Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Project Title: Renovation of Two Storey Building

BILL OF QUANTITIES
A Building Permit/ Miscelaneous Fee 20,000.00
B Demolition Works 15,000.00
C Excavation 3,000.00
D Formworks & Scaffoldings 58,369.11
E Concrete & Masonry Works 308,928.44
F Doors & Windows 177,886.80
G Tile Work 265,165.58
H Plumbing Works 126,627.64
I Electrical Works 218,385.74
K Ceiling Works 169,865.50
L Painting Works 62,489.70
M Roof Works 153,243.09
N Finishes 42,997.50
O Carpentry Works & Furnitures 100,327.50
GRAND TOTAL IN WORDS IN FIGURES

1,722,286.59

Submitted by:

(Company/ Business Name)

NOTE :
For those items which are not clear what materials are intended should be verified
through the companies Specification. Non compliance to the specified materials will be
1.0
the basis for non acceptance of work and issuance of non comformance report
for non acceptance of work and issuance of non comformance report
All material SPECS / dimensions required herein must be satisfied. Commercial sizes are
2.0
not tolerable / allowed subject for replacement
3.0 Power & Water to be provided by Area Operation Office.
Construction Duration shall be within 30 Calendar Days including 10 days completion of
4.0 corrective works & deficiencies.
Payment shall be 40% DP; 50% upon Completion; 10% after 3 months from the date of
5.0 accpetance & upon submission of Building Permits & Certificate of Occupancy.
6.0 Application for Water & Power connection shall be applied by Operations
Project Title: Renovation of Two Storey Building
LOCATION: Quezon City
OWNER: Pedro Talagon

DETAILED ESTIMATE
A. Building Permit/ Miscelaneous Qty Unit Unit Cost Amount (Php)
Building Permit 1 lot 20,000.00 20,000.00
SUB TOTAL COST IN WORDS IN FIGURES
20,000.00
B. Demolition Works Qty Unit Unit Cost Amount (Php)
Demolition Works 1 lot 15,000.00 15,000.00
SUB TOTAL COST IN WORDS IN FIGURES

15,000.00
C. Excavation Qty Unit Unit Cost Amount (Php)
Excavation 1 lot 3,000.00 3,000.00
Backfill 1.5 cu.m 550.00 825.00
SUB TOTAL COST IN WORDS IN FIGURES

3,000.00

D. Formworks & Scaffoldings Qty Unit Unit Cost Amount (Php)


1/4 " Plywood 15 pcs 500.00 7,500.00
2" x 3" lumber 350 bd.ft 60.00 21,000.00
2" x 2" Lumber 200 bd.ft 60.00 12,000.00
C.W. Nails 15 kgs 15.00 225.00
Material Cost 40,725.00
Cost Labor 12,217.50
Cost of Contingency 2,647.13
Vat Cost 2,779.48
SUB TOTAL COST IN WORDS IN FIGURES

58,369.11
E. Concrete & Masonry Works Qty Unit Unit Cost Amount (Php)
Septic Tank 2.7 cu.m
12 mm dia. X 6m Steel Bar 22 pcs 220.00 4,840.00
CHB 4" 205 pcs 15.00 3,075.00
Portland Cement 25.65 bags 240.00 6,156.00
Washed Sand 3.51 cum 800.00 2,808.00
Gravel 1.35 cum 900.00 1,215.00
Tie Wire # 16 3 kgs 75.00 225.00
Water Proofing Compound 10 bags 2,500.00 25,000.00
Stairs 5 cu.m
12 mm dia. X 6m Steel Bar 10 pcs 220.00 2,200.00
10 mm dia. X 6m Steel Bars 28 pcs 150.00 4,200.00
Portland Cement 47.5 bags 240.00 11,400.00
Washed Sand 5 cum 800.00 4,000.00
Gravel 2.5 cum 900.00 2,250.00
Tie Wire # 16 3 kgs 75.00 225.00
Column, Beams and Slabs 20 cu.m
10 mm dia. X 6m Steel Bars 500 pcs 150.00 75,000.00
Portland Cement 180 bags 240.00 43,200.00
Washed Sand 10.00 cum 800.00 8,000.00
Gravel 20.00 cum 900.00 18,000.00
Tie Wire # 16 50 kgs 75.00 3,750.00
Material Cost 215,544.00
Cost Labor 64,663.20
Cost of Contingency 14,010.36
Vat Cost 14,710.88
SUB TOTAL COST IN WORDS IN FIGURES

308,928.44
F. Doors & Windows Qty Unit Unit Cost Amount (Php)
Plain PVC Flush door w/ jamb & 4 sets 2,500.00 10,000.00
Sliding Window 6.00 mm thick
tainted glass w/ analok aluminum 3 sets 9,000.00 27,000.00
frame (2.00mx1.20m) (W1)
Sliding Window 6.00 mm thick
tainted glass w/ analok aluminum 4 sets 7,800.00 31,200.00
frame (1.80mx1.20m) (W2)
Awning Window 6.00 mm thick 2 sets 4,200.00 8,400.00
Front Door 80cm x 210cm 4 sets 8,000.00 32,000.00
Material Cost 108,600.00
Cost Labor 32,580.00
Cost of Contingency 7,059.00
Contractors Profit 21,177.00
Vat Cost 8,470.80
SUB TOTAL COST IN WORDS IN FIGURES

