Weekly Report: Project: 2B + G + 4floors + Gym

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 16

Weekly report

Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

CCS ACTIVITY DESCRIPTION


ACT NO.
Scaffolding for 1 th elevation had been done 100%
01
Steel & form work for Attic slab for LV room had been done 100%
02
Preparation for external plaster for elevation no 1 had been done 60%
03
Block work for boundary wall had been done 60 %
04
Flooring Tiles work for the fourth floor had been done 100%
05
Flooring Tiles work for the gym floor had been done 100%
06
Flooring Tiles work for wet area in the fourth floor had been done 100%
07
Paint work for walls in the gym floor had been done 90%
08
Paint work for ceiling in the gym floor had been done 90%
09
external paint work for elevation 2 had been done 95 %
10
external paint work for elevation 3 had been done 95 %
11
external paint work for elevation 4 had been done 40 %
12
False ceiling works in the first floor had been done 80 %
13
False ceiling works in the second floor had been done 80 %
14
False ceiling works in the third floor had been done 80 %
15
roof waterproofing had been done 10 %
16
DB Dressing in the fourth floor had been done 100%

DB Dressing in the 1st basement had been done 100%


17
Water heater installation in the gym floor had been done 100%
18
Wire pulling in the ground floor had been done 100%
19
Cable tray installation in the 1st basement had been done 80%
20
MEP services in the substation had been done 100%
21
Water meter room works in the second floor had been done 100%
22

This report must be submitted no later than 9:00 a.m. Sheet 1 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

Sanitary fixtures in the first floor had been done 30%


23
Fire figting pump room works had been done 80%
24
Drainage work in 2nd basement LL had been done 100%
25
FCU (Indoor unit) installation in the gym floor had been done 100%
26
Duct installation in the gym floor had been done 50%
27
CCTV wire pulling in the 1st,2nd,3rd floor had been done 100%
28
Fire alarm devices fixing in third floor had been done 100%
29
Fire alarm device fixing in the fourth floor had been done 100%
30
FACP fixing in the ground floor had been done 100%
31
LPG Riser installation had been done 80%
32

This report must be submitted no later than 9:00 a.m. Sheet 2 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 3 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 4 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 5 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 6 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 7 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 8 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 9 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 10 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 11 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 12 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 13 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 14 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 15 of 16


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 30


Date 18 – 25 Apr 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 16 of 16

You might also like