Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 19

Weekly report

Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

CCS ACTIVITY DESCRIPTION


ACT NO.
Preparation for external plaster work in the elevations 2 had been done 100%
01
Preparation for external plaster work in the elevations 3 had been done 60%
02
Plaster work in the fourth floor had been done 90%
03
Flooring Tiles work for the fiirst floor had been done 95%
04
Wall Tiles work for the wet area in the first floor had been done 95%
05
Flooring Tiles work for the second floor had been done 95%
06
Wall Tiles work for the wet area in the first floor had been done 95%
07
Wall Tiles work for the wet area in the second floor had been done 95%
08
Wall Tiles work for the wet area in the third floor had been done 70%
09
Spray plaster in the third floor had been done 100%
10
Paint work for walls in the third floor had been done 80%
11
Paint work for celing in the third floor had been done 80%
12
Water proofing for wet area in the first floor had been done 100%
13
Fales celing works in the first floor had been done 70 %
14
Kitchen cabinet works had been done in the first floor 10%
15
Concrete Demolation for substation had been done 80%
16

GI Box installation and piping in the gym floor had been done 100%
18
Electrical wire pulling in the third floor had been done 100%
19
Electrical wire pulling in the fourth floor had been done 50%
17
DB Dressing in the first floor had been done 25%
18
Drainage H/L installation in the third floor had been done 100%
19
Pex piping in the gym floor had been done 100%
20

This report must be submitted no later than 9:00 a.m. Sheet 1 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

PPR installation in the third floor had been done 100%


21
Fire fighting H/L installation in the third floor had been done 50%
22
Fire pump room works in second basement had been done 15%
23
Duct installation in the third floor had been done 50%
24
Structured cabling in the third floor had been done 100%
25

This report must be submitted no later than 9:00 a.m. Sheet 2 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 3 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 4 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 5 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 6 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 7 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 8 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 9 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 10 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 11 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 12 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 13 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 14 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 15 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 16 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 17 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 18 of 19


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 24


Date 08 Mar 19 - 14 Mar 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 19 of 19

You might also like