177,886.80

G. Tile Work Qty Unit Unit Cost Amount (Php)


Ground- Fourth Floor 120 m2
60x60 floor tiles 434 pcs 210.00 91,140.00
Portland Cement 113 bags 240.00 27,120.00
Sand 28.25 cu.m 800.00 22,600.00
Tile Adhesive 113 bags 350.00 39,550.00
Tile Grout 23 bags 200.00 4,600.00
Material Cost 185,010.00
Cost Labor 55,503.00
Cost of Contingency 12,025.65
Vat Cost 12,626.93
SUB TOTAL COST IN WORDS IN FIGURES

265,165.58

H. Plumbing Works Qty Unit Unit Cost Amount (Php)


PVC Pipe 6" dia. 12 pcs 1,400.00 16,800.00
PVC Pipe 4" dia. 10 pcs 850.00 8,500.00
PVC Pipe 3" dia. 10 pcs 680.00 6,800.00
PVC Pipe 2" dia. 15 pcs 450.00 6,750.00
PVC Fittings 1 lot 2,000.00 2,000.00
Water Closet with Fittings and
5 set 4,500.00 22,500.00
Accessories
Lavatory with Fittings and
5 set 2,000.00 10,000.00
Accessories
Fittings and Miscellenous 1 lot 15,000.00 15,000.00
Material Cost 88,350.00
Cost Labor 26,505.00
Cost of Contingency 5,742.75
Vat Cost 6,029.89
SUB TOTAL COST IN WORDS IN FIGURES

126,627.64

I. Electrical Works Qty Unit Unit Cost Amount (Php)


Building Wiring
2" PVC pipe, Orange 20 pcs 210.00 4,200.00
Panel Board 1 set 35,000.00 35,000.00
2" PVC Elbow, Orange 6 pcs 26.00 156.00
1 1/4 " PVC Pipe, Orange 6 pcs 180.00 1,080.00
1 1/4" PVC Elbow, Orange 8 pcs 20.00 160.00
14 sq.mm THHN Copper Wire 100 mts. 60.00 6,000.00
22 sq.mm THHN Copper Wire 100 mts. 80.00 8,000.00
8 sq.mm THHN Copper Wire 100 mts. 40.00 4,000.00
6" Recessed Type,Vertical Pinglight
20 pcs 350.00 7,000.00
Fixture
4" Surface Type,Vertical Round
10 pcs 450.00 4,500.00
Pinglight Fixture
18 watts T8 led tube warm white 20 pcs 500.00 10,000.00
One-gang Single switch, 16A, Flush 1 sets 300.00 300.00
Two-gang single switch, 16A, Flush 1 sets 450.00 450.00
Three-gang single switch, 16A, 2 sets 520.00 1,040.00
One-gang Single switch element, 1 pcs 350.00 350.00
Three-way switch element, 16A, 8 pcs 200.00 1,600.00
Two-gang Plate, Flush Type 1 pcs 200.00 200.00
Three-gang plate, Flush type 2 pcs 200.00 400.00
Two-gang Convenience outlet with 13 sets 320.00 4,160.00
One-gang convenience Outlet with 9 sets 250.00 2,250.00
4"x4" PVC Junction Box 25 pcs 25.00 625.00
2"x 4" PVC Utility Box 30 pcs 20.00 600.00
5.5mm2 or #10/7 THHN Copper 4 boxes 4,900.00 19,600.00
3.5mm2 or #12/7 THHN Copper 5 boxes 3,900.00 19,500.00
2.0mm2 or #14/7 THHN Copper 5 boxes 2,500.00 12,500.00
1/2" PVC Pipe Orange 80 pcs 100.00 8,000.00
PVC Solvent, 200CC 1 can 200.00 200.00
Electrical Tape, Big 10 rolls 50.00 500.00
Material Cost 152,371.00
Cost Labor 45,711.30
Cost of Contingency 9,904.12
Vat Cost 10,399.32
SUB TOTAL COST IN WORDS IN FIGURES

