08 Mar - 14 Mar 2019
08 Mar - 14 Mar 2019
GI Box installation and piping in the gym floor had been done 100%
18
Electrical wire pulling in the third floor had been done 100%
19
Electrical wire pulling in the fourth floor had been done 50%
17
DB Dressing in the first floor had been done 25%
18
Drainage H/L installation in the third floor had been done 100%
19
Pex piping in the gym floor had been done 100%
20