Professional Documents
Culture Documents
TR-CA-MS-002 - B Excavation & Backfilling-Sent To Hiba
TR-CA-MS-002 - B Excavation & Backfilling-Sent To Hiba
TR-CA-MS-002
Rev Date Description DSGN CHKD APPD
A 11-Sep-17 Issued for internal review
CLASSIFICATION
CONTROLLED
UNCONTROLLE
D
Sheet No.
1 of 10
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 1 of 9
TABLE OF CONTENT
1.0 PURPOSE
2.0 OBJECTIVES
3.0 SCOPE
4.0 REFERENCES
6.0 PROCEDURE
8.0 ATTACHMENTS
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 2 of 9
1.0 PURPOSE
The purpose of this method of statement is to describe step by step the activities to be performed for
excavation and backfilling at Qayyarah power plant project. This method of statement is also set the
guidelines and quality control requirements for the construction team at site.
2.0 OBJECTIVES
Objectives are:
- Achieve high quality / and safety level in task performance,
- Enhance customer satisfaction,
- Complete the task in timely manner,
- Direct and control excavation and backfilling activities in a proper way.
3.0 SCOPE
This method of statement describes a proper technique that will be utilized during excavation and
backfilling work as per project specifications and contract drawings.
4.0 REFERENCES
- Project specification
- TR EHS manual
5.0 HEALTH, SAFETY AND ENVIRONMENT (HSE) REQUIREMENTS
5.1 General
This procedure is to be adopted on all sites where excavations are to occur. It is designed to ensure
that damage to existing services is kept to a minimum, thereby giving a safer working environment
for all employees and less unnecessary indirect and direct costs as a result of damaged services.
Arrangement for shoring, plant selection, access/egress, security etc. will be detailed in the method
statement for the activity. Where specific designs are required further information will be obtained
from the designer of the temporary works.
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 3 of 9
A color-coded master plan should be drawn up by the Contractor for all known/charted ervices. This
must be kept up to date by the contractor throughout the life of the Contract.
The Services Coordinator should arrange a site awareness meeting to ensure that all staff are
aware of service locations, and given knowledge of the procedures for drafting and implementation
of the Permit to Dig system for all excavations. This meeting must be reconvened during the
Contract as new work opens up or Statutory Authorities are employed to install services (e.g. gas,
electric etc.).
The site must obtain good quality service location equipment to ascertain position and depth of
services. The Statutory Authorities must be asked to mark out their services on site, and positive
service identification by trial holing must be established (this may be particularly useful for services
difficult to TR i.e. plastic/gas/water/telecom etc.
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 4 of 9
The color-coded master plan for all known services must be displayed in a prominent
position.
Competent persons will be appointed to draft Permits to Dig.
Authority diversions and Permit to Dig must be included in the weekly program. From this, a
list of Permits required may be drafted and distributed to the relevant person / contractor.
All persons using service location equipment must be trained in the use of the equipment.
A survey must be carried out with the service location equipment for the full length of each
service and the location indicated on site by means of pegs/paint/visual bunting/referencing
etc. Record the depth and line of the service e.g. every 5 meters. This information must then
be transferred to the relevant Permit to Dig. Do not drive pins/pegs into the ground before
service depth is known.
All areas to be excavated must be surveyed even if services are not thought to be present.
If services cannot be located, the relevant Authority must be consulted.
- Services to private housing are not likely to be shown on drawings - even small services
can kill, hand digging only is permitted around these services.
- If a cable is embedded or covered by concrete or tarmac, the Statutory Authority must be
consulted and requests made that the service is made dead prior to excavation. This is
their statutory obligation. If this is refused then the Safety, Health and Environmental
Department must be contacted immediately for further consultation. This must be done
before excavation begins.
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 5 of 9
- All excavations will be assessed for support requirements regardless of the depth of the
excavation. Soil / ground conditions can vary greatly and often in short distances. It
should not be forgotten that 1 cubic meter of soil weighs approx. 1.3 tones.
- Adequate prior design consideration must be given to the ground conditions that will be
met, the method of excavation to be used, and the manner in which any support required
would be provided.
In summary, the following factors must be addressed in the design, planning and execution of the
works:
Ground condition
Surface water
Further advice and guidance on safe temporary slopes may be obtained from the Design Engineer
and the Safety, Health and Environmental Department.