218,385.74

K. Ceiling Works Qty Unit Unit Cost Amount (Php)


Ground Floor 36 m2
Gypsum Board 12.5 pcs 550.00 6,875.00
Gypsum Board 12.5 pcs 550.00 6,875.00
Carrying Channel 24.59016 pcs 550.00 13,524.59
Metal Furring 36.88525 pcs 150.00 5,532.79
Wall Angle 4.918033 150.00 737.70
Hanger 20 pcs 60.00 1,200.00
Screw 1000 pcs 10.00 10,000.00
Mesh Tape 4 rolls 200.00 800.00
Patching Compound 20 kg 300.00 6,000.00
Putty Plate 4 pcs 150.00 600.00
Putty Knife 4 pcs 150.00 600.00
Concrete Nails 3 kgs 20.00 60.00
Second Floor 36 m2
Gypsum Board 12.5 pcs 550.00 6,875.00
Gypsum Board 12.5 pcs 550.00 6,875.00
Carrying Channel 24.59016 pcs 240.00 5,901.64
Metal Furring 36.88525 pcs 150.00 5,532.79
Wall Angle 4.918033 pcs 150.00 737.70
Hanger 20 pcs 60.00 1,200.00
Screw 1000 pcs 10.00 10,000.00
Mesh Tape 4 rolls 200.00 800.00
Patching Compound 20 kg 300.00 6,000.00
Putty Plate 4 pcs 150.00 600.00
Putty Knife 4 pcs 150.00 600.00
Concrete Nails 3 kgs 20.00 60.00
3rd and 4th Floor 36 m2
Gypsum Board 12.5 pcs 550.00 6,875.00
Carrying Channel 12.29508 pcs 240.00 2,950.82
Metal Furring 18.44262 pcs 150.00 2,766.39
Wall Angle 3.688525 pcs 150.00 553.28
Hanger 20 pcs 60.00 1,200.00
Screw 500 pcs 10.00 5,000.00
Mesh Tape 4 rolls 200.00 800.00
Patching Compound 20 bags 300.00 6,000.00
Putty Plate 4 pcs 150.00 600.00
Putty Knife 4 pcs 150.00 600.00
Concrete Nails 3 kgs 20.00 60.00

Material Cost 118,517.70


Cost Labor 35,555.31
Cost of Contingency 7,703.65
Vat Cost 8,088.83
SUB TOTAL COST IN WORDS IN FIGURES

169,865.50
L. Painting Works Qty Unit Unit Cost Amount (Php)
Walls and Ceiling 288 m2
Flat Wall Latex (Primer) 12 gals 700.00 8,400.00
Gloss Latex Paint 35 gals 700.00 24,500.00
Concrete Neutralizer 2 gals 700.00 1,400.00
Patching compound 20 kg 300.00 6,000.00
Paint Brush (2") 15 pcs 30.00 450.00
Paint Brush (4") 15 pcs 50.00 750.00
Roller Brsh (9") w/ tray 8 pcs 150.00 1,200.00
Sand Paper 20 rolls 30.00 600.00
Masking Tape 1" 10 rolls 20.00 200.00
Paint Rug 10 kgs 10.00 100.00

Material Cost 43,600.00


Cost Labor 13,080.00
Cost of Contingency 2,834.00
Vat Cost 2,975.70
SUB TOTAL COST IN WORDS IN FIGURES

62,489.70

M. Roof Works Qty Unit Unit Cost Amount (Php)


2" x 2" x 1/4" angle bar 50 pcs 900.00 45,000.00
2" x 3 " C Purlins 20 pcs 860.00 17,200.00
10 mm dia. X 6m Steel Bars 7 pcs 150.00 1,050.00
Prepainted Rib type roof 20 lnm 250.00 5,000.00
Prepainted Gutter, GA 24 x 2.44m 6 lnm 250.00 1,500.00
2" x 10" C Purlins Fascia 2 pcs 800.00 1,600.00
4" Downspout 14 pcs 50.00 700.00
Gutter Clip 20 pcs 10.00 200.00
Pre painted flashing , GA 24 x 18 lnm 300.00 5,400.00
Red Oxide primer 5 gal 600.00 3,000.00
Tekscrew 1200 pcs 10.00 12,000.00
Rivet 1200 pcs 10.00 12,000.00
4" Elbow 7 pcs 30.00 210.00
Sealant 5 packs 100.00 500.00
Welding Rod 20 kg 75.00 1,500.00
Thinner 1 gal 60.00 60.00
Material Cost 106,920.00
Cost Labor 32,076.00
Cost of Contingency 6,949.80
Vat Cost 7,297.29
SUB TOTAL COST IN WORDS IN FIGURES
153,243.09

N. Finishes Qty Unit Unit Cost Amount (Php)


Stone Finish
Accent Walls 1 ls 30,000.00 30,000.00

Material Cost 30,000.00


Cost Labor 9,000.00
Cost of Contingency 1,950.00
Vat Cost 2,047.50
SUB TOTAL COST IN WORDS IN FIGURES

42,997.50

O. Carpentry Works & Furnitures Qty Unit Unit Cost Amount (Php)
Partitions 1 ls 30,000.00 30,000.00
Cabinets 1 set 40,000.00 40,000.00

Material Cost 70,000.00


Cost Labor 21,000.00
Cost of Contingency 4,550.00
Vat Cost 4,777.50
SUB TOTAL COST IN WORDS IN FIGURES

100,327.50

You might also like