,00
11,6 140 clean sand to silty sand 35 25,00
12 120 clean sand to silty sand 30 22,50
12,4 160 clean sand to silty sand 40 27,50
12,8 172 clean sand to silty sand 43 29,00
13,2 140 clean sand to silty sand 35 25,00
13,6 120 clean sand to silty sand 30 22,50
14 142 clean sand to silty sand 35,5 25,25
14,4 160 clean sand to silty sand 40 27,50
14,8 175 clean sand to silty sand 43,75 29,38
15,2 160 clean sand to silty sand 40 27,50
15,6 190 clean sand to silty sand 47,5 31,25
16 190 clean sand to silty sand 47,5 31,25
16,4 230 clean sand to silty sand 57,5 36,25
16,8 240 clean sand to silty sand 60 37,50
17,2 245 clean sand to silty sand 61,25 38,13
Gambar Jenis perlapisan Tanah

B. PERHITUNGAN PONDASI
Pada perhitungan pondasi digunakan :
L = 17,2 m
SF = 2.5
BJ Beton = 24 kN/m3
Tabel Kapasitas Dukung Tiang Bor
Kapasitas Daya Dukung Tiang Bor Tunggal Metode O'Neil dan Reese

Diameter (m)
No Jenis Parameter
Thickness 0,4
Lapisan Tanah
L/d 43
As 2,011

1 lempung 1,60 fs 3,753

Qs 7,545

As 1,005

2 lanau 0,80 fs 4,120

Qs 4,142

As 5,027

3 pasir 4,00 fs 6,403

Qs 32,187

As 12,064

4 pasir 9,60 fs 13,283

Qs 160,236

Ab 0,126
Tahanan 300,000
Pasir   fb
Ujung
Qb 37,699

51,874
Wp
Qult 189,935

Qall 75,974

Tabel distribusi beban


Diameter (m) 0,4
Qall (ton) 75,974
Beban (ton) 300
Jumlah Tiang 4
Distribusi Beban (ton) 303,896
Ket Aman

Jadi penampang paling ekonomis dan efektif adalah tiang bor dengan panjang dan lebar
17,2 x 0,4 m menurut data SPT adalah berjumlah 4 buah. Dengan penampang yang
demikian, maka didapatkan tiang yang dapat menahan beban sebesar 300 kN. Kemudian
dalam menentukan jarak ujung tiang, karena jumlah fondasi sebanyak 4 bore pile maka
digunakan perletakan fondasi yang tersusun seperti yang terlihat pada gambar dibawah ini.

You might also like