- Battered sides
- Double sided support e.g. proprietary support systems
- Single sided with raking support where only one face of the excavation is involved
- Single sided cantilever support e.g. sheeting system
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 6 of 9
Where works are adjacent to public thoroughfares, then these must be adequately
fenced. Barriers or stop blocks will be provided where cranes, dumpers, lorries, tipping
vehicles etc. are operating to prevent them from maneuvering too close to the
excavation, or where vehicles have to tip material into excavations to prevent the vehicle
from overturning into the excavation. In this case, support of the excavation must take
into consideration the proximity of vehicles to the sides of the excavation.
5.4.3 Lighting
During hours of darkness, edges of excavations will be illuminated where there are
public thoroughfares. During winter, in deep excavations, shafts and tunnels, lighting will
be necessary to enable operations to proceed safely. Such lighting will be suitable for
use in the excavations.
5.4.4 Ventilation
The gases involved with excavations may be natural e.g. methane, Hydrogen sulphide,
Carbon dioxide, or may arise from vehicle engines e.g. carbon monoxide, leakage from
LPG equipment or underground storage, or from sewers. Air may need to be blown into
the excavation to disperse any potential gases. Gas monitoring may be required where
assessed under Confined Space Procedure (TRP/15).
5.4.5 Means of Escape
All persons will be instructed in escape and rescue procedures. These will be contained
in the method statement for the activity. Instruction will be in accordance with
Environmental Aspects & Health & Safety Risk Planning.
5.4.6 Working under Overhead Cables
- Any excavation works being considered under, adjacent to or alongside overhead power
cables will be carried out in accordance with the contractors Health and Safety Plan, and
in particular the section on avoidance of danger from overhead electric lines. In any case
the initial risk assessment must consider having the power isolated or diverted during the
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 7 of 9
works, where this is not possible, then as a minimum the following points will be strictly
adhered to:
A report of the inspection shall be recorded in the Site Inspection Register, or where statutory inspections
are carried out by a Sub-Contractors - Suppliers, then that company’s equivalent report.
6.0 PROCEDURE
6.1 Site Preparation
6.1.1 Existing Services
Site investigation shall be carried out and acquire information about site services might
have been placed/embedded below the ground. Services, wherever found shall be
rerouted and protected to place will not affect site activities.
6.1.2 Setting out
Site survey shall be performed to mark/stake-out the lines and levels of the objective
excavation for foundations as indicated in the approved drawings.
6.2 Excavation
6.2.1 The area to be excavated shall be properly marked and clear before starting the works.
6.2.2 The depth of excavation shall be periodically checked by the site surveyor to avoid over
excavation. the bank of excavated area shall be sloped 30 degrees and shall be
maintained to avoid a collapse of the bank into the excavated area.
6.2.3 All excavated material shall be kept a minimum of 1.0 meter from the edge of excavation
or shall be stockpiled to the designated area.
6.2.4 For all excavation activities, adequate safety barriers, sign boards, advance warning
signs would be used.
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 8 of 9
6.2.5 As soon as the excavation reaches the required depth/elevation the surface shall be
leveled and inspected.
6.2.6 Before the backfilling and compaction starts, it shall make sure that the excavated level
is free from standing water or excessive moisture content.
6.3 Backfilling
6.3.1 After excavation is complete and approved, backfilling shall be commenced using
specified, approved sub-base material. Care shall be taken to remove bolder,
vegetations and any other deleterious materials.
6.3.2 Thickness of the backfill shall be placed in layers as per approved foundation design
drawings. Backfilled layer shall be followed by compaction. Compaction test shall be
carried out once the surface is ready.
6.3.3 Compaction test shall be carried out by approved 3rd party inspector under te supervision
of TR QC engineer and client representative. Results shall be submitted to client for
review and approval where required.
6.3.4 Backfilling shall be followed for the next layers, where applicable, until final level is
achieved.
7.0 TESTING AND INSPECTION
7.1 All backfilling sub-grade materials shall be inspected and approved before use.
7.2 Compacted layers shall be test to the required dry density percentage as per project specifications.
7.3 Where compaction performed in layers, succeeding layer backfilling shall not start unless the
previous layer is approved by client. Verbal instruction is not accepted.
7.4 Compaction test report shall be sent to client as soon as received from the 3rd party.
TR-CA-MS-002
METHOD OF STATEMENT FOR EXCAVATION REV A
AND BACKFILLING FOR Qayyarah POWER 11-SEP-17
PLANT PROJECT Page 9 of 9
9.0 ATTACHMENTS