Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 13

Weekly report

Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

CCS ACTIVITY DESCRIPTION


ACT NO.
block work in the gym floor had been done 95%
01
Preparation for external plaster work in the elevations 1 + 2 had been done 50%
02
Plaster work in the third floor had been done 100%
03
plaster work in the O.T.S had been done 90%
04
Flooring Tiles work for the fiirst floor had been done 80%
05
Wall Tiles work for the corridor in the first floor had been done 95%
06
Wall Tiles work for the wet area in the first floor had been done 90%
07
Flooring Tiles work for the second floor had been done 30%
08
Wall Tiles work for the wet area in the first floor had been done 30%
09
Spray plaster in the second floor had been done 100%
10
Spray plaster in the third floor had been done 70%
12
Primer work in the third floor had been done 40%
13
Paint work for the walls in the O.T.S had been done 70%
14
Water proofing for wet area in the first floor had been done 20 %
15
Scaffolding for elevators work had been done 100%
16
Fales celing works in the first floor had been done 25 %
17
GI box installation and piping in the fourth floor had been one 70%
18
DB installation and piping in the fourth floor had been done 70%
19
Electrical wire pulling in the tgird floor had been done 50%
20
Floor piping in the third floor had been done 50%
21
Pex piping in the fourth floor had been done 100%
23
PPR Installation in the third floor had been done 30%
24
Duct installation in the second floor had been done 80%
25

This report must be submitted no later than 9:00 a.m. Sheet 1 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

Fire fighting riser installation in the first floor had been done
26
Fire fighting H/L piping in the second floor had been done 40%
27
LPG gas piping in the first floor had been done 20% (Mock up)
28
Structured cabling in the first floor had been done 50%
29

This report must be submitted no later than 9:00 a.m. Sheet 2 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 3 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 4 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 5 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 6 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 7 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 8 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 9 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 10 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 11 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 12 of 13


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date 21 FEB-28 FEB 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 13 of 13

You might also like