Weekly Report: Project: 2B + G + 4floors + Gym
Weekly Report: Project: 2B + G + 4floors + Gym
Fire fighting riser installation in the first floor had been done
26
Fire fighting H/L piping in the second floor had been done 40%
27
LPG gas piping in the first floor had been done 20% (Mock up)
28
Structured cabling in the first floor had been done 50%
29